IN THE HIGH COURT OF SOUTH AFRICA
(WESTERN CAPE DIVISION, CAPE TOWN)
Case no: 2025-139019
In the matter between:
CONTOUR TECHNOLOGY (PTY) LTD Applicant
And
BERGRIVIER MUNICIPALITY
THE MUNICIPAL MANAGER:
BERGRIVIER MUNICIPALITY
THE EXECUTIVE MAYOR:
BERGRIVIER MUNICIPALITY
ONTEC (PTY) LTD
First Respondent
Second Respondent
Third Respondent
Fourth Respondent
Coram: JUSTICE J CLOETE
Heard: 10 September 2025
Delivered electronically: 15 September 2025
ORDER
1. The application for the relief sought in Part A of the applicant’s notice of motion
is dismissed;
2. The application for the relief sought in prayer 2 of the applicant’s notice of
motion is postponed for hearing simultaneously with Part B and the costs
incurred in respect thereof shall be costs in the cause;
3. The parties are directed to approach the Judge President for an expedited date
for the hearing of Part B (subject to her overriding discretion in this regard);
4. In respect of the applicant and the first to third respondents, each party shall
bear their own costs in relation to Part A; and
5. The applicant shall pay the costs of the fourth respondent in relation to Part A,
including the wasted costs of 2 September 2025, on scale C (party and party)
and including the costs of counsel.
JUDGMENT
CLOETE J:
[1] The applicant (‘Contour’) has approached this court for urgent final
declaratory relief, as well as interim interdictory relief (Part A) pending, essentially,
the review of certain decisions taken by the first and/or second and/or third
respondents (collectively, unless otherwise indicated, the ‘municipality’) in respect of
a tender awarded to the fourth respondent (‘Ontec’) to supply the municipality with
an integrated pre -paid electricity vending and management system for electricity
consumers within its municipal area of jurisdiction (Part B). For convenience I refer
to this as the ‘new tender’ or the ‘new tender award’. Both the municipality and Ontec
oppose.
[2] The application was launched on 15 August 2025 and enrolled for hearing of
the declaratory relief and Part A in the ‘fast lane’ of motion court on 2 September
2025. It did not proceed on that day because the papers were not complete and
their length warranted, in the opinion of the urgent duty judge concerned, a special
allocation before a judge outside of the fast lane. The Deputy Judge President
allocated the matter to me for hearing on 10 September 2025.
[3] The final relief sought is contained in prayer 2 of the notice of motion , for an
order declaring that an agreement concluded between Contour and the municipality
in respect of the same services (the ‘2021 agreement’) did not terminate on 31 July
2025 and remains extant. The Part A relief is contained in prayer 3 thereof and is for
the following orders: (a) prayer 3.1, that the municipality and Ontec are interdicted
from taking any steps to implement the new tender ; (b) prayer 3.2, that the
municipality is interdicted from concluding any service level agreement with Ontec
pursuant to the award of the new tender; (c) prayer 3.3, that in the event of them
having already concluded a service level agreement, they are interdicted from giving
effect to it; and (d) prayer 3.4, that the municipality i s directed to permit Contour to
continue rendering services in terms of the 2021 agreement.
[4] There has regrettably been a series of material administrative errors made by
the municipality leading up to the launching of this application. It first awarded the
new tender to Ontec on 7 January 2025 . Contour, the only other successful bidder,
timeously appealed against that award. However, before Contour could exhaust its
internal remedies - and it was disputed by the municipality at that stage that it was
entitled to do so in the manner adopted - the municipality gave notice to Contour on
30 January 2025 that it was cancelling the 2021 agreement as a result of the new
tender to Ontec.
[5] On 6 February 2025 the municipality did an about turn and rescinded th e
cancellation notice to Contour because of concerns it had in respect of one of the
Ontec tender supporting documents, and which had been brought to its attention by
Contour (I will refer to this again later but for present purposes it is the ‘Phoenix
letter’). On 10 February 2025 the municipality cancelled the award to Ontec as a
letter’). On 10 February 2025 the municipality cancelled the award to Ontec as a
result of those concerns with immediate effect , and simultaneously informed it that
Contour, as the next qualifying bidder, would be appointed instead (this much was
procedurally correct in terms of the earlier Bid Adju dication Committee
recommendation accepted by the Acting Municipal Manager ). Ontec objected to the
cancellation but was informed by the municipality on 14 February 2025, and again
before Ontec could exhaust its internal remedies, that its new tender award was
‘permanently cancelled’.
[6] On 17 February 2025 the municipality awarded the new tender to Contour ,
and requested that it consequently withdraw its earlier appeal (which, as mentioned,
it had already told Contour was not competent in its view , and which was in turn
disputed by Contour ). Contour proceeded to withdraw its appeal in good faith.
Ontec however nonetheless pursued its internal remedies against the cancellation of
the new tender to it as it was entitled to do. This resulted in a referral of the dispute
between Ontec and the municipality, by the municipality it self, to Brasika Consulting
(Pty) Ltd (‘Brasika‘) in the person of Adv Helen Venter (‘Venter ’). In the meantime,
and despite a number of requests by Contour for the municipality to sign its service
level agreement , a necessary pre -requisite for the new tender award to be
completed, the mun icipality declined, informing Contour that it would respond
‘pending the outcome of the aforesaid process and based on what is legally feasible’.
Presumably the municipality intended to say it would respond once the di spute
resolution process with Ontec was completed . That process dragged on from early
March 2025 until Venter eventually responded to Contour on 12 June 2025. During
this entire period Contour continued to perform in terms of the 2021 agreement
which remained in force and the municipality voiced no objection.
[7] The upshot of Venter’s response was that she had determined the difficulties
with the Phoenix letter had not been proven as intentional on Ontec’s part ‘beyond a
reasonable doubt’ . Venter had further determined that: (a) the new tender earlier
awarded to Ontec was ‘functus officio in nature’ and could not have been ‘unilaterally
cancelled by the Municipality without following due course and having such contract
declared invalid and s et aside by a cour t’; and (b) the municipality was not able to
‘lawfully conclude a valid and enforceable contract with Contour [i.e. the new tender
‘lawfully conclude a valid and enforceable contract with Contour [i.e. the new tender
award] and that such award is regarded as invalid ab initio.’
[8] In her report dated 20 May 2025, which Venter declined to provide to Contour
due to its confidentiality but which the municipality subsequently annexed to its
answering affidavit, Venter explicitly advised the municipality that it could ‘only undo
its own administrative actions via a court of law’ and as such its purported
cancellation of the new tender with Ontec was irregular. She also advised that ‘ as
the award decision was functus officio, i.e. rights have vested with Ontec, any
municipal administrative act does not detract from the legal consequences thereof
and those rights remain binding until varied or set aside by a court.’
[9] In light of that advice, one would have thought that the municipality, whose
Municipal Man ager is also an Advocate and thus presumably versed in the law,
would have realised that the same applied to the subsequent award of the new
tender to Contour in light of the Oudekraal principle1, and that such award , if the
municipality believed its decision was defective, was likewise subject to self -review.
As the majority of the Constitutional Court put it in MEC for Health, EC v Ki rland
Investments 2:
‘[64] Can a decision by a state official , communicated to the subject, and in
reliance on which it acts, be set aside by a court even when government has
not applied (or counter -applied) for the court to do so? … Even where the
decision is defective … government should generally not be exempt from the
forms and processes of review. It should be held to the pain and duty of
proper process. It must apply formally for a court to set aside the defective
decision, so that the court can properly consider its effects on those subject to
it.
[65] The reasons spring from deep within the Constitution’s scrutiny of
power. The Constitution regulates all public power . Perhaps the most
important power it controls is the power the state exercises over its subjects.
When government errs by issuing a defective decision, the subject affected by
it is entitled to proper notice , and to be afforded a proper hearing, on whethe r
the decision should be set aside . Government should not be allowed to take
shortcuts ... Once the subject has relied on a decision, government cannot,
barring specific statutory authority, simply ignore what it has done …’
[10] However on 17 June 2025 the municipality, in the person of the Municipal
Manager, informed Contour that the double award presented the municipality wit h
Manager, informed Contour that the double award presented the municipality wit h
‘an unfortunate situation where we were exposed to the conundrum of having
1 Oudekraal Estates (Pty) Ltd v City of Cape Town and Others 2004 (6) SA 222 (SCA)
2 2014 (3) SA 481 (CC)
awarded two contracts for the same tender … because there was already a lawful
contractual relationship between Ontec and the Municipality prior to the subsequent
“award” to Contour the principles of legality dictate …’ that the award to Contour was
‘unlawful’. The Municipal Manager proceeded to inform Contour that its ‘month -to-
month contractual arrangement’ in terms of the 2021 agreement would expire on 31
July 2025. In response, Contour pointed out that the 2021 agreement was valid for a
minimum period of 3 years, was still extant, and could only be terminated on 90 days
notice; and further given that the municipality had awarded it the new tender , this
could not simply be unilaterally revoked.
[11] On 24 June 2025, Contour submitted its appeal against the decision to revoke
the new tender award to it. It recorded that an appeal precluded the municipality from
implementing its unilateral ‘cancellation’ or concluding a service level agreement with
Ontec until finalisation of the appeal process. It sought an undertaking in these terms
to be furnished by 27 June 2025 , failing which it would approach court for urgent
relief. On 30 June 2025 the Municipal Manager responded. She advised that
because she had made the decision to revoke the new tender award to Contour, the
appeal authority would be the Executive Mayor , but that ‘the Municipal Finance
Management Act 3, by implication prohibits councillors from making decisions
regarding procurement contracts and tenders’. She stated that in the circumstances
the municipality required time to obtain external legal advice and would resp ond to
the request for an undertaking by 11 July 2025. The external advisor turned out to be
Venter.
[12] On 15 July 2025 (4 days after her self-imposed deadline) the Municipal
Manager reverted to Contour with the advice received. It was conceded that the
municipality had made ‘certain administrative errors’ but the matter was nonetheless
municipality had made ‘certain administrative errors’ but the matter was nonetheless
considered ‘as having been exhausted’ for two reasons. First, the internal appeal
remedy in terms of s 62 of the Systems Act4 was not applicable since the Municipal
Manager had not exercised a delegated power but an original one in revoking the
new tender to Contour. Second, the 90-day termination notice period - although
3 Local Government: Municipal Finance Management Act 56 of 2003
4 Local Government: Municipal Systems Act 32 of 2000
entrenched in the 2021 agreement - was not applicable because that agreement was
now on a month-to-month basis.
[13] As to the applicability or otherwise of s 62 of the Systems Act, this is not an
issue before me for either the final declaratory relief or the Part A relief, and counsel
for Contour confirmed this in argument. As to the alleged month-to-month contractual
arrangement in respect of the 2021 agreement, the following. On 25 February 2025
the municipality wrote to Contour, apologising for the delay in finalising the award of
the new tender to it , but confirming that the commence ment date of the new tender
would remain as 1 March 2025 with a termination date of 30 June 2027. Contour
was clearly under the bona fide impression, created by the municipality itself, that the
new tender was replacing the 2021 agreement, but could not yet be implemented per
the new tender because of Ontec’s objection process. Contour thus responded on 27
February 2025 that ‘considering the circumstances which have presented
themselves we shall continue to render services … on a month-to-month basis under
the [2021] agreement’. In other words, Contour had only offered to assist the
municipality by continuing to provide the essential services in the interim in terms of
the 2021 agreement on a mont h-to-month basis because otherwise it would be
performing these services in a vacuum. The municipality must have understood it in
the same way because as a fact Contour continued to perform those services.
[14] Reverting to the chronology of events, on 17 July 2025, Contour responded to
the Municipal Manager’s letter of 15 July 2025. It disputed that s 62 of the Systems
Act was not applicable; reaffirmed its previous position; and urged the municipality to
reconsider its stance and revert with an appropriate undertaking by 21 July 2025.
That undertaking was not forthcoming. In addition, Contour wrote to the Western
Cape Provincial Treasury on 25 July 2025, requesting that it exercise its
Cape Provincial Treasury on 25 July 2025, requesting that it exercise its
constitutional and statutory oversight by issuing gui dance to the municipality, but to
which it appears no response was received. Instead, on 1 August 2025 the
municipality informed Contour that it was to cease all services on that same day. On
5 August 2025 Contour advised the municipality that it would be approaching court
for relief. The application was launched eight working days later.
[15] Against this background I do not agree with the contentions of the municipality
and Ontec that Contour’s urgency is self–created. Given the particular factual matrix
of this matter, it would be placing form above substance to find that Contour knew of
the municipality’s final position by 15 July 2025 (on the muni cipality’s version) or
even as early as 12 June 2025 (on Ontec’s version). Had Contour rushed off to court
shortly after 12 June 2025 without even attempting to exhaust what it believes to be
its internal remedies, it risked being told by a court to first do so. Had Contour acted
in similar vein shortly after 15 July 2025, without first requesting the municipality to
reconsider its stance, and bearing in mind it was providing an essential service to it ,
it risked damaging that relationship. This was not a situation of equal bargaining
power and in addition, the manner in which the municipality had flip-flopped about,
not only with Contour but also Ontec, made it prudent , in my view, to first adopt a
conciliatory and cautio us approach. In addition, Contour needed to afford the
municipality and Ontec a reasonable time to oppose and file answering papers.
[16] Returning again to the chronology of events, on 11 August 2025 the Municipal
Manager wrote to Contour , demanding it refrain from continuing to provide services
‘without any legal contract supporting such ’. At that time the municipality was aware
that Contour disputed: (a) the revocation of the award of the new tender to it ; (b) the
termination notice period given in respect of the 2021 agreement ; and (c) that it was
not entitled to an internal appeal. Contour was also informed the municipality would
be publicly notifying its electricity consumers that only Ontec was authorised to
supply the services in question. This the municipality proceeded t o do. It thereafter
forged ahead and actively engaged with Ontec in the transfer process , continuing to
forged ahead and actively engaged with Ontec in the transfer process , continuing to
do so even while it knew this application was pending. On 1 September 2025, the
day before the matter was initially enrolled for hearing, the municipality refused to
renew Contour’s key access to the Eskom system , thereby preventing it from
performing.
[17] The Municipal Manager deposed to the municipality’s answering affidavit on 1
September 2025. In paragraph 94.4 she alleged that the service level agreement
with Ontec had not yet been signed since ‘feedback from Ontec on changes is still
outstanding’. This was demonstrated to be a blatant untruth, because it emerged in
a supplementary affidavit deposed to by the self-same Municipal Manager, handed
up at the hearing , that Ontec had already signed the service level agreement on 20
August 2025 without any changes. The service level agreement was signed by the
municipality, again without any changes, only on 8 September 2025 , thus two days
before the matter was argued.
[18] Counsel for Contour submitted that both the municipality and Ontec had acted
in bad faith by pushing ahead with finalisation of the new tender award in the face of
pending litigation. While the equities might lie in Contour’s favour, the difficulty which
Contour faced by the time the matter was heard was that, as a fact, the new tender
award process with Ontec was complete, both in the contractual and practical sense,
and Contour was thus constrained to seek, not a preservation of the status quo, but
a reversal thereof, which is not the purpose of interim interdictory relief. Moreover,
the law is not on Contour’s side in respect of the steps taken to finalise the new
tender award to Ontec in the face of pending litigation.
[19] As both counsel for the municipality and Ontec submitted, their clients were
entitled at law to have done so. This is clear from the Constitutional Court decision in
Tshwane City v Afriforum and Another 5 where the court stated:
‘[71] There is another issue of importance that requires attention . It is the
notion that the mere launch of an application for a restraining order or the
review proceedings had the legal effect of automatically restraining Council
from erecting street signs or removing old street names …
[74] …It needs to be stated categorically , that no aspect of our law requires of
any entity or person to desist from implementing an apparently lawful decision
simply because an application, that might even be dismissed, has been
launched to hopefully stall that implementation. Any decision [ ie. judgment in
this context] to that effect lacks a sound jurisprudential basis and is not part of
this context] to that effect lacks a sound jurisprudential basis and is not part of
our law. It is a restraining order itself, as opposed to the sheer hope of one
being granted, that can in law restrain. To suggest otherwise reduces the
actual grant of an interdict to a superfluity.
5 2016 (6) SA 279 (CC)
[75] For these reasons there was no obligation on Council to desist from
removing old street names upon becoming aware that an urgent application
for a restraining order had been filed . Only sheer choice or discretion, but
certainly not any obligation or l egal barrier, would lead to action being
desisted from in anticipation of a successful challenge or application for an
interdict.’
[20] As I see it , there are potentially four revie wable decisions taken by the
municipality, namely: (a) the initial award of the new tender to Ontec; (b) the award
of the new tender thereafter to Contour; (c) the revocation of the award of the new
tender to Contour; and (d) the award for the second time, or reinstatement, of the
new tender to Ontec . Some or all of these will come under scrutiny in Part B,
including no doubt the domino effect of the municip ality’s decisions. There was a
voluntary and frank acknowledgement by counsel for Ontec that a determination,
one way or the other, is required by way of Part B. Counsel for the municipality was
more hesitant on this score, but accepted that a self -review by the municipality in
respect of some of these decisions might be necessary.
[21] In any event, as was also stated by the majo rity of the Constitutional Court
Kirland:
‘[67] In the face of government’s attitude, Kirland succeeded in the high court
and the Supreme Court of Appeal. The main [ie the minority] judgment would
reverse this, on the basis that all the evidence about the controversial
approval is before us, and it shows the approval was defective. This outcome,
and the reasoning supporting it, would have untoward consequences for
those subject to government decision -making. The evidence is not all before
us. And it would be fundamentally unfair to Kirland to set aside that decision
now, without requ iring government to bring a proper application, in which it
explains the history of the decision, its shifting attitudes towards it and its
explains the history of the decision, its shifting attitudes towards it and its
delay in dealing with it. In response, Kirland is entitled to be heard on whether
it has been prejudiced and why it would be unfair to set the decision aside
now. This is a protection the Constitution itself affords Kirland. The main
judgment would abrogate that protection. The court should not do so.’
[22] The main complaint of Contour in relation to the initial award of the new
tender to Ontec pertains to the Phoenix letter. The tender specifications include that
the supplier offers must ‘comprise a complete and fully functional integrated
prepayment vendin g and management system including all the operating and
database security needed to operate such a system ’. Importantly, the supplier’s
system must fully integrate with the Municipality’s Phoenix ERP system; and the
failure to implement within the required timeline ‘will result in the cancellation of the
tender’. There is no dispute that at all material times Contour has been able to fulfil
these requirements and already had such a system in place.
[23] The new tender was initially awarded to Ontec subject to these requirements,
failing which it would be cancelled and awarded to the tenderer with the second
highest score, ie. Contour. When Contour’s appeal process commenced, the
municipality provided it with a letter, purportedly from Phoenix, in which it was stated
that Ontec’s system was not only compatible but was already successfully
integrated. This letter was one of Ontec’s tender supporting documents. It turned out
that neither of these representations were true at the time of the new tender award to
Ontec, although it has by now apparently met these requirements. It is the stance of
both the municipality and Ontec that this is good enough for the new tender to have
been validly awarded, and it is Contour’s stance that it is not. Ontec disavows any
fraudulent conduct on its part, whereas Contour maintains it acted fraudulently in
relation to the Phoenix letter. These are issues for determination in Part B. I am of
the view that were this not an application to temporarily restrain the exercise of a
the view that were this not an application to temporarily restrain the exercise of a
statutory power , Contour would have met the ordinary first requirement of a prima
facie right even if open to doubt. However given this is indeed such an application,
and having given this careful thought, I am unable to conclude that this is the
‘clearest of cases’ when regard is had to the OUTA6 test, or that the circumstances
which present themselves are ‘exceptional’ when regard is had to the Gordhan test.7
6 National Treasury v Opposition to Urban Tolling Alliance 2012 (6) SA 223 (CC) at para 47
7 Economic Freedom Fighters v Gor dhan and Others; Public Protector and Another v Gordhan and
Others 2020 (6) SA 325 (CC) at para 42
Contour itself does not claim this to be the case either. Moreover, Contour also
needs to satisfy the other requirem ents for interim interdictory relief, namely a well-
grounded apprehension of irreparable harm; the balance of convenience in its
favour; and the absence of any other satisfactory remedy.
[24] In this regard, the following. The municipality and Ontec have already fully
implemented the new tender award. They have already concluded a service level
agreement. The proverbial horse has now bolted and to grant the relief in prayers 3.1
to 3.3 of Part A will be to reverse the status quo. The only potential way to stymie
the continued implementation of the new tender to Ontec is to grant the final
declaratory relief which Contour seeks in prayer 2 of its notice of motion, namely that
the 2021 agreement remains extant and did not terminate on 31 July 2025 as the
municipality contends it did . Herein lies another fundamental difficulty for Contour.
On its own version, the municipality is entitled to terminate that agreement on 90
days notice . Accordingly, and even assuming for present purposes that the notice
previously given by the municipali ty was irregular, there is nothing to prevent the
municipality from giving 90 days notice tomorrow, and given its past conduct, there is
every reason to believe that is exactly what it will do. There was certainly no
undertaking forthcoming during argument that it would not. I cannot bar the
municipality, as Contour effectively seeks in prayer 3.4 of its Part A relief, from giving
90 days’ notice of termination, since that would be making a contract for the parties,
and this is legally impermissible. Linked to this is m y concern that a decision on the
final declaratory relief in prayer 2 is probably premature and is better dealt with in
Part B when the court will have all the evidence before it.
[25] Granting the prayer 2 relief at this stage may have the following further
[25] Granting the prayer 2 relief at this stage may have the following further
consequences. The municipality will have two service providers for the same
essential services for a further 90 days. It will generate confusion for those whom the
municipality is constitutionally bound to serve in an efficient manner , ie. the end
consumers. It will also result in considerable additional expense to the fiscus for that
period because the municipality will have to these two service providers. At the end
of that notice period there will have to be a full transfer process back to Ontec at
least until determination of Part B , again with the attendant cost, not only to the
municipality but also to Ontec. In these circumstances I am compelled to conclude
that the balance of convenience is not in Contour’s favour.
[26] Turning now to the requirements of a well -grounded apprehension of
irreparable harm and the absence of any other satisfactory remedy. The services at
issue are ongoing and will continue to be so , unlike, for example, the construction of
a road network or a hospital . If Contour succeeds in Part B the court is at libert y to
grant any order that is just and equitable under s 8 (1) of PAJA 8, including a
declaration of rights with regard to the 2021 agreement, the new tender, and such
consequential relief as that court might deem appropriate. Any interim harm to
Contour is thus not irreparable . Further, Contour retains the right to institute action
for contractual damages if it so elects, and there is no serious suggestion that, given
the nature of the services, those damages it alleges it has already sustained, and will
continue to sustain, are not capable of quantification. Counsel for Contour, relying
on Edrei Investments 9 submitted that the election whether to claim specific
performance or damages was exclusively Contour’s. That may be so, but in Edrei
Investments the court was persuaded that the applicant’s other operational
requirements should prevail over an alternative claim for damages in granting an
interim interdict. I do not understand the law to be that , as a general principle, the
mere election to claim specific performance instead of damages means it follows that
there is no alternative satisfactory remedy.
[27] For all these reasons the application before me must fail. As far as Ontec is
concerned, costs must follow the result although I make it clear that in awarding
Ontec its costs , I make no finding on the validity of its new tender award. Counsel
were all in agreement that scale C is appropriate . As far as the municipality is
were all in agreement that scale C is appropriate . As far as the municipality is
concerned, despite its success in fending off the relief sought by Contour at this
stage, I am of the firm view that it should not be entitled to its costs. Finally, it is in
the interests of all the parties that Part B be heard and determined on an expedited
basis and this is catered for in the order hereunder.
[28] The following order is made :
8 Promotion of Administrative Justice Act 3 of 2000
9 Edrei Investments v Dis-Chem Pharmacies 2012 (2) SA 553 (ECP)
1. The application for the relief sought in Part A of the applicant’s
notice of motion is dismissed;
2. The application for the relief sought in prayer 2 of the applicant’s
notice of motion is postponed for hearing simultaneously with
Part B and the costs incurred in respect thereof shall be costs in
the cause;
3. The parties are directed to approach the Judge President for an
expedited date for the hearing of Part B ( subject to her overriding
discretion in this regard);
4. In respect of the applicant and the first to third respondents, each
party shall bear their own costs in relation to Part A; and
5. The applicant shall pay the costs of the fourth respondent in
relation to Part A, including the wasted costs of 2 September 2025,
on scale C (party and party) and including the costs of counsel.
_____________________________
J I CLOETE
Judge of the High Court
Appearances
For applicant: Adv Nick De Jager
Adv Matt WIlliams
Instructed by: Dirk Kotze Attorneys
For 1st – 3rd respondents: Adv Michael Bishop
Adv Michael Tsele
Instructed by: Enderstein Malumbete Inc
For 4th respondent: Adv Adiel Nacerodien
Instructed by: Ward Brink Attorneys