Sun Packaging (Pty) Ltd v Vreulink (665/94) [1996] ZASCA 73; 1996 (4) SA 176 (SCA); (31 May 1996)

80 Reportability
Contract Law

Brief Summary

Contract — Amendment of plea — Application to amend plea to introduce alternative defence based on Conventional Penalties Act — Trial judge refusing amendment on grounds that proposed plea did not disclose a defence and was excipiable — Appellant's employment with respondent prematurely terminated, leading to claim for compensation under employment contract — Court determining whether clause providing for compensation constituted a penalty stipulation — Finding that clause did not impose a penalty as it allowed for termination without breach of contract — Amendment to introduce plea based on penalty stipulation therefore rightly refused.

Comprehensive Summary

Summary of Judgment


Introduction


The proceedings were an appeal to the Supreme Court of South Africa (Appellate Division) against a refusal by the Cape Provincial Division to permit an amendment to a plea. The issue arose interlocutorily, at the commencement of a trial that was still pending.


The appellant, Sun Packaging (Pty) Ltd, was the defendant in the main action and the applicant in the amendment application. The respondent, Anton Hendrik Vreulink, was the plaintiff in the main action and opposed the proposed amendment.


In the court a quo (Mitchell AJ), the appellant sought to amend its plea to introduce an additional, alternative defence to the respondent’s main contractual claim. The trial court refused the amendment on the basis that the proposed alternative defence did not disclose a defence in law and would render the amended pleading excipiable. The appeal concerned the correctness of that refusal.


The dispute’s subject-matter was whether a contractual provision in an employment agreement—providing for payment to the employee if the company changed its operations in a way directly affecting his employment—constituted a “penalty stipulation” under the Conventional Penalties Act 15 of 1962, thereby permitting judicial moderation of the amount claimed.


Material Facts


The respondent’s claim was founded on an alleged contract of employment. He had worked for the appellant from 1986, and on 22 March 1991 the terms of the relationship were reduced to writing in a letter from the appellant to the respondent, which the respondent accepted.


The letter recorded that the respondent had expressed concern at a recent meeting about the future of the company and his own job security, particularly in light of a controlling acquisition by Holdains. Against that background, the letter provided that, with effect from 1 January 1991, the respondent would be employed as Director/General Manager, Speciality Products at the appellant’s Cape factory for a period of five years, with a stipulated annual remuneration package. The contract also contained a renewal mechanism: it would automatically renew for a further five years unless either party gave notice of termination at least six months before termination.


Central to the dispute was clause 3 of the letter. Clause 3 recorded the company’s policy to remain operative for an extensive period of time, but provided that if the company decided, for some unforeseen reason, to restrict, limit, or change its operations to the extent that the respondent’s employment was directly affected, the respondent would be compensated for the “premature termination” of the contract by reference to the unexpired portion of the five-year term, calculated on annual salary at the time of termination with an escalation of 18% per annum thereafter.


The respondent alleged that his employment was prematurely terminated by the appellant with effect from 1 September 1992. The reason given by the appellant in a letter dated 20 August 1992 was that due to “reorganisation” the respondent’s position was being made redundant. For purposes of the appeal, it was accepted that this amounted to an “unforeseen reason” within clause 3 and that the company’s operational change directly affected his employment.


Relying on clause 3, the respondent’s main claim was for payment of R739 174,37, alleged to be the clause 3 compensation for the unexpired portion of the five-year contract. An alternative claim was advanced based on the company’s personnel policy, in an amount of R78 553,19.


In its plea, the appellant admitted the alternative claim and tendered payment of it, while raising other defences to the main claim (including lack of authority for the letter’s author and allegations of fraud). The proposed amendment sought to add a further alternative defence, namely that clause 3 constituted a penalty stipulation and that the claimed amount was out of proportion to any prejudice suffered, so that the court should reduce it under section 3 of the Conventional Penalties Act. The proposed plea asserted that in view of the amount admitted under the personnel policy, the respondent had suffered no prejudice, and therefore was entitled to no compensation under clause 3.


Legal Issues


The central question was whether clause 3, properly construed, constituted a “penalty stipulation” as contemplated in the Conventional Penalties Act 15 of 1962, such that the appellant could invoke section 3 to seek reduction of the amount claimed as excessive.


This required determination of whether the liability to pay under clause 3 arose “in respect of an act or omission in conflict with a contractual obligation”, as required by section 1(1) of the Act. In other words, it required deciding whether payment under clause 3 was triggered by a breach by the appellant of its obligation to employ the respondent for five years, or whether clause 3 instead conferred a contractual right/option to terminate early upon payment of an agreed sum.


Closely linked was the procedural issue: whether the proposed amendment should be permitted, or whether it was properly refused because it would introduce a defence that was bad in law and thus excipiable. This engaged the interpretive question whether clause 3 was reasonably capable of bearing the meaning contended for by the appellant.


The dispute primarily concerned the application of law to contractual language (interpretation and legal characterisation of clause 3’s effect). It also implicated whether extrinsic evidence could be relevant to interpretation on the pleadings as they stood, though the court treated the evidentiary point as secondary and dependent on what was pleaded.


Court’s Reasoning


The court approached the matter on the basis that, for section 3 of the Conventional Penalties Act to apply, clause 3 first had to qualify as a penalty stipulation. Relying on the statutory language and authority, the court stressed that a penalty stipulation under section 1(1) presupposes that the debtor’s liability to pay arises from an act or omission conflicting with a contractual obligation, which entails breach of contract. Absent breach, the Act’s moderation mechanism is not triggered.


The court accepted that an amendment introducing a pleading that is excipiable is ordinarily not allowed. It noted the appellant’s reliance on the principle that an excipient bears the burden of showing that on every reasonable interpretation of the pleading (and the contract on which it is based), no cause of action or defence is disclosed. On that footing, the appellant contended that clause 3 could reasonably be interpreted as treating early termination—even if within the clause’s criteria—as a breach of clause 1, thereby converting the clause 3 payment into a penalty amenable to reduction.


On the argument that evidence might influence interpretation, the court held that a mere notional possibility that surrounding circumstances could assist does not prevent determination of interpretation on exception-like grounds. The court scrutinised the proposed amended plea and found that it contained no allegations identifying relevant surrounding circumstances or background facts that would assist interpretation. The plea’s assertion that clause 3 “constitute[s] a penalty stipulation” was treated as a bare, essentially linguistic conclusion, unsupported by pleaded contextual matter. The court also rejected the suggestion that evidence relating to alleged fraud could affect the meaning of clause 3, holding such evidence irrelevant to interpretation of the clause.


Turning to the text of clause 3, the court recognised that some features might initially appear to support ambiguity: clause 3 contemplated “premature termination”, and the term “terminate” can be used both for termination pursuant to a contractual right and for termination brought about by repudiatory breach. The court also noted that there was no express provision elsewhere granting an early termination right.


However, the court held that clause 3, properly construed, fell within a category of contractual arrangements in which the parties agree that a specified act is permitted on payment of a stated sum, rather than prohibited with the sum payable as a consequence of breach. Drawing on the distinction between a covenant not to do an act with a penalty for doing it, and a covenant that an act may be done subject to payment, the court reasoned that clause 3 operated as a form of alternative or facultative obligation. On this view, clause 1 created the primary obligation to employ for five years, but clause 3 qualified that obligation by granting the appellant an option, provided specified prerequisites were met, to terminate early on payment of compensation. The amount was characterised as the price of exercising the option, not damages for breach.


The court found textual indications consistent with a lawful termination right rather than a breach-based remedy. Clause 3 spoke of “compensated” rather than “damages”, did not use the language of breach, and framed termination as justified by an “unforeseen reason” involving an operational decision affecting employment. The clause also limited its operation to specific circumstances, which the court regarded as inconsistent with an intention to stipulate a fixed payment for any premature termination amounting to breach. Additionally, the court considered the structure of termination: clause 3’s application depended on the appellant’s decision to change operations, whereas repudiation does not itself ordinarily end a contract without the innocent party’s election to cancel.


The appellant argued that construing clause 3 as an option would create an absurdity, because the appellant might avoid paying the larger clause 3 amount by unlawfully repudiating the contract in circumstances outside clause 3, leaving the respondent to ordinary common-law damages that could be less. The court acknowledged the potential anomaly that a breaching party could end up better off than if it complied with the contract’s termination mechanism, but held that this did not justify departing from what it considered the clause’s plain meaning. The court emphasised that the contract must be interpreted as it was made, and that parties may structure their relationship so as to fall outside the Conventional Penalties Act.


The court briefly noted a possible uncertainty about the interaction between clause 2 (automatic renewal unless notice is given) and clause 3 (early termination on operational change), but treated this as bearing on the scope of the right rather than the existence of the right in the distinct circumstances addressed by clause 3.


Finally, the court stated that courts are generally reluctant to decide interpretation disputes on exception where the meaning is uncertain, but held that here the clause’s meaning was not doubtful merely because the parties disagreed about it or because it was not a professionally drafted “lawyer’s contract”. The court concluded that clause 3 had only one proper meaning: it conferred a right to terminate upon payment, rather than creating a breach-triggered obligation.


Outcome and Relief


The appeal was dismissed. The Supreme Court of Appeal upheld the refusal of the proposed amendment on the basis that the proposed alternative defence under the Conventional Penalties Act was not legally sustainable, since clause 3 was not a penalty stipulation and thus was not subject to moderation under section 3.


The appellant was ordered to pay the respondent’s costs of appeal, including the costs occasioned by the employment of two counsel.


Cases Cited


Aubrey and Pastellides (Pty) Ltd v Glen Anil Investments (Pty) Ltd 1960 (4) SA 865 (A).


Avenue Shipping Co and Others v South African Railways and Harbours 1936 CPD 20.


Bridge v Campbell Discount Co Ltd [1962] 1 All E.R. 385 (HL).


Da Mata v Otto NO 1972 (3) SA 858 (A).


Davenport Corner Tea Room (Pty) Ltd v Joubert 1962 (2) SA 709 (D).


Dettmann v Goldfain and Another 1975 (3) SA 385 (A).


Legh v Lillie 158 E.R. 69.


Lewis v Oneanate (Pty) Ltd and Another 1992 (4) SA 811 (A).


Pangbourne Properties Ltd v Gill and Ramsden (Pty) Ltd 1996 (1) SA 1182 (A).


Regina v Westminster Compensation Appeal Tribunal and Sell [1953] 1 WLR 506 (CA).


Standard Building Society v Cartoulis 1939 AD 510.


Tobacco Manufacturers Committee v Jacob Green and Sons 1953 (3) SA 480 (A).


Total South Africa (Pty) Ltd v Bekker NO 1992 (1) SA 617 (A).


Deverill v Burnell 28 L.T. 874.


Legislation Cited


Conventional Penalties Act 15 of 1962.


Rules of Court Cited


No specific rule of court was cited in the judgment.


Held


Clause 3 of the employment agreement did not constitute a penalty stipulation as contemplated by section 1(1) of the Conventional Penalties Act 15 of 1962 because the obligation to pay under clause 3 did not arise from breach of contract. Instead, clause 3 conferred on the employer an option, in defined circumstances, to terminate employment early upon payment of a contractually agreed sum as the price of that termination.


Because clause 3 was not a penalty stipulation, section 3 of the Conventional Penalties Act (permitting reduction of excessive penalties) was inapplicable. The proposed amended plea invoking section 3 therefore disclosed no valid defence and would have been excipiable. The trial court’s refusal to allow the amendment was correct, and the appeal was dismissed with costs, including the costs of two counsel.


LEGAL PRINCIPLES


The Conventional Penalties Act 15 of 1962 applies only where the debtor’s liability to pay arises in consequence of breach of a contractual obligation, as reflected in the requirement in section 1(1) that the payment be “in respect of an act or omission in conflict with a contractual obligation”. A contractual stipulation that requires payment upon the exercise of a contractual right to terminate, rather than upon breach, does not constitute a penalty stipulation and is not subject to moderation under section 3.


In interpreting contractual language, the parties’ intention is ascertained primarily from the text used, read in its context and in light of admissible evidence. Evidence of background facts may form part of the contextual matrix, while evidence of surrounding circumstances is conventionally admissible where there is uncertainty or ambiguity; however, a party seeking to rely on extrinsic evidence must plead a basis showing its relevance. A bare allegation that a provision is a penalty stipulation, without pleaded contextual facts, does not itself establish ambiguity or justify deferring interpretation.


A contractual provision may be structured as an alternative (facultative) arrangement, in which a primary obligation is qualified by a reserved right to perform an alternative prestation. Where a contract permits an act (such as early termination) on payment of a specified amount, the payment may constitute the price for the permitted act rather than damages for breach. The absence of breach-based language (such as “breach” or “damages”), coupled with text indicating a defined circumstance in which termination is contemplated, supports characterisation as the exercise of a contractual right rather than a breach-triggered penalty.


An amendment to a pleading will generally be refused where it would render the pleading excipiable, including where the proposed amendment introduces a defence that is unsustainable on a proper construction of the contract relied upon.

About SAFLII
Databases
Search
Terms of Use
RSS Feeds
South Africa: Supreme Court of Appeal
SAFLII
>>
Databases
>>
South Africa: Supreme Court of Appeal
>>
1996
>>
[1996] ZASCA 73
|

|

Sun Packaging (Pty) Ltd v Vreulink (665/94) [1996] ZASCA 73; 1996 (4) SA 176 (SCA); (1996) 17 ILJ 633 (A) (31 May 1996)

Case No 665/94
IN THE SUPREME COURT OF SOUTH AFRICA
(APPELLATE DIVISION)
In the matter between:
SUN PACKAGING (PTY) LTD
Appellant
and
ANTON HENDRIK VREULINK
Respondent
Coram: NESTADT, F H GROSSKOPF, HARMS, OLIVIER JJA et ZULMAN AJA
Date heard: 24 May 1996
Date delivered: 31 May 1996
JUD GMENT NESTADT. JA:
Iri a judgment reported in 1995(2) SA 326(C), the court
a
quo
(Mitchell AJ, sitting in the Cape Provincial Division) refused
an application to amend a plea. The appellant was the applicant.
2
It is the defendant in an action brought against it by the respondent. The application to amend was moved at the commencement of the
trial. As will be seen, its object was to introduce an alternative defence to the respondent's main claim. The trial judge found,
however, that the proposed plea did not disclose a defence and, if granted, would, on this ground, be excipiable. He therefore upheld
the respondent's opposition to the amendment. In issue before us is the correctness of this decision. The trial is still pending.
It is necessary to analyse the pleadings in a little detail.
The respondent's cause of action against the appellant is based on a
contract of employment. The summons alleges that he first started
working for the appellant in 1986. On 22 March 1991, the terms of
their relationship were reduced to writing. They were contained in
3
a letter of that date written by the appellant to the respondent. The letter (which is annexed to the summons) commences by referring
to the "concern" which the respondent had expressed at "a recent meeting" between the parties "regarding
the future of our company and also your own future within the company, especially in the light of the recent announcement that Holdains
have acquired a controlling
interest in our holding company
" It is also stated that "the offer
of this contract has come about due to your request for job security in the light of the changes mentioned above." Against this
background, it is recorded (in clause 1) that with effect from 1 January 1991 the respondent would be employed as a "Director/General
Manager, Speciality Products" at the appellant's factory in the Cape for a period of five years. His "annual
4
remuneration package" was to be R140 400 (subject to annual
revision). In terms of clause 2 the contract "will be automatically
renewed for a further period of five years unless notice of termination
is given by the one party to the other at least six months prior to
termination". Then follows the clause on which this appeal turns.
It is clause 3. It reads:
"I confirm that it is an integral part of the Company's policy to remain operative for an extensive period of time - in fact
our latest Annual Report stresses that part of our Mission is 'to build Sunpak into a 100 year Company'. However, should the Company
decide for some unforeseen reason to restrict, limit or in any other way change it's operation to the extent that your employment
is directly affected, you will be compensated for the premature termination of this contract as follows; Compensation = Unexpired
portion of 5 year contract based on annual salary at time of termination with an escalation of 18% per annum thereafter."
The final provision is that all other general terms of employment are
5
to be governed by the company's "Personnel Policy". The terms of the letter were accepted by the respondent.
I return to the further allegations contained in the
summons. They make out the case that the respondent's concern, to
which reference has been made, was not misplaced. He did not
remain in the appellant's employment for the five year period
provided for. Instead, his employment was prematurely terminated
by the appellant with effect from 1 September 1992. The reason
given by the appellant appears from a letter to the respondent dated
20 August 1992. It is that due to "the reorganisation" of the
appellant, his position was being "made redundant". This, so it must
be accepted (for the purposes of this appeal), constituted an
"unforeseen reason to
change its operation to the extent that [the
6
respondent's] employment [was] directly affected" within the meaning of clause 3. Relying on it, the respondent's main claim
is for payment of an amount of R739 174,37. This, so it is alleged, represents the compensation due to the respondent for the unexpired
portion of his five year contract, calculated according to clause 3. An alternative claim, based on the appellant's personnel policy
is for payment of R78 553,19.
The appellant's plea admits the alternative claim and tenders payment thereof. The plea to the main claim, however, raises various
defences. One is that the writer of the letter was not authorised to act on behalf of the appellant. Another is that the agreement
was a fraud on it. The (alternative) plea which the appellant now wishes to advance seeks to invoke a further defence, viz the protection
of the Conventional Penalties Act, 15 of 1962.
7
This Act provides, of course, for the enforceability of penalty
stipulations in contracts. The material part of sec 1(1) reads:
"A stipulation, hereinafter referred to as a penalty stipulation, whereby it is provided that any person shall, in respect of
an act or omission in conflict with a contractual obligation, be
liable to pay a sum of money
for the benefit of any other
person, hereinafter referred to as a creditor, either by way of a penalty or as liquidated damages, shall, subject to the provisions
of this Act, be capable of being enforced in any competent court."
However, by virtue of sec 3, the penalty may be reduced if it is
excessive, ie if the Court considers it out of proportion to the
prejudice suffered by the creditor. It is on this section that the
appellant relies. Alleging that "the provisions of clause 3
constitute a penalty stipulation in terms of sec 3 of the
Act", the
amendment pleads that the compensation claimed by the respondent
is (for a number of reasons which it is unnecessary to detail) out of
8
proportion to any prejudice suffered by him; indeed that having regard to the amount of R78 553,19 for which liability is admitted,
he had suffered no prejudice at all; the respondent was therefore not entitled to any compensation under clause 3.
Following from what has been said, two points need to be emphasised. The first is the obvious one that it is a prerequisite to the
operation of sec 3 that the creditor's claim be based on a penalty stipulation (Christie:
The Law of Contract in South Africa
. 2nd ed, 657-8). Accordingly, unless clause 3 constitutes a penalty, it is not subject to moderation. The other is that on the wording
of sec 1(1), and especially "an act or omission in conflict with a contractual obligation", the liability of the debtor
to pay must derive from a breach of contract
(Da Mata v Otto NO
1972(3) SA 858(A)
9
at 871 A). Failing this, the stipulation relied on by the creditor would not qualify as a penalty. As the present case shows, this
may give rise to a quaint state of affairs, namely a debtor who, in order to avoid or reduce liability, contends that he breached
his contractual obligations. But that is the effect of the Act
The question before the court a
quo
was whether clause 3 is a penalty stipulation. The answer was held to depend on its proper interpretation and, in particular, on
whether the compensation provided for is payable in consequence of a breach by the appellant of its obligation to employ the respondent
for five years (as provided for in clause 1). If so, the proposed plea was clearly good in law and the amendment should have been
allowed. It was decided, however (see especially at 329 C-E and 330 H), that the clause
10
afforded the appellant the right, in return for payment of the compensation provided for therein, to terminate the respondent's employment
prior to the expiry of the five year period stipulated in clause 1; that in doing so, the appellant had therefore not committed any
breach of contract; this being so, clause 3 was not a penalty stipulation; and, seeing the Act did not apply, the plea that the amount
claimed by the respondent be reduced (to nil) in terms of sec 3 was thus not legally sustainable.
Before us, Mr Gauntlett, on behalf of the appellant, accepted that if this was so, the application to amend was rightly refused. This
concession was soundly based. An amendment which renders a pleading excipiable will not normally be allowed. But he
11
stressed the principle that an excipient has the duty to persuade the court that upon every interpretation which the pleading in question,
and in particular the document on which it is based, can reasonably bear, no cause of action or defence (as the case may be) is disclosed;
failing this, the exception ought not to be upheld (
Lewis v Oneanate (Pty) Ltd and Another
1992(4) SA 811(A) at 817 F-G). Proceeding on this basis, counsel submitted that clause 3, whilst undoubtedly open to the construction
that it afforded the appellant the right to terminate, was also reasonably capable of meaning that a premature termination of the
respondent's employment (even where the criteria for its operation are satisfied) amounts to a breach of the appellant's obligations
under clause 1. In summary, the argument was that this was so (i) on what I may call a linguistic approach (or,
12
as it was put, on an "internal" interpretation), alternatively (ii) because the proper meaning of the clause could not be
determined without the aid of evidence. In either event, so it was said, clause 3 was capable of being a penalty; it should therefore
not have been held that the proposed plea was excipiable; and the amendment ought thus to have been allowed.
It will be apparent that the argument assumes that the problem is one of interpretation. I am not sure that this is in truth so. It
may be that it is basically one as to the legal effect of the clause (cf
Aubv and Pastellides (Pty) Ltd v Glen Anil Investments (Pty) Ltd
1960(4) SA 865(A) at 872 G). But this would not affect the result of the appeal and I leave it aside. Problems of contractual interpretation
are often before the courts. No wonder then that there
13
is a large body of case law dealing with the applicable principles.
Text-book writers have also contributed to the subject. Mr
Gauntlett
cited the most important authorities in both classes. Save to the
extent which follows, I have not thought it necessary to refer to them
in this judgment. The basic principles are, for the most part, clear.
The determining factor is the intention of the parties. This is
ascertained from the language used, read in its contextual setting and
in the light of any admissible evidence
(Total South Africa fPty) Ltd
v Bekker NO 1992(1) SA 617(A) at 624 F-G). Broadly speaking
there are three classes of such evidence. One is of background facts.
Another relates to surrounding circumstances. The third is evidence
of what passed between the parties on the subject of the contract.
Only the first and second need be considered. It would seem that
14
evidence of the former, ie background facts, is part of the context and as such is always admissible. It has been described as encompassing
the "genesis of the transaction" or its "factual matrix". Its aim is to put the Court "in the armchair of
the author(s)" of the document (LAWSA, First Reissue, vol 9, para 547, p 373). Evidence of surrounding circumstances, on the
other hand, is only justified in cases of uncertainty or ambiguity. At least this is the conventional thinking. But the possibility
of the adoption of a more liberal approach has recently been raised by this Court
(Pangbourne Properties Ltd vs Gill and Ramsden (Ptv) Ltd
1996(1) SA 1182(A) at 1187 B-F). Whether this would mean that ambiguity is not, after all, a
sine qua non
for the admission of evidence of surrounding circumstances, is an issue which, for reasons which follow, it is
15
unnecessary to decide.
With these principles (and problems) in mind, I turn to a consideration of the argument. It is convenient to begin with that part
of it based on the quest for evidence ((ii) above). It can be briefly disposed of. The mere notional possibility that evidence of
surrounding circumstances may influence the interpretation of a contract does not necessarily operate to debar a Court from deciding
the issue on exception. The contention that such evidence exists must be examined with care
(Davenport Corner Tea Room (Pty) Ltd v Joubert
1962(2) SA 709(D) at 716 A-E). The proposed plea contains no allegations in this regard. It will be recalled that it
simply states that "the provisions of clause 3
constitute a penalty
stipulation
" This smacks of a purely linguistic allegation (if I
16
may call it such). Nor does the rest of the plea advance the matter. To be admissible evidence must be relevant. I fail to see how,
as was suggested, evidence of the alleged fraud could possibly affect the proper interpretation of clause 3. When it comes to background
facts, the position is no more favourable to the appellant. One looks first, in this regard, to the terms of the contract of employment
itself. Mr
Gauntlett
carefully took us through them. The submission was that the acquisition of control by Holdains and evidence of the parties' respective
bargaining positions when the contract of employment was entered into, might bear on the meaning of the clause. I remain entirely
unpersuaded that this could be so. Ultimately, we must look to the wording of clause 3 itself. And if its meaning is clear, this
would provide a further and perhaps the
17
most cogent reason for my conclusion that extrinsic evidence is not admissible in aid of interpretation.
This brings me to the argument that clause 3 is indeed ambiguous and that within the confines of the language, it is open to the interpretation
contended for on behalf of the appellant ((i) above). There are factors which support this. Clearly, the possibility of (premature)
termination is contemplated. This can only mean a termination by the appellant. "Terminate" is an ambiguous word, since
it may refer to a termination by a right under the agreement or by a deliberate breach by one party amounting to a repudiation of
the whole contract (per Lord Radcliffe in
Bridge v Campbell Discount Co Ltd
[1962] 1 All E.R. 385(HL).
The appellant's primary obligation was to employ the respondent for five years. The
18
reference in clause 3 itself to a "premature" termination reinforces this. And there is, of course, no express mention of
the appellant having a right to terminate the respondent's employment (early).
But it does not follow that clause 3 is to be construed as not affording the appellant such a right. In
Legh v Lillie
158 E.R. 69
(referred to in
Tobacco Manufacturers Committee v Jacob Green and Sons
1953(3) SA 480(A) at 488 in fin - 489 B) a distinction was drawn between covenants not to do particular acts with a penalty for doing
them and covenants that acts shall not be done unless subject to a certain payment. The second type of undertaking would not involve
a breach. Similarly, the parties to a contract may agree that it be terminable by one of them on payment of a specified sum. Depending
on the wording used, this may amount to a right (in the
19
form of an option) so to terminate (Halsbury's
Laws of England
, 4th
ed, vol 12, para 1119). A comparable principle is referred to in
Wessels'
Law of Contract in South Africa
. 2nd ed, vol 1, para 1454.
Under the heading "Alternative Obligations", the following is said:
"In the
facultative
obligation there is a promise to deliver some definite thing or to perform some definite act, but at the same time the debtor reserves
to himself the right of performing his contract by some other prestation, e.g., I promise to deliver A, but I reserve to myself the
right of delivering B instead. The primary object of the obligation is A, but I have the power
(facultas
) of substituting B."
(See too the further examples of alternative contracts given in the
dissenting judgment of Bovill CJ in
Deverill v Bumell
.
28 L.T. 874
at 876-7).
In my opinion, clause 3 is an example of the type of
agreement postulated by Wessels. The appellant undertook in clause
20
1 to employ the respondent until 31 December 1995. But this obligation was qualified by the contingency of premature termination referred
to in clause 3. By virtue of this clause, and provided its prerequisites were satisfied, the appellant reserved to itself the right,
and thus had the option, on payment of the agreed compensation, to terminate the respondent's employment before such date. The sum
payable was the price of such right. The choice of this course would not involve a breach of its obligations under clause 1. The
contract was in the alternative.
It was urged upon us that this result would elevate form above substance. This is not so. In a case such as ours, form is substance.
They coincide. We have to interpret clause 3 as it is, not as it could have been. Then it was said (I quote from counsel's
21
heads) that "such an approach would
be an invitation to the framers
of contracts to evade the application of the Act by a mere contrivance of words". But there is nothing wrong with that. There
is no reason why parties to a contract should not so structure their relationship. They did so here. Clause 3 does not use the word
"damages". The reference is to "compensation". Ordinarily, these words are not synonomous
(Avenue Shipping Co and Others v South African Railways and Harbours
1936 CPD 20
at 26). This is some indication that a lawful termination was intended (cf
Regina v Westminster Compensation Appeal Tribunal and Sell
[1953] 1 WLR 506
(CA)). Another is that there is no mention of "breach". The wording is rather suggestive of a premature termination being
justified by "some unforeseen reason". The possibility of this
22
happening is foreseen. And "premature" itself simply means "before
the proper time" (The Shorter OED); I do not read it as necessarily
pointing to a breach (which, incidentally, is not even alleged in the
plea). The application of the clause is moreover, confined. The
appellant must have decided to restrict its business operations to an
extent that the respondent's employment be "directly affected". Only
then could the respondent's employment be terminated by the
appellant. Had the termination envisaged by clause 3 been intended
to constitute a breach, one would not expect its ambit to be limited.
The clause would simply have provided for the payment of
compensation in the event of any (unjustified) premature termination.
Bear in mind also that in terms of the clause, termination is
dependent on the appellant's decision. But a repudiation per se does
23
not normally bring a contract to an end; it is the innocent party who has the election whether or not to cancel.
It is true, of course (and this follows from what has been said), that where the appellant unjustifiably discharges the respondent
in circumstances not covered by clause 3, the respondent's remedy will be one for his ordinary common law damages. On the basis that
such damages might be less than the compensation stipulated for, Mr
Gauntlett
advanced an argument with which I must specifically deal. It was that the appellant could avoid payment of the compensation by the
simple device of unlawfully repudiating the contract. In other words, by ensuring that its dismissal of the respondent did not fall
under clause 3 but constituted instead a breach, the appellant would in these circumstances pay less than if it
24
had exercised its right of termination. This, it was said, would lead to an absurdity; accordingly, clause 3 had to be interpreted
as relating to a breach, not the exercise of a right. A similar argument was rejected by the court a
quo
(at 329 F-I) and in my opinion correctly so. It may be regarded as anomalous that a party breaching a contract be in a better position
than if he had performed it. But such a result is no warrant for not giving effect to the plain meaning of the clause. The sanctity
of contract behoves us to do so. The question was raised whether there was not a conflict between clause 2 (which it will be recalled
provides for the automatic renewal of the respondent's employment unless notice of termination be given six months prior to the five
year period) and clause 3. If, say, there was an automatic renewal, would the appellant have the
25
right to terminate during the last six months? I am not sure of the answer. But this uncertainty bears on the scope of the right,
not on whether the appellant has a right to terminate in an entirely different situation.
As a rule, courts are reluctant to decide upon exception questions concerning the interpretation of a contract. But this is where
its meaning is uncertain
(Dettmann v Goldfain and Another
1975(3) SA 385(A) at 400 A). In casu, the position is different. Difficulty in interpreting a document does not necessarily imply
that it is ambiguous (
Standard Building Society vCartoulis
1939 AD 510
at 516). Contracts are not rendered uncertain because parties disagree as to their meaning
(Williston on Contracts
. 3rd ed, vol 4, para 601 (supplement)). Counsel was probably right in saying that
26
the letter is not a lawyer's contract. But this is no reason for interpreting it differently. For the reasons given, I do not find
the meaning of clause 3 doubtful. Properly interpreted, it has only one meaning. It affords the appellant the right to terminate.
This is what Mitchell AJ found. His conclusion that the amendment should be refused was therefore the correct one.
The appeal is dismissed with costs, including those occasioned by the employment of two counsel.
H H Nestadt
Judge of Appeal
F H Grosskopf, JA )
Harms, JA
) Concur
Olivier, JA ) Zulman, AJA )