Tainama Civils (Pty) Ltd v Thulamela Local Municipality and Others (8279/2022) [2026] ZALMPPHC 58 (18 May 2026)

55 Reportability
Administrative Law

Brief Summary

Administrative Law — Review of administrative action — Condonation for late filing of review application — Applicant's review application launched 11 days after expiry of 180-day period prescribed by PAJA — Court satisfied that reasons for delay justified granting of condonation. The First Respondent awarded a tender for the upgrading of Tshilamba Street to the Second Respondent on 19 January 2022. The Applicant, aggrieved by this decision, sought to review the award but filed the application outside the 180-day period stipulated by the Promotion of Administrative Justice Act (PAJA). The legal issue was whether the court should grant condonation for the late filing of the review application. The court held that condonation should be granted due to the Applicant's reasonable explanation for the delay and the circumstances surrounding the tender process.

REPUB LIC OF SOUTH AFRICA
IN THE HIGH COURT OF SOUTH AFRICA
LIMPOPO DIVISION , POLOKWANE
(1) REPORTABLE: -¥ES/NO
(2) OF INTEREST TO THE JUDGES: ¥Ee/NO
(3) REVISED.
•••••••••••• •••••••••••• • ---
1~)05j'l.£ DATE..... ..... SIGNATURE
In the matter between:
TAINAMA CIVILS (PTY) LTD
And
THULAMELA LOCAL MUNICIPALITY
FARIZA CONSTRUCTION J.V
FARIZA CONSTRUCT ION
TBS MANAGEMENT CONSULT ANT AND PROJECTS
CASE NO: 8279/2022
Applicant
First Respondent
Second Respondent
Third Respondent
Fourth Respondent

2
JUDGMENT
NKOANAA.J
Introduction
[1] The First Respondent issued bid number 27/2021/2022 for the upgrading of
Tshilamba Street, Phase 3. The tender was adjudicated and awarded to the Second
Respondent on 19 January 2022.
[2] Aggrieved by this administrative action, the applicant instituted these review
proceedings
The Parties
[3] Only the Applicant and the First Respondent actively participated in these
proceedings. The Second, Third and Fourth respondents took no part.

3
Applicant's Case
[4] The applicant instituted the review proceedings on 29 July 2022, while the impugned
administrative action was taken on 19 January 2022. By the time the application was
launched, the 180-day period prescribed by PAJA had expired.
[5] The Applicant in its Founding Affidavit embodied a condonation application. It is
important to state that the applicant's application exceeded the 180-day period by
approximately 11 days. The reasons proffered by the Applicant on why the review
application was launched late can be summarized as follows.
[6] Upon learning, in the latter part of December 2021, that the tender had been awarded
to the Second Respondent, the Applicant engaged its legal team, who briefed
counsel to consider the merits of a possible review. On 7 January 2022, and
prompted by reports that the tender had been awarded to the Second Respondent,
the Applicant requested access to the First Respondent's records. The First
Respondent replied on 14 January 2022, stating that no award had yet been made.
[7] First consultation took place on 14 January 2022, which was followed by a second
consultation on 17 May 2022, whereafter a decision was made, that a second request
to access the First Respondent's record had to be submitted.

4
[8] The said request was made on 25 May 2022 and on 22 June 2022 a representative
of the First Respondent contacted the Applicant's legal representative's office and
instructed them to send a courier to collect the documentation relating to the matter.
Once the documents were received, then the review application was concluded.
[9] The condonation application is opposed in that it is argued that the review
proceedings were not launched within a period of 180 days as provided for in Section
7(1) of PAJA.
[1 O] Given that the application was launched only 11 days after the expiry of the 180-day
period, and after the applicant received the documents relating to the administrative
decision on 22 June 2022, the Court is satisfied that condonation for the late
institution of the review application should be granted.
[11] I will now turn to the Applicant's case. The Applicant contends that the decision taken
by the First Respondent's Municipal Manager to award the tender to the Second
Respondent is an administrative action which adversely affected the Applicant's
rights as a prospective bidder.

5
(12) The Applicant's relies on Section 217 of the Constitution which states that "an organ
of state in the National, Provincial or local sphere of government, or any other
institution identified in national legislation, contracts for goods or services, it must do
so in accordance with the system which is fair, equitable, transparent, competitive
and cost-effective."
(13) The Applicant also relies on the Preferential Procurement Policy Framework Act 5 of
2000, which was enacted to give effect to Section 217(3) of the Constitution.
(14) Furthermore, the Applicant relies on The Local Government:Municipal Finance and
Management Act, Act 56 of 2003 ("the MFMA"). It is the Applicant's case that in
terms of Section 111 of the MFMA, each Municipality must have and implement a
supply chain management policy which gives effect to the provisions of Part I of
Chapter 11 of MFMA. Other provisions of the MFMA are also relied upon, including
its regulations.
(15) The Applicants' gripe with the First Respondent's handling of the tender, which led
to the impugned decision are in the main as appearing below.

6
[16] It was stated in terms of the score for functionality that experience of the construction
company, as demonstrated to company experience on similar projects and past
performance in road construction will weigh 50 points, proof of plant and equipment
or lease agreement will weigh 30 and financial references 20 points respectively.
[17) It was also stated that failure to comply with tender conditions or to supply the
necessary information in tender closure will result in the tender being rejected. It
was also stated that bidder submissions will be evaluated based on compliance with
certain criteria to determine their responsiveness to the bid requirement. The bid
closed on 29 October 2021 .
[18] On 11 November 2021, the Bid Evaluation Committee ("BEC") considered all of the
submitted tenders. also.
[19] On 15 November 2021, the BEC chairperson tabled relevant scores of each bidder
and after considering the tender documents for 29 contractors and service providers,
it was determined that 17 did not qualify for further evaluation and 12 remained.
[20] The Applicant and the Second Respondent each scored 30 out of 30 for similar
projects and road construction experience, and both achieved an overall score of 93
out of 100.
[21] Mr Mulaudzi, the chairperson of the BEC, recommended to the Bid Adjudication
Committee("BAC") that the tender should be awarded to the Second Respondent as
they had scored the highest points.

7
[22] On 23 November 2021, the chairperson of the BAC directed an e-mail to the BEC in
terms of which they were asked to consider doing re-evaluation of the bid in question,
to address some issues raised by the adjudication committee.
[23] The BEC chairperson on 24 November 2021 wrote back to the BAC chairperson
and requested to be furnished with a list of all the items that need to be reconsidered
for evaluation. The BAC chairperson, Mr Mudzili replied on the same day and listed
the issues of experience, plant, authenticity of some clients used as references and
the issues of highlighted similar works, municipal rates issues and other critical
issues that might be picked up in the process.
[24] The BEC replied on 1 December 2021 and stated that in respect of similar work, they
used the same evaluation which they had applied to similar projects and that there
was consistency in the evaluation process. The Applicant's case goes further to state
that the BEC misinterpreted what was considered of them and whether a bidder had
complied with the compulsory requirements in the tender project.
[25] The BEC submitted the evaluation report to the BAC without any further changes.
Then on 15 December 2021, the BAC directed a memorandum to the Municipal
Manager of the first respondent in terms of which they recommended that certain
issues must be observed before the bid is finalised.
[26] The BAC recorded the difficulties that they had encountered with specific reference
to each tender, which issues were erroneously or irregularly considered by the BEC.

8
[27] On 22 December 2021, the Municipal Manager responded to the BAC, stating that,
after considering the issues it had raised, he was satisfied that the concerns had
been clarified and that there was no need for the BEC to undertake a second re­
evaluation. He accordingly approved the BEC's recommendation to appoint the
Second Respondent as the service provider.
[28] The Applicant contends that the Municipal Manager's conduct was inconsistent with
section 29 of the First Respondent's Supply Chain Management Policy, which
required the BAC either to make the final award or to recommend that the Municipal
Manager do so. On the Applicant's case, that function did not lie with the BEC.
[29] The decision to award the tender to the second respondent is attacked on several
grounds as listed in Section 6 of PAJA.
[30] In its Notice of Motion, the Applicant sought condonation for the late delivery of the
review application. Second, it sought that the decision of the First Respondent to
award the tender 27/2021/2022 to the Second Respondent be reviewed and set
aside in terms of Section 8(1)(c) of PAJA and it also sought costs.
[31] On 12 October 2023, the applicant filed a notice of intention to amend its notice of
motion by introducing paragraph 3 as an alternative prayer, seeking a declaration
that the First Respondent's decision to award tender 27/2021/2022 to the second
respondent was unlawful. Furthermore, that the decision be reviewed and set aside.

9
[32] The Applicant also introduced a just and equitable compensation remedy in
accordance with section 8(1)(c)(ii)(bb) of PAJA which was followed by a referral to
viva voca evidence to determine the loss of profits and other ancillary orders. The
amended papers were delivered with the Registrar on 27 October 2023.
[33] On 11 November 2024, the Applicant made an application to be allowed to deliver a
supplementary affidavit. In the main, the Applicant stated that additional facts came
to its attention relating to the fact that the First Respondent in its Answering Affidavit
suggested that since the contract was envisaged for a period of 12 months. By the
time the matter was to be adjudicated, the tender would have been concluded and
therefore the relief sought will be moot.
(34] The Applicant stated that it recently came to know of correspondence between the
First Respondent and Second Respondent, which will be relevant to the
determination of the issues in the review.
(35] In the correspondence the Respondents seemed to suggest that the completion of
the contract was delayed by a period of seven months, and that the Second
Respondent had abandoned site on November 2023, thereby failing to fulfil its
contractual obligations.

[36] The applicant relied on letters dated 19 February 2024 and 4 March 2024. The
purpose of the supplementary affidavit was to show that the contract did not run for
only 12 months and had not yet been finalised when the application for leave to file
that affidavit was brought.
The First Respondent 's case
[37] The First Respondent, in its answering affidavit raised points in limines. The first one
dealt with the fact that the application was brought outside the 180 days period as
provided by Section 7(1) of PAJA. I need not say more about this as I have already
concluded that condonation must be granted.
[38) The second point raised was that of mootness, in that they stated that when the
matter would be finally heard in the Opposed motion Court, the execution of the
tender would have been concluded. Therefore, the application is moot.
[39) Thirdly, they raised a point in limine of non-joinder of interested parties. These are
the parties who will be affected by the order sought and the parties have not been
joined in these proceedings.
[40] On 18 November 2024, the first respondent filed a supplementary affidavit in
response to the applicant's suppl ementary affidavit of 11 November 2024 , with the
aim of clarifying any confusion arising from it.

11
[41] The First Respondent confirmed that they terminated the contract with the Second
Respondent on 4 March 2024. When the contract was terminated, the Second
Respondent had completed 92% of the project task and the remaining 8% was
completed and finalised by the First Respondent through its internal processes.
[42] The First Respondent further stated that the contract works were certified as
complete on 13 September 2024, as reflected in the certificate of completion
annexed to their affidavit as "CC 1 ".
[43] The First Respondent contended that the matter had become moot because, by the
time the Applicant filed its supplementary affidavit and the matter was heard on 21
November 2024, the tender had already been concluded and finalised. It is therefore
necessary to consider the issue of mootness first, as my finding on it may be
dispositive of the matter.
Mootness
[44] The matter was argued on 21 November 2024. By that date, the factual position was
no longer in dispute. The First Respondent placed before the Court evidence that the
contract awarded pursuant to the impugned tender process had been completed on
13 Septemfinber 2024. It is further common cause that the contract with the initially
appointed contractor had been terminated on 4 March 2024 , and that the subsequent
appointment was fully implemented and finalised.

12
[45] On these facts, the impugned administrative action has been fully spent. No practical
or effective relief can now be granted to the Applicant. The Constitutional Court has
consistently held that courts do not decide abstract or academic questions where the
underlying dispute has ceased to exist. The doctrine of mootness is rooted in judicial
economy, the separation of powers, and the principle that courts adjudicate live
controversies, not hypothetical disputes.
[46] The Applicant urged the Court to determine the matter notwithstanding mootness,
relying on the seriousness of the alleged procurement irregularities. These include
the contradictory understanding of the process between the BEG and BAG, the
absence of a final BAG recommendation, and the Municipal Manager's intervention
in awarding the tender solely on the BEC's recommendations and the basis of
Municipal Infrastructure Grant ("MIG") and Municipal Disaster Relief Grant ("MDRG")
funding deadlines.
[47] These allegations, if established, would undoubtedly raise concerns about
compliance with the MFMA and the municipality's SCM policy. However, the test is
not whether the allegations are serious, but whether the interests of justice require
the Court to pronounce on a matter that is no longer live.

13
[48] The Constitutional Court has identified limited circumstances in which a court may
decide a moot matter: where the issue is of public importance and likely to recur;
where legal certainty is required; or where the conduct complained of is capable of
repetition yet evading review. The discretion is narrow and must be exercised
sparingly.1
[49] The SCA had this to say regarding mootness in the case of Radio Pretoria v
Chairman, Independent Communications Authority of South Africa, and
Another 2005 (1) SA 47 (SCA) para
[41] It is clear that the question of a temporary licence is no longer a live issue.
That question is moot. No order by us will impact on Radio Pretoria's ability to
continue broadcasting until the litigation concerning /CASA 's decision to refuse
the four-year licence application has been finally resolved. Courts of appeal
often have to deal with congested court rolls. They do not give advice
gratuitously.
They decide real disputes and do not speculate or theorise (see the Coin
Security case, supra, at paragraph [7) (875A-D)) . Furthermore, statutory
enactments are to be applied to or interpreted against particular facts
and disputes and not in isolation.
[50] The Constitutional Court also had an occasion to consider the issue of mootness in
Minister of Tourism and others v Afriforum NPC and another 2023 JDR 0761
(CC) para
1 Independent Electoral Commission v Langeberg Mun icipality200 I (3) SA 474(CC)para 9

14
[23] A case is moot when there is no longer a live dispute or controversy
between the parties which would be practically affected in one way or
another by a court's decision or which would be resolved by a court's
decision. A case is also moot when a court's decision would be of
academic interest only. In National Coalition for Gay and Lesbian
Equality it was said:
"A case is moot and therefore not justiciable , if it no longer
presents an existing or live controversy which should exist
if the Court is to avoid giving advisory opinions on abstract
propositions of law.
[51] In the present matter, the alleged irregularities do not, in my view, justify the Court
departing from the ordinary rule.
[52] First, the procurement process at issue was unique to this tender, and the factual
matrix, particularly the contradictory BEC/BAC interpretation of how functionality
points must be calculated and the MIG/MDRG funding related urgency is highly
specific. While procurement irregularities are regrettably not uncommon, the Court is
not persuaded that the precise pattern of issues is likely to recur in a manner that
would evade judicial scrutiny.
[53] Second, the Applicant had ample opportunity to pursue interim relief or to seek to
interdict implementation of the award pending review. As the dominus litis the
Applicant should have done more to expeditiously prosecute the review. The fact that
the contract proceeded to completion before the hearing, is not a basis for the Court
to resuscitate a dispute that has become academic.

15
[54] Third, while the Municipality's reliance on MIG/MDRG deadlines as justification for
bypassing the BAC raises questions of administrative propriety, those questions can
be addressed through internal oversight mechanisms. Judicial intervention at this
stage would serve no practical purpose.
[55] In all the circumstances, I am not satisfied that the interests of justice require this
Court to determine the merits of a dispute that has become moot. The matter is best
disposed of on that basis. To proceed to the merits would be to issue what would
amount to an advisory opinion, something our courts have repeatedly cautioned
against.
[56] It is necessary to emphasise that the applicant approached this Court seeking a
judicial review of the tender award. That is the only relief this Court is empowered to
determine on the papers before it. A review court does not fashion remedies beyond
the statutory and constitutional framework governing administrative action. Its task is
confined to determining whether the impugned decision is lawful, rational, and
procedurally fair.
[57] However, because the contract has been fully implemented and completed, and
because the impugned administrative action has already produced its final
consequences, the Court is unable to grant any effective review remedy . The Court
cannot set aside a contract that no longer exists, nor can it remit a matter for

16
reconsideration where the underlying procurement process has been overtaken by
events.
(58] The Applicant therefore finds itself in a position where the Court cannot determine
the review on its merits, not because the grounds are weak or ill-founded, but
because the factual substratum necessary for a review remedy has fallen away. This
reinforces the conclusion that the matter is moot and must be disposed of on that
basis.
(59] Following the amendment of the notice of motion, the applicant sought, in the
alternative, just and equitable compensation in terms of s 8(1 )(c)(ii)(bb) of PAJA. This
form of relief is exceptional and is granted only in rare circumstances. It presupposes
a prior judicial finding that the impugned administrative action was unlawful.
(60] Compensation under PAJA is not a primary remedy. It is contingent upon a court first
determining that the administrative action in question is unlawful. Only then does the
enquiry shift to whether compensation is appropriate in the circumstances.
(61] In this matter, the Court has expressly declined to determine the merits of the review
because the dispute is moot. The Court therefore makes no finding on the lawfulness
of the tender award. Without such a finding, the statutory precondition for awarding
compensation under s 8(1)(c)(ii)(bb) is absent.

17
[62] To award compensation in the absence of a finding of unlawfulness would be to grant
a remedy without establishing a wrong, something PAJA does not permit. It would
also collapse the distinction between review and damages, a distinction our courts
have consistently maintained.
[63] The alternative claim for just and equitable compensation must therefore fail, not on
its merits, but because the Court cannot reach the merits at all.
Conclusion and Costs
[64] The remaining issue concerns costs. Although the matter falls to be disposed of on
mootness, it does not follow that the Applicant should bear the costs of the
proceedings. The general rule that costs follow the result is not inflexible, particularly
where the litigation has become moot through circumstances not attributable to the
applicant.
[65] On the facts, the applicant launched the proceedings at a time when the dispute was
live, and when the impugned procurement process had not yet been fully
implemented. The applicant cannot be faulted for approaching the Court to challenge
what it contended were serious irregularities in the tender process, including the
conflicting approaches of the BEC and BAC to the calculation of functionality points
and the Municipal Manager's intervention in the absence of a BAC recommendation.
These were not frivolous or vexatious grounds; they were matters that, at the time of
institution, warranted judicial scrutiny.

18
[66] In these circumstances, the interests of justice are best served by directing that each
party pay its own costs. Such an order recognises the Applicant's legitimate
concerns, avoids punishing a party for raising issues that were serious at the time,
and reflects the fact that the Court has not determined the merits.
[67] In the result, I make the following order:
67.1 The application is dismissed.
67.2 Each party to pay its own costs.
::::---,.,
NKOANAA.J
ACTING JUDGE OF THE HIGH COURT
LIMPOPO DIVISION, POLOKWANE
Heard on 21 November 2024
Judgment delivered on:

19
This Judgment was handed down electronically by circulation to the Parties' representatives
by e-mail , the date and time for hand down of the Judgment is deemed to be 18 May 2026
at 10:00.
For the Applicant
Adv. M Lauw
Instructed by DDKK Attorneys Inc
Polokwane
For the First Respondent
Adv M Mojapelo SC
Adv M Matshisevhe
Instructed by Madima M Attorneys Inc.
Thohoyandou