About SAFLII
Databases
Search
Terms of Use
RSS Feeds
South Africa: Supreme Court of Appeal
SAFLII
>>
Databases
>>
South Africa: Supreme Court of Appeal
>>
1995
>>
[1995] ZASCA 118
|
|
Rens v Coltman (563/94) [1995] ZASCA 118; 1996 (1) SA 452 (SCA); (28 September 1995)
Case No 563/94 /mb
IN THE SUPREME COURT OF SOUTH
AFRICA
(APPELLATE DIVISION)
In the matter of:
R RENS
APPELLANT
and
E COLTMAN
RESPONDENT
CORAM
: JOUBERT, NESTADT JJA et SCOTT AJA
HEARD
: 12
SEPTEMBER 1995
DELIVERED
: 28 SEPTEMBER 1995
JUDGMENT
SCOTT AJA/
...
2
SCOTT AJA
:
The appellant is a quantity surveyor of East London.
In
February 1989 he was engaged in his
professional capacity by the respondent to investigate the cause of an apparent
subsidence and
consequential cracking of certain walls of the latter's house and
to advise her what work would have to be done to remedy the situation.
He was
also asked to give an estimate of the cost of such work. After inspecting the
house, he wrote to the respondent's attorneys
advising that the foundations at
the south east corner of the dwelling where the cracks were occurring had not
been soundly founded
and that there was evidence of root material beneath the
footing. The remedial work that he recommended was, however, minimal and
involved simply draining the area and allowing the building to settle before
repairing the cracks. At the time, the appellant was
aware that the respondent
proposed recovering the cost of the remedial
3
work from the builder of the house. Acting on the advice so given, the
respondent settled the claim against the builder and accepted
the sum of R3 200
in full and final settlement. The nature of the problem and the extent of the
work required to solve it were, however,
far greater than the appellant had
thought. His advice to the respondent as to the remedial work required was
plainly incorrect and
his estimate of R3 200 was woefully too low. In due
course, the respondent sued the appellant for damages, founding her claim both
in contract and in delict. The appellant admitted that he ought to have
conducted a more detailed investigation and that had he done
so he would have
established that more extensive remedial work was required to remedy the defects
at much greater expense. Ultimately,
liability on the part of the appellant was
admitted and the only questions which remained in issue were the causal link
between the
appellant's conduct and the damage suffered by the respondent, and
the
4
quantum of the respondent's damages.
In the course of the
trial the pleadings were much amended by both sides and various admissions were
made which served to curtail
the proceedings. The respondent's claim as finally
formulated comprised two parts. The first was a claim for R27 528,42, being the
sum of R30 728,42 which would have been recoverable from the builder as at May
1989, less the payment of R3 200 actually received
from the builder. The
relevance of May 1989 is that this was the month in which the respondent had
settled her claim with the builder.
The second leg of the claim was for the
additional expense incurred by the respondent in consequence of the incorrect
advice and
was made up of the cost of the unnecessary work carried out in
pursuance of the appellant's advice, the extra cost incurred by reason
of the
need to accommodate this work when effecting repairs, and the extra cost
occasioned by the delay in effecting the correct
remedial
5
work and the consequent increase in building costs. The latter claim
amounted to R24 997,55 and included the sum of R3 083,60 which
had been paid for
the unnecessary work carried out on the advice of the appellant.
The total amount which was ultimately claimed, and, indeed, awarded by
the trial Court (Kroon J sitting in the East London Circuit
Local Division), was
therefore the sum of R52 525,97 (ie R27 528,42 plus R24 997,55). The amount of
R24 997,55 was in reality a residual
amount after making certain deductions from
the sum of R55 725,97 which, it was ultimately agreed between the parties, was
the cost
of implementing what was referred to as the "KRC design to remedy the
defective foundations of the house as at June 1992. The figure
of R55 725,97
included the cost of the additional work occasioned by the previous attempt to
remedy the situation as well as the
sum of R3 083,60, which, as previously
mentioned,
6
had been paid for the unnecessary work. The amount awarded was,
therefore, the sum of R55 725,97 less the amount of R3 200 paid to
the
respondent by the builder ie R52 525,97. The second leg of the claim ie R24
997,55 was simply the sum of R52 525,97 less the
sum of R27 528,42.
It is necessary at this stage to explain the reference to the KRC design.
In about August 1989 the respondent engaged the services
of a Mr Peter Dowling
who is a structural engineer and who carries on business as such under the name
KRC Structural Engineering.
After examining the house he designed a method of
rectifying the fault which, simply stated, involved propping up the roof and
rebuilding
the affected walls on foundations supported by bases which were to be
soundly founded beneath the unsatisfactory material. The design
was somewhat
refined by a Mr John Morris who is a consulting engineering technologist and in
due course
7
tenders were obtained and the design implemented, save that the
contractor elected to remove the roof rather than prop it up. This
was the KRC
design.
On behalf of the appellant another structural engineer, Mr Leslie Weaver,
was employed to give an opinion regarding the remedial work
that would be
necessary to solve the problem. His design was somewhat simpler than the KRC
design and would have been less expensive
to implement. It was referred to at
the trial as the "Weaver" design.
Returning to the first leg of respondent's claim, it was common cause
that in May 1989 appropriate remedial work could have been executed
at a cost of
R30 728,42 by implementing the Weaver design. The award by the trial court of
this amount, less the sum of R3 200, was
attacked on the ground that it had not
been shown that the respondent
8
would have succeeded in recovering such a sum from the builder. Indeed,
much of the evidence at the trial was devoted to this issue.
As far as the second leg of the claim is concerned, it was contended on
behalf of the appellant that the Court a quo erred in awarding
in effect the
cost of executing the remedial work as late as June 1992. In other words, the
contention was that the appellant should
not have been awarded the full
difference between the cost of the remedial work in May
1989
and June 1992
when the work was actually done. The appellant's case was that the respondent
ought reasonably to have known of her
cause of action against the appellant by
not later than August 1990 and that in so far as the second leg of the claim is
concerned,
damages should have been determined by having regard to the cost of
the remedial work as at
August
1990
and not June
1992. On this basis the appellant in his plea, as finally amended, tendered
payment of the sum of R6 943 which represented
the
9
figure of R40 871 being the cost of repairs as at August 1990 in
accordance with the Weaver design and which included the wasted expense
of R3
083,60, less the sum of R30 728 being the cost of repairs as at May 1989, and
less the amount R3 200 received from the builder.
I turn now to deal with the finding of the trial Court that the appellant
would have recovered the amount of R30 728,42 from the party
to which, until
now, I have referred simply as the builder. Before proceeding further a brief
explanation is required. The party
with whom the respondent contracted for the
construction of the house was a company called Galon (Pty) Ltd which traded
under the
style of Rodlang Homes. The shareholders were a Mr Parker and a Mr
Rodney Langheim who was the party involved in the actual building
work.
According to the evidence Mr Parker is a well known estate agent in East London
who since 1981 has carried on business as such
through the vehicle of a company
called Action
10
Property (Pty) Ltd ("Action Property") which subsequently on 12 December
1991 was converted to a close corporation. Mr Parker's venture
into the building
industry was short-lived and unsuccessful. In about January 1988, that is to say
more than a year after the respondent's
house had been completed, Mr Parker and
Mr Langheim decided to terminate what was essentially the partnership agreement
between them.
The full terms of the termination agreement are not clear but what
is common cause is that Action Property, in which Mr Parker was
the sole
shareholder, acquired all the assets and liabilities of Galon (Pty) Ltd and in
particular an accumulated loss. It was accordingly
not in dispute that as at May
1989 any action which the respondent may have had against the builder arising
out of the defective
construction of the house lay against Action
Property.
Counsel for the appellant submitted that the Court a
quo
erred in
accepting that Action Property would have been able to meet the claim
11
of R30 728,48 and he argued that this amount was accordingly not
recoverable from the appellant. Much emphasis was placed both in
this Court and
in the Court below on the financial statements of the company for the year
ending 31 August 1990 which showed that
both as at 31 August 1989 and 31 August
1990 the liabilities of the company exceeded its assets so that on those dates
it was technically
insolvent. As previously mentioned, however, Mr Parker was
the sole shareholder in Action Property being the vehicle through which
he
carried on business as an estate agent. Its share capital was minimal and as in
the case of many private companies, was financed
by way of a loan account rather
than by way of a share issue. Having regard to the nature of its business for
which little in the
way of capital would have been required, it is perhaps not
surprising in these circumstances that its financial statements for the
years
1989 and 1990 should have shown the company to be technically
insolvent.
12
Nonetheless, it operated a successful business. The accounts, as
explained by the company's auditor, revealed that in 1989 it produced
a profit
of R50 325 after deducting "directors emoluments" of R28 000,00. In 1990 the
profit was R35 516 after deducting R45 200
in respect of "directors emoluments".
Its financial position was such that during the two year period, 1989 to 1990,
it was able
to repay over R100 000 in respect of Mr Parker's loan
account.
In his evidence, Mr Parker explained that the cash flow of Action
Property was unpredictable in the sense that a sizable bank overdraft
one day
could be converted to a substantial balance the next day depending on what
commissions had been received in the interim.
He testified that after giving the
matter some thought he was satisfied that had Action Property been unable to
meet the respondent's
claim in 1989 he, Parker, would have injected sufficient
capital into the company to enable it to do
13
so. He justified what he would have done on two grounds. The first was
that he felt morally obliged to see that the respondent's claim
was met,
particularly as she had worked for him at some previous stage. The second was
founded upon more practical and commercial
considerations. He explained that he
was very well known in East London where he conducted his business; that his
name was synonymous
with that of Action Property and that had the company gone
insolvent he would have been extremely embarrassed and his standing in
the
community as an estate agent much reduced.
Kroon J was unpersuaded that Mr Parker would have come to the appellant's
assistance for altruistic reasons. He found on the probabilities,
however, that
in order to avoid personal embarrassment and for commercial reasons Mr Parker
would not have permitted Action Property
to be liquidated at the instance of an
unpaid creditor (the
14
respondent) and to this end, if necessary, would have injected capital
into the company. The learned judge found also that notwithstanding
the
technical insolvency of Action Property it would probably have been able to meet
a claim in the region of R30 000 even in the
absence of a further injection of
capital by Mr Parker, although it might have required time to meet the
claim.
Mr Lang
, who appeared for the appellant, attacked the finding of
the Court a quo on various grounds. He submitted that having rejected Mr
Parker's evidence in one respect, namely, that he would have come to the
appellant's assistance on moral grounds, it ought not to
have accepted his
evidence that he would have come to her assistance for any other reason. He
argued that the alleged embarrassment
and loss of standing was unjustified in
that had the company gone into liquidation, Mr Parker would have been able to
justify this
event on the basis of his unsuccessful
15
venture into the building industry and nothing would have precluded him
from continuing his estate agency business under the style
of Action
Property.
This argument overlooks the evidence that Mr Parker was a well known
estate agent whose name, according to both Mr Parker and his
attorney, was
synonymous with that of Action Property. To suggest in these circumstances that
the liquidation of the company would
not be seen as reflecting adversely upon Mr
Parker is, I think, somewhat unrealistic; nor was it ever put to him in
cross-examination
that he could have escaped liability by adopting the device of
allowing his company to go into liquidation and blaming it on his
venture into
the building industry. The business was clearly a successful one. It provided Mr
Parker with a good income and it was
not in dispute that he was well-off and
would have had little difficulty in raising an amount in the region of R30 000.
It is not
at
16
all improbable, I think, that in these circumstances and if necessary, he
would have been prepared to put money into the company in
order to preserve its
good will and his own good standing in the community as an estate agent. The
company, as I have previously
said, was financed by way of loans which he made
to the company. Injecting capital into the company in this way would have been
nothing
unusual. His assertion that he would not have allowed his company to go
into liquidation was furthermore supported by the evidence
of his attorney, Mr
Moolman, who expressed the view that Mr Parker would have avoided this if it was
at all possible. In all the
circumstances, I am unpersuaded that there is any
justification for interfering with the finding of the trial Court that but for
the appellant's incorrect advice the respondent would have succeeded in
recovering damages from Action Property in the sum of R30
728,42. Indeed, I
think, the finding would have been equally justified if the amount in question
had
17
been based on the KRC design and hence slightly higher
I turn to the next point argued by
Mr Lang
, and that is that the
Court erred in awarding damages to the appellant on the basis of the cost of
remedial work as at June 1992.
As previously explained, the total amount awarded
was based ultimately upon an agreed figure of R55 725,97 which represented the
actual cost of performing the remedial work in June 1992 together with the sum
of R3 083,60 previously paid for unnecessary work.
It was common cause,
therefore, that the cost of the work in June 1992 in accordance with the KRC
design was R52 642,39 (R55 725,97
less R3 083,60).
Mr Lang
contended that
the appellant's damages should not have been determined on the basis of the
actual cost, but on the basis of what
the remedial work would have cost had it
been executed in August 1990. He submitted that by the latter date the
respondent ought
to have realised that the appellant's advice was incorrect and
should have been
18
aware of her cause of action against him.
Before dealing with
Mr Lang
's argument, which was essentially one of fact, it is necessary to
make certain general observations regarding the computation of
damages in cases
such as the present where there is a delay prior to the discovery of the breach
and its consequences. The claim
in the present case was founded both in contract
and delict. The Court a
quo
, relying upon a passage in
Jackson &
Powell on Professional
Negligence 3 ed at para 2-117, accepted that
regardless of which test was applied (ie the test for determining damages in
contract
or delict) the result in the particular circumstances of the case was
the same. Counsel accepted this as being correct and no argument
was addressed
to us on the point. As the appellant's liability in contract was common cause it
is unnecessary to have to decide the
point and I shall consider the claim for
the purpose of the computation of damages as being one in contract.
19
The fundamental rule with regard to the award of damages for breach of
contract is now well established. The innocent party should
be placed in the
position he or she would have occupied had the contract been properly performed,
so far as this can be done by the
payment of money without undue hardship to the
party in breach. The application of this rule will ordinarily require in many
cases,
and typically the case of a breach of a contract of sale by the
purchaser, that the date for the assessment of damages be the date
of
performance, or as it has often been expressed, the date of the breach. But even
in contracts of this nature, there is no hard
and fast rule (cf
Culverwell
and Another v Brown
1990 (1) SA 7
(A) at 30 G - 31 H) and in each case the
appropriate date may vary depending upon the circumstances and the proper
application of
the fundamental rule that the injured party is to be placed in
the position he would have occupied had the agreement been fulfilled.
The
position is the same in England. In
20
Miliangos v George Frank (Textiles) Ltd
[1975] 3 All ER 801
(HL)
Lord Wilberforce (at 813) recognised that "as a general rule in English law
damages for tort or for breach of contract are assessed
as at the date of the
breach" but in the same passage emphasised that the general rule did not
preclude the Courts in particular
cases from determining damages as at some
later date.
Where, for instance, it is appropriate to measure damages on the basis of
the cost of repairs or remedial work it would be unfair
and contrary to the
fundamental rule stated above to insist that in each case and regardless of the
escalation in costs the appropriate
date is to be the date of performance. This
is particularly so in building contracts where the breach may be discovered even
years
later. The point is well illustrated in the case of
East Ham Borough
Council v. Bernard Sunley & Sons. Ltd.
[1965] 3 All ER 619
(HL) where,
in 1959, ie some two years after the
21
architect's final certificate had been issued, certain stone panels fell
from
the building prompting an investigation which in turn revealed
widespread
faults. It was held that the damages were to be assessed
by reference to the
actual cost of repairs in 1960 - 61, as this was a reasonably foreseeable
loss
arising from the breach of contract. The inapplicability in
appropriate
circumstances of the date of performance (or breach) or in the case
of
delict, the date of the wrong, was stressed by Megaw LJ in
Dodd
Properties
(Kent) Ltd and another v Canterbury City Council and others
[1980]
1 All
ER 928 (CA). Although the action in that case was based in tort, it is
clear
from the earlier remarks of the learned judge that the following passage
(at
933 g - h) is equally apposite to an action in contract.
"Indeed, where, as in the present case, there is serious structural
damage to a building, it would be patently absurd, and contrary
to the general
principle on which damages fall to be assessed, that a plaintiff, in a time of
rising prices, should be limited to
recovery on the basis of the prices
of
22
repair at the time of the wrongdoing, on the facts here, being two years, at
least, before the time when, acting with all reasonable
speed, he could first
have been able to put the repairs in hand. Once that is accepted, as it must be,
little of practical reality
remains in postulating that, in a tort such as this,
the 'general rule' is applicable. The damages are not required by English law
to
be assessed as at the date of breach."
The rule with
regard to the time of assessment where the cost of repairs is
the
appropriate measure of damages, is stated in
Chitty on Contracts
26
ed vol 1 at para 1780 as follows:
"The time at which the cost of repairs should be assessed is when it was
reasonable for the plaintiff to begin repairs, which may
be as late as the date
of the hearing if the plaintiff was acting reasonably in not mitigating
earlier."
Such an approach is in consonance with the
fundamental rule stated above
that the innocent party should be put in the position he would have been
in
had the contract been properly performed, and in my view is the
proper
approach to be adopted in cases where the true measure of damages is
the
23
cost of repairs or remedial work.
In the present case it was
not disputed that the damage suffered by the respondent both as to the
non-recoverability from the builder
and the additional expense arising from the
delay and escalation in building costs was foreseeable; nor was it ever
contended that
any yardstick other than the cost of the remedial work was the
true measure of damages to be adopted. All that was contested was
the
reasonableness of having the remedial work executed as late as June
1992.
Before considering this issue it is necessary to set out, as briefly as
the circumstances permit, the principal events preceding the
execution of the
work.
Following the appellant's advice which was given in February 1989 the
respondent's attorney entered into correspondence with Mr Parker's
attorney
which culminated in the former accepting payment of the sum of
24
R3 200 in full and final settlement of the respondent's claim. This was
in May 1989. The following month, certain remedial work was
carried out as
directed by the appellant. This was not the same as that initially proposed by
him. After receiving the appellant's
letter the respondent raised with him the
need to possibly underpin the foundations at the south east corner of the house.
She did
so on the strength of what other people had told her. Although the
appellant's attitude was that this was not necessary, the work
that was actually
carried out involved placing a large quantity of concrete under the foundations.
The respondent was advised by
the appellant to leave the cracks until some 9 to
12 months had elapsed before having them repaired so as to allow the house to
settle.
Because of their unsightly nature the builder in fact filled in the
cracks at the same time he placed the concrete under the foundations.
The cracks
were mainly in the kitchen.
By September of 1989 the cracks had reappeared. The
window
25
frame in the kitchen was coming away from the wall and with hindsight the
respondent realised that even at this stage the kitchen
floor had begun to
slope. She got in touch with her attorney who in turn consulted the appellant.
On 3 October 1989 the appellant
wrote to the respondent's attorney advising that
he had visited the house in the company of the builder, a Mr Klinkhardt, and had
observed that the soil around the foundation substructure appeared to be drying
out. He advised that the matter should be left until
March or April of the next
year. The respondent explained that living in the house as she did, it was not
readily noticeable whether
the cracks were widening or not. In 1990, however,
she went on holiday and upon returning in about August noticed that the cracks
had definitely widened. By then she had negotiated with the municipality of
Gonubie to have the vlei on the opposite side of the
road drained. She thought
that this ground was at a slightly higher level than her own
26
property and she hoped that this would improve the situation by removing
the wetness which she understood from the appellant was the
main cause of the
problem. By then the municipality had also tarred the road and installed storm
water drains so that when it rained
the water no longer drained onto her
property. At about that time she was also negotiating to have a swimming pool
installed. When
the hole was made for the pool she used the soil to raise the
level at the affected area in the hope of increasing the run-off and
so
eliminate any pooling of water in the area. All these steps, of course, were
aimed at drying out the area which according to the
advice that had been given
to her was what was required.
By the middle of 1991 it was clear to the respondent that the condition
of the house was deteriorating. One wall was visibly bulging
and the slope of
the kitchen floor was plainly discernible. In about June of that year she again
complained to her attorney who in
the course of the
27
next month or two addressed letters to the appellant advising him of the
situation and requesting his assistance. According to the
respondent's attorney,
Mr Richards, the appellant undertook to investigate the matter but advised that
he was having difficulty in
getting in touch with the builder, Mr Klinkhardt. At
about this time - the respondent thought it was in July 1991 and the appellant
did not testify - the appellant spoke to the respondent on the telephone.
According to the respondent the appellant was abrupt and
said that he had not
undertaken to fix the house. She testified that at this stage she realised that
she might have a claim against
the appellant. She telephoned Mr Richards and
said that she wished to take the matter further and possibly sue the appellant.
Mr
Richards, however, was reluctant to act for her in such an action as he felt
he had a conflict of interests.
The respondent testified that she realised from what
Mr
28
Richards had told her at the stage when the appellant was first
consulted
that it was necessary to engage the services of an expert. She said that
she
racked her brains for several weeks and eventually spoke to an architect,
a
Mr Hall, whom she knew personally. Mr Hall in turn enlisted the aid
of
Mr Peter Dowling of KRC Structural Engineering and the three of
them
met at the house towards the end of August 1991. Mr Dowling thought
the
building could be saved and estimated the costs of the necessary
remedial
work to be possibly somewhere in the region of R30 000 to R45 000.
It
appears that Mr Dowling then embarked upon designing a method of
repairing the house, although quite when this was done is not
clear.
Perhaps mindful of what had gone before, the
respondent
decided to procure a second opinion. She consulted the telephone
directory
and eventually succeeded in obtaining the services of Mr John Morris of
a
firm of consulting engineers. This was in early January 1992. The two
of
29
them met at the house on 4 February 1992 and Mr Morris conducted various
tests. He was also given a report prepared by Mr Dowling.
In due course Mr
Morris prepared a further report which was dated 21 February 1992. Mr Dowling's
report was revised in certain respects
and the work was eventually put out for
tender.
On 27 May 1992 Mr Morris discussed the tenders received with the
respondent and in due course the contract was awarded to a firm called
Pearson
Construction which completed the work in June 1992.
In arguing that the cost of repairs should have been determined as at
August 1990 as opposed to June 1992,
Mr Lang
assumed that the respondent
bore the onus of establishing that the latter date was reasonable. No argument
was addressed to us on
the question of onus; nor, I might add, was any
allegation made in the plea that the respondent ought to have mitigated her loss
by having the repairs effected by August 1990 or for that
30
matter by any other date. Having regard to the evidence, however, and in
particular that of the respondent which was not contradicted,
I find it
unnecessary to have to determine the incidence of the onus and shall simply
assume, without deciding, that it rested upon
the respondent.
Mr Lang
argued that the appropriate date for the assessment of
damages was August 1990, presumably because at about this time the respondent
returned from holiday and noticed that the cracks had widened. But this does not
justify the conclusion that she ought to have realised
that the advice was
incorrect and to have set about getting in other experts to attend to the
problem. The respondent was a layman
who had been advised by an expert that the
solution lay in allowing the subsoil around the foundations to dry out and
stabilize.
When she had expressed dissatisfaction in September 1989 the
appellant had reported that the subsoil appeared to be drying out and
that in
effect more time was required to
31
enable the house to settle before repairing the cracks. The mere fact
that the house had not settled as soon as had been anticipated
was no basis for
concluding that the appellant's assessment of the problem was wholly incorrect
and that the foundations were so
defective that the south east corner of the
house would virtually have to be rebuilt. As the respondent explained, she was
led to
believe that further settling could take place and she really had no idea
when it would stop or whether at any particular stage the
movement of the house
had finally come to an end. In the belief that the wetness of the area was the
cause of the problem the respondent
herself took a number of practical steps to
alleviate the problem. This is indicative of her continuing acceptance of the
correctness
of the appellant's advice. In my view her conduct cannot be regarded
as unreasonable. It was only in about July 1991 when the appellant
in effect
disavowed responsibility that the respondent sought alternative professional
advice. It is true that
32
it took almost another year before the work was finally done, but I do
not think that this was attributable to any undue dilatoriness
on the part of
the respondent. She consulted an expert within weeks after, as she put it,
racking her brains to think of whom to
turn to. Her architect friend brought in
Mr Dowling who in turn proceeded to prepare a design for the remedial work which
she was
told was going to be extensive. It is probably true that by employing Mr
Morris there was a further delay. But given the respondent's
previous experience
with the appellant and the extensive nature of the proposed remedial work, her
decision to seek a second opinion
was certainly prudent. In all the
circumstances I cannot find fault with the conduct of the respondent. There is
no basis in my view
for the contention that her failure to have the remedial
work carried out sooner was unreasonable. I accordingly agree with the finding
of Kroon J that the respondent acted reasonably in having the work done in June
1992.
33
A further point raised by
Mr Lang
on appeal was that the Court a
quo erred in not awarding damages on the basis of the cost of the remedial work
in accordance with
the less expensive Weaver design rather than the more
expensive KRC design which was the design actually adopted in the execution
of
the work. He submitted that by adopting the cost of repairs based upon the
Weaver design for the purpose of the first leg of the
claim, that is to say, for
the purpose of determining the amount that the respondent would have recovered
from Action Property, the
respondent necessarily accepted the adequacy of this
design. Accordingly, so the argument went, there was no basis upon which the
trial court could reject it and determine the award in respect of the second leg
of the claim on the KRC design.
In my view this argument is ill-founded. First, the mere fact that the
Weaver design may have been a little less expensive is not
in issue.
34
The question is whether in taking the course she did, the respondent
acted reasonably or not. As I have indicated above, the respondent
actually
called in another expert, namely Mr Morris, to give a second opinion. Mr Morris
revised the original KRC design and in so
doing rendered it less expensive.
Thereafter the work was put out for tender. I do not think the respondent's
conduct in this regard
can be faulted. The onus of showing that there was
another less costly remedy which the respondent ought to have adopted rested
upon
the appellant. The mere fact that another less expensive design was
produced ex
post facto
did not have the effect of discharging the burden
upon the appellant. As was pointed out in
Holmdene Brickworks (Pty.) Ltd. v
Roberts Construction Co. Ltd.
1977 (3) SA 670
(A) at 689 E, the measures
taken by the innocent party to extricate himself from the harm occasioned by the
breach "ought not to
be weighed in nice scales and the Court should not be
astute to hold that the onus (on
35
the defendant) has been discharged.
Secondly, it is necessary to observe that the respondent's true measure
of damages was the cost of the remedial work executed in June
1992 together with
the cost of the earlier unsuccessful work, less the amount previously received
from Action Property. The two-legged
nature of the claim as pleaded appears to
have been the product of various amendments in the course of the trial and
probably owes
its origin to an attempt to deal with the defence raised in
respect of a part of the claim, ie the alleged irrecoverability of damages
from
Action Property. The mere fact that the cost of repairs as at May 1989 was
calculated on the basis of the Weaver design for
the purpose of this somewhat
artificial division of the claim into two components did not in my view bind the
Court to the Weaver
design for the purpose of the proper determination of the
overall damages to which the respondent was entitled.
36
In the result the appeal is dismissed with
costs.
D G SCOTT
JOUBERT JA)
- Concur NESTADT JA)