Drennan Maud & Partners v Town Board of the Township of Pennington (8161/92) [1998] ZASCA 29; 1998 (3) SA 200 (SCA); [1998] 2 All SA 571 (A) (27 March 1998)

80 Reportability
Contract Law

Brief Summary

Contract — Breach of contract — Duty of care — Town Board engaged consulting engineers to design and supervise construction of a protective wall against flooding — Wall inadequately constructed leading to erosion and damage — Town Board claimed damages for breach of duty of care — Special plea of prescription raised, asserting that the Town Board had knowledge of the breach by the completion of the wall — Court held that the Town Board had acquired the requisite knowledge before the prescription period, thus the claim was prescribed and the special plea upheld.

Comprehensive Summary

Summary of Judgment


1. Introduction


This was an appeal in the Supreme Court of Appeal of South Africa concerning a special plea of prescription raised in response to a contractual damages claim. The substantive merits of the alleged breach of contract were not determined; only the prescription point was finally adjudicated.


The appellant was Drennan Maud & Partners, a partnership of consulting civil engineers and engineering geologists. The respondent was The Town Board of the Township of Pennington (“the Town Board”), a local authority controlling (among other things) public property in the Pennington area in KwaZulu-Natal.


The procedural history was that the Town Board instituted action by summons served on 20 November 1992, claiming damages said to have been caused by the appellant’s defective professional recommendations and design. By agreement or court order, the appellant’s special plea of prescription was separated for prior determination. The court a quo (Thirion J, Durban and Coast Local Division) dismissed the special plea. Leave to appeal was granted to the Supreme Court of Appeal. The Town Board also pursued a cross-appeal directed at the court a quo’s decision to make no order as to costs when dismissing the special plea.


The general subject-matter of the dispute was the Town Board’s claim that professional engineering services were rendered negligently (in breach of contract), resulting in the construction of a riverbank retaining wall that failed to achieve its protective purpose, and the consequential question whether the Town Board’s damages claim had prescribed under the Prescription Act 68 of 1969.


2. Material Facts


In September 1987 severe floods altered the course and mouth of the Umzinto River at Pennington, causing significant erosion on the right-hand (southern) bank. Adjacent to the affected area were (i) an admiralty reserve consisting of sandy beachfront, (ii) Lot 1166, a strip of land used as public open space and owned/controlled by the Town Board (including a car park and ablution block), and (iii) Salmon Drive, a cul-de-sac owned by the Town Board providing access to Lot 1166. Inland were privately owned lots (including Lots 667, 666, 665 and 664). The court proceeded on the assumption most favourable to the Town Board, namely that the wall was built on the admiralty reserve close to the northern border of Lot 1166.


The Town Board engaged the appellant to propose measures to reinstate and protect the right bank, and the appellant recommended a reinforced concrete retaining wall running from a railway bridge embankment to the river mouth. The Town Board accepted the proposal and instructed the appellant to design and supervise the wall’s construction; a contractor was appointed to build it according to the appellant’s design.


Two design/construction changes occurred during implementation. First, after the bedrock was found to dip more deeply than anticipated, the founding method for most of the wall was altered: the initial portion would be founded on bedrock, but the remainder would be supported on grout-injected piles bearing on bedrock beneath sand. It was common cause in the appeal that the Town Board consented to this alteration. Second, the wall was not completed to its intended length because of insufficient funds; the appellant warned that a partially completed wall could cause intensive scouring downstream of the wall’s end and could lead to damage, including the risk of undermining behind the wall.


After May 1989, and outside the scope of the contract, members of the public placed sea sand backfill behind the wall up to the top of the wall.


Heavy rain events occurred between 22–23 September 1989, 2–3 November 1989, 10–11 November 1989, and 29–30 November 1989, with the first and last being exceptionally heavy. During the September floods, and again in early November, sinkholes and subsidences formed in the backfill behind the wall, particularly near the wall, and these features progressively enlarged. By January 1990 the river was flowing freely under the piled section of the wall, and the protective intervention had become ineffective.


The Town Board sued for damages comprising amounts spent on construction of the wall, the appellant’s professional fees, and related remedial costs (backfilling, landscaping and grassing). Although the Town Board’s pleadings were amended late in the trial, the central complaint relevant to prescription was that the appellant had breached its contractual duty to exercise reasonable care and skill in recommending and designing protective works, and that the wall failed to protect the Town Board’s properties (ultimately identified in evidence as Lot 1166 and, at least potentially, Salmon Drive).


For purposes of prescription, the critical evidence concerned what the Town Board knew (or was deemed to know) by 20 November 1989. The Town Clerk, Ms Mann, testified that she and the Board’s chairperson inspected the site during or shortly after the September floods and observed depressions behind the wall, which caused concern. By mid-November 1989 deterioration in the backfill had become substantial and observable. On 18 November 1989, the Town Board received advice from a local engineer (Mr Robinson) that an engineer could be liable for faulty design. On 20 November 1989, a committee decided to seek urgent attention from the appellant. A meeting took place on 27 November 1989, where the chairperson, Mr Potgieter, distinguished between toe-end erosion and erosion behind the wall and attributed the latter to the use of piling rather than a continuous foundation.


The court a quo accepted that by 20 November 1989 the Town Board could, by reasonable care, have acquired knowledge that the wall’s design was defective in that it did not permit reclamation of previously eroded land because flooding would cause scour that removed sand from under and behind the wall. However, it found that the appellant had not shown the Town Board had (or should be deemed to have had) knowledge by that date that the wall would fail in its purpose of protecting the relevant properties. The Supreme Court of Appeal reassessed that conclusion on the record.


3. Legal Issues


The central legal question was whether, by 20 November 1989, the Town Board had knowledge or deemed knowledge (through the exercise of reasonable care) of “the facts from which the debt arises” as contemplated by section 12(3) of the Prescription Act 68 of 1969, such that the Town Board’s claim had become prescribed by the time summons was served on 20 November 1992 (more than three years later).


The dispute required determination of a mixed question involving the application of law to fact. It required identifying what facts were necessary to trigger prescription under section 12(3), and then deciding whether the Town Board’s actual knowledge, together with what it could have acquired by reasonable care (including the evaluation of observable facts), met that statutory threshold before the critical date.


A further interpretive issue arose regarding whether “the facts from which the debt arises” meant the facts completing the cause of action as pleaded, or rather the facts grounding the claim/debt in the broader sense used in the Prescription Act. A related point was whether knowledge of one relevant defect sufficed to start prescription, even if the creditor had not appreciated the full extent or all aspects of the defective performance.


4. Court’s Reasoning


The Supreme Court of Appeal approached the matter through the statutory framework in section 12 of the Prescription Act, emphasising section 12(3), which postpones the running of prescription until the creditor has knowledge of the debtor’s identity and the facts giving rise to the debt, while deeming such knowledge to exist where it could have been acquired by reasonable care. It was common cause that the identity of the debtor was known; the dispute concerned the factual knowledge component.


Olivier JA (majority judgment)


Olivier JA accepted (without deciding) the interpretation adopted by the court a quo that the statutory phrase could be equated to “all the facts from which the cause of action arises,” but held that the trial court’s ultimate conclusion turned essentially on factual evaluation and was affected by a misconception as to the property interests the wall was intended to protect.


A key step in Olivier JA’s reasoning was clarifying the contractual purpose of the wall as it emerged from the evidence. The court a quo’s analysis proceeded on the footing that the wall’s object was to protect a private inland lot (Lot 666). The appellate court held this to be incorrect on the evidence: the appellant’s contractual obligation was directed to protecting the Town Board’s own properties, specifically Lot 1166 and the end of Salmon Drive, and not (as a primary contractual object) a private property further inland. This misidentification mattered because it shaped the trial court’s assessment of whether it was reasonably apparent that the observed scour and subsidence would threaten the protected interests.


Olivier JA endorsed the trial court’s unchallenged findings that the damage to the backfill was visible before 20 November 1989 and that, by reasonable care, the Town Board could have acquired knowledge by that date that the design was defective in a material respect: the piled foundation permitted scour below and behind the wall. The remaining question was whether, by that date, the Town Board should also have realised that this defect meant the wall would not serve its protective function in relation to Lot 1166 and Salmon Drive.


On that question, the appellate court held that the trial court’s contrary finding could not be supported. Olivier JA reasoned that the observable features—particularly the scouring action at the toe end and the existence of a substantial subsidence nearer the middle of the wall (with visible pooling suggesting seepage/flow under the wall)—were such that a reasonable person, aware of the history of flood damage and the object of the works, would have appreciated that the same mechanism would progressively undermine the wall’s purpose and that there was nothing to prevent the erosion from spreading towards the protected properties. The court stressed that “reasonable care” in section 12(3) required diligence not only in gathering facts but also in appreciating their significance, meaning that the creditor is deemed to know what a reasonable person would infer from the facts.


Olivier JA also addressed the appellant’s report/letter of 23 November 1989, which expressed the view that the wall’s bank-protection function was satisfactory. The court held that this could not materially postpone prescription because the report was not based on an inspection of the site as it existed near the critical date; it followed that it could not reliably negate what reasonable care would have revealed from the conditions that were plainly observable on site. The court also noted that the case was not one where the debtor had wilfully prevented knowledge under section 12(2), and that the Town Board was not shown to have been misled into inactivity by that report.


Finally, Olivier JA linked the knowledge enquiry to the nature of the loss claimed. The Town Board did not claim prospective future damage to its property; it claimed as damages the wasted costs of building the wall and associated expenses. On that basis, the court held that the relevant loss had occurred once the Town Board should have appreciated (through deemed knowledge) that the wall did not serve the purpose for which it was built, rendering the expenditure wasted. Even if physical damage to the Town Board’s own land had not yet occurred by the critical date, prescription could nonetheless commence because the claimed patrimonial loss (wasted expenditure) was already sustained.


Harms JA (concurring)


Harms JA agreed with the result but added an interpretive emphasis. He stated that the court a quo had not been referred to authority on the meaning of “debt” in the Prescription Act and that “debt” is not confined to the pleaded cause of action; it refers more broadly to the claim. There was, in his view, no reason to assign a different meaning to “debt” in section 12(3) than in other provisions such as section 15(1).


On that approach, Harms JA identified the “debt/claim” as arising from a single contractual obligation: the duty to exercise reasonable care and skill in recommending and designing a wall to reinstate and protect the right bank. The breach occurred when the defective design was made (before May 1989). Once the Town Board knew or was deemed to know that the design was defective in a relevant respect (as the trial court had already found regarding scour and reclamation failure), it was not necessary for prescription purposes that the Town Board also appreciate every further consequence or every other respect in which the design might be defective. He supported this by noting that section 12(3) does not postpone prescription until the creditor discovers the full extent of rights or all manifestations of defective performance.


In Harms JA’s reasoning, therefore, the trial court’s first finding—that the Town Board had deemed knowledge that the design was defective in permitting scour that removed sand under and behind the wall—was already decisive and sufficient to uphold the special plea.


5. Outcome and Relief


The Supreme Court of Appeal upheld the appeal. It set aside the order of the court a quo dismissing the special plea and replaced it with an order upholding the special plea of prescription and dismissing the Town Board’s claim.


The Town Board’s cross-appeal (seeking costs in the court a quo following its success there) was dismissed, because the appellant ultimately succeeded and the special plea was upheld.


The costs orders were made in favour of the appellant. The appeal was allowed with costs (including the costs consequent upon the employment of two counsel). The substituted order in the court a quo upheld the special plea and dismissed the plaintiff’s claim with costs, also including the costs of two counsel.


Cases Cited


The judgment cited Gericke v Sack 1978 (1) SA 821 (A) in relation to the onus of proving knowledge for purposes of prescription. It cited Oslo Land Co Ltd v Union Government 1938 AD 584 regarding when a debt for damages becomes due and also in relation to the characterisation of the obligation. It cited Evins v Shield Insurance Co Ltd 1980 (2) SA 814 (A) and Swart v Van der Vyver 1970 (1) SA 633 (A) in relation to when loss occurs and when a damages debt becomes due. In Harms JA’s concurring judgment, reference was made to Sentrachem Ltd v Prinsloo 1997 (2) SA 1 (A) and Standard Bank of South Africa Ltd v Oneanate Investments (Pty) Ltd (in liquidation) 1998 (1) SA 811 (SCA) on the meaning of “debt” in the Prescription Act, and to Van Staden v Fourie 1989 (3) SA 200 (A) on the principle that prescription does not await discovery of the full extent of rights.


Legislation Cited


The Prescription Act 68 of 1969 was applied, in particular section 12(1)–(3), and (in the concurring judgment’s discussion of interpretive authority) reference was made to the meaning of “debt” as used in section 15(1) of the same Act.


Rules of Court Cited


No rules of court were cited in the reported judgments.


Held


The Supreme Court of Appeal held that the Town Board had, at least by 18 November 1989, knowledge or deemed knowledge (as contemplated by section 12(3) of the Prescription Act) of facts sufficient to found its damages claim arising from the appellant’s defective design of the retaining wall. On the evidence accepted in the proceedings, the observable scouring and subsidence behind the wall, together with the known use of piled foundations, were such that a reasonable person in the Town Board’s position would have appreciated the significance of those facts and deduced that the design defect would cause the wall to fail in its protective purpose.


Because summons was served only on 20 November 1992, more than three years after the Town Board was deemed to have such knowledge, the Town Board’s contractual damages claim had prescribed. The appellant’s special plea was therefore upheld, and the Town Board’s action was dismissed with costs.


LEGAL PRINCIPLES


Section 12(3) of the Prescription Act 68 of 1969 requires knowledge of the debtor’s identity and the material facts from which the debt arises, but it also deems such knowledge to exist where it could have been acquired through the exercise of reasonable care. In applying this standard, reasonable care encompasses not only diligence in observing and discovering relevant facts, but also reasonable appreciation of the significance and implications of those facts.


For purposes of prescription, the relevant “debt” in the Prescription Act is the claim in a broad sense and is not necessarily confined to the pleaded cause of action. Where the claim is founded on breach of a single contractual obligation, prescription is not postponed until the creditor appreciates every distinct consequence or every different respect in which performance was defective; once knowledge (actual or deemed) exists that performance was defective in a relevant respect giving rise to the claim, prescription may commence.


A damages claim for wasted expenditure may become due (and prescription may commence) once the creditor has actual or deemed knowledge that the expenditure was wasted because the contracted-for performance failed in its purpose, even if later physical damage to property has not yet fully manifested, provided that the loss claimed has already occurred.

About SAFLII
Databases
Search
Terms of Use
RSS Feeds
South Africa: Supreme Court of Appeal
SAFLII
>>
Databases
>>
South Africa: Supreme Court of Appeal
>>
1998
>>
[1998] ZASCA 29
|

|

Drennan Maud & Partners v Town Board of the Township of Pennington (8161/92) [1998] ZASCA 29; 1998 (3) SA 200 (SCA); [1998] 2 All SA 571 (A) (27 March 1998)

REPUBLIC
OF
SOUTH AFRICA
REPORTABLE
Case no: 8161/92
IN THE SUPREME COURT OF APPEAL OF
SOUTH AFRICA
In the matter between:
DRENNAN MAUD & PARTNERS
Appellant
and
THE TOWN BOARD OF THE TOWNSHIP
OF PENNINGTON
Respondent
Coram
: Van Heerden DCJ, Harms, Olivier, Scott and Zulman JJA
Date of hearing
: 20 February 1998
Date of delivery
: 27 March 1998
JUDGMENT
2
OLIVIER JA
The Umzinto river in
KwaZulu-Natal
flows into the
Indian Ocean
within the
area under the control of the Respondent, the Town Board of Pennington
(hereinafter referred to as the "Town Board"). In September 1987 heavy floods
occurred. The river came down in spate, breached the right-hand (southern) bank,
passed over beach area, and entered the sea some 300 metres south of its former
mouth. The effect was that a large portion of the original river bank area was eroded. As the floods subsided, a quantity of sand
was deposited on the eroded
area, but it was evident that future floods would create a real risk to properties on
the south bank.
These properties can be described as follows: Along the original river
course is admiralty reserve - a wide, sandy area. Adjacent to it and to the south
is
Lot
1166, a strip of land with a beach frontage, and used as public open space.
On this property, which is owned and controlled by the Town Board, the Town
Board established a car park and built an ablution block. Inland and adjacent to
3
Lot
1166, are a number of privately owned properties, Lots 667,666,665 and 664,
and
Salmon Drive
, a cul de sac owned by the Town Board giving access to the
parking area on
Lot
1166.
Wishing to protect
Lot
1166 and
Salmon Drive
against future flooding, the Town Board consulted the appellant, a partnership of consulting civil engineers
and engineering geologists, with the request that it present the Town Board with
proposals for the reinstatement and protection of the right-hand bank of the river.
The appellant recommended the construction of a reinforced concrete retaining
wall, running more or less parallel to the border between the admiralty reserve and
Lot
1166, from the southern embankment of a railway bridge crossing the river to
the mouth of the river. The Town Board accepted the proposal and instructed the
appellant to design and supervise the building of the wall. The Town Board
subsequently engaged a construction firm to build the wall in accordance with the
design.
According to the original design the wall was to end in the sea, a total
4
distance of about 350 metres from the embankment. It was to have a footing more
than a metre wide, be founded on bedrock, and was to rise to a uniform level, 0.6
metres above that of the original beach.
It is unclear whether the wall as designed and built stood on the admiralty
reserve or on the adjoining
Lot
1166. For the purpose of this judgment the issue
is not crucial, and I shall adopt the assumption most favourable to the Town
Board, namely that it was built on the admiralty reserve, close to the northern
border of
Lot
1166.
During the course of construction two alterations to the original design were
proposed by the appellant to the Town Board.
First, it was proposed to change the method of founding the wall over much
of its length. While the first 60 metres of the wall from the railway embankment
would continue to stand on a foundation bedded on rock, the foundation of the
remainder of the wall, though beneath sand level, would be supported above
bedrock on grout injected piles that would stand on bedrock. The reason for this
5
alteration was practical: After some 60 metres the bedrock dipped abruptly to a
depth not anticipated by the appellant. To excavate the extra sand overburden
would have been prohibitively expensive.
Second, construction was terminated when only 270 instead of 360 metres
of wall, measured from the embankment, had been built. There were insufficient
funds. The Town Board was warned by the appellant that this decision could have
serious consequences because a partially completed wall could cause intensive
scouring of the river bank just downstream from the end of the wall. This in turn could lead to Lots 665 and 664 being severely damaged
and, further, there was the
possibility of the river undercutting the backfill behind the wall which, in the
event of a severe flood, could result in erosion of the public open space "south of
Lot 666" (ie Lot 1166).
After May 1989, outside the scope of the contract, members of the public
backfilled the area behind the wall with sea sand to the level of the top of the wall.
It is common cause that heavy rain fell in the catchment area of the river on
6
a few separate occasions relevant to this appeal, viz between 22 to 23 September
1989, 2 to 3 November 1989, 10 to 11 November 1989 and 29 to 30 November
1989. The first and last of these were exceptionally heavy.
The September rains, the first since the wall had been built, caused the river
to come down in spate, bursting through the sand bank which had blocked the free flow of water to the sea in September 1987. There
was a strong flow in the river
along the wall. During the September and again the early November floods,
sinkholes formed in the backfill behind the wall, more particularly near the toe of
the wall. These sinkholes developed progressively and became substantial. By
January 1990, the river was flowing freely under the whole length of the piled section of the wall. Both the river and the Town Board
were back to where they
had been before the appellant was consulted.
The learned judge a quo correctly described the cause of the
ineffectiveness of the wall when he said the following:
It would seem that what happened was that during the
7
floods, the river, due to the combined effect of the velocity of its flow, the turbulence of its flow and
perhaps also the gradient, scoured the river bed
alongside the wall down to below the level of the
footing of the wall and then eroded the sand under the
wall in the piled section and the fill at the back of the
wall, or else that the fill, being sand with little cohesion
and not being compacted, became saturated from below
with water from the river and consequently slipped
under the wall into the channel of the river and was
washed out to sea, thereby enabling the river to invade
the area at the back of the wall and eventually to form
a channel on the landward side of the wall. There was
also erosion by the tides at the toe of the wall and for
some distance along the wall.
The Town Board issued a summons against the appellant, claiming as
damages the amounts spent on the construction of the wall, the professional fees
of the appellant, and the cost of backfilling, landscaping and grassing the area
behind the wall. It based its claim for damages on an alleged breach by the
appellant of the contract. In essence, the Town Board alleged that the appellant
had breached its obligation to exercise reasonable care and skill in making its
recommendations and preparing its design. In particular, it was alleged that the
8
appellant should have realised that piled foundations would have aggravated the
problem rather than solve it. The claim was based on the erosion which occurred
roughly in the middle section of the wall, the allegation being that the design
change had taken place without the consent or authority of the Town Board. The
latter allegation was shown to be incorrect and the case proceeded on the basis that
the Town Board had consented to the alteration. The erosion at the toe of the
wall, which was foreseen, did not form part of the complaint.
However, the merits of the Town Board's claim are not at this stage of the
proceedings in issue because of a special plea of prescription which, by an order
of court, had to be decided separately.
The special plea alleged that the cause of action (the breach of contract)
arose not later than the completion date of the wall (May 1989) and that by no later
than 13 November 1989 the Town Board had knowledge of the identity of the
debtor (the appellant) and the facts from which the alleged claim arose. In a
rejoinder it was additionally alleged that had the Town Board exercised reasonable
9
care in the light of the facts known to it by 13 November, it could have had
knowledge of those facts.
The averments relating to knowledge were necessary in the light of s 12 of
the Prescription Act, No 68 of 1969 ("the Act") which reads as follows:
12 (1) Subject to the provisions of
subsections (2) and (3), prescription
shall commence to run as soon as
the debt is due.
(2)
If the debtor wilfully prevents the creditor from coming to know of the
existence of the debt, prescription
shah not commence to run until the
creditor becomes aware of the existence of the debt.
(3)
A debt shall not be deemed to be
due until the creditor has knowledge
of the identity of the debtor and of
the facts from which the debt arises:
provided that a creditor shall be
deemed to have such knowledge if
he could have acquired it by
exercising reasonable care.
Important is sub-section (3). As the action was instituted by the issue and
10
service of summons on the appellant only on 20 November 1992, the Town
Board's claim (which is subject to a three year extinctive prescription period)
would have become prescribed if it had acquired the actual or deemed knowledge
required by ss (3) before 20 November 1989. In the light of Gericke v Sack
1978(1) SA 821 (A) the
onus
to prove such knowledge rested on the appellant.
The special plea was adjudicated upon and dismissed by Thirion J in the
Durban
and Coast Local Division. He subsequently granted leave to appeal to this
Court.
Originally the Town Board averred that in terms of the contract the
appellant would -
(a)
investigate the cause of erosion damage to the immovable property owned
by or under the control of the Town Board at the mouth of the river;
(b)
make recommendations about the most efficient method of
(i) reclaiming the land lost as a consequence of erosion, and
(ii) protecting "the said property" against further erosion damage;
11
(c) design the works required to give effect to the recommendations.
(This is taken from the judgment of the court below and may have been a summary of the pleading and not its actual wording. The original
pleading is not in the
record.) At the end of the trial, the Town Board amended its particulars of
claim in some respects, but failed to make all the consequential amendments that
were necessary. (In the end the failure had no effect on the outcome of the case.)
The apparent reason for the amendment was that, as will appear, the Town Board
had knowledge, before 20 November 1989, that the wall did not serve the purpose
of reclaiming land lost as a consequence of the erosion. In the light of that fact the
claim as originally formulated would have become prescribed. The Town Board,
therefore, withdrew the allegation that one of the purposes would be the
reclamation of the land lost as a consequence of the floods, and instead solely
relied on the duty of the appellants to design a wall which would protect the
property described in the pleadings.
The amended particulars of claim state that the terms of the contract were
12
that-
(a)
the appellant would investigate the cause of erosion damage to
"certain immovable property owned by, alternatively under the
control of" the Town Board;
(b)
the appellant would make recommendations concerning the most
efficient and cost effective method of protecting the "said property";
(c)
the defendant would design the works;
(d)
in performing its obligations, the defendant would exercise
reasonable care and skill.
It became clear from the evidence that by the "immovable property" was
meant
Lot
1166 and, perhaps,
Salmon Drive
.
The enquiry after the amendment can thus be defined as follows :
when did
the Town Board, acting through its employees and members, become aware, or is
deemed to have become aware, that the appellant had committed a design fault
which resulted in a failure to protect the Town Board's properties as described, ie
13
Lot
1166 and the end of
Salmon Drive
?
If such knowledge was acquired, or deemed to have been acquired, by the
Town Board on or before 20 November 1989, its claim would have become prescribed.
Only one witness testified at the trial, viz Ms Mann, the Town Clerk of
Pennington for some 25 years.
She testified that she had visited the area under discussion, accompanied by
Mr Potgieter, the Chairman of the Town Board, during or shortly after the floods
of September 1989. The purpose of the visit was to see how the wall was
withstanding the flood. They observed three small depressions - about 40
centimetres in diameter and 30 centimetres deep - behind the wall and some
distance upstream from the toe opposite the ablution block. They were "most concerned" when they noticed these depressions.
At the toe of the wall were
larger depressions but they were to be expected because the wall had not been
completed. Because it was school holidays, they felt that there could be a danger
14
to school children on the beach and decided to have warning signs erected. Along
the beach - one near the toe and another opposite the three depressions.
Ms Mann did not inspect the site after the rains of 2 and 3 November it
being the duty of the Town Manager to do so and report to her. Nevertheless, she
was aware that sink holes were occurring or had enlarged, but, according to her,
these were concentrated more towards the toe. Shown a photograph of a large and
deep subsidence which had by then taken the place of the three sinkholes
described above, she stated that she had become aware of its existence only
towards the end of November 1989 although she could not say exactly when.
At an informal meeting of the Town Board on 18 November Mr
Robinson, a local property owner and President of the SA Council of Professional
Engineers, informed the Town Board that if they were dissatisfied with the work
of the consulting engineers, a complaint should be lodged with his Council, that
a professional engineer is liable for faulty design, and that such liability cannot
become prescribed. At that stage the Town Board felt that it had been left "with
15
a wall that was incomplete and not very satisfactory," although, according to Ms
Mann, the Town Board still believed that it was the non-completion of the wall
that caused the problem.
On 20 November 1989 a special committee of the Town Board decided that
a letter be faxed to the appellant advising it that the wall required urgent attention
and requesting that a full report be submitted at a meeting to be held on either 27
or 28 November, failing which the Town Board would have no option but to
appeal to "higher authority". Ms Mann testified that what required urgent
attention was the erosion of the beach at the toe end of the wall.
The envisaged meeting took place on 27 November 1989. A letter by the
appellant dated 23 November was tabled. In it the appellant stated that "scour
occurred under the base of the wall and at the unprotected portion at the southern
end of the wall." The works were "primarily designed as protection for the right
bank and for
Salmon Drive
." Disappointment at the collapse of "some of the
backfill" was expressed, but it was ascribed to scour action. The appellant also
16
disclaimed responsibility for the erosion of the backfill. The letter concluded with
a summary stating that the structural integrity of the works had not been impaired
and that "the river bank protection function of the works is satisfactory, the
reclamation work aspect is a little disappointing and measures may have to be
considered to protect the bottom of the backfill, to prevent scour and associated
development of sink holes."
Ms Mann testified that the meeting was the first occasion that the
Town Board became aware that the problem was due to scour between the piles;
prior thereto the only scour it was aware of was at the toe of the wall. However,
it is clear from the minutes of the meeting that at least Mr Potgieter, the Chairman
of the Town Board, clearly distinguished between the damage at the toe of the wall
and the erosion of the backfill further back. He was of the view that the cause of
the latter was the use of piling instead of solid uninterrupted foundations.
The heavy rains of 29 and 30 November caused further erosion of the
backfill. By January 1990 the river was freely flowing only on the landward side
17
of the wall, a sand bank having built up on the other side.
From the cross-examination of Ms Mann the following became apparent:
(i) Prior to 20 November 1989 she was aware of a large subsidence beside the
wall, originating at the toe end and extending some distance away from it. (ii) The row of sink holes observed in September 1989 led
her to the conclusion
that there was a serious problem with the wall or the back-fill.
(iii) The water in the subsidence described in (i) - and which is clearly visible
in the relevant photographs - indicated that water was seeping from the river
under the wall into the subsidence.
(iv) Before 16 November 1989 the Town Board was aware that the river could
pass under the wall near the toe of the wall.
(v) It was apparent that a substantial deterioration and erosion of the backfill
had occurred between 2 and 16 November 1989. It had no connection with
the problem at the toe.
(vi) The formation of this subsidence was there to be observed by the Town
18
Board's employees working on site under the supervision of the Town
Manager.
(vii) Anybody looking at the situation prior to 16 November 1989 would at least
have thought that it was possible that water was coming under the wall at
that point. The wall was 3.6 metres high from its footing, and the hole was
about 4 metres deep. Consequently, she conceded that, as a reasonable
person looking at the site, it should have occurred to her that there might be
something wrong with the wall and that the large subsidence had been
formed by the river coming through underneath the wall and removing the
sand.
Although Ms Mann denied that the Town Board was aware that the
problems were caused by faulty design before 27 November 1989, there was never
any reason to believe that the wall itself was not properly built or constructed in
accordance with the design. Furthermore, at the meeting of 27 November 1989,
Potgieter accused Dr Maud of being responsible for a faulty design. And if
19
Potgieter, as chairman of the Town Board, realised this to be the position on 27
November 1989, the Town Board ought to have realised it by 18 November 1989,
because nothing had changed in the meantime.
The learned judge dismissed the special plea on the strength of the
following conclusions:
(i) The damage to the backfill on the landward side of the wall was
visible before 20 November 1989.
(ii) By 18 November 1989 a visual inspection of the wall by even a
layman would have revealed that the integrity or structure of the wall
had not been impaired. That left as the only cause of the subsidence
the fact that the wall was not founded on bedrock but rested on end
bearing piles which went down through sand, thus making scour
below and behind the wall possible. At least one inference could be
drawn in these circumstances: that the appellant had not taken
sufficient precaution in designing the wall to ensure that the wall
20
would permit the
reclamation
of the land previously eroded by the
river.
(iii) The Town Board, by the exercise of reasonable care, could have acquired knowledge by not later than 20 November 1989 that the
design of the wall was defective in that, though the wall was built in accordance with the design, it did not serve the purpose of
permitting
the
reclamation
of previously eroded land, because the river,
whenever it flooded would, through scour action, remove the sand
from under and behind the wall.
(iv) In spite of the aforegoing, the Town Board could not, by the exercise
of reasonable care, have acquired knowledge on or before
20 November 1989 that the wall, though it allowed scouring away of
the backfill, would not serve the purpose of protecting the eroded south bank of the river and certain endangered immovable property,
which the learned judge assumed was Lot 666. He found that the
21
wall had not been built along the new bank but some 25 metres to the north. The depressions formed behind the wall were close to the
wall
and remained fairly narrow despite the floods. There was no
indication that the erosion would, in time, reach the river bank. In
the result, the appellant failed to prove that the Town Board had
knowledge or could, by the exercise of reasonable care, have
acquired knowledge, on or before 20 November 1989, "that the wall,
due to its being designed to rest on piles instead of being founded on
bedrock, would not serve the purpose of protecting the right bank of
the river and the adjacent properties."
Conclusions (i), (ii) and (iii) were not attacked by either counsel and
correctly so.
The consequence of these conclusions is that the damage to the backfill
south of the wall was visible before 20 November 1989 and that by then it would
have been clear to even a layman that the only cause of the large subsidence was
22
the fact that part of the wall was built on piles thus making it possible for scour
and erosion to take place below and behind the wall. A probable inference would
be that the designer was at fault. Even if it is accepted that the respondent was not
as a fact aware of the existence of the large substantial subsidence near the middle
of the wall, it could, by the exercise of reasonable care, have acquired knowledge
by not later than 20 November 1989 of the existence of such subsidence and that
the design of the wall by the appellant was defective.
What remains to be evaluated is the conclusion reached by Thirion J that the
respondent could not, by the exercise of reasonable care, have acquired knowledge
on or before 20 November 1989 that the wall, built as it was on piles and allowing scouring away of the backfill, would not serve
the purpose of
protecting
the right
bank of the river and the endangered immovable property, which he described as
Lot 666.
In reaching the said conclusion, Thirion J discussed the meaning of the
words "the facts from which the debt arises" in s 12(3) of the Act. He equated
23
this phrase with "all the facts from which the cause of action arises." The
interpretation given by the learned judge was debated at length by counsel in this
Court I shall assume in favour of the Town Board that the interpretation given by
the learned judge is correct. In my view, such interpretation did not influence the
learned judges's final conclusion, which was essentially one of fact.
The learned judge was also criticised for holding that in order to decide the
special plea, the "facts which are material to the plaintiffs cause of action have to
be ascertained from plaintiffs particulars of claim." I doubt whether that
formulation is correct. That approach would have been in order had the appellant
excepted to the particulars of claim. But here a trial had taken place. At the end
of the trial there was no doubt as to the Town Board's cause of complaint.
However, I say this in passing, because the final conclusion reached by the learned
judge was based on his view of what a reasonable person in the position of the
Town Board should have known or be deemed to know on or before 20 November
1989.
24
The discussion by the learned judge of this final matter took as its point of
departure that the only object of building the wall was to protect
Lot
666. This is
not so.
Lot
666 is a private property, belonging to Mr Bowden. The protection
of this property, along with other beachfront properties, was at best only of
secondary concern to the respondent and never part of the appellant's contractual
obligations. The appellant's contractual obligation was to design a wall which
would protect
Lot
1166 and the end of
Salmon Drive
i.e. the respondent's
properties. If the wall failed in any of these respects, and only then, would it not
have served its purpose in terms of the contract. The evidence, therefore, refutes
the conception that what was to be protected was only
Lot
666, which is further
away from the wall than
Lot
1166. This misconception probably had a direct
effect on the conclusion reached by the learned judge.
In any event, even if one were to accept that the sole object of the wall was
to protect
Lot
666, it is clear that a reasonable person, cognisant of the history of
the matter and the previous damage to
Lot
1166 and the imminent danger to Lots
25
654,655 and 666, should have realised that the defective design would eventually
result in what happened in January 1990, viz that the river would freely flow
underneath the wall and that progressive erosion of the whole of the right bank would occur during a future serious flood. Sec 12(3)
of the Act provides that a
creditor shall be deemed to have the required knowledge "if he could have
acquired it by exercising reasonable care." In my view the requirement
"exercising reasonable care" requires diligence not only in the ascertainment of the
facts underlying the debt, but also in relation to the evaluation and significance of
those facts. This means that the creditor is deemed to have the requisite
knowledge if a reasonable person in his position would have deduced the
identity of the debtor and the facts from which the debt arises.
In the present case, the application of this test to the actual knowledge in
possession of the respondent, convinces me that by 18 November 1989 at the latest
it would have led the reasonable person to realise that the faulty design of the wall
would, during a future flood, result in damage to the whole of the right river bank
26
of the
Umzinto
River
, including Lots 1166 and 666.
In reaching the conclusion that it was, by 20 November 1989, not
reasonably foreseeable that the abovementioned design fault would result in
damage to the Town Boards properties, Thirion J stated:
The wall was a very substantial structure. It was 3,6
metre in height (or depth). It had a broad footing where
it rested on piles. The floods occurred at a time when
the backfill had not yet become compacted. The floods
were of unusual intensity. The defendant itself was, as
at 23 November 1989, still of the view that the wall
was fulfilling its function of protecting the river bank and the defendant was, after all, the expert to whom the
plaintiff was entitled to look for an explanation of what
was happening at the wall. They did try to get in touch with defendant but no one of the partners was available
before 21 November 1989 to advise the plaintiff as to
what was happening. The subsidences which had
occurred up to 20 November 1989 had been in a narrow
band behind the wall. There was no indication that the
erosion would, in time, spread to the river bank.
In all the circumstances I find that the defendant has not
proved that the plaintiff had knowledge or could, by the
exercise of reasonable care, have acquired knowledge
on or before 20 November 1989 that the wall, due to its
27
being designed to rest on piles instead of being founded
on bedrock, would not serve the purpose of protecting
the right bank of the river and the adjacent properties.
The very crux of the appeal is whether these conclusions are supportable.
In my view they are not.
It is true that the wall was a substantial structure, as described by the learned
judge. But the essence of the Town Boards knowledge on or before 18 November
1989 was that the nature of the design fault was clearly visible at the toe end of the
wall. Anyone observing what was taking place there could see the scouring action of the river and sea, and how sand behind the wall
was being sucked out into the
river. Near the middle of the wall another large subsidence had formed. At its
bottom, a large pool of water was clearly visible. A reasonable person, observing
the washing away of the backfill near the toe end of the wall and the subsidence
it has formed there, could not fail to see the similarity between that subsidence and
the one near the middle of the wall. The reasonable person would have realised
28
that the cause of this subsidence was scouring away of the backfill because of the
piling used as foundation and the exposure of the sand between the piles to the fast
flowing river water on the other side of the wall and the piles.
Any reasonable person should have seen that there was nothing to stop
further erosion and the growth of the subsidence until it linked up with the
subsidence at the toe end of the wall. Any reasonable person would have realised
that the subsidence would also spread southwards, ie towards
Lot
1166 and the
end of
Salmon Drive
, eventually causing extensive erosion of these properties.
As indicated earlier, the wall was built either on or very close to
Lot
1166.
Even on the assumption that it was built close to Lot 1166, it should have been
observable that the subsidence, as it was on or before 20 November 1989, had
already reached the said
Lot
, or was very close to it and would eventually spread
much further.
Had the learned judge directed his attention to the correct properties to be
protected, ie Lot 1166 and
Salmon Drive
, and not
Lot
666, which was further
29
inland, he would, in my respectful opinion, have reached the correct conclusion.
It should also be noted that the subsidence near the middle of the wall was
not exactly a " . . . narrow band behind the wall." No viva voce evidence was
offered as to the exact measurements of this subsidence, but it is manifest from the
photographic exhibits, that, even before 20 November 1989, it was more than 3,6
metres deep, of considerable length and quite a few metres wide. Having regard
to the history of the matter and the observable facts, a reasonable person in the
position of the Town Board should have foreseen that the erosion would spread
to
Lot
1166 and even further.
Thirion J also relied on a report dated 23 November 1989 by the appellant to the respondent. In it the appellant averred that the
wall was fulfilling its
function of protecting the river bank. From this the learned judge deduced that the
respondent, relying on the expert advice of its consultants, could also not have
known of the danger of the subsidence spreading towards its properties.
Little, if any, weight can, however, be given to this report. It appears from
30
the report itself that the appellant had last visited the site on 14 September 1989,
ie some five weeks before the report was given. There was no evidence that the
appellant had based its report on the position as it was just prior to 20 November
1989. Furthermore, the appellant sought to justify itself. It was not a case of a
debtor wilfully preventing the creditor from coming to know of the existence of
the debt (s 12(2)). The Town Board disagreed with its contents and was not
misled by it.
On the assumption, in respondent's favour, that the damage, which occurred
and was observable before 20 November 1989, did not as a fact occur on the
respondent's property, ie Lot 1166, but further north on the admiralty reserve land,
the consequence of the interpretation which I have placed on s 12(3) of the Act is
that the prescriptive period nevertheless began to run before there was physical
damage to the respondent's property.
This conclusion is, in my view, consistent with the principle that a debt to
pay damages becomes due when loss occurs as a result of a delict ( Oslo Land Co
31 Lt
d v Union Government
1938 AD 584
at 590; Evins v Shield Insurance Co Ltd
1980(2) SA SA 814 (A) at 838 H to 839 G) or a breach of contract (Swart v Van der
Vyver 1970(1) SA 633 (A) at 643 C-D). In the present case, the respondent did
not claim prospective damage in the sense of damage to its property. It claimed,
as damages, the wasted costs of building the wall. That loss or damage had
already occurred when the Town Board should have been aware (ie acquired
deemed knowledge) that the wall did not serve the purpose for which it was built
and that the costs of building it was wasted.
In the result, the appeal is well-founded. The employment of two counsel
by the appellant for the appeal was, in my view, justified.
The effect of the outcome of the appeal is that the special plea raised by the
appellant is upheld, resulting in the dismissal of the action. In the result, the
appellant is entitled to the costs of the trial before Thirion J, such costs to include
the costs attendant upon the employment of two counsel.
The court a quo, in dismissing the appellant's special plea, made no order
32
as to costs. The respondent cross-appealed against this order, arguing that in the
light of its success, it was entitled to its costs. In view of the outcome of this
appeal, the cross-appeal must also be dismissed.
The following order is made
:
1.
The appeal is allowed with costs and the cross-appeal dismissed with costs,
such costs to include the costs attendant upon the employment of two
counsel.
2.
The order of the court a quo is set aside and replaced by the following
order:
"The special plea is upheld and the plaintiffs claim is dismissed with costs,
such costs to include the costs of two counsel."
I concur
Van Heerden DCJ Zulman JA
(Case no: 8161/92
In the matter between:
DRENNAN MAUD & PARTNERS
Appellant
and
THE TOWN BOARD OF THE TOWNSHIP
OF PENNINGTON
Respondent
Coram
: Van Heerden DCJ, Harms, Olivier, Scott and Zulman JJA
Date of hearin
g: 20 February 1998
Date of delivery
: 27 March 1998
JUDGMENT
2
HARMS JA
The only issue in this appeal is whether the Town Board, by the
relevant date, had knowledge- or deemed knowledge - "of the facts from which the
debt arises"
(s 12(3)
of the
Prescription Act 68 of 1969
). In this regard the learned
trial judge made two pertinent findings of fact. The first was that the Town Board
had deemed knowledge that the design of the wall was defective: It did not permit the reclamation of previously eroded land, because
the river, whenever it flooded
would, through scour action, remove the sand from under and behind the wall. The
second finding was that the appellant had failed to prove that the Town Board had
knowledge or deemed knowledge "that the wall, due to its being designed to rest on
piles instead of being founded on bedrock, would not serve the purpose of
protecting the right bank of the river and the adjacent properties."
In relation to the phrase in
s 12(3)
of the
Prescription Act, namely
"the
facts from which the debt arises", Thirion J held that it means knowledge of all the
3
facts which are material to complete the plaintiffs cause of action, and that in this
context the term "facts" is an elliptical form of "alleged facts". It is apparent that
the learned judge's attention was not drawn to the body of authority that dealt with
the meaning of the word "debt" in s 15(1) of the Act (collected and discussed in two
later cases of this Court, namely Sentrachem Ltd v Prinsloo 1997(2) SA 1 (A) at
15B-16D and Standard Bank of South Africa Ltd v Oneanate Investments (Pty) Ltd
(in liquidation)
1998 1 SA 811
(SCA) at 825B-827F). In short, the word "debt"
does not refer to the "cause of action", but more generally to the "claim". There is
in my view no reason to give the word another meaning in s 12(3). The effect of
this finding of Thirion J on his reasoning was that he sought to determine whether
the appellant had established that the Town Board had knowledge of all the facts
underlying its cause of action as pleaded. Such an onus was not cast upon the
appellant by s 12(3).
In addition, Thirion J held that in order to decide the special plea, the "facts
4
which are material to the plaintiffs cause of action have to be ascertained from
plaintiff's particulars of claim." I cannot agree. That approach would have been in
order had the appellant excepted to the particulars of claim.
In deciding whether a "debt" has become prescribed, one has to
identify the "debt", or, put differently, what the "claim" was in the broad sense of
the meaning of that word. The contract, it was clear from the evidence, required the
appellant to recommend, design and supervise the building of a wall for the
"reinstatement and protection of the right bank" of the river. It was common cause
that reasonable care and skill had to be employed. The breach relied upon was the
failure to exercise such reasonable care and skill in recommending and designing a
wall that would reinstate and protect the right bank of the river. The breach was
committed when the design was made - before May 1989. The Town Board had
knowledge or deemed knowledge of the breach when it realised that the design was
defective in a relevant regard. The breach was not a breach of a divisible but of a
5
single obligation. Therefore, once the Town Board had realised, as found by the
trial judge, that the design of the wall was defective in the one respect, it does not
matter that the Town Board had not appreciated that the design was defective in
another respect (the second finding referred to). Cf Oslo Land Co Ltd v
Union
Government
1938 AD 584
at 590. Reference should also be made to Van Staden
v Fourie
1989 3 SA 200
(A) at 216B-F where it was held that the subsection "stel
... nie die aanvang van verjaring uit totdat die skuldeiser die voile omvang van sy
regte uitgevind het nie."
It follows from this that the learned Judge's first factual finding was
decisive of the case and that I concur with the order proposed by Olivier JA.
LTC HARMS
Judge of Appeal
Scott JA - Agrees