Orion Cellular (Proprietary) Limited and Telkom South Africa Limited / Standard Bank of South Africa Limited / Edgars Consolidated Stores Limited (19/IR/Apr03) [2004] ZACT 18; [2004] 1 CPLR 198 (CT) (24 February 2004)

70 Reportability
Competition Law

Brief Summary

Competition Law — Confidential Information — Access to confidential agreements — Orion Cellular sought access to agreements between Telkom and its customers, Standard Bank and Edcon, alleging predatory conduct by Telkom — Tribunal to determine confidentiality of agreements under the Competition Act — Held, agreements were not confidential and Orion entitled to access them to prepare its case.

CompTribOrion001 
COMPETITION TRIBUNAL
REPUBLIC OF SOUTH AFRICA 
Case no.19/R/April 2003
In the matter between:
Orion Cellular (Proprietary) Limited            First Applicant
and
Telkom  South Africa Limited  First Respondent
The Standard Bank of South Africa Limited Second Respondent
Edgars Consolidated Stores Limited    Third Respondent
            DECISION
Introduction 
This case deals with the protection given to confidential information under the  
Competition Act, and with circumstances in which the Tribunal may order that  
access to a firm’s confidential information be provided to a competitor.
Following a hearing on 15 December 2003, an order in the matter was issued  
on 23 December 2003. The reasons for the order follow.
Factual background
Two applications with overlapping subject­matter which were heard on 15  
December 2003 are to be decided. The parties to them are identical. The  
applicant, Orion Cellular (Pty) Ltd (“Orion”), is a company which provides  
services to users of telephone systems, and in particular provides a least­cost  
routing system for cellular­to­cellular telephone calls. The first respondent is  
Telkom SA Limited (“Telkom”), a listed company which has a statutory  
monopoly in landline telephone communications in South Africa.  The second  
respondent is The Standard Bank of SA Limited (“Standard Bank”), the  
banking arm of a listed financial services group. The third respondent is  
Edgars Consolidated Stores Limited (“Edcon”), a listed retail group.

The applications are interlocutory applications in a proceeding (“the main  
application”) which Orion has brought before the Tribunal for interim relief  
while a complaint brought by Orion against Telkom before the Competition  
Commission is being investigated. In the main application, Orion alleges, in  
effect, that Telkom is engaging in a campaign of predatory activities of which  
Orion is the victim. Orion alleges that Telkom negotiated with two of Orion’s  
customers, Standard Bank and Edcon, and entered into agreements with both  
of them which undercut Orion and induced them to choose Telkom over  
Orion. A prime part of the alleged inducement was discounts provided by  
Telkom for its services. Orion alleges that the conduct of Telkom in concluding  
these agreements amounted to contraventions of ss. 8(d)(i) or 8(c) or 8(d)(iv)  
and/or 9 of the Competition Act, 1998, as amended (“the Act”).
In the first application (“the production application”), dated 17 September  
2003, Orion sought an order compelling the respondents to produce all signed  
and unsigned agreements between them in respect of the services provided  
by Telkom relating to the subject­matter of the main application.
In the second application (“the s. 45 application”), dated 14 November 2003,  
Orion claimed an order in terms of s. 45 of the Act directing that a so­called  
“volume and term voice discount plan agreement” dated 13 March 2003  
between Telkom and Standard Bank, and a “volume and term voice discount  
plan agreement” between Telkom and Edcon dated 15 July 2003, be made  
available to Orion, and that it be declared that the information contained in  
these agreements is not confidential. These are in effect the same  
agreements as those referred to in the production application. 
From the evidence it is clear that, when it filed the main application, Orion and  
its attorneys had not seen these agreements. By the time the production  
application was filed, Orion’s attorneys (but not anybody at Orion) had been

application was filed, Orion’s attorneys (but not anybody at Orion) had been  
allowed by Telkom to inspect the agreement with Standard Bank, but subject  
to conditions which prevented the attorneys from making copies of the  
agreement or extracts from it, and also preventing them from disclosing the  
contents of the agreement to their client or its external consultants.
The   attorneys   who   inspected   the   agreement,   Messrs   Stein   and   Scop,  
considered that the agreement was not confidential but that it and the Edcon  
agreement, which had been concluded later, were pivotal to Orion’s case in  
the main application, and that it was essential that Orion be enabled to inspect  
them in order to prepare its replying evidence in the main application. Telkom  
had   denied   in   its   answering   evidence   in   the   main   application   that   the  
conclusion of the agreements had been illegal, and there was thus a basic  
dispute about their effect, and this question would have to be taken further in  
the replying evidence. 
The two interlocutory applications were opposed by Telkom, which filed  
affidavits setting out its attitude towards them. The applications were not  
2

opposed by Standard Bank and Edcon, but both those companies submitted  
letters to the Tribunal stating that, while they would abide by the Tribunal’s  
decision, they regarded the agreements as confidential.
Copies of the agreements were made available to the Tribunal by Telkom  
when it filed its answering evidence in the production application, under cover  
of a Form CC7 claiming confidentiality for them in terms of s. 44 of the Act. 
The Form CC7 stated that confidentiality was claimed in respect of the whole  
of both agreements and, in each case, an annexure to the agreement. The  
firm owning the relevant information was said to be Telkom and its customer  
(Standard Bank in the case of one agreement and Edcon in the case of the  
other). The forms stated further in the relevant place that the nature of the  
economic value associated with the confidential information was that “such  
information is of a sensitive commercial nature and has economic value.  
Should the information be divulged to unauthorised parties, it would seriously  
prejudice the interests of the parties and their shareholders.”
In   making   the   agreements   available   for   inspection   by   Orion’s   attorneys   on  the   conditions  
outlined   above,   Telkom   maintained   that   it   was   abiding   by   the   principles   set   out   by   the  
Competition Appeal Court in  The Competition Commission of South Africa and Unilever  
PLC and others   (case no. 13/CACJan02) . In that case a merger was under consideration by  
the Tribunal and access to the record supplied by the Commission to the Tribunal was sought  
by the parties to the merger after the Commission had recommended conditional approval of  
the merger and had withheld from the parties certain information on which it had relied in  
formulating its recommendation. The parties to the merger wanted access in order to consider  
whether to challenge claims that the withheld information was confidential. The Competition

whether to challenge claims that the withheld information was confidential. The Competition  
Appeal Court ruled that access should be provided to the parties’ legal representatives at the  
offices of the Commission, that the legal representatives were not entitled to reproduce the  
record, and that the legal representatives were to give undertakings of confidentiality to the  
Commission before having sight of the record.
This case is not the only litigation between the parties. We were informed at  
the hearing that in a High Court case heard in the Transvaal Provincial  
Division earlier in 2003, in which a decision had been issued some weeks  
before the hearing in this matter, Telkom alleged that Orion had acted  
unlawfully in providing to certain corporate customers a system having the  
capacity to route cellular­to­cellular (“CTC”) calls from a customer’s  
switchboard directly into the cellular network, thereby bypassing Telkom and  
hence depriving Telkom of some of its revenue. It appears that the High Court  
has ruled largely in favour of Orion. Its decision is, however, being taken on  
appeal by Telkom.
The two applications before the Tribunal were argued together and since the  
relief sought in them is in practice identical they are treated in the Tribunal’s  
order and in this decision as one matter. 
The questions posed to the Tribunal by both applications are whether the  
Standard Bank agreement and the Edcon agreement are confidential, and  
whether they are to be made available to Orion and others, conditionally or  
3

otherwise.
We point out at the outset that the  Unilever decision cited above takes a dispute about the  
confidentiality of information under consideration by the Commission or Tribunal only to the  
point where a potential litigant is enabled to make a decision whether  there is a basis to  
challenge a claim to confidentiality of the information. Once that party’s legal representatives  
have inspected the allegedly confidential document and on their advice their client proceeds  
with the challenge, the matter  reaches another plane, and the rules in the   Unilever  case  
reach their ambital limit. Other considerations then apply.
Telkom also made a claim to confidentiality, supported by a Form CC7, in  
respect of paragraph 17 of its answering affidavit in the s. 45 application. A  
copy  of   this   paragraph  was  supplied  to   the  Tribunal   but   not  to   Orion.   The  
claim   to   confidentiality   in   the   Form   CC7   contained   the   assertion   that   the  
information   in   that   paragraph   was   owned   by   Telkom.   The   nature   of   the  
economic value of the relevant information was stated in the same wording  
as in the Form CC7 relating to the agreements which Telkom entered into with  
Standard Bank and Edcon. That wording is set out above.
Regrettably,   the   status   of   paragraph   17   was   not   argued   by   the   parties’  
counsel on 15 December 2003, and the claim to confidentiality in regard to it  
was   accordingly   left   in   limbo.   In   order   to   preserve   any   justification   which  
Telkom may have for it, a ruling that paragraph 17 should provisionally be  
treated   as   confidential,   but   subject   to   restricted   access   by   Orion   and   its  
advisors, was included in the order made on 23 December 2003.
Relevant statutory provisions 
Confidential information is defined in s. 1 of the Act as:
“trade,   business   or   industrial   information   that   belongs   to   a   firm,   has   a   particular

economic value, and is not generally available to or known by others ”. 
S. 44 provides that a person who submits information to the Commission or  
the Tribunal, may identify information as confidential.  Such a claim must be  
supported by a written statement explaining why the information is considered  
to be confidential. Form CC7 has been prescribed for this purpose.
In terms of s. 44(3), the Tribunal may determine whether or not the  
information is confidential, and if it finds that the information is confidential,  
may make any appropriate order concerning access to that information.
A person seeking such a determination may in terms of s. 45(1) apply to the  
Tribunal in the prescribed manner and form for the determination. Rule 42 of  
the rules for the Conduct of Proceedings in the Competition Tribunal (“the  
Tribunal’s rules”) lays down the procedure for such an application, namely the  
filing of a notice of motion and supporting affidavit. Until a final determination  
has been made concerning the status of the information, the Tribunal must, in  
4

terms of s. 45(3) of the Act, treat the information as confidential.
Telkom made much in the proceedings of rules 21 and 28 of the Tribunal’s rules. Rule 21  
deals generally with the convening of pre­hearing conferences for matters which are to be  
heard by the Tribunal, and their subject­matter. Rule 22 sets out powers which the presiding  
Tribunal member at a pre­hearing conference may exercise. These include, under sub­rule  
22(1))(c)(v),   the   power   to   give   directions   regarding   the   production   and   discovery   of  
documents whether formal or  informal. Rule 28 states that rules 21 and 22 ( inter alia ) apply to  
pre­hearing procedures in cases of interim relief applications. 
 
Reference should also be made to s. 27(1)(d) of the Act, which empowers the  
Tribunal to make any ruling or order necessary or incidental to the  
performance of its functions in terms of the Act.
The parties’ submissions at the hearing
Orion was represented at the hearing on 15 December 2003 by Messrs Kuper  
and Bhana. Mr Kuper made it clear at the outset that he and Mr Bhana had  
not seen the agreements in contention, and were not prepared to enter into  
any undertaking which paved the way for them to read the agreements but  
which prevented them from discussing the contents of the agreements with  
their client. They felt that this arrangement would place them in an invidious  
position   and   would   clash   with   their   duty   to   render   advice   to   their   client.  
Telkom’s counsel, Mr Unterhalter, insisted that such undertakings be provided  
if Messrs Kuper and Bhana were to read the agreements. Mr Kuper said that  
if Telkom’s requirement was upheld, he and Mr Bhana would not make the  
undertakings   and   would   be   forced   to   withdraw   from   the   hearing   while   the  
contents of the agreements were under consideration.
This issue was debated for some time. The Tribunal made it clear that it would  
prefer to have Messrs Kuper and Bhana present throughout the hearing, and

prefer to have Messrs Kuper and Bhana present throughout the hearing, and  
also made it clear that it expected Mr Unterhalter to take the Tribunal through  
an analysis of the agreements in order to point out why Telkom considered  
them to be confidential.
At the point when the contents of the agreement were about to be considered  
in this context, Mr Kuper announced that he and Mr Bhana had reconsidered  
the matter and were now prepared to make the   undertakings which Telkom  
had insisted upon. Mr Unterhalter accepted their oral undertakings on behalf  
of Telkom. The hearing then proceeded on the basis that Orion’s counsel and  
attorneys, but not directors or other officials of Orion, nor any members of the  
public, would be present while Telkom’s counsel made his analysis of the  
agreements and submissions regarding them. Representatives of Standard  
Bank and Edcon remained in the hearing room, or were admitted to it, only  
while the agreements applicable to their respective companies were under  
discussion.
5

Mr Unterhalter announced that Telkom was revising its position on the  
contents of the agreements and would now not claim any confidentiality in the  
body of the agreements. The only confidentiality which Telkom would now  
claim lay in certain numerical data in an annexure  to each of the agreements.  
He handed in copies of the annexures in which these data had been blocked  
out. He conceded that, in regard to one item of blocked­out data, namely the  
dates of commencement of the agreements, there was no confidentiality, but  
he persisted with the confidentiality claims in respect of the remaining  
blocked­out data. He asserted that the agreements represented the outcome  
of commercial negotiations that differed from customer to customer and led to  
different outcomes and hence different data. 
The subject of discounts in an industry such as telecommunications in South  
Africa was, he said, inherently non­transparent. Tariffs might be set by a  
regulatory body, specifying maximum charges, but, he asserted, this did not  
oblige Telkom to disclose the nature and magnitude of discounts from those  
maxima which it might give to any of its customers. Any discounts given in  
such an industry must be regarded, he contended, as confidential. The  
“particular economic value” associated with this information, within the  
definition of confidential information in the Act, lay in the fact that the data  
reflected specially negotiated regimes with particular customers, achieving a  
competitive advantage which enabled Telkom to procure the customer at the  
expense of a competitor. The information was the basis on which a participant  
in the industry such as Telkom secured business in a competitive market.
Price­sensitive negotiations, said Mr Unterhalter, are specifically held in  
confidence for the purpose of determining the level at which a participant is  
willing to make an offering to induce a customer to switch suppliers. Once this

willing to make an offering to induce a customer to switch suppliers. Once this  
information is made known, it offers all other participants the opportunity to  
enter the picture and undercut the incumbent. Its value was ultimately that  
“you win the business, nothing more and nothing less.” There was nothing to  
prevent Orion, once it knew this “base price” from approaching Standard Bank  
and Edcon and soliciting their business by offering them suitably pitched  
alternative offerings. The same would apply to other competitors of Telkom  
such as Nashua, Autopage, M­Tel and Vodacom, which had a collective  
turnover of about R1.2 billion and hence represented a real competitive threat  
to Telkom.
Mr Unterhalter emphasised that the data in the two agreements were to some  
extent different, reflecting the different sizes of the periodical payments made  
by Standard Bank and Edcon for Telkom’s telephone services, and also the  
give­and­take of the negotiations. He asserted that the allegedly confidential  
information “belonged” (in the phraseology of the definition in s. 1 of the Act)  
to both Telkom and its customer, Standard Bank or Edcon. He rejected the  
suggestion put to him by the Tribunal that there is little inherent confidentiality  
in the size of a firm’s telephone account or, if there is such confidentiality, that  
6

it belongs solely to the customer and not to Telkom. He claimed that  
information regarding the volume of business transacted with Telkom by  
Standard Bank and Edcon, and the projections for future volume set out in the  
agreements, had been “procured” or calculated by Telkom, and was “vital” to  
Telkom’s assessment of these customers’ businesses and the way in which  
Telkom had structured its own business.  
He referred to several High Court decisions in the field of delictual unlawful  
competition and other fields in which information had been found to be  
confidential.
Apart from asserting the confidentiality of the information in contention, Mr  
Unterhalter went on to allege that Orion had in effect mistaken its remedy, and  
that it should have called upon Telkom to make the contested information  
available to an independent expert, such as an accountant, acting on Orion’s  
behalf, who could have entered into a confidentiality undertaking with Telkom  
to use the information for the purposes of the main application and for no  
other purpose. The expert would be entitled to share the information with legal  
representatives of Orion who had made similar undertakings. This procedure,  
he asserted, would have been acceptable to Telkom and would have made it  
unnecessary for Orion’s directors and other personnel to have access to the  
relevant information at any stage. The experts and Orion’s legal  
representatives could between them have drawn up such papers as were  
necessary for Orion’s case.
Orion had failed entirely, Mr Unterhalter contended, to provide evidence in its  
founding papers in the main application about predatory pricing. Even if Orion  
were permitted access to the agreements with Standard Bank and Edcon, that  
would not enable Orion to cure the lack of crucial information in the main  
application since the agreements would not disclose to Orion any information  
about Telkom’s cost structures and, in particular, its average variable costs.

about Telkom’s cost structures and, in particular, its average variable costs.  
Without setting out this information and demonstrating its relationship to  
Telkom’s charges to its customers, Orion would, he asserted, be unable to  
make out a case of predation.
Had Orion taken the route of requesting access to the agreements by an  
independent expert on the basis outlined above, Orion could have awaited the  
expert’s reports after scrutinising the agreements, and her or his  
recommendations on how to proceed with Orion’s case. Only if the expert was  
“stumped” and found it essential to exchange ideas with Orion’s officials,  
would it have been permissible and timely to bring an application to the  
Tribunal seeking leave for Orion’s officials to have access to the agreements.  
This, he contended, would have been the logical route for Orion to follow after  
there had been compliance with the rules set out in the  Unilever decision.  
Telkom accepted that to date there had been compliance with those rules.
7

Referring to the Tribunal’s rules 21 and 28, Mr Unterhalter contended that the  
production application and the s 45 application were premature. Orion should,  
he asserted, have completed its evidence in the main application and then  
ensured that a pre­hearing conference was held in terms of the Tribunal’s  
rules at which to press for access to the agreements in contention on the  
basis of the presiding Tribunal member’s powers to grant discovery. Until  
then, its case was “unripe”. In motion proceedings, in the absence of  
exceptional circumstances, he contended, the kind of discovery sought by  
Orion was not permissible since its goal was to enable Orion to make out its  
original case. That case should have been made out in Orion’s founding  
papers. If Orion were now permitted access to the agreements, the evidential  
basis for its case would emerge only in its replying affidavits, and the courts  
had become irritated with this trend and had “declared war” on “unnecessarily  
prolix” replying affidavits. He referred in this regard to the case of  Minister of  
Environmental Affairs and Tourism and Others v Phambili Fisheries  
(Pty) Ltd and Another         [2003] 2 All S.A. 616 (SCA) at 641 para. 80.
Mr Kuper’s approach, on behalf of Orion, was that Telkom was unjustifiably  
resisting access to its agreements with Standard Bank and Edcon and then, in  
the name of confidentiality, making a virtue of that denial of access. In its  
evidence Telkom steadfastly averred that Orion was a “pirate” and was  
operating illegally – a contention which was under debate in the High Court  
proceedings and in which the first round of the litigation had gone in favour of  
Orion.
The documents to which Orion requested access could now be limited, Mr  
Kuper said, to Telkom’s signed agreements with Standard Bank and Edcon  
since it had emerged that signed agreements were now in existence.
Telkom’s argument about the alleged prematurity of the production application

Telkom’s argument about the alleged prematurity of the production application  
and the section 45 application was denied by Mr Kuper. It would be  
“purposeless” for Orion to file replying evidence in the main application  
without having inspected the agreements in contention, and only then pick up  
the cudgels to obtain access to those documents.
Telkom’s original stance, as set out in its affidavits, that only Orion’s legal  
representatives, and not any officials of Orion, should have access to the  
agreements, and that the case should be completed and heard by the  
Tribunal on that basis, would, Mr Kuper submitted, be “a travesty of a right to  
fair process.”
The proposition advanced on behalf of Telkom at the hearing that Orion had  
mistakenly sought access on its own behalf to the agreement, instead of  
access by an independent expert, was untenable, Mr Kuper argued. What  
would be the position if it emerged that the only true experts were officials o f 
Orion or of another competitor of Telkom? It was possible that the  
8

complexities of determining average variable costs of Telkom and other  
necessary features of Orion’s case of predation would be above the capacity  
of an ordinary accountant or similar witness as had been posited by Telkom,  
and Orion would then again be unable to present its case properly.
In the circumstances where Orion’s attorneys had been permitted by Telkom  
to read the agreements but not take copies or extracts, nor to discuss the  
contents with Orion’s officials, it would be impossible for those legal  
representatives to give meaningful advice to Orion. They would be hamstrung  
at every turn by their obligations of confidentiality when it came to the practical  
business of preparing evidence. This would lead to a denial to Orion of its  
constitutional and other rights to fair process.
In regard to the position of Standard Bank and Edcon in the litigation, Mr  
Kuper considered that it was clear that they were not seeking to impose any  
rights in regard to the allegedly confidential information in their agreements  
with Telkom, and it could be inferred that they did not attach significant  
importance to that information, being content to abide by any ruling the  
Tribunal saw fit to make.
The concessions made by Telkom at the hearing about the extent of the  
confidential information, by limiting its claims to the blocked­out numerals in  
the annexures, was so large a backdown on its original stance, that Orion was  
now, at the eleventh   hour, dealing with an entirely different case from the one  
which had confronted it at the outset, Mr Kuper said. Had this been Telkom’s  
stance originally, Orion’s evidence in the matter would have been very  
different. 
Mr Kuper considered that the case for claiming confidentiality in the blocked­
out dat a referred to above had been overstated by Telkom, but he was not  
averse to some restrictions on access to that information if the Tribunal found  
confidentiality to exist, provided Orion was left free to pursue its case

confidentiality to exist, provided Orion was left free to pursue its case  
effectively and make use of the advice of the best consultants available to it,  
whether inside or outside its organsation. He contended that such restrictions  
would be easy for Telkom to monitor or “police”. He submitted that precedents  
about the nature of confidential information from the realms of delictual  
unlawful competition and other branches of the law outside the ambit of the  
Act were inapplicable in view of the very precise definition of confidential  
information in the Act, and he emphasised that the test of confidentiality  
involved not only “economic value” but the more stringent criterion of  
“particular economic value”. 
Tribunal’s approach to the issue of confidentiality and its rulings on that  
issue 
9

The Tribunal considers that the panel dealing with the main application will,  
after hearing what will be extensive evidence about the nature and  
commercial importance of the various elements of the discount “packages”  
provided by Telkom to Standard Bank and Edcon in terms of the agreements  
in contention, be in a better position than the current panel to make a final and  
definitive statement about the correctness of Telkom’s claims to the  
confidentiality of the blocked­out data in the annexures to the agreements  
handed in at the hearing.
Accordingly the Tribunal at this stage made only an interim finding and ruling,  
which it considers will conveniently reconcile the interests of the parties while  
meeting the needs of equity and fairness. 
Thus, for this limited purpose, the Tribunal’s order provides that the only  
information which Telkom ultimately claimed as confidential, namely the  
blocked­out data in the annexures to its agreements with Standard Bank and  
Edcon (excluding dates of commencement) is provisionally to be treated as  
confidential.
This ruling should not be taken as an indication of sympathy on the Tribunal’s  
part with the arguments advanced by Telkom for such confidentiality. On the  
contrary, we consider that the matter will best be considered afresh and with  
an open mind when the main application is heard.
While this ruling is to some extent adverse to Orion, which argued that the  
information in question was not confidential, we consider that the potential  
harm to Orion if it is ultimately found by the Tribunal that the blocked­out  
information is not confidential, is fully mitigated by our order on the question of  
access to the information in the interim. Orion has in any case succeeded in  
having the ambit of the confidentiality reduced, from Telkom’s original claims  
to the whole of the agreements, to a few numerical parameters in the  
annexures. 
Equally, if the Tribunal finally concludes, having heard the main application,

annexures. 
Equally, if the Tribunal finally concludes, having heard the main application,  
that Telkom’s claim to confidentiality is sound, our order on the issue of  
confidentiality will have preserved Telkom’s rights up to that point except in  
the limited manner explained in the next section of this decision.
Conclusions and rulings on the issue of access to information which is  
to be treated as confidential
What   is   clear   to   us   is   that   basic   justice   will   not   be   served   if   Orion   is   not  
enabled to study the blocked­out data in the agreements in issue, using its  
own directors and other personnel if they are the people best able to advise it,  
and   also   using   any   independent   external   experts   if   their   evidence   should  
10

prove necessary. 
Orion has presented a case which, if it is upheld when the main application is  
decided, will mean that Telkom has committed a serious contravention of the  
Act. We have heard and read nothing to suggest that Orion is making its  
accusations frivolously or speculatively. Its evidence on the financial details of  
the allegations of predation is indeed sketchy, but in the face of the kind of  
opposition which Telkom mounted in the applications before us, conceding  
access to the body of the agreements only at the eleventh hour, it is clear that  
Telkom has made strenuous efforts to prevent Orion from finding the kind of  
information it would have needed to mount a fully documented case at the  
outset. We say so while not prejudging the main application in any way. If  
Telkom is correct and the case Orion has brought on its papers in the main  
application is defective and is not cured in Orion’s replying evidence, then  
Orion must at that stage suffer the consequences. We are only concerned  
with the interim issue of access to documents.
The argument which Telkom has now for the first time advanced, that Orion  
should have nominated an independent expert to inspect the agreements in  
contention but not reveal their contents to Orion, and then to conduct the case  
for Orion with legal representatives of Orion similarly equipped with  
information about the agreements which they are not entitled to disclose to  
their client, has in our view been successfully demolished by Mr Kuper. It is  
Kafkaesque in its distance from fairness and openness.
In any case, if Telkom was willing to subject its agreement to scrutiny by an  
independent expert acting for Orion, why has this willingness emerged only on  
the date of the hearing and at the stage of argument? Why was the sanctity of  
the entire contents of the agreements claimed by Telkom in its Form CC7 but  
abandoned in respect of all but a few items of numerical data at the very last

abandoned in respect of all but a few items of numerical data at the very last  
moment, namely when Telkom had to address oral argument to the Tribunal  
on its claims to that confidentiality? These facts suggest to us that there might  
be some substance in Orion’s arguments that Telkom is obfuscating the  
issues of access to information, with obvious benefits to itself in terms of delay  
and corresponding inconvenience and even danger to the viability of Orion.  
We make no finding in this regard.
Similar considerations apply to Telkom’s arguments that Orion’s applications  
are premature, and that the appropriate time to seek access to the  
agreements would have been after Orion had filed its replying evidence and  
could use rules 22 and 28 of the Tribunal’s rules to seek a ruling at a pre­
hearing conference giving it discovery of the agreements. It takes little  
imagination to see that at that stage Telkom would plausibly have argued that  
discovery was irrelevant and should not be granted because Orion’s evidence  
had been completed. The threat to Orion’s prospects at that stage of  
mounting a successful case of predation based on the contents of the  
11

agreements would be terminal.
We do not consider it necessary to venture any conclusion regarding  
Telkom’s allegations that it has no case to meet in the main application on the  
basis of lack of relevant averments and defective evidence by Orion, and the  
argument that Orion should not be allowed to make out its case in its replying  
evidence. If Telkom is correct about these allegations, it will have its way  
when the main application is decided.
Mr Kuper was quick to point out that it would have been easy for Telkom, if  
there was no targeting of Orion and no illegal deep discounting, to produce  
evidence to say that its discount packages had been provided to customers  
other than those it had in common with Orion and that the depth of the  
discounts was such that nobody could regard them as predatory. We have not  
taken any such factors into account in reaching our conclusions since they are  
relevant to the main application and not to the interlocutory applications  
before us.
It would, of course, be wholly unacceptable for the Tribunal to fail to come to  
the assistance of a firm which is the victim of true predatory pricing practices  
by paying excessive regard to claims for confidentiality in any documents, let  
alone the very documents which form the basis for the complaint of predation.  
If it allows itself to be mesmerised by claims of confidentiality in those  
circumstances, the Tribunal would be delaying remedies and providing  
mechanisms for the predator to cover it traces, and it would effectively be  
playing the role of an accomplice. This consideration is relevant in this case,  
but the Tribunal has balanced it by giving careful attention to Telkom’s  
interests at this stage and to the need to refrain from pre­judging the merits of  
the main application. 
The order we have made provides for Orion’s personnel and legal  
representatives, and any outside experts which Orion selects, to have access

representatives, and any outside experts which Orion selects, to have access  
to the data to which Telkom claims confidentiality, but on strict terms. These  
include the terms that the individuals concerned make written undertakings of  
confidentiality, and that they use the information only for the purposes of the  
main application and any further interlocutory litigation which may be  
necessary in the course of bringing the main application to finality. Telkom is  
to be provided with the names of all the individuals concerned. We consider  
that the strictness of these terms is adequate for the protection of Telkom’s  
interests.
The order also provides that if Orion or other firms having an interest in the  
subject­matter choose to approach the Tribunal to obtain less onerous  
conditions for access to the allegedly confidential information, they may do so.  
We see no need for Telkom to have a reciprocal right to approach the  
Tribunal for a variation which sets more onerous terms: once the existing  
12

terms have been exercised by Orion, it would be inequitable or in practice  
impossible to reduce its corresponding rights.
Orion’s attorneys are, on the evidence, subject to written undertakings of  
confidentiality in favour of Telkom which were drawn and imposed by Telkom  
and which prohibit the attorneys from disclosing the contents of those  
agreements to Orion and its officials, its counsel, and Orion’s outside  
witnesses and consultants. It would be inconsistent for these undertakings to  
be maintained in the face of our order. Our order therefore includes provision  
for those undertakings to be superseded by the confidentiality regime set out  
in the order, which will naturally bind the same attorneys.  
The information to which the order extends includes paragraph 17 of Telkom’s  
answering affidavit in the section 45 application. Our reading of that  
paragraph suggests to us that nothing in it is truly confidential, but in the  
absence of the parties’ submissions on it we have in Telkom’s favour  
assumed that confidentiality may exist. Orion’s interest in that information is  
safeguarded by the access which our order provides, but the access is  
subject to limitations. We doubt whether Orion will in practice suffer any  
deprivation by viewing the relevant paragraph subject to this regimen.
We have made a single order since it appears to us that the relief in both  
applications should be identical, even if the basis for granting it may be  
formally different. If the production application alone had been heard, we  
consider that we could by the exercise of our residual powers under section  
27 of the Act, if not under the Tribunal’s statutory powers to direct discovery,  
have made the relevant order. Telkom’s argument that that the production  
application was premature is in our view, as mentioned above, incorrect. S.  
45(1) (b) of the Act provides the basis for our findings and orders to the extent  
that they correspond to Orion’s claims in the s. 45 application.
Costs

that they correspond to Orion’s claims in the s. 45 application.
Costs
As Orion has substantially succeeded in both applications, our order provides  
that Telkom should pay Orion’s costs, including those of three legal  
representatives.
                                24 February 2004
M. Moerane Date
  
Concurring: L. Reyburn, T. Orleyn
13