Development Bank of Southern Africa v Hollard Insurance Company Limited and Another (096485/2023 ; 008205/2024) [2026] ZAGPJHC 30 (15 January 2026)

78 Reportability
Contract Law

Brief Summary

Execution — Payment Guarantee — The Development Bank of Southern Africa (DBSA) sought payment from Hollard Insurance Company Limited under an advance payment guarantee after GS Group defaulted on its obligations. The court had to determine whether DBSA's demand for payment was compliant with the terms of the guarantee and whether Hollard was liable to pay the certified amount due to DBSA.

Comprehensive Summary

Summary of Judgment


1. Introduction


This judgment concerned two consolidated motion applications heard in the Gauteng Division of the High Court, Johannesburg. The first application (case number 096485/2023) was brought by the Development Bank of Southern Africa (DBSA) against Hollard Insurance Company Limited (Hollard) as first respondent and G5 Group (Pty) Ltd (formerly known as NJR Projects (Pty) Ltd) as second respondent. DBSA sought payment under an advance payment guarantee issued by Hollard in relation to an advance payment made to the contractor under a construction contract.


The second application (case number 008205/2024) was brought by Hollard against NJR Projects (Pty) Limited, Mr Nhlabanele Jeophrey Ramahlaleroa, and Mr Pheane Edwin Sodi, seeking to enforce payment obligations arising from an advance payment guarantee, a performance guarantee, and associated indemnity and suretyship instruments. The second application followed a Part A order previously granted; the court dealt with Part B. During the hearing it emerged that NJR Projects had been liquidated, and the adjudication in Part B ultimately proceeded only in relation to Mr Sodi, with an existing payment order already granted against Mr Ramahlaleroa.


The general subject-matter of the consolidated dispute was the enforceability of on-demand construction guarantees (specifically an advance payment guarantee and a performance guarantee), the alleged non-compliance with guarantee demand procedures, allegations that the advance payment had been fully recouped, and an allegation that DBSA’s claim under the advance payment guarantee was tainted by fraud. In the second application, the further subject-matter was the enforcement of indemnity and suretyship obligations after Hollard had been called upon to pay DBSA.


2. Material Facts


DBSA is a public entity established under the Development Bank of Southern Africa Act 13 of 1997 and operates, among other functions, through its Infrastructure Delivery Division as an implementing agent for state infrastructure projects. During 2018 DBSA issued a tender (RFP 167/2018) for construction works at the Parys Department of Correctional Services. GS Group (Pty) Ltd, later referred to as G5 Group (Pty) Ltd, was appointed as contractor for a contract value recorded as R282,736,949.24 (including VAT), and a JBCC principal building agreement was concluded around 7 March 2019.


The contractor requested an advance payment to procure materials to meet timelines. DBSA required an advance payment guarantee, and Hollard issued the guarantee in DBSA’s favour. The guarantee recorded, among other items, a guaranteed sum of R23,060,000.00, a guarantee expiry date of 31 October 2022, and a recoupment regime reflected as commencing in May 2021 for 18 months, with a stated monthly recoupment figure of R1,281,111.11, and with an express note that where recoupment amounts or periods are irregular, a schedule should be attached. The guarantee set out a demand process requiring a first demand to the contractor, followed (after seven calendar days) by a demand to the guarantor, and contemplated provision of a recovery statement and payment certificate; it also stated that payment by the guarantor was due within seven days of receipt of the first written demand to the guarantor. The guarantee further provided that DBSA had an “absolute right” to arrange its affairs with the contractor and that the guarantee would be treated as a liquid document for purposes of obtaining a court order.


It was common cause that the contractor defaulted in relation to repayment/recoupment of the advance payment. DBSA recovered R10,931,544.09, leaving a balance claimed under the guarantee. On 11 October 2022, DBSA issued a notice of default to the contractor under the construction agreement, with notice of intended termination if default persisted. On 17 October 2022, the principal agent issued interim payment certificate no. 48 reflecting a negative certified amount of minus R11,547,075.65, indicating indebtedness by the contractor to DBSA in that amount.


DBSA issued demands in October 2022 seeking to call on the advance payment guarantee. A demand was emailed to Hollard on 28 October 2022, and DBSA also sent a demand to Hollard’s physical address on 31 October 2022. The demand documentation included correspondence to the contractor dated 21 October 2022 and a subsequent letter dated 25 October 2022 said to rectify an error in the earlier letter, together with interim payment certificate no. 48 reflecting the negative certified amount.


Hollard disputed liability on three grounds material to the first application. First, it alleged DBSA’s demand was non-compliant with the guarantee procedure and irregular in timing and supporting documentation, including an assertion that the recovery statement was only supplied after expiry and that recoupment should have been monthly. Second, it contended the advance payment had been fully recouped, relying on an interpretation of certificate 48. Third, it contended DBSA’s claim was tainted by fraud, pointing to discrepancies between different versions of certificate 48 and associated documents.


In the second application, it was undisputed that on 6 February 2018 NJR Projects, represented by Mr Ramahlaleroa and Mr Sodi, executed a deed of indemnity in favour of Hollard and that both individuals also executed a deed of suretyship and indemnity. Hollard issued a performance guarantee in favour of DBSA on or about 18 January 2019 for R28,273,694.93, and later issued the advance payment guarantee in February 2021 for R23,060,000.00.


DBSA made a demand on Hollard under the advance payment guarantee, triggering Hollard’s recourse claims in the second application. On 12 December 2023, DBSA further demanded payment from Hollard under the performance guarantee in the amount of R28,273,694.93, arising from NJR’s failure to complete the construction work and DBSA’s termination of the contract. During the hearing, NJR Projects’ liquidation was noted, and the court recorded that an order for payment had already been granted against Mr Ramahlaleroa, leaving the adjudication in Part B focused on Mr Sodi’s liability.


3. Legal Issues


In the first application, the central legal questions were whether Hollard was obliged to pay DBSA R11,547,075.65 (with the order later reflecting R11,547,075.00) under the advance payment guarantee, notwithstanding Hollard’s objections. This required determination of whether DBSA’s demands were procedurally compliant with the guarantee, whether the advance payment had been fully recouped such that Hollard’s liability had diminished to nil, and whether the claim fell within the fraud exception to the enforcement of autonomous guarantees.


These questions were principally questions of application of law to fact, with some issues of contractual interpretation (a legal question informed by context and wording) and evaluative findings on whether the papers permitted an inference of fraud and whether the procedural steps required by the guarantee were met.


In the second application, the central legal questions were whether Mr Sodi, as a signatory to a deed of indemnity and suretyship, was liable to Hollard for amounts Hollard was exposed to pay (or had to pay) under the advance payment guarantee and performance guarantee, and whether technical objections raised by Mr Sodi could defeat Hollard’s claim. This again involved application of legal principles concerning autonomous guarantees, the limited role of underlying contractual disputes, and the enforceability of indemnity and suretyship undertakings.


4. Court’s Reasoning


Interpretation and procedural compliance under the advance payment guarantee


The court addressed Hollard’s contention that DBSA’s demand was non-compliant, including allegations of premature demand, inadequate documents, irregular recoupment scheduling, and expiry of the guarantee before proper documentation was furnished. DBSA’s case was that its letter to the contractor dated 21 October 2022 constituted the first written demand contemplated by the guarantee, and that by 28 October 2022 the seven-day period had elapsed for purposes of calling on Hollard.


The court accepted DBSA’s explanation for the follow-up letter dated 25 October 2022, treating it as a rectification of a typographical error rather than a withdrawal of the earlier demand or a non-compliant reset of the process. The court considered the correction non-sinister and not prejudicial to Hollard, emphasising that both notices were received before 31 October 2022.


On the alleged unilateral change of recoupment terms, the court referred to an interpretive approach favouring a sensible and businesslike meaning, citing Natal Joint Municipal Pension Fund v Endumeni Municipality 2012 (4) SA 593 (SCA). It reasoned that the guarantee itself contemplated the possibility of irregular recoupment amounts or periods and required an attached schedule in such cases, which undermined the suggestion that only the fixed monthly recoupment reflected in the guarantee could apply in practice. The court also relied on the guarantee clause providing that DBSA had the absolute right to arrange its affairs with the contractor, which the court treated as including the ability to alter the recoupment regime as between employer and contractor without releasing the guarantor.


Regarding the complaint that the recovery statement was not attached or was provided late, the court accepted DBSA’s stance that payment was due within seven days of the demand to the guarantor and that the payment certificate constituted a liquid document under the guarantee’s terms. The court’s reasoning treated Hollard’s procedural objections as insufficient to defeat the call in the circumstances described in the papers.


Full recoupment contention


Hollard argued that interim certificate 48 showed the advance payment of R23,060,000.00 as fully recovered and that the guarantee, being an advance payment guarantee rather than a performance guarantee, was limited to repayment of that advance within the recoupment period.


The court rejected Hollard’s interpretation of full recoupment. It relied, among other considerations raised on the papers, on DBSA’s criticism of Hollard’s reading of the certificate and on the fact that the contractor (G5 Group) did not deny indebtedness. The court further considered DBSA’s supplementary affidavit point that Hollard itself claimed R39 million in the second application, which amount was stated to include the R11,547,075.00 claimed by DBSA, and treated this as undermining the proposition that DBSA had already recovered the full advance payment.


In addition, the court again referred to the guarantee clause giving DBSA an “absolute right” to arrange its affairs with the contractor, treating Hollard’s “full recoupment” argument as unsustainable on the papers and concluding that the contention had to fail.


Fraud allegation and the autonomy principle


Hollard’s fraud allegation was based on asserted discrepancies between two versions of interim payment certificate 48, including changes in item descriptions, the identification of architects, VAT differences, and the implication that one version suggested full recovery whereas another suggested otherwise. DBSA responded that the alterations were made by the principal agent at DBSA’s request to provide clarity and did not alter the certified amount due; DBSA supported this with confirmatory affidavits from individuals employed by the principal agent.


The court applied the fraud exception principles as articulated in Guardrisk Insurance Company Ltd and Others v Kentz (Pty) Ltd [2014] ZASCA 182, [2014] 1 ALL SA 307 (SCA), including the propositions that fraud is a narrow exception, the party alleging fraud bears the onus on a balance of probabilities, fraud is not lightly inferred, and that mere error, misunderstanding, or oversight—even if unreasonable—does not amount to fraud. The court also referenced the statement that it is insufficient to show incorrectness; knowledge of incorrectness and bad faith are required.


On that basis, the court held that the papers did not justify an inference that DBSA intended to defraud Hollard. The court treated DBSA’s explanations as consistent with error correction and clarification rather than fraudulent misrepresentation, and it noted that the contractor did not dispute the entries relied upon. The court further referred to Set Square Developments (Pty) Ltd v Power Guarantees (Pty) Ltd and Another [2025] ZASCA 64; 2025 (6) SA 552 (SCA) for the proposition that courts will not, save for proof of fraud, consider underlying contractual disputes when faced with an on-demand or unconditional guarantee, as doing so would undermine the autonomy of such guarantees.


The court therefore concluded that fraud had not been proved and that the autonomy of the guarantee remained operative. Hollard was found liable to pay DBSA under the advance payment guarantee.


Second application: indemnity/suretyship enforcement and the performance guarantee


For Part B of the second application, the court recorded that NJR Projects had been liquidated and that an order for payment had already been granted against Mr Ramahlaleroa, leaving only Mr Sodi’s liability for determination.


In relation to the advance payment guarantee component, the court reasoned that Mr Sodi’s defences mirrored Hollard’s defences in the first application. Since Hollard’s defences failed and Hollard was held liable to DBSA, the court concluded that Mr Sodi was liable to Hollard for the amount claimed in respect of the advance payment guarantee, namely R11,547,075.65.


In relation to the performance guarantee, the court dealt with technical objections advanced on Mr Sodi’s behalf, including contentions that Hollard had not shown the guarantees were issued on a written request by NJR and that NJR did not acknowledge receipt of a default payment notice. The court considered these objections inadequate on the papers, noting that Hollard alleged the guarantees were issued at the contractor’s request and annexed the written request in reply, and that there was no stated requirement for an acknowledgement signature where DBSA was satisfied with service and annexed the notice in its demand.


The court rejected the proposition that cancellation of the construction contract automatically cancelled the performance guarantee. It treated the applicable principle as settled: cancellation of the building contract does not automatically cancel an autonomous, on-demand performance guarantee. The court relied on Lombard Insurance Co Ltd v Landmark Holdings (Pty) Ltd and Others 2010 (2) SA 86 (SCA) for the principle that the guarantor’s obligation is independent of disputes under the underlying contract and that the only basis to escape liability is proof of fraud by the beneficiary. The court observed that fraud was not established in relation to the performance guarantee call.


Accordingly, the court held that Mr Sodi was liable to Hollard in respect of the sums claimed, and it granted a costs order against him, including the costs of two counsel where employed.


5. Outcome and Relief


In case number 096485/2023, the court ordered Hollard to pay DBSA R11,547,075.00 under the advance payment guarantee dated 21 February 2021 within seven days of the order. Hollard was further ordered to pay interest on that amount at the prescribed rate, calculated from 31 October 2022 (the date of demand) to the date of final payment. The respondents were ordered to pay DBSA’s costs on the party-and-party scale on Scale C.


In case number 008205/2024, the rule nisi issued on 23 April 2024 in respect of the first respondent was extended to 9 March 2026 at 10h00, and Hollard’s claim against the first respondent was postponed sine die with no order as to costs. The third respondent, jointly and severally with the second respondent (the one paying the other to be absolved), was ordered to pay Hollard R39,820,769.93, together with interest at 12.5% per annum from 30 January 2024 to date of final payment. The third respondent was also directed to pay Hollard’s costs on Scale C, including the costs of two counsel where so employed.


Cases Cited


Natal Joint Municipal Pension Fund v Endumeni Municipality 2012 (4) SA 593 (SCA)


Guardrisk Insurance Company Ltd and Others v Kentz (Pty) Ltd [2014] ZASCA 182, [2014] 1 ALL SA 307 (SCA)


Loomcraft Fabrics CC v Nedbank Ltd and Another 1996 (1) SA 812 (A)


Set Square Developments (Pty) Ltd v Power Guarantees (Pty) Ltd and Another [2025] ZASCA 64; 2025 (6) SA 552 (SCA)


Botha v Smuts and Another [2024] ZACC 22; 2024 (12) BCLR 1477 (CC); 2025 (1) SA 581 (CC)


Lombard Insurance Co Ltd v Landmark Holdings (Pty) Ltd and Others 2010 (2) SA 86 (SCA)


Legislation Cited


Development Bank of Southern Africa Act 13 of 1997


Constitution of the Republic of South Africa, 1996 (section 239)


Rules of Court Cited


No rules of court were expressly cited in the judgment.


Held


The court held that Hollard was liable to DBSA under the advance payment guarantee for the certified indebtedness reflected in interim payment certificate 48, and that Hollard’s defences based on alleged procedural non-compliance, alleged full recoupment, and alleged fraud were not sustained on the papers. The court treated the alleged irregularities and discrepancies as insufficient to establish fraud, applying the narrow fraud exception applicable to autonomous guarantees.


The court further held that, in the related recourse proceedings, Mr Sodi remained liable to Hollard under the deed of indemnity and deed of suretyship and indemnity, including for amounts arising from Hollard’s exposure under both the advance payment guarantee and the performance guarantee. Technical objections raised to Hollard’s claim did not defeat enforcement, and cancellation of the underlying construction contract did not, by itself, extinguish the independent obligation arising under the performance guarantee.


LEGAL PRINCIPLES


The judgment applied the principle that an on-demand guarantee (including construction-related guarantees) is treated as autonomous from the underlying construction contract, and that disputes about performance or cancellation under the building contract do not, without more, relieve the guarantor of its independent payment obligation where the guarantee’s demand requirements are met.


The judgment applied the principle that the fraud exception to enforcement of an autonomous guarantee is narrow. Fraud must be proved by the party alleging it, on a balance of probabilities, and will not be lightly inferred. The judgment applied the further principle that mere error, misunderstanding, or oversight, even if unreasonable, does not amount to fraud, and that it is insufficient to show that a beneficiary’s contention is wrong; knowledge of falsity and bad faith are required.


The judgment also applied the interpretive approach that contractual provisions should be construed to prefer a sensible, businesslike meaning over an interpretation producing insensible or unbusinesslike results, in assessing the guarantee’s recoupment provisions and the effect of clauses permitting irregular schedules and allowing the employer to arrange its affairs with the contractor.

REPUBLIC OF SOUTH AFRICA
IN THE HIGH COURT OF SOUTH AFRICA GAUTENG DIVISION, JOHANNESBURG
(1)
(2)
(3)
REPORTABLE: YES/ NO
OF INTEREST TO OTHER JUDGES: YES/NO REVISED.
DATE
In the matter between:
DEVELOPMENT BANK OF SOUTHERN AFRICA
and
HOLLARD INSURANCE COMPANY LIMITED
G5 GROUP (PTY) LTD
and in the matter between:
HOLLARD INSURANCE COMPANY LIMITED
and
NJR PROJECTS (PTY) LIMITED
NHLABANELE JEOPHREY RAMAHLALEROA
PHEANE EDWIN SODI
Case No: 096485/2023
Applicant
First Respondent
Second Respondent
Case No: 008205/2024
Applicant
First Respondent
Second Respondent
Third Respondent

This Judgment was handed down electronically and by circulation to the parties' legal representatives by way of email and shall be uploaded on Caselines. The date for hand down is deemed to be on 15th January 2026.
JUDGMENT
MALI J
Introduction
[1] This matter concerns two consolidated applications . The first application is between the Development Bank of Southern Africa (DBSA) and Hollard
Insurance Company Limited (Hollard). DBSA claims payment from Hollard in terms of an advanced payment guarantee issued by Hollard in respect of advanced payments made by DBSA to GS Group which used to be known as NJR Projects, the Contractor (second respondent), in terms of the construction contract concluded between DBSA and GS Group.
[2] The subject of the first application is the payment of the amount of R11 ,S47,07S.6S by Hollard who provided a payment guarantee on behalf of GS Group when DBSA advanced GS Group an amount of R23,060,000.00 to meet its obligations towards infrastructure
development.
[3] The second application is between Hollard and NJR Projects (Pty) Limited
(the first respondent), Mr. Nhlabanele Jeophrey Ramahlaleroa (the second
respondent) and Mr. Pheane Edwin Sodi (the third respondent). The claim advanced by Hollard is one for payment of an amount of money. Payment
is being claimed in terms of an advanced payment guarantee and a performance guarantee, together with a deed of indemnity, read in conjunction with a deed of suretyship and indemnity. The claim against NJR was triggered when the DBSA issued a demand on Hollard to make payment in terms of the advanced payment guarantee.
2

The first application
[4] DBSA is a public entity established, in terms of the Development Bank of Southern Africa Act, 1 and an organ of State as envisaged in section 239 of the Constitution of the Republic of South Africa, 1996. Amongst others, DBSA is an Infrastructure Delivery Division ("IDD"), which is an implementing agent for the South African National Department of Public Works and Infrastructure in various infrastructure projects.
[5] The first respondent is Hollard Insurance Company Limited; a limited liability company incorporated in accordance with the laws of Republic of South Africa. The second respondent is GS Group (Pty) Ltd, a private company incorporated in accordance with the laws of Republic of South Africa.
Background facts
[6] During 2018, the applicant in its capacity as an IDD, issued a tender for the appointment of a contractor for the construction of additional accommodation at the Parys Department of Correctional Services, in terms of tender number: RFP 167/2018. The second respondent was appointed to upgrade and construct additional accommodation for the Parys Department of Correctional Services for the value of R282,736,949.24 (including VAT). On or about 7 March 2019, upon acceptance of the appointment, the DBSA as the Employer and GS as the Contractor concluded a Principal Building Agreement JBCC (the "Construction Agreement").
[7] The Construction Agreement consisted of, inter alia, the Conditions of Contract and the Contract, including the Contract Data and the relevant material terms. Subsequently, G 5 Group requested advanced payment in the amount R35,009,018.50 from DBSA for the procurement of certain materials required under the Construction Agreement to comply with timelines. DBSA required GS Group to provide an advance payment
1 Act 13 of 1997.
3

guarantee (guarantee). Hollard issued the guarantee in favour of DBSA. Some of clauses of the guarantee provide as follows:
"Work means: Contract RFP 167/2018 - Parys Department of Correctional Services-Upgrading of Additional Accommodation.
Site means: Parys
Guarantee Advance Payment sum means (amount) R23 060 000.00
Guarantee expiry date means (date) 31 October 2022
Recoupment period (no of month) 18 (Eighteen)
1.1. Recoupment period commencement (Start month) May 2021
Monthly recoupment (amount) R1 281 111.11
Note! Where the recoupment amounts and/or periods are irregular a schedule of recoupment amount and dates is to be attached.
3.0. Subject to the Guarantor's maximum liability referred to in 1.0 the Guarantor hereby undertakes to pay the Employer the sum certified upon receipt of the documents identified in 3.1 to 3.3:
3.1 A copy of a first written demand Issued by the Employer to the Recipient stating that payment of a sum certified by the Principal
Agent has not been made in terms of the Agreement, and failing such payment within seven (7) calendar days, the Employer
intends to call upon the Guarantor to make payment in terms of
3.2;
3.2 A first written demand issued by the Employer to the Guarantor at the Guarantor's physical address with a copy to the Recipient
stating that a period of seven (7) calendar days has elapsed since
the first written demand in terms of 3.1 and that the sum certified
has still not been paid therefore the Employer calls up this Advance
Payment Guarantee and demands payment of the sum certified
from the Guarantor;
4

3.3 A copy of the recovery statement and payment certificate which
entitles the Employer to receive payment in terms of the Agreement
of the sum certified in 3.0.
6. Payment by the Guarantor in terms of 3.0 or 4.0 shall be made within seven
(7) calendar days upon receipt of the first written demand to the Guarantor.
7.The Employer shall have the absolute right to arrange his affairs with the Recipient in any manner which the Employer deems fit and the Guarantor
shall not have the right to claim his release from this Advance Payment
Guarantee on account of any conduct alleged to be prejudicial to the Guarantor.
10. This Advance Payment Guarantee, with the required demand notices in terms of 3.0 or 4.0, shall be regarded as a liquid document for the purpose
of obtaining a court order."
[8] It is common cause that GS Group defaulted towards the payment of the
advanced payment based on the guarantee . DBSA had only recovered an amount of R10,931,S44.09. On 11 October 2022, DBSA issued a notice of
default in terms of clause 36.1 of the Construction Agreement to GS Group
and gave notice of its intention to terminate the Construction Agreement
should the default persist for more than ten (10) working days from the date
thereof. On 17 October 2022, the Principal Agent certified an amount due
to the Group GS (by the Department) of minus R11,547,075.65 in interim
payment certificate. The certificate showed a minus sign (-48) indicating
that Group GS is indebted to DBSA in the amount R11,547,075.65.
[9] On 28 October 2022, DBSA sent a written demand to Hollard by email
demanding a payment of the certified amount of R11,547,075.65 owing to
it in consequence of Group G5's failure to make payment of the certified
amount within 7 calendar days of the demand . On 31 October 2022, DBSA
sent the same demand to Hollard's physical address. DBSA attached both
the demands to Hollard a copy of the letter dated 21 October 2022
addressed to Group G5 with an amount of R12 128 815.91 which was an

addressed to Group G5 with an amount of R12 128 815.91 which was an
error and the letter dated 25 October 2022 rectifying the certified amount
5

to R128 445.91 and a copy of interim payment certificate No. 48 reflecting
the certified amount of minus R11 547 075.65.
[10] On 3 November 2022, Hollard's attorneys responded to the demand of 28 October 2022, complaining that the demand was premature because 7 calendar days would not yet have lapsed from the date of demand which Hollard assumed to be 25 October 2022. Further, written exchanges
occurred and on 5 December 2022, Hollard's attorneys wrote to DBSA contending that the recovery statement had been materially altered to indicate a recovery due and that this alteration was intended to rectify a patent defect in the certificate previously furnished which was impermissible in law. Hollard concluded by welcoming any litigation
instituted by DBSA to recover the amount owing.
Issue
[11] The issue is whether Hollard is liable to pay DBSA an amount of R11 547 075.65 in terms of the Advance Payment Guarantee issued by Hollard on 21 February 2021.
Discussion
[12] Hollard raises 3 arguments: (i) DBSA has not complied with the procedures
relating to the demand; (ii) the advance payment advanced to the G5 Group has been recouped in full; and (iii) DBSA's claim is tainted with fraud.
Compliance
[13] Hollard's argument is that DBSA's demand for payment is non-compliant
with the terms of the advance payment guarantee and therefore fatally defective. This is because DBSA breached the clauses of the guarantee in that the recoupment had to occur on monthly basis. And in the event of breach on the part of the G5 Group, DBSA was supposed to have complied with clauses 3.1 to 3.3 of the guarantee. DBSA unilaterally changed the terms of the contract by not claiming monthly recoupments.
[14] Furthermore, DBSA's demands to G5 Group that payment be made by 28 October 2022 are premature because 7 calendar days would not yet have
6

lapsed from the date of demand - which Hollard assumed to be 25 October
2022. DBSA's advanced payment recoupment schedule is irregular and not in accordance with the provisions of the guarantee. The payment certificate
attached to the demand did not attach to it the accompanying recovery
statement. On the other hand, Hollard submitted that the guarantee had expired. On Hollard's calculations DBSA provided the recovery statement
on 14 November 2022 after the expiry of the guarantee.
[15] DBSA responding to the above referred to the letter of demand to G5 Group sent on 21 October 2022 which constitutes the first written demand in terms of clause 3.1 of the guarantee. Therefore, by 28 October 2022 the 7 calendar days would have expired when DBSA sent the demand to Hollard. Even if the Court were to find that the 21 October 2022 demand to the Contractor does not constitute the first written demand, the written
demand of 25 October 2022 which merely rectified the certified amount would not constitute non-compliance with the terms of the guarantee.
[16] According to DBSA, it is not mandatory to attach all the document referred to in clauses 3.1 to 3.3 in paragraph 9 above. For example, in present, the accompanying recovery statement was not attached to the certified
payment document. Hollard has an obligation to pay within 7 days of receipt of the first demand without having to be in receipt of all the above­
mentioned documents. This is in terms of clauses 6 and 10 of the guarantee. The payment certificate with an amount of R11 ,547,075.65 is a liquid document. There is nothing in these clauses pointing to any conditions like further documentation to be provided by DBSA.
[17] DBSA further submits that the demand dated 21 October 2022 was a valid demand and constituted the first written demand as contemplated in clause

3.1 of the guarantee. DBSA would have been entitled to wait for the full 7 calendar days (in terms of clause 3.1 of the guarantee) to expire before the 7 calendar days, within which Hollard was to make payment commenced
in terms of clause 3.2 of the guarantee.
[18] DBSA has explained the reason for the letter of demand of 25 October
2022. It is not the second demand, and it is not a cancellation of the
7

demand of 21 October 2022. It was meant to rectify the typographical error
in the letter of 21 October 2022 which depicted the amount of
R12 128 915.91 instead of the amount of R12 8445.91 certified by the
Principal Agent. There is nothing sinister in DBSA's explanation, human
error or typographical errors happens. Of utmost importance herein is that
in principle the letter of 21 October 2025 remains the correct demand. To
ease matters, DBSA does not seek to increase the value of the demand,
the rectification is not prejudicial to Hollard. Both notices were received by
Hollard before 31 October 2022.
[19) Pertaining to the allegation of unilateral changes, a sensible meaning
should be preferred to one that leads to insensible or unbusinesslike
result.2 It would not been sensible for DBSA to make a monthly recoupment
of R1 281 111.11, contrary to real time different recoupment amounts and
schedules. Furthermore, the guarantee expressly provides for recoupment
amounts and/or periods that are irregular or different to the recoupment
schedule as contemplated in the guarantee. It is for this reason that it is
expressly recorded in the guarantee that where the amounts and/or
periods are irregular, a schedule of recoupment amounts and dates are to
be attached.
Did DBSA make full recoupment?
[20) Hollard's argument is that DBSA relies on certificate 48 to pursue its claim
for payment. Hollard's interpretation is that the certificate reveals that an
advance payment in the amount of R23 060 000.00 has been made and
that the amount has been fully recovered. The advance payment
recoupment is unequivocally recorded as R23 060 000.00.
[21) Hollard's submissions are that the guarantee is an "advance payment
guarantee". It is not a performance guarantee in terms of which Hollard
undertakes to make payment of money in lieu of performance. What is
guaranteed is the due repayment of the advance payment, totaling the
2 Natal Joint Municipal Pension Fund v Endumeni Municipality 2012 (4) SA 593 (SCA).
8

amount of R23 060 000 .00, which DBSA had paid to G5 Group, the contractor. The guarantee was scheduled to expire on 31 October 2022.
[22] The duration of the guarantee is limited to the time it would take to recover
the advance payment which has been made. DBSA omitted the agreed
payment terms. The repayment period in which the advance payment had to be repaid in terms of the guarantee is a set period of 18 months, commencing in May 2021. Regular monthly repayments , in the amount of R1 281 111.11 per month, were required to be recouped from the Contractor . As such, the recoupment amount and the recoupment period
are fixed and regular.
[23] In terms of the guarantee, Hollard undertook payment to the applicant a sum of money, as certified, upon receipt of the documents listed in clauses 3.1 to 3.3 of the guarantee . Clause 1.2 of the guarantee , if read with clause
1.2.2, limits Hollard's liability to the outstanding diminishing amount of the capital amount guaranteed . In terms of the advance payment guarantee it was agreed that a fixed amount would be recovered monthly. Deductions
in respect of each recoupment were required to be made on each of the monthly payment certificates that are issued to the Contractor.
[24] In retort to the above DBSA disputes that there was a full recovery as is evident from certificate 48, DBSA criticises Hollard's interpretation of the certificate, on the backdrop of the recovery statement and G5 Group's documents. G5 Group does not deny that it is indebted to DBSA in terms
of the amount claimed from Hollard. In fact, Hollard does not dispute that G5 Group sent an "Application for advance in respect of unfixed material off site in terms of the conditions of contract backed by advance guarantee" in August 2022. GS Group states that: "Current Surplus (Shortfall) on recovery" is an amount of R12 513 516 . 60).

[25] Moreover, in the supplementary affidavit filed by DBSA, DBSA states that Hollard claims R39 Million in the second application herein. The amount of R39 Million is inclusive of R11 ,547,075.00 claimed by DBSA from Hollard in terms of the guarantee . Thus, on Hollard's own version DBSA has not recovered the full amount from GS Group.
9

[26] Furthermore, Hollard's submission ignores that the guarantee also expressly entitles DBSA as the Employer the absolute right to arrange its affairs with G5 Group as the Contractor in any manner it deems fit. This includes the absolute right to alter the recoupment regime. There is nothing
more to be said about this, Hollard's contention that DBSA has made full recoupment must fail.
Is DBSA 's claim tainted with fraud?
[27] Hollard argues that DBSA's claim might be fraudulent due to discrepancies
between two versions of payment certificate 48. Hollard compares "FA4" (attached to the founding affidavit) with a different version attached as part of "FA?'' (accompanying DBSA's demand dated October 28, 2022) to highlight material changes, despite both certificates sharing the date of Monday, October 17, 2022.
[28] Key differences highlighted by Hollard include Item 2.2 Description: On FA4, the item description reads "materials off site", while on FA?, it reads "materials on site". Architects Listed: The FA? version lists Gildenhuys & Jooste as architects; Hollard contends it is unlikely the same architects
would issue two different certificates with the same number and date. There is also an issue pertaining to VAT Amount (Item 12): The VAT entry on FA4 is approximately R2.4 million higher than the entry for the same item on FA?.
[29] Furthermore, Advance Payment Recovery (Item 13): which is most concerning to Hollard is that FA4 records the advance payment of R23,060,008.00 as fully recovered, whereas the annexure to FA7 suggests
otherwise.
[30] DBSA, in reply, explains the discrepancies. It states that the alterations
visible in Annexure "FA?'' were made by the Principal Agent at DBSA's request to provide clarity to Hollard regarding the interpretation of the recovery statement. DBSA emphasises that these clarifications did not alter the certified amount due of R 12,128,455.91 .
10

[31] DBSA rejects Hollard's legal objection, arguing that the Principal Agent, in exercising its duty to certify amounts due and to act with reasonable judgment, has the implied power to correct errors reasonably. This explanation is supported by the confirmatory affidavits of Mr. Jooste and Mr. De Beer, both employed by the Principal Agent, who verified the challenged entries.
[32] In Guardrisk Insurance Company Ltd and Others v Kentz (Pty) Ltd,3 the SCA dealt with performance guarantee, whereas in the present case the subject matter is the advanced payment guarantee, nevertheless the common issue is the allegation of fraud. The SCA stated the following:
"(17) It would be useful to briefly consider the legal position in relation to the fraud exception. It is trite that where a beneficiary who makes a call on a guarantee does so with knowledge that it is not entitled to payment, our courts will step in to protect the bank and decline enforcement of the guarantee in question. The fraud exception falls within a narrow compass and applies where:
the seller, for the purpose of drawing on the credit, fraudulently
presents to the confirming bank documents that contain, expressly or by implication, material representations of facts that to his (the seller's) knowledge are untrue.'

(18) In so far as the fraud exception is concerned, the party alleging and relying on such exception bears the onus of proving it. That onus is an ordinary civil one which has to be discharged on a balance of probabilities but will not lightly be inferred. In Loomcra'ft Fabrics CC v Nedbank Ltd & another it was pointed out that in order to succeed in respect of fraud exception, a party had to prove that the beneficiary presented the bills (documents) to the bank knowing that they contained material misrepresentations of fact upon which the bank would rely and which they knew were untrue. Mere error, misunderstanding or oversight, however unreasonable, would not amount to fraud. Nor was it enough to show that the beneficiary's contentions were incorrect. A party had to go further and
3 [2014] ZASCA 182, [2014]1 ALL SA 307 (SCA) at (17] - [18].
11

show that the beneficiary knew it to be incorrect, and the contention was advanced in bad faith." [Emphasis added]
[33] The SCA dismissed the appeal having held as follows:4
"[22] In my view, Guardrisk has not established the fraud exception. In fact, what it has sought to do is to have this court determine the rights and obligations of the parties .... The finding by the high court that the appellants had not discharged the onus resting on them to establish fraud on the part of Kentz cannot be faulted. I agree with the reasoning of the high court that:
'The evidence before court clearly demonstrates that Kentz held the view that it was entitled to lawfully pursue its claims under the guarantees. The mere fact that it presented its claims knowing that Brokrew held a contrary view about the cancellation with which it disagreed is not fraudulent."'
[34] It cannot be inferred from the papers before court that DBSA intended to defraud Hollard. As clearly stipulated in Guardrisk, mere error, however unreasonable, would never amount to fraud. More is required. To make matters worse, G5 Group does not dispute a single entry by DBSA. DBSA went into lengths explaining the entries for the ease of reference of all involved. I state this fully aware about the autonomous status of the guarantee, even if G5 Group had issues, it would not have turned on anything.
[35] Furthermore, in Set Square Developments (Pty) Ltd v Power Guarantees (Pty) Ltd and Another , 5 the court held that:
4 Id at (22).
" ... reliance on 'mistake' is unsustainable on the facts of this case. It bears emphasis that where parties seek relief on the ground of mistake, they must explicitly plead the details as to the nature of the mistake and show that the mistake was reasonable. In any event, invoking either unilateral or mutual error to impugn the underlying contract in this case is precluded because, as I have explained, our courts will not, save for proof of fraud, consider the
5 (2025] ZASCA 64; 2025 (6) SA 552 (SCA) at (33].
12

underlying contractual disputes between an employer and a contractor when
faced an on-demand or unconditional performance guarantee. To do so
would undermine the autonomous nature and efficacy of such guarantee."
[36] Gleaned from the above, the autonomy of the guarantee is sacrosanct
unless there is a proven case of fraud, which in this case has not been
proven. In conclusion, under the circumstances, Hollard did not adduce
sufficient evidence of fraud on the part of DBSA. Hollard's contention
cannot succeed. Overall, Hollard is found liable to pay DBSA in term of
the advance payment guarantee.
The Second Application
[37] This application is preceded by Part A which was granted against the
respondents. This court is seized with Part B, wherein Hollard seeks an
order for payment against the first, second and third respondents in the
amount of R39 820.769.93 with interest, in terms of the notice of motion.
as well as the order directing the third respondent (Mr. Sodi) to indemnify
Hollard against all costs incurred by Hollard in opposing the application
brought by DBSA (the first application). It transpired during the hearing of
both applications that NJR Projects just got liquidated. An order for
payment was already granted in favour of Hollard against Mr.
Ramahleleroa and the adjudication is only against Mr. Sodi in this
application.
[38] The claim advanced by Hollard is one for payment of an amount of money.
Payment is being claimed in terms of an advanced payment guarantee and
a performance guarantee together with a deed of indemnity, read in
conjunction with a deed of suretyship and indemnity. It is not in dispute
that on 6 February 2018 NJR Projects duly represented by Mr.
Ramahleleroa and Mr. Sodi signed and executed a deed of indemnity in
favour of Hollard. Mr. Ramahleleroa and Mr. Sodi further signed and
executed a written deed of suretyship and indemnity in favour of Hollard.
[39] On or about 18 January 2019, Hollard issued a performance guarantee in

[39] On or about 18 January 2019, Hollard issued a performance guarantee in
favour of DBSA for the obligations of NJ R Projects in the amount of
13

R28 273 694.93 (Twenty-Eight Million, Two Hundred and Seventy-Three
Thousand, Six Hundred and Ninety-Four Rands and Ninety-Three Cents).
[40) Thereafter and on or about 19 February 2021, Hollard issued the advanced
payment guarantee in favour of DBSA for the obligations of NJR which later became G5 Group in the amount of R23 060 000.00 (Twenty-Three Million
and Sixty Thousand Rands); as discussed in the first application. I shall commence with the claim for the advance payment guarantee.
[41) The claim against NJR/G5 Group was triggered when the DBSA issued a demand on Hollard to make payment in terms of the advanced payment
guarantee.
[42) Pertaining to the advanced payment guarantee Mr. Sodi makes common
cause with Hollard in the first application in decrying non-compliance and fraud by DBSA. This submission is coupled with the argument that the guarantee expired on 31 October 2022. In essence if the first application is decided in Hollard's favour, then Mr. Sodi literally walks in this application.
[43] Without repeating the arguments and discussion in the first application, I have already decided that Hollard is not successful. It follows that Mr. Sodi is liable for the amount claimed by Hollard in terms of the advanced
payment guarantee of R11,547,075.65.
[44] Regarding the Performance Guarantee, on 12 December 2023, Hollard received a written demand for payment from DBSA in the amount of R28 273 694.93 (Twenty-Eight Million, Two Hundred and Seventy-Three
Thousand, Six Hundred and Ninety-Four Rands and Ninety-Three Cents). The demand originates from NJR's failure to complete the construction
work and DBSA having terminated its contract with NJR.
[45] Lot of technical arguments were advanced on behalf of Mr. Sodi, for example, one of the arguments is that Hollard does not state that the guarantees were issued on the written request of NJR. In the founding

affidavit, Hollard states that the guarantees were issued at the request. So, what is missing is written request. In the replying affidavit, Hollard annexed
14

the written request. There is nothing peculiar about this.6 In the present, Hollard's case is clear from the affidavits read with the relevant annexures. Hollard alleged what it needs to allege, that the claim is based on indemnity
and suretyship.
[46] Another technical point advanced against Hollard is that NJR did not sign for the acknowledgement for the default payment notice sent by DBSA.
There is no requirement for this, of importance is that a copy of the default notice was annexed to DBSA's demand for payment and DBSA was satisfied with the service.
[47] Another argument mounted against Hollard is that when the contract was cancelled by the employer it follows that the performance guarantee was cancelled. The trite principle is that if a contractor is in breach with the employer, the employer can ask for specific performance and/or cancellation. If excused from further performance, the contractor will still liable for damages. It is trite that the cancellation of a building contract does not automatically cancel the performance guarantee, due to the autonomy principle which treats the guarantee as an independent, "on­demand" undertaking for payment.
[48] In Lombard Insurance Co Ltd v Landmark Holdings (Pty) Ltd & others7 the SCA held that: " ... [a] guarantee ... is not unlike irrevocable letters of credit issued by banks and used in international trade, the essential feature of [a guarantee] is the establishment of a contractual obligation on the part of a bank to pay the beneficiary (seller). This obligation is wholly independent of the underlying contract ... Whatever disputes may subsequently arise between buyer and seller is of no moment insofar as the bank's obligation is concerned. The bank's liability to the seller is to honour the credit. The bank undertakes to pay provided only that the conditions specified in the credit are met. The only basis upon which the bank can escape liability is proof of fraud on the part of the beneficiary." In the present

case there are no allegations of fraud proven against Hollard, they are not even alleged.
~See Botha v Smuts and Another[2024] ZACC 22; 2024 (12) BCLR 1477 (CC); 2025 (1) SA 581 (CC) at [64]- [66]
7 201 0 (2} SA 86 para 20.
15

[49) For the foregoing the defenses raised against Hollard must not succeed. In conclusion the third respondent is liable to pay Hollard in respect of the guarantee.
Order
In the result, the following orders are granted:
1. In respect of case number 096485/2023:
1.1. The first respondent is ordered to make payment to the applicant in the amount of R11 547 075.00 (Eleven Million, Five Hundred and Forty-Seven Thousand and Seventy-Five Rands) in terms of the Advance Payment Guarantee issued by the first respondent dated 21 February 2021, within seven days of this order.
1.2. The first respondent is ordered to pay interest on the amount of R11 547 075.00 (Eleven Million, Five Hundred and Forty-Seven
Thousand and Seventy-Five Rands) at the prescribed rate of interest, from the date of demand, 31 October 2022, to date of final payment.
1.3. The respondents are ordered to pay the applicant's costs on party and party scale on Scale C.
2. In respect of case number 8205/2024:
2.1 The rule nisi issued by Judge Keightley on 23 April 2024, in respect of the first respondent is extended to 9 March 2026 at 1 0h00.
2.2 The applicant's claim against the first respondent is postponed sine die, no order as to costs.
2.3. The third respondent is ordered, jointly and severally together with the second respondent, the one paying the others to be absolved: -
2.3.1 To make payment to the applicant in the sum of
R39 820 769.93.
2.3.2. Pay interest at 12.5% per annum from 30 January 2024 to date of final payment.
16

2.4. The t hird respondent is directed to pay the applicant's costs, such
costs to include the costs of two counsel, where so employed and to
be taxed on scale C.
N.P. MALI
E HIGH COURT
JOHANNESBURG
Heard on: 24 July 2025
Delivered on: 15 January 2026
APPEARANCES :
First Applicat ion:
For the Applicant:
Instructed by:
For the First Respondent:
Instructed by:
For the Second Respondent:
Instructed by:
Second Application:
For the Applicant:
Instructed by:
Adv L. Segeels-Ncube
Cliff Dekker Hofmeyr Incorporated
072 764 7424 or joe.whittle@cdhlegal.com
Adv R. Stockwell SC and Adv I. L. Posthumus
Moll Quibell and Associates
(010) 446 5621 or corrie@mqlaw.co.za
Adv W.B. Pye SC and Adv N. Loopoo
Bowes & Turner Inc
083 601 2187 or andrew@tbt.co.za
Adv I. L. Posthumus
Moll Quibell and Associates
(010) 446 5621 or corrie@mglaw .co.za
17

For the First and Third Respondents :
Instructed by:
Adv W.B. Pye SC and Adv N. Loopoo
Bowes & Turner Inc
083 601 2187 or andrew@tbt.co .za
18