Maano Water (Pty) Ltd v Eskom Holdings SOC Limited (383/24) [2025] ZASCA 87 (12 June 2025)

55 Reportability
Public Procurement

Brief Summary

Tender — Cancellation of tender — Reviewability of executive action — Appellant sought to compel Eskom to resume negotiations after cancellation of tender for supply of sulphuric acid — High Court dismissed application, finding no clear right to continue negotiations — Appeal dismissed; decision to cancel tender deemed an executive action, rationally connected to changed market conditions and within Eskom's authority under tender conditions — No enforceable right to negotiate to deadlock established.

Comprehensive Summary

Case Note


Maano Water (Pty) Ltd v Eskom Holdings SOC Limited (383/24) [2025] ZASCA 87 (12 June 2025)


Reportability


This case is reportable due to its implications for the reviewability of tender cancellations by state-owned enterprises and the distinction between executive and administrative actions. The judgment clarifies the legal framework surrounding procurement processes and the obligations of parties involved in tender negotiations, particularly in the context of changing market conditions.


Cases Cited



  • Tshwane City and Others v Nambiti Technologies (Pty) Ltd [2015] ZASCA 167; 2016 (2) SA 494 (SCA)

  • Premier, Free State and Others v Firechem Free State (Pty) Ltd 2000 (4) SA 413 (SCA)

  • Southernport Developments (Pty) Ltd v Transnet Ltd 2005 (2) SA 202 (SCA)

  • Letaba Sawmills (Edms) Bpk v Majovi (Edms) Bpk 1993 (1) SA 768 (A)

  • Makate v Vodacom (Pty) Ltd [2016] ZACC 13; 2016 (4) SA 121 (CC)


Legislation Cited



  • Promotion of Administrative Justice Act 2 of 2000 (PAJA)

  • Preferential Procurement Policy Framework Act 5 of 2000

  • Preferential Procurement Regulations, 2017


Rules of Court Cited



  • Uniform Rules of Court, Rule 53


HEADNOTE


Summary


The Supreme Court of Appeal dismissed the appeal by Maano Water (Pty) Ltd against Eskom Holdings SOC Limited regarding the cancellation of a tender for the supply of sulphuric acid. The court found that the cancellation was an executive action, not subject to review under the Promotion of Administrative Justice Act, and that Eskom acted within its rights to terminate negotiations due to a failure to reach an agreement.


Key Issues


The key legal issues addressed in this case include the nature of the action taken by Eskom in cancelling the tender, the rights of Maano Water to compel negotiations, and the implications of market changes on procurement processes.


Held


The court held that Eskom's decision to cancel the tender was lawful and rational, and that Maano Water did not have a clear right to compel further negotiations. The appeal was dismissed, and Maano was ordered to pay the costs.


THE FACTS


Eskom issued Tender CORP 5542 in August 2021 for a five-year contract to supply sulphuric acid. After negotiations with the highest bidder failed due to rising costs, Eskom engaged with Maano Water, the second-ranked bidder. Maano proposed a dollar-based pricing model, which Eskom rejected. Following unsuccessful negotiations, Eskom cancelled the tender in August 2022, prompting Maano to seek a court order to compel negotiations or review the cancellation.


THE ISSUES


The court had to decide whether Eskom's cancellation of the tender constituted administrative action subject to review under PAJA or executive action, and whether Maano had a right to continue negotiations until a deadlock was reached.


ANALYSIS


The court analyzed the nature of Eskom's action, concluding that it was an executive decision not subject to PAJA. It emphasized that no contract had been formed, and thus Maano's expectations did not equate to enforceable rights. The court also found that Eskom's reasons for cancellation were rational and based on significant changes in market conditions, which justified the termination of negotiations.


REMEDY


The court dismissed Maano's appeal and ordered it to pay the costs of the appeal, affirming Eskom's right to cancel the tender process.


LEGAL PRINCIPLES


The judgment established that decisions by state-owned enterprises regarding tender cancellations are typically executive actions, not administrative, and that tenderers do not possess rights until a contract is formed. The court also highlighted the importance of rationality in decision-making processes and the need for clear mechanisms in agreements to negotiate.






THE SUPREME COURT OF APPEAL OF SOUTH AFRICA
JUDGMENT

Not Reportable
Case no: 383/24

In the matter between:

MAANO WATER (PTY) LTD APPELLANT

and

ESKOM HOLDINGS SOC LIMITED RESPONDENT

Neutral citation: Maano Water (Pty) Ltd v Eskom Holdings SOC Limited (383/24)
[2025] ZASCA 87 (12 June 2025)
Coram: MATOJANE and KEIGHTLEY JJA , and PHATSHOANE AJA
Heard: 20 May 2025
Delivered: This judgment was handed down electronically by circulation to
the parties ’ representatives by email, published on the Supreme Court of Appeal
website, released to SAFLII. The date and time for h and-down is deemed to be 11h00
on 12 June 2025.
Summary: Reviewability of tender cancellation – State owne d enterprises –
executive action distinguished from administrative action – rationality as ground for
review – absence of authority as ground for review - pactum de contrahendo – averred
‘right to negotiate to deadlock ’.

2

ORDER


On appeal from: Gauteng Division of the High Court, Johannesburg (Malindi J , sitting
as a court of first instance ):
1 The appeal is dismissed.
2 The appellant is ordered to pay the costs of the appeal .


JUDGMENT


Matojane JA (Keightley JA and Phatsoane AJA concurring):

Introduction
[1] This appeal lies against the judgment of the Gauteng Division of the High Court,
Johannesburg (high court ) delivered on 12 December 2022, which dismissed an
urgent application of the appellant (Maano) . In that application Maano sought a
mandamus to compel the respondent (Eskom) to resume contract -price -adjustment
(CPA) negotiations or, in the alternative , to review and set aside Eskom ’s decision ,
communicated to Maano in a letter dated 4 August 2022 and published on the National
Treasury E -portal and Eskom tender bulletin platforms , to cancel Tender CORP 5542.
Leave to appeal was granted by the high court on 27 March 2024.

[2] The factual matrix is largely common cause. In August 2021 Eskom issued
Tender CORP 5542 to procure a five-year contract to supply sulphuric acid to its power
stations . Eskom entered into negotiations with the highest ranked bidder (Afro -Zonke)
for the conclusion of a contra ct. A key component of the contract was an agreed model
for calculating the CPA. When Eskom commenced negotiatio ns with Afro -Zonke , the
global price of sulphur had risen by approximately 250%. The primary cause was the
conflict in Ukraine, which commenced in early 2022. The spike in the cost of crude
sulphur and shipping had not been foreseen when the tender was issued.

3
[3] Negotiations between Eskom and Afro -Zonke failed because Afro -Zonke tried
to pass its increased costs , arising from the global spike, on to Eskom. Subsequently,
Eskom began talks with Maano, the second preferred bidder. On 21 April 2022, Maa no
proposed a hybrid model for calculating the CPA that was entirely dollar -based.
However, on 4 May 2022, Eskom rejected this, stating that a dollar -based model was
unacceptable. Its further reasoning was that it created unmanageable exposure due
to excha nge rate fluctuations and changes in the dollar price of crude sulphur, which
they coul d not hedge against. A meeting held between Maano and Eskom on 10 May
2022, concluded with both parties maintaining these stances . Subsequently, Eskom
decided to cancel the entire tender process. Maano now seeks to challenge this
cancellation and compel a return to the negotiating table.

[4] A factual dispute exists centre d on the meeting between the parties of 10 May
2022. Maano contends that Eskom un dertook to consider the hybrid model and either
accept it or make a counter -proposal. Eskom disputes this, asserting that it had
consistently communicated its rejection of dollar -based CPA models due to the
unacceptable transfer of exchange rate and commod ity price risk to Eskom .. Eskom
contends that negotiations had reached an impasse by 10 May 2022.

[5] After 10 May 2022, Eskom did not revert to Maano. Following some prodding
from Maano, Eskom published a notice in August 2022, cancelling the entire tender
process. Eskom's stated reason s appear in the Procurement Tender Committee (PTC)
extract of minutes of 10 June 2022 . The PTC received a report (the feedback report)
from the mandated team negotiating with Maano . The feedback report includ ed a
request for approval from the PTC to ‘terminate the negotiations held with Maano
Water (Pty) Ltd, cancel the tender and re -issue the tender ’. The report state d that the
initial mandate for the negotiation was based on a value of about R289 million for the
2023 to 2027 financial years. However, the price based on Maano ’s CPA model would
be significantly higher , at about R529 million . This was substantially above Eskom's
desired ‘aspiration base ’ of about R246 million .

[6] Ultimately, the report detailed the failure of negotiations with Maano and cited
reasons for the request to approve the cancellation of the tender altogether .
Significantly, the PTC accepted the negotiating team ’s explanation that if they were to
4
commence negotiations with the third -ranked bidder , the probability was high that the
same challenges would be experienced as with Maano, in that the third-ranked bidder
would also pass on the ir increas e to Eskom. As a result, the PTC approved both
recommendations, namely to terminate the negotiations with Maano, and to cancel the
current tender and issue a new one.

[7] Maano relies on it having a right, under the terms of the tender documents, to
hold Eskom to negotiate until deadlock. Maano assert s further that the sole reason for
the cancellation of the tender was the alleged failure of its negotiations with Eskom. It
disputes that deadlock had been reached as, it says, had Eskom engaged further,
Maano would likely have reverted to its original rand-based CPA model.

[8] Maano launched its urgent application on 25 August 2022 , pursuing its primary
remedy of a mandamus , in final form, to force Eskom back to the negotiating table. It
based its assertion o f a clear right on the argument that Eskom was legally obliged ,
and hence Manno had a corresponding right, to continue negotiations as no deadlock
had been reached . Consequently, Eskom had breached Maano ’s right by unilaterally
terminat ing the tender process after negotiations had comme nced , and while t he
tender validity period – being until 28 September 2022 - had not yet expire d.

The core issue : reviewability of the tender cancellation
[9] The high court proceedings focused entirely on the mandamus relief sought by
Maano. It dismissed the application on the basis that Ma ano had failed to establish a
clear right to hold Eskom to continue negotiations. The high court found that Eskom
was entitled, under clause 1.6.1 of the tender contract, to terminate negotiations
where, after good faith engagement , a deadlock was reached. The high court did not
address Maano ’s alternative relief, namely the review and setting aside of the tender .
However, w hen the appeal was argued before this Court, it became clear that, contrary
to the approach adopted in the high court, the fundamental issue was that of review.
In other words, the antecedent question for Maano to succeed in getting Eskom back
to the negotiating table , was whether it could establish that the decision to cancel the
tender was unlawful and reviewable. This is because, w ithout a successful challenge
to this cancellation, any relief seeking to compel further negotiations would be moot
for the simple reason that the tender would no longer exist. Put differently, unless set
5
aside, the cancellation of the tender effectively terminated any claim by Maano to a
right to continue to negotiate .

[10] Unfortunat ely, Maano ’s focus on interdict ory relief, in the form of a mandamus ,
as its primary form of relief had the effect that its case for a review of the tender
cancellation was not fully ventilated in its founding papers. A related complicating
factor is that Maano eschewed any reliance on rule 53 of the Uniform Rules of Court.
Consequently, neither the high court nor this Court had access to the record of the
decision to cancel the tender process .

[11] Insofar as the groun ds of review were addressed in the foundin g affidavit,
Maano contended, first, that the tender cancellation was not an independent
administrative act because it was ‘designed as a reason for not continuing with the
negotiations ’. In the alternative, and if the cancellation was considered to be an
independent administrative act, Maano argued that it was subject to review and setting
aside under ‘virtually all of the provisions of s 6(2)’ of the Promotion of Administrative
Justice Act 2 of 2000 (PAJA). It cited, among other grounds, that Eskom had no power
to cancel a procurement process where a tender has been awarded and the details of
the contract are being negotiated. It als o identified, as additional grounds, bias,
procedural unfairness, and irratio nality.

[12] A preliminary question is whether the decision to cancel the tender constitutes
administrative action, subject to review under PAJA, or an executive action, reviewable
under the principle of legality. As I have indicated, Maano ’s stance was that it was the
former.

[13] This Court has consistently held that decisions by organs of state and state
owned enterprises not to procure goods or services, particularly prior to the formation
of a binding contract, typically fall with in the realm of executive action. This Court in
Tshwane City and Others v Nambiti Technologies (Pty) Ltd ( Nambiti )1 stated that such
decisions do not directly affect rights and are therefore not administrative action. This

1 Tshwane City and Others v Nambiti Technologies (Pty) Ltd [2015] ZASCA 167; 2016 (2) SA 494 (SCA);
[2016] 1 All SA 332 (SCA) .
6
Court explained that when a tender is cancelled, no one loses any rights, as no
contract has been formed.2 Tenderers only have expectations, not rights, at that stage.
A decision not to procure services by tender does not have a direct, external legal
effect on the tenderers' rights.3

[14] Maano sought to distinguish this case from Nambiti on the basis that it had been
awarded the tender and that , pursuant to that award, the parties were at, what Maano
asserted to be, an advanced stage of negotiations. However, Maano ’s underlying
assumption is incorrect. It had not been awarded the tender : after negotiations with
the preferred bidder, A fro-Zonke failed, Maano became no more than the first reserve
bidder . Had the tender not been cancelled, the failure of negotiations with Maano
would have resulted in the third bidder taking Maano ’s place as the second reserve .
The material overlap between this case and Nambiti is that in neither case had a
contract been concluded before the tender was cancelled. Maano is thus in the
substantially same position as the reviewing party in Nambit i: the cancellation of the
tender may have affected its expectations, but not any rights.

[15] The wording of the tender document in the present case, which explicitly grants
Eskom the right to ‘cancel the ten der process at any time prior to the formation of a
contract ,’4 reinforces this position. Even in the absence of such explicit wording, the
fundamental reasons animating public procurement – being essentially an executive
function – would likely lead to the same conclusion. It follows that the review falls
outside of the ambit of PAJA. Is it nonetheless possible to discern from Maano ’s
application a valid basis for review under the broader principle of legality?

[16] As indicated earlier, Maano ’s case fo r review was not fully developed in its
founding affidavit. A generous reading of the grounds of review identified by Maano

2 Nambiti para 24 states the general principle as follows: ‘Whether the cancellation of a tender before
adjudication is administrative action in terms of these requirements depends on whether it involves a
decision of an administrative nature and whether it has direct, external legal effect .’ See also Grey's
Marine Hout Bay (Pty) Ltd and Others v Minister of Public Works and Others 2005 (6) SA 313 (SCA)
para 21.
3 Nambiti para 32.
4 Clause 1.6.1 of Eskom ’s Standard conditions of Tender reads: ‘Eskom may accept or reject any
variation, deviation or alternative tender and reserves the right to accept the whole or any part of the
tender. Eskom may cancel the tender process at any time prior to the formation of a contract and will
give written reaso ns for the cancellation upon written request to do so … .’
7
present s limited possibilities : absence of authority , and irrationality , with bias
or mala fides as sub -categories of the latter .

[17] As to rationality , the question is whether the respondent's decision to cancel the
tender was rationally connected to the purpose for which it was taken. Maano
contended that the sole reason for the cancellation of the tender was to provide Eskom
with a reason to avoid contin uing negotiations . According to Maano, Eskom gave no
indication that Maano had not complied with any tender requirements: it simply aborted
the tender process without explanation, demonstrating bias or mala fides on Eskom ’s
part.

[18] There are obvious difficulties with Maano ’s submissions in this regard. Most
fundamentally, its averment as to the sole reason for the cancellation is patently wrong.
Eskom provided clear and consistent reasons for this, as articulated in its answering
affidavit and corroborated by contemporaneous documents, including the feedback
report and the Procurement Tender Committee resolutions. These reasons
fundamentally stem from changed global circumstances pertaining to sul phuric acid
prices. The respondent explained that the proposed CPA model, particularly Maano ’s
shift to a dollar -based index, exposed Eskom to an unlimited and unsustainable
financial risk. This was not only a sticking point in the negotiations with Maano b ut, as
recorded in the feedback report, and accepted by the PTC, would be equally
problematic in negotiations with the second reserve bidder. The core problem was that
the tende r had been overtaken by broader global events , giving rise to broader policy
and economic issue s for Eskom, which render ed the original tender no longer fit for
purpose.

[19] The evidence demonstrates that Eskom engaged in six meetings with Maano ,
consistently articulating its position regarding the unacceptability of the proposed
pricing model. The decision to cancel was not a capricious one but a considered
response to external market volatility and the need to protect public funds. It would, in
fact, have been irrational for a public body, entrusted with finite resources, to pro ceed
with a contract that exposed it to such significant and unmanageable financial risk.
Realistically, these external factors meant that none of the tenders received were
acceptable. This was the reason cited by Eskom in its letter advising Maano of the
8
cancellation. It was a permissible reason for tender cancellation s under regulation
13(1)( c) of the 2017 Regulations promulgated under the Preferential Procurement
Policy Framework Act 5 of 2000.5 Any suggestion of irrationality, bias or mala fides on
the part of Eskom in these circumstances is without any foundation.

[20] The remaining question is whether there is any merit in Maano ’s argument that
Eskom had lacked authority to cancel the tender. The fulcrum around which the
argument turns is Maano ’s assertion that it had a ‘right to negotiate to deadlock ’, which
it contend s Eskom breached. From a review perspective , the gist of Maano ’s case is
that Eskom had no authority to cancel the tender before deadlock was reached in its
negotiations with Maano . This alleged right , and hence correlative obligation on
Eskom, is purportedly sourced from clause 1.1 in Eskom ’s Standard Conditions of
Tender (the S CTs).

[21] Maano made no reference to the SCTs in its founding papers . They were, in
fact, attached to Eskom ’s answering affidavit , and Maano ’s reliance on clause 1.1 was
only articulated in its submissions to this Court. The clause simply reads that ‘[t]he
Employer [Eskom] , the Eskom Representative and each eligible tenderer submitting a
tender shall act timeously, ethically and in a manner which is fair, equitable,
transparent, competitive and cost effective. ’ From this provision, Maano sought to infer
a restriction on Eskom ’s power to cancel the tender until a deadlock in negotiations
was reached.

[22] The argument has two components: legal and factual. The legal component
raises the question of whether Eskom ’s undertaking in the SCTs to act in a manner
which is ‘fair, equitable [and] transparent ’ requires it to remain at the negotiating table,
and bars it from exercising its power to cancel the tender, until deadlock. If so, t he
factual component of the argument is triggered, with the question being whether there
was a deadlock in negotiations with Maano.


5 Preferential Procurement Regulations, 2017 published under GN R32 in GG 40553 of 20 January
2017 , repealed by GN 2721 in GG 47452 of 4 November 2022 .
9
[23] As to the legal component, what Maano effectively argues is that clause 1.1 of
the SCTs constitutes a pactum de contrahendo , or an ‘agreement to agree ’. The
general principle, as established in cases like Premier, Free State and others v
Firechem Free State (Pty) Ltd 6 and Southernport Developments (Pty) Ltd v Transnet
Ltd,7 is that an agreement to agree is generally too vague to be enforced unless the
parties have agreed on the essential terms of the contemplated contract, and there is
an objective mechanism or external yar dstick by which any outstanding terms can be
determined . Letaba Sawmills (Edms) Bpk v Majovi (Edms) Bpk (Letaba Sawmills )8
concerned a lease agreement where the rental amount was to be agreed upon by the
parties but , if they failed to agree, the amount w ould be determined by an arbitrator.
The term was held not to be vague and was enforceable because the arbitration clause
provided a clear deadlock -breaking mechanism.

[24] The judgment in Makate v Vodacom (Pty) Ltd ,9 while not directly addressing
‘negotiate to deadlock ’ clauses, underscored the role of good faith in contracts. It
highlighted that less formal agreements can be legally binding if both parties
clearly intended to be bound and if there is a way to determine crucial, undefined terms
– like ‘reasonable remuneration ’ in that specific instance. The Constitutional Court, in
line with the Letaba Sawmills principle, reaffirmed that for an ‘agreement to agree ’ to
be enforceable, there must be a deadlock -breaking mechanism in place. The court
held:
‘Agreements to negotiate in good faith are taken as a species of the pacta de contrahendo
(agreements to agree). Generally they are regarded as a category of contracts whose purpose is
to create other contracts in future. But sometimes contracting parties, as was the position here,
may be confronted by a situation where they are not able to agree on some of the terms of the

6 Free State & others v Firechem Free State (Pty) Ltd 2000 (4) SA 413 (SCA) at 431G –J Schultz JA
explained that ‘[a]n agreement that the parties will negotiate to conclude another agreement is not
enforceable, because of the absolute discretion vested in the parties to agree or disagree: Scheepers
v Vermeulen 1948 (4) SA 884 (O) at 892, Putco Ltd v TV & Radio Guarantee Co (Pty) Ltd and other
Related Cases 1985 (4) SA 809 (A) at 828I. Such a discretion was vested in the parties as they were
to sign 'a contract' the precise terms of which were not fixed in the letter of acceptance, which, unlike
the action committee's recommendation, did not refer to annexure B. As the Tender Board neither
awarded a contract for the whole of the Free State nor exactly followed that committee's
recommendations as to demar cation, the elusive annexure B, whatever it did contain, could not have
served as the contract to be signed. There was, accordingly, room for a breakdown in negotiations
before a contract was concluded. ’
7 Southernport Developments (Pty) Ltd v Transnet Ltd 2005 (2) SA 202 (SCA) .
8 Letaba Sawmills (Edms) Bpk v Majovi (Edms) Bpk 1993 (1) SA 768 (A ).
9 Makate v Vodacom (Pty) Ltd [2016] ZACC 13; 2016 (4) SA 121 (CC) .
10
contract. To resolve the problem, they may arrange to negotiate and agree on the outstanding
terms on a future date. The arrangement may form part of the concluded agreement. A dispute
may arise, if one of the contracting parties, as was the case here, refu ses to negotiate the
outstanding term so that the parties ’ agreement may be executed. When this occurs, the question
that arises sharply is whether the term to negotiate is enforceable at the instance of the innocent
party .’10

[25] The contractual clause r elied upon by Maano is too vague to give rise to an
enforceable right to negotiate to deadlock , and hence a limitation on Eskom ’s power
to cancel the tender . At best, it records an undertaking by both parties as to how they
will be guided in their conduct. It is not directed specifically at contract negotiations .
Even if it could be interpreted more favourably for Maano , clause 1.1 provides no
mechanism for resolving an impasse, which is a crucial element for such an agreement
to be enforceable. Finally on this score, Maano ’s preferred interpretation is untenable
given the express power provided to Eskom in clause 1.6. 1 of the SCTs to ‘cancel the
tender process at any time prior to the formation of a contract. ’

[26] Although it is not strictly necessary to do so, for completeness ’s sake, it is worth
recording that Maano ’s argument fails also at the factual level. It claims that on 10 May
Eskom committed to review its hybrid model and respond with either an acceptance
or a counter -offer. Eskom, however, refutes this, stating it consistently rejected the
dollar -based hybrid CPA model due to the inherent financial risks,
specifically exposure to rand-dollar exchange rate fluctuations and volatile global
sulphur prices. Eskom maintains that by 10 May 2022, a clear deadlock had been
reached. This was because Maano continued to push for the dollar -based model
despite Eskom's persistent objections . Eskom further argues that its delay in informing
Maano of the cancellation until 4 August 2022, was not in bad faith, as it intended to
provide reasons if Maano requested them.

[27] Applying the Plascon -Evans rule for factual disputes in motion proceedings,
where final relief is sought, the Court must accept the facts averred by Eskom that are
not denied by Maano , and Maano ’s facts admitted by Eskom , unless Eskom ’s version

10 Ibid para 95.
11
is so far -fetched or clearly untenabl e that the Court is justified in rejecting it merely on
the papers.11

[28] Eskom's consistent position throughout the negotiations, articulated in
meetings and correspondence, was that dollar -based CPA models were unacceptable
due to the transfer of risk against which it could not hedge . Maano's repeated
insistence on dollar -based models, even after Eskom articulated its objections, lends
credence to Eskom's assertion that negotiations had reached a dead end on this
specific point. While Maano's repl ying affidavit belatedly suggested it ‘would probably
have reverted ’ to its original rand-based model, this was not conveyed to Eskom during
the negotiations, nor does it override Eskom's consistent rejection of the proposed
dollar -based models. Furthermor e, Maano's prior statements indicating the
unsustainability of its original rand-based model under changed market conditions
(due to a 250% increase in raw material costs) weaken the credibility of its late
assertion that it would have reverted.

[29] Therefore, on the facts, Eskom ’s version prevails. By 10 May 2022, Eskom had
genuinely concluded that further negotiation on Maano's proposed CPA models would
be fruitless due to Maano's persistence in a model Eskom found unacceptable and
unmanageable. The not ion that Eskom made an abrupt about -turn and undertook to
consider the hybrid model again, or to make an entirely new counter -proposal, is not
supported by the consistent narrative of the negotiations .

Conclusion and order
[30] Maano has not made out a case for the review and setting aside of the
cancellation of the tender. The decision to cancel was an executive action, rationally
taken in response to significant and unavoidable changes in market conditions . In
addition, there is no merit in Maano ’s contention that Eskom lacked authority to cancel
the tender. Clause 1.1 of the SCTs did not limit the express power of Eskom to cancel
the tender process . The high court was correct to dismiss Maano ’s application.



11 Plascon -Evans Paints Ltd v Van Riebeeck Paints (Pty) Ltd 1984 (3) SA 623 (A) .
12
Order
[31] In the premises, the following order is made:
1. The appeal is dismissed .
2. The appellant is ordered to pay the costs of the appeal.

_________________
K E MATOJANE
JUDGE OF APPEAL







13
Appearances

For the appellant: P F Louw SC and J W Steyn
Instructed by: Van Der Vyver Inc, Mid rand
EG Cooper Majiedt Inc , Bloemfontein .

For the respondent: A Ste in SC and M Augustine
Instructed by: Cheadle Thompson & Haysom Inc , Johannesburg
McIntyre Van Der Post Inc, Bloemfontein .