Competition Commission v Stefanutti Stocks Holdings Ltd (017038) [2013] ZACT 63 (22 July 2013)

80 Reportability
Competition Law

Brief Summary

Competition Law — Consent Agreement — Confirmation of consent agreement between Competition Commission and Stefanutti Stocks Holdings Ltd regarding contraventions of section 4(1)(b)(iii) of the Competition Act — Stefanutti admitting to collusive tendering practices in the construction industry — Tribunal confirming the consent agreement as an order, promoting transparency and competition in the market.

Comprehensive Summary

Summary of Judgment


1. Introduction


The proceedings took the form of an application to the Competition Tribunal for the confirmation of a consent agreement as an order of the Tribunal in terms of section 49D read with section 58(1)(a)(iii) and section 58(1)(b) of the Competition Act 89 of 1998 (as amended). The decision recorded is the Tribunal’s confirmation of the consent order agreed between the parties, annexed to the Tribunal’s order as “A”.


The parties were the Competition Commission (as applicant) and Stefanutti Stocks Holdings Ltd (as respondent). The panel comprised N Manoim (Presiding Member), Y Carrim, and T Madima. The matter was heard on 18 July 2013 and decided on 22 July 2013.


The procedural history reflected in the consent agreement was that the Commission had initiated complaints in February 2009 and September 2009 into alleged prohibited practices in the construction industry, and later (in February 2011) established a settlement initiative directed at fast-tracking resolution of construction bid-rigging matters. Stefanutti applied for settlement/leniency under that process on 15 April 2011, and the parties ultimately concluded a written consent agreement signed on 21 June 2013, which was then placed before the Tribunal for confirmation.


The general subject-matter of the dispute concerned alleged collusive tendering (bid-rigging) in the construction industry, characterised in the consent agreement as the exchange of cover prices, the inclusion of losers’ fees, and tender allocation arrangements. The conduct was treated as contraventions of section 4(1)(b)(iii) of the Competition Act.


2. Material Facts


The consent agreement recorded that the Commission initiated a complaint on 10 February 2009 into alleged prohibited practices relating to collusive conduct in the construction of stadiums for the 2010 FIFA Soccer World Cup, implicating a number of construction firms including Stefanutti. It also recorded that, on 1 September 2009, following immunity applications under the Commission’s Corporate Leniency Policy, the Commission initiated a further complaint into alleged contraventions of section 4(1)(b) (price fixing, market allocation, and collusive tendering) relating to a range of construction projects involving multiple named firms and joint ventures.


The consent agreement further recorded that, following these and other investigations, the Commission formed the view that there had been widespread collusion in contravention of section 4(1)(b)(iii) in the construction industry. In response, the Commission published an Invitation (1 February 2011) offering firms an opportunity to settle contraventions through the Construction Fast Track Process (CFTP), subject to requirements including truthful disclosure, cooperation, cessation of the prohibited conduct, and payment of an administrative penalty determined with reference to turnover in relevant sub-sectors.


Within that settlement framework, Stefanutti applied on 15 April 2011 and disclosed 39 prohibited practices, of which the consent agreement characterised 24 as “prescribed” (time-barred) and 15 as “non-prescribed” (not time-barred). The agreement recorded that Stefanutti was first to apply in respect of 3 of the 15 non-prescribed prohibited practices, and not first to apply in respect of the remaining 12 non-prescribed practices.


In addition to disclosed conduct, the consent agreement recorded that Stefanutti was implicated in 9 non-prescribed prohibited practices that it did not disclose, and that it agreed to settle those as well. The agreement therefore proceeded on the basis that Stefanutti would settle a total of 21 non-prescribed prohibited practices, comprising 14 in the Civil Engineering sub-sector and 7 in the General Building sub-sector.


The prohibited practices were described as collusive tendering typically involving cover pricing, sometimes coupled with losers’ fees and profit-sharing or allocation arrangements. The consent agreement described multiple project-specific arrangements, including (among others) building and civil engineering tenders such as the UCT Women’s Residence project, Bayhead Road Extension / Khangela Bridge project, Green Point Stadium project, FNB Soccer City Stadium project, and the Durban International Convention Centre project, as well as other projects (including some outside South Africa) such as projects at Tati (Botswana) and Ngezi (Zimbabwe). In those descriptions, the agreement recorded that Stefanutti either provided or received cover prices, and in certain instances agreed on and/or paid or was to receive compensation (including losers’ fees), with the effect that bids were rendered non-competitive and tender outcomes were predetermined amongst competitors.


The consent agreement contained an explicit admission by Stefanutti that it entered into the agreements detailed in the consent agreement, with competitors, in contravention of section 4(1)(b)(iii). It also recorded cooperation undertakings, including that Stefanutti had provided truthful and timely disclosure and expeditious cooperation, had confirmed it had ceased the conduct, and had not destroyed or falsified relevant information.


For prospective conduct, the agreement recorded undertakings that Stefanutti would cooperate further in subsequent proceedings, make employees/former employees available as witnesses, submit a competition law compliance programme within 60 days of confirmation, circulate a statement summarising the consent agreement to management and operational staff within 60 days, and refrain from future prohibited practices.


On penalty, the agreement recorded that Stefanutti accepted liability for an administrative penalty calculated by reference to the Commission’s Invitation methodology, restricted to non-prescribed prohibited practices. The agreed administrative penalty was R 306 892 664, with specified payment terms spread over four instalments across three years. The agreement further recorded that the fourth payment would attract 10% per annum interest on the amount of that instalment.


3. Legal Issues


The central legal question before the Tribunal, as reflected in the Tribunal’s order, was whether the Tribunal should confirm the consent agreement concluded between the Commission and Stefanutti as an order of the Tribunal under section 49D read with section 58 of the Competition Act.


The consent agreement itself framed the underlying contraventions as falling within section 4(1)(b)(iii) (collusive tendering), and addressed the legal distinction between “prescribed” and “non-prescribed” prohibited practices by reference to section 67 of the Act (with the settlement and penalty calculation confined to non-prescribed conduct). In this procedural setting, the Tribunal’s task (on the face of the order) was not to determine the merits of the alleged cartel conduct through contested evidence, but to determine whether to make the agreed settlement terms an enforceable Tribunal order.


Accordingly, the dispute before the Tribunal principally concerned the application of statutory provisions governing consent agreements and Tribunal orders to an agreed set of facts and admissions, rather than the resolution of factual disputes. The Tribunal’s order as issued did not reflect the determination of contested questions of fact.


4. Court’s Reasoning


The Tribunal’s published decision in this matter was confined to a brief order stating that it confirmed the order as agreed to and proposed by the Competition Commission and the respondent, annexed and marked “A”. No further reasoning was set out in the text of the Tribunal’s decision beyond the confirmation itself.


From the content and structure of the order, the Tribunal’s approach proceeded on the basis that the parties had concluded a consent agreement in terms contemplated by section 49D, and that the Tribunal was being asked to exercise its statutory power under section 58 to confirm that agreement as a Tribunal order. The confirmed agreement included, among other terms, admissions of contravention, cooperation obligations, compliance commitments, and an agreed administrative penalty and payment schedule.


The Tribunal did not, in the text provided, engage in an extended evaluative analysis of the projects, the market effects of the conduct, or the penalty methodology. The decision reflects acceptance of the settlement mechanism provided for in the Act and the parties’ agreement as the basis for granting the confirmation order.


5. Outcome and Relief


The Competition Tribunal confirmed the consent agreement between the Competition Commission and Stefanutti Stocks Holdings Ltd as an order of the Tribunal, as annexed and marked “A”.


The confirmed order incorporated the settlement terms recorded in the consent agreement, including Stefanutti’s admission of contraventions of section 4(1)(b)(iii), its cooperation and future-conduct undertakings, the obligation to submit a competition law compliance programme and circulate a summary statement internally, and the obligation to pay an agreed administrative penalty of R 306 892 664 in instalments, with interest as specified on the fourth payment. The Tribunal’s order as provided did not record a separate costs order.


Cases Cited


No cases were cited in the text provided.


Legislation Cited


Competition Act 89 of 1998 (as amended), including sections 2, 4(1)(b), 19, 21(1), 22, 26, 49B, 49D, 58(1)(a)(iii), 58(1)(b), 59(1)(a), 59(2), 59(3), 59(4), and 67(2).


Constitution of the Republic of South Africa, 1996, section 217.


Rules of Court Cited


No rules of court were cited in the text provided.


Held


The Tribunal made an order confirming the consent agreement concluded between the Competition Commission and Stefanutti Stocks Holdings Ltd as a Tribunal order. The confirmed order reflected settlement of 21 non-prescribed instances of collusive tendering in contravention of section 4(1)(b)(iii) of the Competition Act, together with cooperation and compliance undertakings and payment of an agreed administrative penalty on specified terms.


LEGAL PRINCIPLES


The matter applied the statutory mechanism in terms of which the Competition Commission may conclude a consent agreement with a respondent firm under section 49D of the Competition Act, and may approach the Competition Tribunal to have that agreement confirmed as an order under section 58.


The consent agreement proceeded on the principle that collusive tendering (bid-rigging) constitutes a prohibited restrictive horizontal practice under section 4(1)(b)(iii) of the Competition Act, and may be manifested through arrangements such as cover pricing, losers’ fees, and tender allocation agreements, which distort competitive tender outcomes.


The settlement also reflected the application of the Act’s prescription/time-bar framework (as referenced in the consent agreement by section 67), distinguishing between prescribed and non-prescribed prohibited practices for purposes of settlement scope and penalty calculation, with the administrative penalty in this matter calculated with reference only to the non-prescribed conduct.


The consent order reflected the statutory basis for an administrative penalty under section 58(1)(a)(iii) read with section 59, and recorded that payment to the Commission would be paid over to the National Revenue Fund as contemplated in section 59(4).

About SAFLII
Databases
Search
Terms of Use
RSS Feeds
South Africa: Competition Tribunal
SAFLII
>>
Databases
>>
South Africa: Competition Tribunal
>>
2013
>>
[2013] ZACT 63
|

|

Competition Commission v Stefanutti Stocks Holdings Ltd (017038) [2013] ZACT 63 (22 July 2013)

COMPETITION
TRIBUNAL
REPUBLIC
OF SOUTH AFRICA
Case
No:
017038
In
the matter between:
The
Competition Commission
Applicant
and
Stefanutti
Stocks Holdings Ltd
Respondent
Panel:
N
Manoim (Presiding Member), Y Carrim (Tribunal Member) and T
Madima (Tribunal Member)
Heard
on:
18
July 2013
Decided
on:
22
July 2013
Order
The
Tribunal hereby confirms the order as agreed to and proposed by the
Competition Commission and the respondent, annexed hereto
marked “A”.
Presiding
Member N Manoim
Concurring:
Y Carrim and T Madima
THE
COMPETITION TRIBUNAL OF SOUTH AFRICA
HELD
IN PRETORIA
CT
Case No;
CC
Case No: 2009Feb4279/2009Sep4641
Application
for confirmation of a consent agreement
In
the matter between:
THE
COMPETITION COMMISSION
Applicant
And
STEFANUTTI STOCKS
HOLDINGS LIMITED
Respondent
CONSENT
AGREEMENT IN TERMS OF SECTION 49D READ WITH ECTION 58 (1)(a)(iii) AS
READ WITH SECTION 58(1)(B) OF THE COMPETITION ACT,
1998 (ACT NO.:89
OF 1998), AS AMMENDED BETWEEN THE COMPETITION AND STEFANUTTI STOCKS
‘HOLDINGS LIMITED, IN REGARD TO CONTRAVENTIONS
OF
SECTION
4(1)(B)(iii)
OF THE
COMPETITION ACT, 1998
PREAMBLE
WHEREA
S
the
Competition Commission Is empowered to,
inter
alia,
investigate alleged contraventions of the
Competition Act, 1998
:
WHEREA
S
the
Competition Commission is empowered to,
inter
alia,
conclude consent agreements in terms of
section 49D
of the
Competition Act, 1998
;
WHEREA
S
the Competition Commission has invited firm in the construction
industry to engage in settlement of contraventions of the
Competition
Act, 1998
;
WHEAREAS
Stefanutti
Stocks Holdings Limited (StefanuttI) has accepted the Invitation and
has agreed to settle in accordance with the terms
of the Invitation;
NOW
THEREFORE
the
Competition Commission and Stefanutti hereby agree that application
be made to the Competition Tribunal for the confirmation
of this
consent agreement as an order of the Competition Tribunal in terms of
section 49D
as read with
sections 58(1)(a)(iii)
and
58
(1 )(b) of the
Competition Ad, 1998.
1.
Definitions
For
the purposes of this consent agreement, unless the context indicates
otherwise, the following definitions shall apply:
1.1.
"Act”
means
the Competition Act, 1998 (Act No. 88 of 1998), as amended;
1.2.
“CFTP” means the Construction Fast Track Process
announced by the Commission on 1 February 2011 to fast track
the
settlement process and to resolve the Commissions investigations
into the construction industry;
1.3
'‘CIDB Regulations” refers to the Construction Industry
Development Regulations, 2004 {as amended) (Government
Notice No.692
of 9 June 2004, published in Government Gazette No.26427 of 9 June
2004);
1.4.
"CLP" means the Com mission’s Corporate Leniency
Policy (Government Notice No, 628 of 23 May 2QQ8, published
in
Government Gazette No. 31064 of 23 May 2008)1
1.5.
“Commission"
means
the Competition Commission of South Africa, a statutory body
established in terms of section 19 of the Act, with its principal

place of business at
1
5f
Floor,
Mulayo Building (Block
C),
the
dti Campus, 77 Meintjies Street Sunnyside, Pretoria, Gauteng;
1.6.
“Commissioner” means the Commissioner of the Competition
Commission, appointed in terms of section 22 of the
Act;
1.7.
Complaints
means
the com
p
l
aint
s
initiate
d
by the Commissioner of the
Competition
Commission in terms of section 49B of the Act under case numbers
2009Feb4279 and 2009Sep4641;
1.8.
"Consent
Agreement” means this agreement duly signed and concluded
between
the Commission and Stefanutti Stocks Holdings Limited
("Stefanutt'f};

Cover
Price” means generally, a price that is provided by a firm
that wishes to win a tender to a firm that does not wish
to do so
:
in order that the firm that does not wish to win the tender may
submit a higher price; or a price that is provided by a firm
that
does not wish to win a tender to a firm that does wish to win that
tender in order that the firm that wishes to win the
tender may
submit a lower price.
1.10.
"Invitation" means the invitation to Firms in the
Construction industry to engage in settlement of contraventions
of
the
Competition Act, as
published on the website of the Commission
on 1 February 2011;
1.11.

Parties”
means the Commission and Stefanutti;
1.12.
"prescribed
prohibited practices' refers to prohibited restrictive horizontal
practices relating to the construction industry
that are
contemplated in section 4(1)(b) of the Act and that ceased after 30
November 1998, but more than three years before
the complaints were
initiated;
1.13.
“Non-prescribed
prohibited practices"
refers to prohibited restrictive horizontal
practices
relating
to the construction industry that are contemplated in section 4(1
)(b) of the Act and that are on-going or had not ceased
three years
before the complaints were initiated, as contemplated in section 67
of the Act;
1.14.
“Respondent”
means Stefanutti;
1.15.
‘‘Stefanuitl”
means Stefanutti Stocks Holdings Limited; a company incorporated
under the laws of the Republic of South Africa with its principal

place of business at Protec Park, corner Zuurfontein Avenue and
Oranjerivier Drive, ChloorKop Kempton Park, East Rand.
1.16.
“Subsector"
refers.to the classes of construction work defined in Schedule 3 of
the C1DB Regulations, substituted by Government Notice No.
8986 of
14 November 2008, published in Government Gazette No. 31603 of 14
November
2008;
1.1.7.
“Tribunal”
means the Competition Tribunal of South Africa, a statutory body
established in terms of section 26 of the Act, with its principal

place of business at 3
fd
Floor, Mulayo building (Block C), the dti Campus, 77 Meintjies
Street, Sunnyside, Pretoria, Gauteng.
2.
The Complaints
2.1.
On 10 February 2009 the Commission Initiated a complaint in terms of
section 49B(1) of the Act into alleged prohibited practices
relating
to collusive conduct in the construction of the stadiums for the
2010 FIFA Soccer World Cup against Grinaker-LTA (the
construction
operating business unit of Aveng),. Group Five Limited, Basil Read
(Pty) Ltd, WBHO Construction <Pty) Ltd, Murray
& Roberts
Limited, Stefanutti Stocks Holdings Limited, I nterbeton Abu Dhabi
nv He and Bouygues Construction SA.
2.2.
In addition, on 01 September 2009, following the receipt of
applications for immunity in terms of the CLP, the Commission

initiated a Complaint in terms of section 49B(1) of the Act into
particular prohibited practices relating to conduct in construction

projects, by the firms listed below. The Complaint concerned alleged
contraventions of section 4(1)(b) of the Act as regards
price
fixing, market allocation and collusive tendering. The investigation
was initiated against the following firms: Grinaker
LTA Ltd, Aveng
(Africa) Ltd, Stefanutti Stocks Holdings Limited, Group Five Ltd,
Murray & Roberts, Concor Ltd, G. LMero &
Son Building (Pty)
Ltd, Giurtcich Coastal Projects (Pty) Ltd, Hochtief Construction AG,
Dura Soletanche-Bachy (Pty) Ltd, Nishimatsu
Construction Co Ltd,
Esorfrankt Ltd, VNA Pilings CC, Radio Geotechnics (Pty) Ltd, Diabor
Ltd, Gauteng Piling (Pty) Ltd, Fairbrother
Geotechmca! CC,
Geomechantes GC,. Wilson Bayly Holmes-Ovcon Ltd and other
construction firms, including joint ventures.
3.
The Invitation to Firms in the Construction Industry to Engage in
Settlement of Contraventions of the Act
3.1.
The Commission’s investigation of the Complaints, as well as
several other of the Commission's investigations in the
construction
industry, led the Commission to believe that there was widespread
collusion in contravention of section 4(1)(b)(iii)
of the Act in the
construction industry.
3.2.
Section 4(1)(b) provides-

4,
Restrictive horizontal practices prohibited
(1)
An agreement between, or concerted practice by, firms, or a decision
by
an
association of firms, is prohibited if it is between parties in
a
horizontal
relationship
and if—
(a)
it has the effect of substantially preventing, or lessen^
competition in a market
,
unless
a party to the agreement, concerted practice, or decision can prove
that any technological, efficiency or other pro-competitive
gain
resulting from it outweighs that effect; or
(b)
it involves any of the following restrictive horizontal practices
:
(i)
directly or Indirectly fixing
a
purchase
or selling price or any other trading condition;
(ii)
dividing markets by allocating customers, suppliers
,
territories,
or specific types of goods or services;
or
(iii)
collusive
tendering
.”
3.3.
The collusive conduct engaged in, in the context of the Invitation
and this Consent Agreement, was collusive tendering or

"bid-rigging”. Collusive tendering involves particular
conduct by firms whereby as competitors they collude regarding
a
tender resulting in the tender process being distorted* The bid
prices and the bid submissions by these competitors as well
as the
outcome of the tender process is not the result of competition on
the merits, "Cover pricing
11
in this context occurs when conspiring firms agree that one or more
of them will submit a bid that is not intended to win the
contract.
The agreement is reached in a way that among
c
oIluding
firms one firm wishes to win the tender and the others agree to
submit non-competitive bids with prices that would be
higher than
the bid of the designated winner, or the price will be too high to
be accepted, or the bid contains special terms
that are
known
to be unacceptable to the client. Collusive tendering therefore
applies to agreements or concerted practices which have
as their
object or effect the prevention, lessening, restriction and
distortion of competition in South Africa.
3.4.
In terms of section 2 of the Act, two of the key objects of the Act
are to promote the efficiency, adaptability and development
of the
economy, and to provide consumers with competitive prices and
product choices. Section 217 of the Constitution of the
Republic of
South Africa, 1996 calls for a procurement or tender system which is
fair, equitable, transparent, competitive and
cost-effective,
3.5.
In addition, the Commission is required in terms of section 21(1} of
the Act,
inter
alia,
to implement measures to increase market transparency, to
investigate and evaluate alleged contraventions of Chapter 2 of the

Act, and to negotiate and conclude consent agreements in terms of
section 49D for confirmation as an order of the Competition
Tribunal
in terms of section 58(1 )(b}- of the Act..
3.6.
Therefore, in the interest of transparency, efficiency, disrupting
cartels and incentivrsing competitive behaviour m the
construction
industry and a cost- effective, comprehensive and speedy resolution
of the investigations referred to above, the
Commission decided to
fast'track these investigations and their resolution by inviting
firms that were involved in collusive
tendering in the form of
bid-rigging of projects in the construction industry, to apply to
engage In settlement discussions on
the terms set out in the
Invitation,
3.7.
On 1 February 2011 the Commission issued a media release about the
Invitation and published same on its website. In the Invitation,

hereto attached and marked as Arjnsxuire A, the Commission -offered
firms the opportunity to settle the alleged contraventions
of the
Act, if they would:
3.7.1.
submit an application
m
terms of PART 2 of the invitation;
3.7.2.
agreed to pay an administrative
penalties
determined by the c
ommission
as envisaged in paragraph 10.2. read with paragraphs 19- 28 of the
Invitation; and
3.7.3.
comply with the requirements of the settlement process as set out in
PART 1 and PART 3 of the Invitation,
3.8.
This agreement sets outs the detail of the non-pnsscribed prohibited
practices only which the respondent is liable to settle
regard being
had
to the provisions of section 67(2) of the
Act
and the penalty is calculated taking into account only the said
non-prescribed prohibited practices.
3.9.
Applying firms were required to
inter
alia
provide the Commission with truthful
and
timely disclosure of information and documents relating to the
prohibited practices and to provide full and expeditious

co-operation to the Commission concerning the prohibited practices,
3.10.
An applying firm could request the Commission to consider its
application in terms of the invitation as an application for
a
marker or as an application for immunity under the CLP. Firms could
also apply for a marker or for immunity under the CLP before
making
an application in terms of the Invitation.
3.11.
The deadline to apply for a settlement in terms of the Invitation
was 12hQ0 on 15 April 2011.
4.
Application by Stefanutti
4.1.
Stefanutti applied for leniency and Settlement in terms of the
invitation. Stefanutti is involved in engineering and construction

activities throughout the building environment Its offerings extend
across a wide scope of supply including construction of fixed

infrastructure, municipal services, mining & industrial
facilities and all structures and buildings.-—
4.2.
Stefanutti applied for leniency and Settlement on 15 April 2011 and
disclosed 39 prohibited practices, Out of the 39 prohibited

practices disclosed, 24 are prescribed prohibited practices and 15
are non-prescribed
4.3.
Stefanutti was first to apply for 3 out of the 15
non^rescnWd‘"^r6HiBited" practices and is not first
to
apply for 12 non-prescribed prohibited practices.
4.4.
Stefanutti is implicated in 9 non-prescribed prohibited practices
which it did not
disclose, and has agreed to
settle these 9 non~prescribed prohibited practices.
4.5.
The total number of prohibited practices being settled under the
Consent Agreement is twenty one (21) non-prescribed prohibited

practices, Fourteen (14) prohibited practices are in the Civil
Engineering sub-sector, and seven (7) prohibited practices are
in
the General Building sub-sector.
4.6.
The twenty one 21 prohibited practices or contraventions by
Stefanutti of section 4(1)(b)(iii) of the Act which are the subject

of this Consent Agreement, are set out below.
5.
Disclosed Projects
5.1.
UCT-Women's
Residence in Cape Town
Stefanutti
reached agreement with Grinaker-LTA and Group Five on or about
November 2005, in that they agreed on a cover price
and a loser’s
fee in relation to this project, which was allocated pursuant to the
Caps Club Meeting. In terms of the cover
price and the losers’
fee agreement, Grinaker-LTA and Stefanutti would submit cover prices
to ensure that Group Five would
win the tender. Further, they agreed
that Group Five would pay Stefanutti and Grinaker- LTA a loser's fee
in the amount of R500
000 each. This conduct is collusive tendering
in contravention of section 4(1)(b)(iii) of the Act.
This
project was for building works and residential development at the
University of Cape Town's women’s residence. The
client was
the University of Cape Town. The project was awarded to Group Five.
The project was completed in 2007.
5.2.
Bayhead Road Extension Khangela Bridge Project (Tender Ref No:
IR-1010)
Stefanutti
in joint with Basil Read (“Stefanutti-Basil Read Joint
Venture”) reached agreement with Group Five; on
or about
September 2005, in that they agreed on a cover price in respect of
this project. In terms of the agreement, Group Five
would provide a
cover price to Stefanutti-Basil Read Joint Venture to ensure that
the Stefanutti-Basil Read Joint venture won
the tender. The
Stefanutti-Basil
Read Joint Venture further agreed with Group Five to share profits
in respect to this project. In order to implement
the profit sharing
agreement, the Stefanutti-Basil Read Joint Venture subcontracted a
portion of the project to Group Five. The
StefanutthBasii Read Joint
Venture was awarded the tender, with Group Five Joining in as a
subcontractor. This conduct is collusive
tendering in contravention
of section 4(1)(b)(iii) of the Act,
This
project was for the construction of Khangela Bridge and extension of
Bayhead road
in
Durban for the Elhekwini Municipality. The project was completed in
January 2010.
5.3.
Civil Works for Tati
Activox
Project (Tender Ref No:. H32250-CC002/04)
Stefanutti
in a joint venture with Grinaker LTA (Stefanutfl-Grinaker Joint
Venture) reached agreement with Basil Read.. and Murray
&
Roberts on or about June 2007, in that they agreed on a cover price
in respect of this project. In terms of the agreement,

Stefanutti-Grinaker Joint Venture gave a cover price to Basil Read
and Murray & Roberts so that Basil Read and Murray &
Roberts
could submit a non-competitive bid to ensure that the
Stefanutti-Grihaker, Joint Venture won the tender. The
Stefanutti-Grinaker
Joint Venture was awarded the tender in line
with the collusive agreement This conduct is collusive tendering in
contravention
of section 4(1 )(b)(iii) of the Act,
This
project was for the civil works at Tati Activox near Francistown in
Botswana for Botswana Metal Refinery (Pty) Ltd. The project
was
completed on 31 September 2008.
5.4.
Coal Mill Line - Dwaalboom (Tender Ref No: DB/09)'
Stefanutti
in joint venture with Goncor (Stefanutti-Concor Joint Venture)
reached agreement with WBHO and Grinaker LTA, on or
about September
2006, in that they agreed on a cover price in respect of this
project. In terms of the agreement Stefanutti-Conor
Joint Venture
gave a cover price to WBHO and Grinaker LTA
so
that WBHO and Grinaker LTA could submit non-competitive bids to
ensure that the SiefanuttbGoncor Joint Venture won the tender.
In
line with the cover price agreement, the Stefanutti-Concor Joint
Venture was awarded the tender. This conduct is collusive
tendering
in contravention of section 4(1)(b)(iii) of the Act.
This
project was for the civil works for the Dwaaiboom expansion for
Pretoria Portland Cement Company (Pty) Ltd, The closing date
for the
tender was 31 July 200&
5.5.
Construction of Green Point Stadium (Tender Ref
No
.:
Q06/63)
Stefanutti
reached agreement with WBHO on or about December 2006, in that they
agreed on a cover price, in respect of this project
In terms of the
agreement WBHO provided a cover price to Stefanutti so that
Stefanutti coufd submit a non­competitive bid
to ensure that
WBHO won the tender. WBHO was in joint venture with Murray &
Roberts when bidding for the tender, and won
the tender in line
with
the collusive arrangement. This conduct is collusive tendering in
contravention
of section 4(1)(b)(iii) of the Act
This
project was far the construction of Green Point Stadium in Cape
Town, for the City of Cape Town. The project was completed
on 10
November 2009.
5.6.
FNB Soccer City Stadium
Stefanutti
reached agreement with Grinaker LTA in that they agreed on a cover
price in respect of this project. In terms of th©
agreement
Grinaker LTA would provide a cover price to Stefanutti to ensure
that Grinaker LTA won £he tender. The tender
was awarded to
Grinaker LTA in line with the cover price arrangement. Unis conduct
is collusive tendering in contravention of
section 4(1)(b)p) of the
Act.
This
project involved the provision of general building and related works
at Soccer City Stadium for the City of Johannesburg.
The project was
completed
on
30 April 2009.
5.7.
Mondi Multi Fuel Boiler (Tender Ref No: M679736001)
Stefanutti
reached agreement with JT Ross, on or about October 2005, in that
they agreed to add a losers' fee in respect of this
project, In
terms of the agreement the firm which won the bid was to pay R49 950
to the losing firm. Stefanutti was awarded this
tender and, in line
with the agreement, paid the agreed fee of R49 950 to JT Ross on or
about May 2007. This conduct is collusive
tendering in contravention
of section 4(1)(b)(iii) of the Act
This
project involved the civil works which included foundations,
channels, and minor buildings for a boiler at Mondi Paper South

Africa (Pty) Ltd situated at Merebank, Durban, The project was
completed on 30 November 2006.
5.8.
PP Rust North Phase 1 Civils
Stefanutti
reached agreement with Grinaker LTA, Co near, Murray & Roberts,
WBHO and Group Five on or about June 2007, in that
they agreed on
a
cover price in respect of this project. In terms of the agreement,
Stefanutti provided a cover price to Grinaker, Concor, Murray
&
Roberts, WBHO and Group Five to ensure that WBHO won the tender. The
tender was awarded to WBHO in fine with the collusive
agreement This
conduct is coBusive tendering in contravention of section 4(1 )(b)p)
of the Act.
This
project was for the construction of a concrete infrastructure to
platinum mine for Anglo Platinum Limited.
5.9.
Civil Works for the Tati Nickel Dense Medium Separation (“DMS”)
Project
(Tender Ref No: C2585Z7/010)
Stefanutti
in joint venture with Grinaker LTA (Stefanutti-Grinaker Joint
Venture) reached agreement with Murray & Roberts
and Basil Read,
on or about February 2007, in that they agreed on a cover price in
respect of this project. In terms of the agreement,

Stefanutti/Grinaker Joint Venture gave a cover price to Murray &
Roberts
and Basil Read so that Murray & Roberts could win the tender.
The tender was awarded to Murray & Roberts in line
with the
collusive agreement. This conduct is coifusive tendering in
contravention of section 4(1 )(b)(iii) of the Act.
This
project was for the DMS civil works at Tati near Francstown in
Botswana for Tati Mining Company. The project was completed
in
December 2008.
5.10.
Z-Mill and Civils Structural Works (Tender Ref No: 070616/CEP3244)
Stefanutti
reached
agreement with Group Five and WBHO, on or about July 2007,
m
that they agreed on a caver price in respect
of
this
project in terms of the agreement Stefanutti provided a cover price
to Group Five and WBHO to ensure that Stefanutti won the
tender The
project was awarded to Stefanutti in line with the collusive
arrangement This conduct is collusive tendering in contravention
of
section 4(1)(b)(iii) of the Act.
This
project involved civil and structural steel works for the Sendzimir
Cold Rolling Mill for Columbus Stainless Steel. The project
was
completed on 31 October 2008.
5.11.
PPC -
Dwaalboom
DB-05 Preheater Towers (Tender Ref No: 060650)
Stefanutti
reached agreement with Concor on or about July 2005, in that they
agreed on a cover/price in respect of this project.
In terms of the
agreement . Concor provided a cover price to Stefanutti so that the
latter would submit a non­competitive
bid to ensure that Concor
won the tender Concor was awarded the tender in line with the cover
price agreement This conduct
m
collusive tendering in contravention of section 4(1)(b)(iii} of the
Act.
This
project was for the construction of a pre-heater tower at Dwaalboom
for
Pretoria
Portland Cement. The project was completed on 7 January 2008.
5.12.
Durban International Convention Centre [Tender Ref No: CSA 0936]
Stefanutti
in joint venture with Fikiie Construction (Pty) Ltd (Stocks Fikiie
C&R JV) reached agreement with Grinaker LTA,
WBHO and Group Ffve
on or about October 2004 in respect of the Durban International
Convention Centre (Durban
ICC)
project. Group Five and WBHO were in a joint venture known as
Masinya JV and Grinaker LTA and Sivukile Contractors (Pty)
Ltd were
in a joint venture known as Wozant JV. in terms of the agreement
Grinaker-LTA provided a cover price to Stefanutti,
WBHO and Group
Five to ensure that the joint venture involving Grinaker-LTA won the
tender. Stefanutti, WBHO, Group Five and
Grinaker-LTA also agreed on
a loser’s fee arrangement in terms of which they agreed that a
tender fee of R750 000 wouid
be. included in the tender price so
that the winner of the tender would pay the losing bidders. This
conduct is collusive tendering
in contravention of section 4(1
J(b)(iii) of the Act.
The
project was for the construction of the Durban Internationa}
Convention Centre for the
City
of
Durban, The tender was awarded to Masinya JV. The project was
completed in July 2008.
6.
Non Disclosed Projects and Meeting
6.1.
The Ngezi Phase 1 Civil Work
Stefanutti
reached agreement with Concor on or about January 2007 in that they
agreed on a" cover price in respect’
of this project, in
terms of the agreement, Concor provided a cover price to Stefanutti
in order for Stefanutti to win the tender.
In line with the cover
price arrangement, Stefanutti was awarded the tender. This conduct
is collusive tendering in contravention
of section 4(1)(b)(iii) of
the Act.
This
project involved the construction of concrete Infrastructure for a
platinum concentrating facility in Zimbabwe for Zimplats,
a member
of the Impala group of companies in Zimbabwe. The project was
scheduled to be completed in June 2009.
6.2.
Sappi Amakhulu Expansion of Sappi Plant
Stefanutti
in joint venture with Group Five, reached agreement with Grinaker
LTA on or about 2006 in that they agreed on a cover
price in respect
of this project. In terms of the agreement Grinaker LTA provided a
cover price to Stefanutti to
ensure
that Stefarrutti-Group Five joint venture would win the tender. This
conduct is coliusive tendering in contravention of
section
4(1)(b)(iii) of the Act.
This
project was for the extension of the Sappi Plant in Umkomaas,
Kwazuiu Natal for Sappi Saicor. The project was completed in
April
2008
6.3.
New Distribution Depot BATSA (Tender Ref No: MF0032)
Stefanutti
reached agreement with Giuricich, Edilcon, G D Irons and Rainbow
Construction in that they agreed on a cover price
in respect of this
project, in terms of the agreement Giuricich provided a cover, price
to Stefanutti, Edilcon, G D Irons and
Rainbow Construction to ensure
that Giuricich won the tender.
In
addition,
Giuricich agreed to pay Stefanutti a losers' fee in the amount of
R219 166.88 in the event that Giuricich won the tender.
In line with
the cover price arrangement, the tender was - awarded to Giuricich.
This conduct is collusive tendering in contravention
of section
4(1)(b)(iii) of the Act.
This
project was for the construction of a new distribution depot for
British American Tobacco. The project was completed on 9
September
200S.
6.4.
New Tusks Residence
Stefanutti
reached agreement with Giuricich on or about 2006 in that they
agreed on a cover price in respect of this project.
In terms
of
the
agreement, Stefanutti provided a cover price to Giuricich to ensure
that Stefanutti would win the tender. Stefanutti was awarded
the
tender in line, with the collusive agreement This conduct is
collusive tendering in contravention of section 4(l)(b)(iii)
of the
Act
The
project was for the construction of new residence village for the
University of Pretoria. The project was completed on or
about March
2003.
6.5
Gauteng Freeway Improvement Project (“GFIP”) - Package A
[Tender
Ref
No. NRA N1 001200-2008/1], Package B [Tender Ref No.:NRA N1
001-200-2008/2], Package E [Tender Ref No.: NRA N1 003-120-2008/1].
Stefanutti
in joint venture with Concor reached agreement with WBHO on or about
2006 In respect of the Gauteng Freeway Improvement
project (“GFIP

)
which comprised of three packages, namely; Package A, B and E. In
terms of the agreement Stefanutti, Concor and WBHO agreed
to
allocate the various packages among themselves. They further agreed
to exchange cover prices to give effect to the allocation

arrangements.. This conduct is collusive tendering in contravention
of section 4(1)(b)(iii)
of
the Act.
The
project was for the addition of lanes, construction of retaining
walls, bridges and structure as well as various intersections
on the
southern sections of freeways around Johannesburg. The client for
the project was SANRAL. The tender for Package A was
awarded to
Group Five, Package B was awarded to WBHO, and Package E was awarded
to Group Five. The projects for Package A, B
and
B
were
completed in2010.
6.7.
Anglo-Platinum Housing (Thabazimbi and Burgersfort)
(Tender
Ref No.H07/0040/00 & T08/0026)
Housing
Africa Development (Pty) Ltd (“Housing Africa"), a
subsidiary of Stefanutti reached agreement with Group Five
on or
about 2007 in that they agreed on a cover price in respect of this
project which had two packages, namely; the Thabazimbi
Package and
the Burgarsfort Package, In terms
of
the agreement, Housing Africa provided a cover price to Group Five
in respect to the Thabazimbi Package. The agreement also involved

Stefanutti and Group Five agreeing on an allocation arrangement In
terms of which Stefanutti would submit a non-competitive bid
in
respect of the Thabazimbi Package to enable Group Five to win the
tender, and that Stefanutti would win the Burgersfort Package.

Housing Africa also provided a cover price to Group Five in respect
to the Burgersfort Package, and they also agreed on an allocation

arrangement in terms of which Group Five would submit a
non-competitive bid In respect of the Burgersfort Package to enable
Stefanutti to win the tender, and that Group Five would win the
Thabazimbi project In line with.the collusive agreement, Group
Five
was swarded.the tender for the Thabazimbi Package, and Stefanutti
was awarded, the tender for the Burgersfort Package. This
conduct is
collusive tendering in contravention of section 4(1)(b)(iii) of the
Act
This
project was for the construction of housing units for Anglo Platinum
mine.
6.8.
Niccl
Apartments
(Tender
Ref No: BJ1138)
Stefanutti
reached agreement with Vlaming, G Liviero, Guiridch and Bartlett
Construction on or about 2006 in that they agreed
on a cover price
in respect of this project. In tenns of the agreement, Stefanutti, G
Liviero, Guiridch and Bartlett Construction
received a cover price
from Vlaming to ensure that they would submit non-competitive bids
so that Vlaming would win the Project.
Vlaming was awarded the
tender in line with the Collusive agreement. This conduct is
collusive tendering in contravention of
section 4(1)(b)(m) of the
Act
This
project was for the construction of a high rise building comprising
of SO residential apartments for Precoated Metals (Pty)
Ltd. The
project was completed on 03 October
2008.
6.9.
Oilfantspoort Water Reticulation Works Contract
(Tender
Ref No: Q171-07)
Stefanutti
reached agreement with Group Five on or about 2008 in that they
agreed on a cover price in respect
of
this project in terms of the agreement, Stefanutti received a cover
price from Group Five to ensure that Stefanutti would submit
a
non-competitive bid to enable Group Five to win the Project Group
Five was awarded the tender in line with the collusive agreement,

This conduct is collusive tendering in contravention of section 4(1
)(b)(iii)
of
the Act.
This
project was the installation and commissioning of raw water rising
main, sedimentation units, gravity filter units, contact
tank and
plant for chlorine production. The contract for this project also
included the construction of various buildings and
lagoon as well as
various pipe and valve work at Olifantspoort water purification
works and associated engineer pump stations.
The client for the
project was Lepelele Northern Water. The
p
roje
ct
was
completed on October
2009.
6.10.
Goedgevonden Crushing Project
(tender
Ref No: 6447-RLS-OGE100-C108)
Stefanutti
reached agreement with Grinaker LTA on or about 2007 in that they
agreed on a cover price in respect of this project
in terms of the
agreement Stefanutti provided a cover price to Grinaker LTA to
ensure that Grinaker LTA would submit a non-competitive
bid to
enable Grinaker LTA to win the tender, since Stefanutti did not want
to win it The agreement was also that Grinaker would
add a margin in
the amount of R1 million to its tender price, so that it would later
pay Stefanutti a compensation fee in that
amount
This
project was for the development of land for a crushing quarry for a
rail loop for Xstrata, Xstrata however decided not to
continue with
this project, as a result the payment to Stefanutti was not made.
7.
Admission
Stefanutti
admits that it entered into the agreements detailed in paragraphs 5
and 6
above
with its competitors in contravention of section 4(1)(b)(iii) of the
Act.
8.
Co-operation
In
so far
as
the Commission is aware and in compliance with the requirements as
set out in the Invitation, Stefanutti;
8.1.
has provided the-Commission with truthful and timely disclosure,
including information and documents in its possession or
under its
control,
relating to the prohibited practices;
8.2.
has provided full and expeditious co-operation to the Commission
c
once
rning
the pr
ohibited
pra
c
ti
c
e
s
;
8.3.
has provided a written undertaking that it has immediately ceased to
engage in, and will not in the future engage in, any
form of
prohibited
practice;
8.4.
has confirmed that it has not destroyed, falsified or concealed
information, evidence and documents relating to the prohibited

practices;
8.5.
has confirmed that it has not misrepresented or made a wiifui or
negligent misrepresentation concerning the material facts
of any
prohibited practice or otherwise acted dishonestly.
9.
Agree
ment
Concerning Future Conduct
8.1.
In compliance with the
requirements
as
set out in the Invitation, Stefanutti agrees and undertakes to
provide the
Commission
with
full
and
expeditious co-operation from the time
that
this
Consent
Agreement
is
concluded
until
the
subsequent
proceedings
In
the
Competition Tribunal or the Competition Appeal Court are completed.
This includes, but is not limited to;
9.1.1.
to the extent that it is in existence and has not yet been provided,
providing (further) evidence, written or otherwise,
which is in its
possession or under its control, concerning the contraventions
contained
in this Consent Agreement;
9.1.2.
Stefanutti will avail its employees and former employees to testify
as witnesses for the Commission in any cases regarding
the
contraventions contained in this Consent Agreement;
9.2.
Stefanutti
shall
submit
a
copy
of the competition law compliance programme it
has
developed
to the Commission within 60 days of the date of confirmation of the
Consent Agreement as an order by the Competition
Tribunal.
Stefanutti confirms that its compliance agreement incorporates
corporate governance to ensure that its
empl
oyees
,
mana
gement
directors and agents do not engage in future
contraventions
of the Act. Stefanutti also confirms that its compliance programme
indudes mechanisms for the monitoring and detection-of-any

contravention of the Act.
9.3.
Stefanutti shall circulate a statement summarising the contents of
this Consent Agreement to aii management and operational
staff
employed at Stefanutti within 60 days from the date of confirmation
of this Consent Agreement by the Tribunal.
9.4.
Stefanutti
will not in the future engage in any form of prohibited conduct and
will not engage in collusive tendering which wiil
distort the
outcome of tender processes but undertakes henceforth to engage in
competitive bidding.
10.
Administrative Penalty
10.1.
Having regard to the provisions of sections 58(1)(a)(iii) as read
with sections 59(1)(a)
,
59(2) and 59(3) of the Act, and as envisaged in paragraph 10.2 read
with paragraphs 19-28 of the Invitation, Stefanutti accepts
that it
is liable to
pay
an administrative penalty (“penalty”).
10.2.
According to the Invitation, the level of the penalty is to be set
on the basis of a percentage of the annual turnover of
Stefanutti in
the relevant subsector in
the
Republic and Its exports from the Republic for the financial year
preceding the date of the Invitation.
10.3.
The projects which Stefanutti has been found to have contravened the
Act, fall under the Civil Engineering and General Building
GfDB
sub-sectors.
10.4.
Accordingly, Stefanutti is liable'for and has'agreed to pay an
administrative penalty in the sum of R 306 892 664 which
penalty is
calculated in accordance with the Invitation. In addition,
Stefanutti will pay an interest of
10%
per annum on the fourth payment as reflected in the payment terms.
11.
Terms of payment
11.1.
Stefanittu will pay the amount and interest set out abouve [in
paragraph 10.4]
to
the Commission in four payments over three years, the first such
payment of R 68 964 000 within 30 days from the date of confirmation

of this Consent Agreement as an order of the Tribunal.
11.2.
Stefanutti will make the second payment of R 68 954 000, exactly one
year from the date of the previous payment and the
third payment of
R 68 964 664 exactly one year from the date of the second payment.
11.3.
Stefanutti will make the fourth payment of R 100 000 000 plus 10%
per annum interest on the latter amount, which is a total
of R 110
000 000, exactly one year after the third payment.
11.4.
This payment shall bo made into the Commission's bank account,
details of which are as follows:
Bank
name: Absa Bank
Branch
name: Pretoria
Account
holder Competition Commission Fees Account
Account
number: 4050778576
Account
type: Current Account
Brach
Code: 323 345
11.5.
The penalty
will
be
paid over by the Commission to the National Revenue Fund in
accordance with section 59(4) of the Act.
12.
Full and Final Settlement
This
agreement is entered into in full and final settlement of the
specific conduct listed In paragraphs 5 and S of this consent

agreement and, upon confirmation as an order by the Tribunal,
concludes ali proceedings between the Commission and Stefanutti
in
respect of this conduct only.
Dated
and signed at KEMPTON PARK on the 21
st
day of JUNE 2013
For
Stefanittu
Dated
and signed at PRETORIA on the 21
st
day of JUNE 2013
For
the Commission
Shan
Ramburuth
Commissioner