THE SUPREME COURT OF APPEAL OF SOUTH AFRICA
JUDGMENT
Reportable
Case no: 236/2024
In the matter between:
RUSTENBURG LOCAL MUNICIPALITY APPELLANT
and
BURRIE SMIT ONTWIKKELAARS (PTY) LTD RESPONDENT
Neutral citation: Rustenburg Local Municipality v Burrie Smit Ontwikkelaars (Pty)
Ltd (236/2024) [2025] ZASCA 147 (7 October 2025)
Coram: SCHIPPERS, BAARTMAN and COPPIN JJA and STEYN and KUBUSHI
AJJA
Heard: 26 August 2025
Delivered: This judgment was handed down electronically by circulation to the
parties’ representatives by email, publication on the Supreme Court of Appeal website,
and release to SAFLII. The date for hand dow n is deemed to be 7 October 2025 at
11h00
Summary: Expropriation – Expropriation Act 63 of 1975 (the Act) – meaning and
effect of s 12(3) – interest on unpaid compensation from expropriation date – offer of
compensation rejected – effect on costs – applicability of costs formula in s 15 and
s 14(8)(e) of the Act – nature of court’s discretion – costs to be ordered against owner
if compensation determined by the court less than or equal to offer rejected – inclusion
of solatium in compensation – apportionment of costs – compensation determined by
court less than amount claimed by owner but exceeds amount last offered as
compensation – applicability of s 15(2)(c).
2
___________________________________________________________________
ORDER
___________________________________________________________________
On appeal from : North West Division of t he High Court, Mahikeng (Hendricks JP,
sitting as a court of first instance):
1 The appeal is upheld with costs, including the costs of two counsel where so
employed.
2 The cross -appeal is dismissed with costs, including the costs of two counsel
where so employed.
3 Paragraphs (c), (e), and (f) of the order of the high court of 3 November 2023 are
set aside and are replaced with the following paragraphs:
‘(c)(i) The defendant is ordered to pay interest on the amount of R593 690.80 at
the applicable rate from the agreed date of expropriation, being 31 July 2004,
until 7 August 2007, less the amount of R391 683.00 that the defendant already
paid as interest on 7 August 2007;
(c)(ii) The interest referred to in paragraphs (b) and (c)(i) is simple statutory
interest as envisaged in s 12(3)( a) of the Expropriation Act 63 of 1975 (the Act)
charged at the rate determined from time to time by the Minister of Finance in
terms of s 80(1)(a) of the Public Finance Management Act 29 of 1999.
(d) . . .
(e) The plaintiff is ordered to pay the defendant’s costs, including the costs of two
counsel where so employed, incurred after 11 November 2016, the qualifying
fees of Messrs Ballack, Rudolph, Nagy and D Griffiths incurred after 11
November 2016, and the costs of the interlocutory application reserved on 17
September 2019;
(f) In respect of all the costs incurred until 11 November 2016 – which include
the costs of the interlocutory applications reserved on 3 August 2015 and 11
October 2016, each party is to bear its own costs.’
3
___________________________________________________________________
JUDGMENT
___________________________________________________________________
Coppin JA (Schippers and Baartman JJA and Steyn and Kubushi AJJA
concurring):
[1] This appeal engages the following issues concerning compensation for
expropriation in terms of the Expropriation Act 63 of 1975 (the Act) : the nature and
rate of the interest payable on unpaid compensation as envisaged in s 12(3) of the
Act; and the impact of a rejected offer of compensation on costs as contemplated in
s 14(8)(e) read with s 15. These issues were not resolved by the North West Division
of the High Court, Mahikeng (high court) that determined the amount payable for the
expropriation of land. Resolving these issues involves interpreting relevant provisions
of the Act. As with all expropriation laws, its provisions must be strictly interpreted.
[2] The respondent, Burrie Smit Ontwikkelaars ( Pty) Ltd, a property development
company, was the registered owner of a tract of land, the remaining extent of portion
43 of the farm Waterval 306, Registration Division JQ, North West Province,
measuring about 87 5316 hectares (the property). It acquired the property in 1995 and
designated it for township development . The appellant, the Rusten burg Local
Municipality (the municipality) , on behalf of the Rand Water Board , by notice of
expropriation dated 6 July 2004, and a cting in terms of s 79(24) of the Local
Government Ordinance 17 of 1939 (the Ordinance), read with the relevant provision
of the Act, expropriated a portion of the property (approximately 3 2350 hectares) for
the construction of a 100 mega -litre water reservoir (the reservoir area) . It also
expropriated an area of the property measuring approximately 7 834 square meters
(m2) to serve as a servitude for the conveyance of water by means of a pipeline(s) (the
servitude area). The expropriation was urgent due to the bulk water supply needs in
Rustenburg.
Rustenburg.
[3] Although the expropriation notice is dated 6 July 2004, it is undisputed that the
actual date of the expropriation was 31 July 2004 . Under s 79(24) of the Ordinance,
the municipality was obliged to compensate the respondent for expropriating its
4
property. The municipality offered the respondent compensation as follows:
R1 941 000 for the reservoir area (ie, R60 per m2), plus R235 020 for the servitude
area (ie, R30 per m2), and R55 000 as a solatium. On 7 August 2007, the municipality
sent a cheque to the respondent as payment under s 11(1) of the Act for the total
amount of R2 622 703, which included the compensation offered, plus interest up to
31 July 2007 in the amount of R391 683. The respondent deposited the cheque, but
demanded further compensation: R2 249 750 for the reservoir area, R665 980 for the
servitude area, with a solatium, and value-added tax (VAT).
[4] The parties were unable to agree on the amount payable. On 24 November
2008, the respondent instituted action proceedings in the high court for a determination
of the quantum of the compensation. The respondent sought R85 per m² for the
reservoir and servitude areas, a solatium, plus VAT, and compensation for the loss of
the potential development of the remaining part of its property.
[5] The municipality defended the actio n and essentially argued that the
compensation it had offered was fair. It also disputed the respondent’s claim for
alleged financial loss due to the loss of developmental potential of the remnant
property. On 11 November 2016, before the trial commenced, the municipality made
a written ‘without prejudice ’ tender to the respondent of R1.5 million , which the
respondent rejected.
[6] It is agreed that the trial commenced on 11 June 2018 and that substantial legal
costs were incurred. It ran for three years with 37 days of hearings. On 7 June 2023,
the high court determined that the respondent was entitled to the following
compensation: R 2 264 500 for the reservoir area (ie, a rate of R70 m2) and R 274 190
(ie, a rate of R35 per m2) for the servitude area, plus R55 000 as a solatium. The high
court reserved the question s of costs and inter est for later determination. On 3
court reserved the question s of costs and inter est for later determination. On 3
November 2023, after receiving submissions from the parties on those questions, the
high court, made an order in the following terms:
‘(a) The defendant is ordered to pay the plaintiff an amount of R362 670.00 as compensation
in terms of Sections 12(1)(a) and (b) of the Expropriation Act (R323 500.00 for the reservoir
area and R39 170.00 for the servitude area).
5
(b) The defendant is ordered to pay interest on the said amount of R362 670.00 at the
applicable rate from 07 August 2007 until date of final payment.
(c) The defendant is ordered to pay interest at the applicable rate from the actual date of
expropriation as agreed between the parties, namely 31 July 2004 until 07 August 2007, less
the amount of R391 683.00 that was already paid as interest on 07 August 2007.
(d) No other amount as solatium is payable in terms of Section 12(2) of the Expropriation Act
63 of 1975.
(e) The reserved costs of the interlocutory applications of 03 August 2015; 11 October 2016;
and 17 September 2019 are costs in the action.
(f) Each party is ordered to pay its own costs.’
[7] The nature and rate of the interest were not specified in paragraphs (b) and (c)
of the high court’s order , and the capital sum on which the interest was payable was
also not stated in paragraph (c). The municipality also took issue with the costs order
in paragraph (f). It alleged that the costs order was not in compliance with s 14(8) (e)
of the Act and did not take into account the municipality’s without prejudice tender to
the respondent on 11 November 2016, before the trial commenced. It further argued
that in its costs order, the high court did not mention the qualifying fees of the expert
witnesses it had called. The high court granted the municipality leave to appeal its
‘costs and interest’ orders. It also granted the respondent leave to cross -appeal
against those same orders.
[8] The municipality argues that the without prejudice tender was not more than or
equal to the high court’s determination of the compensation. It contends that in respect
of the period up to 11 November 2016 , in terms of s 15(2) (c), the high court sh ould
have awarded it 40.8% of its taxed or agreed party and party costs; and in respect of
the period after 11 November 2016, in terms of s 14(8)(e)(i) of the Act, all its taxed or
the period after 11 November 2016, in terms of s 14(8)(e)(i) of the Act, all its taxed or
agreed party and party costs . The municipality further argues that the costs orders
should have included the costs of two counsel , as well as the qualifying fees of Mrs
Theron and Messrs Engelbrecht, Dacomb, and Griffiths. An apportionment is required
under s 15(2)(c) if the difference between the offer and the award is greater than the
difference between the claim and the award.1
1 10(3) Lawsa 2 ed para 150.
6
[9] The parties have in writing agreed on a statement of issues and facts regarding
this appeal in terms of rule 8(8) and rule 8(9) of this Court’s rules. They agree d as
follows:
‘1. The appeal hinges on the following issues arising from the “ORDER/JUDGMENT ON
VALUE-ADDED TAX, VAT, INTEREST AND COSTS” made on 3 November 2023 by [the high
court], namely:
1.1 From paragraph (b) and (c) of the Order with regard to the interest payable, the issue
arises whether on a prop er interpretation of s 12 (3)(a) of the Expropriation Act 63 of 1977
(“Act”)
1.1.1 the interest is compounded at 11.5% the Government Gazette Notice 25778 from 7
August 2007 to date of payment, or
1.1.2. whether the interest payable in terms of the s aid section is simple statutory interest at
the rate determined from time to time by the Minister of Finance in terms of s 80(1)(a) of the
Public Finance Management Act 29 of 1999: and
1.1.3. whether the amount of R2 538 690 should be inserted in paragraph (c). (Common cause
between the parties.)
1.2 From the Order with regard to costs, the issue arises whether the Court a quo was correct
to order each party to pay its own costs; or
1.2.1. whether the Court was bound by s14(8) of the Act to award costs of suit to the defendant
(the present appellant) from 12 November 2016, including the costs of two counsel and the
qualifying fees of its expert witnesses; or
1.2.2 whether the Court should have apportioned the costs?’
Interest
[10] We were informed from the bar that the nature and rate of the interest were no
longer in issue between the parties and they agree that paragraph (c) of the high
court’s order should be amended as follows:
‘The defendant is ordered to pay interest on R 2 593 690.80 at the applicable rate from the
actual date of expropriation as agreed between the parties, namely 31 July 2004 until 7 August
2007 less the amount of capital R391 683.00 that was already paid as interest on 7 August
2007.’
2007.’
And that a sub-paragraph be inserted after the existing paragraph (c) that reads as
follows:
‘(c)(i) The interest playable as referred to in paragraphs (b) and (c) above is simple statutory
interest in terms of s 12(3)(a) of the Expropriation Act 63 or 1975 (‘the Act’) at the rate
7
determined from time to time by the Minister of Finance in terms of s 80(1)(a) of the Public
Finance Management Act 29 of 1999.’
[11] Section 12(3) provides that ‘[i]nterest at the standard interest rate d etermined
in terms of section 26(1) of the Exchequer Act, 1975 (Act 66 of 1975), shall, subject to
the provisions of subsection (4) , be payable from the date on which the State takes
possession of the property in question in terms of s 8(3) or (5) on any outstanding
portion of the amount of compensation payable in accordance with subsection (1) ...’
(Emphasis added.)
[12] In Community Development Board v Mahomed and Others NNO,2 this Court
interpreted the portion of s 12(3) of the Act, emphasised in the previous paragraph, as
follows:
‘The expression “the amount o f compensation payable” must have been intended by the
Legislature to refer to the amount as ultimately determined . . . of that amount [and] “any
outstanding portion” must mean any part of it not yet paid as at the date of taking possession
of the property and for as long as it remains unpaid thereafter. If the whole amount in question
is paid only after it has been determined, interest will be payable on it from the date of taking
possession until the date of payment.’3
[13] In Davehill (Pty) Ltd and Others v Community Development Board (Davehill),4
this Court hel d the following regarding the liability to pay compensation and interest
upon expropriation of property:
‘The liability to pay statutory interest arises from considerations of equity, and was designed
to compensate a person whose property has been expropriated for his loss of possession and
fruits of the property up to the time that compensation was paid. . . . In effect, statutory interest
runs from day to day on the outstanding portion of the amount of compensation payable
(whether it be the full amount or a reduced amount because of an interim payment in terms of
(whether it be the full amount or a reduced amount because of an interim payment in terms of
s 11(1)), and ceases the moment compensation is paid in full. At that date , the amount of
statutory interest due can be computed at the rate prescribed in s 12(3), ie , “at the standard
interest rate determined in terms of s 26(1) of the Exchequer and Audit Act 1975”…’5
2 Community Development Board v Mahomed and Others NNO 1987 (2) SA 899 (A).
3 Ibid at 909H-J.
4 Davehill (Pty) Ltd and Others v Community Development Board [1988] 1 All SA 388; 1988 (1) SA 290
(A).
5 Ibid at 297G-J.
8
[14] Although the section refers to ‘the Exchequer Act 66 of 1975’, that statute has
been repealed and replaced with the Public Finance Management Act 1 of 1999
(PFMA). Section 80 of the PFMA is the applicable provision. In Davehill, this Court
also stated when interest due becomes payable.6
[15] That leaves the question of costs. The matter has not been rendered moot as
contemplated in s 16(2)(a) of the Superior Courts Act 10 of 2013. The parties correctly
submitted that there are exceptional circumstances in this case, since the high court
failed to exercise a discretion at all in respect of the co sts. This ordinarily constitutes
exceptional circumstances for the purposes of s 16(2) of the Superior Courts Act.7 The
fact that the hearing in the high court took place over an extensive period in which
substantial costs were incurred , is another factor that justifies the hearing of this
appeal on the issue of the costs only.8
Costs
[16] The municipality argues that the high court was compelled by s 14(8) of the Act
to take into account its without prejudice tender made on 11 November 2016 in the
amount of R1.5 million. This, combined with the payment of R2 231 020 made to the
respondent on 3 August 2007, totals R3 731 020, which is more than the
compensation of R2 593 680 determined by the high court. The municipality submits
that because the high court was bound by s 14(8) , it should have been awarded its
taxed or agreed party and party costs after 11 November 2016, including the qualifying
fees of its experts.
[17] Counsel for the respondent argued, in essence, that the without prejudice offer
must be considered separately, and not in addition to the payment that the municipality
had already made in terms of s 11(1) of the Act. So construed, the amount determined
by the high court as compensation was much higher than the offer. According to this
6 Ibid at 298.
6 Ibid at 298.
7 Naylor and Another v Jansen [2006] ZASCA 94; [2006] SCA 92 (RSA); 2007 (1) SA 16 (SCA) para
10; Van Staden & Others N NO v Pro-Wiz Group (Pty) Ltd [2019] ZASCA 7; 2019 (4) SA 532 (SCA)
para 8.
8 Oudebaaskraal (E dms) B PK en Andere v Jansen van Vuuren en Andere 2001 (2) SA 806 (SCA)
812C-F.
9
argument, the municipality’s contention ‘does not accord with’ the wording of the offer
of R1.5 million, which was ‘in full and final settlement’.
[18] The Act prescribes the costs orders that must be made in respect of
proceedings where compensation is determined in the absence of an agreement. 9
Section 15(2) of the Act provides as follows:
‘. . .
(2) if the compensation awarded by the court in any proceedings contemplated in section
14(1) –
(a) is equal to or exceeds the amount last claimed by the owner one month prior to the date
for which the proceedings were for the first time placed on the ro ll, costs shall be awarded
against the Minister;
(b) is equal to or less than the amount last offered by the Minister one month prior to the date
contemplated in paragraph (a), costs shall be awarded against the owner in question;
(c) is less than the amount last so claimed by the owner in question, but exceeds the amount
last so offered by the Minister, so much of the costs of the owner shall be awarded against the
Minister as bears to such costs the same proportion as the difference between the
compensation so awarded and the amount so offered, b ears to the difference between the
amount of compensation so awarded and the amount so claimed.’
[19] Section 15(3) of the Act grants the court a limited discretion in relation to costs.
It provides:
‘(3) Notwithstanding the provisions of subsection (2), the court shall in its discretion decide as
to the costs –
(a) In a case not mentioned in subsection (2);
(b) if any party did not within a reasonable time comply with reasonable requests under section
10 (7);
(c) if any party abused the provisions of section 10(7); or
(d) if, in the opinion of the court, the conduct of any party during or prior to the proceedings,
justifies a deviation from subsection (2).’
[20] Since s 14 of the Act als o contains provisions about the determination of the
costs, s 15(3A) provides as follows:
costs, s 15(3A) provides as follows:
9 A Gildenhuys Onteieningsreg 2 ed (1976) at 392-394.
10
‘(3A) In the case of a conflict between the provisions of this section and the provisions of
section 14 the provisions of the last-mentioned section shall prevail.’
[21] Section 14(1) of the Act essentially provides that the amount of compensation
payable for the expropriation of property shall , in the absence of an agreement, be
determined by the high court with jurisdiction. Section 14(8) addresses written offers
made regarding the compensation , as discussed above, but more importantly
s 14(8)(e) deals with the consequences of not accepting an offer to settle the dispute.
Subsections (e), (f), and (g) provide:
‘(e) if such an offer to settle the dispute is not accepted and the court determines the
compensation at an amount –
(i) which is equal to or more than the amount of the offer by the owner, the court shall order
the Minister to pay the owner’s costs incurred after the date of the offer; and
(ii) which is equal to or less than the amount of the offer by the Minister, the court shall order
the owner to pay the Minister’s costs so incurred.
(f) The court shall in its discretion decide on costs incurred prior to the date of an offer.
(g) If a court has made an order as to costs without knowledge of an offer which had not been
accepted and non-acceptance thereof is brought to the notice of the court within five days from
the date of the judgment, costs shall be reconsidered in the light thereof.’
[22] In terms of s 5(1) of the Act, for the purposes of applying subsection (1), any
reference to ‘the Minister’ and ‘the State’ in the Act, is to be interpreted as a ‘reference
to the local authority concerned’. It is not in dispute that the municipality is a ‘local
authority’ as defined in the Act and that it had the power to expropriate the
respondent’s property in accordance with the provisions of the Act.
[23] In this instance , to settle the compensation issue, the municipality served a
settlement offer on the respondent on 11 November 2016 . The written notice ,
settlement offer on the respondent on 11 November 2016 . The written notice ,
embodying the offe r, is headed ‘Defendant’s without prejudice tender’ and reads as
follows:
‘TAKE NOTICE THAT the Defendant hereby tenders without prejudice payment of the sum of
R 1 500 000.00 ( ONE MILLION FIVE HUNDRED THOUSAND RAND ) in full and final
settlement of the Plaintiff’s claim against the defendant.
TAKE FURTHER NOTICE THAT the Defendan t does not tender any interest or any
contribution to the legal costs in addition to the aforesaid amount.
11
TAKE FURTHER NOTICE THAT the Plaintiff is hereby provided notice that it may accept the
tender within 10 (ten) days from the date of service of this Notice.’ (Without prejudice offer)
[24] When the municipality made the without prejudice offer, it had already paid the
respondent a total amount of R2 622 703 around 6 August 2007, in terms of s 11(1)
of the Act . The payment included R2 176 020 as compensation (R1 941 000 for the
reservoir area and R235 000 for the servitude area), and R55 000 as a solatium, plus
R391 683 as interest . Th is payment was made after the municipality sent a notice
under s 10(2) and s 11(1) of the Act, which included the offer to the respondent along
with a cheque for R2 622 703. The respondent did not accept the offer in final
settlement, but banked the cheque and proceeded to claim what it considered to be
the compensation due to it. In doing so, the respondent acted within the law, since the
municipality had already accepted its liability to compensate the respondent for the
expropriated property.10 The fact that it was part payment of compensation cannot be
ignored.
[25] The ultimate dispute between the parties is whether the municipality made the
without prejudice offer in respect of the balance of compensation owed to the
respondent, taking into account the part payment, or whether the offer represented the
total amount of compensation. It is clear on the facts and the law that the part payment
of compensation was made in terms of ss 10(2) and 11(1) of the Act. The notice of
expropriation contained no offer of compensation and the municipality paid
compensation in its letter of 10 November 2016, as it was obliged to do under s 11(1).
The without prejudice tender was made after the first payment of compensation to the
respondent. The municipality did not demand the return of the latter; neither did it
request that the first offer of compensation be replaced with the without prejudice offer.
request that the first offer of compensation be replaced with the without prejudice offer.
It is clear from the wording of the without prejudice offer that it was merely in respect
of the respondent’s claim against the municipality, ie, the balance that the respondent
maintained it was still owed taking into account the s 11(1) payment. It was not in
respect of the municipality’s total liability.
10 See ABSA Bank Ltd v Van De Vyver NO [2002] 3 All SA 425; 2002 (4) SA 397 (SCA) paras 13-14.
12
[26] Although the high court subsequently determined that the total amount of
compensation was R2 538 690, it undoubtedly understood that the a mount of
R2 176 020 which had been paid by the municipality in terms of s 10(2) and s 11(1) of
the Act had to be deducted from the amount of R2 538 690, leaving a balance owing
of R 362 670. (As an aside, that amount ought to have been less, because the amount
awarded as a solatium, namely, R55 000, should also have been deducted, because
in applying the formula in s 15 and 14(8) , any solatium payable in terms of the Act
must be included in the compensation in terms of s 12(2)). The solatium is part and
parcel of the compensation .11 However, the high court did not grant leave to appeal
on this aspect.
[27] In any event, a ssuming that the high court was correct in its conclusion that
R362 670 was owing, that amount is obviously less than the without prejudice offer of
the municipality (ie, of R1.5 million). Or looked at differently, the amount of R3 676 020
(made up of the municipality’s first payment of R2 176 020 – leaving aside the solatium
for the moment – plus the offer of R1.5 million) is obviously much more than the
amount determined by the high court as compensation (ie, R 2 538 690).
[28] Since the amount of compensation determined by the high court was less than
the amount the municipality offered as compensation for what it had expropriated –
and in circumstances where the respondent did not accept the offer of 11 November
2016 of R1.5 million - in terms of s 14 (8)(e)(ii) of the Act the high court was obliged to
order the respondent to pay the costs of the municipality incurred after that date.12 In
the absence of any acceptable justification, as provided in s 15(3), for deviating from
the costs formula, the high court was obliged to comply with the formula. In respect of
determining the costs until 11 November 2016, under s 14(8)(f), the high court could
determining the costs until 11 November 2016, under s 14(8)(f), the high court could
exercise a discretion. The high court did not consider s 15 or s 14(8), and determined
the liability for costs without reference to those sections. That was a misdirection that
entitles this Court to determine the question of costs afresh.
11 Dormehl v Gemeenskapsontwikkelingsraad 1979 (1) SA 900 (T) at 911B-912A. 10(3) Lawsa 2 ed
para 150. See also A Gildenhuys Onteieningsreg 2 ed (1976) at 186.
12 See s 14 (8)(e) and 15(2)(b) of the Expropriation Act 63 of 1975.
13
[29] This is not a matter where, as outlined in s 15(2)(c), or s 14(8)(e)(i) of the Act,
the compensation set by the high court was less than the amount claimed by
the respondent but more than the amount offered by the municipality , requiring the
high court to apportion the costs. It was not open to th e high court, nor is it open to
this Court, to apportion the costs incurred after the without prejudice offer . The
submissions by the respondent’s counsel to the contrary are incorrect.
[30] In terms of s 15(2)(b) read with s 14(8)(e)(ii) of the Act the respondent must pay
the costs of the municipality incurred from the date of the without prejudice offer, ie,
after 11 November 2016, and such costs are to include , the costs of two counsel ,
where so employed, and the qualification fees of those expert witnesses of the
municipality who testified from 11 November 2016. In respect of the costs up to and
including 11 November 2016, it is fair that each party bear its own costs, including the
costs of its expert witnesses who had testified by 11 November 2016. One cannot
establish from the record on what date any particular expert testified , but there is
nothing to indicate that the calling of any expert was otherwise not reasonably
necessary.
[31] In the result:
1 The appeal is upheld with costs, including the costs of two counsel where so
employed.
2 The cross-appeal is dismissed with costs, including the costs of two counsel
where so employed.
3 Paragraphs (c), (e), and (f) of the order of the high court of 3 November 2023
are set aside and are replaced with the following paragraphs:
‘(c)(i) The defendant is ordered to pay interest on the amount of R593 690.80
at the applicable rate from the agreed date of expropriation, being 31 July 2004,
until 7 August 2007, less the amount of R391 683.00 that the defendant already
paid as interest on 7 August 2007;
(c)(ii) The interest referred to in paragraphs (b) and (c)(i) is simple statutory
(c)(ii) The interest referred to in paragraphs (b) and (c)(i) is simple statutory
interest as envisaged in s 12(3)(a) of the Expropriation Act 63 of 1975 (the Act)
charged at the rate determined from time to time by the Minister of Finance in
terms of s 80(1)(a) of the Public Finance Management Act 29 of 1999.
(d) . . .
14
(e) The plaintiff is ordered to pay the defendant’s costs, including the costs
of two counsel where so employed, incurred after 11 November 2016, the
qualifying fees of Messrs Ballack, Rudolph, Nagy and D Griffi ths incurred after
11 November 2016, and the costs of the interlocutory application reserved on 17
September 2019;
(f) In respect of all the costs incurred until 11 November 2016, which shall include
the costs of the interlocutory applications reserved on 3 August 2015 and 11
October 2016, each party is to bear its own costs.’
________________
P COPPIN
JUDGE OF APPEAL
15
Appearances
For the appellant: IM Lindeque
Instructed by: Ncube Incorporated Attorneys, Sandton
Honey Attorneys, Bloemfontein
For the respondent: RF De Villiers with SM van Vuren
Instructed by: Zietsman-Horn Inc. Rustenburg
Symington De Kok Inc., Bloemfontein.