GNH Office Automation CC and Another v Provincial Tender Board Eastern Cape and Another (427/96) [1998] ZASCA 25; 1998 (3) SA 45 (SCA); (26 March 1998)

82 Reportability
Public Procurement

Brief Summary

Tender Law — Suspension of contracts — Appellants were awarded contracts for the supply of typewriters and office furniture by the Eastern Cape Department of Education and Culture, which were later suspended by the Provincial Tender Board citing irregularities — Appellants challenged the suspension, arguing that the Board exceeded its powers as the Act did not confer authority to suspend contracts, only to cancel them — Court held that the Board lacked the power to suspend the contracts as such authority was not expressly provided in the relevant legislation or regulations, and suspension and cancellation are distinct legal concepts.

About SAFLII
Databases
Search
Terms of Use
RSS Feeds
South Africa: Supreme Court of Appeal
SAFLII
>>
Databases
>>
South Africa: Supreme Court of Appeal
>>
1998
>>
[1998] ZASCA 25
|

|

GNH Office Automation CC and Another v Provincial Tender Board Eastern Cape and Another (427/96) [1998] ZASCA 25; 1998 (3) SA 45 (SCA); (26 March 1998)

REPUBLIC OF SOUTH AFRICA
Case No
427/96
IN THE SUPREME COURT OF APPEAL
OF SOUTH AFRICA
In die matter of:
GNH OFFICE AUTOMATION C.C.
First Appellant
NAUGIS INVESTMENTS C.C.
Second Appellant
and
PROVINCIAL TENDER BOARD
EASTERN CAPE
First Respondent
THE PREMIER OF THE EASTERN
CAPE
GOVERNMENT
Second Respondent
CORAM
: Smalberger, Eksteen, Olivier, Streicher JJA et Farlam AJA
DATE OF HEARING
: 27 February 1998
DATE OF DELIVERY
: 26 March 1998
JUDGMENT
/
SMALBERGER JA
:. ..
2
SMALBERGER JA
:
In July 1995 the now defunct Transkei Tender Board was
requested by the Eastern Cape Department of Education and Culture ("the
Department") to invite tenders for the supply of 4000 typewriters and an
equivalent number of typists' desks and chairs. The appellants were the
successful tenderers. The contract for the supply of the typewriters was
awarded to the first appellant and that for the supply of the desks and
chairs to the second appellant. Both appellants are close corporations of
which the sole member is Mr Shanil Singh.
Following on complaints with regard to alleged irregularities
in respect of the award of the tenders, the Department, purporting to act
in terms of sec 4(1) of the Provincial Tender Board Act (Eastern Cape) 2
of 1994 ("the Act"), notified the appellants in writing on 15 November
1995 that the first respondent ("the Board"), the legal successor to the
Transkei Tender Board, had decided, on 13 November 1995, to suspend
3
the approval of their respective tenders. On 20 November 1995 the
appellants' attorneys wrote to the Department rejecting what they
referred to as the "unlawful suspension" of the contracts. The Department
responded on 22 November 1995 confirming its attitude and stating that
no goods delivered in terms of the suspended contracts would be accepted.
On 1 December 1995 the appellants launched an urgent
application in the Transkei Division of the Supreme Court in which they
sought inter alia a rule nisi calling upon the present respondents to show
cause why they "should not be interdicted and restrained from unlawfully purporting to suspend the contracts" entered into
between the appellants
and the Province of the Eastern Cape. The rule nisi was granted in the
terms sought. (The appellants also sought relief against two other
respondents but that issue has been finally determined and no longer
features in the matter before us.)
4
After hearing argument on the return day the judge a quo
(Pickering J) discharged the rule
nis
and made an appropriate order as to
costs. The judgment of the learned judge is reported - see GNH Office
[1996]3 All SA 87 (Tk). The appellants were subsequently granted the
required leave to appeal to this Court.
The respondents were not represented at the hearing of the
appeal. The State Attorney, Bisho, who acts on their behalf, had
previously advised the Registar of this Court that the respondents would
not be filing heads of argument and would abide the decision of the Court.
I find this attitude perplexing and regrettable. As will appear later, this
appeal involves the interpretation of a provision of the Act which has important practical consequences for the Board and the Province
and in
respect of which the parties require clarity and certainty. In the
circumstances one would have expected the respondents, as responsible
5
Provincial bodies, to have been anxious to present their views to the
Court. Indeed, it is arguable that they were under a duty to do so. Their
attitude has precluded this Court from having the benefit of full argument,
thereby depriving it of assistance to which it was entitled in the resolution
of what remained a live issue between the parties. Their conduct could
be construed as an act of discourtesy towards this Court.
The facts and circumstances giving rise to the award of the
tenders to the appellants, and the later (purported) suspension of the
contracts arising therefrom, are fully set out in the judgment of the court
a quo ("the judgment"). It is not necessary to repeat mem. After a
careful analysis of the facts Pickering J concluded that the conduct of an
official of the Department in relation to the award of the contracts to the
appellants was not "impartial, unbiased and fair" (at 106 b). He further
held that "the entire tendering process was tainted and fatally flawed by
the involvement of Singh therein" (at 106d). While there is undoubtedly
6
evidence to support these findings it is unnecessary, for the purposes of
the present appeal, to decide whether they are correct.
Leave to appeal was sought and granted on a number of
grounds. However, because of the view I take of the matter, it is only
necessary to consider one of them. It relates to whether the Board had
the power to suspend the contracts which had been concluded between
the appellants and the Province. This is the primary issue which the
parties seek to have resolved. The essence of the appellants' complaint,
which gave rise to the proceedings in the court a quo, was that the Board,
in purporting to suspend the contracts, exceeded its administrative
powers. While there may have been other remedies available to the
appellants for the enforcement of their contractual rights, no objection was
raised in the court a quo to the way they went about challenging the
Board's decision. Having regard to the peculiar circumstances of the
present matter it was in my view permissible for them to have followed
7
the course they did, as there was a need for an authoritative determination
of the validity of the Board's action (cf Baxter, Administrative Law
(Second Impression 1994) at 359-360).
The power of the Board to terminate a contract entered into
with the Province after tenders have been called for derives from the Act
and the Tender Board Regulations, 1995 (Eastern Cape) ("the Regulations") made in terms of sec 9 of the Act.
Sec 4(l)(a) of the Act provides (to the extent relevant):
"(1) Within the framework of the principles set out in the
guidelines, the Board shall have the sole power to procure supplies
and services for the Province . . . and may for that purpose

(a) on behalf of the Province conclude an agreement, which
shall be in writing, with a person within or outside the
Republic for the furnishing of supplies and services to the
Province . . ."
In terms of sec 4(f) the Board may
"on behalf of the Province, resile from any agreement
concluded under this section and, in an appropriate case,
claim damages".
8
It is apparent from these provisions that the Board acts as a
statutory agent for the Province both in concluding and, where
appropriate, resiling from any agreement falling within the scope of sec
4(l)(a). While sec 4(l)(f) authorises the Board to resile from an
agreement it does not expressly confer a power to suspend such
agreement, nor could such a power be inferred simply from the wording
of the section. To hold otherwise would mean that the notion of
suspension must always be implicit in the concept of "resile" or "cancel",
which can clearly not be so.
The relevant portion of regulation 3(2)(a) provides as
follows:
"3 (2)(a) If the Board is of the opinion that a person

(i) ...
(ii)
(iii) fails or has failed to comply with any of the
conditions of an agreement, or performs or has
performed unsatisfactorily under an agreement; or
9
(iv) who has concluded an agreement referred to in
section 4(l)(a) of the Act, has in respect of the
agreement promised, offered or given a bribe, or has
acted in respect thereof in a fraudulent manner or in
bad faith or in any other improper manner,
the Board may, in addition to any other legal remedies it
may have, restrict the person by resolving that no offer from
the person should be considered during such period as the
Board may stipulate, and, in the case contemplated in
subparagraph (iii) or (iv), cancel any contracts with that
person."
Regulation 3(2)(a) is an elaboration of the powers conferred
upon the Board by sec 4(1) of the Act. It empowers the Board, where it
is of the opinion that the conduct of a person with whom it has contracted
on behalf of the Province falls within the provisions of regulation
3(2)(a)(iii) or (iv), to "cancel any contracts with that person". In doing
so it acts in its capacity as statutory agent. Forming the prescribed
opinion is a necessary pre-requisite to the exercise of the power to cancel.
It is the jurisdictional fact that must exist before there can be a
10
cancellation (South African Defence and Aid Fund and Another v Minister of Justice
1967 (1)SA31 (C)at 34F-H). As it is clear from the
record that the Board had not yet formed any opinion with regard to the
matters referred to in regulation 3(2)(a)(iii) and (iv) when it decided to act
against the appellants, it could not lawfully have cancelled the contracts
with the appellants in terms of the regulation. The Board's "other legal
remedies" (which would encompass both statutory and common law
remedies) did not empower it to suspend the contracts. There exists no express statutory provision entitling it to do so. Nor does
the common
law recognise a power or right to suspend the operation of a contract. At
most a party can temporarily suspend his or her own performance in
appropriate circumstances (Moodley and Another v Moodley and Another
1990 (1) SA 427
(D & CLD) at 431 E). This is not the situation that
applies in the present matter.
It follows that for the Board to have the power to suspend a
11
contract, such power must have been impliedly conferred by regulation
3(2)(a) read with sec 4(l)(f) of the Act. Baxter supra at 404-5 (quoted
in the judgment at 102 h-i) states the position thus:
"Powers may be presumed to have been impliedly conferred
because they constitute a logical or necessary consequence of the powers which have been expressly conferred, because
they are reasonably required in order to exercise the powers
expressly conferred, or because they are ancillary or incidental
to those expressly conferred."
In this regard the court a quo held (at 103 d-e) that "the power to suspend
a contract pending an investigation into the allegations is in my view a
logical and necessary consequence of the powers conferred upon the
Board".
I am in respectful disagreement. I see no logical reason why
the Board's power to cancel a contract after it has formed an opinion
about a certain state of affairs should imply a power to suspend the
contract before such opinion is formed. Cancellation and suspension are
12
distinct juridical concepts with differing consequences. Cancellation
means "To destroy the force, effectiveness, or validity of. To annul or
abrogate". Suspension is "A temporary step, a temporary delay,
interruption or cessation" (Black's Law Dictionary, 5
th
Edition at 187,
1297). The one (suspension) is not a logical component of the other
(cancellation). The power to suspend is not reasonably necessary for the
purposes of cancellation. Nor is it necessary to give effect to the power
to cancel; the effective exercise of the power to cancel is not thwarted by
the denial of a power to suspend. It may be useful or convenient to have
a power to suspend, but that is not the test (Lekhari v Johannesburg City
Council
1956 (1) SA 552
(A) at 567 B). As cancellation and suspension
are unrelated concepts this is not a case, as found by the court a quo (at
103 e), of the greater including the lesser.
Furthermore, any such implied power must inevitably give
rise to uncertainty in regard to matters such as when and under what
13
circumstances the power may be exercised, what considerations are to
govern its exercise and the duration of any suspension. Apart from the attendant uncertainty, suspension could lead to delays in performance,
prejudice to a tenderer and resultant financial loss. These considerations
militate against the existence of an implied power. In my view, if the law maker had intended the Board to have the power to suspend
it would
have expressly conferred such power on the Board and have prescribed
the parameters within which such power could be exercised - as has been
done in regulation 3(2)(a) in respect of the power to cancel.
There is a further consideration. Regulation 3(2)(a) is cast
in very wide terms. It permits of cancellation inter alia where a party
"has performed unsatisfactorily under an agreement" or has acted in an
"improper manner". These terms are sufficiently wide to allow grounds
for cancellation over and above those recognised by the common law.
This can have far-reaching consequences. To the extent that the
14
regulation departs from the common law a restrictive interpretation is
called for. This too would militate against a power to suspend being
implied - for the conferral of an implied power would extend rather than
restrict the operation of regulation 3(2)(a).
A final observation. As previously observed, sec 4 of the
Act, which governs the powers of the Board, confers upon the Board (in subsec (l)(f) ) the power to resile from any agreement. I have
already
expressed the view that tins provision does not impliedly confer a power
to suspend. If that is so, the principal Act, in terms of which the
Regulations were framed, does not authorise the suspension of a contract.
Any empowering provision to that effect in the Regulations, whether
expressly or impliedly conferred, would consequently be ultra vires.
In my view, therefore, the Board acted beyond its powers in
suspending the contracts with the appellants. The suspension was
accordingly a nullity. The appellants sought relief in the form of a final
15
interdict. A more appropriate form of relief, and one which gives formal
effect to this judgment and obviates uncertainty, would be an order setting
aside the suspension of the contracts, even though such an order may not
strictly be necessary.
This judgment does not preclude the Board from exercising
such powers as it might have under the Act and Regulations to cancel the
contracts with the appellants, subject to any valid defences the appellants
may raise.
In the result the following order is made:
(1)
The appeal is allowed, with costs;
(2)
Paragraphs 1 and 2 of the order made by the court a quo,
insofar as they relate to the present respondents, are set
aside, and there is substituted in their stead the following:
"1. The purported suspension by the first respondent of
the contract entered into between the first applicant
16
and the Province of the Eastern Cape in relation to the
supply of 4000 typewriters, and the contract between
second applicant and the Province of the Eastern
Cape in relation to the supply of 4000 typists' desks
and chairs, is set aside;
2. The first and second respondents are ordered, jointly
and severally, the one paying the other to be
absolved, to pay the costs of the applicants."
J W SMALBERGER
EKSTEEN, JA)
OLIVIER, JA) Concur
STREICHER, JA)
FARLAM, AJA)