Mulebeke and Others v Cest La Vie Construction and Others (2025/145152) [2025] ZAGPJHC 955 (30 September 2025)

60 Reportability
Contract Law

Brief Summary

Contract — Cancellation of building agreements — Applicants, owners of stands in Derby Villas Estate, sought to cancel building agreements with Cest La Vie Construction (Pty) Ltd due to alleged breaches and misrepresentations regarding construction progress and NHBRC registration — Respondents contended that no valid cancellation occurred as applicants failed to provide required notice to remedy breach — Court addressed whether alleged misrepresentations constituted actionable misrepresentations or mere promises of future performance — Holding that applicants were not entitled to cancel the agreements without providing the contractual notice, thus the cancellations were ineffective and interdictory relief sought to secure access to properties was denied.

2



This judgment is handed down electronically by circulation to the parties’ legal
representatives by email and by being uploaded to CaseLines. The date for hand down
is deemed to be 22 September 2025.

MAHON AJ:
Introduction
[1] This is an urgent application in which the applicants, who are the registered
owners of two stands in the Derby Villas Estate, Johannesburg, seek relief
arising from building agreements concluded with the first respondent, Cest La
Vie Construction (Pty) Ltd. They ask the court to confirm that those agreements
have been validly cancelled and to grant interdictory relief securing their and
their nominated contractors’ free and undisturbed access to the properties so
that building work may proceed under their own management.
[2] The respondents oppose the application. They contend that the building
agreements remain in force, that the applicants did not comply with the
contractual provisions requiring a prior notice to remedy breach before
cancellation, and that the applicants have not shown any unlawful denial of
personal access to their properties, only that entry by unauthorised contractors
has been regulated.
[3] During the hearing the court raised, and counsel addressed, a further question:
whether the statements on which the applicants rely as misrepresentations are,
on a proper characterisation, promises of future performance rather than
statements of existing fact. That question matters because a promise that

3


something will be done engages the law of contract and breach, whereas a
misrepresentation concerns a false statement about an existing state of affairs
and can support rescission without prior notice to remedy breach.
[4] The application accordingly turns on three broad issues: whether the applicant s’
purported cancellations of their building agreements were legally effective;
whether, in the light of the nature of the statements relied on, the alleged
misrepresentations entitled them to bypass the contractual notice requirement;
and whether the facts justify the final interdictory relief sought to compel access
to the properties.
Background Facts
[5] The applicants are the registered owners of two stands in the Derby Villas
Estate, Johannesburg. The first and second applicants own erf 2971, and the
third and fourth applicants own erf 2996. Each pair concluded a written building
agreement with the first respondent, Cest La Vie Construction (Pty) Ltd,
represented by its sole director, the second respondent. The agreements
obliged the first respondent to construct homes on the stands for agreed prices
and within specified periods.
[6] For the first and second applicants, the history is protracted. They initially signed
a building agreement in April 2020, which was superseded by a second
agreement dated 7 August 2023. Their stand was registered in April 2024. They
complain that construction progress was slow and beset by problems, including
a collapse of part of a wall and concerns over the first respondent’s registration
with the National Home Builders Registration Council (NHBRC). Although

4


payments were made and dates for the houses to be complete were repeatedly
promised, the works remained far from complete by mid-2025.
[7] The third and fourth applicants concluded their building agreement on 7 May
2024. Their site was likewise registered with the deeds office later in 2024. They
too experienced lengthy delays and raised concerns about the first respondent’s
NHBRC compliance. Despite additional payments for agreed variations,
construction scarcely advanced beyond the foundations and was nowhere near
complete.
[8] By early July 2025 both sets of applicants had lost confidence in the first
respondent’s performance. Acting through their attorneys, they each addressed
letters purporting to cancel their building agreements. The letters alleged
persistent breaches, including failure to have the houses complete within the
agreed periods, failure to remedy defective work, and misstatements about
NHBRC registration. No prior notice to remedy breach was given in terms of
clause 15.3 of the agreements, which requires written notice identifying the
default and affording 21 days to remedy it.
[9] The first respondent, through its director, disputed the validity of the
cancellations and insisted that the agreements remained in force. It warned that
owners who attempted to engage alternative contractors without its consent
would be prevented from doing so and might face interdict proceedings.
Security guards employed by the fifth respondent were instructed to deny
access to contractors not authorised by the first respondent. The applicants

5


allege that this instruction extended to them personally, though the respondents
maintain that owners were never barred, only their contractors.
[10] The applicants contend that they have suffered continuing harm in the form of
delayed ability to have their homes complete and ready for occupation, financial
losses on bonds and rental, and personal hardship to their families. They
therefore seek confirmation of the cancellations and interdictory relief to ensure
that they and their contractors may access the properties without interference.
[11] The respondents deny that any valid cancellation has occurred. They
emphasise that the agreements contain a clear notice- to-remedy clause, that
NHBRC registration was in place, and that the complaints of misrepresentation
are not borne out. They further dispute that the applicants have been unlawfully
excluded from their own properties.
Submissions and Exchanges at the Hearing
[12] The matter was argued as an urgent application. At the outset, the respondents
challenged the appropriateness of entertaining the application urgently, relying
primarily on alleged defects in service and the absence of an explanation in the
founding papers for non-compliance with Rule 6(12)(b). It was pointed out that
the fourth respondent initially received only a WhatsApp copy of the notice of
motion and only later obtained the founding papers by way of a Dropbox link.
Counsel argued that this fell short of the requirement that an applicant seeking
urgent relief must set out fully the reasons for any failure to effect proper service,
and that the court ought to strike the matter from the roll or, at the least, reserve
the question of costs to reflect the irregularities.

6


[13] The court engaged extensively on the issue of urgency. It was observed that,
assuming the correctness of the applicants’ version for this purpose, the
deprivation of access to their own properties amounted to an ongoing harm that
justified urgent intervention. The court noted that all parties who wished to
participate had in fact received the papers and were represented, and
questioned whether any real prejudice had been caused by the alleged
procedural defects. Counsel for the respondents accepted that their clients were
able to file answering papers and argue the merits, but maintained that the lack
of formal service should not be overlooked, cautioning that a precedent might
be set which would undermine the discipline required by Rule 6(12)(b).
[14] In my view, this concern should not carry weight in the present matter. All
respondents who wished to be heard were fully apprised of the applicatio n in
time to instruct attorneys and file detailed answering papers. The substance of
the rule, namely to ensure that respondents are informed and able to
participate, was therefore met. This was not a case where non-compliance
undermined the purpose of service or caused real prejudice. It was instead one
where the practical realities of urgent motion practice justified condonation for
what were, in context, formal defects in an application where ongoing harm can
only be arrested through an urgent hearing.
[15] Argument then turned to the merits. The respondents’ principal submission was
that the building agreements remain of full force and effect because clause 15.3
of each contract stipulates that, before cancellation for breach, the innocent
party must give written notice identifying the default and allowing 21 days to
remedy it. No such notice was given. On this basis, it was argued, the purported

7


cancellations of July and August 2025 were ineffectual and incapable of
founding the declaratory or interdictory relief sought.
[16] The applicants accepted that no clause 15.3 notice was given but sought to
justify their course on the footing that they were induced to contract by
misrepresentations, particularly about the first respondent’s NHBRC
registration and ability to have the houses complete within agreed timeframes.
They contended that these misrepresentations vitiated the agreements and
excused the requirement of a prior notice to remedy breach.
[17] During argument the court raised the question whether the statements relied
upon as misrepresentations were, on a proper characterisation, promises of
future performance rather than statements of existing fact. Counsel were invited
to address whether such promises, if not fulfilled, would amount to contractual
breaches requiring notice to remedy, rather than actionable misrepresentations
permitting cancellation without an obligation to provide for notice under clause
15.3. The applicants submitted that the respondents’ statements about NHBRC
registration and completion dates were presented as present compliance and
therefore fell within the concept of misrepresentation. The respondents
maintained that, even if some statements proved inaccurate, they were no more
than undertakings as to what would be done in the future.
[18] A further aspect that emerged from the contractual framework is that, for as long
as the building agreements remain extant, the applicants are contractually
precluded from introducing their own contractors to perform the works or to gain
site access for that purpose. Clause 3.1 expressly appoints the first respondent

8


as the builder and provides that it will supply all material and labour required for
the works.
[19] Read with clause 15.3, which makes notice to remedy breach a condition
precedent to cancellation, these provisions mean that the builder not only has
the duty to construct the dwellings but also the right to regulate and control
access to the site in order to perform and to assume the associated risks.
Allowing outside contractors on site before a valid cancellation would undermine
the builder’s responsibility for NHBRC compliance, warranties and insurance,
and would defeat the carefully defined cancellation procedure.
[20] Other issues received more limited attention. The respondents disputed that the
applicants themselves had ever been refused access to their properties,
contending that security personnel merely enforced restrictions on the entry of
unauthorised contractors. The applicants, in reply, insisted that they and their
contractors had in fact been excluded and that their proprietary rights were
infringed. The court noted that these competing versions raised factual disputes
which might engage the Plascon-Evans rule
1 if final interdictory relief were
sought.
Cancellation and Misrepresentation
[21] The decisive question is whether the applicants were entitled to cancel their
building agreements without giving the contractual 21-day notice contemplated
by clause 15.3 of the agreements.

1 See Plascon-Evans Paints Ltd v Van Riebeeck Paints (Pty) Ltd 1984 (3) SA 623 (A)

9


[22] Clause 15.3 stipulates that the employer may cancel the agreement only if th e
builder defaults in one of three defined ways:
[22.1] without reasonable cause wholly suspends the works before
completion,
[22.2] without reasonable cause refuses to proceed with the works with
reasonable diligence, or
[22.3] without reasonable cause fails to comply timeously with local
authority conditions,
and even then only if the default continues for 21 days after written notice
specifying the default.
[23] This wording makes it clear that clause 15.3 is not a general cancellation clause
for every conceivable breach. It is directed at defined defaults relating to the
progress and legality of the works. If the employer relies on some other breach
that does not fit these categories, cancellation might be governed by the
common law rather than by clause 15.3. The first question is therefore whether
the breaches on which the applicants relied fall within one or more of the defined
categories.
[24] The applicants’ notices of cancellation and founding papers emphasise
persistent and lengthy delays in construction, periods when work cease d
altogether, failure to have the houses complete within the agreed or promised
timeframes, defective work including a collapsed wall, and misstatements about
NHBRC registration and ability to perform.

10


[25] Each of these complaints concerns either suspension of the works or a failure
to proceed with reasonable diligence. They therefore fall squarely within the
defaults enumerated in clause 15.3. There is no pleaded breach of a different
character that could sustain a common-law right to cancel independently of
clause 15.3.
[26] It follows that the operation of clause 15.3 is engaged and that the 21-day notice
to remedy default was a condition precedent to cancellation. It is common cause
that no such notice was given. Unless the applicants can establish that their
case falls within a different ground for rescission not subject to clause 15.3, the
absence of the required notice is fatal.
[27] The applicants sought to avoid the operation of clause 15.3 by characterising
certain statements by the first respondent as misrepresentations. They
contended that they were induced to contract, and later to persist with the
agreements, by statements that the first respondent would be duly registered
with the National Home Builders Registration Council (NHBRC), that
construction would be complete within specified timeframes, and that adequate
resources and contractors were in place to achieve those outcomes.
[28] The legal distinction between a misrepresentation and a contractual promise is
critical. A misrepresentation is a false statement of an existing fact, made before
or at the time of contracting, which induces a party to contract and, if proved,
may justify rescission without the need to comply with contractual notice
provisions. A contractual promise, by contrast, is an undertaking to bring about
a state of affairs in the future. Non-performance of such an undertaking does

11


not constitute a misrepresentation; it is a breach of contract, which must be
addressed through the contract’s own remedial mechanisms.
[29] Counsel were invited to identify any specific statement that was, at the time it
was made, false as to an existing fact. None emerged. The undertakings relied
upon - that the houses would be complete within six months, that project plans
would be met, or that NHBRC registration would be secured - are, on their face,
commitments about what would be done, not assertions of an existing state of
affairs. Even on the applicants’ version, these are promises of future
performance and therefore part of the contractual bargain, not extraneous
representations.
[30] At worst, there were delays in progressing individual NHBRC enrolments or
inspections. That may constitute non-performance of a contractual undertaking
to comply with statutory requirements, but it is not a misrepresentation of an
existing fact at the time the contracts were concluded.
[31] The applicants also referred to alleged coercive demands for additional
payments. Even accepting those allegations at face value, they do not transform
the builder’s promises into actionable misrepresentations. At most, they raise
issues of performance and breach that remain subject to clause 15.3.
[32] The result is that no independent ground for rescission based on
misrepresentation has been established. All the breaches on which the
applicants rely either fall within clause 15.3 or are not established on the facts.
The 21-day notice to remedy default was therefore a necessary condition to a
valid cancellation, and the applicants’ failure to give such notice is fatal to their

12


case. Their purported cancellations of July and August 2025 were invalid, and
the building agreements remain in force.
Consequences for the Interdictory and Access Relief
[33] The principal relief sought by the applicants, apart from confirmation of
cancellation, is a final interdict to secure their and their contractors’ free and
undisturbed access to the properties for purposes of carrying out their own
work.
[34] That relief cannot be granted. The finding that the building agreements have not
been validly cancelled means that those agreements remain of full force and
effect. While they remain extant, the first respondent continues to hold the
exclusive contractual mandate to construct the dwellings and to regulate access
to the sites for that purpose.
[35] Clause 3.1 expressly records that the builder “will supply all material and labour
required for the works”. Read with clause 15.3, which provides the sole
mechanism for termination, this confers on the builder not merely the duty to
build but the correlative right to control the building site and to prevent the
introduction of outside contractors whose presence could compromise safety,
NHBRC compliance, warranties, insurance cover, and the integrity of the works.
The applicants cannot, while the agreements endure, unilaterally appoint their
own contractors or insist on their access for purposes of carrying out their own
work without breaching the agreements.
[36] The factual dispute about whether the applicants themselves have been barred
from entering their properties does not assist them. On the respondents’

13


version, which must be preferred where there is a genuine dispute of fact on
final motion, the applicants have never been refused personal access. What
has been regulated is the entry of third-party contractors not appointed by the
first respondent . Indeed, the respondents have expressly undertaken not to
deprive the applicants themselves of access to their properties. Even if there
had been occasional interruptions or misunderstandings, those do not translate
into a clear right to compel access for outside contractors when the contract
itself forbids such access.
[37] Final interdictory relief requires proof of a clear right, an injury actually
committed or reasonably apprehended, and the absence of an adequate
alternative remedy. Because the applicants’ agreements remain binding and
give the first respondent exclusive rights over the construction works and
associated access, the applicants cannot demonstrate the clear right that is the
first and essential element. The remaining requirements therefore need not be
considered in detail.
[38] Accordingly, the prayer for an interdict to secure unrestricted access for
purposes of carrying out their own work must also fail. The contractual
arrangements that they themselves concluded, and that have not been validly
terminated, preclude such relief.
[39] As to costs, I do not consider there to be any compelling reasons why the
ordinary rule should not apply, namely, that costs should follow the result. As
for the scale of costs, I am of the view that Scale B is appropriate.
[40] In the circumstances, the following order is made: