Bigen Africa Services (Pty) Ltd v Umngeni-Uthukela Water Board and Another (213485/2025) [2026] ZAGPPHC 89 (30 January 2026)

70 Reportability
Administrative Law

Brief Summary

Administrative Law — Judicial Review — Tender validity period — Applicant seeking to set aside tender award on grounds of invalid extension of tender validity period — Court finding that the tender validity period lapsed before award was made, rendering the award unlawful — Urgency of review application justified due to potential implementation of unlawful contract.

IN THE HIGH COURT OF SOUTH AFRICA
(GAUTENG DIVISION, PRETORIA)
(1) REPORTABLE;
(2) OF INTEREST TO OTHER JUDGES: tJO
(3) REVISED~
In the matter between:
30 JANUARY 2026
DATE
BIGEN AFRICA SERVICES (PTY) LTD
and
UMNGENI-UTHUKELA WATER BOARD
ZUTARI (PTY) LTD
Case No~ 3485/2025
Applicant
First Respondent
Second Respondent
Th;s judgment is prepared and authored by the Judge whose name is reflected as
such and is handed down electronically by circulation to the parties I their legal
representat ives by email and by uploading it to the electronic file of this matter on
CaseLines. The date for handing down is deemed to be 30 January 2026.
JUDGMENT

2
RETIEF J
INTRODUCTION
[1] The applicant brings an urgent judicial review in terms of the Promotion of
Administrative Justice Act, 3 of 2000 [PAJA] seeking to set aside a decision of the
first respondent to award a tender to the second respondent [impugned decision] .
The nub of its attack is that the tender period [initial period] was not validly
extended resulting in the decision to award the tender to the second respondent ,
the successful bidder, Zutari (Pty} Ltd, being made in a period when no tender
process existed and thus, unlawful.
[2] According to the applicants papers it raised yet a further ground of attack,
namely its permissibility to correct an arithmetical error post submission of its
tender [correction ground]. However, the correction ground was not advanced in
written argument nor by Counsel in his oral argument. At the hearing, the
applicant's Counsel advanced, without withdrawing the correction ground, that the
pivotal dispute was whether the tender was indeed validly extended. The pivotal
argument was further nailed to the post when the applicant conceded that it too,
was not going to persist with prayer 4 in its notice of motion. Prayer 4, the remedial
relief subsequent upon a favourable finding of the correction ground.
[3] The first respondent in its papers raised a jurisdictional in limine point which
it, at the commencement of the hearing, correctly abandoned. The second
respondent did not oppose the application nor filed papers. Therefore , the
remaining aspects to determine are urgency and the crisp validity extension
ground. Before dealing with this crisp issue this Court deals with the urgency.
URGENCY
[4]The launching of a review application does not suspend the operation of the
award. When a contract has been implemented it becomes difficult for a court to
award an appropriate remedy. It is common cause on the papers that an award
letter has been sent to the second respondent.

3
[5] The consequence of a delay in considering an attack of the lawfulness of a
tender process when an award has already been awarded appears obvious and a
need to move swiftly arises.1Therefore, the delay in setting the matter down,
alternatively launching the application in the normal course becomes apparent.
The applicant argues that if it is to proceed in the normal course, regardless of the
finding of legality of the decision itself, the delay would result in an implemented
contract over an extended period of time. In this way it would not be afforded
substantial redress at a hearing in due course. In other words, if the application is
not heard urgently then, the first respondent would continue to implement an
unlawful agreement which is an untenable situation and, the applicant would not
be afforded the opportunity to bid again in time to come.
[6] Procedurally, the applicant advanced that the first respondent was provided
with adequate time to present their case. The first respondent did not advanced
any argument to the contrary. In consequence, it submitted that there would be no
prejudice to the first respondent if the matter was to heard as urgent.2
[7] The respondent in reply invited the Court to consider the prayers sought by
the applicant to demonstrate that it would be entitled, in due course, to seek
substantial redress. The respondent's argument is highly diluted on the basis that
the tender has already been awarded to the second respondent, the applicant had
already instituted an internal appeal and, the first respondent dismissed the
appeal on the 29 October 2025. In other words, the first respondent was intent,
notwithstanding the applicant's grievance not to suspend the implementation of the
contract which, if implemented may result in a contract being awarded absent a
lawful tender process. This Court is not amenable to delay the adjudication of a
matter concerning the lawfulness of a tender process having regard to all the

matter concerning the lawfulness of a tender process having regard to all the
consequences which may follow including those attracted by the second
respondent. This is stated regardless of the formulation of the prayers.
See Infinite Blue Trading 29 CC t/a Motau Projects v City Power Johannesburg (SOC)
Limited and Others [2019] ZAGPJHC 169 (30 May 2019) at par [27].
Mogalakwena Municipality v Provincial Executive Council, Limpopo and Others 2016
(4) SA 99 (GP) at par [64].

4
[8] This Court considers the matter to be urgent and in dealing with the crisp
issue, considers the salient background facts.
BACKGROUND RELEVANT FACTS
[9]The first respondent issued a Tender RFC No. 2020/011/16 for the
appointment of a professional service provider to review detailed feasibility studies
and undertake the detailed design, contract administration, close-out stages of the
Upper Umkhomazi Water Project for Phase 1 (156 ML reinforced concrete
reservoir and ancillary works). The tender was issued on the 26 February 2025,
with the compulsory briefing cession on the 6 March 2025 and a closing date of
the 8 May 2025 at 12h00 [the tender]. The closing date of the tender was the 8
May 2025 and the tender bid validity period was for a period of 120 days from the
closing date, expiring on the 5 September 2025.
[1 O] The applicant submitted a tender by the closing date. A day
thereafter , on the 9 May 2025, the applicant notified the first respondent of an
arithmetical error it identified in its bid document. The error occurred in that its
pricing schedule in that the total stated therein was R1 ,214,476,290.40 however,
the correct total should have been R647, 114,759.98. The applicant requested that
the error be corrected, providing a detailed breakdown and an explanation for this
error in its correspondence.
[11] The first respondent decision was not to allow the correction, stating
in its regret letter dated the 15 October 2025 that: "The committee resolved that
the tender offer of R1,214,476,290.40 shall govern and you cannot be allowed to
change your tender offer after the publication of the tender results".
[12] On the 4 September 2025 (one day before the lapsing of the tender
validity period), the first respondent addressed an email to all the participating
tenderers requesting their consent to extend the tender validity period to the 31
November 2025. The email was addressed for attention to all bidders, it was dated

November 2025. The email was addressed for attention to all bidders, it was dated
the 4 September 2025 and signed by the Senior Procurement Manager:
Acquisition and Support, Mr S.Makhura. The email correspondence was headed

5
"Urgent Message: Request for Extension of Tender Validity'. The relevant
content of the request letter was the following:
"1.
2. The evaluation and the adjudication process for the abovementioned
bid has been slightly delayed owing to various internal procedural
constraints and challenges. It has therefore become necessary for
the validity of the bids to be extended for a period up to and including
31 November 2025 in terms of the same conditions embodied in your
initial tender.
3. It is in this regard that you are hereby requested to indicate if your
organisation still has an interest in this bid by giving consent ( own
emphasis) to extend the validity of your price proposal. Kindly
indicate your response below by close of business (own emphasis)
the 5
th
of September 2025.
Is prepared to extend the validity of the bid and (own
emphasis) will still be interested in bidding for the service.
Is not prepared to extend the validity of the bid and (own
emphasis) is no longer interested in bidding for the service.
Other
Represented by: Signature: _____ _
FULL NAME"
( extension letter]
[13] The extension letter was drafted in such a way that it called upon the
tenderers to inform the first respondent whether it consented to the extension of
the period AND whether it accepted the consequences flowing from the elected
consent. In other words, if they were still interested in the being part of the bid
process. Such response was to be provided by an election tick box system. Each
organisation was requested to make an election by ticking a box. The proposed

6
elections were whether they were prepared to extend the validity bid and willing to
remain in the bidding process or if they were not prepared to extend the validity
period and were no longer interested in remaining in the process or they could
elect "other". "other' ostensibly then could be to consent to the extension of the
period but elect not to remain in the bidding process or not to consent to the
extension period but still elect to remain in the process. Either way "other" created
further options other than what was set out.
[14] The extension letter included a place for the signature and full name
of the organisation under the election boxes. In this way a tenderer could make its
election as elicited by ticking a box, to sign and date and return the extension letter
to the first respondent.
[15] Five (5) of the tenderers , including the applicant made their election
and returned the duly completed extension letter back to the first respondent in
time. Two tenderers, Gibb (Pty) Ltd and Royal Haskoning DHV (Pty) Ltd failed to
respond at all [non-responsive tenderers].
[16] The first respondent proceeded with the evaluation and after the Bid
Evaluation and Adjudication Committees' recommendations, and in October 2025,
a letter of award was addressed to the second respondent.
[17] The applicant lodged an internal appeal on the 24 October 2025,
arguing that the process was irregular due to the refusal to correct its arithmetic
error and the lapse of the validity period. The first respondent dismissed the
appeal on the 29 October 2025, maintaining its position on both points.
[18] Procedurally, the applicant launched its urgent application on the 27
November 2025 in terms of rule 53, calling upon the first respondent to deliver the
record pertaining to its decision by the 28 November 2025. It is common cause
that the record was duly delivered by the first respondent and that the applicant
supplemented its papers by filing it electronically with the Registrar on the 12

supplemented its papers by filing it electronically with the Registrar on the 12
December 2025.

7
EXTRACT FROM THE FIRST RESPONDENT'S SUPPLY CHAIN
MANAGEMENT POLICY (SCM POLICY]
[19] According to the record filed by the first respondent, the portion
dealing with the extension of the validity period appears to be blank. A point taken
by the applicant during argument, contending that when it filed its supplementary
affidavit, it was none the wiser as to what the SCM policy factually stated on this
point. The first respondent in its answering affidavit did not correctly address nor
assist the applicant by referring to and/or attaching a copy of the correct page to
complete the record. It merely responded with a bare denial.
[20] However, at the hearing, the Counsel for the first respondent
confirmed that the correct policy which applied was that portion which was
attached by the applicant to its supplementary affidavit referred to as "FA 1" at
paragraph 13.4.11 thereof.
[21] Paragraph 13.4.11 reads as follows:
"13.4. 11 Validity Period of Bids
(1) The validity period must be in calendar days and must be
reasonable considering the lead time for the award.
(2) This period must be sufficient to enable UW to complete
their valuation of bids, review the recommendation and
award the contract.
(3) An extension of bid validity must be requested in writing
from all bidders before the expiration date.
(4) The extension must be for the minimum period required to
complete the evaluation, to obtain the necessary
approvals and to award the contract.
(5) Motivation for the extension of the validity period must be
approved as per the SCM Manager."

8
APPLICANT'S ARGUMENT
[22] The applicant contends that the tender validity period serves two
purposes. The first purpose is that it represents the period during which a tenderer
is required to keep its tender offer open and, the second purpose is that it is the
period within which the organ of State should finalise the tender process itself. In
other words, when the first respondent should make a final award. The applicant in
advancing its argument relied on both the Takubiza Trading & Projects CC v
Ekurhuleni3 [Takubiza a quo] and as confirmed by the Supreme Court of Appeal
[SCA].
4
The SCA in the Takubiza matter on appeal stated at paragraph [13] that:
"[13] Fourth, as was held by the High Court, the validity period is indeed
one of the fundamental 'rules of the game', being the period within
which the process should be finalised. To extend the tender validity
period, the consent of all the participants to the tender process is
required (own emphasis). Unless there is a timeous request and
favourable response from all the tenderers (own emphasis) prior to
the expiry of the tender, the tender comes to an end."
[23] The applicant by advancing the findings in the Takubiza matter in the
SCA, by relying on the common cause fact that not all the participants responded
signalling their consent and, by advancing that the first respondent's SCM policy
did not provided for an exclusionary stipulation argued that the position in
Takubiza matter as confirmed in the SCA applied to the facts in this application.
[24] In consequence, it argued that the tender period came to an end on
the 5 September 2025. The recommendation to award and the letter of award to
the second respondent occurred after the validity period. Therefore, during a
period when no lawful tender process existed.
Unreported case number 14382/2021 at par [63] and [64].
Ekurhuleni Metropolitan Municipality v Takubiza Trading & Projects CC and Others
2023 (1) SA 44 (SCA) at par [13].

9
FIRST RESPONDENT'S ARGUMENT
[25] The first respondent argues that it complied with its SCM policy in
that it, on the 4 September 2025, requested all tenderers to extend the validity
period to the 31 November 2025. It argues that the two (2) non-responsive
tenderers did not bring an end to the tender process but an end to those non­
responsive tenderers' bids. For this proposition, the first respondent's Counsel
invited the Court to consider the matter of Aventino Ecotroopers Joint Venture and
Others v MEC, Department of Roads and Infrastructure and Transport, Gautenq.
and Others [Aventino matter].5
[26] In the Aventino matter the SCA considered the wording of the
appellant's own SCM policy which stated that "[B]idders may either accept or
reject the extended validity period and those who do not wish to extend the validity
period would be regarded as non-responsive and would be excluded from further
assessment." [exclusionary stipulation].
[27] This argument was advanced and persisted with notwithstanding the
first respondent Counsel's concession that the wording in the SCM policy in the
Aventino is distinguishable from the wording in the first respondent's SCM policy.
[28] In an attempt to possibly overcome a perceived hurdle or to extend
the reach of its defence on the papers the first respondent's Counsel contended
that if a tenderer did not respond to the extension letter then an inference could be
drawn that it, by its omission, could be regarded as non-responsive and excluded
from the process. No authority other than the Aventino matter was provided for this
proposition nor was this Court taken to the papers to demonstrate that this basis
was underscored by the evidence. The outcome of this proposition will be
expanded in the discussion below.
DISCUSSION
(1233/2023) [2025] ZASCA 32.

10
[29] Bearing the content of the SCM policy in mind, namely without an
exclusionary stipulation clause, one must accept that the SPM, Mr MS Makhura
who was authorised to draft the urgent message of request for extension of tender
of the 4 September 2025 on behalf of the first respondent did so, with the
knowledge of its content, scope and of the time constraints it placed on all the
tenderers who received it.
[30] In drafting the letter it appears that the SPM wished to inform the
tenderers of an urgent need to extend the validity period, to gauge whether they
consented to it and, to ascertain from each tenderer whether they accepted the
consequences of the consent. In other words did they want to remain in the
process. This is why the enquiry is not only confined to the two enquiries but
includes a further open-ended option.
[31] Without expanding on the obvious fact that the exclusion letter is not
the first respondent's SCM policy and therefore does not replace nor amend the
provisions of the first respondent's SCM policy, the exclusion letter itself too, does
not support the first respondent's reliance on the Aventino matter.
[32] According to the exclusion letter a tenderer would only tick a box if it
also agreed to the outcome attached to its decision to consent or not. Failing
which it could elect "other' and expand in the place provided. Therefore , no
automatic exclusion existed nor could it be inferred. The first respondent's reliance
on the Aventino matter as it speaks to its own SCM policy and as advanced in
respect of the exclusion letter must fail as too, the unsupported argument
advanced during argument. There is no automatic opt-out.
[33] In light thereof and on the facts the reasoning of the SCA in the
Takubiza matter as advanced stands. Section 217 of the Constitution through
which the facts of this matter must be viewed also weighs in favour of a fair
procurement system for all ?(seven) tenderers. No timeous request nor a

procurement system for all ?(seven) tenderers. No timeous request nor a
favourable response, or simply a response from all the tenderers prior to the expiry
of the tender is demonstrated. This Court finds that the tender process was not
validly extended and that it came to an end on the 5 September 2025.

11
[34] The Court also notes that the second respondent did not enter the
arena, notwithstanding prayer 3 in which the applicant seeks that the agreement
between the first and second respondent as a direct result of the declarator relief
in prayer 2, is to be set aside.
[35) There is no reason why costs should not follow the result and none
was argued.
The following order:
1. The application be heard as an urgent application in terms of the
provisions of 6(12) of the Uniform Rules of Court and that the
necessary condonation be granted to the Applicant in respect of the
non-compliance with the prescribed time limits, forms, and service.
2. The decision of the First Respondent to award Tender RFC No.
2020/011/16 for the appointment of a PSP to review the detailed
feasibility studies and undertake the detailed design, contract
administration, and close-out stages of the Upper Umkhomazi Water
Project Phase 1: 156ML reinforced concrete reservoir and ancillary
works [the tender] to the Second Respondent be declared
unconstitutional, is reviewed and is hereby set aside.
3. The agreement concluded between the First and Second
Respondent pursuant to the tender award is set aside.
4. The First Respondent is ordered to pay the Applicant's costs, taxed
scale C.

12
Appearances:
For the Applicant:
Instructed by attorneys:
For the First Respondent
Instructed by attorneys:
Date of argument:
Date of judgment:
APJ Els SC
Judge of the High Court
Gauteng Division
Cell: 083 455 6579
Email: apjels@rsabar.com
JJ Jacobs Incorporated
Tel: (066) 266 4051
Email: hannes@jjjacobsinc.co.za
Ref: Jacobs/NNVIG002
BL Makola SC
Cell: 082 498 6227
Email: benny.makola@group621.co .. za
Xaba Attorneys
C/O TF Matlakala Incorporated
Email: mail@xabainc.com
Ref: D. Xaba
28 January 2026
30 January 2026