Minister of Public Works and Land Affairs v Group Five Building Ltd. (681/94) [1996] ZASCA 93 (17 September 1996)

80 Reportability
Contract Law

Brief Summary

Contract — Building contract — Interpretation of Bills of Quantities — Dispute regarding roofing method — Appellant (Minister) and respondent (Group Five) entered into a contract for construction of an archive building, specifying roofing requirements in the Bills of Quantities — Respondent claimed method A for tile installation was prescribed, while appellant contended method B was appropriate due to local conditions — Court a quo found in favor of respondent, interpreting the contract narrowly — Appeal court held that ambiguity in the Bills of Quantities could be resolved by considering the entire contract, including drawings and other specifications, which indicated method B was intended — Appeal upheld.

Comprehensive Summary

Summary of Judgment


1. Introduction


The proceedings were an appeal to the Supreme Court of South Africa (Appellate Division) concerning the interpretation of a building contract and, in particular, the proper construction of an item in the Bills of Quantities dealing with the fixing of roof tiles.


The appellant was the Minister of Public Works and Land Affairs and the respondent was Group Five Building Limited. The respondent (as plaintiff in the court a quo) instituted action in the Cape Provincial Division seeking a declaratory order that the contract prescribed one method of fixing roof tiles (described in the manufacturer’s brochure as “method A”). The appellant opposed the claim and delivered a counterclaim for a declarator that the contract prescribed the alternative “method B”. Van Niekerk J found in favour of the respondent (method A). The appellant obtained leave to appeal pursuant to a petition to the Chief Justice and appealed against that decision.


The subject-matter of the dispute was the contractual meaning of the phrase requiring installation “alles streng ooreenkomstig die vervaardiger se voorskrifte” in a Bills of Quantities item for roof tiling, read with the relevant manufacturer’s brochure and the contract drawings, and whether that contractual scheme selected method A (normal headlap) or method B (greater headlap) for the roof tiles.


2. Material Facts


The parties concluded a building contract for the erection of an archive building in Cape Town on the site of the old Roeland Street gaol. As is customary, the contract comprised multiple documents, including the Conditions of Contract, the Bills of Quantities, and the Drawings. Clause 6(1) of the Conditions of Contract provided that all material and work shall be as described on the drawings and in the Bills of Quantities.


The dispute centred on a roofing item in the Bills of Quantities. Under the heading for roof coverings, the Bills prescribed the use of “‘Cordova’ of ander goedgekeurde groen geglasuurde klei dakteëls … soos vervaardig deur ‘Corobrick (Edms) Bpk.’”. The critical provision was item 157A, which specified clay roof tiles to a flat pitch, laid and fixed as described, “alles streng ooreenkomstig die vervaardiger se voorskrifte”, for an area of 4312 square metres.


It was common cause that the only information about tile size and overlap referred to by the phrase “vervaardiger se voorskrifte” was contained in a Corobrik brochure. The brochure gave the tile size as 406 by 203 mm, and set out two alternative methods of fixing tiles. Method A was described as appropriate under “normal conditions”, with a headlap of 102 mm. Method B was suggested for tiles “laid on a very low pitched roof and where extreme windy conditions prevail”, with a headlap of 203 mm. The greater headlap in method B would require more tiles for the same roof area than method A.


It was accepted that item 157A itself did not explicitly stipulate the overlap. The item referred to a “plat helling”, and the evidence indicated that this expression functioned to convey that the roof would not be steep and would not be difficult to work on, but it did not itself resolve which method (A or B) applied. On the evidence, it was also common cause that Roeland Street, Cape Town, could be regarded as a locality “where extreme windy conditions prevail”.


A further material feature relied on by the court was that the method of fixing tiles affects other building work, particularly carpentry, because tiles are fixed to wooden battens and batten spacing depends on the chosen method. The brochure stated that batten spacing was generally 305 mm centres for method A and generally 203 mm centres for method B.


The court relied on the fact that the Drawings formed part of the contract and were intended to be read with the Bills of Quantities. The tender documentation informed tenderers that the plans issued with the tender documents were not a complete set but served as a guide to indicate the scope of work and enable tenderers to familiarise themselves with the nature and extent of the works and how they were to be executed. Among the drawings were a section drawing and a roof plan (“dakplan”), both describing the method of fixing tiles in terms closely corresponding to item 157A, but additionally stipulating that tiles were to be fixed on battens at 203 mm centres. The court accepted that method A would be physically impossible where battens were spaced at 203 mm centres, and that this spacing aligned with method B.


3. Legal Issues


The central legal question was one of contractual interpretation, namely whether, on a proper construction of the contract documents (including the Bills of Quantities, the manufacturer’s brochure, and the Drawings), method A or method B was contractually prescribed for the fixing of the Cordova roof tiles under item 157A.


A further interpretive question concerned the contractual effect of the Standard System of Measuring Builders’ Work incorporated by clause B1.6 of the Bills of Quantities, and whether that incorporation entitled a tenderer to interpret the roofing requirements by confining attention to the roofing section of the Bills of Quantities alone, rather than considering other contract documents.


The dispute was therefore primarily about the application of interpretive legal principles to the contractual text and incorporated documents, rather than a pure factual dispute. Where factual matters featured (such as the windy conditions in Cape Town and the functional significance of batten spacing), they were treated as contextual facts relevant to interpretation, with certain aspects being common cause.


4. Court’s Reasoning


The court approached the matter by first identifying that the brochure, strictly speaking, did not contain binding “voorskrifte” in the sense of mandatory instructions, but was instead an informative document suggesting how the tiles might be used under particular circumstances. The brochure contemplated that the user would decide which method was appropriate, and in the present contract it was the architect’s duty to stipulate how the tiles were to be laid. Item 157A, apart from its reference to the manufacturer’s instructions, did not stipulate the overlap required.


The respondent’s argument (accepted in the court a quo) was that the interpretation exercise should be confined to item 157A read with the brochure, bolstered by the Standard System provisions requiring clear, complete descriptions in Bills of Quantities and discouraging the combination of trades within the same item. From this, the respondent contended that method A should be inferred as the “normal” method, and that if method B had been intended it should have been expressly stated.


The appellate court accepted that the parties had specifically incorporated the Standard System and that the Bills of Quantities were intended to be read in its light. However, it rejected the proposition that the Standard System could cure ambiguity. It reasoned that if an item in the Bills of Quantities is ambiguous, the Standard System cannot render it unambiguous; rather, the ambiguity indicates that the drafter did not meet the prescribed standard, and the ambiguity must be resolved by applying ordinary principles of contractual interpretation.


When item 157A and the brochure were considered on their own, the court did not accept that method A necessarily followed merely because it was described as applying under “normal conditions”. The brochure’s alternative method B applied where a very low-pitched roof and extreme windy conditions prevail. The court noted that item 157A referred to a “plat helling”, and while that phrase did not decisively indicate which method was intended, there was at least no indication that the roof was anything other than “a very low pitched roof”. Additionally, the evidence established that Cape Town could be regarded as extremely windy. In that context, the court concluded there was no sufficient reason—based only on item 157A and the brochure—to assume that method A rather than method B had been intended. The contractual text, read with the brochure, therefore remained ambiguous on the selection between methods A and B.


The court then considered whether the ambiguity could be resolved by reference to other contractual provisions, emphasising that the method of fixing tiles has consequences for carpentry because batten spacing depends on the headlap method. While the appellant relied on the carpentry section of the Bills of Quantities specifying battens at 203 mm centres (consistent with method B), the court did not find it necessary to decide the respondent’s argument that, due to the Standard System, one trade’s item should not be read with another trade’s items.


Instead, the court placed decisive weight on the fact that the contract expressly contemplated that the Drawings were to be read together with the Bills of Quantities. Clause 6(1) of the Conditions of Contract expressly referred to both drawings and Bills of Quantities as describing material and work. The tender documentation indicated that the plans served as a guide to the scope and mode of execution of the works, reinforcing their interpretive relevance. The court reasoned that it was implausible that a roofing specialist or tenderer would tender without determining from the drawings how the roof was to be constructed, especially given that the drawings formed part of the contract.


On the drawings, the description of the method of fixing the tiles corresponded closely with item 157A but additionally stipulated fixing on battens at 203 mm centres, which matched method B. The court found that method A could not physically be applied where battens are spaced at 203 mm centres. Accordingly, by reading the ambiguous item 157A and brochure together with the drawings (as part of the contract), the ambiguity was resolved in favour of method B.


The court addressed, and rejected as determinative, the respondent’s attempt to characterise the matter as a mere “discrepancy” to be dealt with under clause 6(2) of the Conditions of Contract (requiring the contractor to seek a decision from the owner’s representative upon detecting discrepancies). The court reasoned that since attempts to resolve the dispute had failed and the matter was before the courts under clause 27(2), the interpretive task was for the court. Applying ordinary interpretive principles, the court stated that a contract should, where possible, be interpreted so as to avoid discrepancies, and that this could be achieved by reading the contract documents together.


5. Outcome and Relief


The appeal succeeded. The order of the court a quo was set aside and replaced with an order declaring that, on a proper construction of item 157A of “Lys no 8” of the Bills of Quantities forming part of Contract No. 860109, the applicable method of fixing roof tiles was method B, described as the “B” method for a 203 mm headlap in annexure PPC3 to the plaintiff’s particulars of claim.


The respondent’s claim for a declarator in favour of method A (Claim A) was dismissed. The respondent (plaintiff in the action) was ordered to pay the costs of the action, including the costs of two counsel. The appeal costs were likewise awarded against the respondent, including the costs of two counsel.


Cases Cited


No external cases were cited in the judgment.


Legislation Cited


No legislation was cited in the judgment.


Rules of Court Cited


No rules of court were cited in the judgment.


Held


The Appellate Division held that item 157A of the Bills of Quantities, read with the manufacturer’s brochure alone, did not unambiguously select method A and remained ambiguous as between methods A and B. The incorporated Standard System of Measuring Builders’ Work could not remove that ambiguity.


Reading the contract as a whole, and in particular reading item 157A and the brochure together with the contract drawings (which formed part of the contract and stipulated batten spacing at 203 mm centres), the court held that the contract required method B (203 mm headlap). The court therefore granted a declaratory order in favour of method B, dismissed the respondent’s claim, and ordered the respondent to pay costs including the costs of two counsel.


LEGAL PRINCIPLES


A contractual incorporation of a measurement or drafting standard (here, the Standard System of Measuring Builders’ Work) means the relevant document (the Bills of Quantities) should be read in the light of that standard, but such a standard does not convert an ambiguous contractual provision into an unambiguous one. Where ambiguity remains, it must be resolved by applying ordinary principles of contractual interpretation.


In interpreting a contract consisting of multiple interrelated documents (such as conditions of contract, bills of quantities, and drawings), the interpretive exercise requires that the contract be read as a whole. Where possible, a court should prefer an interpretation that avoids discrepancies between contractual documents.


Where a contractual provision is ambiguous and other incorporated contract documents supply clarifying detail (such as drawings specifying construction requirements), those documents may properly be used to resolve the ambiguity, particularly where the contract contemplates that those documents are to be read together to describe the work to be performed.

About SAFLII
Databases
Search
Terms of Use
RSS Feeds
South Africa: Supreme Court of Appeal
SAFLII
>>
Databases
>>
South Africa: Supreme Court of Appeal
>>
1996
>>
[1996] ZASCA 93
|

|

Minister of Public Works and Land Affairs v Group Five Building Ltd. (681/94) [1996] ZASCA 93 (17 September 1996)

Case No 681/94 IN THE SUPREME COURT OF SOUTH AFRICA (APPELLATE DIVISION)
In the matter between:
THE MINISTER OF PUBLIC WORKS AND
LAND AFFAIRS
Appellant
and
GROUP FIVE BUILDING LIMITED
Respondent
CORAM: E M GROSSKOPF,EKSTEEN, HARMS, OLIVIER, JJA etZULMAN,AJA
HEARD: 22 AUGUST 1996
DELIVERD: 17 SEPTEMBER 1996
JUDGMENT E M GROSSKOPF. JA
2 This appeal concerns the interpretation of a building contract between
the parties for the erection by the respondent of the archive building in
Cape Town on the site of the old Roeland Street gaol. As is usual the
contract consists of a number of documents including the Conditions of
Contract, the Bills of Quantities and the Drawings. In terms of clause 6 (1)
of the Conditions of Contract,
"[all] material and work shall be as described on the Drawings and in the .... Bills of Quantities."
The dispute arises from one item in the Bills of Quantities, relating
to the roofing of the building. Under the heading "Dakbedekkings" the Bills
of Quantities prescribe the use of "'Cordova' of ander goedgekeurde groen
geglasuurde klei dakte
ls ... soos vervaardig deur 'Corobrick (Edms) Bpk.'"
Then follows the disputed provision, viz., item 157A. It reads as follows,
with the critical words underlined:
3
"Klei dakte
ls tot plat helling op dakhoutwerk gel
, en bevestig soos beskryf
alles streng ooreenkomstig die vervaardiger se voorskrifte
".
An area of 4312 square metres is specified for this item. The Bills of
Quantities do not indicate how many tiles would be required to cover this
area. The number of tiles could be determined from the area given, the size
of the tiles and the extent of their overlap. The sole information regarding
the size of the tiles and their overlap was to be found in the "vervaardiger
se voorskrifte" mentioned in the Item. These "voorskrifte", it was common
cause, were embodied in a brochure issued by Corobrik. According to this
brochure the size of the Cordova tiles was 406 by 203 mm. However, two
ways of fixing the tiles were set out in the brochure. The one (described as
method A) was for tiles laid under normal conditions. Here a 102 mm
headlap was considered adequate. The second (method B) was for tiles "laid
on a very low pitched roof and where extreme windy conditions prevail".
4 Here a headlap of 203 mm was suggested. By requiring a greater overlap,
method B would use more tiles than method A in covering the same area.
This forms the crux of the dispute between the parties. The respondent sued
in the Cape Provincial Division for an order declaring that method A was
prescribed by the contract. The appellant opposed the claim, and
counterclaimed for an order declaring that method B was the chosen one.
The court a quo (Van Niekerk J) held in favour of the respondent. With
leave granted pursuant to a petition to the Chief Justice the appellant now
appeals against this judgment.
Strictly speaking the brochure does not contain any "voorskrifte"
(directions or instructions). It is more in the nature of an informative
document, giving details of the product and suggesting how it is to be used
in particular circumstances. Its contemplation clearly is that the person
5 using the tiles would have to decide which of the suggested methods would
be appropriate. In the present case it was the architect's duty to stipulate
how the tiles were to be laid. Save for the reference to the manufacturer's
instructions, item 157A of the Bills of Quantities does not reflect any
stipulation as to the overlap required by the contract. I shall consider later
whether any of the other contractual provisions casts light on this matter.
The respondent's argument, which was accepted by the court a quo, was essentially that the court should look no further than item
157A read with the brochure, and that this limited perspective provides an answer to the problem. This argument was developed as
follows.
Clause B1.6 of the Bills of Quantities provides;
"Hierdie Hoeveelheidslyste is opgestel ooreenkomstig die jongste Standaardstelsel vir die Opname van Bouerswerk uitgereik deur
die Vereniging van Suid-Afrikaanse Bourekenaars. Waar van hierdie stelsel afgewyk is, sal dit duidelik aangedui wees en voorrang
6 geniet."
The Standard System of Measuring Builders' Work, to which
reference is made in the above clause, and to which I shall refer as the
Standard System, provides inter alia as follows:
"3
Scope of bills of quantities
The bills of quantities shall set out all the work to be done in sufficient detail to give a clear idea of the character and cost.
Everything of consequence in respect of costs, shown on the drawings or described in the specifications, shall be embodied and nothing
shall be left to assumption. The bills of quantities shall be as simple as possible provided that they fully describe the materials
and workmanship and accurately represent the work to be executed.
4
Descriptions
Descriptions shall be clear and complete, leaving no reasonable doubt
as to their intent and meaning and containing all the essential
information necessary for pricing
5
Separation of items
Items shall be separated in accordance with the detailed instructions laid down in the various trades, based on the following rules:
a) The recognised and customary trades shall be separated and a combination of such trades in the same item shall be avoided ...."
7 Item 157A of the Bills of Quantities falls within the section dealing
with roofing. By reason of the above provisions of the Standard System a
tenderer is entitled to assume, so it is contended, that every provision
relating to roofing is contained clearly and unambiguously in that section.
He could accordingly not be expected to have regard to any other part of
the contract to determine what the roofing requirements are. And, for
present purposes, the only relevant part of the roofing section is contained
in Item 157A read with the brochure. If the enquiry is limited to these
provisions, the argument concluded, the only reasonable inference is that
method A was prescribed, since it is the normal method to be employed -
if the exceptional method B was intended, the person drawing the Bills of
Quantities would, pursuant to the Standard System, have expressly so
provided.
8 This argument rests heavily on the Standard System, and there was
some debate before us as to its legal effect. The parties specifically
incorporated it in their contract and must, in my view, have intended that
the Bills of Quantities should be read in the light of the Standard System.
It is difficult to generalise on how such an approach would affect the
process of interpretation. One thing is clear, however. If an item in Bills of
Quantities is ambiguous the Standard System cannot render it unambiguous.
In such a case one can only infer that the quantity surveyor who drew the
Bills did not achieve the high standards prescribed by the Standard System.
And the ambiguity would, in my view, have to be resolved by applying
ordinary contractual principles.
I turn now to the interpretation of item 157A read with the brochure.
As already stated, the brochure suggests two alternative methods of fixing
9
the tiles. The one is said to be appropriate "under normal conditions". The
other is suggested for "a very low pitched roof and where extreme windy conditions prevail". Does this mean, as the respondent
contended, that, in the absence of any indication to the contrary, the normal method, i e method A, should be employed? In my view
this does not follow. Item 157A itself mentions that the tiles are to be fixed on a "plat helling". The evidence discloses
that this expression served only to indicate to a tenderer that work on the roof would not be rendered difficult by a steep pitch,
and I accept that it casts no real light on which method would be appropriate. Nevertheless, putting it at its lowest, there is no
indication in the Item that the roof is anything other than "a very low pitched roof. And it was common cause on the evidence
that Roeland Street, Cape Town, may well be considered a locality "where extreme windy conditions prevail". What
10 reason therefore is there to assume, by looking only at the Item and the
brochure, that the architect who drew the plans and the quantity surveyor
who drew the Bills intended method A to be employed rather than method
B?
The appellant's contention is that this ambiguity may be resolved by
having regard to other provisions of the contract. In this regard it is
important to note that the method of fixing the tiles influences other aspects
of the building work, and in particular the carpentry. The tiles are fixed to
wooden battens, and the distance between the battens depends on the
method to be used in laying the tiles. Thus the brochure stipulates that, for
method A, the battens are generally to be spaced at 305 mm centres,
whereas for method B the spacing was to be, generally, at 203 mm centres.
The section of the Bills of Quantities dealing with the trade of carpenters
11
and joiners lays down that the battens are to be spaced at 203 mm, which is a clear indication that method B is to be applied. But,
the respondent argues, by reason of the Standard System, the item dealing with work to be performed by the roofer must be read by
itself and not in conjunction with items relating to other "recognised and customary trades" (clause 5 of the Standard
System) such as carpenters and joiners. It is not necessary to deal with this argument for reasons which follow.
In the introduction to the Bills of Quantities the tenderer is informed that the building plans issued together with the tender documents
do not comprise a complete set "maar dien slegs om 'n gids vir tenderdoeleindes te wees, om die omvang van die werk aan te dui
en om die Tenderaar in staat te stel om bekend te raak met die aard en omvang van die Werke en die wyse waarop dit uitgevoer word."
Quite clearly these plans are intended
12
to be read together with the Bills of Quantities. See also the specific
reference to "the Drawings" in clause 6(1) of the conditions of Contract, quoted above. I cannot imagine that a roofing
specialist or other tenderer would make a tender before ascertaining from the plans exactly how the roof is to be constructed. Among
these drawings (which, it must be emphasized, form a part of the contract) is one showing a section of the building and another which
is described as a "dakplan". Both these plans contain a description of the method to be employed in fixing the tiles. This
description corresponds closely with Item 157A, except that it stipulates also that the tiles are to be fixed on battens at 203 mm
centres. This is the distance prescribed for Method B. In fact it would be physically impossible to apply Method A where battens
are spaced in this way.
The respondent's counsel brushed aside the references to the batten
13
spaces in the drawings and in other items of the Bills of Quantities as
merely pointing to a discrepancy between item 157A and the information contained in these documents. Such a discrepancy, it was contended,
was provided for in the contractual documents. Clause 6(2) of the Conditions of Contract lays down that, if a contractor were to
detect a difference or discrepancy between or in the drawings, specification and/or bills of quantities, it shall be his duty to
seek in writing a decision of the owner's representative on the true intent and meaning of the contract. I do not think this provision
is really relevant. Obviously an apparent difference or discrepancy in the documents must be resolved in some way, and the contract
makes provision for this. It is common cause, however, that all attempts to resolve the dispute between the parties have failed and
that, pursuant to clause 27(2) of the Conditions of Contract, the matter has been
14 placed before the courts. We now have to interpret the contract. In
accordance with ordinary principles of interpretation, a court will, where
possible, interpret a contract so as to avoid discrepancies. This can be done
in the present case by reading the ambiguous provisions of item 157A and
the brochure with the descriptions set out on the drawings. If this is done,
it seems clear that the contract between the parties required method B to be
applied.
In the result the appeal succeeds with costs including the costs of two counsel. The order of the court a quo is set aside and the
following substituted:
1. An order is made declaring that on a proper construction of item 157A of "Lys no 8" of the Bills of Quantities, being
part of Contract no. 860109, the applicable method of fixing roof
15
tiles was that described as the "B" method of fixing tiles for a
203 mm headlap in annexure PPC3 to the plaintiffs particulars of claim.
2.
Claim A of the plaintiffs particulars of claim is dismissed.
3.
The plaintiff is ordered to pay the costs of this action, which are to include the costs of two counsel.
E M GROSSKOPF, JA
EKSTEEN, JA
HARMS, JA OLIVIER, JA
ZULMAN, AJA Concur