Capital Propfund First and Another v UPL South Africa (Pty) Ltd (18959/2024P) [2026] ZAKZPHC 6 (26 January 2026)

80 Reportability

Brief Summary

Delict — Negligence — Exception to particulars of claim — Plaintiffs alleging contamination of property due to defendant's introduction of hazardous chemicals — Defendant arguing impermissibility of delictual claim due to existing contractual relationship — Court dismissing exception, affirming that plaintiffs' claim is validly framed in delict despite underlying contract — Defendant ordered to pay costs.

Comprehensive Summary

Summary of Judgment


1. Introduction


The proceedings concerned an exception brought in the High Court of South Africa, KwaZulu-Natal Division, Pietermaritzburg, by the defendant (as excipient) against the plaintiffs’ particulars of claim. The exception was directed at whether the pleading disclosed a legally cognisable cause of action and whether it was allegedly vague and embarrassing in material respects.


The parties were Capital Propfund (Pty) Ltd and Lussindale Investments (Pty) Ltd as plaintiffs (and respondents in the exception), and UPL South Africa (Pty) Ltd as defendant (and excipient). The plaintiffs are described as property-owning entities conducting business in Gauteng and as the joint registered owners of a warehouse property situated in Cornubia Ridge Logistic Park, KwaZulu-Natal.


The procedural history reflected that the plaintiffs instituted action in December 2024, claiming delictual damages arising from contamination allegedly caused by UPL’s conduct in relation to hazardous agrochemical products stored at the premises. In February 2025, UPL delivered a notice in terms of Uniform Rule 23(1) and also took steps initially directed at Uniform Rule 30; however, by the hearing the matter proceeded solely as an exception. Certain grounds of exception were abandoned in the joint practice note, and argument focused primarily on whether a delictual claim was competent given an alleged contractual context and whether wrongfulness had been adequately pleaded. The hearing took place on 21 October 2025, with supplementary submissions filed on 3 and 10 November 2025, and judgment delivered on 26 January 2026.


The general subject matter of the dispute was whether the plaintiffs’ pleaded case—framed in delict, based on alleged physical contamination and pollution of soil following a warehouse fire—was legally competent and sufficiently pleaded to require the defendant to plead, or whether it was excipiable for lacking necessary averments, including in relation to contract/delict “concurrence”, wrongfulness, foreseeability, causation, and the nature of the loss.


2. Material Facts


It was treated as undisputed on the pleadings that UPL occupied and was in possession of a portion of the warehouse at the relevant time. The plaintiffs pleaded that they were the joint owners of the warehouse property and that the warehouse formed part of a letting business intended to generate rental income.


The plaintiffs alleged that on 12 July 2021, while UPL occupied part of the warehouse, UPL introduced and stored substantial quantities of agrochemical and pesticide products containing hazardous and toxic substances in the warehouse. The plaintiffs pleaded that they were unaware of the chemical composition of those products.


A fire occurred at the warehouse and was extinguished with water. The plaintiffs alleged that the firefighting runoff water mixed with the chemicals and permeated through/under the warehouse slab into sediment and soil, resulting in contamination and pollution of the soil by toxic elements contained in the chemicals. The pleading attributed the environmental harm to the interaction of stored chemicals and the foreseeable use of water by fire-combatting systems.


Following the fire, the warehouse (except for the slab) was demolished and rubble removed. The plaintiffs pleaded that the contamination rendered the property permanently unfit, alternatively unfit for the foreseeable future, for human occupation and commercial use, and that it would not generate income and was effectively valueless for a projected period until 12 July 2031. They further pleaded that, absent the contamination on 12 July 2021, they would have reconstructed the warehouse within approximately 12 months (by 12 July 2022) and would thereafter have leased it to generate income until at least 12 July 2031.


The plaintiffs pleaded a delictual cause of action framed as a positive act, alternatively an omission. The positive act was pleaded as bringing chemicals onto the property, which were washed into the soil causing damage; the omission was pleaded as a failure to take measures to prevent contamination of soil by chemicals in UPL’s possession stored at the warehouse. They pleaded foreseeability and reasonable preventability of contamination arising from fire and the discharge of water through sprinklers and firefighting measures.


As to damages, the plaintiffs pleaded a main claim based on diminution in value of the property: a pre-contamination value of R100 million and a post-contamination value of R1 million, yielding R99 million. Alternatively, they pleaded a rental-based claim quantified at R81 million, calculated from a pleaded reasonable rental and a specified period from 12 July 2022 to 12 July 2031.


To the extent that there were disputes raised by UPL, they arose not from evidence but from challenges to pleading sufficiency. UPL contended, among other things, that the plaintiffs’ formulation obscured which event in the pleaded chain caused the damage, that foreseeability regarding the fire and/or the use of water was not properly pleaded, that the fire and firefighting could constitute a novus actus interveniens, and that the pleaded loss was in substance pure economic loss. The court approached these as exception-related characterisation and pleading questions, rather than factual disputes to be resolved on evidence.


3. Legal Issues


The central legal questions the court was required to determine were whether the plaintiffs’ particulars of claim were excipiable on the basis that they failed to disclose a cause of action or were vague and embarrassing, with the principal focus on two interrelated issues.


First, the court had to decide whether it was legally permissible for the plaintiffs to pursue a delictual claim where, on UPL’s argument, the pleadings suggested that UPL’s occupation arose from a contractual relationship (a lease) and the delict claim allegedly circumvented the contractual allocation of risk. This raised a question of law (the scope of the “concurrence” principle and whether delict is precluded), coupled with the application of law to the pleaded facts.


Second, the court had to determine whether the particulars sufficiently pleaded the delictual elements implicated in the exception grounds, including wrongfulness, foreseeability, causation (both factual and legal causation), and whether the pleaded damages reflected physical damage as opposed to pure economic loss. These issues involved the application of legal standards to pleaded allegations, and in parts required evaluative judgment on whether the pleading provided adequate notice and whether any lack of clarity caused prejudice.


Additionally, the court had to address whether allegations about a novus actus interveniens needed to be pleaded by the plaintiffs (as part of causation), and whether the quantum and formulation of damages complied with pleading requirements, including the defendant’s ability to assess the claim.


4. Court’s Reasoning


The court commenced by setting out the established principles applicable to exceptions. It emphasised that at exception stage the court accepts the pleaded facts as true, does not have regard to extrinsic evidence, and considers whether any defect appears ex facie the pleading. It further noted that only material facts must be pleaded (not legal conclusions), and that an over-technical approach should be avoided because it undermines the purpose of exceptions as a mechanism to eliminate cases without legal merit. The court reiterated the test for a vague-and-embarrassing exception as requiring both vagueness and resulting prejudice.


Delict claim despite an alleged contractual relationship


On the main issue, the court accepted that the plaintiffs’ claim was pleaded in delict and that UPL’s argument was essentially that such a claim is incompetent where a contract governs the parties’ relationship. UPL relied on authority cautioning against extending delictual liability into the realm of negligent performance of contractual obligations in a manner that would undermine contractual allocations of risk.


The court, however, reasoned that the principle in Lillicrap, Wassenaar and Partners v Pilkington Brothers SA (Pty) Ltd 1985 (1) SA 475 (A), as discussed in later authority, does not amount to a blanket rule that delict is excluded whenever a contract exists between the parties. The court treated the relevant qualification as being that the exclusionary approach applies primarily where the delict claim is founded on negligent performance of a contractual duty and where superimposing delict would undermine the parties’ bargain.


The court applied the approach that delict and contract may in appropriate circumstances both arise from the same conduct, allowing a plaintiff an election, and relied on the proposition (as articulated in Holtzhausen v Absa Bank Ltd 2008 (5) SA 630 (SCA)) that Lillicrap is not authority for a general preclusion of delict in the presence of a competent contractual claim.


Crucially, the court characterised the pleaded harm as physical damage to property caused by alleged negligent conduct or omission, rather than loss arising from defective contractual performance. It held that the duty not to cause physical harm to another’s property exists independently of contract and is not extinguished by the mere existence of a contractual relationship. In support of this, the court relied on the statement in Trustees, Two Oceans Aquarium Trust v Kantey & Templer (Pty) Ltd 2006 (3) SA 138 (SCA) that negligent positive conduct causing physical damage to property is prima facie wrongful, making wrongfulness seldom contentious in such cases.


On that basis, the court held that the plaintiffs’ election to sue in delict was not barred and that this ground of exception could not succeed.


Foreseeability, causation, and alleged vagueness about the causal chain


UPL’s further challenges targeted foreseeability and causation, including a contention that it was unclear which event in the sequence caused the damage and that the fire or the use of water constituted a novus actus interveniens.


The court analysed causation by reference to the two-stage enquiry identified in International Shipping Co (Pty) Ltd v Bentley 1990 (1) SA 680 (A): factual causation (the “but for” test) and legal causation (remoteness and policy-based limits). It held that the plaintiffs had pleaded an overarching cause (the presence of toxic chemicals brought onto the premises, which UPL allegedly knew the nature of) and had also pleaded a chain of events from the outbreak of the fire to the runoff and infiltration resulting in contamination.


The court treated UPL’s complaint as effectively requiring the plaintiffs to establish and prove each link in the causal chain at pleading stage. It rejected this approach as inconsistent with pleading standards, emphasising that the trial court would ultimately determine on evidence what would have occurred but for the alleged wrongful act or omission, and whether the chain sufficed for liability. The court thus considered the pleading adequate to place the defendant on notice of the case it was required to meet.


On the question of novus actus interveniens, the court explained the concept by reference to Fourie NO v Hansen and Another 2001 (2) SA 823 (W) (including the Lawsa formulation). It reasoned that novus actus interveniens is a matter that may serve to limit liability and is typically raised as a defensive contention. The court held that the absence of such allegations in the plaintiffs’ particulars could not render the particulars excipiable, because it remained open to UPL to plead such matters in its plea.


Regarding foreseeability, the court found that the plaintiffs had pleaded foreseeability as an aspect of fault, including an express allegation that it was foreseeable that if the warehouse and contents burned, fire-combatting systems (including sprinklers) would discharge substantial volumes of water that would wash chemicals into the soil, and that a reasonable operator would have avoided bringing such chemicals into the warehouse or would have taken steps to prevent contamination.


The court stressed that pleadings must be read as a whole, rather than dissected into isolated statements, and applied the guidance in Home Talk Developments (Pty) Ltd and Others v Ekurhuleni Metropolitan Municipality [2017] ZASCA 77; 2018 (1) SA 391 (SCA) that pleadings must define the issues and provide sufficient notice of the general nature of the case. It concluded that UPL’s insistence on pleading foreseeability for each event in the chain was an overly rigid, technical standard and that the plaintiffs’ allegations were sufficient for purposes of exception.


Characterisation of the loss: physical damage vs pure economic loss, and the pleading of damages


Although UPL had indicated it no longer persisted with aspects of the ground alleging uncertainty as to physical damage versus pure economic loss, the court nonetheless addressed the issue because it remained connected to wrongfulness and pleading sufficiency.


The court reaffirmed the distinction that delict treats pure economic loss differently from physical harm to person or property, and that pure economic loss is not prima facie actionable absent policy considerations establishing wrongfulness. However, it held that on the pleadings the plaintiffs alleged physical contamination damage to their property, which the court regarded as a recognised category of delictual harm where wrongfulness is presumed and generally not controversial.


The court then turned to the measure of damages. It relied on Trotman and Another v Edwick 1951 (1) SA 443 (A) to distinguish delictual damages as restoring the diminution in the plaintiff’s patrimony caused by the wrongful conduct. It accepted that the main claim, formulated as the difference between pre-delict and post-delict market value, was an acceptable method of quantification, referring to De La Rey's Transport (Edms) Bpk v Lewis 1978 (1) SA 797 (A) in support of the acceptability of such valuation approaches.


As to the alternative rental-based claim, the court characterised it as a form of pecuniary loss, pleaded as a prospective-loss measure linked to the alleged physical damage and inability to use the property. The court relied on the approach in Jowell v Bramwell-Jones and Others 1998 (1) SA 836 (W), as accepted on appeal in Jowell v Bramwell-Jones and Others 2000 (3) SA 274 (SCA), that a plaintiff is not barred from claiming damages (including prospective loss) merely because precise assessment is difficult, and that courts assess such claims by weighing probabilities, contingencies, and expert evidence.


The court further held that the pleading of damages was adequate for purposes of Uniform Rule 18(10), in that it enabled the defendant reasonably to assess the quantum claimed. It emphasised that disputes about the correct measure, valuation, or proof were matters for trial rather than exception.


Remaining grounds


The court gave brief reasons for dismissing the remaining, less-pursued grounds. It regarded certain details—such as who extinguished the fire, the identity of authorities refusing reconstruction permission, and further detail about measures allegedly not taken—as matters capable of resolution through requests for further particulars for trial or through evidence. It also accepted that pleading the cause of action in the alternative as positive conduct or omission was permissible and not excipiable.


Overall, the court concluded that the particulars disclosed a cognisable cause of action, were not vague and embarrassing, and were sufficiently particularised to enable UPL to plead without prejudice.


5. Outcome and Relief


The court dismissed the exception. It ordered the defendant to pay the plaintiffs’ costs on Scale C, and directed that the costs include those occasioned by the employment of two counsel where so employed.


Cases Cited


Telematrix (Pty) Ltd t/a Matrix Vehicle Tracking v Advertising Standards Authority SA 2006 (1) SA 461 (SCA)


Barclays National Bank Ltd v Thompson 1989 (1) SA 547 (A)


Living Hands (Pty) Ltd and Another v Ditz and Others 2013 (2) SA 368 (GSJ)


Merb (Pty) Ltd and Others v Matthews and Others [2021] ZAGPJHC 693


Trope v South African Reserve Bank 1992 (3) SA 208 (T)


Tembani and Others v President of the Republic of South Africa and Another [2022] ZASCA 70; 2023 (1) SA 432 (SCA)


Lillicrap, Wassenaar and Partners v Pilkington Brothers (SA) (Pty) Ltd 1985 (1) SA 475 (A)


Country Cloud Trading CC v MEC, Department of Infrastructure Development [2014] ZACC 28; 2015 (1) SA 1 (CC)


Trustees, Two Oceans Aquarium Trust v Kantey & Templer (Pty) Ltd 2006 (3) SA 138 (SCA)


Holtzhausen v Absa Bank Ltd 2008 (5) SA 630 (SCA)


International Shipping Co (Pty) Ltd v Bentley 1990 (1) SA 680 (A)


Fourie NO v Hansen and Another 2001 (2) SA 823 (W)


Home Talk Developments (Pty) Ltd and Others v Ekurhuleni Metropolitan Municipality [2017] ZASCA 77; 2018 (1) SA 391 (SCA)


Kruger v Van Der Merwe and Another 1966 (2) SA 266 (A)


Trotman and Another v Edwick 1951 (1) SA 443 (A)


De La Rey's Transport (Edms) Bpk v Lewis 1978 (1) SA 797 (A)


Jowell v Bramwell-Jones and Others 1998 (1) SA 836 (W)


Jowell v Bramwell-Jones and Others 2000 (3) SA 274 (SCA)


Legislation Cited


No legislation was cited in the judgment beyond references to the Uniform Rules of Court.


Rules of Court Cited


Uniform Rule 23(1)


Uniform Rule 30(1)


Uniform Rule 30(2)(b)


Uniform Rule 18(10)


Held


The court held that the plaintiffs’ particulars of claim, read as a whole and accepted as true for exception purposes, disclosed a cognisable delictual cause of action based on alleged physical damage to property arising from contamination following a warehouse fire in circumstances where hazardous chemicals were allegedly introduced and stored by UPL.


It held that the existence or suggestion of a contractual relationship did not, on the pleaded case, preclude a delictual claim, because the pleaded wrong was not framed as negligent performance of contractual obligations but as breach of an independent delictual duty not to cause physical harm to another’s property.


It further held that the particulars sufficiently pleaded foreseeability and causation for purposes of exception, that a novus actus interveniens was a matter for defence rather than an omission rendering the claim excipiable, and that the pleaded damages—both diminution in market value and the alternative prospective rental-based measure—were adequately particularised at pleading stage and were not, in the court’s characterisation, impermissible pure economic loss claims divorced from physical damage.


LEGAL PRINCIPLES


An exception is determined on the basis that the pleaded allegations are accepted as true, with no reliance on extrinsic evidence, and the defect must appear ex facie the pleading. A court considers whether the pleading discloses a cause of action or is vague and embarrassing to the extent that it causes prejudice, and an overly technical approach should be avoided so as not to defeat the exception procedure’s purpose.


The “concurrence” principle derived from Lillicrap does not operate as a general bar against delictual claims where parties are contractually connected. Where the pleaded wrong concerns the breach of an independent legal duty imposed by delict—particularly the duty not to negligently cause physical damage to another’s property—the plaintiff is not precluded from suing in delict merely because a contractual relationship may also exist.


Negligent conduct in the form of a positive act causing physical damage to property is treated as prima facie wrongful, with wrongfulness generally not being contentious in that category of cases, distinguishing such claims from those for pure economic loss, which require a more intensive policy-based enquiry into wrongfulness.


Causation in delict entails both factual causation (the “but for” enquiry) and legal causation (remoteness and policy-based limits). At pleading stage, a plaintiff is required to allege material facts sufficient to set out the general nature of the claim and the basis on which liability is asserted; the plaintiff is not required to prove each link in the causal chain on exception.


A novus actus interveniens is an intervening, independent, unforeseeable factor which may neutralise the causative potency of the defendant’s original conduct; however, it is typically a matter raised in defence and does not need to be negatived by the plaintiff at the level of initial pleadings for the particulars to be legally competent.


Delictual damages aim to restore the diminution in the plaintiff’s patrimony caused by the wrongful conduct. Quantification may permissibly be approached through methods such as the difference between pre-delict and post-delict market value, and claims may include prospective loss where properly pleaded, even if the precise assessment is difficult, provided the pleading enables the defendant reasonably to assess the quantum as required by Uniform Rule 18(10).

IN THE HIGH COURT OF SOUTH AFRICA
KWAZULU-NATAL DIVISION, PIETERMARITZBURG

Case No:18959/2024P

In the matter between:

CAPITAL PROPFUND FIRST PLAINTIFF

LUSSINDALE INVESTMENTS (PTY) LTD SECOND PLAINTIFF

and

UPL SOUTH AFRICA (PTY) LTD DEFENDANT

In Re
UPL SOUTH AFRICA (PTY) LTD EXCIPIENT

and

CAPITAL PROPFUND FIRST RESPONDENT

LUSSINDALE INVESTMENTS (PTY) LTD SECOND RESPONDENT

2




ORDER


The following order is granted:
1. The exception is dismissed.
2. The defendant is ordered to pay the plaintiff’s costs of on Scale C
3. The costs shall include costs occasion ed by employment of two counsel
where so employed.


JUDGMENT


Siwendu J

Introduction
[1] The court is called upon to determine an exception brought by the
defendant against the plaintiffs’ cause of action and particulars of claim . The
plaintiffs, Capital Propfund (Pty) Ltd and Lussi ndale Investments (Pty) Ltd
(collectively, ‘the plaintiffs’), are property-owning entities conducting business
in the Gauteng Province. They are joint registered owners of a warehouse situated
in the Cornubia Ridge Logistic Park, KwaZulu-Natal (‘the warehouse’).

[2] The plaintiffs instituted an action against the defendant, UPL South Africa
(Pty) Ltd ( ‘UPL’), in December 2024. They allege that on 12 July 2021, while
UPL occupied a portion of the warehouse, UPL introduced substantial quantities
of agrochemical and pesticide products containing hazardous and toxic

3



substances into the warehouse. The plaintiffs were unaware of the chemical
composition of these products.

[3] Fire broke out at the warehouse and was extinguished using water. The
firefighting runoff water is alleged to have mixed with the chemicals, permeating
the sediment beneath the warehouse slab and the soil. Toxic elements in the
chemicals contaminated and polluted the soil.

[4] Except for the slab, the warehouse was demolished after the fire and the
rubble removed from the property. The plaintiffs state that the contamination of
the soil has rendered the property permanently unfit for human occupation and
commercial use. They allege that the property will not generate an income for the
plaintiffs and has been rendered valueless for a period projected to 12 July 2031.

[5] The plaintiffs aver that had the property on which the warehouse stands not
been polluted and contaminated on 12 July 2021, the plaintiffs would have
reconstructed the warehouse within approximately twelve months, by 12 July
2022, and afterward leased it to generate income until at least 12 July 2031.

Cause of action
[6] It is necessary to outline the structure of the particulars and cause of action
set out by the plaintiffs to understand the exception . The plaintiffs framed their
action based on the ‘positive act’, alternatively based on an ‘omission’ by UPL,
created by:
(a) bringing chemicals to the warehouse , which were washed into the soil
causing damage to the property, and,
(b) in the alternative , UPL’s failure to take measures to prevent the
contamination of the soil by the chemicals in its possession, stored at the
warehouse.

4




[7] They allege that UPL ’s conduct or omission was wrongful due to the
damage to their property, which caused them to suffer loss. The particulars state
that UPL knew that:
(a) the chemicals brought into the warehouse contained toxins which, if they
were to enter the soil, would contaminate and damage same,
(b) the water used to extinguish a fire in the warehouse would wash some of
the chemicals out of the warehouse or through the slab and into the sediment and
soil below the warehouse,
(c) it could have refrained from bringing chemicals containing toxins ,
alternatively taken steps to prevent them entering the soil; and
(d) it owed the plaintiffs a legal duty to ensure there is no damage the property
or warehouse that would cause a loss to the plaintiffs.

[8] Specifically, it is alleged that UPL could and should have refrained from
bringing chemicals containing toxins into the warehouse, alternatively, it should
have taken steps to prevent the chemicals from entering the soil. UPL owed the
plaintiffs a legal duty to ensure they don’t suffer loss due to chemicals brought
on the property.

[9] Regarding UPL’s fault, the plaintiffs pleaded that it was:
(a) reasonably foreseeable that chemicals containing toxins brought into the
warehouse could be washed from the warehouse by firefighting runoff water into
the sediment and the soil below the warehouse, and
(b) reasonable steps could be taken to avoid such contamination including not
bringing such chemicals into the warehouse at all or alternatively, placing them
in containers from which they could not spill or placing the containers onto
surfaces or receptacles which would prevent the contamination should a spill
occur;

5



(c) it was at all relevant times before and on 12 July 2021 foreseeable that if
the warehouse and its contents including the chemicals would burn, the fire
combatting systems in the warehouse, including the sprinkler systems, would
discharge substantial volumes of water into the warehouse which would wash the
chemicals into the soil; and,
(d) a reasonable manager and operator of a warehouse would either have
refrained from bringing such chemicals into the warehouse or would have taken
steps to avoid contamination.

[10] As to the causation and loss, the plaintiffs pleaded that UPL’s negligent
and wrongful acts referred to above caused the plaintiffs to suffer loss in that the
‘property can probably not again, alternatively for the foreseeable future but
probably until 12 July 2031, be used to generate rental income for the plaintiffs.’

[11] The plaintiffs computed their damages of R99 million by subtracting the
reasonable market value of the property with the contamination, which they found
to be R 1 million from its previous market value immediately before the
contamination and before improvements which was R99 million. The alternative
basis for the damages claim of R81 million was based on a loss of reasonable
monthly rental of R7,5 million per month, the plaintiffs claim they would have
earned for the period from 12 July 2022 to 12 July 2031, had the property not
been damaged.

The exception and applicable principles
[12] UPL initially sought an order striking out the plaintiffs’ particulars of claim
as an irregular step in terms of Uniform rule 30(1),1 simultaneously delivered a
notice calling upon the plaintiffs to remove the cause of complaint in terms of

1 Rule 30(1) reads: ‘A party to a cause in which an irregular step has been taken by any other party may apply to
court to set it aside.’

6



Uniform rule 30(2)(b).2 In the alternative, UPL sought an order upholding its
exception in terms of Uniform rule 23(1), with leave granted to the plaintiffs to
amend their particulars of claim within 15 days of the order.

[13] Although the notice of exception in terms of Uniform rule 23(1), together
with the notice to remove the cause of complaint in terms of Uniform rule
30(2)(b), was delivered in February 2025, the rule 30(1) and 30(2)(b) applications
were not pursued. At the hearing, the matter proceeded solely on UPL’s grounds
of exception.

[14] It also bears mentioning that the joint practice note filed states that UPL no
longer persisted with the fourth and sixth ground for exception. The fourth ground
pertains to the allegation of the conduct or omission flowing from the storage of
the chemicals causing damage and loss to the property. The sixth ground of
exception which was abandoned pertains to the reference and meaning of
‘dangerous goods’ stored at the warehouse.

[15] During the hearing both counsels devoted extensive argument on only two
exception grounds, namely (a) the permissibility of a delictual claim as a cause
of action where a contract is alleged to exist and, (b) the concomitant question of
wrongfulness. Although the fourth ground of exception was purportedly
abandoned, ie whether the plaintiffs’ claim is for physical damage or for pure
economic loss, it nonetheless formed a part of the issues originally raised under
that ground. Given that the determination of an exception is a ‘useful mechanism
to weed out cases without legal merit’,3 and to enable the court ‘to dispose of the

2 Rule 30(2)(b) states that ‘the applicant has, within ten days of becoming aware of the step, by written notice
afforded his opponent an opportunity of removing the cause of complaint within ten days’ .
3 Telematrix (Pty) Ltd t/a Matrix Vehicle T racking v Advertising Standards Authority SA 2006 (1) SA 461 (SCA)
(Telematrix) para 3.

7



case in whole or in part’ and avoid the unnecessary leading of evidence, that issue
could not be extricated from the exception.4

[16] While on the above point, it is useful to stress that both parties were ad
idem about the applicable principles governing adjudication of an exception as
these are well -established. Relevant to the present matter is that only material
facts need to be pleaded, not legal conclusions. The court may not rely on
extrinsic evidence, as the defects must appear ex facie the pleading. The court
accepts the pleaded facts as true, and all the facts pleaded by the plaintiffs are
taken as admitted.

[17] Although each ground of exception must be considered on its merits, as
held by the court in Living Hands (Pty) Ltd and Another v Ditz and Others ,5 an
over-technical approach should be avoided because it destroys the usefulness of
the exception procedure, which is to weed out cases without legal meri t.
Ultimately, the test when determining whether a vague -and-embarrassing
exception should be upheld is to establish (a) whether the pleading lacks
particularity to the extent that it is vague; and (b) whether the vagueness causes
prejudice to the excipient. 6 Against these principles, I turn to each of the
exceptions raised.

Is the plaintiffs’ delictual claim excipiable?
[18] It is not disputed that UPL occupied and was in possession of a portion of
the warehouse. UPL’s first complaint is that ex facie paragraphs 4, 5, and 13 of
the particulars of claim:

4 Barclays National Bank Ltd v Thompson 1989 (1) SA 547 (A) at 553F-I.
5 Living Hands (Pty) Ltd and Another v Ditz and Others 2013 (2) SA 368 (GSJ) (Living Hands ) para 15 . A
summary of the applicable principles is also referred to in Merb (Pty) Ltd and Others v Matthews and Others
[2021] ZAGPJHC 693 paras 8-13.
6 Trope v South African Reserve Bank 1992 (3) SA 208 (T) ; Tembani and Others v President of the Republic of

South Africa and Another [2022] ZASCA 70; 2023 (1) SA 432 (SCA) paras 14 -20.

8



(a) there was until at least 12 July 2021, a contractual relationship between the
plaintiffs and UPL, pursuant to which the plaintiffs leased part of the warehouse
to UPL to generate income.
(b) the plaintiffs’ claim is based solely on a delictual cause of action. As a
matter of law, it is impermissible for the plaintiffs to bring a delictual claim in a
manner that ‘circumvents or undermines the contractual arrangement between the
parties’. Accordingly, the particulars of claim lack the necessary averments to
sustain an action.

[19] Both parties agreed that, properly characterised, the plaintiffs’ claim is
delictual in nature. UPL contends however that the particulars of claim indicate
that its occupation of the premises arose pursuant to a contract which the plaintiffs
now seek to avoid. The particulars of claim do not disclose the basis upon which
UPL came to occupy the premises, nor the terms governing such occupation.

[20] The plaintiffs expressly contended that they do not seek to enforce any
contractual right, nor do they allege defective or negligent performance of a
contract, or breach of any contractual obligation owed to them by UPL. On the
pleadings as they stand, the claim is framed exclusively in delict.

[21] UPL’s stance is that the delictual claim is incompetent, as its conduct
cannot be wrongful in delict where the parties’ relationship is governed by a
contract. It further argues that the pleading is excipiable because it constitutes an
impermissible attempt to circumvent a contractual relationship by recasting a
contractual dispute as a delictual claim.

9



[22] In support of this contention, UPL relies on the decision in Lillicrap,
Wassenaar and Partners v Pilkington Brothers SA (Pty) Ltd,7 as endorsed by the
Constitutional Court in Country Cloud Trading CC v MEC, Department of
Infrastructure Development.8 The authorities caution against extending delictual
liability to cases involving the negligent performance of contractual obligations,
particularly where contractual remedies are adequate and the parties have freely
allocated risk and responsibility by agreement. Generally referred to as the
‘concurrence problem ’, t he authorities emphasise that where parties have
deliberately structured their relationship by contract, the law should hesitate
before superimposing delictual liability in a manner that undermines their agreed
allocation of risk. On this footing, UPL submits that it is impermissi ble for the
plaintiffs to subvert their contractual dealings by advancing a delictual claim.

[23] UPL also relies on the decision of the Supreme Court of Appeal (SCA) in
Trustees, Two Oceans Aquarium Trust v Kantey & Templer (Pty) Ltd .9 In that
matter, the plaintiff pleaded alternative causes of action arising from structural
failure, alleging both breach of the contractual obligations and, in the alternative,
delictual liability for negligent design. The SCA held that the plaintiff had failed
to establish the existence of a legally cognisable duty in respect of the alleged
negligent decision and that the delictua l claim was therefore unsustainable. The
thrust of these authorities, according to UPL, is that wrongfulness in delict is not
established merely by alleging negligent conduct where the parties’ relationship
is, in substance, regulated by contract.

7 Lillicrap, Wassenaar and Partners v Pilkington Brothers (SA) (Pty) Ltd 1985 (1) SA 475 (A) (Lillicrap) at.501F-
G the court held that: ‘
‘A Court should therefore in my view be loath to extend the law of delict into this area and thereby eliminate

provisions which the parties considered necessary or desirable for their own protection. The possible counter to
this argument, viz that the parties are in general entitled to couch their contract in such terms that delictual liability
is also excluded or qualified, does not in my view carry conviction. Contracts are for the most part concluded by
businessmen. Why should the law of delict introduce an unwanted liability which, unless excluded, could provide
a trap for the unwary?’
8 Country Cloud Trading CC v MEC, Department of Infrastructure Development [2014] ZACC 28; 2015 (1) SA
1 (CC) (Country Cloud) para 63.
9 Trustees, Two Oceans Aquarium Trust v Kantey & Templer (Pty) Ltd 2006 (3) SA 138 (SCA) (Two Oceans).

10




[24] These cases emphasise that the determination of wrongfulness requires
careful consideration of public and legal policy, including whether the harm
complained of constitutes pure economic loss or physical damage. At the stage
of exception, the enquiry is whether the particulars of claim disclose facts which,
if proved, would establish wrongfulness. UPL’s complaint is that the plaintiffs’
pleading fails to do so.

[25] Properly understood, however, the principle articulated in Lillicrap does
not operate as a blanket prohibition on delictual claims between parties who may
be contractually linked. The same conduct may constitute both a breach of
contract and a delict, giving rise to a concurrence of actions and affording the
plaintiff an election as to which remedy to pursue. The authorities establish only
that where a claim is grounded in the improper performance of a contractual
obligation, and the parties have deliberately structured their relationship through
contract, delictual liability should not ordinarily be superimposed in a manner
that undermines their agreed allocation of risk.

[26] UPL submits that the court is not asked to infer the existence of a contract.
The submission is with respect correct, because the pleadings must be accepted
to be correct as they stand. Even so, the exclusionary rule in Lillicrap applies only
where the claim is founded on a breach of a contractual duty, and not where the
conduct complained of constitutes a breach of an independent delictual duty
imposed by law. As the SCA made it clear in Holtzhausen v Absa Bank ,10
Lillicrap is not authority for the general proposition that an action in delict is
precluded whenever a contractual claim is competent. Contrary to the assertions

10 Holtzhausen v Absa Bank Ltd 2008 (5) SA 630 (SCA). Formatted: German (Germany)

11



by UPL, where the same conduct gives rise to both contractual and delictual
liability, the plaintiff is free to elect which cause of action to pursue.

[27] Accepted ex facie , the plaintiffs’ particulars of claim allege physical
damage to their property. The claim is rooted in the alleged breach of a legal duty
imposed by the law of delict, namely the duty not to cause physical damage to
another’s property through negligent co nduct or omission. The existence of a
contractual relationship does not extinguish nor diminish UPL’s independent
delictual duty not to cause such harm. As stated in Two Oceans,11 ‘Negligent
conduct manifesting itself in the form of a positive act causing physical damage
to the property or person of another is prima facie wrongful. In those cases,
wrongfulness is therefore seldom contentious.’

[28] Although UPL criticises the plaintiffs for electing to pursue a delictual
claim, there is no legal bar to such an election. The plaintiffs’ claim, as pleaded,
falls outside the narrow exclusionary rule articulated in Lillicrap and affirmed in
Country Cloud. The duty not to cause physical damage exists independently of
any contractual relationship and is owed to all persons who may reasonably be
harmed by such conduct. The claim is directed at preventing physical harm to
property rather than protecting purel y contractual interests. The plaintiffs are
therefore not precluded from pursuing a delictual remedy, and this ground of
exception falls to be dismissed.

Failure to plead reasonable foreseeability of the setting alight of the
warehouse and lack of clarity on which event caused the damage


11 Two Oceans para 10.

12



[29] The second and third themes of exception concern an alleged failure to
plead foreseeability in relation to the setting alight of the warehouse, as well as
the absence of precise particulars of the actual cause of the damage from the series
of the chain of acts after the fire broke out. Even though these grounds were not
pursued with vigour during argument, it is nonetheless necessary to address them,
since their thrust forms part of the broader conspectus of alleged deficiencies in
the pleading of the essential elements of the delict. Ultimately, they are not merely
about foreseeability but whether causation was pleaded.

[30] UPL complains that:
(a) it is not alleged that the setting alight of the warehouse, or the use of water
to extinguish the fire, was reasonably foreseeable. Accordingly, the particulars
lack the averments necessary to sustain an action.
(b) Moreover, in any event, the setting alight of the warehouse and/or the use of
water constituted a novus actus interveniens, breaking the chain of causation.

[31] Connected to the above is the claim of irregularity, alternatively vagueness,
which UPL contend is embarrassing, and alternatively lack the averments
necessary to sustain an action because: The allegation in paragraph 15 that ‘the
bringing of the chemicals into the warehouse and onto the subject property was a
positive act which caused the aforesaid damage to the subject property ’ was
irreconcilable with the allegations in paragraphs 7 to 10, which refer to other
events, namely the (a) setting of the warehouse alight, (b) the runoff firefighting
water entering the sediment permeatin g the slab below; (c) the toxic elements
chemicals polluting the soil and (d) the contamination of the and pollution of the
soil as the alleged cause of the damage.

[32] The compliant is that i t is unclear which event is said to have caused the
damage, and the defendant would be prejudiced and embarrassed in having to

13



plead to the allegation. Paragraphs 14, 15, 16, and 18 allege that there was
‘damage’ to the property. It is not apparent from the particulars of claim what
damage, if any, was caused.

[33] As I understand it, this second aspect to the complaint is about factual
causation, aptly expressed by the court in International Shipping Co (Pty) Ltd v
Bentley12 as an inquiry into the ‘but for’ test. The court held, it i s designed to
determine whether the postulated cause is the causa sine qua non of the loss in
question. Consequently, if the wrongful conduct was not the cause of plaintiffs’
loss, then no legal liability can arise. The plaintiffs pleaded the overarching cause
of the damage, namely the presence of toxic chemicals brought onto the property,
the composition and nature of which they allege could only have been known to
UPL. They further pleaded a series of factual averme nts, commencing with the
outbreak of the fire and extending to a chain of subsequent conduct, which they
allege caused the damage to the property referred to in paragraph 31 above. It is
for the trial court, on the evidence before it, to evaluate what would have occurred
but for the wrongful conduct or, alternatively, the omission pleaded.

[34] Before dealing with the complaint relating to foreseeability, it is necessary
to interpose consideration of the alleged failure to plead a novus actus
interveniens (novus), since that allegation implicates causation and my finding
above. As pointed by the court in International Shipping,13 a demonstration that
the wrongful act was a causa sine qua non of the loss does not necessarily result
in legal liability. A court must consider the second enquiry of legal causation,
which examines whether the wrongful act is linked sufficiently closely or directly
to the loss for legal liability to ensue, or whether the loss is too remote. The court
further held that legal causation is a juridical problem, in the resolution of which

further held that legal causation is a juridical problem, in the resolution of which

12 International Shipping Co (Pty) Ltd v Bentley 1990 (1) SA 680 (A) (International Shipping) at 700G-H.
13 International Shipping at 700H-701F.

14



considerations of policy may play a role. Its essence thus lies in policy -based
limits on the extent of liability. (Own emphasis.)

[35] Regarding the alleged failure by the plaintiffs to plead a novus actus
interveniens, and the effect of the complaint calls for a revisit of the meaning of
a novus. The court in Fourie NO v Hansen and Another ,14 which referred, with
approval, to the description in Lawsa has relevance. The court held that:
‘The law relating to subsequent independent causes excusing a defendant from liability from
his initial negligent act has been succinctly summed up by the authors of Joubert (ed) The Law
of South Africa . . . where it is stated:
“An intervening cause is an independent, unconnected and extraneous factor or event
which is not foreseeable, and which actively contributes to the occurrence of harm after
the defendant's original conduct has occurred. Such an independent force can take t he
form of an intervening natural phenomenon, conduct by a third party, or even the
plaintiff's own conduct . . . A novus actus has the effect of completely neutralising the
causative potency of the defendant's original conduct, for it indicates that, even though
the causative link remains factually intact, the link between the conduct and the harm
is too tenuous.”’

[36] The existence of a novus would potentially serve to limit UPL’s liability to
the plaintiffs. The absence of those factual averments from the particulars can
hardly render the particulars excipiable. It is open to UPL to plead those facts in
its defence.

[37] Turning to the exception based on the failure to plead foreseeability, ex
facie the particulars, the plaintiffs traversed ‘foreseeability’ as an element of
‘fault’. As demonstrated in respect of the causation discussion above, the express
overarching allegation is that it was foreseeable that the chemicals could be
washed from the warehouse fire -fighting run-off water into the sediment below

washed from the warehouse fire -fighting run-off water into the sediment below

14 Fourie NO v Hansen and Another 2001 (2) SA 823 (W) at 842E=H.

15



the soil below the warehouse . The particulars allege that UPL failed to take
reasonable steps or measures to avoid contamination or spillage.

[38] The above must be read in context, and in conjunction with the assertion
in paragraph 23 of the particulars alleging that:
‘it was at all relevant times before and on 12 July 2021 foreseeable that if the warehouse and
its contents including the chemicals would burn, the fire combatting systems in the warehouse,
including the sprinkler systems, would discharge substantial volume s of water into the
warehouse which would wash the chemicals into the soil and a reasonable manager and
operator of a warehouse would either have refrained from bringing such chemicals into the
warehouse or would have taken steps to avoid contamination.’

[39] A proper approach is to assess whether the particulars, read as a whole,
give sufficient notice of the basis of the plaintiffs’ claim, rather than dissecting
each aspect of the chain in isolation. As pointed out by the court in Home Talk v
Ekurhuleni Municipality,15
‘What is important is that the pleadings should make clear the general nature of the case of the
pleader. They are meant to mark out the parameters of the case sought to be advanced and
define the issues between the litigants. In that regard, it is a basic principle that a pleading
should be so framed as to enable the other party to fairly and reasonably know the case he or
she is called upon to meet. These requirements in respect of pleadings are the very essence of
the adversarial system.’ (Footnotes omitted.)

[40] UPL’s complaint fails to properly consider the averments in paragraph 23
of the particulars . UPL imposes a rigid standard to pleadings by effectively
requiring the plaintiffs to plead that each event in the alleged chain of fault and
to pre-emptively “prove” that each detail across multiple links in the chain of
causation and that each of the details were foreseeable.16 This is inconsistent with

causation and that each of the details were foreseeable.16 This is inconsistent with

15 Home Talk Developments (Pty) Ltd and Others v Ekurhuleni Metropolitan Municipality [2017] ZASCA 77;
2018 (1) SA 391 (SCA) para 28.
16 Kruger v Van Der Merwe and Another 1966 (2) SA 266 (A) clarifies in the headnote that the doctrine of
foreseeability in relation to the remoteness of damage does not require foresight as to the exact nature and extent

16



established pleading standards, which recognise s that plaintiffs are not required
to anticipate every technical objection or to provide exhaustive proof of causation
at the pleading stage. That is for the trial court to evaluate.

[41] Imposing such a standard would elevate form over substance, contrary to
the court’s injunction in in Living Hands and the injunction to deal with
exceptions ‘sensibly’ and not in an overly technical or formalistic manner.17 The
plaintiffs’ pleadings, as drafted, provide adequate facts as to the nature of their
claim and sufficiently allege sequence of the cause(s) of the damage and
foreseeability in a manner consistent with the principles of pleading .
Accordingly, UPL’s complaint is overly technical and should be rejected.

Is the claim one for pure economic loss?
[42] As already alluded to, the joint practice notes stated that aspects of th e
fourth ground of the e xception were no longer persisted with. The contention
was that although paragraphs 14, 15, 16 and 18 of the particulars of claim refer
to damage to the property it is ‘not apparent whether from the plaintiffs’ claim is
for physical damage or pure economic loss, and the defendant would be
embarrassed in having to plead to these allegations’.

[43] It was submitted that the plaintiffs’ claim is, in substance, one for pure
economic loss in delict, notwithstanding the contractual relationship between the
parties. On that characterisation, UPL contended that the particulars of claim lack
the averments necessary to sustain a cause of action and are therefore excipiable.


of the damage. It is sufficient if the person sought to be held liable should reasonably have foreseen the general
nature of the harm that might because of his conduct befall the person exposed to a risk of harm.
17 Living Hands para 15. See also Telematrix para 3.

17



[44] As traversed and disposed of in the section dealing with the delictual nature
of the claim, it is well established in our law that a claim for pure economic loss,
being financial loss unaccompanied by physical harm to person or property or the
infringement of a recognised legal interest is not prima facie actionable because
the law of delict treats conduct causing physical damage to property differently
to conduct causing pure economic loss.18 Liability for such loss arises only where
the plaintiff establishes that the defendant’s conduct was wrongful, in the sense
that public or legal policy considerations justify the imposition of delictual
liability. I had found that the harm suffered by the plaintiffs is for physical
damage to the property, which constitutes a recognised and established category
of delictual damages.

[45] The plaintiffs’ damages claim is framed as follows:
‘The market value of the subject property without any improvement prior to the contamination
on 12 July 2021 was R100 million. After the contamination the market value was R1 million
with the result that the plaintiffs suffered damages in the amount of R99 million, alternatively,
the loss of the reasonable monthly rental which the plaintiffs could have earned was R81
million being the product of the reasonable rental at R750 000 per month multiplied by 108
months (12 July 2022 to 12 July 2031)’.

[46] I observe that the claim for R99 million relates to an alleged loss or
diminution in the value of the property following the contamination (‘the main
damages claim’). The rental the plaintiffs would have realised is pleaded in the
alternative (‘rental claim’). The latter must be considered against the averments
in the particulars of claim that the plaintiffs utilised a portion of the warehouse to
conduct a letting business; that UPL was in occupation of a portion of the
warehouse; and that the plaintiffs would, but for the alleged contamination, have

warehouse; and that the plaintiffs would, but for the alleged contamination, have
leased the reconstructed warehouse to generate income until at least 12 July 2031.

18 Two Oceans para 10.

18




[47] The legal principles governing the nature of the damages that the plaintiffs
may lawfully recover, and the distinction between the main damages claim for
the alleged loss or diminution in the value of the property on the one hand,
compared with the alternative claim pleaded for t he loss of rental were not
traversed fully either during the hearing or in the heads of argument. I accordingly
invited both parties to file supplementary submissions on the question whether
the plaintiffs’ damages claim is, in essence, one for pure economic loss.

[48] The debate as to whether the damages, as presently framed, constitute s a
claim for pure economic loss was obscured by two factors: the first was the
exception premised on the existence of a contractual relationship, and the dispute
about whether the plaintiffs have pleaded wrongfulness. That debate has been
put to rest because I have found the element of wrongfulness is presumed and
will generally not be controversial in cases as the present one.19

[49] To my mind, t he second obscuration arises from the correct measure of
damages in the circumstances of the present case. The starting point is in Trotman
and Another v Edwick20 which set out the difference between contractual and
delictual damages, and held that:
‘A litigant who sues on contract sues on contract sues to have his bargain or its equivalent in
money or in money and kind. The litigant who sues on delict sues to recover the loss which he
has sustained because of the wrongful conduct of another, in other words that the amount by
which his patrimony has been diminished by such conduct should be restored to him.’

[50] There can be no dispute in principle that the plaintiffs would be entitled to
recover the amount by which it suffered patrimonial loss. The main claim falls in

19 Two Oceans para 10.
20 Trotman and Another v Edwick 1951 (1) SA 443 (A) at 449B-C.

19



this category. That being so, the main damages claim for R99 million is based on
the difference between the pre-delict value and the post delict value of the
property. Damages based on the pre-delict value is one of the acceptable methods
for computing same.21 It is up to UPL to dispute the measure chosen to prove the
damages and the duty of the plaintiffs to demonstrate prove it through evidence
at the trial.

[51] With regards to the alternative claim for loss of rental. The fact that the
plaintiffs elected to bring a claim in delict does not mean the property was not
utilised for value. In my view, the claim for rental qualifies as one for pecuniary
loss. The plaintiffs seek to be recompensed for their prospective loss as an
alternative measure of their damages. T he dictum of the Court in Jowell v
Bramwell-Jones and Others22 is of assistance and states that:
‘There is no doubt that a plaintiff who has been the victim of a delict and has suffered some
damage will not be barred from suing for such damages, including prospective loss, merely
because the measure of damages is very difficult to assess. The Court will do its best on such
evidence as can be presented to it, and in so doing will weigh up probabilities and make do
allowance for uncertainties and contingent factors, having regard to the opinions of expects.
[sic]’
On appeal, the SCA accepted th is dictum that a claim for pr ospective loss is
competent and albeit fact dependent.23 What is required by Uniform rule 18(10)
is for the plaintiffs to set out their damages claim in a manner that will enable the
defendant reasonably to assess the quantum thereof. I find the plaintiffs to have
adequately set out the basis of their damages in respect of the main claim and the
alternative claim. It will be for the trial court in due course to assess whether the

21 De La Rey's Transport (Edms) Bpk v Lewis 1978 (1) SA 797 (A) at 80 3F, where the court held that there is no

good reason for rejecting the finding of the magistrate that ‘the value before conveyance was R500 - a finding
which was accepted by the Court a quo.’
22 Jowell v Bramwell-Jones and Others 1998 (1) SA 836 (W) at 902I-903E.
23 Jowell v Bramwell-Jones and Others 2000 (3) SA 274 (SCA) para 22.

20



benchmark utilised by the plaintiff for the value of the loss is the amount
quantified on a balance of probabilities.

Other exception grounds
[52] As already alluded to during argument, little reliance was placed on the
remaining grounds of exception, which concerned:
(a) whether the fire was extinguished by the plaintiffs or UPL and is a matter
capable of resolution by a request for further particulars for trial or by the leading
of evidence;
(b) the particulars of the measures allegedly not taken by a reasonable manager
to prevent the harm caused by the fire, was in my view adequately pleaded;
(c) whether the cause of action is founded on conduct or an omission, which
was pleaded in the alternative as demonstrated above, is permissible and does not
render the particulars excipiable; and,
(d) the identity of the relevant authorities that have not granted permission to
reconstruct the warehouse, is likewise capable of being addressed by a request
for further particulars for trial or by the leading of evidence.

Conclusion
[53] For the reasons stated above, the exception application falls to be dismissed
as the particulars reveal a cognis able cause of action and are not vague and
embarrassing. They are of sufficient particularity to enable UPL to plead. UPL
is not prejudiced thereby.

[54] There is no reason why the costs should not follow the results. In view of
the quantum of the claim, the degree of complexity and importance of the case to
both parties, they engaged the services of senior counsel. I can find no cogent
reasons to limit the costs . Accordingly, UPL is liable to pay the costs o f the
plaintiffs on scale C.

21




Order
[55] In the result, I make the following order:
1. The exception is dismissed
2. The defendant is ordered to pay the plaintiffs costs of on scale C
3. The costs shall include costs occasioned by employment of two counsel
where so employed.

________________
NTY SIWENDU J

Date of Hearing: 21 October 2025
Additional submissions: 3 and 10 November 2025
Delivery: 26 January 2026

Appearances:
For the Plaintiffs: Mr P F Louw SC
Instructed by: Kokinis Inc.
Locally represented by: ER Browne Incorporated

For the Defendant: Mr Alfred Cockrell SC,
With him: Mr Adrian Friedman
Instructed by: Bowman Gilfillan Inc.
Locally represented by: Hay & Scott Attorneys

22