ISCOR Limited and Saldanha Steel (Pty) Ltd (67/LM/Dec01) [2002] ZACT 17 (4 April 2002)

62 Reportability
Competition Law

Brief Summary

Merger Control — Approval of merger — Iscor Limited's acquisition of Industrial Development Corporation's share in Saldanha Steel (Pty) Ltd — Merger assessed under section 12A of the Competition Act — Saldanha classified as a failing firm — Approval granted with conditions despite differing views on competitive impact — Commission's concerns about supply conditions to downstream customers addressed through imposed conditions — Merger deemed necessary to prevent closure of Saldanha plant, with significant public interest implications.

COMPETITION TRIBUNAL 
REPUBLIC OF SOUTH AFRICA
      Case No: 67/LM/Dec01
In the large merger between: 
Iscor Limited 
and
Saldanha Steel (Pty) Ltd
_______________________________________________________________
Reasons for decision
_______________________________________________________________
Decision
1. The   Industrial   Development   Corporation   of   South   Africa   Limited   (‘IDC’)  
and   Iscor   Limited   (‘Iscor’)   currently   own   Saldanha   Steel   (Pty)   Ltd   (‘  
Saldanha’)  in   equal   shares.   In   terms  of  this   transaction,   Iscor  seeks  to  
purchase the IDC’s half share so that Saldanha becomes a wholly owned  
subsidiary of Iscor.
2. The   merging   parties   have   asked   for   the   merger   to   be   approved  
unconditionally. In its recommendation to us the Commission also asked  
for unconditional approval, but at the hearing it asked for the merger to be  
approved with a condition relating to supply to a downstream customer of  
Saldanha’s, Duferco. 
3. The Commission and the parties have advanced different reasons for why  
the merger should be approved.
4. The merging parties argue that as the merger amounts to a change from  
joint control to sole control, there is no lessening of competition. Hence the  
merger should be regarded as neutral in substance with no effect on the  
competitive fabric of the market.
5. The   Commission   does   not   examine   this   argument   in   any   depth   in   its  
recommendation to us, but finds that the two firms were never competitors  
in South Africa as Saldanha only supplied offshore customers. Since the  
1

Commission defines the market as a national one, the two firms were not  
competitors.
6. We   find   neither   theory   entirely   satisfactory   for   the   reasons   we   outline  
below.   Nevertheless   we   have   decided   to   approve   the   merger   with  
conditions. Briefly our basis for approving the merger are­ 
1. Saldanha is a failing firm within the meaning of section 12A (2) (g)  
of the Act
2. Prohibiting the merger would in all probability lead to the closure of  
the   Saldanha   plant   an   outcome   that   cannot   be   justified   on  
substantial public interest grounds because of the adverse effect on  
the Saldanha region.
3. The   horizontal   anticompetitive   effects   of   the   merger   are   hard   to  
quantify.   Firstly,   because   Saldanha   never   competed   in   the   local  
market and secondly because of its disadvantageous location. The  
vertical anti­competitive effects can be cured by the imposition of  
conditions.
Background
7. Saldanha Bay according to one popular theory was named in error 1. The  
explorer   in whose honour it was named had never been to the bay. If that  
is so, it was not the last miscalculation to plague the area.
8. The first record of a European explorer arriving at Saldanha was that of an  
English explorer in 1612. Yet although the bay’s potential was known of  
since that time, little development took place until the 20 th  century. The  
area was proclaimed a municipality in 1954, but by the mid – 1960’s its  
population did not exceed 2500. 
9. The town relied on fishing and the presence of a naval dockyard for its  
1  Legend has it that the Portuguese explorer Antonio de Saldanha was the first European to  
discover the bay in 1503. This was however the mistaken of a subsequent Dutch explorer, who  
gave   that   honour   to   de   Saldanha,   based   on   an   erroneous   reading   of   the   latter’s   notes.   De  
Saldanha  had  not  seen  his   eponymous   bay,  but  was  describing  Table   Bay.  The   name  stuck

however. See the  Saldanha Bay Story  Jose Burman and Stephen Levin quoted in the “Report of  
the Board of Investigation into the Saldanha Steel Project” dated   4 October 1995, Chapter 2  
paragraph 2.1 This report was prepared by a Board of Investigation under the chairmanship of JH  
Steyn and was submitted to the Minister of Environment Affairs and Tourism.
2

livelihood.   During   the   Second   World   War   Iscor   officials   had   visited  
Saldanha   to   consider   its   possibilities.   They   were   attracted   by   its  
favourable   location   in   relation   to   international   shipping   lanes   and   the  
physical   attributes 2  of   the   harbour.   They   believed   that   with   the   proper  
development it could be an industrially competitive export zone.
10. Their   visit   had   no   immediate   consequences   and   it   was   not   until   Iscor  
required an outlet for its iron ore mine situated at Sishen, which is near  
Kimberley that their proposals were reconsidered. 
11. Although   Sishen   was   initially   intended   to   supply   Iscor’s   steel   factories  
domestic needs, it was soon realised that the mine’s iron ore production  
potential   exceeded   the   needs   of   the   local   steel   industry.   Hence   Iscor  
wanted to enter the export market. Given Sishen’s inauspicious location  
there was no obvious harbour outlet or a favourable transport link. The  
solution planners thought lay in Saldanha. 
12. A railway line was constructed in the 1970’s to link Sishen to Saldanha a  
distance of 861 kilometers. The project also entailed expansions to the  
mine and the development of the harbour so it could serve as an iron ore  
loading port. 
13. This project proved a great success. Today 76% of Sishen’s production is  
exported through Saldanha Bay. 3 
14. In   the  1970’s   planners  came  up  with  the  idea  that   if  iron   ore  could   be  
beneficiated before it was exported this would yield even greater returns.  
They proposed that a steel factory be constructed at Saldanha Bay, that  
would receive the Sishen ore, beneficiate it and then export the resultant  
product through the port.
15. It is not hard to see why the scheme was so seductive for government. A  
large   factory   would   boost   the   other   ailing   industrial   efforts   then   at

large   factory   would   boost   the   other   ailing   industrial   efforts   then   at  
Saldanha, create new jobs and make South African exports competitive in  
a strategic industry. It was also foreseeable that a successful plant could  
lead to other downstream activity in the region.
2  In Saldanha Steel’s literature the port is described in the most glowing terms:
“Saldanha Bay is one of the great natural harbours of the world. Apart from the entrance  
it   is   completely   landlocked   yet   the   water   is   deep   enough   for   large   ships.   But   for   a  
shortage of drinking water, Saldanha Bay would certainly have been the Cape’s main  
port, and not Cape Town.”
3  See Kumba Circular to shareholders dated 29 October 2001 page 12. South Africa supplies 5%  
of the global iron ore production of which Sishen contributes 81%.
3

16. For   various   reasons,   which   are   not   relevant   to   our   enquiry,   the   idea  
conceived of in the seventies was not implemented until the mid­nineties. 4
17. In 1994 the change in South Africa’s political dispensation was to have  
profound   effects   on   Iscor.   The   company   had   previously   enjoyed   the  
protection of high tariff barriers and confined itself to a domestic market.  
Now the new government was committed to both lowering tariff barriers  
and to ensuring that its companies competed in export markets. In 1995  
the tariff on steel was reduced from 30% to an effective 5%. At the same  
time the General Export Incentive scheme was phased out.
18. Iscor responded to these changes in 1994 by embarking on a five­year  
transformation program to transform its business to become internationally  
competitive.
19. The   following   year,   in   1995,   Iscor   and   the   Industrial   Development  
Corporation entered into a joint venture agreement to establish Saldanha  
Steel with each party owning 50% of the company. With the opening up of  
economic opportunities previously denied to apartheid South Africa, the  
object of the company was the:
“development   of   a   robust   competitive   business   which   will   compete  
principally in world markets..” 5
20. The factory was only built in 1997 and production only started towards the  
middle of 1998, 18 months later than anticipated. 
21. The delay cost Saldanha dearly. In the first place it led to massive cost  
overruns,   and   secondly,   and   perhaps   crucially,   it   meant   that   Saldanha  
entered the market at the most inopportune moment for a nascent steel  
producer. In 1998 world steel prices had plunged due to the crisis in Asian  
economies. 
22. Once   the  Asian  crisis  was   behind   them   world  steel   producers  believed  
there would be an international recovery in demand because the US and  
European economies remained buoyant. In eager anticipation plants that

European economies remained buoyant. In eager anticipation plants that  
had   been   mothballed   during   the   Asian   crisis   were   brought   back   into  
production. The result of this optimism was that world steel production had  
grown   by   5,1%   in   1999   and   by   8,2%   in   2000   far   exceeding   economic  
4  This had led one unnamed cynic to remark that Saldanha was conceived of in the seventies,  
designed in the eighties and built in the nineties. See Financial Mail dated November 17 2000.
5  Saldanha Steel Shareholders agreement clause 2.1
4

growth.6
23. Saldanha   came   onto   the   market   just   as   steel   prices   has   plummeted  
internationally.   This   volatility   remains   to   the   present   day.   As   a   result  
revenue projections in its initial budgets have proved woefully unrealistic. 
24. To compound the problems expenses were also underestimated. Bernard  
Smith, a former Managing Director, told the Steyn Commission in 1995  
that the project would cost R4,7 billion 7. Today the merging parties tell us  
the final costs were R8,7 billion.
25. This meant the two shareholders had to inject loans to keep the company  
financed so it was soon consuming more debt than iron ore. This led the  
auditors to remark in August 2001 that:
“ The ability of the company to continue as a going concern for the  
foreseeable future depends on the continued financial support by  
the   shareholders.   The   shareholders   have   reconfirmed   their  
intention to fund the company’s cash flow requirements for the next  
twelve months by way of interest free loans, as referred to in the  
Directors report..” 8
26. At the end of June 2001 the firm had shown an after tax loss of R 3287  
million dwarfing even the loss of the previous year of R 945 million.
27. In   2001   Saldanha   was   losing   $   91   per   ton   in   production   without   even  
contributing to financial interest or depreciation.
28. Not surprisingly the shareholders insisted on action on all fronts. A report  
was   commissioned   by   consulting   firm   McKinsey   to   assess   whether   the  
plant   was   viable   in   the   long   term.   The   consultants   concluded   it   was,  
provided   a   number   of   recommendations   were   implemented   .The  
recommendations heralded an improvement initiative that was sanguinely  
labelled Operation Rainbow.
29. Consultants together with Saldanha staff analysed the production process  
from   start   to   finish   in   a   bid   to   lower   production   costs   and   improve

from   start   to   finish   in   a   bid   to   lower   production   costs   and   improve  
efficiencies. It is too early to determine whether these efforts have been  
successful because some significant repairs have still to be implemented  
6  Saldanha’s 2001 Annual Report. The report of the Managing Director pg 5.
7  See Steyn Report paragraph 2.2.2.
8  See Report of the Independent Auditors dated 13 August 2001, contained in the Annual Report  
of 2001.
5

but Saldanha claims some modest success to date.
30. But   it   was   financial   as   opposed   to   production   engineering   that   saved  
Saldanha from imminent failure at the end of 2001. 
31. Since 2000 there had been an idea that Iscor assets were considerably  
undervalued because they combined both mining and steel assets in one  
listed company. The market it was thought would re­rate the firms if they  
were separated into a mining and steel company. The problem was what  
to do with the Saldanha debt in order to achieve this. If all this debt was to  
be   inherited   by   the   stand­alone   steel   company   it   would   be   very  
unattractive to investors. Eventually after months of tough negotiations, in  
which the IDC played a crucial role, an acceptable structure was arrived  
at, the crucial elements of which were that – 
a)   The Saldanha debt was apportioned between Kumba, the newly  
named company that inherited the mining assets and Iscor 9; 
b) Iscor was guaranteed supply of iron ore from Sishen on favourable  
terms; and
c) Iscor would acquire IDC’s 50% stake in Saldanha.
32. In   effect   debt   was   taken   off   the   Saldanha   book   and   bolstered   by   the  
injection of equity into Iscor and Kumba financed partly by the IDC and  
partly borne by the respective shareholders of those companies who given  
their re­rating by the market could not complain.
33.  The listing of the two companies proved spectacular. After the unbundling  
Iscor ‘s shares started at R6 in November last year. At one stage they had  
reached R17 although they have appeared to have stabilised at around R  
13,50 at the time of this decision. 10
34. Then fortune at long last smiled on Saldanha. The spectacular crash of  
the rand at last made its export prices competitive. So it happened that for  
the month of December 2001 the company reported its first profit.
35. Despite these propitious events we still consider Saldanha to be a failing

35. Despite these propitious events we still consider Saldanha to be a failing  
9  For   the   period   reckoned   from   1   July   2001,   to   the   date   of   the   unbundling,   Kumba   will   be  
indebted   to   Iscor   to   the   extent   of   R   250   million.   The   loan   account   will   be   settled   after   the  
unbundling   by   the   issue   of   10   million   shares   by   Kumba   to   IDC   on   behalf   of   Iscor   as   part  
consideration for the acquisition by Iscor of IDC’s shareholding in Saldanha steel.
10  See Business Day, 21 February 2002.
6

firm within the meaning of the Act, and we explain why below, but before  
that   we   need   to   determine   whether   the   merger   raises   any   competition  
concerns.
Competition Issues
a) Joint to sole control   
36.   In   their   competitiveness   report,   the   parties   main   argument   for   the  
approval of the transaction was that the merger did not ‘de facto’ amount  
to a change of control, as Iscor had been effectively managing Saldanha  
Steel   since   January   2001.   Although   at   the   hearing   the   parties   also  
invoked the failing firm doctrine, this initial argument was not abandoned  
and we must therefore consider it. 11
37. This  argument   was   not   fully  developed   beyond   the  parties’   observation  
that   whilst   there   was   a   structural   change   as   a   result   of   the   acquisition  
there would be no change in the competitive environment.
38. It is not self­evident that because a company goes from joint control to  
sole   control,   its   competitive   inclination   remains   unchanged.   For   this  
reason the onus is on the parties to the merger to establish that this is the  
case.
39.   In Europe in the   ICI /Tioxide   case, the Commission had to decide the  
reverse situation, namely whether a move from sole control to joint control  
amounted   to   a   concentration.   In   coming   to   their   decision   they   had   to  
evaluate the distinction between joint and sole control: 
“…because     decisive   influence   exercised   solely   is   substantially  
different to decisive influence exercised jointly, since the latter has  
to take into account the potentially different interests of the other  
party   or   parties   concerned..   By   changing   the   quality   of   decisive  
influence   exercised   by   ICI   on   Tioxide,   the   transaction   will   bring  
about   a   durable   change   of   the   structure   of   the   concerned  
parties.”12
40.   In this case the merging parties have done no more than make a bald

parties.”12
40.   In this case the merging parties have done no more than make a bald  
11  In their Competitiveness Report the parties argued quixotically that Saldanha was not a failing  
firm within the meaning of the Competition Act, but then go on to illustrate the fact that Saldanha  
has “been financially troubled since its inception.” ( See page 20 of the Competitiveness Report.)
12  ICI /Tioxide  1991(4) CMLR 854 
7

assertion   that   Iscor   enjoys   ‘management   control’   over   Saldanha.   13We  
have not been provided with any agreement to that effect or any evidence  
to indicate that the IDC has been constrained from exercising any rights it  
enjoyed as a result of the 1995 shareholders agreement. 
41. On the other hand there is evidence to suggest that the change of control  
would make a significant difference to the way Iscor relates to  Saldanha  
Steel.
42. In the first place its incentives have changed. It has gone from a situation  
where   it   enjoyed   only   half   of   the   benefits   of   an   enterprise,   which  
constituted a competitor, to being its sole owner and controller.
43.   In   the   Saldanha   shareholders   agreement,   entered   into   in   1995,   Iscor  
insisted   on   a   clause   that   would   effectively   preclude   Saldanha   from  
entering the local market as a competitor. 14 A sole shareholder would not  
require such a clause as it could achieve the same end without a contract.  
Iscor required the clause because it did not have sole control and in this  
respect it knew that its interests and the IDC ‘s would not coincide.
44.   Another fact that illustrates this, is the supply arrangement it has now  
secured   for   itself   with   Kumba   in   relation   to   Sishen.   Prior   to   the  
restructuring, Iscor then owner of Sishen, supplied Saldanha on an arms  
length   basis.   Yet   its   mine   at   Thabazimbi   supplied   its   Vanderbijlpark  
factory at cost plus a 3% management fee i.e. on more favourable terms.  
When Iscor was restructured it ensured its supply agreement with Sishen  
at cost plus a 3 % management fee i.e. on the same terms as Thabazimbi  
was supplying it.  15The fact that Iscor supplied Saldanha less favourably  
prior to the restructuring is again indicative of the fact that its incentives as  
a joint shareholder were different to that of a sole shareholder.
45. Furthermore in communicating with its shareholders Iscor has made much

45. Furthermore in communicating with its shareholders Iscor has made much  
of the fact that having sole control of Saldanha would allow it to introduce  
changes beneficial to Iscor.
“Full   control   of   Saldanha   will   allow   the   realisation   of   significant  
13  Iscor assumed management control in January 2001. According to the circular to shareholders  
until   this   date   Saldanha   Steel   had   been   ‘independently   managed.’   See   Iscor   circular   to  
shareholders dated 29  October 2001, page 11
14  Clause 16 . We examine this more fully below when we deal with the horizontal effects of the  
merger.
15  Iscor owns an undivided share in Sishen equal to its current needs and the right to acquire  
more if its needs increase.
8

synergistic   benefits   for   Iscor   in   the   areas   of   product   rationalisation,  
marketing, and future capital expenditure.” 16
46. Presumably these changes would have been implemented some time ago  
if Iscor was able to behave as if it were a sole controller. The reality is that  
the IDC acted as a constraint. Despite the fact that at our hearings the IDC  
protested modestly that it was not in the business of making steel and was  
therefore content to let Iscor manage the business, the IDC was no mere  
passive investor or spectator at board level. It had risked an enormous  
amount in the undertaking and it is improbable that given its exposure it  
would not have kept the closest scrutiny over Saldanha’s affairs. 
47. Finally the IDC is a significant player in the steel industry apart from its  
stake in Saldanha. Its joint ownership of Duferco Steel Processing (DSP)  
a   customer   and   a   potential   competitor   of   Iscor   are   illustrative   of   the  
difference in interests. Iscor as a sole shareholder in Saldanha has every  
incentive to squeeze DSP, but the IDC, because of its interest in DSP,  
does not.
48. In our view the argument that the change from joint control to sole control  
leaves the competitive environment unchanged, is without substance.
49. For this reason we need to go on to analyse the competitive effect of the  
merger.
b)   Horizontal effects
50. Both firms are involved in the manufacture of steel products. Since steel  
products   have   a   variety   of   different   applications   they   are   not   all  
substitutes.   In   this   case   both   the   Commission   and   the   parties   are   in  
agreement   on   the   product   market   but   some   prefatory   remarks   are  
necessary before we consider this.
51. Steel is manufactured in an integrated process. Raw  materials such as  
iron ore, coal and dolomite are charged to blast furnaces where they are  
converted to liquid iron. The liquid iron is refined in basic oxygen furnaces

converted to liquid iron. The liquid iron is refined in basic oxygen furnaces  
and electric arc furnaces to produce liquid steel. The liquid steel is cast  
into slabs, which are hot rolled into heavy plate in a plate mill or coils in a  
strip mill. The coil is either sold directly as hot rolled strip or processed  
further into cold rolled and coated products.
16  See Iscor Revised Listing procedures dated 29  October 2001, page 13.
9

52. Both Iscor and Saldanha produce Hot Rolled Coil (HRC), which is also the  
only area of product overlap between the parties. However, Saldanha has  
been specifically equipped to roll to a thinner gauge of between 1mm to  
1.6 mm in thickness, called Ultra Thin Hot Rolled Coil (UTHRC), which is  
thinner than the HRC that is produced by Iscor and other competitors such  
as Highveld Steel. Saldanha currently only exports this product.
53. HRC is a basic material used in the manufacture of general engineering  
products   such   as   containers,   pipe,   wheel   rims,   agricultural   implements  
and gas cylinders. Gauges as thin as UTHRC are traditionally produced  
as Cold Rolled Coils (CRC), which are used in automotive components,  
tubular   products   mainly   in   furniture   applications   and   in   high   precision  
tubing   for   conveyance   of   gases   and   fluids.   Since   CRC   tends   to   be  
smoother and more pliable than UTHRC, UTHRC can only be used as a  
substitute   for   CRC   in   those   applications   where   surface   conditions   and  
annealing   strength   (i.e.   brittleness)   are   suitable   for   hot   rolled   material.  
Currently no customers in South Africa utilize UTHRC. In order to convert  
from CRC to UTHRC technical changes to welding and forming equipment  
needs to be made by potential customers. 
54. However   UTHRC   presently   only   constitutes   35%   of   Saldanha   ‘s  
production   and   thus   65%   of   its   current   production   comprises   product,  
which could be sold in the domestic market.
55. Iscor in response to this have argued that Saldanha’s location in relation  
to downstream industry make it an unlikely entrant into the local market.  
The   bulk   of   the   downstream   manufacturing   capacity   is   located   in   the  
Gauteng region with only one major customer in the Western Cape  17 the  
nearest market to Saldanha.
56. The evidence of the parties is that the South African market consumes

56. The evidence of the parties is that the South African market consumes  
approximately   2,4   million   tons   of   flat   steel   products   annually.   Of   this  
approximately 900 000 tonnes is in the form of HRC.
57. The evidence of the parties as to transport costs is that for  a firm located  
in the industrial heartland transport costs per ton from Saldanha would be  
in   the   vicinity   of   R240   to   R   270   per   ton.   Iscor’s   transport   costs   from  
Vanderbijlpark to the central market would be R 54 per ton. The parties  
argue  that  if  the  same  firm  were  to  import  product  from  Europe,  which  
would be landed at Durban, transport costs would be approximately R140  
per   ton.   The   parties   argue   convincingly,   that   based   on   these   figures  
17  Pro Roof.
10

Saldanha’s transport cost disadvantage make it an unlikely entrant to the  
inland  market. 18
58. Iscor argues that had it been intended that Saldanha would compete in the  
local market it would not have been situated where it is.
59. However this bold assertion by Iscor is belied by its own conduct. As we  
mentioned earlier, Iscor in 1995 insisted on a clause in the shareholders  
agreement   that   provided   that   it   would   be   responsible   for   the   sale   of  
Saldanha’s products in the domestic market.
60. Despite the euphemistic language, the effect of this clause is to exclude  
Saldanha from the domestic market except with Iscor ‘s consent. Without  
taking too conclusive view of it, the clause amounts to a market division  
between competitors and thus might well be pro no scripta on the grounds  
that it amounts to an unlawful horizontal restraint. In fact Saldanha had no  
domestic customers except for DSP.
61. The fact that Iscor insisted on this clause is a clear indication that it feared  
that   Saldanha   might   enter   the   domestic   market   as   a   rival,   despite   its  
claims to the contrary that such rivalry is infeasible.
62. Post  merger of  course the clause  becomes academic, but  it cannot  be  
used to justify the fact that Saldanha was never a competitor of Iscor’s.  
We do not know if but for the restraint imposed on it, Saldanha might not  
have entered the local market.
63. That is not to say that the market for HRC in South Africa is characterised  
by intense rivalry. Indeed, as the table below suggests, this is largely a  
two firm market with Iscor having achieved an overwhelmingly dominant  
share,   more   than   80   %,   and   its   only   local   rival   Highveld   holding   to   a  
relatively  constant   15  %  share.   Competition  from  imports   is  slight,   less  
than 3 % at present and the trend shows this dropping in the past three  
years. 
Table 1: HOT ROLLED PRODUCTS
S.A. MARKET SHARE

years. 
Table 1: HOT ROLLED PRODUCTS
S.A. MARKET SHARE
18  When dealing with the fact that it was struggling to make its exports competitive, Iscor made  
the point that its transport costs to export were significant in relation to its ex factory cost because  
of its inland location. The same can be said of Saldanha’s transport costs inland in relation to its  
ex factory price.(See Iscor Revised Listing particulars, page 12)
11

INDEX
MA 100%
90% Iscor
80% 80.4% 82.1%
70% 79.3% 79.2% 72.7% 71.9%
12

60%
50% Highveld
40%
30%
20% 13.9% 15.2% 16.1% 15.0% 14.3% 15.1% Imports
10%
0% 6.8% 5.6% 11.2% 13.1% 5.3% 2.7%
95/96
96/97
97/98
98/99
99/00
Jul00­Mar01
64.  The parties nevertheless contend that the market is an international one.  
The   Commission   argue   for   a   national   one.   There   is   no   doubt   that  
international steel prices play a function in determining the price on the  
domestic   market   as   Iscor   has   a   policy   of   import   parity   pricing   19.  
According to Iscor’s Revised Listing Particulars:
“Iscor’s   steel   pricing   policy   in   the   domestic   market   is   based   on   import  
parity principles as its main competition in most of its product ranges is  
represented by imports. The exceptions to this principle are:
­ in the case of products where local competition exists and where  
over capacity results in prices that are lower than import parity, as it  
is the case with certain lower quality long products; and 
­ where Iscor offers lower price incentives (negotiated on a case by  
case   basis   )   with   local   manufacturers   to   encourage   secondary  
exports. 
65.  Many suggest that if a firm can set prices at import parity that fact alone  
is indicative of the fact that it has market power. We do not need to decide  
however whether the market is an international one or a domestic one as  
that assessment would not alter the outcome of our decision. We have  
assumed however that the market is a national one. 20 
19  See the Revised Listing particulars dated 29 October 2001, page 18 as well as the pricing  
documents received from Iscor, which provide for an import parity rebate.
20  As shown in Table 1, the low level of import penetration, particularly in recent years suggests  
13

66. Nevertheless   we   conclude   that   although   Saldanha   poses   potential  
competition   to   Iscor,   its   geographic   disadvantage   from   the   largest  
customer   base   in   the   interior,   the   absence   of   a   customer   base   of  
significance in the Western Cape, coupled with an absence of a market for  
the product it is most competitive in (UTHRC), all suggest that its potential  
to compete successfully with Iscor is remote. 
c) Vertical issues 
67. Saldanha   has   only   one   local   customer   and   that   is   Duferco   Steel  
Processing  (Pty   Ltd)   (‘DSP’)   a  company  that   is   jointly   owned   in  equal  
shares by the IDC and Duferco a Swiss company. 21
68. DSP   was   established   as   part   of   the   broader   Saldanha   industrial  
development strategy to process HRC. Saldanha Steel and DSP entered  
into an agreement in 1997 to set out the terms on which Saldanha would  
supply HRC to DSP for a 10­year period. 
69. In terms of the agreement DSP was – 
a) obliged to purchase exclusively from Saldanha a specified amount of  
HRC per annum;  22 and
b) was  further  prohibited  from  reselling  the  HRC   that   it had purchased  
from Saldanha and processed in markets in Southern Africa, without  
the consent of Saldanha. 23
70. The first clause was presumably inserted to guarantee DSP as a customer  
and from DSP ‘  point  of view   to ensure that  it had a secure  source of  
supply. The prohibition on resale was inserted again as with clause 16 of  
the Saldanha shareholders agreement for the benefit of Iscor which also  
processes HRC in the manner that DSP does. Again both clauses served  
Iscor by ensuring that potential rivals were confined to the export market.
71. The   agreement   was   premised   on   the   assumption   that   Saldanha   would  
produce 1,2 million tons of HRC per year and that DSP would be able to  
that the market is more likely to be a national one.

that the market is more likely to be a national one.
21  While the IDC ‘s shareholding is an indication of the extent of the incestuous relationships that  
exist in the steel industry, the role played by the IDC in developing industry in South Africa is  
recognised.
22  Article 2 of the agreement.
23  Article 3 of the agreement.
14

absorb 450 000 tons of this output per annum. As we have outlined above,  
Saldanha’s production ambitions were not realised and it was not able to  
supply DSP on the original contract terms. An arrangement was entered  
into in 2000, in terms of which Iscor undertook to supply 50% of DSP’s  
needs.
72. The new arrangement has not been formalised into an agreement yet. The  
status of the 1997 agreement is unclear. Iscor alleges that the “agreement  
has effectively been abrogated by disuse.” Confusingly, they also in the  
same breath state that “if the merger is approved, Iscor proposes to take  
the business out of Saldanha Steel, and therefore there will be a need to  
be a cession from Saldanha Steel to Iscor”    24 This suggests they regard  
the agreement as still binding if it was not there would be no need for a  
cession.   Yet   later   on   they   state   that   part   of   their   future   strategy   for  
Saldanha is to develop  a steel grade for thin HRC for supply to DSP for  
cold reduction to dimensions suitable for West Africa. 25
73. In a submission to the Competition Commission, DSP expressed anxiety  
about   its   conditions   of   supply   given   its   present   lack   of   contractual  
security.26
74. DSP points out that with the merger it would only have one supplier for it  
most critical raw material, which accounts for 70% of its production costs.  
This  single  supplier  relationship  exposes  it   to  a  potential  squeeze  from  
Iscor   both   in   relation   to   price,   quality   and   quantity.   Since   DSP   is   a  
potential   competitor   of   Iscor,   if   it   were   to   supply   the   local   market,   its  
vulnerability to a supply squeeze is well founded. DSP states that it does  
not have any alternative supplier to Iscor and when in the past it found  
alternative sources it was faced with the prospect of anti­dumping duties  
being imposed.
75. At   the   hearing   we   raised   these   concerns   with   the   merging   parties.   In

response to  the proposal  by the Commission that the  vertical  concerns  
could   be   obviated   by   the   Tribunal   imposing   appropriate   conditions,   the  
merging parties raised no serious objections.
76. We   have   accordingly   framed   conditions,   which   are   designed   to   ensure  
that whatever contractual arrangements the parties may enter into, DSP  
has no constraints on its source of supply and that it is free to compete in  
the domestic market. 
24  Paragraphs 5.2 – 5.3 of the Parties response to the Tribunal questions.
25  Paragraph  11.2 .2–of the Parties response to the Tribunal questions.
26  Letter from Horacio Malfatto dated 14 February 2002.
15

d)   Failing firm
i) Theoretical   
77. The jurisprudence of competition law recognises what has become known  
as the ‘failing firm defence’ to sanitise a merger that might otherwise raise  
competition concerns.
78. The   defence   first   emerged   in   US   law   when   in   a   1930   decision,  
International   Shoe   v   FTC   27the   Supreme   Court   recognised   that   the  
acquisition of a failing firm did not violate section 7 of the Clayton Act. 
79. What is surprising is that notwithstanding amendments to the Clayton Act  
subsequent   to   this   case,   and   discussion   of   the   failing   firm   defence   in  
Congressional debates preceding the amendments,  the  language never  
found   its   way   into   the   statute.   28  Nevertheless   the   defence   is   well  
recognised   in   the   case   law   and   has   been   invoked   on   numerous  
occasions.29
80. The defence is also recognised in the U.S. Horizontal Merger Guidelines  
which provide for the following ;
“A merger is not likely to create or enhance market power or facilitate its  
exercise if the following circumstances are met: 
1) the   allegedly   failing   firm   would   be  
unable   to   meet   its   financial   obligations  
in the near future; 
2) it   would   not   be   able   to   reorganize  
successfully   under   Chapter   II   of   the  
Bankruptcy Act; 
3) it   has   made   unsuccessful   good­faith  
efforts   to   elicit   reasonable   alternative  
offers of acquisition of the assets of the  
failing   firm   that   would   both   keep   its  
27  280 US 291 (1930)
28  See Areeda and Hovenkamp,  ”Antitrust Law”   2 nd Edition, paragraph 951a.
29  See American Bar Association,  Antitrust Law Developments (Third)  Volume 1 pg. 313 fn. 219  
and the cases decided therein.
16

tangible   and   intangible   assets   in   the  
relevant market and pose a less severe  
danger   to   competition   than   does   the  
proposed merger; and 
4) absent the acquisition, the assets of the  
failing   firm   would   exit   the   relevant  
market.”30
81. Influenced by the US approach the defence has also found its way into  
European law albeit in an altered form. As in US, the European Merger  
Regulation contains no express recognition of the doctrine, but it has been  
recognised now in case law and the practice of the Commission. In the  
judgement   of   the   European   Court   of   Justice   (the   ‘ECJ’)   in   the   case   of  
France v Commission 31 the ECJ accepted   the failing firm test applied by  
the Commission, in approving the merger between the only two German  
producers of potash. 32  
82. The Commission ‘s test requires that the following conditions be satisfied:
a) the   acquired   firm   would   have  
withdrawn from the market if not taken  
over by the other firm;
b) the   acquirer   would   gain   the   market  
share of the acquired firm if the latter  
were to exit the market; and
c) no   alternatives   were   available   that  
were less anticompetitive.
83. It has been pointed out that the second condition is a European innovation  
and   is   more   stringent   than   the   U.S.   test,   which   has   no   such  
requirement.33
84. In Australia, the Merger Guidelines indicate that the Australian Consumer  
and Competition Commission ( the ‘ACCC’) will recognise the failing firm  
notion   provided   certain   conditions   are   satisfied.   Their     approach   is  
instructive and worth quoting at length: 34
30  Paragraph  5.1  of  the  Revised  Guidelines  April   8,  1997  issued  by  the  U.S. Department  of  
Justice and the Federal Trade Commission.
31  1998 (4) CMLR 829
32  Kali­Salz/Mdk/Treuhand  Case IV/M308 OJ L 186.
33  See Bellamy and Child,  “European Law of Competition” , Sweet and Maxwell, (2001) pg. 418.
34  See paragraph 5.134­5 of the Guidelines.

34  See paragraph 5.134­5 of the Guidelines.
17

“Briefly, the Commission  [the ACCC]  will need to be convinced that  
the firm cannot be successfully re­organised and there is no other  
viable  buyer  for  the business, and no  likelihood of  such a  buyer  
emerging,   such   that   the   firm’s   resources   are   likely   to   exit   the  
market absent the merger and so cease to represent an actual or  
potential constraint on the market.
If the target firm is considered to be failing, the Commission will  
consider   the   likely   effect   of   the   acquisition   on   competition  
compared   to  the  effect   of  the  target’s  assets   exiting   the   market.  
Under   the   latter   circumstances,   the   distribution   of   the   target’s  
customer base among the remaining market participants would be  
determined by market forces, whereas an acquisition would tend to  
deliver   those   customers   to   the   acquiring   firm.   If   the   competitive  
strength of the remaining participants is evenly matched, the level  
of competition in the market may be better served by allowing the  
firm   to   fail.   However,   the   loss   of   capacity   will   tend   to   reduce  
competitive pressures in the market. Depending on the effect of the  
acquisition   on   the   relative   strength   of     remaining   participants,  
retaining the failed firm’s capacity in the market may still be pro­
competitive.” 
85. In Canada the failing firm doctrine is given statutory recognition as one of  
the   factors   to   be   taken   into   account   in   determining   whether   a   merger  
prevents or lessens competition. In this respect our Act is identical to the  
Canadian Competition Act. 35
86. There is thus no doubt that the failing firm doctrine is widely recognised in  
competition law jurisprudence, and regardless of whether the doctrine has  
become part of the case law or enjoys an express statutory recognition,  
has been applied with a degree of uniformity. 36  What is more difficult to

has been applied with a degree of uniformity. 36  What is more difficult to  
discern,   and   which   is   relevant   to   an   assessment   of   how   much   of   their  
jurisprudence to adopt, is the exact rationale for the defence.
87. Writing in the context of European merger regulation, Bishop and Walker  
argue that if other firms will buy the assets after a firm has failed, then the  
failing   firm   defence   is   not   valid 37.   The   defence   is   only   reasonable   if  
35  See Section 93 (b).
36  All require satisfaction to varying degrees of the fact that the firm is a failing one, that re­
organisation is not an option and that there is no other less anti­competitive outcome. Failure on  
its own absent these other criteria is not sufficient.
37  Presumably the only other time that other potential buyers will not be interested in acquiring a  
18

productive assets would otherwise exit the market. 38
88. A similar theme is echoed in the US Horizontal Merger Guidelines, where  
it is argued that if imminent failure would mean that the assets of the firm  
would   exit   the   market,   then   post   merger   performance   if   the   merger   is  
approved, may be no worse than if the merger had been blocked and the  
assets left the market.   39
89. The rationale expressed here seems to be that if the status quo remains  
unchanged if the failing firm’s assets exit or are acquired one would favour  
their acquisition. That still begs the question of the underlying rationale of  
invoking the  defence  when  the post  merger  state  of  the  market  is  less  
competitive than before because the acquiring firm would enjoy a greater  
market share on acquisition of the failing firm than it would have if it just  
exited.40 Here case law is not that consistent.
90. Areeda alludes to this difficulty in his comment on the  International Shoe  
case:
“International Shoe suggests two differing and perhaps inconsistent  
grounds   for   a   failing   firm   defence   (1)   Acquisition   of   a   failing  
company may have no significant adverse effects on competition;  
and   (2)   the   interests   of   stockholders,   creditors,   employees,   and  
others   affected   by   the   fate   of   the   failing   company   deserve  
recognition.   These   propositions   are   hardly   sufficient   grounds   for  
making the defence absolute in all circumstances; nor do they point  
to   any   unified   or   simple   way   of   identifying   the   defence’s   proper  
domain.”41
91. Areeda goes on to say that: 
“as     a   general   proposition   the   cases   have   not   attempted   to   determine  
failing firm will be when they are unaware of a value enhancing factor, which might be known only  
to the acquiring firm such as e.g. a secret efficiency gain or because the acquisition will enable

the acquirer to strengthen its market share to such an extent that it is able to exercise market  
power, a position the other potential buyers would not be able to secure if they purchase the  
failing firm.   
38  See   Bishop   and   Walker,   ‘ Economics   of   EC   Competition   Law:   Concepts,   Application   and  
Measurement’, Sweet and Maxwell, (1998), pg 162
39  See US Guidelines op cit para. 5.0.
40  For instance on exit the failing firm’s share may be taken over in some proportion by the  
remaining firms,  whilst in an acquisition the acquirer  may take all the failing firms share or a  
disproportionate amount to that it would have got if there was only exit.
41  See Areeda op cit para 952a pg 225.
19

whether  an acquisition benefits   competition  more than  failure  would  do  
harm.”
92.  Areeda is critical of the one leg of the  International Shoe  test namely the  
adverse impact on shareholders, employees or creditors. He points out  
that antitrust is traditionally unsympathetic to these concerns when they  
are asserted as a justification for an anticompetitive outcome. Thus a loss  
to shareholders is no panacea to firms involved in a price fixing cartel.  
Furthermore the private interests are not always reconciled if a merger  
goes ahead. A firm may be willing to purchase only the assets of a failing  
firm and thus satisfy shareholders to some extent but not employees.
93.   Areeda does however acknowledge that there are circumstances where  
private   interests   may   be   worth   recognising.   Although   he   gives   several  
examples  42one is particularly relevant to the circumstances of this case.  
He argues that new entry and investment are encouraged the more the  
costs   of   failure   are   reduced.   Expressed   differently,   if   firms   taking  
investment decisions know that competition law might increase the costs  
of failure by harshly applying merger control in the event of their exit, they  
would be less likely to assume the risk.
94. Areeda then looks at the other rationale for the failing firm defence which  
is to ensure that productive assets are reassigned to more efficient users.  
He   points   out   correctly   that   a   number   of   these   defences   are   more  
appropriately classified as efficiency defences and need not be used to  
broaden the failing firm defence beyond what it need be.
95.  This is particularly apposite in interpreting our statute where we have an  
express efficiency defence, which is absent in the Clayton Act. 43
96. Areeda however goes on to identify efficiency defences which arise in a  
failing firm context and which do not qualify for acceptance in the typical

failing firm context and which do not qualify for acceptance in the typical  
economies   defence   and   he   argues   for   their   recognition   as   part   of   the  
failing firm defence. Into this category he would include the following :
a) an   acquisition   would   preclude   the   administrative   costs   of  
bankruptcy 
b) it would keep in the market resources that might otherwise be taken  
42  See Areeda op cit Para 9252c2 pages 229 –230 Areeda also refers to the fact that bankruptcy  
has high social costs even if re­organisation is successful, secondly an acquirer may pay more for  
a firm’s assets because it can put them to more efficient use.
43  See our decision in   Trident Steel     89/ LM/ Oct 00,   for a discussion of the United States  
approach.
20

out of production, even though they are not yet depleted
c)   it would assign productive assets to managers capable of using  
them more efficiently. 44
97.   If we follow the Areeda approach and look at the failing firm defence in  
the context of our Act, then there may be other aspects of a failing firm  
defence   that   can   more   appropriately   be   assumed   under   other   sections  
provided expressly for by the Act. Thus as is the case with the Kali und  
Salz   merger,   although   the   transaction   led   to   unacceptably   high  
concentration,   the   failing   firm   defence   was   successfully   raised   in   part  
because the merger obviated a large loss of jobs in Eastern Germany. 45 
98.  In our statute there would be no need to invoke the failing firm doctrine to  
such a situation when the adjudicator can have regard to the employment  
effect in terms of the public interest criteria. 46
99. Similarly, where the failing firm defence is in reality an efficiency defence,  
the merging parties should rely on the efficiency defence in section 12 (A)  
(1)( a)( i). This is not to say that alternatives cannot be alleged, but it is  
important   that   we   avoid   conceptual   confusion.   The   danger   of   following  
some overseas jurisdictions uncritically, is that they may recognise under  
a   failing   firm   defence,   factors   that   we,   with   our  more   extensive  merger  
regime,   might   recognise   under   another   classification,   employment   loss  
being a good example.
100.This perhaps leads us to an important contextual difference between the  
way we should apply the failing firm doctrine and the way it is applied in  
other jurisdictions.
101.In our Act, the failing firm doctrine is not used as a ‘defence’ to a merger  
that has been found on an initial market analysis to be anticompetitive.  
Rather it is recognised as one of list of ‘factors’ that one takes into account  
before one can determine whether a merger is anti­competitive.

before one can determine whether a merger is anti­competitive. 
102.Thus  in  some   jurisdictions,   such  as   the  United  States,   the  adjudicator  
would first determine whether a merger was anti­competitive and then only  
if it was, consider the failing firm doctrine as a defence. 
103.Our Act  does not  divide  the  inquiry  into two  discrete stages. The  way  
section 12A(2) is drafted, the consideration of whether a merger is anti­
44  See Areeda op cit para 952d pages 230­ 231.
45  See opinion of the Advocate General
46  Section 12 A (3) (b)
21

competitive   involves   as   part   of   that   inquiry   a   consideration   of   a   non­
exhaustive list of factors, one of which is whether a party to the merger is  
a failing firm. In contrast to this, our ‘efficiency defence’ 47 is a real defence  
to   an   anti­competitive   merger   and   for   this   reason   is   located   in   a   self­
standing sub­paragraph of section 12A, as a reading of section 12A(1)(a)
(i) makes clear. To invoke the efficiency defence one first has to conclude  
that the merger is anti­competitive. This one does by first conducting the  
inquiry into the factors contained in section 12A(2). Then, and only if that  
inquiry leads to the conclusion that the merger is anti­competitive, does  
one go on to enquire whether the efficiencies gained outweigh the anti­
competitive effects.
104.The   distinction   might   appear   to   be   a   mere   lawyers   quibble   with   no  
practical significance, but this is not so. If the failing firm doctrine was a  
“true   defence”,   then   if   all   the   elements   of   the   defence   could   be  
established,   an   anti­competitive   merger   would   have   to   be   approved.  
However if it is just one of a list of factors to be taken into account, in the  
list set out in section 12A(2), then even if it was established, that the firm  
was   failing,   by   say   the   application   of   the   US   or   EU   tests,   one   might  
nevertheless still find a merger to be anti­competitive because of the way  
one balances this failing firm factor in relation to all the others. It is thus  
possible   in   terms   of   the   Act,   that   a   credible   failing   firm   theory   may  
nevertheless   not   save   a   merger,   which   raises   serious   competition  
concerns. 
105.Conversely,   where   the   competitive   loss   is   low,   then   one   may   be   less  
exacting in requiring a showing of all the elements of the traditional failing  
firm defence. If the failing firm concept was a defence, in the sense that

firm defence. If the failing firm concept was a defence, in the sense that  
the   efficiency   defence   is,   then   this   type   of   flexibility   would   be  
impermissible and one would have to satisfy all the elements of a test that  
the legislature had provided before it could be invoked.
106.Whilst this approach may risk making the concept more nebulous, it does  
allow the adjudicator the flexibility to achieve real interest balancing, as  
opposed to the application of rigid formulas.
107.A flexible approach, allows one for instance to have regard to some of  
the rationale for the failing firm defence even though they do not constitute  
elements of a traditional defence. Thus if one rationale, as Areeda puts it,  
47The phrase ‘efficiency defence’ is just a convenient shorthand for the defence that the merger  
can be justified on account of any ‘technological, efficiency or other pro­competitive gain’ that  
would offset any anti­competitive effect of the merger and that would not likely be obtained absent  
the merger. (See section 12 A (1)(a)(i) ).
22

is to avoid inhibiting investment decisions because we regard investment  
in general terms as pro­competitive, then evidence that not allowing the  
acquirer to rescue a failing firm might inhibit entrepreneurial or investor  
risk,   would  be   relevant  and  pertinent  despite  the   fact   that   they   are  not  
elements of a traditional test. This distinction is important to bear in mind  
before one imports   en bloc   the jurisprudence on this doctrine from other  
jurisdictions.
108.This is not to say that we would abandon all reference to these tests.  
Rather we are saying that some of the elements of the defences would be  
more sacrosanct than others. If the merging parties had not established  
the   requirement   that   there   were   no   other   viable   less   anti­competitive  
outcomes,   the   failing   firm   doctrine   would   not   avail   them.   This   is   the  
approach   which   we   took   in   the   Sasol/Schumann48  merger,   where  
although we applied the test set out in the US Guidelines the failing firm  
doctrine was not found to have been established on this ground.
109.Other controversies in foreign case law about the failing firm doctrine are  
partially answered for us by the language of the Act. For instance it is not  
necessary to show that a firm has failed only that it is likely to fail. Nor  
does failure need to equate to insolvency, otherwise the legislature would  
presumably   have   used   that   language.   As   Areeda   has   expressed   it   “  
insolvency is not a necessary ingredient of failure:
“Low   revenues   may   dictate   that   a   firm   withdraw   from   a   market  
rather than reinvest capital, even though it is continuously able to  
pay its maturing debts. Although proof of such a case poses more  
serious problems, the opportunity to make it cannot reasonably be  
foreclosed.”
110.In summary we are saying the following:
1. A failing firm defence should  
not be invoked if it amounts  
in   substance   to   another

not be invoked if it amounts  
in   substance   to   another  
factor  or defence which the  
Act   already   provides.   In  
particular we draw  attention  
to the efficiency defence and  
the public interest criteria.
2. The   merger   criteria   for   a  
failing   firm   set   out   in   the  
48  See Tribunal Case No: 23/LM/May01
23

tests   of   other   jurisdictions  
will   carry   serious   weight   in  
our assessment. Organising  
ones evidence on the basis  
of   these   criteria   would   thus  
be   useful   and   instructive   to  
the Tribunal. 
3. A   merger   would   not   be  
regarded   as   lessening  
competition if the conditions  
laid out in the more stringent  
EU test can be satisfied. 
4. A   party   falling   short   of   the  
“market   share   would   have  
gone to us” requirement, but  
that   could   satisfy   the   other  
elements   of   the   test   or   the  
standard   in   the   US   test,  
would   have   a   reasonable  
possibility   of   success  
depending on the degree of  
the   anti­competitive   sting.  
Thus   where   the   anti­
competitive   effects   of   the  
merger are otherwise slight,  
then   the   Tribunal   might   be  
less   stringent   in   the  
application   of   some   of   the  
criteria.   Here   the   party  
should   have   regard   to  
evidence   that   establishes  
some   rationale   for   the  
existence   of   the   failing   firm  
doctrine.   We   have   referred  
to   some   of   these   in   our  
discussion   although   we   do  
not   suggest   that   this   is   an  
exhaustive list. 
5. Evidence   of   the   extent   of  
failure   or   its   imminence,  
would   be   weighed   up  
against   the   evidence   of   the  
anti­competitive   effect.   The  
24

greater   the   anticompetitive  
threat   the   greater   the  
showing   that   failure   is  
imminent 
6. No   leniency   would   be  
afforded   to   the   requirement  
that   there   be   evidence   that  
there   is   no   less  
anticompetitive alternative. 
7. The onus is on the merging  
firms   to   establish   the  
evidence   necessary   to  
invoke   the   doctrine   of   the  
failing firm. 49
ii) Applying the failing firm doctrine to the facts of this case 
111.At   the   time   that   the   Saldanha   project   was   first   conceptualised   in   the  
1970’s, Iscor was still a parastatal. In 1989 Iscor was privatised and then  
listed. At that stage the company was involved in both mining and steel  
manufacture although they were operated as separate businesses. When  
Iscor listed, the markets initial euphoria was soon tempered by the fact  
that analysts did not like the idea it was running two businesses and there  
were  perceptions  it lacked focus and would land up doing neither well.  
After  listing the Iscor  share price was to drop from R2 to 60  cents per  
share.
112.In   1994   Iscor   brought   in   new   management   to   run   the   separate  
businesses.  According to  an  article  in  the  Financial   Mail,  Iscor  had  not  
adapted quickly enough to the post ‘94 economic environment. 
“Though   it   took   advantage   of   export   opportunities,   especially   in  
Asia, it did not restructure quickly enough to remain internationally  
competitive in steel.” 50
113.The   idea   was   then   to   transform   both   businesses   to   make   them  
internationally competitive. This theme of the international competitiveness  
of Iscor was to drive both the company’s and government policy thereafter  
49  This is the case in the European Union. See Whish,  Competition Law , 4 th edition Butterworths  
page 780. Whish relies on  Rewe/ Meinl  OJ (1999) L 274/1. for this proposition. It is also the case  
in US law. See Areeda op cit para 951 C

in US law. See Areeda op cit para 951 C 
50  Financial Mail November 17 2001 pg 51. Article entitled  “The IDC and Iscor – In for the Chop” .
25

and provided the context for the decision we have to arrive at in relation to  
this transaction.
114.In   1995,   as   we   noted   earlier,   Iscor   and   the   IDC   entered   into   a  
shareholders agreement to establish Saldanha.   The construction of the  
factory commenced in May 1996 , but the first coils were only produced in  
the fourth quarter of 1998.
115.The plant was bedevilled by numerous problems from the outset.
• Concerns   about   the  
environmental   impact  
of the plant including its  
site led to delays in the  
commencement   of  
construction.51
• The   construction   itself  
took   longer   than  
anticipated.
• When   production  
commenced   it   was   at  
levels   substantially  
below   those   budgeted.  
The   plant   had   been  
designed   to   produce  
100   000   tons   per  
month,   but   for  most   of  
1998   and   1999   the  
production   levels   were  
considerably   below  
this. The Corex smelter  
and   gassifier   was  
producing   at   only   70%  
of   its   capacity   due   to  
design   flaws.   It   was  
only   in   October   2001  
that   production  
reached a peak of 90%  
and   it   is   by   no   means  
clear   that   this   is  
sustainable   as   the  
Corex   will   require  
51  Environmental concerns had led to  the Steyn Commission of Inquiry in 1995.
26

repair   later   this   year.  
The   Conarc   furnace   is  
one   of   the   few   in  
existence   in   the   world  
and   thus   there   was  
limited   experience   in  
dealing   with   it   when  
problems   arose,   as  
they did.
• By   the   time   Saldanha  
was   ready   to   place   its  
product on the market,  
as   we   noted   above,  
steel   prices   had  
plunged   and   were  
continuing   downwards.  
The   project   could   not  
have come to market at  
a   less   opportune  
moment.
• Expertise   in   running   a  
plant   with   technology  
that   was   new   to   the  
South   African   steel  
industry was not what it  
should   be   and  
production   delays  
occasioned   by  
technical   problems  
were frequent.
• The   delays   in  
commencement   and  
the   sub­optimum  
returns   on   initial  
production   had   meant  
that   the   shareholders  
had   to   dig   deep   into  
their pockets to provide  
loans   to   continue   the  
joint venture. 
• In   2001   at   then   prices  
and   production   costs  
the   firm   was   losing   $  
27

91 per ton.
116.Despite the fact that the two shareholders are very large concerns with a  
considerable  ability  to   raise  capital   their  balance  sheets   started  to   take  
strain under the weight of the obligations that they started to incur. This  
was   to   lead   to   a   strained   relationship   between   the   shareholders,   and  
according to the Financial Mail, the IDC had at one stage contemplated  
taking over control of Iscor. 52
117.Iscor’s   own   performance   was   compromised   by   Saldanha’s   difficulties.  
Iscor’s   share   of   Saldanha   Steel’s   after   tax   loss   excluding   impairment  
charge for the year 2001 amounted to R 526 million compared to R 473  
million for 2000.
118.Faced   with   these   growing   problems   the   shareholders   engaged   the  
services   of   consultants   in   2001,   who   as   part   of   their   wider   brief,  
considered the option of liquidating Saldanha steel or mothballing it for a  
period until international prices for HRC had improved.
119.The consultants concluded that neither of these  options was  attractive  
and   might   indeed   result   in   a   greater   cost   in   the   short   term   to   the  
shareholders than continuing the operations.
120.The   shareholders   accepted   the   recommendation   and   the   fortunes   of  
Saldanha and its shareholders have now improved both as a result of the  
restructuring   we   describe   earlier,   the   improvements   to   Saldanha’s  
production and the favourable rand dollar exchange rate.
121.This change in fortunes begs the question of whether Saldanha should  
still continue to be regarded as a failing firm. Indeed Saldanha reported in  
December 2001 that it was in the black for the first time for its figures of  
that month.
122.The   parties   have   urged   us   not   to   place   too   much   emphasis   on   these  
factors to come to a conclusion that the firm is no longer failing.

factors to come to a conclusion that the firm is no longer failing.
123.Saldanha’s   recent   results   are   not   yet   evidence   that   it   has   turned   the  
corner and its revival in fortunes is largely the result of the decline of the  
rand which on a rand / dollar exchange gave a windfall to exporters at the  
end of last year.
124.The fact that Saldanha’s debt has been restructured does not mean it  
52  See Financial Mail dated November 17 2000.
28

has   been   eliminated.   If   Saldanha   was   still   carrying   its   pre­restructuring  
debt, the December results would have shown a considerable loss. It is  
the deep pockets of its shareholders that have kept Saldanha from exiting  
the   market.   The   fact   that   they   have   concluded   that   the   costs   of   its  
retention outweigh the costs of its closure does not make it any less than a  
failing firm. As we pointed our earlier in our theoretical discussion, our Act  
does not require that a firm must have failed only that it is likely to fail.  
Without   the   financial   restructuring   of   Iscor   and   the   IDC   that   we   have  
referred to Saldanha  would have failed ­  no independent firm would have  
provided the finance necessary to bail it out of its debt obligations given its  
past performance and its less than certain future.
125.Whilst   there   is   no   doubt   that   Iscor   and   the   IDC   remain   confident   that  
Saldanha has a future, this will only become clear in the long term. In the  
medium term the risks to the shareholders remain considerable.
126.The extent of the financial disaster is not in doubt and the numbers speak  
for themselves. 53 In a letter to the Tribunal, dated 15/02/02, by the Chief  
Executive Officer of ISCOR, Mr Louis van Niekerk, indicates that by 2001  
Saldanha   Steel   had   a   debt   burden   of   R5,8   billion   consisting   of   the  
following:
Foreign Loans R 3.3 billion
South African Banks R 1.5 billion
IDC (through project loan) R 1.0 billion
TOTAL R 5.8 billion
127.He also said that both Iscor and the IDC would absorb R3.0 billion each  
of   Saldanha’s   debt   i.e.   re­capitalisation   of   Saldanha’s   debt   by  
shareholders.54
128.The IDC, according to Mr Ngqula, 55 (the CEO of the IDC) stands to lose  
R  6.5 billion,  Iscor R  2.7  billion and the local  banks R 1.5 billion  if  the  
merger was not approved. This amounts to a total of R10.7 billion. 56  He

merger was not approved. This amounts to a total of R10.7 billion. 56  He  
53  Whilst the figures we have been provided with at the hearing and those that appear in other  
documentation emanating from the parties are not always consistent their portent as a symbol of  
the financial gloom is. The inconsistencies are attributable to the fact that the information is not  
provided for the same reporting periods
54  According to the Iscor 2001 Annual report Iscor ‘s share of the Saldanha loss excluding the 3  
billion rand impairment charge amounted to R526 million compared to R 473 million the previous  
year. The Iscor board said it would not declare a dividend in view of the uncertainty in steel price  
recovery and the funding requirements of Saldanha.
55  Oral evidence during the hearing on 18 February 2002.
56  Contrast this amount with the original projections of the cost of the project prior to construction  
29

also mentioned that there were foreign loans to the amount of R3 billion.  
Both Iscor and the IDC would absorb R3 billion of Saldanha’s debt, as  
shareholders. 
129.According to the McKinsey Report, Saldanha Steel’s ultimate net present  
cost   to   shareholders   would   be   R11.5   billion,   should   Saldanha   continue  
business as pre the merger. Ceasing operations  at Saldanha  Steel   will  
have a total cash impact of R5.8 billion for mothballing, R7.3 billion for  
liquidation and a further equity write off of R4.7 billion is to be expected in  
both   scenarios.   For   both   liquidation   and   mothballing   shareholders   are  
likely to be exposed to the full Saldanha Steel debt position of R 5.5 billion  
in addition to the R1.0 billion injected up to June 2001. Moreover, large  
contract cancellation costs of approximately R 7.0 billion must be faced.
130.Iscor   has   launched   a   rights   issue   for   R1.67   billion   to   bring   down   its  
Saldanha­driven debt, while the IDC recorded the impairment loss of R2.6  
billion in its interim results. Iscor’s share of Saldanha’s operating loss in  
the 6 months to December 2001 was R266m. 57
131.In the short term Saldanha will have to decrease its production levels as  
its main refinery Corex will be shut down for 45 days to undergo repairs in  
May 2002.
132.The   evidence   that   the   patient   is   in   remission   is   too   inconclusive.  
Saldanha must at the present moment still be regarded as a failing firm.
133.The next  issue  we must  examine  is  whether even  if the firm  is  failing  
there   is   not   an   alternative   buyer   whose   purchase   would   not   raise  
competition concerns.
134.The   evidence   of   the   merging   parties   is   that   they   have   approached  
various international concerns over the past few years. All it seems were  
approached on the basis that they would be offered a stake in Iscor. All  
apparently   placed   various   conditions   on   the   deal   which   included   an

apparently   placed   various   conditions   on   the   deal   which   included   an  
insistence   that   Saldanha   be   integrated   first   into   Iscor.   None   it   appears  
would have been interested in purchasing Saldanha as a going concern  
and that is hardly surprising as given its debt levels the shareholders could  
never have got their price. 58  On the other hand if Saldanha is liquidated  
of R 4,7 billion . See the Steyn Report par 2.2.2 , quoting Bernard Smith a previous Managing  
Director of Saldanha. According to the parties the final capitalised cost was R8.7 billion.
57  Business Day – Company News – 8 February 2002
58  LNM Holdings, a foreign steel company have now purchased the largest stake in Iscor. They  
30

equipment is more likely to be sold off piecemeal to another firm based  
offshore and hence will not remedy any domestic competition concerns.
135.The fact that the shareholders had commissioned the consultants report,  
which had looked at all these issues in detail lends credibility to the fact  
that the present option is the only realistic scenario. 
136.Purchasing only Saldanha is highly unlikely to prove attractive to a third  
party purchaser. Firstly they would have to source supply from Sishen and  
it  is highly unlikely that they would be able to procure supply on the same  
favourable   terms   as   Iscor   has,   which   it   could   only   have   obtained   as   a  
result of the window of opportunity afforded by the unbundling. 
137.Without   a   competitive   source   of   supply   and   given   Saldanha’s   as   yet  
untested production process, it is hardly a jewel to be added to any steel  
makers crown. Nor would any firm want to enter into the domestic market  
to   take   on   the   dominant   Iscor   more   favourably   located   next   to   the  
domestic   customer   base.   The   firm   would   then   only   enter   to   supply   the  
international market and hence have no effect on our domestic market.
138.We conclude that it is unlikely that an alternative buyer for the firm would  
be found.
139.What distinguishes this case from the typical failing firm case, is that the  
buyer   is   not   an   arms   length   independent   firm,   but   a   50%   shareholder  
seeking to reduce the loss it has incurred to date. To prevent Iscor from  
protecting   the   investment   it   had   made   to   date   would   be   to   discourage  
investment in new plant and innovation, which is what Iscor has done to  
date in Saldanha.
140.Iscor   is   not   taking   advantage   of   a   competitors   demise   to   secure   a  
monopoly,   the   standard   problem   presented   by   a   failing   firm   defence.  
Together with its partner the IDC it had embarked on a project to invest

Together with its partner the IDC it had embarked on a project to invest  
considerable capital in new and innovative productive capacity. The dream  
has run into trouble. It would not serve the cause of competition policy,  
which seeks to encourage firms to invest in plant and innovation, to apply  
the failing firm doctrine so rigidly that we inhibit such schemes, otherwise  
firms may become afraid to risk their capital. 
141.Finally   the   transaction   costs   occasioned   by   Saldanha’s     failure   or   exit  
either by liquidation or by temporarily mothballing  would be excessive and  
have indicated in a letter to Iscor, given to us, that they would not have done so if this merger is  
not implemented. The LNM Group is according to Iscor the world’s second largest steel company.
31

exceed   mere   loss   to   the   shareholders.   Both   Iscor   and   the   IDC   have  
absorbed   debt   by   way   of   institutional   loans   to   finance   their   respective  
stakes in Saldanha from both domestic and foreign firms. If the venture  
were allowed to fail this would according to McKinsey‘s report lead a re­
rating  of   their  credit   status,   increasing   their  costs   of   capital.   Given  that  
both firms continually raise capital in the market to finance development,  
the costs of such a failure would be felt throughout the economy.
142.Our   conclusion   is   that   the   failing   firm   concerns   outweigh   the   loss   to  
potential   competition   that   might   otherwise   be   occasioned   by   the  
transaction and that accordingly the merger does not substantially lessen  
or prevent competition in the relevant market.
Public interest
143.If   the   merger   is   approved   we   have   no   evidence   that   this   would   be   in  
conflict with any of the public interest grounds set out in section 12 A (3) .  
We have been informed that employment levels will remain unaffected by  
the transaction .
144.However   if   the   merger   is   not   approved   this   will   have   adverse   public  
interest   considerations.   One   of   the   factors   that   we   have   to   look   at   in  
examining the public interest is the effect on the particular industrial sector  
or region. 
145.There   is   evidence   that   the   Saldanha   Steel   plant   is   a   vital   part   of   the  
town’s economic life. If the plant was to be shutdown or be mothballed for  
a period this would not only have a substantial impact on the employees of  
the   plant   who   would   be   retrenched,   but   also   on   all   the   firms   and  
individuals in the West coast region whose livelihoods are so dependent  
on the plants functioning. 59 The effect of Saldanha on the local economy  
is  best  expressed  in  a  report  by  Wesgro   60on  the  contribution  that   the

is  best  expressed  in  a  report  by  Wesgro   60on  the  contribution  that   the  
project   made   to   the   gross   regional   product   of   the   region   during   its  
construction phase – a figure of R 1,15 billion.
146.Were Saldanha a larger economic region the effect might be muted but  
given its dependency on a small number of industries the effect would be  
devastating. Saldanha Steel has to its credit been a good corporate citizen  
in the area and is involved in a number of important social programs that  
59  More than 340 million was paid out in salaries and wages to local residents during the  
construction phase alone. 
60  The Western Cape Trade and Investment Promotion Agency 
32

contribute to the upliftment of the area. Without the plant these projects  
would become less viable, if they survived at all.
147.The public interest thus strongly favours the approval of the merger.
Views of the Department of Trade and Industry
148.Government industrial policy has played and will continue to play a key  
part in the structure of our local steel industry. The Department of Trade  
and   Industry   has   been   involved   with   and   has   been   a   champion   of   the  
Saldana project for many years and for this reason we invited the DTI to  
make submission to us on the merger 61. Regrettably these submissions  
were only received at the hearing itself in the form of oral testimony by  
Department representatives. 
149.Nevertheless,   the   thrust   of   the   DTI   submission   was   that   they   were   in  
favour of the merger, as it would enhance the competitiveness of Iscor  
internationally.
150.Iscor needs to compete in a global market against firms much larger than  
it. Unless it can expand its productive capacity it will falter in its attempts to  
secure international markets.
151.The DTI is also of the view that if Iscor can become a lower cost producer  
this will  benefit  the downstream steel  industry  in South Africa and thus  
Iscor’s   customers   will   also   become   more   competitive.   The   DTI   also  
endorsed the public interest submissions made by the parties which we  
referred to earlier.
152.What is missing from the DTI’s approach and which we could not get a  
satisfactory answer for, was why Iscor should pass on these cost savings  
to its customers in the domestic market where it faces no serious local  
competition. 
153.The fall in the rand means that Iscor can maintain its price at an import  
parity price and since it faces no domestic pressure retain the margin for  
itself. Whilst it’s true that our tariffs on steel imports are comparatively low  
at 5 % the authorities have not been reticent about imposing steep anti­

at 5 % the authorities have not been reticent about imposing steep anti­
61  In 1995 in a submission to the Steyn Commission the Minister of Trade and Industry stated  
that “ the Saldanha Steel Mill epitomises the type of world class industry that South Africa can  
and must develop.” Paragraph 3.2.3 of the Report op cit.
33

dumping duties at the behest of Iscor. In 1999 the Board on Tariffs and  
Trade   (the   BTT)   imposed   anti­dumping   duties   of   81,7   %   and   94,8%,  
respectively, on steel imported from Russia and the Ukraine. 62
154. The low figures of import penetration indicate that foreign competition does  
not impose a serious price constraint on Iscor. Within a few days of our order  
being handed down in this matter Iscor announced that it was to increase  
prices on its flat­steel products by 9,8% from May because, according to its  
Corporate Affairs Executive, Phaldie Kalam, the company’s flat­steel business  
has been “under severe pressure” because of dollar prices for steel being at a  
30­year low. “In particular, margins at our Vanderbijlpark and Saldanha steel  
mills have been constrained,” he said. 63
155. Were   Iscor   faced   by   a   strong   domestic   competitor   it   might   be   more  
constrained   in   the   local   market.   We   are   concerned   that   downmarket   firms  
may not see Iscor’s growth through the same rose tinted spectacles as the  
DTI, but that is not a subject that we need dwell on for the purpose of this  
decision for all the reasons given above.
Conclusion 
156. We are of the view that the merger will have an anti­competitive effect both  
because of the removal of Saldanha as a potential competitor to Iscor and the  
vertical effects on DSP. The vertical problems can be cured by the conditions  
we have imposed. In respect of the horizontal effects, when we balance the  
loss   of   potential   competition   with   the   prospect   of   Saldanha   failing   we  
conclude that the merger will not substantially lessen or prevent competition.  
In   addition,   from   a   public   interest   perspective,   we   arrive   at   the   same  
conclusion as the failure of the transaction would in all probability lead to a  
closure   temporarily   or   permanent   of   the   firm,   and   with   that   a   devastating  
impact on the region.

impact on the region.
157.The   merger   is   approved   subject   to   the   conditions   set   out   in   the   order  
attached hereto.
62  The problems of the international steel market are to a large degree created by distortions  
because of protectionist measures imposed by governments in varied forms. These distortions  
impact upon other markets, as steel companies denied access to one market have to find other  
outlets for their production. Thus a company denied access to the markets of country A, because  
of a tariff or quota, will land up exporting to Country B only to be accused of dumping. As John  
Kay, an economist writing in a column for the Financial Times, recently observed,” So long as  
politicians love steel, steel will always be a problem.” (Financial Times, 26 March 2002).
63  See Business Day: Company News, In Brief dated 26 February2002 on page 15.  
34

4 April 2002
N Manoim Date
Concurring: P.E. Maponya and M. Holden  
35