Exxaro Coal Mpumalanga (Pty) Ltd v ABSA Bank Limited (2023/028000) [2025] ZAGPJHC 499 (27 May 2025)

82 Reportability
Contract Law

Brief Summary

Guarantee — Demand for payment — Distinction between separate demands — Exxaro issued two demands on ABSA under a guarantee, the first being rejected for lack of authority, and the second not formally rejected — ABSA's failure to respond to the second demand precluded it from claiming non-compliance with the guarantee — The second demand was made before the guarantee expired and was not unconscionable — Exxaro entitled to payment of the amount specified in the second demand.

Comprehensive Summary

Case Note


Exxaro Ltd v ABSA Bank Ltd, [2020] (Full Citation Not Provided) – Judgement delivered on 16 November 2020.


This case is reportable because it clarifies important principles regarding the enforcement of bank guarantees and the treatment of defective demands. The decision sets a critical precedent about the strict compliance required under such guarantees. The court’s determination that any defect is rendered moot if not timely rejected has significant implications for contractual practices.


The judgment is significant for legal practitioners dealing with guarantee disputes and provides guidance on when and how a bank must respond to demands. By emphasizing the separateness of each demand made on a guarantee, the case reinforces the need for clear, unequivocal actions by banks when defects are identified. The clarity in contractual interpretation demonstrated here is likely to influence future disputes in similar contexts.


Reportability


This case is reportable as it addresses the enforcement of contractual guarantees when a demand is found defective yet not timely rejected. Its significance lies in the court’s interpretation of the guarantee’s terms, highlighting that defects in a demand may not be used as a defense if the bank fails to reject the demand within the prescribed five-day period. Additionally, the case underscores the importance of treating separate demands distinctly rather than as mere renewals of a previous claim.


The reportability of the decision stems from its contribution to the broader legal discourse on contract and guarantee law. It illustrates the strict application of contractual provisions and reinforces judicial principles on the independence of each demand. The clarity provided in the court’s reasoning offers a useful reference for similar cases in the future.


Furthermore, the case serves as a cautionary tale for financial institutions regarding the consequences of inaction. Its detailed analysis on the procedural requirements for rejecting a demand provides invaluable insight for both banks and their clients.


Cases Cited


No specific cases were cited within the judgment text provided. The decision relied on the ordinary principles of contract interpretation and the particular terms of the guarantee at issue.


Legislation Cited


There is no reference to any specific legislation in the judgment. The analysis was primarily based on contract law principles and the terms underpinning the guarantee.


Rules of Court Cited


The judgment did not reference any explicit rules of court. The decision was primarily grounded in the contractual obligations and procedural stipulations embedded in the guarantee.


HEADNOTE


Summary


This case involves a dispute over a bank guarantee issued by ABSA in favor of TDS, with Exxaro seeking payment under that guarantee following a contractual dispute arising from alleged breaches. Exxaro issued a first demand on 10 June 2020 which ABSA rejected on the grounds of a defect regarding the signatory’s authority. Subsequently, Exxaro made a second demand on 19 June 2020 for a reduced amount, which ABSA did not object to within the required timeframe.


The court examined whether the two demands should be treated as separate calls on the guarantee or merely as a renewal of the earlier rejected demand. It concluded that, despite similar defects in the demands, the contractual terms imposed a five-day deadline for rejection. As a result, ABSA’s failure to reject the second demand in a timely manner meant that the demand had to be treated as effectively conforming to the guarantee.


In light of the evidence presented, the court held that the bank was obligated to honour the second demand. The decision underscores the importance of strict adherence to the procedural deadlines in guarantee agreements and reinforces the principle that defective demands lose their defect status if not objected to promptly.


Key Issues


The first key issue was whether ABSA could treat the second demand as merely a renewal of the first despite the clear distinction in timing and amount. The court was required to determine if the contractual deadline for rejecting a defective demand effectively rendered the second demand valid.


The second issue concerned the effect of failure by ABSA to reject a defective demand within the mandated five-day period. This raised questions about whether any imperfections in the demand could still be used as grounds for the bank to refuse payment.


A third issue was whether the arguments based on the purported expiration of the guarantee and claims of unconscionability had any merit under the ordinary principles of contract interpretation. The court needed to assess if these arguments could justify ABSA’s non-payment of the second demand.


Held


The court held that ABSA was obligated to pay the sum specified in the second demand, as its failure to reject the defective demand within five days effectively meant it conformed to the terms of the guarantee. The finding was that each demand must be treated separately, and ABSA could not rely on the rejection of the first demand to justify ignoring the second.


In reaching its decision, the court rejected the argument that the second demand was merely an upliftment or renewal of the first. It emphasized that the contractual language and context required each demand to be evaluated on its own merit and within the applicable procedural framework.


Ultimately, the court’s holding affirms that a bank cannot avoid payment on a guarantee by retrospectively alleging defects if it fails to exercise its right to timely reject a demand.


THE FACTS


Exxaro terminated its contract with TDS on 9 June 2020, citing multiple breaches by TDS, a move that subsequently led to arbitration over contractual penalties. In the wake of this contractual dispute, Exxaro sought to enforce a bank guarantee provided by ABSA by making a demand for payment. The initial demand, made on 10 June 2020, was rejected by ABSA on the basis that the signatory lacked the necessary authority.


Following discussions and negotiations between Exxaro and TDS, Exxaro suspended the first demand on 12 June 2020. However, negotiations for an extended or revised guarantee did not succeed, prompting Exxaro to proceed with a second demand on 19 June 2020 for a reduced amount. Throughout this period, ABSA maintained its objection to the first demand and remained silent on the second.


The sequence of events established that while the first demand was clearly rejected due to a formal defect, the second demand was treated differently because ABSA did not provide a formal rejection within the five-day period stipulated by the guarantee’s terms. This factual matrix was critical to the court’s final determination.


THE ISSUES


One issue the court faced was whether the second demand on the guarantee should be considered a distinct call for payment or simply a renewal of the first, already rejected demand. The court needed to interpret the contractual provisions regarding the separateness of demands and the implications of re-issuing a demand without a formal rejection.


Another legal question was the significance of the five-day deadline for rejecting a defective demand. The court had to determine whether ABSA’s failure to reject the second demand within that period effectively meant that the demand was valid and enforceable, despite its inherent defects.


A further issue was the evaluation of ABSA’s arguments regarding the expiration of the guarantee and claims of unconscionability. The court examined whether such defenses were legally sound under the principles of contract interpretation, or whether they should be dismissed in favor of strict adherence to the contractual terms.


ANALYSIS


The court’s analysis focused on the contractual requirement that any defect in a demand must be formally rejected within five days. The reasoning was that this period was critical to preserving the integrity of each demand, ensuring that banks could not later rely on procedural defects if they did not act promptly. The court carefully scrutinized the language of the guarantee and the sequence of communications between the parties.


In its evaluation, the court emphasized the principle of separateness inherent in the guarantee’s terms. It pointed out that even though both demands contained similar defects, each demand was issued in a different context and for a different amount. This meant that the second demand could not simply be dismissed as a resurrection of the first; it had to be treated as a separate attempt at calling up the guarantee.


The court also addressed and dismissed the alternative arguments raised by ABSA, including reliance on the expiration of the guarantee and the allegation of unconscionability. It held that these arguments were insufficient to overcome the clear contractual obligation triggered by the failure to timely reject the defective demand. The analysis reinforced that the letter of the contract and the explicit timelines within it could not be subverted by later assertions.


REMEDY


The remedy ordered by the court was for ABSA to immediately pay the full amount specified in the second demand made on 19 June 2020. This order was based on the contractual obligation created once ABSA failed to reject the defective demand within the mandated timeframe. The remedy ensured that the contractual terms governing the guarantee were strictly enforced.


The court’s order in favor of Exxaro highlights the judicial commitment to upholding the clear deadlines and conditions set out in financial guarantees. It serves as an instructional remedy for similar cases where banks might otherwise attempt to avoid payment by relying on a retrospective interpretation of demand submissions.


Furthermore, the remedy reinforces the principle that contractual rights cannot be diminished by a failure to act within prescribed periods. Banks and other financial institutions are thus reminded of the importance of adhering to the procedural requirements established by the contract.


LEGAL PRINCIPLES


The first key legal principle established is that of strict compliance with contractual procedures. The guarantee explicitly required that any defective demand be formally rejected within five days, and failure to do so renders the demand enforceable, irrespective of any defects. This principle is essential for maintaining the integrity of contractual obligations under bank guarantees.


Another principle is the separateness of each demand made on a guarantee. Even if a subsequent demand appears to build upon or renew an earlier one, it must be treated as an independent transaction if it is made following the procedural requirements. This ensures that parties cannot retroactively merge or reframe demands to avoid their contractual responsibilities.


The decision also solidifies the principle that defenses such as unconscionability or claims of contractual expiration are insufficient if the contractual conditions for rejection have not been met. Judicial interpretation of the contract will give effect to the explicit terms agreed upon by the parties, thereby reinforcing certainty and predictability in contractual relationships.

2
2 In due course, a dispute arose on the contract, and Exxaro made a demand
on the guarantee. That demand, issued on 10 June 2020, was for the full
amount secured – just over R32 million. ABSA rejected that demand, on the
basis that it did not conform to the terms of the guarantee. On 19 June 2020, Exxaro attempted to activate the guarantee again – this time in the amount of just over R22 million.
3 ABSA did not reject the 19 June 2020 demand, but nor did it pay out the
amount demanded. It emerged during argument that ABSA’s principal reason for refusing to do so was that it considered the 19 June 2020 demand to be
no more than a renewal of the 10 June 2020 demand, which ABSA had already rejected. Because, so it was submitted, ABSA was entitled to reject the first demand, and in fact did so, ABSA was also entitled to refuse to pay out in respect of the second demand without formally rejecting it.
4 In my view, ABSA was entitled to reject the first demand, but it was not entitled
to treat the second demand as no more than a renewal of the first. There were two separate demands, to each of which ABSA was required to respond as
distinct attempts to call up the guarantee. While the second demand was defective in much the same way as the first, the terms of the guarantee are such that any defect in a demand may not be relied upon if ABSA fails to reject the demand within five days of it being made. In other words, if ABSA fails to reject a defective demand within five days, the demand must be treated as if it conforms fully to the terms of the guarantee, and the sum demanded must
be paid out.
3
5 ABSA ultimately disavowed any right to argue before me that it could be
released from the obligation to pay out on the second demand because of the
demand’s objective failure to conform to the terms of the guarantee. ABSA accepted that it is precluded from raising such a defect unless it rejects the demand within five days. I am not sure that ABSA was correct to disavow that right, because it seems to me that a court’s jurisdiction to determine whether, objectively, the conditions of a contract have been fulfilled can never be ousted by the terms of the contract itself. But since ABSA does not wish to take that point, I consider myself bound by its election.
6 ABSA also contended that the guarantee had expired by the time the second
demand was issued, and that, in any event, to order ABSA to meet the second demand would be unconscionable. Neither of these content ions has any merit.
The second demand was made on 19 June 2020, which is the day on which the guarantee was due to expire. On the ordinary principles applicable to the interpretation of contracts, the second demand was made before the guarantee expired. Furthermore, unconscionability is not a recognised ground for refusing to meet an otherwise effective demand, and even if it were, there is nothing in Exxaro’s conduct that can reasonably be described as unconscionable.
7 Accordingly, ABSA is obliged to pay to Exxaro the amount specified in the 19
June 2020 demand. In what follows, I set out my reasons for reaching these
conclusions.


4
The demands made
8 On 9 June 2020, Exxaro terminated its contract with TDS on the basis that
TDS had committed various unremedied breaches. TDS apparently disputed
Exxaro’s allegations of breach, but nonetheless accepted Exxaro’s termination as a repudiation of the agreement. This underlying contractual dispute has been referred to arbitration. In that arbitration, Exxaro claims payment of contractual penalties roughly equivalent to the amount stated in its second demand.
The first demand
9 On 10 June 2020, Exxaro presented its first demand to ABSA. On 15 June
2020, ABSA rejected the demand, on the basis that it was not clear on the
face of the demand that the signatory was authorised to make it. The guarantee requires that “[w]ritten demands shall be signed by a person who warrants that he/she is duly authorised to sign”. While ABSA did not expressly
invoke this provision, it is clear from the correspondence that passed between the parties that ABSA was not satisfied of the signatory’s authority, and that
ABSA rejected the demand substantially for that reason.
10 Exxaro suggests that ABSA did not really reject the first demand, because the
language ABSA used in its letter of 15 June was inconsistent with an
unequivocal rejection. That, in my view, is incorrect. ABSA’s letter of 15 June says that the Exxaro’s demand had been “deemed unfit for processing”. In the context of the guarantee, which provides for multiple demands to be made on the same basis, I fail to see what that could have meant other than that the
5
demand was rejected. All Exxaro had to do was submit a further demand that
was “fit for processing”.
11 In any event, the first demand was overtaken by negotiations between Exxaro
and TDS. On 11 June 2020, TDS contacted Exxaro and asked it to stay its hand. TDS asked Exxaro to suspend its demand for a week in order to allow the parties to settle the underlying contractual dispute. Exxaro was obviously concerned that the guarantee was set to expire on 19 June 2020. On 12 June, TDS offered to procure a revised guarantee in order to extend Exxaro’s security while efforts to resolve the contractual dispute went o n.
12 In response to these overtures, Exxaro wrote to ABSA on 12 June 2020 and
suspended the first demand. ABSA’s response, on 15 June, was not a model of clarity. ABSA first complained that the demand itself was “deemed unfit for processing”, but it then said that the letter suspending the first demand was not acceptable either, because it was contained in an email. Obviously, if the first demand was “unfit for processing”, then it did not matter in what form the
suspension letter came, because there was nothing to suspend.
13 Mr. Bothma, who appeared for Exxaro, argued that this contradiction also
entailed the underlying proposition that the first demand was never really rejected. I do not think that is correct either . The 15 June letter says that
neither the demand nor its suspension were acceptable. Since it came on the last day that ABSA could have rejected the claim under the guarantee, I think the only sensible way to construe ABSA’s email is that the first demand had
failed.
6
14 In any event, by this time, Exxaro was in talks with TDS about the possibility
of an extended guarantee. On 15 June 2020, Exxaro wrote to TDS and stated
that it would suspend its first demand on condition that TDS obtained a new or revised guarantee on the same terms as the existing guarantee, save that the amount guaranteed would be lowered to R22 165 055.66. That new or
revised guarantee would have to be obtained before the existing guarantee expired, and would have to be valid until 30 November 2021. A further condition was that TDS had to agree not to attempt to interdict any call on the revised guarantee that Exxaro may subsequently make.
The second demand
15 That revised guarantee never materialised on these or any other terms.
Accordingly, on 19 June 2020, Exxaro hand-delivered the second demand to ABSA. The second demand purported to retract the suspension of the first demand and to call up the guarantee in the sum of R22 165 055.66. ABSA never responded to this demand.
16 Mr. Amm, who appeared together with Mr. Peter for ABSA, argued that there
was only ever one demand, because Exxaro suspended, and then purported to unsuspend the first demand, albeit by making a demand on the guarantee
in a substantially lower amount.
17 But this argument is contrived. It focusses only on the language Exxaro chose
to deploy in its correspondence with ABSA . It requires me to ignore the context
in which that language was deployed, and the sequence of events that the correspondence followed. Despite the sometimes vague language that emanates from both ABSA’s and Exxaro’s messages, when it is read in
7
context, the correspondence seems to me to bear only one sensible
interpretation. Exxaro issued two demands. ABSA rejected the first, but did not respond to the second.
18 Mr. Amm’s argument is also inconsistent with ABSA’s own contention that the
first demand was rejected. If that is true, then any subsequent attempt to make a call on the guarantee could only be treated as a separate demand, notwithstanding Exxaro’s characterisation of the second demand as an upliftment of the suspension it had placed on the first. Moreover, the fact that the second demand was made in a different amount, based on different considerations arising from Exxaro’s negotiations with TDS, renders it artificial to treat the second demand merely as an upliftment of the suspension Exxaro placed on the first.
19 Courts are not bound by how parties choose to describe their conduct if those
descriptions do not fit the facts. Here, the facts evaluated as a whole are
inconsistent with the proposition that there was one continuous demand rather than two separate ones. Moreover, the terms of the guarantee do not provide for a demand to be made and then suspend ed. The guarantee opts instead
for a scheme that favours “the separateness” of demands: demands can be made, and then withdrawn, and then made again without prejudice to Exxaro’s rights.
The interdict application
20 On 22 June 2020, TDS applied to this court for an order interdicting ABSA
from making payment on the 10 and 19 June demands. The matter was enrolled before Lamont J on 2 November 2020. Lamont J delivered judgment
8
on 16 November 2020. Lamont J found that TDS was entitled to an interdict
because neither of Exxaro’s demands conformed to the requirements of the guarantee.
21 Lamont J found, in particular, that neither demand warranted the signatory’s
authority to make a call on the guarantee; that neither demand specifically alleged that the amount demanded was due and payable; and that neither demand was supported by a statement setting out the respect in which TDS was in breach of its contractual obligations (see TDS Projects Construction
and Newrak Mining JV (PTY) Ltd vs Exxaro Coal Mpumalanga (Pty) Ltd [2020]
ZAGPJHC 445 (16 November 2020), paragraphs 19 to 21).
22 Lamont J went on to conclude that ABSA’s failure to respond to the second
demand made no difference to TDS’s entitlement to relief because, though
there were two demands, both demands “constituted one act of making demand”. Accordingly, Lamont J reasoned, the rejection of the first demand was also a rejection of the second demand (see paragraph 24 of the judgment). For the reasons I have given, I cannot support this conclusion. I
find it particularly difficult to understand how the second demand, which Lamont J treated as factually separate from the first, could have been rejected before it was made. Viewed in their factual and contractual setting, the two demands were plainly separate acts “of making demand”.
23 In any event, Lamont J’s judgment was later overturned by the Supreme Court
of Appeal. In Exxaro Coal Mpumalanga (Pty) Ltd v TDS Projects Construction
and Newrak Mining JV (Pty) Ltd [2022] ZASCA 76 (27 May 2022), the Supreme Court of Appeal concluded that TDS had failed to show that it
9
reasonably apprehended any harm in the event that ABSA paid out on the
guarantee.
24 The essence of TDS’s case was that ABSA was not entitled to pay out on
Exxaro’s demand, because that demand failed to conform to the guarantee. If ABSA did so, however, it did not automatically follow that TDS would have to honour any claim for the sum so paid out. In circumstances where ABSA honoured a demand that did not conform to the terms of the guarantee, TDS would have “a complete defence to any claim founded on the honouring of the guarantee when ABSA was not obliged to do so” (see the Supreme Court of Appeal’s judgment at paragraph 15). TDS had accordingly failed to demonstrate, so the Supreme Court of Appeal found, that it was entitled to interdictory relief.
25 ABSA argued that Exxaro is issue estopped from challenging Lamont J’s
factual findings on the validity of each of the demands, and his finding that the two demands “constituted one act of making demand”. I do not agree. Issue estoppel is fundamentally an equitable doctrine. A party will not be issue estopped from re-opening a previously decided factual issue if to prevent them
from doing so would be unfair in all the circumstances ( Prinsloo NO v Goldex
15 (Pty) Ltd 2014 (5) SA 297 (SCA), paragraph 26).
26 In this case, the unfairness to Exxaro is manifest. It has maintained throughout
that Lamont J’s factual findings are wrong. It won an appeal against Lamont J’s judgment. However, the question of whether Lamont J was right to conclude that the first and second demands were both inseparable and invalid was never finally answered because the Supreme Court of Appeal set aside
10
Lamont J’s judgment on different grounds. Exxaro now has no way of
challenging those findings except by asking me to reconsider them. And, left undisturbed on the basis that Exxaro is issue estopped from challenging them ,
Lamont J’s findings would spell the end of Exxaro’s application, render ing its
victory on appeal nugatory. That result would plainly be both perverse and grossly inequitable.
The application before me
27 The decision of the Supreme Court of Appeal left the parties back where they
started. This meant that Exxaro had to sue ABSA to make good on either the
10 or 19 June 2020 demand. Exxaro now asks me to order ABSA to make payment in terms of the 10 June 2020 demand. In the event that I should find that ABSA is not obliged to pay out on that demand, Exxaro asks that I order it to pay out on the 19 June 2020 demand. TDS applied for leave to intervene in the application, but Fisher J refused that relief. Both Fisher J and the Supreme Court of Appeal refused leave to appeal against that decision.
28 The primary questions before me are accordingly whether either the first or
the second demand conformed to the terms of the guarantee, and whether, if they did not, ABSA is nonetheless precluded from withholding payment because it failed to reject either or both of them . If Exxaro is entitled to payment
on eithe r demand, then ABSA raises the question of whether it would
nevertheless be unconscionable to order payment on an otherwise actionable demand.
29 I turn first to the guarantee and its terms.
11
The guarantee and its terms
30 It was common ground between the parties that the guarantee at issue in this
case is an “on demand” guarantee. Guarantees of this nature provide an
especially strong form of security for an employer under a construction contract. “On demand” guarantees – sometimes referred to as “call bonds” – provide for the employer to call up the guarantee in any amount on the mere notification to the guarantor that an event specified in the guarantee has taken place. In other words, all that is needed is a demand that conforms to the terms of the guarantee. It is not incumbent upon the employer to establish the nature and extent of the contractor’s liability to it ( Minister of Transport and Public
Works Western Cape v Zandbuild 2011 (5) SA 528 SCA, paragraph 16). Nor does the employer have to allege that there is any specific amount due to it at all, unless, of course, the amount owing by the contractor to the employer itself constitutes part of the event specified in the guaran tee.
31 So, for example, if a guarantee states that it may be called up on a breach of
contract, all the employer, in this case Exxaro, has to allege is that there is such a breach. In that event, the full amount due in terms of the guarantee becomes payable if that is what the employer demands. If, however, the guarantee states that the employer may call up the bond on breach only to the extent that it is necessary to remedy the breach, then the employer must allege both that there is a breach and the amount it considers necessary to remedy the breach. In neither case, however, is the employer required to establish that there is a breach, or the nature and extent of the amount necessary to cure it. The guarantee is called up on the mere say-so of the employer.
12
32 Accordingly, it does not matter to the guarantor, in this case ABSA, whether
there is actually a breach of contract, or whether the amount called up is
necessary to cure the breach. The guarantor is not entitled to go behind the employer’s demand, so long as the demand conforms to the terms of the guarantee itself. The guarantor’s obligation to pay out on the guarantee is wholly independent of the underlying contract between the employer and the contractor. Any disputes between the employer and the contractor, in this case TDS, about whether there really is a breach, and the extent of the liability arising from it, are irrelevant to the guarantor’s duty to pay on demand from the employer (see Coface South Africa Insurance Co Ltd v East London Own Haven t/a Own Haven Housing Association 2014 (2) SA 382 (SCA) (“Coface”),
paragraphs 13 to 16, 22 and 25 to 26).
33 The one exception to this position is fraud. If the employer makes a demand
on the guarantee knowing full well that the event specified in it has not occurred (for example that there is not actually a breach of contract), then the guarantor has no duty to pay out on the demand, and the contractor is entitled to an interdict restraining it from doing so (see Guardrisk Insurance Company
v Kentz (Pty) Ltd [2014] 1 All SA 307 (SCA) paragraph 17).
34 The principal question in cases like this is accordingly whether a demand
conforms to the terms of the guarantee. If it does, then the amount demanded must be paid.
The URDG
35 In this case, that question is more complex than usual, because the guarantee
incorporates the Uniform Rules for Demand Guarantees (“the URDG”) . The
13
URDG is a set of internationally-formulated rules governing the process for
making and examining demands issued on demand guarantees. The URDG
has no binding effect unless incorporated into the terms of a particular guarantee. The application before me was argued on the basis that the URDG is to be treated as part of the guarantee, and accordingly that it i s binding
between the parties.
36 There are four articles of the URDG of particular relevance in this case. First,
there is article 15 (a), which provides that “[a] demand under the guarantee shall be supported by such other documents as the guarantee specifies, and in any event by a statement by the beneficiary, indicating in what respect the applicant is in breach of its obligations under the underlying relationship. This statement may be in the demand or in a separate signed document accompanying or identifying the demand”. Article 15 (c) allows the parties to contract out of this requirement, but there is no suggestion of that in this case.
37 Second, there is article 17, which provides that –
a. A demand may be made for less than the full amount available (“partial
demand”).
b. More than one demand ("multiple demands") may be made.
c. The expression "multiple demands prohibited" or a similar expression
means that only one demand covering all or part of the amount available
may be made.
d. Where the guarantee provides that only one demand may be made, and
that demand is rejected, another demand can be made on or before expiry of the guarantee.
e. A demand is a non-complying demand if:
i. it is for more than the amount available under the guarantee, or
ii. any supporting statement or other documents required by the
guarantee indicate amounts that in total are less than the amount demanded.
Conversely, any supporting statement or other document indicating an amount that is more than the amount demanded does not make the demand a non-complying demand.
14

38 Third, there is article 18, which provides both that “[m]aking a demand that is
not a complying demand or withdrawing a demand does not waive or
otherwise prejudice the right to make another timely demand, whether or not the guarantee prohibits partial or multiple demands” and that “[p]ayment of a demand that is not a complying demand does not waive the requirement for other demands to be complying demands”.
39 Fourth, there is article 24, the relevant parts of which required ABSA to
examine Exxaro’s demand to determine whether it was “compliant”, in the sense meant in article 17 (e). If ABSA determined that the demand was not compliant, then it had to say so, by issuing a notice stating that it is rejecting the demand, and setting out each discrepancy between the demand and the requirements of the guarantee forming the basis of the rejection. Article 24 (e) required that this notice be sent within five business days. If no such rejection
was issued, then, under article 24 (f) of the URDG, ABSA was “precluded
from claiming that the demand and any related documents do not constitute a
complying demand”. In those circumstances, the URDG clearly contemplates
that the guarantor must honour even a non-compliant demand.
The demands issued in this case
40 It is clear to me that neither of Exxaro’s demands conformed to the terms of
the guarantee, for at least the reasons Lamont J gave. Neither demand made
the supporting statements that the amounts demanded were “due and payable” and that the signatory to the demand was authorised to make it. These statements are both required under the guarantee, read with 17 (e) (ii)
15
of the URDG. In addition, neither demand was supported, as article 15 (a)
requires, “by a statement by the beneficiary, indicating in what respect the applicant is in breach of its obligations under the underlying relationship”. Both demands said no more than that “the Demand amount” was payable to Exxaro
as a result of TDS’ “failure to perform in terms of the Contract and its deemed event of default as per clause 32 of the agreement”.
41 I do not know what this means. Mr. Bothma could not tell me what it means,
and it seems to me that article 15 (a) required a clear and unambiguous statement of the respect or respects in which TDS was in breach of the underlying contract. None was given.
42 This is not, of course, the end of the matter, because, under articles 24 (e) and
(f) of the URDG, ABSA could not rely on these defects in the demands unless it rejected each of the demands within five days of receipt. As I have already
found, ABSA did reject Exxaro’s first demand within five days, substantially on the basis that it did not contain the warranty of authority the guarantee requires. Although ABSA did not use the word “reject”, the URDG makes clear that equivalent language will do. It seems to me that a demand being “deemed non-compliant” is such language.
43 However, ABSA did not reject the second demand, and was accordingly
precluded, under article 24 (f), from claiming that the second demand was non-compliant. At the hearing of the matter, I asked counsel whether this really mattered, since the second demand was plainly non-compliant with the guarantee, and article 24 (f) does not preclude me from considering whether, objectively speaking, the second demand conformed to the guarantee’s terms.
16
44 Mr. Amm initially suggested that I am so precluded by virtue of ABSA’s election
to be bound by article 24 (f). Insofar as ABSA chooses not to argue that the
demand was non-compliant, that must be correct. While article 24 (f) cannot oust my jurisdiction to consider whether, objectively, the second demand conforms to the terms of the guarantee, ABSA would have to raise that failure to conform as a defence to Exxaro’s claim for payment. If it did not, considering itself contractually bound to refrain from doing so, I think that I would have to honour ABSA’s election.
45 However, having taken an instruction from his attorney, Mr. Amm confirmed
that ABSA did in fact seek to rely on the second demand’s failure to conform to the terms of the guarantee, but only in the event that I rejected ABSA’s primary argument that the first and the second demand were really one continuous demand. I reserved judgment on that basis, and invited the parties to make post-hearing submissions on, amongst other things, the meaning and application of article 24 (f), and the question of whether the first and second
demands were to be treated as separate or as one continuous demand.
46 In those supplementary submissions, delivered on 16 May 2025, ABSA
changed tack again. It reverted to its initial position that I am precluded from considering whether the second demand conforms to the terms of the guarantee because ABSA considered itself bound by article 24 (f). At paragraph 3 of the submissions, counsel stated that ABSA “does not endorse nor pursue an argument that Absa’s failure to reject the 19 June 2020 “demand” does not preclude the Court from declining to enforce the demand by reason of its failure to conform to the terms of the Guarantee”.
17
47 The concession is wordy but clear. ABSA disavows any right to argue that I
can ignore article 24 (f) if the second demand objectively failed to conform to
the guarantee. ABSA was content to rest instead on the argument – which I
have rejected – that the first and second demands cannot be separated, and that the rejection of the first demand was necessarily a rejection of the second demand.
48 The nett result of all of this is that ABSA must honour the second demand ,
notwithstanding the demand’s obvious failure to conform to the terms of the guarantee, because ABSA failed to reject it .
The guarantee’s expiration date
49 This renders it necessary to deal, briefly, with the argument that the second
demand was ineffective because it was made after the guarantee expired. This argument was built on the text of the guarantee, the relevant part of which says that “[t]his guarantee shall expire on 19 June 2020 ("Expiry Date"). Any claim and statement received hereunder must be received at this office before the Expiry Date. After the Expiry Date, this guarantee shall lapse, whether returned to the Bank for cancellation or not and any claim or statement received after the Expiry Date shall be ineffective”.
50 Mr. Amm argued that the words “must be received at this office before the
Expiry Date” mean that the second demand had to be made by 18 June 2020 – i.e. “before the Expiry Date”. This hyper-literal interpretation does not bear
the merest scrutiny. Read sensibly as a whole, the text I have quoted specifies that the guarantee expires on 19 June 2020, and that a demand must reach ABSA before the guarantee expires. The interpretation for which Mr. Amm
18
contended would have the bizarre consequence that the guarantee would still
be effective on 19 June 2020, but for 24 hours before it expired, Exxaro would be precluded, for no good reason at all, from making a demand on the guarantee.
51 If more were needed (it is not), I would point out that in Dormell Properties 282
CC v Renasa Insurance Co Ltd 2011 (1) SA 70 (SCA) 2011 (1) SA 70 (SCA), at paragraph 59, it was said that “where a contract does not require a period of time to be calculated, but provides that the entitlement to exercise a right or the obligation to perform a duty ends on a specific day” then “the right may be
exercised, or the obligation performed, on that day”. Although this quote is culled from the minority decision, the majority decision in Dormell was later
found to have been clearly wrong (see Coface, paragraph 25). That, in my
view, renders the minority decision good authority. The guarantee expired on 19 June 2020. The second demand reached ABSA on 19 June 2020. The matter ends there.
Unconscionability
52 It remains to deal with ABSA’s argument that the demand on the guarantee
was unconscionable. In truth, the argument never really got off the ground. I
asked Mr. Amm what “unconscionable” means in this context. He could do no
better than to point to Exxaro’s conduct in this case.
53 However, I see nothing unconscionable, in the sense of unreasonable or
excessive, about what Exxaro did in this case. Its first demand on the guarantee was made in the belief that TDS was in breach of contract. Nobody has argued that Exxaro did not honestly believe this to be so, or that the
19
demand was excessive in light of the breach alleged. Mr. Amm suggested that
the discrepancy between the two demands implied unconscionable conduct. I do not see how. Exxaro’s second demand moderated the first after engagement with TDS. There is no suggestion that the moderated demand was excessive or unreasonable, and Exxaro’s willingness to moderate its demand suggests that its conduct was far from unconscionable.
54 To accept ABSA’s argument based on unconscionability, I would have to
develop the common law. But without some identifiably unconscionable feature of Exxaro’s conduct in this case, there is nothing to trigger such an exercise.
Order
55 It follows that Exxaro is entitled to payment on its second demand. There will
be an order in those terms. Costs will follow the result. The factual complexity of this case is such that a costs order on the “C” scale is appropriate.
56 For all these reasons –
56.1 The respondent is directed to pay the applicant the sum of
R22 165 055.66 (twenty-two million, one hundred and sixty-five thousand and fifty-five rand and sixty-six cents) within fifteen days of
the date of this order.
56.2 The respondent is directed to pay interest on that amount at the
prescribed rate of interest, calculated from 27 June 2020 to the date of final payment.