South Durban Community Environmental Alliance and Another v Minister of Forestry, Fisheries and the Environment and Others (479/2023) [2025] ZASCA 134 (17 September 2025)

82 Reportability
Environmental Law

Brief Summary

Environmental Law — Environmental Authorisation — Public participation process — Appeal against Minister's decision to grant environmental authorisation for Eskom's gas power plant — Appellants contended inadequate assessment of climate change impacts and public participation — Supreme Court of Appeal found public participation process insufficient, failing to accommodate local language needs, and held that the Minister did not comply with the National Environmental Management Act — Appeal upheld, Minister's decision set aside, and environmental authorisation revoked.

Comprehensive Summary

Summary of Judgment


1. Introduction


The proceedings concerned an appeal to the Supreme Court of Appeal of South Africa (SCA) against the dismissal of a judicial review application directed at an environmental decision taken within the national environmental management framework. The dispute arose from the granting of an environmental authorisation to Eskom for the construction and operation of a large-scale, combined cycle gas power plant in Richards Bay.


The appellants were South Durban Community Environmental Alliance (SDCEA) and the Groundwork Trust. The respondents included the Minister of Forestry, Fisheries and the Environment, the departmental decision-maker who had upheld the authorisation on internal appeal, as well as other parties associated with the authorisation process (including Eskom and the relevant departmental functionaries).


Procedurally, the matter progressed through multiple stages. In December 2019, a Chief Director in the Department of Forestry, Fisheries and the Environment granted the environmental authorisation. SDCEA and the Groundwork Trust pursued an internal appeal to the Minister, which was dismissed. They then instituted review proceedings in the High Court, Pretoria, seeking to have both the Minister’s decision and the authorisation set aside; that review application was also dismissed. The present proceedings were an appeal to the SCA against that outcome, culminating in the SCA upholding the appeal and granting substitutionary relief.


The general subject-matter of the dispute was the lawfulness of the environmental authorisation process and outcome, including whether legally required considerations (notably relating to climate change impacts, need and desirability, alternatives, cumulative impacts, and public participation) had been properly addressed under the governing environmental management principles and statutory framework.


2. Material Facts


Eskom proposed to construct a mid-merit, gas- and diesel-fuelled “gas-to-power” station at the Richards Bay Industrial Development Zone, with an installed generation capacity of 3000 MW. The plant was intended to run primarily on gas, with diesel used as a back-up fuel. The gas supply was contemplated to be delivered from a gas terminal at the Richards Bay Port via a new gas pipeline that had not yet been built; it was envisaged that Transnet would construct the pipeline. The proposed gas sources included Mozambique, with a further possibility mentioned of sourcing gas from the Karoo Basin.


The project’s related infrastructure was to be located within the Umhlathuze Local Municipality in the KwaZulu-Natal Province. In anticipation of the project, Eskom appointed Savannah Environmental (Pty) Ltd to conduct the required scoping and environmental impact assessment processes. A first report was published on 21 August 2017, and the final environmental impact report was published in August 2019. On 23 December 2019, the Chief Director approved the environmental authorisation for the project.


The court treated as material the fact that the public participation process connected to the environmental impact report used invitations that were all written in English, notwithstanding that 79% of Umhlathuze residents spoke isiZulu. This feature was central to the SCA’s evaluation of whether the consultation and participation requirements were met.


The appellants’ challenges included contentions that the authorisation was granted without sufficient assessment of climate change impacts, without proper consideration of the project’s need and desirability, without adequate consideration of alternatives, and without proper consideration of cumulative impacts. They also alleged that the public participation process did not satisfy the required standards.


The Minister, the Chief Director and Eskom disputed the appellants’ contentions. In particular, they advanced that renewable energy was not considered as an alternative because the plant’s function was said to be the provision of emergency power for short periods as and when required, which renewables were asserted not to be suitable for. They further contended that the decision formed part of government’s broader integrated energy approach in which gas would function as a “bridge” as coal is phased out, and that judicial interference would trench upon the separation of powers.


3. Legal Issues


The central legal questions the SCA was required to determine were whether the Minister’s dismissal of the internal appeal (and, by consequence, the continued validity of the environmental authorisation) was lawful in light of the statutory and constitutional requirements governing environmental decision-making, including the obligations imposed by the National Environmental Management Act 107 of 1998 (NEMA) and the constitutional environmental right in section 24 of the Constitution.


More specifically, the issues included whether the decision-making process was legally defective due to (a) an inadequate public participation process, and (b) a failure to heed and apply the NEMA principles requiring consideration of environmental impacts, including cumulative effects and need and desirability. The dispute therefore concerned a combination of law (the proper interpretation and application of NEMA and constitutional requirements), application of law to fact (whether the process undertaken met the legal standard), and evaluative judgment in relation to whether the deficiencies were material and warranted setting aside the decisions.


A further issue arose regarding remedy: whether, after setting aside the Minister’s decision, the SCA should remit the matter for reconsideration or whether exceptional circumstances justified substitution (the court replacing the administrative decision with its own outcome).


4. Court’s Reasoning


The SCA’s reasoning placed significant emphasis on the role of public participation in environmental governance. It linked effective public participation directly to the constitutional protection in section 24—the right to an environment that is not harmful to health and well-being. The court’s approach treated participation not as a procedural formality but as a pivotal mechanism through which affected persons can meaningfully influence environmental decision-making on projects that may affect them.


The court held that for consultation to be effective, it must be undertaken in good faith and through culturally appropriate measures and procedures. Applying that standard to the facts, the SCA concluded that the public participation process was inadequate because invitations to participate were provided only in English despite the demographic reality that a substantial majority of residents in the relevant municipality spoke isiZulu. This linguistic mismatch was treated as a substantive deficiency undermining the accessibility and inclusiveness of the participatory process.


In addition to the participation finding, the SCA reasoned that the Minister and Eskom did not heed the principles prescribed under NEMA for the management of activities that may significantly damage the environment. The court emphasised that organs of state are bound by NEMA, and that sectoral environmental laws and policies must be interpreted consistently with NEMA’s framework. It described NEMA as establishing a comprehensive environmental management framework that guides the implementation of environmental laws and policies, and it held that, when considering environmental authorisations, the Minister must satisfy herself that the statutory requirements are met.


A distinct aspect of the court’s reasoning was its rejection of the contention that the Minister’s decision should be insulated from review on the basis that it involved executive policy. The SCA held that, when making evaluations prescribed under NEMA, the Minister is not engaged in a “multifaceted policy formulation process”. Instead, the Minister is required to apply the NEMA framework and principles to the authorisation decision, including being compelled to consider environmental impacts, cumulative effects, and need and desirability. The court stated that this approach is required not only of the Minister but of all competent authorities and organs of state acting under NEMA.


Having found reviewable defects, the SCA proceeded beyond mere setting aside. It held that exceptional circumstances existed justifying substitution, and it accordingly replaced the Minister’s dismissal of the internal appeal with an order that upheld the internal appeal and set aside the authorisation. The summary provided indicates that the court both reviewed and set aside the Minister’s decision and then substituted its own decision to finally dispose of the matter.


5. Outcome and Relief


The SCA upheld the appeal against the dismissal of the review.


It set aside the Minister’s decision dismissing the internal appeal, and it further substituted that decision with its own. The substituted outcome was that the internal appeal was upheld and the environmental authorisation was set aside.


The provided text does not specify any separate or additional relief beyond substitution and the setting aside of the authorisation, and it does not record any explicit costs order in the summary provided.


Cases Cited


No other cases are mentioned in the provided text.


Legislation Cited


The Constitution of the Republic of South Africa, 1996, section 24.


National Environmental Management Act 107 of 1998.


Rules of Court Cited


No rules of court are mentioned in the provided text.


Held


The Supreme Court of Appeal held that the public participation process relating to the environmental impact report was inadequate because participation invitations were issued only in English despite the linguistic profile of the affected local community, undermining effective, culturally appropriate consultation required for meaningful participation in environmental decision-making.


The court further held that the Minister and Eskom did not heed the principles under the National Environmental Management Act 107 of 1998. It held that organs of state are bound by NEMA and that the Minister, when considering an environmental authorisation, must apply the NEMA framework and be compelled to consider environmental impacts, cumulative effects, and the need and desirability of the proposed activity. The court rejected the characterisation of the Minister’s task as a broad policy formulation exercise for purposes of insulating the decision from review.


The court held that exceptional circumstances justified substitution, and it substituted the Minister’s decision with one that upheld the internal appeal and set aside the environmental authorisation.


LEGAL PRINCIPLES


Public participation is a pivotal component of environmental governance and is closely connected to the constitutional right in section 24 to an environment not harmful to health and well-being. For public participation to be effective, consultation must be conducted in good faith and through culturally appropriate measures and procedures.


The National Environmental Management Act 107 of 1998 establishes a comprehensive environmental management framework that binds organs of state and guides the interpretation and implementation of sectoral environmental laws and policies. Competent authorities, including the Minister, must ensure that NEMA’s requirements are satisfied when determining applications for environmental authorisations.


In environmental authorisation decisions under NEMA, the decision-maker is compelled to consider environmental impacts, including cumulative impacts, as well as the need and desirability of the activity. In performing this function, the Minister is not engaged in a multifaceted policy formulation process but is required to apply the statutory framework to the authorisation decision.


Where reviewable defects are established and exceptional circumstances exist, a court may substitute its decision for that of the administrative decision-maker, including by upholding an internal appeal and setting aside an environmental authorisation.

THE SUPREME COURT OF APPEAL OF SOUTH AFRICA
MEDIA SUMMARY OF JUDGMENT DELIVERED IN THE SUPREME COURT OF
APPEAL

From: The Registrar, Supreme Court of Appeal
Date: 17 September 2025
Status: Immediate
The following summary is for the benefit of the media in the reporting of this case and does not
form part of the judgments of the Supreme Court of Appeal
South Durban Community Environmental Alliance and Another v The Minister of Forestry, Fisheries
and the Environment and Others (479/2023) [2025] ZASCA 134 (17 September 2025)
Today, the Supreme Court of Appeal (SCA) upheld an appeal against the dismissal of the review of the
Minister’s decision.
During December 2019 the Chief Director in the Integrated Environmental Authorisations section of the
Department of Forestry, Fisheries and the Environment granted to Eskom an environmental
authorisation for the construction and operation of a combined cycle gas power plant in Richards Bay.
An appeal by South Durban Community Environmental Alliance (SDCEA), and the Groundwork Trust
to the Minister of the same Department against the granting of the environmental authorisation was
dismissed by the Minister. An application to the High Court, Pretoria, by SDCEA and the Groundwork
Trust for a review and setting aside of the Minister’s decision and environmental authorisation also
failed.
The environmental authorisation relates to a power plant that Eskom proposes to build at the Richards
Bay Industrial Development Zone. The proposed plant will be a mid-merit, gas and diesel fuelled ‘gas-
to power’ power station, with an installed power generation cap acity of 3000MW . The intention is to
primarily power the plant with gas and to use diesel as back-up. Gas will be delivered to the plant from
a gas terminal at the Richards Bay Port via a gas pipeline which is yet to be built. It is envisaged that
Transnet will construct the port to power plant pipeline. The gas will be sourced from Mozambique, but
it could also be sources from the Karoo Basin.

it could also be sources from the Karoo Basin.
The infrastructure related to the power plant will be located within Umhlathuze Local Municipality in the
KwaZulu-Natal Province. In anticipation of the project Eskom engaged the services of Savannah
Environmental (Pty) Ltd to conduct a scoping and environmental impact assessment in order to identify
any significant environmental and social issues and concerns in relation to the project . Savannah
published the first report on 21 August 2017 and the final environmental impact report was published in
August 2019.
On 23 December 2019 the Chief Director approved the environmental authorisation for the project.
In the appeal before the SCA, SDCEA and Ground Works argued that the environmental authorisation
was granted without sufficient assessment of the power plant’s climate change impacts, the need or
desirability to have it, and without a considering alternatives to it and its cumulative impacts. They also
argued that the public participation process undertaken on the environmental impact report fell short of
the requirements . The appellants argued that these factors should have been central to the

2

consideration of Eskom’s environmental authorisation application and that failure to sufficiently consider
any one or more of them must result in a review and setting aside of the environmental authorisation.
The Minister, the Chief Director and Eskom argued that renewable energy sources were not considered
as alternative energy sources because what was needed was the provision of emergency power, for
short periods of time, as and when required. Renewable power sources are not suitable for this function,
Eskom argued. In addition, the Minister was exercising her executive power and interference by courts
would constitute breach of the separation of powers principle. The argument was that the power plant
is part of the implementation of the government’s integrated energy resource strategy in terms of which,
as coal is phased out as the country’s main energy so urce natural gas will act as a ‘bridge before
renewable alternatives are fully implemented’. They warned that a hasty transition to renewables might
be unsustainable.
The SCA did not agree. It held that public participation is pivotal to the fulfilment of the right to an
environment that is not harmful to health and well -being that is protected in section 24 of the
Constitution. Through this process, parties that are affected or likely to be affe cted by the project to
which an environmental impact assessment relates are provided with an opportunity to make input with
regard to the proposed project . To be effective, consultation must be conducted in good faith, through
culturally appropriate measures and pr ocedures. The Court found that the public participation process
undertaken in relation to the environmental impact report was inadequate in that the invitations to the
members of the public were all written in English despite the fact that 79% of the residents of
Umhlathuze spoke isiZulu.
In addition , The Minister and Eskom did not heed the principles prescribed under National

In addition , The Minister and Eskom did not heed the principles prescribed under National
Environmental Management Act 107 0f 1998 (NEMA) for management of all activities which may result
in significant damage to the environment. The SCA emphasised that organs of state are bound by
NEMA and must interpret all sectoral en vironmental management laws and policies against the
approach set in that legislation. It highlighted that NEMA establishes a compreh ensive environmental
management framework which guides the implementation of all environmental laws and policies. When
considering environmental authorisations t he Minister, must satisfy herself that the requirements
stipulated in NEMA are met. When making evaluations prescribed under NEMA the Minister is not
engaged in a multifaceted policy formulation process. The Court held further that NEMA requires the
same approach from all competent authorities or organs of state. Under NEMA the Minister was
compelled to consider the environmental impacts of the power plant, its cumulative effects and its need
and desirability.
Having reviewed and set the Minister’s decision aside, the SCA found that exceptional circumstances
existed for it to substitute the Minister’s decision with its own. It upheld the appeal by the SDCEA and
Groundwork Trust, set aside the Minister’s decision and substituted it with a decision upholding the
internal appeal and setting aside the environmental authorisation.
~~~~ends~~~~