Ethekwini Municipality v Mthethwa and Others (Reasons) (2025/159888) [2025] ZALCD 45 (6 November 2025)

49 Reportability

Brief Summary

Labour Law — Review Application — Jurisdictional Ruling — Applicant sought to interdict arbitration proceedings pending a review of a jurisdictional ruling made by the arbitrator of the South African Local Government Bargaining Council (SALGBC), which dismissed an objection regarding the timeliness of a dispute referral. The applicant contended that the first respondent's referral was out of time, while the arbitrator found it was made within the appropriate timeframe. The applicant's review application was deemed competent, but the court held that interdicting arbitration proceedings should only occur in exceptional circumstances, which were not demonstrated in this case. The application was dismissed with costs.

THE LABOUR COURT OF SOUTH AFRICA, DURBAN
Not Reportable
Case no: 2025 – 159888

In the matter between:

ETHEKWINI MUNICIPALITY Applicant
and
PHUMELELA AUBREY MTHETHWA First Respondent
SOUTH AFRICAN LOCAL GOVERNMENT
BARGAINING COUNCIL Second Respondent
E.T. MHLONGO N.O Third Respondent
S MADIKIZELA N.O Fourth Respondent
SBONELO MCHUNU Fifth Respondent

Heard: 23 October 2025
Delivered: 6 November 2025
This judgment was handed down electronically by circulation to the parties
and legal representatives by email. The time for hand- down is deemed to be 6
November 2025
Summary: Review application – review of jurisdictional ruling – when
appropriate to consider review in medias res – s 158(1B) of LRA considered –

2

meaning of just and equitable considered – jurisdiction and material error of
law at stake – review application competent and properly brought
Interdict arbitration proceedings – interdict pending review application –
should however only be exercised in truly exceptional circumstances –
requires grave injustice and irremediable prejudice – exceptional
circumstances not shown
Ruling – nature of ruling by arbitrator considered – ruling on jurisdiction not a
final ruling – bargaining council cannot finally decide own jurisdiction – only
constitutes ruling for convenience – ruling may be revisited once evidence is
considered
Alternative remedy – applicant has proper prescribed alternative remedy
available – no reason or basis for interference at this stage in Court
No basis for urgent intervention in this instance – application dismissed with
costs

JUDGMENT: REASONS

SNYMAN, AJ
Introduction
[1] The current application is yet again another case of intervention by this Court
being sought by an applicant in the case of incomplete dispute resolution
proceedings under the Labour Relations Act (LRA) 1. This is despite this Court
regularly lamenting this kind of behaviour, as this kind of conduct
compromises the fundamental principle of the expeditious resolution of
employment disputes under the LRA. As pertinently said in Food and Allied
Workers Union on behalf of Gaoshubelwe v Pieman’s Pantry (Pty) Ltd
2:


1 Act 66 of 1995 (as amended).
2 (2018) 39 ILJ 1213 (CC) at para 187. See also National Education Health and Allied Workers Union
v University of Cape Town and Others (2003) 24 ILJ 95 (CC) at para 31.

3

‘… Our courts have, on occasion, pronounced on the importance of labour
disputes to be conducted with expedition. For example, in National Research
Foundation the Labour Court held:
‘[15] It is now trite that there exists a particular requirement of expedition
where it comes to the prosecution of employment law disputes. …’


[2] In casu, the applicant has crafted the relief sought in its notice of motion as
being that the arbitration proceedings scheduled for 14 November 2025 be
interdicted and that any further conducting of the arbitration proceeding also
be interdicted / suspended, pending the finalization of a review application
that has been brought by the applicant in this Court under case number 2025
– 157754. This review application has just been brought, and is pending.

[3] The applicant’s review application under case number 2025 – 157754 is thus
brought in medias res, in terms of which the applicant seeks to review and set
aside a juri sdictional ruling made by the third respondent in his capacity as
arbitrator of the second respondent (SALGBC) . The jurisdictional ruling was
given as a result of a point in limine raised by the applicant at the
commencement of the arbitration, to the effect that the first respondent’s
referral of an unfair labour practice dispute to the SALGBC was out of time,
and thus the SALGBC has no jurisdiction to entertain the same. The third
respondent, being the appointed arbitrator, considered the point and
dismissed it, finding that the referral had been made in time, and he then
directed that the dispute proceed to arbitration on the merits . Needless to say,
the applicant was dissatisfied with this outcome, leading to the said review.

[4] However, this application does not concern deciding the review, other than
perhaps conducting a cursory assessment of its merits, as will be dealt with
later in this judgment . Instead, what the applicant want s in this application is

later in this judgment . Instead, what the applicant want s in this application is
to effectively interdict any further arbitration proceedings at the SALGBC until
such time as the applicant review application br ought in medias res has been
finally decided. Although this seems on face value to be interim relief, what

4

the applicant for all intents and purposes is seeking is final relief,3 especially
considering the undetermined time (likely years) it would take for review
proceedings to be concluded, as there is simply no legal basis for the review
application to be decided urgently . The current application is opposed by the
first respondent.

[5] The application came before me for argument on 23 October 2025. After
hearing argument by both parties, and considering the affidavits and heads of
argument filed by the parties, I granted the following order:


1. The applicant’s application is dismissed.
2. The applicant is ordered to pay the first respondent’s costs on the party
and party scale B.
3. Written reasons for this order will be provided on 5 November 2025.’

[6] This judgment now constitutes the written reasons in terms of paragraph 3 of
the above order, starting with an exposition of the relevant background facts.

The relevant background

[7] Fortunately, and where it comes to the background facts in this matter, these
facts are straight forward and mostly undisputed.

[8] On 9 December 2022, the a pplicant advertised a vacancy for the position of
Head: Metropolitan Police. The closing date for applications was 13 January
2023. The first respondent duly submitted his application for the post. The
first respondent however was, despite having been previously considered for

3 See Zondo and Another v Uthukela District Municipality and Another (2015) 36 ILJ 502 (LC) at para
4, where the Court held: ‘ … what the applicants were actually seeking is that the disciplinary
proceedings against the applicants be interdicted from in any way proceeding until the applicants'
review application in respect of the legal representation ruling has been finally determined. This is
clearly not interim relief, but final relief. In effect, the disciplinary proceedings would be permanently
stayed until the event of the outcome of the legal representation review application. As matters stand,

this is indefinitely … ’. See also BHT Water Treatment (Pty) Ltd v Leslie and Another 1993 (1) SA 47
(W) at 55D-F.

5

the position which still had similar essential requirements , not even shortlisted
for being interviewed for the position.

[9] On 1 March 2024, and following the shortlisting and interview process, the
fifth respondent, being the successful candidate, duly assumed his duties .
On 4 March 2024, the f irst respondent delivered a WhatsApp message to the
fifth respondent to congratulate him on his appointment.

[10] However, and on 10 June 2024, the f irst respondent sent an email to Ms K
Makhathini, being the Deputy City Manager at the a pplicant, regarding his
application for the post , confirming that he had not been shortlisted and
subsequently receiv ing a letter from Human Capital stating that he was
unsuccessful. The first respondent expressed his dissatis faction and
requested that he be provided with reasons for hi m not being shortlisted.
There is no indication that such reasons were ever forthcoming.

[11] On 27 January 2025, a bulletin was circulated to all staff at the a pplicant
notifying the staff of appointments to various to posts within the applicant, with
effective date of such appointments , including the appointment of the f ifth
respondent to the post of Head: Metropolitan Police. The first respondent also
received this bulletin.

[12] According to the first respondent, this bulletin circulated to all staff on 27
January 2025 marked the actual end of the recruitment and selection process
as envisaged in the a pplicant's Standard Operating Procedure (SOP) number
36 on Recruitment and Selection of Staff. Therefore, and in the view of the
first respondent, the recruitment and placement process for the position of
Head: Metropolitan Police for which he applied, was only finally concluded on
that date.

[13] When the first respondent bec ame aware of the appointment bulletin
confirming the appoint ment of the fifth respondent, he decided to refer a
dispute to the SALGBC in terms of section 186(2) of the LRA, as an unfair

dispute to the SALGBC in terms of section 186(2) of the LRA, as an unfair
labour practice relating to promotion. This referral was made on 25 March

6

2025. The fifth respondent was joined as the second respondent to that
dispute, being the successful incumbent to the post.

[14] On 3 April 2024, the matter was unsuccessfully conciliated, and a certificate of
failure to settle was issued confirming that the dispute remained unresolved.
The dispute was then referred to arbitration by the first respondent.

[15] In May 2025, the applicant delivered a written objection in limine to the
SALGBC, in terms of which it was contended that the first respondent’s
referral of the dispute to the SALGBC was out of time , as the dispute actually
arose on 1 March 2024 when the fifth respondent assumed his duties.
According to the applicant, this meant the referral was outside the prescribed
90 days’ time limit, however the first respondent never applied for
condonation. As far as the applicant was concerned, this meant the SALGBC
had no jurisdiction to arbitrate.

[16] The first respondent opposed this objection in limine and filed an answering
affidavit on 27 May 2025. In this answering affidavit, he affirmed his view that
the appropriate time to refer his dispute was only when the recruitment and
selection process was finally completed, by way of the circular of 27 January
2025, and this meant his referral on 25 March 2025 was in time.

[17] The objection in limine came before the third respondent for argument on 17
July 2025, based on the process filed earlier by the parties. In a ruling handed
down on 8 August 2025, the t hird respondent dismissed the objection in
limine. He reasoned that he had the duty to determine when the first
respondent became aware of the appointment of the fifth respondent to the
position. Whilst the third respondent accepted that the applicant resolved on
28 February 2024 to appoint the fifth respondent to the position and
employees became aware of this at around this time, the circular of 27
January 2025 was the actual and formal notification to employees of the

January 2025 was the actual and formal notification to employees of the
appointment of the fifth respondent. According to the third respondent, it is
this notification of 27 January 2025 that made the applicant aware of the
appointment for the purposes of the unfair labour practice jurisdiction, and

7

thus his referral on 25 March 2025 was not late. The third respondent also
directed that the SALGBC set the matter down for arbitration within 30 days .
The SALGBC, pursuant to this ruling, then issued a notice of set down on 14
August 2025, setting down the matter for arbitration for on 14 November
2025. In this notice of set down, the parties were advised of the appointment
of the fourth respondent as the arbitrator assigned to conduct the arbitration
hearing.

[18] Having received this ruling, the applicant instructed its attorneys of record to
challenge the same. Pursuant to this instruction, a consultation with its
attorneys and counsel took place on 21 August 2025, and the applicant was
advised t hat the appropriate process was t o pursue a review application to
challenge the ruling. Therefore, and on 1 September 2025, the a pplicant's
attorneys delivered a letter to the SALGBC informing it of the a pplicant's
intention to institute an application to review and set aside the r uling, by the
end of that week, and a request was made that the arbitration hearing
scheduled for 14 November 2025 be cancelled pending the finalization of the
review application, failing which urgent proceedings would be instituted to stay
the arbitration hearing. The second respondent answered on the same date (1
September 2025) that it was unable to remove the arbitration from the roll,
and the applicant would have to approach the Court. This application then
followed on 9 September 2025.

Urgency

[19] I intend to first deal with the issue of urgency. The applicant received the
jurisdictional ruling of the third respondent on 8 August 2025. The application,
as said, was brought on 9 September 2025, which is not the epitome of
expedition, and it is true that the applicant could have acted more promptly. I
do however consider that the applicant had to first complete and file its review
application, and then it attempted to get agreement from the SALGBC on 1

application, and then it attempted to get agreement from the SALGBC on 1
September 2025 to cancel the arbitration, but this was not successful. If this
was agreed to, it would have avoided litigation. When this intervention was not
successful, the application followed within a week after that, which I consider

8

to be sufficiently expeditious. The first respondent was afforded sufficient
opportunity to oppose the application. And when the matter was argued,
urgency was not really placed in issue. In line with the principles set out in
Association of Mineworkers and Construction Union and Others v Northam
Platinum Ltd and Another 4, I will accept that the applicant took sufficiently
prompt and urgent action, satisfies the requirement that the application was in
effect brought at the earliest appropriate opportunity, and that this is not a
case of self -created urgency. It is in any event in my view important that this
matter be disposed of on the merits , considering that the arbitration is
scheduled to proceed on 14 November 2025. I will thus finally decide this
application as one of urgency.

Analysis

[20] I will first consider whether the applicant has established the existence of a
clear right to the relief sought.5 In this context, it must be decided whethe r the
applicant’s review application, brought in medias res, constitutes proper cause
for the interdicting of the arbitration proceedings to follow , until such time as
that review has been decided. This would necessitate a decision whethe r it
was competent and proper to have brought the review application at this
stage, prior to the final completion of the arbitration proceedings.

[21] This Court and the Labour Appeal Court has made it clear that as a matter of
principle, review applications in medias res must be strongly discouraged. The
following dictum from the judgment in Jiba v Minister: Department of Justice
and Constitutional Development and Others6 is apposite:

‘… Urgent applications to review and set aside preliminary rulings made
during the course of a disciplinary enquiry or to challenge the validity of the

4 (2016) 37 ILJ 2840 (LC) at paras 21 – 26. See also Jiba v Minister: Department of Justice and
Constitutional Development and Others (2010) 31 ILJ 112 (LC) at para 18; Transport and Allied

Constitutional Development and Others (2010) 31 ILJ 112 (LC) at para 18; Transport and Allied
Workers Union of SA v Algoa Bus Co (Pty) Ltd and Others (2015) 36 ILJ 2148 (LC) at para 11.
5 As the applicant seeks a final interdict, the applicant must establish: (a) a clear right; (b) an injury
actually committed or reasonably apprehended; and (c) the absence of any other satisfactory remedy
– see Setlogelo v Setlogelo 1914 AD 221 at 227; Masstores (Pty) Ltd v Pick ‘n Pay Retailers (Pty) Ltd
2017 (1) SA 613 (CC) at para 8; V & A Waterfront Properties (Pty) Ltd and Another v Helicopter and
Marine Services (Pty) Ltd and Others 2006 (1) SA 252 (SCA) at para 20.
6 (2010) 31 ILJ 112 (LC) at para 17.

9

institution of the proceedings ought to be discouraged. These are matters best
dealt with in arbitration proceedings consequent on any allegation of unfair
dismissal …’

[22] There are a number of reasons for this sentiment expressed above, which can
hardly be better described than by way of reference to the following dictum in
Trustees for the time being of the National Bioinformatics Network Trust v
Jacobson and Others7, where the Court held:

‘There are at least two reasons why the limited basis for intervention in
criminal and civil proceedings ought to extend to uncompleted arbitration
proceedings conducted under the auspices of the CCMA, and why this court
ought to be slow to intervene in those proceedings. The first is a policy related
reason — for this court routinely to intervene in uncompleted arbitration
proceedings would undermine the informal nature of the system of
dispute resolution established by the Act. The second (related) reason is that
to permit applications for review on a piecemeal basis would frustrate the
expeditious resolution of labour disputes. In other words, in general terms,
justice would be advanced rather than frustrated by permitting CCMA
arbitration proceedings to run their course without intervention by this court.


[23] The reasoning in Jacobson supra has recently once again been endorsed by
the LAC in South African Cabin Crew Association obo Members v South
African Airways (Soc) Ltd and Others 8 where the Court had the following to
say:

‘Although the Labour Court may review interlocutory rulings made by
commissioners under section 158(1)(g) of the LRA, sound reasons underpin
the Labour Court’s reluctance to intervene in incomplete arbitrations. The first
reason is policy-related: such intervention in medias res would undermine the
informal nature of the dispute resolution process. The second reason is that
piecemeal reviews would hinder the prompt resolution of labour disputes. This

piecemeal reviews would hinder the prompt resolution of labour disputes. This

7 (2009) 30 ILJ 2513 (LC) at para 4. See also EOH Abantu (Pty) Ltd v Commission for Conciliation,
Mediation and Arbitration and O thers (2010) 31 ILJ 937 (LC) at para 16; Ntombela and Others v
United National Transport Union and Others (2019) 40 ILJ 874 (LC) at para 41.
8 [2025] 10 BLLR 1048 (LAC) at para 26.

10

legislative policy was confirmed in Trustees for the time being of the
National Bioinformatics Network Trust v Jacobson & others as follows.
“In other words, in general terms, justice would be advanced rather than
frustrated by permitting CCMA arbitration proceedings to run their course
without intervention by this court.”

Section 158(1B) of the LRA gives effect to the policy consideration that
judicial intervention would generally be deferred until the issue in dispute had
been finally determined. To this end, this section provides that the Labour
Court may not review any decision or ruling made during consideration or
arbitration proceedings before final determination of the issue in dispute by
the CCMA, except if the Labour Court is of the opinion that it is just and
equitable to review the decision or ruling. The court in South African
Broadcasting Corporation (SOC) Limited v Commission for Conciliation,
Mediation and Arbitration and Others noted that “ [a] case must be truly
exceptional to warrant a departure from the norm that a review is appropriate
only once the dispute has been finally determined in a completed arbitration
hearing. This is consistent with the statutory purpose of expeditious dispute
resolution which the LRA seeks to achieve”.’

[24] Therefore, it is clear that the aforesaid considerations are the very reason for
the adopting of section 158(1B) of the LRA, which reads:

‘The Labour Court may not review any decision or ruling made
during conciliation or arbitration proceedings conducted under the auspices of
the Commission or any bargaining council in terms of the provisions of this
Act before the issue in dispute has been finally determined by the
Commission or the bargaining council, as the case may be, except if the
Labour Court is of the opinion that it is just and equitable to review the
decision or ruling made before the issue in dispute has been finally
determined.’

decision or ruling made before the issue in dispute has been finally
determined.’

[25] So, the point of departure is that review applications in medias res are not
allowed, unless it can be shown by the applicant that it is just and equitable to

11

do so. But what does just and equitable mean? In Ntombela and Others v
United National Transport Union and Others9 this was dealt with as follows:

‘I will start with the question whether the intervention sought by the applicant,
pending the review, is appropriate and justified. In this regard, and as touched
on above, s 158(1B) provides some answer. It in effect prohibits a review
application in the case of CCMA arbitration proceedings that have not yet
been completed, unless an applicant shows it is just and equitable to do so. In
other words, the applicants need to show proper cause why such a review
should be allowed. I can find no trace in the application that the
applicants ever did this. It is incumbent on a review applicant to make out a
proper case in the founding affidavit in such a review application as to why
this court should exercise its discretion in entertaining the review application
on the basis that it is just and equitable to do so. Ordinarily, this failure by the
applicants would render the pending review application to be incompetent,
because no case is made out to provide a justified basis upon which this court
can decide whether the preliminary review application is competent, which in
itself must dispose of the review based on the provisions of s 158(1B).’

[26] The applicant has contended that it would be just and equitable to allow the
review in medias res in this instance because it concerns an issue of
jurisdiction, which issue has been determined by the third respondent in a
manner that is fundamentally in error. A substantial portion of the applicant’s
founding affidavit is devoted to a discussion of the review application,
indicating in what manner the third respondent erred and why his findings of
jurisdiction would be unsustainable not only on the facts, but also on the law.
In summary, the applicant argues that it is just and equitable that it be allowed
to challenge a jurisdiction al ruling up front , when such ruling is based on a

to challenge a jurisdiction al ruling up front , when such ruling is based on a
material error of law.

[27] I do accept that institutions such as the bargaining councils and the CCMA
cannot finally determine their own jurisdiction. In SA Rugby Players

9 (2019) 40 ILJ 874 (LC) at para 40.

12

Association and Others v SA Rugby (Pty) Ltd and O thers10 it was held that :
‘… The CCMA is a creature of statute and is not a court of law. As a general
rule, it cannot decide its own jurisdiction. It can only make a ruling for
convenience …’. The Court in Ntombela supra adopted the same view, where
the Court said: ‘… it had to be emphasised that jurisdictional rulings by CCMA
arbitrators, other than condonation rulings, are not final rulings. It is trite that
jurisdictional rulings of CCMA arbitrators are rulings of convenience. …’11.

[28] As touched on shortly above, the applicant has argued that the decision of the
third respondent that the SALGBC has jurisdiction continues a material error
of law, in that the third respondent failed to appreciate the actual date when
the dispute arose. The time limit imposed by s ection 191(1)(b)(ii)12 within
which an unfair labour practice dispute must be referred to conciliation
constitutes a jurisdictional fact, and the failure to adhere to the same means,
effectively, that the proceedings that would follow must be seen to be
irregular, and thus null and void. Where an arbitrator determines that this
jurisdictional requirement has been complied with, then it is a ruling for
convenience, and would enable the arbitration to continue, subject of course
to the caveat that the issue of jurisdiction can only finally be determined by the
Labour Court. This consideration, in my view, substantiates a review
application in medias res , especially where it is said this ruling by the
arbitrator is founded on an error of law. This appears to be clear from the
following dictum in South African Cabin Crew Association supra, where the
Court held:
13

‘Judicial intervention is all the more justified where a review is instituted in
medias res to challenge and set aside a ruling premised on a material error of
law. Because section 33(1) of the Constitution affords everyone the right to

law. Because section 33(1) of the Constitution affords everyone the right to

10 (2008) 29 ILJ 2218 (LAC) at para 40. See also Qibe v Joy Global Africa (Pty) Ltd: In re Joy Global
Africa (Pty) Ltd v Commission for Conciliation, Mediation and Arbitration and O thers (2015)
36 ILJ 1283 (LAC) at para 5; Universal Church of the Kingdom of God v Myeni and O thers (2015)
36 ILJ 2832 (LAC) at para 27.
11 Id at para 54.
12 The section prescribes that a referral must be made within: ‘ … 90 days of the date of the act or
omission which allegedly constitutes the unfair labour practice or, if it is a later date, within 90 days of
the date on which the employee became aware of the act or occurrence …’.
13 Id at para 28.

13

administrative action that is lawful, reasonable and procedurally fair, the
courts are empowered to review errors of law, as long as such errors are
material in nature. An error of law arises from questions of law and generally
relates to a misinterpretation or misapplication of a legal principle or section in
legislation.’

A similar approach was adopted in Ntombela supra, where the Court said:14

‘… it is still necessary to consider the nature of and reason for the review
challenge, as this is certainly a relevant consideration in deciding whether
justice will be best served by allowing the matter to proceed. In the review
application at stake in this instance, it concerns a simple point of law. Was it
permissible for the third respondent to issue a ruling on 11 July 2018 finding
that the CCMA does have jurisdiction to decide the unfair labour practice
dispute by UNTU, when he had issued a ruling on 6 March 2018 deciding that
the CCMA does not have this jurisdiction? According to the applicants, this is
not permissible, and the third respondent was functus officio. In my view, this
is the kind of legal question that would justify the bringing of a review
application despite the arbitration proceedings at the CCMA not being
concluded. The simple reason for this is that it is the kind of issue that causes
uncertainty, and involves a legal issue that would in fact dispose of a matter
on the merits thereof if successful, no matter what may happen if the dispute
is ultimately arbitrated. This is what is contemplated by ‘just and equitable’ in s
158(1B) …


[29] Therefore, I do believe that the applicant’s review application, despite the
arbitration proceedings not being complete, is permissible and competent.
The applicant has satisfied the requirements of ‘just and equitable’ under
section 158(1B), in order to bring the review application at this point. It follows
that the pending review application could legitimately serve as a foundation

that the pending review application could legitimately serve as a foundation
for the relief sought by the applicant. It must be said that if the applicant failed
in convincing this Court that bring ing the review application at this juncture
was just and equitable, then this would have been the end of the applicant’s

14 Id at para 42.

14

application in casu, a s it would have no foundation for the relief sought. So,
and at least, the applicant successfully cleared this first hurdle.

[30] However, and unfortunately for the applicant, this is not where the enquiry
ends.15 This is because the existence of a proper and competent review
application is not per se determinative of the applicant’s entitlement to
interdictory relief. It is simply a possible basis for it. But more is needed to
justify urgent intervention to interdict / stay pending arbitration proceedings. In
this context, the determination moves beyond the consideration of what is just
and equitable, and into t he realm of what is truly exceptional circumstances .
Or differently put, th e applicant must also prove that there exists truly
expectational circumstances that justify the suspension of the pending
arbitration proceeding until the review is decided, which is more than the just
and equitable consideration. Having due regard to several of the primary
objectives of the LRA, especially those relating to a simpl ified dispute
resolution process and the imperative of expeditious dispute resolution, this is
a hefty burden to discharge. As made clear in South African Cabin Crew
Association supra:16

‘Exceptional circumstances justifying judicial intervention in incomplete
proceedings have been found to exist where such intervention was necessary
to prevent illegality, to prevent grave injustice, or where justice could not
otherwise be achieved.’

[31] In Spar Group Ltd t/a Spar South Rand Distribution Centre v CCMA and
Others17 the Court expressed the following concerns where it comes to what
the Court described as a ‘worrying trend’ of litigants seeking to review
interlocutory rulings by arbitrators and then pursuing an interdict to suspend
arbitration pending the determination of such a review:


15 See Ntombela (supra) at para 44.
16 Id at para 27 . See also Ntombela (supra) at para 31; Workforce Group (Pty) Ltd v National Textile

Bargaining Council and Another (2011) 32 ILJ 3042 (LC) at para 18.
17 [2010] JOL 26397 (LC) at para 8.

15

‘A worrying trend has developed where parties who are not happy with rulings
made by commissioners or arbitrators in uncompleted matters would want to
interdict the uncompleted proceedings. This Court may in exceptional cases
where a grave injustice might otherwise result or where justice might not by
other means be attained, interdict uncompleted proceedings. I share the
views and sentiments expressed by Van Niekerk J in Trustees for the time
being of the National Bioinformatics Network Trust v Jacobson & others …’

[32] I accept the proposition that should it ultimately be found that the third
respondent committed a material error of law in finding that the second
respondent had jurisdiction, this could lead to an outcome that the entire
arbitration proceedings that followed would be effectively vitiated without
more, with all the time and expense wasted as a result of such outcome. It is
indeed a factor to consider. However, I do not believe this would constitute a
grave injustice or illegality necessary to establish exceptional circumstances.
The point always remains that the jurisdictional ruling stands until set aside,
and any consequences flowing from it will remain valid and binding if not set
aside.
18

[33] What happened in this case is not an open and shut jurisdictional issue, so to
speak. The finding of the third respondent is effectively a decision based on
factual findings , namely when the first respondent was aware, for the
purposes of section 191(1)(b)(ii) , of the alleged unfair labour practice. This
kind of decision can really only be properly made after considering the
evidence by the first respondent about the events in 2024, and why he
believes that the circular of 27 January 2025 is the trigger for him pursuing an
unfair labour practice. There may well be substance in his argument in this
regard, which the third respondent at least on a prima facie basis, considering
what was before him at that time , accepted. But all the third respondent had

what was before him at that time , accepted. But all the third respondent had
was that which was placed before him by the parties in a process akin to
motion proceedings. I do not believe this can lead to a final determination of

18 See Oudekraal Estates (Pty) Ltd v City of Cape Town and Others 2004 (6) SA 222 (SCA) at para
26; Manok Family Trust v Blue Horison Investments 10 (Pty) Ltd and Others 2014 (5) SA 503 (SCA)
at para 17; MEC for Health, Eastern Cape and Another V Kirland Investments (Pty) Ltd t/a Eye and
Lazer Institute 2014 (3) SA 481 (CC ) at paras 88 – 89 and 103; Camps Bay Ratepayers' and
Residents' Association and Another v Harrison and Another 2011 (4) SA 42 (CC) at para 62;

16

jurisdiction in the context of the issue at stake in this matter. It would be far
more appropriate to allow the arbitration to proceed so that evidence about
this can be properly ventilated. 19 There are certainly no exceptional
circumstances to justify why this should not be allowed.

[34] The point I make is simply this. If the arbitrator conducting the unfair labour
practice arbitration on the merits, after considering the evidence of the first
respondent, together with the proper challenging of that evidence, concludes
that the first respondent was in fac t aware, as contemplated by section
191(1)(b)(ii), of the alleged unfair labour practice already on 1 March 2024 as
contended by the applicant to be the case, then it would still be well within the
purview of such arbitrator to decide that the SALGBC has no jurisdiction ,
because the dispute was referred late without condonation, and then dispose
of the matter on that basis . Or in other words, the applicant’s ability to still
raise this, once all the evidence is in, is not compromised. If this happens, it
may well render the current review application moot, thus removing the need
to wait for years to have this issue decided in this Court , as it could be
disposed of right here and now in immanent arbitration. A similar state of
affairs was considered in Ntombela supra, and the Court decided as follows:20

‘All said, the subject-matter of the jurisdictional ruling of the third respondent
did not finally dispose of the merits of the case. It only was a determination as
to the nature of the dispute that was placed before the CCMA for arbitration.
In making this ruling, the actual merits of the matter need not be considered or
decided. Ultimately, the true or real nature of the actual dispute may only be
determined once all the evidence was in, at arbitration, and even at that point
it would be competent for the third respondent to decline jurisdiction. In simple

it would be competent for the third respondent to decline jurisdiction. In simple
terms, the third respondent had not yet discharged all the duties and functions
bestowed upon him by the LRA in finally bringing this matter to an end.



19 As held in EOH Abantu (Pty) Ltd v CCMA and Others (2010) 31 ILJ 937 (LC) at para 29: ‘Where the
jurisdictional issue in question requires the resolution of factual dispute, the leading of oral evidence
and a determination of difficult questions of mixed law and fact, on matters that are intimately bound
up with the substantive merits of the dispute may legitimately be deferred to the arbitration stage of
the proceedings …’.
20 Id at para 56.

17

The Court in Mlambo v Safety and Security Sectoral Bargaining Council and
Others21 similarly decided, finding as follows:

‘Where, having assumed jurisdiction, it later transpires that those facts do not
satisfy jurisdictional requirements, nothing in my view prevents an arbitrator
from changing his mind provided that the initial ruling is not one of those
referred to as being irrevocable. It might be argued that this approach could
encourage vacillation by arbitrators when issuing provisional rulings, thus
resulting in parties sitting in arbitration proceedings that B might as well turn
out to be an expensive academic exercise. Inasmuch as there might be merit
in these arguments, one would rather be sitting with a final outcome that is
valid, fair, legally sound, competent and enforceable than one that is a nullity.


[35] It also cannot b e ignored that if the case of the first respondent is so poor on
the merits, as the applicant actually submits it is, then once again the entire
pending review process could be short circuited by the applicant’s
participation in the arbitration process and defeating the first respondent’s
case on the merits. This approach will not compromise the applicant’s current
pending review at all . If the applicant is ultimately unsuccessful in the
arbitration, it can still pursue the current review, even together with a review
application challenging any finding on the merits of the dispute. These are
considerations that detract from the existence of any exceptional
circumstances justifying a need to intervene, as it provides for other options to
attain justice. As decided in Ntombela supra:22

‘But there is a further consideration that works against the applicants being
entitled to the relief they ask for. This is the consideration of an alternative
remedy, which is similar to the issue of substantial redress being available in
due course discussed under the heading of urgency above. The arbitration

due course discussed under the heading of urgency above. The arbitration
proceedings have not even been set down. The applicants have never
actually engaged with the third respondent by way of a proper postponement
application before him, in terms of which he could then exercise his own
discretion as to whether the matter should be postponed pending the review

21 (2012) 33 ILJ 2427 (LC) at para 55.
22 Id at para 67.

18

before this court being decided. Or the applicants could have simply
participated in the arbitration, and if they were not satisfied with the outcome,
then take all the determinations made in the proceedings on review to this
court.’

[36] The Court in Southern Sun Hotel Interests (Pty) Ltd v Commission for
Conciliation, Mediation and Arbitration and O thers23 made the same point,
deciding as follows:

‘As I have stated above, the applicant could have attended the part- heard
arbitration in order to finalize the matter and, had it been dissatisfied, taken it
on review. Alternatively, it could have applied to the arbitrator already hearing
the matter to postpone the hearing pending the outcome of a review against
his jurisdictional ruling. Had the arbitrator refused, the CCMA would have
been functus officio. The applicant could then have applied to the Labour
Court to review and set aside the arbitrator's refusal to postpone. Instead, the
applicant launched an urgent application in this court - and sought costs
against the CCMA - in circumstances where it had not followed the procedure
prescribed by the CCMA Rules. …


[37] Another concern I have, which I in fact raised with the applicant’s counsel
when this matter was argued, is why the applicant did not bring an actual
application for postponement to the arbitrator, making out a case that the
matter needs to be postponed so that the review could first be decided. In that
application, the applicant could place a case of possible undue prejudice it
would suffer if arbitration proceeds before the arbitrator, so that the arbitrator
could exercise his or her discretion in this regard. The applicant c ould also
place the review application itself before the arbitrator, so he or she could
assess its prospects of success, as part of exercising a discretion. In my view,
the applicant’s failure to even have attempted this must count against it. In
Workforce Group (Pty) Ltd v National Textile Bargaining Council and

Workforce Group (Pty) Ltd v National Textile Bargaining Council and
Another24 the Court held:


23 (2011) 32 ILJ 2756 (LC) at para 38.
24 (2011) 32 ILJ 3042 (LC) at para 16.

19

‘The applicant has a clear alternative remedy, namely, to apply for a
postponement at the CCMA pending the finalisation of the review application.
In terms of CCMA rule 23, an arbitration may be postponed by agreement
between the parties; or by application and on notice to the other parties. In
this case, the applicant has made no effort to apply for a postponement at the
CCMA. There is nothing in the CCMA rules preventing the arbitrator from
postponing the continuation of the arbitration pending the finalisation of the
review application.’

[38] One also cannot ignore the prejudice to the first respondent. The fact is that
he would have to wait for years for the review to be heard. In the meantime,
the fifth respondent would remain in the position and become entrenched in it,
which would be a formidable obstacle in the way of the first respondent
obtaining the relief of being considered for the position should h e ultimately
establish that he was unfairly treated in not being shortlisted for the position .
The point is that this is an issue that must be resolved with expedition, and the
only way to achieve this is to allow the arbitration to proceed. Again , it must
be emphas ised, in the context of the prejudice consideration, that the
applicant always retains the backup of the right to challenge of any finding on
the merits on review, without even compromising the current review
application. I believe there is little prejudice to the applicant to just proceed
with the arbitration. In EOH Abantu (Pty) Ltd v Commission for Conciliation,
Mediation and Arbitration and Others25 the Court held:

‘(2) The applicant will suffer no prejudice should the matter proceed to
arbitration. It will be able to raise the jurisdictional issue it would like to, and a
commissioner will be able to weigh evidence on the issue (after hearing all the
evidence as this is an issue which is linked to the merits) and give a binding

evidence as this is an issue which is linked to the merits) and give a binding
award. At that stage, would any party be dissatisfied, it will be able to seek to
review the award in accordance with the LRA. This will mean the Labour
Court will have the benefit of the CCMA’s decision and will not become
involved prematurely in matters. This will prevent a flood of similar
applications.


25 (2010) 31 ILJ 937 (LC) at para 16.

20

(3) The third respondent and the first respondent however do suffer prejudice.
The third respondent’s dispute has been delayed due to these
applications despite having the right in terms of the LRA to refer the matter to
the first respondent for arbitration. Should this precedent be confirmed then
the first respondent’s efficient resolution of disputes will be compromised.’

[39] The applicant has simply not made out any case of exceptional circumstances
in line with all the principles discussed above. There will no illegality o r grave
injustice if the arbitration is allowed to continue. There are many other options
available to the applicant to secure its rights. In fact, if the contents of the
applicant’s founding affidavit are properly considered, what the applicant is
actually saying is because its review application has substantial prospects of
success, the third respondent committed a material error of law, and the issue
at stake is one of jurisdiction , th ese factors constitute exceptional
circumstances per se. In my view, the applicant i s conflating what is ‘just and
equitable’ with ‘exceptional circumstances’. Just and equitable substantiates a
review in medias res being permissible. Exceptional circumstances justify
interference in arbitration proceedings that are incomplete, by interdicting it.
These are different cases. In sum, the applicant made out a case for the
former, but not the latter. As such, the applicant has made out no case for
intervention.

[40] In the end, it is my view that the fundamental requirement of the expeditious
resolution of employment disputes must carry the day. The arbitration
proceedings must be allowed to continue. It will not compromise the
applicant’s right to review . There is nothing unique or exceptional about this
case which cries out for immediate and urgent intervention. I also believe that
there are no compelling considerations of injustice that will result if the

there are no compelling considerations of injustice that will result if the
arbitration proceedings are allowed to continue There is a forum for the
applicant to air all its complaints, and that forum is not this Court at this stage.
There is simply no valid cause or reason for it to involve this Court in the
incomplete arbitration proceedings.

Conclusion

21


[41] As a result of all of the above, it is my view that the applicant has failed to
demonstrate a clear right to the relief sought, and in any event has suitable
alternative remedies available to it . The application thus falls to be dismissed
on the basis of the applicant’s failure to satisfy two of the essential
requirements that need to be satisfied in order to obtain the interdictory relief it
seeks. On this basis, I decide that the applicant’s application must be
dismissed.

Costs

[42] In terms of section 162(1) of the LRA, I have a wide discretion where it comes
to the issue of costs. That being said, I believe this is a case where a costs
order against the applicant is justified. One can hardly describe the situation in
casu any better than referring to the following dictum in Ngobeni v Passenger
Rail Agency of SA Corporate Real Estate Solutions and Others 26 where it
was said:

‘The urgent roll in this court has become increasingly and regrettably
populated by applications in which intervention is sought, in one way or
another, in workplace disciplinary hearings. The present application is a prime
example … All of this is indicative of an attempt to use this court and its
processes to frustrate the workplace proceedings already underway. The
abuse goes further — what the applicant effectively seeks to do is to bypass
the statutory dispute-resolution structures in the form of the CCMA and
bargaining councils. One of the primary functions of these structures is to
determine the substantive and procedural fairness of unfair dismissal
disputes. Applicants who move applications on an urgent basis in this court
for orders that effectively constitute findings of procedural unfairness, bypass
and undermine the statutory dispute-resolution system. The court's proper
role is one of supervision over the statutory dispute-resolution bodies; it is not
a court of first instance in respect of the conduct of a disciplinary hearing, nor

a court of first instance in respect of the conduct of a disciplinary hearing, nor
is its function to micromanage discipline in workplaces. …’


26 (2016) 37 ILJ 1704 (LC) at para 14.

22

Although the judgment in Ngobeni dealt with intervention in incomplete
disciplinary proceedings, the same considerations would apply to urgent
intervention being sought in incomplete arbitration proceedings.

[43] The applicant was legally assisted throughout these proceedings. The
applicant should thus have known, from the outset, that its application was
doomed to fail. This Court has made it patently clear, on a number occasions,
how attempts to intervene in incomplete arbitration proceedings are perceived
by this Court, and that is that it should not be entertained save for the gravest
of circumstances. This kind of behaviour as perpetrated by the applicant is not
conducive to the fundamental requirement of the expeditious resolution of
employment disputes, and should be frowned upon. 27 There was nothing
standing in the way of the applicant simply participating in the arbitration,
where it was were free to raise all the defences it wanted, including once
again raising the issue of jurisdiction once all the evidence was in.

[44] And finally, the continuous failure by litigants to heed the numerous warnings
by this Court where it comes to these kinds of applications must be visited
with adverse consequences.
28 I fully align myself with the following dictum in
Mokoena v Merafong Municipality and Others:29

‘In casu, the applicant brought a meritless application to this court and
fairness dictates that the respondents cannot be expected to endure
enormous costs defending litigation where more thought and consideration
had to be put in before approaching this court on an urgent basis. …’

[45] I thus conclude that this is an appropriate case where an exercise of my
discretion under section 162(1) of the LRA must lead to the applicant being
ordered to pay the costs of the application, on the scale as between party and
party, scale B.


27 Ntombela (supra) at para 70.

party, scale B.


27 Ntombela (supra) at para 70.
28 See, for example, Uthukela District Municipality (supra) at para 47; Magoda v Director-General of
Rural Development and Land Reform and Another [2017] JOL 38772 (LC) at para 20; Botes v City of
Joburg Property Company SOC Ltd and Another (J 937/20) [2020] ZALCJHB 200 (28 September
2020) at para 50.
29 (2020) 41 ILJ 234 (LC) at para 36

23

Order

[46] It is for all the reasons set out above that I made the order that I did, as
reflected in paragraph 5 of this judgment, supra.







__________________
S Snyman
Acting Judge of the Labour Court of South Africa



APPEARANCES:

On behalf of the Applicant: Advocate N S V Mfeka

Instructed by: Legator McKenna Inc

On behalf of the First Respondent: Mr M Dlamini of M Dlamini Inc Attorneys