Cunninghame Construction CC t/a Ladysmith Construction v Homestead Hospitality Holdings SA (Pty) Ltd and Others (D13047/2024) [2025] ZAKZDHC 81 (4 December 2025)

55 Reportability
Arbitration Law

Brief Summary

Arbitration — Review of arbitration award — Application to set aside award under s 33(1)(b) of the Arbitration Act 42 of 1965 — Applicant alleging gross irregularity and exceeding of powers by Appeal Tribunal — Tribunal conflating distinct issues of stoppage and abandonment — Court finding that the grounds for review were not raised during the appeal process — Application dismissed with costs.

IN THE HIGH COURT OF SOUTH AFRICA
KWAZULU-NATAL LOCAL DIVISION, DURBAN

CASE NO: D13047/2024

In the matter between:

CUNINGHAME CONSTRUCTION CC APPLICANT
t/a LADYSMITH CONSTRUCTION

and

HOMESTEAD HOSPITALITY HOLDINGS SA (PTY) LTD FIRST RESPONDENT

THE HONOURABLE RETIRED SECOND RESPONDENT
JUSTICE FDJ BRAND

THE HONOURABLE RETIRED THIRD RESPONDENT
JUSTICE GRAHAM LOPES

ADVOCATE MAURICE PILLEMER SC FOURTH RESPONDENT

THE HONOURABLE RETIRED FIFTH RESPONDENT
JUSTICE MJD WALLIS


ORDER


It is hereby ordered that:
1. The application is dismissed with costs, on scale C, including the costs of
two Counsel.
___________________________________________________________________
JUDGMENT
___________________________________________________________________

2

Ramdhani AJ

Introduction
The parties
[1] The applicant is Cuninghame Construction CC t/a L adysmith Construction,
which shall hereinafter be referred to as Ladysmith Construction.

[2] The first respondent is Homestead Hospitality Holdings SA (Pty) L td, which
shall hereinafter be referred to as Homestead.

[3] The second to fourth respondents are identified as the Appeal Arbitrators, who
shall collectively be referred to as ‘the Appeal Tribunal’.

[4] The fifth respondent is the Arbitrator and shall hereinafter be referred to as the
Arbitrator.

The relief
[5] Ladysmith Construction has invoked the provisions of s 33(1)(b) of the
Arbitration Act 42 of 1965 (‘the Act’). Section 33(1)(b) of the Act provides as follows:
‘(1) Where-

(b) an arbitration tribunal has committed any gross irregularity in the conduct
of the arbitration proceedings or has exceeded its powers; or

the court may, on the application of any party to the reference after due notice to the other
party or parties, make an order setting the award aside.’

[6] Ladysmith Construction seeks an order that:
‘1. The arbitration award of the Appeal Tribunal dated 12 September 2024 is reviewed and
set aside.
2. The arbitral disputes:
2.1 are remitted to a new Appeal Tribunal who are to be agreed between the parties within
20 days; and
2.2 failing compliance with paragraph 2.1 above, are remitted to the Association of
Arbitrators (Southern Africa) NPC for reconsideration by the Arbitration Appeal Tribunal

3

appointed by it to make a fresh award in accordance with Sections 32(2) of the Arbitration
Act of 1965.’

[7] Ladysmith Construction avers that the Appeal Tribunal’s award falls to be set
aside in terms of s 33(1)(b) of the Arbitration Act on the main and principal ground
that the Appeal Tribunal exceeded its powers by determining the appeal beyond the
ambit and four corners of the pleadings, by inter alia conflating the stoppage issue
with the issue of an abandonment of the site/project ; which was impermissible
because the pleadings required that both be considered as distinct and separate
questions. During the course of the submissions and interaction with the court in this
review application , the applicants Counsel informed the court that the aforesaid
ground of the Appeal Tribunal straying and not confining itself to the pleadings was
not raised with the Appeal Tribunal during the appeal.

[8] In the appeal that served before the appeal tribunal, the appeal tribunal also
made an analysis as to whether the arbitrator determined the termination issue
outside of and beyond the pleadings.1 In the appeal, Homestead contended that the
arbitrator went beyond his mandate in treating the existence of the payment dispute
as a basis for finding that Homestead did not establish that there was no lawful
excuse for the intimation that the contractual performance was not going to be
forthcoming. In this regard the appeal tribunal was in agreement with Homestead’s
complaint and found that the award by the arbitrator did not deal with the fact that an
objection was raised and dealt with on the basis that no reliance was being placed
by Ladysmith Construction on the payment in dispute providing a lawful excuse for
the refusal to comply with the contractual obligations.


The arbitration and the arbitrator’s separation directive
[9] The arbitration emanated from a settlement agreement in winding -up
proceedings launched by Ladysmith Construction against Homestead. In terms of

proceedings launched by Ladysmith Construction against Homestead. In terms of
clause 2.5 of the arbitration agreement, the arbitration was broadened to determine
which party validly terminated the construction contract and whether in effect,
Homestead accrued a right of termination.

1 Award by the Appeal tribunal, paragraphs 33,36 and 37

4


[10] Consequent upon the settlement agreement being concluded, the parties
thereupon exchanged their respective pleadings in the arbitration which comprised of
Homestead’s initial statement of claim and thereafter Ladysmith Construction’s
statement of defence and claim-in-reconvention.

[11] Clause 2.5 of the settlement agreement is recorded as follows:
‘The disputes between the parties, briefly summarized (and is subject to being fully
ventilated in the exchange of pleadings in arbitration) are inter alia:
2.5.1 the termination of the contract/s by the respondent;
2.5.2 the final amount due to/due by Ladysmith Construction (applicant);
2.5.3 the alleged defects in the applicant’s works;
2.5.4 which party is liable for the cost of the application and the cost of the arbitration.’

[12] In terms of clause 2.5.1 of the settlement agreement, the parties agreed that
the dispute between the parties related inter alia to ‘the termination of the contract/s
by the respondent namely Ladysmith Construction ’. In terms of clause 2.5 more
specifically the preamble thereto, the parties further agreed that the issues that arose
for determination more particularly clauses 2.5.1 to 2.5.4 was ‘subject to being fully
ventilated in the exchange of pleadings in the arbitration’.

[13] Clause 2.5 of the settlement agreement, more particularly clause 2.5.1 thereof
clearly recorded and documented that one of the issues and disputes between the
parties was in regard to ‘the termination’ of the contract/s by Ladysmith Construction.
Such termination would be ventilated in the exchange of pleadings in the arbitration.

[14] On 22 July 2022 the parties convened their first pre-arbitration meeting before
the Arbitrator.It was agreed that the first issue which the Arbitrator was tasked to
determine was whether the common cause termination of the contract concluded
between Ladysmith Construction and Homestead was either a lawful termination at

between Ladysmith Construction and Homestead was either a lawful termination at
the instance of Ladysmith Construction , or a lawful termination at the instance of
Homestead.2


2 Annexure ‘FA1’, Ladysmith Construction’s founding affidavit.

5

[15] After the parties exchanged their respective pleadings, Ladysmith
Construction applied for a separation of issues, which was opposed by Homestead.
On 4 March 2023 and pursuant to an opposed application for separation , the
Arbitrator issued a directive3 on the termination issue. This directive was issued after
the parties made submissions on whether the termination issue should be decided
as a separated issue.

[16] Paragraph 2 of the directive issued by the Arbitrator recorded that the
separated issue involved a determination of the following questions:
‘(a) whether the respondent abandoned the site on 9 May 2022 thereby evincing an intention
no longer to be bound by the construction contract between the parties?
(b) whether the respondent’s conduct in lodging and serving the application for provisional
winding-up order in relation to the claimant evinced an intention no longer to be bound by
the construction contract between the parties?
(c) whether the abandonment of the site on 9 May 2022, if established, when taking together
with the lodging and service of the application for provisional winding -up order evinced an
intention of the respondent no longer to be bound by the con struction contract between the
parties?
(d) if the answer to any one of the three previous questions is in the affirmative, was the
claimant’s cancellation of the contract by way of the emails of 11 and 12 May 2022
(annexure SOC5.1 and 5.2 to the statement of claim) a lawful cancellation of the contract?
(e) if the claimant was not lawfully entitled to cancel the contract, did the purported
cancellation constitute a repudiation thereon, accepted by the respondent, that brought
about the termination of the contract.’

[17] After the directive was issued by the Arbitrator, Homestead effected
amendments to its pleadings by the incorporation and inclusion of paragraphs 27A,
27B and 27C. By way of paragraph 27 of Homestead’s amendment statement of
claim, Homestead averred the following:

claim, Homestead averred the following:
‘Before the final agreed completion date and from 9 to 11 May 2022 the respondent
abandoned the Homestead project and left the site, alternatively was in the process of
abandoning the Homestead project and leaving the site. The respondent then on 11 May
2022 instituted the final winding -up application referenced above. The conduct of the
respondent in abandoning the Homestead project and instituting liquidation proceedings

3 Annexure ‘FA2’, Ladysmith Construction’s founding affidavit at 38–39.

6

constitutes a clear rejection of the agreement which repudiation the claimant accepted and
cancelled the agreement with immediate effect by email addressed on 11 May 2022 .
Thereafter claimant reaffirmed its termination through its attorneys and again in the
answering affidavit in the winding -up application. Copies of the letters of termination are
annexed hereto marked SOC5.1 and SOC5.2.’

[18] Both the arbitration and the appeal proceeded on a very limited ‘termination
issue’ which had been agreed upon between the parties. By way of further
amendments to its statement of claim and in regard to the termination issue ,
Homestead pleaded as follows:
‘ 27A.
From 9 to 11 May 2022 the respondent abandoned alternatively was in the process
of abandoning the Homestead project, abandon alternatively was in the process of
abandoning the site, stopped work and removed both its equipment as well as
materials belonging to the claimant. A list of equipment and materials belonging to
the claimant which were removed by the respondent is annexed hereto marked as
SOC5A.”

27B.
The conduct of the respondent in removing equipment and material belonging to
the claimant, in circumstances where it had no lawful right to do so, constituted a
material breach of the agreement.

27C.
In addition to the respondent’s repudiation of the agreement as recorded in
paragraph 27 above, the respondent’s repeated and persistent material breaches of
the agreement as recorded in paragraphs 27A – 27B were justification for the
claimant’s termination of the agreement.’


The arbitrator’s award
[19] On 1 February 2024 , the Arbitrator delivered his award in regard to the
termination issue.4 In regard to the termination issue, the Arbitrator found inter alia
that:

4 Annexure ‘FA8’, Ladysmith Construction’s founding affidavit.

7

(a) Homestead’s cancellation of the contract was not a lawful cancellation;
(b) Homestead’s cancellation constituted a repudiation of the contract concluded
with Ladysmith Construction; and
(c) Ladysmith Construction’s acceptance of Homestead’s repudiation brought
about a lawful termination of the contract.

[20] Notably the parties were in agreement at the commencement of the arbitration
and during the appeal that the separated issue had been expanded to include
paragraphs 27, 27A, 27B and 27C of the statement of claim.

[21] The Arbitrator declared inter alia that Homestead’s cancellation of the
construction contract was not a lawful cancellation and that this purported
cancellation constituted a repudiation of the construction contract, the acceptance of
which Ladysmith Construction brought about the lawful termination of the contract.

[22] The Arbitrator, in summary, made the following findings:5
(a) The evidence suggested that there was a slowing down of work between 25
April and 9 May 2022 . That at least from the early part of May 2022 onward
the rate of work being undertaken on the Homestead project slowed and this
was a deliberate act on the part of the Ladysmith Construction;
(b) That Homestead was aware that the reason for the slowdown in work was the
issue of non-payment;
(c) By 11 May 2022 in substance the work had stopped;
(d) Homestead’s view that the work stoppage and withdrawal from the site
constituted an unequivocal intention not to be bound by the contract was not
reasonable. The more natural conclusion would be that Ladysmith
Construction had stopped work and left site because of the dispute over
payments and that if that dispute could be resolved, there was no reason why
they would not have returned to complete the project.

[23] In terms of the agreement between the parties, the right to appeal had been
reserved. Homestead appealed the Arbitrator’s award and th e appeal was heard by

5 Vol 2, Annexure ‘FA8’, arbitration award at 103-111.

8

the Appeal Tribunal. Homestead accordingly delivered its appeal against the award
by the Arbitrator, which appeal then served before the Appeal Tribunal.

The appeal tribunal’s award
[24] On 12 February 2024 the Appeal Tribunal delivered its award. 6 The Appeal
Tribunal upheld Homestead’s appeal against the Arbitrator’s award and set aside
and replaced such award with an interim award being that:
(a) Homestead’s cancellation of the construction contract by way of emails of 11
and 12 May 2022 was a lawful cancellation of the contract; and
(b) Ladysmith Construction was ordered to pay the costs of the separated issue.

[25] By way of this appl ication Ladysmith Construction seeks to review and set
aside the arbitration appeal award delivered by the Appeal Tribunal. In furtherance
of such relief, Ladysmith Construction seeks a further order that the arbitration
appeal be remitted to a new Appeal Tribunal for a fresh award alternatively for such
other purposes as the Court may direct.

Ladysmith construction’s case and contentions
[26] Ladysmith Construction, in its founding affidavit stated inter alia that:7
(a) The Appeal Tribunal exceeded its powers by granting the Appeal Tribunal
award for reasons and on grounds outside of Homestead’s pleaded case;
(b) The directive that had been issued was never revisited;
(c) The termination issue was confined to paragraph 27 of Homestead’s
statement of claim;
(d) That the jurisdictional framework created by the pleadings required a
determination as to whether the process of stopping work is the same as
abandoning or was identified or pleaded by Homestead as being the same
thing;
(e) That the pleadings created a pleaded difference between stopping and
abandoning and that by definition these courses of conduct were different;
(f) ‘[s]ave for abandonment, any other conduct which may or may not have
given rise to a claim fell outside the termination issue’;

6 Annexure ‘FA9’, Ladysmith Construction’s founding affidavit.

6 Annexure ‘FA9’, Ladysmith Construction’s founding affidavit.
7 Vol 1, founding affidavit at 13-26.

9

(g) ‘[t]he Appeal Tribunal failed to consider the appeal within the parameters set
by Homestead’s pleadings and the Directive’;
(h) The jurisdiction of both the arbitration and the appeal was confined to what
was pleaded in paragraph 27 of the statement of claim;
(i) The allegations in paragraph 27A to 27C were a different issue that needed to
be addressed because they pertain to material breaches; and
(j) The Appeal Tribunal made no finding on the issue of abandonment but went
outside of the permissible parameters of the case by finding that a go slow
and work stoppage amounted to a repudiation.

[27] Ladysmith Construction contends that the Appeal Tribunal exceeded and
acted beyond their jurisdiction when they made their award by way of their arbitration
appeal award and that the Appeal Tribunal decided the appeal outside and beyond
the pleadings and pleaded issues more particularly Homestead’s pleaded case.

[28] In seeking an order that the arbitral disputes be remitted to a new Appeal
Tribunal, Ladysmith Construction contended that given the views expressed by the
Appeal Tribunal in regard to inter alia the pleaded issues and the issues that arose
for determination in the appeal, the interests of justice militate against the remittal of
the appeal to the same Appeal Tribunal. It contended further that the interests of
justice dictate that a new Appeal Panel will be best suited to determine the issues
afresh ‘without their minds clouded by the impermissible approach adopted by the
Appeal Tribunal in their assessment of the appeal and their identification of what they
saw as the fundamental issue in the appeal’.

[29] Ladysmith Construction and Homestead were in agreement that both the
arbitration and the appeal proceeded on a limited issue which had been agreed
between the parties and they identified the limited issue as the ‘termination issue’.
Ladysmith Construction contended that the framework for the jurisdiction of the

Ladysmith Construction contended that the framework for the jurisdiction of the
Appeal Tribunal is delineated and defined by the pleadings read together with the
directive. It averred that for the purposes of determining the jurisdictional framework
created by the pleadings, it was important to determine whether the process of
stopping work is the same as abandoning the site or project or was identified or
pleaded by Homestead as being the same thing.

10


[30] In relying upon such a contention, it made specific and particular reference to
the aforementioned paragraphs 27, 27A, 27B and 27C of Homestead’s amended
statement of claim. Ladysmith Construction argued that t he pleadings created a
pleaded difference between both causes of conduct and in this regard, the stopping
of work as pleaded in paragraph 27A was an alleged persistent breach which
occurred whilst Ladysmith Construction remained on the site and involved in the
project. It contended that it was not an abandonment of either the project or the site,
which were the only pleaded acts of repudiation as pleaded in paragraph 27 namely
that Ladysmith Construction had abandoned the project and left the site and further
that its act of instituting liquidation proceedings constituted a clear rejection of the
agreement, which repudiation Homestead accepted and cancelled the agreement.

[31] The nub of Homestead's case was that save for an abandonment, any other
conduct which may or may not have given rise to a claim fell outside the termination
issue and in this regard, the directive issued by the Arbitrator dealt solely with the
issue of the abandonment . In regard to the issue of the abandonment, the Appeal
Tribunal did not independently interrogate the issue of abandonment and did not
make any determination as to whether Ladysmith Construction had abandoned the
construction site or the project.

[32] Ladysmith Construction contended although not expressly stated, that it
having stopped work because of a pay dispute was considered by the Appeal
Tribunal as sufficient to constitute a repudiation. However, this was not Homestead’s
pleaded case in respect of the repudiation and in this regard, paragraph 27C of the
amended statement of claim made this clear.

[33] It contended that the Appeal Tribunal critici sed Ladysmith Construction in its
judgment for having referenced the pay dispute and having not pleaded the same as

judgment for having referenced the pay dispute and having not pleaded the same as
an answer to the abandonment issue , however, it averred that Ladysmith
Construction was not obliged to plead the exceptio non ad impleti contractus, since
that would have been an answer to a claim that stopping or slowing down work was
the act of repudiation. It was not a defence to the claim of abandonment of the

11

project or site, and did not fall within the termination issue referred to for
determination.

[34] Consequently, the Appeal Tribunal failed to consider the appeal within the
parameters set by Homestead’s pleadings read together with the directive. Thus, the
jurisdiction of both the arbitration and the appeal was confined to what was pleaded
in paragraph 27 of the amended statement of claim. Paragraph 27A and 27B were
not the pleaded case for repudiation but instead were the pleaded case for the
alleged material breaches that independently (and as alternative) justified the
cancellation of the contract by Homestead.

[35] Ladysmith Construction averred that paragraph 27C fortified its case that
paragraph 27A and 27B were not Homestead’s pleaded case for repudiation but
instead were the pleaded case for the alleged material breaches. Paragraph 27C so
it contended, acknowledged this by contending that paragraphs 27A and 27B dealt
with the issue of Ladysmith Construction’s alleged ‘repeated and persistent material
breaches’ and consequently this is a different issue which needed to be addressed.
The question of whether Ladysmith Construction had repudiated the agreement was
pleaded as relying on two legs only namely whether Ladysmith Construction had
abandoned the Homestead project and the site and whether the liquidation
application amounted to a repudiation. Not only did the Appeal Tribunal make no
finding on the issue of abandonment, but went outside of the permissible perimeters
of the case by finding that a go-slow and work stoppage amounted to repudiation.

[36] The Arbitrator on the one hand, dealt with the question of whether Homestead
was abandoning the site and looked at the full conspectus of the facts before him
and in doing so, he acted within the jurisdiction afforded to him however the Appeal
Tribunal on the other hand, decided the appeal on the basis that a work stoppage
equated to abandoning of the project and the site which was not the pleaded case.

equated to abandoning of the project and the site which was not the pleaded case.
Thus, it contended that the Appeal Tribunal failed to make a decision on the pleaded
case of abandonment and in this regard the Appeal Tribunal acted beyond its
jurisdiction when it granted the award in the appeal.

Assessment and analysis

12

The Law
[37] In the Supreme Court of Appeal (‘SCA’) judgment of Hos+Med Medical Aid
Scheme v Thebe Ya Bophelo Healthcare Marketing & Consulting (Pty) Ltd and
Others,8 the SCA said the following:
‘[28] Thebe argues that the appeal tribunal both exceeded its powers and was guilty of a
gross irregularity. The same conduct, however, was relied on as giving rise to both grounds
for the setting aside of the award. The gravamen of the complaint is that the issues before
the arbitrator, and thus before the appeal tribunal, were defined by the pleadings. The
arbitration agreement said so expressly . The agreement also made provision for
amendments, and both parties amended and added to their pleadings during the course of
the proceedings. Hosmed even introduced an amendment at the stage of appeal. The
arbitration appeal tribunal could not, it was argued, go beyond the pleadings and decide an
issue not pleaded. Unlike a court, which has the inherent jurisdiction to decide a matter even
where it has not been pleaded, an arbitrator has no such power . It was common cause that
the issue of unanimous assent was not pleaded at any stage.

[30] In my view it is clear that the only source of an arbitrator's power is the arbitration
agreement between the parties and an arbitrator cannot stray beyond their submission
where the parties have expressly defined and limited the issues, as the parties have done in
this case to the matters pleaded. Thus the arbitrator, and therefore also the appeal tribunal,
had no jurisdiction to decide a matter not pleaded …

[35] In the circumstances the appeal tribunal exceeded its powers: it went beyond the
terms of the arbitration agreement. This is a clear case where the arbitration appeal tribunal
exercised a power that it did not have. This court recently referred with approval to the
decision of the House of Lords in Lesotho Highlands Development Authority v Impreglio spA

decision of the House of Lords in Lesotho Highlands Development Authority v Impreglio spA
where Lord Steyn distinguished between cases where a tribunal mistakenly exercises a
power that it does have, and those where a tribunal exercises a power that it does not have.
In the latter type of case the tribunal exceeds its power, and , under our Arbitration Act, that
warrants the setting aside of the order. This is the position stated earlier in Dickenson &
Brown v Fisher's Executors applied by the court in Telcordia …’ (Footnotes omitted.) (My
Emphasis.)
[38] In the SCA judgment of Fischer and Another v Ramahlele and Others 9 the
SCA held:

8 Hos+Med Medical Aid Scheme v Thebe Ya Bophelo Healthcare Marketing and Consulting (Pty) Ltd
and Others [2007] ZASCA 163; 2008 (2) SA 608 (SCA) (Hos+Med Medical Aid Scheme).

13

‘[13] Turning then to the nature of civil litigation in our adversarial system, it is for the parties,
either in the pleadings or affidavits (which serve the function of both pleadings and
evidence), to set out and define the nature of their dispute, and it is for the court to
adjudicate upon those issues … (Footnote omitted.)

[14] It is not for the court to raise new issues not traversed in the pleadings or affidavits,
however interesting or important they may seem to it, and to insist that the parties deal with
them. The parties may have their own reasons for not raising those issues …

[15] This last point is of great importance because it calls for judicial restraint . As already
mentioned Gamble J “required” the parties to argue as a preliminary issue what he
described as two issues of legality. Although he added that the parties were amenable to
these proposals, counsel who appeared in this court and in the court below confirmed that
the judge’s own description, that he “required” the points to be argued, was accurate. They
were not asked for their submissions on whether this was an appropriate approach to the
matter, or even (which was more pertinent) whether either question was in issue in the case .
Nor were they asked whether their clients agreed to broaden the issues to encompass these
points … It is a far cry from that for a court to raise issues that do not emerge from the
papers and have not been canvassed in the affidavits and require that those be argued
instead of hearing oral evidence and deciding the issues raised by the parties. ’ (Footnotes
omitted.) (My Emphasis.)

[39] In terms of clause 2.5.1 of the settlement agreement, the parties agreed that
the dispute between the parties related inter alia to ‘the termination of the contract/s
by the respondent namely Ladysmith Constructio n’. In terms of clause 2.5 more
specifically the preamble thereto, the parties further agreed that the issues that arose

specifically the preamble thereto, the parties further agreed that the issues that arose
for determination more particularly clauses 2.5.1 to 2.5.4 was ‘subject to being fully
ventilated in the exchange of pleadings in the arbitration’.

[40] After the Arbitrator issued the directive for the separation of issues,
Homestead effected amendments to its statement of claim. Paragraphs 27, 27A, 27B
and 27C of its statement of claim formed the central feature of Ladysmith
Construction’s basis in contenting that the Appeal Tribunal exceeded their powers by
straying beyond the pleaded and defined issues.

9 Fischer and Another v Ramahlele and Others [2014] ZASCA 88; 2014 (4) SA 614 (SCA).

14


[41] During the course of the submissions that were made to this Court, the parties
were in agreement that the pleadings comprised of three components10 namely:
(a) Clause 2.5 of the settlement agreement (in the liquidation application);
(b) The Arbitrator’s directive, more specifically paragraph 2(a) to 2(e); and
(c) The pleadings comprising of inter alia Homestead’s amended statement of
claim and Ladysmith Construction’s statement of defence.

[42] Consequently, the parties agreed and accepted during the course of
submissions that were made to the Court, that the Appeal Tribunal were bound to
adjudicate and determine the arbitration appeal predicated on clause 2.5 of the
settlement agreement, paragraph 2 of the Arbitrator’s directive and the pleadings.

[43] It is significant to note that Homestead amended its statement of claim by the
incorporation of paragraphs 27A, 27B and 27C after the Arbitrator issued the
directive.
Clause 2.5 of the settlement agreement more particularly clause 2.5.1 thereof
recorded that one of the issues and disputes between the parties was in regard to
‘the termination’ of the contract/s by Ladysmith Construction. Such termination would
be ventilated in the exchange of pleadings in the arbitration, thus it was clearly within
the contemplation of the parties that ‘the termination of the contract/s ’ by Ladysmith
Construction would be ventilated and dealt with in the arbitration.

[44] In regard to Homestead’s amended statement of claim, more particularly
paragraphs 27, 27A, 27B and 27C, the Court makes the following observations,
namely: paragraph 27 of Homestead’s statement of claim documented inter alia
Homestead’s contention and pleaded case that the conduct of Ladysmith
Construction having abandoned the Homestead project and instituting liquidation
proceedings constituted a clear rejection of the agreement which repudiation
Homestead accepted and cancelled the agreement by way of the email addressed

Homestead accepted and cancelled the agreement by way of the email addressed
on the 11 May 2022 . It further records that Homestead thereafter reaffirmed its

10 Homesteads Senor Counsel sought to argue that the notice of appeal also formed part of the
pleadings, for obvious reasons this approach is untenable.

15

termination via its attorneys of record and again in the answering affidavit in the
winding-up application.

[45] At the heart of Ladysmith Construction’s case is its contention that save for
the abandonment, any other conduct which may or may not have given rise to a
claim fell outside of the termination issue and thus so it contends, the Appeal
Tribunal strayed beyond the pleaded issues that arose for determination more
particularly, the issues pleaded in paragraphs 27, 27A, 27B and 27C.

[46] It is apparent that Ladysmith Construction’s main bone of contention is the
averments pleaded by Homestead in paragraphs 27A and 27C, more particularly
paragraph 27 of Homestead’s statement of claim . In my judgment, I find that
paragraphs 27A, 27B and 27C has to be read in context with and together with
paragraph 27 and in regard to the averment in paragraph 27A, that Ladysmith
Construction ‘stopped work’ and that such averment and act falls within Ladysmith
Construction’s act of having abandoned the site alternatively the project.

[47] In regard to paragraph 27C, which has to be read in together with and in
conjunction with paragraphs 27, 27A and 27B and in context , more particularly that
and having regard to the aforementioned paragraphs, the reference to repeated and
persistent material breaches was the reference to the averments pleaded in
paragraphs 27 and 27A . Namely that Ladysmith Construction had abandoned the
site alternatively abandoned the project and had in this regard, removed its
equipment and that such acts would have invariably, have entailed stopping work.
Paragraph 27A must also be read in its totality and with reference to the concluding
words namely ‘were justification for claimant’s termination of the agreement’.


[48] Ladysmith construction denied that it abandoned the site but did not plead in
the alternative that if it’s conduct in stopping work and moving from the site was

the alternative that if it’s conduct in stopping work and moving from the site was
established, that it had a lawful excuse because of nonperformance by Homestead.
Ladysmith construction disavowed reliance on the exceptio non -adimpleti
contractus.11

11 Award by the appeal tribunal, paragraph 34

16


[49] The Appeal Tribunal found that Ladysmith constructions act of stopping work,
moving equipment from the site and declaring the site to be unsafe 12,amounted to a
repudiatory breach.13The defence pleaded and advanced by Ladysmith construction
in the arbitration hearing was that it had not stopped work or taken steps to the
established the site. The arbitrator rejected such a contention based on the evidence
that served before him namely that work had slowed and by 11 May 2022 the work
had stopped, which was confirmed in the letter by Ladysmith constructions attorney.
It is apparent from the evidence in the arbitration that work had effectively stopped
and materials and equipment were being moved off site. On this topic the arbitrator
accepted the submission by Homestead’s counsel that with the construction
contract, the contractor’s action in stopping work and disestablishing from the site is
a substantial pointer towards a repudiation of the contract.14

[50] Clause 2.5.1 of the settlement agreement documented that one of the issues
and disputes between the parties was in regard to ‘the termination’ of the contract/s
by Ladysmith Construction and that such termination would be ventilated in the
exchange of pleadings in the arbitration. Therefore, the ratio in Hos+med Medical Aid
Scheme finds application in casu. Accordingly, the appeal tribunal confined itself to
the issues that emanated from the 3 components of the pleadings and specifically in
terms of the separation directive. The case that Ladysmith Construction came to
meet was defined by the issues pleaded between the parties , read together with
Clause 2.5.1 of the settlement agreement and the separation directive . Further
evidence was adduced in this regard. Therefore, the appeal tribunal did not exceed
his powers as contemplated by s 33(1)(b) of the Arbitration Act.

[51] I am not in agreement and aligned with Ladysmith Construction’s contention

[51] I am not in agreement and aligned with Ladysmith Construction’s contention
that the Appeal Tribunal exceeded its powers by deciding and adjudicating the matter
without reference to the pleadings which comprised of the aforementioned three
components. An Arbitrator’s power or jurisdiction to deal with the issues placed
before him or her is regulated by the arbitration agreement between the parties. The

12 Which was confirmed in writing by Ladysmith constructions attorney
13 Award by the appeal tribunal, paragraphs 25 and 26
14 Award by the arbitrator, paragraph 41

17

validity of the termination of the contract by Homestead is a dispute identified in
terms of paragraph 2.5 of the settlement agreement.

[52] Thus, I am not persuaded with Ladysmith Construction s argument that the
Appeal Tribunal was confined to considering only one pleaded ground of repudiation
located in paragraph 27 of the statement of claim, and that the other termination
related to allegations located in paragraph 27A to 27C of the statement of claim were
excluded from the appeal.

[53] It is common cause that both the Arbitrator and the Appeal Tribunal dealt with
the arbitration in terms of the amended and amplified pleadings vis-à-vis paragraphs
27 and 27A to 27C. Ladysmith Construction contended inter alia that because
Homestead failed to plead the stopping of work as a repudiation of the contract but
pleaded it as a material breach, the Appeal Tribunal exceeded its powers or
committed a gross irregularity in finding the stopping of work was a repudiation.

[54] Paragraphs 29 and 30 of the appeal award demonstrates that the Appeal
Tribunal did not make such a finding but merely agreed that the conduct of
Ladysmith Construction was a substantial pointer to repudiation.

[55] Ladysmith Construction contended that during the course of the adjudication
of the appeal before the Appeal Tribunal, the Appeal Tribunal considered in its view
that a stoppage of work even temporarily constituted an abandonment in the contract
of construction law. In this regard, this is a finding which is unimpeachable and is not
reviewable.

[56] An Arbitrator would no doubt exceed his powers when he purports to exercise
a power which he did not have. If an Arbitrator erroneously exercis es powers
available to him, then the Arbitrator does not exceed his powers and a jurisdictional
challenge on that basis should fail.15


15 Telcordia Technologies Inc v Telkom SA Ltd [2006] ZASCA 112; 2007 (3) SA 266 (SCA) (Telcordia)
paragraphs 52 and 86.

18

[57] Harms J in Telcordia,16 held that for all intents and purposes, an Arbitrator has
the right to be wrong on the merits of a case , and ‘it is a perversion of language and
logic to label mistakes of this kind as a misconception of the nature of the inquiry-
they may be misconceptions about meaning, law or admissibility of evidence but that
is a far cry from saying that they constitute a misconception of the nature of the
enquiry’.

[58] In my judgment, the Appeal Tribunal did not misconceive the nature of the
enquiry and in adjudicating the issues at hand, identified the issues predicated on
the three components namely clause 2.5 .1 of the arbitration agreement, the
separation directive, and the pleadings; consequently, Ladysmith Construction was
afforded a fair hearing and the Appeal Tribunal’s conduct did not amount to a gross
irregularity.17

[59] Harms J correctly held in Telcordia more specifically at paragraph 86 that
where an Arbitrator engages in the correct enquiry but errs either on the fac ts or the
law, that is not an irregularity and does not constitute a basis for setting aside an
award.

[60] What Ladysmith Construction fails to appreciate is that the Arbitrator made a
factual finding that the works had stopped and equipment was being removed from
the site. The Arbitrator then found that Homestead would not have considered that to
be a repudiation of the contract because of the dispute about payment.

[61] Even if the Appeal Tribunal was incorrect on such a construction , that does
not constitute a gross irregularity, nor does it mean that the Appeal Tribunal
exceeded its powers. The attempt to separate paragraph 27 from paragraphs 27A to
C, ignores the fact that in the pre -arbitration minute, the agreement was that the
dispute regarding termination would be adjudicated by arbitration. The Appeal
Tribunal exercised its powers in terms of that agreement.


16 Ibid para 85.

Tribunal exercised its powers in terms of that agreement.


16 Ibid para 85.
17 Lufuno Mphaphuli & Associates (Pty) Ltd v Andrews and Another [2009] ZACC 6; 2009 (4) SA 529
(CC) para 219.

19

The abandonment issue: The appeal tribunal
[62] In Telcordia, the SCA said the following:
‘L. The meaning of s 33(1)(b): “gross irregularity” and “exceeding powers”
[52] The term “exceeding its powers” requires little by way of elucidation and this statement
by Lord Steyn says it all:
“But the issue was whether the tribunal ''exceeded its powers'' within the meaning of
s 68(2)(b) [of the English Act]. This required the courts below to address the question
whether the tribunal purported to exercise a power which it did not have or whether it
erroneously exercised a pow er that it did have. If it is merely a case of erroneous
exercise of power vesting in the tribunal no excess of power under s 68(2)(b) is
involved. Once the matter is approached correctly, it is clear that at the highest in the
present case, on the currency point, there was no more than an erroneous exercise
of the power available under s 48(4). The jurisdictional challenge must therefore fail.”

[85] The fact that the arbitrator may have either misinterpreted the agreement, failed to apply
South African law correctly, or had regard to inadmissible evidence does not mean that he
misconceived the nature of the inquiry or his duties in connection therewith. It only means
that he erred in the performance of his duties. An arbitrator “has the right to be wrong” on the
merits of the case, and it is a perversion of language and logic to label mistakes of this kind
as a misconception of the nature of inqui ry - they may be misconceptions about meaning,
law or the admissibility of evidence but that is a far cry from saying that they constitute a
misconception of the nature of the inquiry. To adapt the quoted words of Hoexter JA: it
cannot be said that the wrong interpretation of the Integrated Agreement prevented the
arbitrator from fulfilling his agreed function or from considering the matter left to him for
decision. On the contrary, in interpreting the Integrated Agreement the arbitrator was

decision. On the contrary, in interpreting the Integrated Agreement the arbitrator was
actually fulfil ling the function assigned to him by the parties, and it follows that the wrong
interpretation of the Integrated Agreement could not afford any ground for review by a court.

[86] Likewise, it is a fallacy to label a wrong interpretation of a contract, a wrong perception
or application of South African law, or an incorrect reliance on inadmissible evidence by the
arbitrator as a transgression of the limits of his power. The power given to the arbitrator was
to interpret the agreement, rightly or wrongly; to determine the applicable law, rightly or
wrongly; and to determine what evidence was admissible, rightly or wrongly. Errors of the
kind mentioned have nothing to do with him exceeding his powers; they are errors
committed within the scope of his mandate. To illustrate, an arbitrator in a “normal” local
arbitration has to apply South African law but if he errs in his understanding or application of
local law the parties have to live with it. If such an error amounted to a transgression of his

20

powers it would mean that all errors of law are reviewable, which is absurd. ’ (Footnotes
omitted.)

[63] Ladysmith Construction contended that a repudiation is pleaded in paragraph
27 and that the only ground upon which the Appeal Tribunal and indeed the Arbitrator
could have relied upon to conclude that Ladysmith Construction repudiated the
agreement was if it had abandoned the site/project.

[64] It demarcated a clear distinction between a material breach and a repudiation,
stating that only the latter was to be considered by the Appeal Tribunal and that the
Appeal Tribunal was prohibited from finding that the pleaded material breaches –
stopping work and decamping from site – amounted to a repudiation of the
agreement. It allege d that only the abandonment issue was to be considered a
repudiation, and the further pleaded material breaches could not also be a
repudiation because they were not pleaded as such.

[65] In Minister of Safety and Security v Slabbert 18 the SCA said the following in
regard to the purpose of pleadings:
‘[11] The purpose of the pleadings is to define the issues for the other party and the court. A
party has a duty to allege in the pleadings the material facts upon which it relies. It is
impermissible for a plaintiff to plead a particular case and seek to establish a different case
at the trial. It is equally not permissible for the trial court to have recourse to issues falling
outside the pleadings when deciding a case.

[12] There are, however, circumstances in which a party may be allowed to rely on an issue
which was not covered by the pleadings. This occurs where the issue in question has been
canvassed fully by both sides at the trial . In South British Insurance Co Ltd v Unicorn
Shipping Lines (Pty) Ltd, this court said:
"However, the absence of such an averment in the pleadings would not
necessarily be fatal if the point was fully canvassed in evidence. This
means fully canvassed by both sides in the sense that the Court was

means fully canvassed by both sides in the sense that the Court was
expected to pronounce upon it as an issue."


18 Minister of Safety and Security v Slabbert [2009] ZASCA 163.

21

[13] The issue on which the court below relied as a basis for liability was not fully
canvassed at the trial presumably because it was not pleaded and the parties' attention
was not drawn to it. It was fleetingly touched upon during Magoxo's cross -examination.
The response elicited was that the plaintiff was still drunk at the time his wife made the
request. The issue was not pursued and furthermore the plaintiff's wife did not testify to
support the contention.’ (Footnotes omitted.) (My Emphasis.)

[66] The main and substantial issue that served before both the arbitration and the
Appeal Tribunal was the ‘termination issue’ and in this regard as is referenced in the
award by the arbitrator, extensive oral testimony was adduced in regard to inter alia
the ‘termination issue’. Prior to the Arbitrator issuing the separation directive on the
‘termination issue ’, it was clearly within the contemplation of the parties (duly
documented in terms of clause 2.5 of the settlement agreement) that ‘the dispute
between the parties, briefly summarised (and is subject to being fully ventilated in the
exchange of pleadings in the arbitration) inter alia: 2.5.1. the termination of the
contract/s by the respondent ’. Even if Homestead’s amended statement of claim is
not a model of absolute clarity (which I make no finding on) the termination issue
was fully canvassed by both parties during the course of the testimony that served
before the Arbitrator.

[67] Homestead averred that the persistent material breaches justified the
cancellation and formed part of the ‘termination issue ’. The Appeal Tribunal dealt
with the question as to whether there was a repudiation , this is apparent from
paragraphs 27 to 29 of its award:
‘[27] The defence pleaded and then advanced by LC in the arbitration hearings was that it
had not stopped work or taken steps to disestablish the site. That was rightly rejected by the
arbitrator on the evidence as it was plain that work had slowed and by 11 May 2022 had

arbitrator on the evidence as it was plain that work had slowed and by 11 May 2022 had
stopped, which was confirmed in the letter that the site was unsafe in circumstances where
Mr Cunninghame had agreed that one of LC’s principal obligations after taking control of the
site was to be responsible for safety.

[28] The arbitrator accepted the submission by Counsel for Homestead that with a
construction contract, the contractor’s action in stopping work and disestablishing from the
site is a substantial pointer towards a repudiation of the contract, but added that this will
depend on the context in which this is done.

22


[29] The arbitrator asked himself the question: would a reasonable person in Homestead’s
position have concluded that by LC packing up and leaving the site they were walking away
from the contract ...’19

[68] The allegations that abandonment could be both a repudiation and a material
breach, but stoppage of work could only be considered as a material breach
because of the way Homestead pleaded paragraphs 27A to 27C, is untenable and
does not find application under s 33(1)(b).

[69] It is a question of law as to what constituted a repudiation and the factual
basis was the evidence that served before both the Arbitrator and the Appeal
Tribunal. For purposes of this review application that serves before the Court, it is
irrelevant and not within the ambit of this Court within the purview of a review,
whether the term abandon encompasses stopping work and disestablishing from site
or whether stopping work and disestablishing from site is a material breach.

[70] Ladysmith Construction contends that the Appeal Tribunal made an error in
fact and law by finding that Ladysmith Construction abandoned the site by equating
a stoppage of work and disestablishment from site with an abandonment. Such a
course of approach is impermissible on review.20

[71] Homestead pleaded an abandonment and the Appeal Tribunal found that
stopping work even on a temporary basis was an abandonment. However, even if it
was not the correct position , that would not found a basis upon which Ladysmith
Construction would be permitted to review the Appeal Tribunal’s award.

[72] I am not persuaded that the Appeal Tribunal exceeded their powers by
straying beyond the pleadings that served before it. In any event and as per the
Telcordia dictum and in regard to Ladysmith Construction’s contention that the
Arbitrator inter alia made no finding on the issue of abandonment and finding that ‘a
go – slow and work stoppage amounted to a repudiation ’ failed to inter alia define

go – slow and work stoppage amounted to a repudiation ’ failed to inter alia define

19 Vol 2, Appeal Tribunal award, at 125.
20 Telcordia paras 85-86.

23

abandonment, an Arbitrator ‘has the right to be wrong on the merits of the case ’.
Ladysmith Construction’s contention and criticisms in this regard is unfounded and
amounts to a misconception of the nature of the enquiry and the issues that the
Appeal Tribunal were tasked to determine. Even if the Appeal Tribunal decided the
appeal on the basis that a work stoppage equated to abandoning the project and the
site, this did not and could not prevent the Appeal Tribunal from fulfilling their agreed
function or considering the issues that arose for determination. Consequently, this
does not afford any ground for review by this Court.

[73] It is a misconception to categorise the aforesaid complaints and criticisms by
Ladysmith Construction as a transgression of the limits of the power of the Appeal
Tribunal. The parties agreed to empower the Appeal Tribunal to determine the
‘termination issue ’ as expanded by the pleadings. Errors of the kind averred and
alluded to by Ladysmith Construction have nothing to do with the Appeal Tribunal
exceeding their powers, such errors as alleged by Ladysmith Construction were (if
any) committed within the scope of the mandate of the Appeal Tribunal. As Harms J
in Telcordia stated:
‘[86] ... an arbitrator in a “normal” local arbitration has to apply South African law but if he
errs in his understanding or application of local law, the parties have to live with it.’

Conclusion
[74] I am satisfied that the Appeal Tribunal did not exceed its powers by straying
beyond the pleadings which comprised of the aforementioned three components,
namely the clause 2.5 of the arbitration agreement, the arbitrator’s separation
directive and the pleadings as amended.

Order
[75] Thus, the following order is made:
1. The application is dismissed with costs on scale C, including the costs of two
Counsel.



_____________________
Ramdhani AJ

24



Appearances
Counsel for the applicant: Advocate W S Shapiro SC
Advocate I Veerasamy


Instructed by: MACGREGOR ERASMUS ATTORNEYS
Applicant’s Attorneys
First Floor, Bond Square
12 Browns Road
The Point
DURBAN
Tel: (031) 201 8955
Ref:B MacGregor & JM Klingbiel/
sv/LAD2/0001


Counsel for the First Respondent: Advocate I Pillay SC
Advocate L Olsen


Instructed by: HAY & SCOTT ATTORNEYS
First Respondent’s Attorneys
Top Floor, 3 Highgate Drive
Redlands Estate
PIETERMARITZBURG
Tel: 033 342 4800
Ref: PS HaySRP/08H346002


Date of hearing: 12 September 2025


Date of judgement: 4 December 2025