IN THE HIGH COURT OF SOUTH AFRICA, MPUMALANGA DIVISION,
(MBOMBELA MAIN SEAT)
DELETE WHICHEVER IS NOT APPLICABLE
(1) REPORTABLE : NO
(2) OF INTEREST TO OTHER JUDGES: NO
(3) REVISED YES/NO
2 ~May 2025
DATE
TUNICA TRADING 104
and
CITY OF MBOMBELA
MONTSHO-MOLOlSANE AJ JUDGMENT Case No. 3550/2024
Plaintiff
Defendant
[1.] This is an application for Summary judgment brought in terms of Uniform Rule
32 of this Court. The Applicant in this application is the Plaintiff in the action
instituted against the Defendant for payment of an amount of R 5 754 244.06,
which is alleged to be outstanding in respect of work done on the construction
of the Nkululeko Circuit road in Mbombela.
[2.] The Defendant entered appearance to defend the action, subsequent to which
the Plea was filed.
(3.) The Respondent opposes the application. and the basis for such opposition is
set out in its Answering affidavit.
(4.] The parties will herein be referred to as in the main action.
Background facts
[5.] The cause of action, as set out in the Particulars of claim, is based on what is
averred to be a Cession agreement concluded by the Plaintiff, the Defendant
and MJ Mthombeni Construction (Pty) Ltd (("MJ Mthombeni"), in terms of
which it was agreed that the Defendant would pay invoices for work done,
directly to the Plaintiff, as the sub-contractor, and not to MJ Mthombeni
Construction as the main contractor. A document titled "DIRECT PAYMENT
AGREEMENT", was drafted and signed by representatives of the Plaintiff, the
Defendant and MJ Mthombeni Construction on 06 April 2023, reflecting the
terms of the agreement. The amount quoted and agreed upon by the parties
was stated an an amount not exceeding R 9 373 658.36, payable once the
Engineer has certified such progress payment to be properly due to the
contractor.
[6.] It is averred that in terms of the Direct Payment Agreement:
2
6.1. the Defendant paid the Plaintiff, an amount of R 788 649.30 on 25
July 2023; R 1 434 167.72 on 07 September 2023; and R 396 586.31
on 15 November 2023;
6.2. MJ Mthombeni paid the Plaintiff a total amount of R 1 503 851.44
being R 531 645.00 on 06 March 2023 and R 972 206.44 on 24 March
2023;
6.3. the Plaintiff alleges that the Defendant and MJ Mthombeni paid a total
amount of R 5 123 254.77, leaving a shortfall of R 5 754 244.06.
[7 .] In its Amended Plea, the Defendant pleaded that:
7 .1. the contract for the construction of the Nkululeko Construction Circuit
road, was entered into between the Defendant and MJ Mthombeni
Construction, subsequent to its appointment under BID number
306/2021, to construct the Nkululeko Circuit road for the tendered
amount of R 18 653 251.62 (eighteen million six hundred and fifty
three thousand two hundred and fifty one rand and sixty two cents).
The appointment was governed by the General Conditions of Contract
for Construction Works, 3rd Edition, 2015;
7.2. the contract on Bid 306/2021 was not concluded with the Plaintiff, and
the Defendant was not a party to the contract entered into between
the Plaintiff and MJ Mthombeni Construction;
7 .3. the Defendant was approached by the representatives of MJ
Mthombeni Construction and the Plaintiff, due to lack of transparency
between them and payments which were not forthcoming from MJ
3
Mthombeni to the Plaintiff. As a result the Defendant drew up the said
document titled "DIRECT PAYMENT AGREEMENT" to quell any and
all infights between them, and avoid the impact thereon on service
delivery;
7.4. the amount of R 9 373 658.36 was an estimate that was subject to
certification by an Engineer for actual work done, the value of which
is subject to the original tendered rates submitted by MJ Mthombeni
Construction before the Bid was awarded, and not the rates stated by
the Plaintiff in its Bill of Quantities rates agreed to between MJ
Mthombeni Construction and the Plaintiff;
7.5. that in terms of the said DIRECT PAYMENT AGREEMENT. it is the
Defendant's Engineer, and not MJ Mthombeni Construction, who
certifies completion of works; and
7 .6. the Defendant denies that the agreement signed is a Cession.
The Summary Judgment application
The Founding affidavit
[8.] In its application for Summary judgment, the Plaintiff refers to the Defendant's
Plea to the Particulars of Claim, and contends that:
8.1. the Defendant paid the Plaintiff monies due to the main contractor, but
in its Plea denies that there was a valid Cession agreement of the
contract;
4
8.2. the Defendant's Plea that it was MJ Mthombeni Construction which
was appointed and not the Plaintiff, is vitiated by two
Acknowledgement Letters, issued on the letterheads of the
Defendant. titled "Municipal Public Accounts Committee" ("MPAC"),
each signed by a Councillor in Ward 14, bearing the City of Mbombela
stamp marked AX1 and AX 2 to the Founding affidavit. Annexure AX1,
reads as follows:
"This letter serves to acknowledge that the Municipal Public
Accounts Committee has received the request to intervene in the
issue of Tunica Trading 104, the committee will address the
issue with relevant department to pay the Tunica Trading 104
before 30 October 2024. This matter has been outstanding for a
while due to unforeseen reasons within the structure. We hereby
confirm that all work was completed and finalised. The two
projects in this regard are Mountainview Road Upgrade and
Nkululeko Circuit road. The values is as per cession agreement
and attached outstanding invoices as follows: (sic)
Project 1: R 6 670 000.00
Project 2: R 9 393 658.00
This matter will be resolved and settled
Working together in building better communities in a City of
excellence for an ultimate destination.
Yours in Ward 14
Mr B. Matsebula
5
MPAC Researcher and Investigator".
8.3. Annexure AX2 reads as follows:
"This letter serves to acknowledge that the Municipal Public
Accounts Committee has received the request to intervene in the
issue of Tunica Trading 104, the committee will address the
issue with relevant department to pay the Tunica Trading 104,
before the 30 October 2024. This matter has been outstanding
for a while due to unforeseen reasons within the structure. We
hereby confirm that all work was completed and finalised. The
two projects in this regard are Mountainview Road Upgrade and
Nkululeko Circuit road. The values is as per Cession agreement
and attached outstanding invoices. (sic)
Please assist the bearer in accordance with the Council's
relevant policy ...
Yours in Ward 14
Councillor M ...
01/09/2024"
[9.] The Plaintiff further contends that:
9.1. the Cession referred to was entered into in the amount of
R 9 373 658.36 and the Defendant cannot avoid liability in light of the
Direct Payment AgreemenUCession that it entered into with the
Plaintiff and MJ Mthombeni Construction, and also that it paid some
6
money to the Plaintiff pursuant thereto, between 25 July 2023 and 15
November 2023.
9.2. that a contractual right may be ceded by the cadent to the cessionary,
without informing the debtor, if the main contract between the parties
is not altered or amended, and moreover, if the debtor carries on
dealing with the original creditor, the cedent, in good faith, the
cessionary, which is the new creditor, is bound by the contract, and
the debtor cannot avoid liability.
(1 0.] The Plaintiff further avers that at the time of completion of the work by the
Plaintiff, the Defendant had underpaid the Plaintiff with the amount of
R 5 754 244.06.
[11.) In the premises, it was contended, the Defendant is indebted to the Plaintiff in
the amount of R 5 754 244.06 which was underpayment for the work
completed by the Plaintiff, and in respect of the Direct Payment Agreement.
The Answering affidavit
(12.] In the Answering affidavit opposing Summary judgment, deposed to by the
General Manager: Corporate Services of the Defendant, it is contended that:
12.1. the Plaintiff was never awarded Bid number 306/2021 subsequent to
which the Defendant entered into a contract for the construction of the
Nkululeko Circuit road;
7
12.2. the rates payable to Mthombeni Construction were subject to the
rates tendered in the Bid submitted by MJ Mthombeni and not as set
out in the Bill of Quantities submitted by the Plaintiff;
12.3. the Defendant disputes the authenticity of the two Acknowledgement
letters, AX1 and AX2, allegedly issued by the Municipal Public
Accounts Committee, indicating that it had received a request to
intervene in the issue with the Plaintiff, and undertaking to address the
issue with the relevant department to pay the Plaintiff before 30
October 2024;
12.4. that the role of the said Committee is one of oversight, and that its
appointment is in accordance with Section 79A of the Local
Government: Municipal Structures Act, no 117 of 1998 ("the
Structures Act"). The Court to the Confirmatory affidavit deposed to
Mr Kenneth Mkhonto the Councillor in Ward 14, disputes that
Annexure AX2 was written by him, and states that it is not his
signature appearing thereon.
12.5. that it is only a Municipal Manager who has the authority and is
responsible for the financial affairs of the Municipality in terms of
Section 60 of the Local Government: Municipal Finance Management
Act, no 56 of 2003 ("the Municipal Finance Management Act").
(13.) It is contended that the Plaintiffs claim should be dismissed as Rule 32(1)
requires that the claim be on a liquid document, or for a liquidated amount,
which has not been established in casu.
8
The Replying affidavit
[14.] In the Plaintiffs Replying affidavit, deposed to by its director, Mr Louis
Wessels, the historical background regarding the advertised Bid 306/2021 and
ultimate award thereof is outlined.
[15.] The Replying affidavit further sets out the circumstances that culminated with
the agreement between the MJ Mthombeni Construct ion and the Plaintiff, and
later on between the Plaintiff, MJ Mthombeni and the Defendant, which is a
Cession agreement. He contends that:
15.1. the Defendant made several payments directly to the Plaintiff, as a
result of the Cession agreement, accompanied by the completed Bill
of Quantities;
15.2. the Defendant was aware that the total amount due, at the time of the
signing of the Cession agreement, was R 9 373 658.36, in accordance
with Table A attached to the agreement, reflecting such amount, which
was signed on behalf of the COM, an acronym for City of Mbombela ,
the Defendant herein;
15.3. Councillor Mkhonto, who deposed to the Defendant's Confirmatory
affidavit disputing the authenticity of Annexure AX2, cannot be trusted
as he is conflicted and that he might have deposed to the affidavit
under duress, in order to secure his employment. The deponent
further questions the absence of an affidavit from Mr 8 Matsebula,
who is referred to as a neutral person, as he is not an employee of the
Defendant :
9
15.4. the main contractor confirmed that the work was completed; and
15.5. on the totality of the evidence, the Defendant does not have a valid
defence.
Issues for determination
(16.) The issues for determination are, the following:
16.1. whether the Plaintiffs claim for Summary judgment is based on a
liquid claim or liquidated amount in money; and.
16.2. whether the Defendant has disclosed a bona tide defence in its
Answering affidavit.
Evaluation
(17.] The following facts are common cause as pleaded in the affidavits before
Court:
17 .1. The Plaintiff and MJ Mthombeni Construction had a subcontracting
agreement in terms of the Nkululeko Circuit road, which extended to
the payment that was to be made to the Plaintiff for work done;
17 .2. the representatives of the Defendant and those of the Plaintiff got
together with MJ Mthombeni, of MJ Mthombeni Construction, and
concluded the Direct Payment Agreement for payment to be made
directly to the Plaintiff in respect of work or services completed, to
which Table A, that specified the amount of the said construction
project as not exceeding the total of R 9 373 658.36, was attached;
10
17.3. the only party who signed Table A, is a representative of the
Defendant, as that signature appears where the phrase-"On behalf of
COM' appears COM is an acronym for the City of Mbombela.
17.4. no date appears on Table A;
[18.) Table A has no probative value, as it was not signed by all three parties.
(19.] In any event, even if this Court were to consider the Direct Payment
Agreement as being a Cession agreement, without having to have regard to
the probative value of Table A, I am of the view that Clause 4.2 of the
agreement is crucial for the purpose of determining whether the Plaintiff has
satisfied the requirements set out in Rule 32(1 ). Clause 4.2 provides:
" 4.2 COM will only be obliged to effect payment to engaged Tunica
Trading in accordance to Table A, and to the amount not exceeding
R 9 373 658.36 (nine million three hundred and seventy three thousand,
six hundred and fifty eight rand and thirty six cents), once the Engineer
has certified such progress payment to be properly due to the
contractor'.
[20.) Clause 4.2 is therefore peremptory, as it accords with the General Conditions
of Contract for Construction Works, 3rd Edition 2015.
(21.J It is important to state that in paragraph 6.3 of the Replying affidavit, the
deponent, who is the director of the Plaintiff, refers to Annexure "COC 1" to the
Summons where he avers the following:
11
"6.3 The main contractor has confirmed that the work was done to
completion".
[22.] It is appropriate to mention that Annexure "COC1" to the Particulars of Claim,
which is relied on by the Plaintiff in this application , is a letter issued on the
letterheads of MJ Mthombeni Construction, and is titled "Final Approval
Certificate". The letter is signed on behalf of MJ Mthombeni Construct ion, and
Tunica Trading 104 (Pty) Ltd. The date 13 September 2023 is reflected next
to each signature. The letter states the Final Approval date as 01 September
2023, and states as follows:
"It is hereby confirmed that the site and the works stated in the contract
above have been duly inspected by MJ Mthombeni Construction (Pty)
Ltd and deemed complete and without any defects. A Final Approval
Certificate is hereby issued in accordance with Clause 5. 16. 1 of the
General Conditions of Contract 2015. (Expiration of Defects Liability
Period)."
(23.) I also take note that there is no reference in the Founding and Replying
affidavits, that an Engineer certified such progress payment to be properly due
to the contractor , as contemplated in Clause 4.2 of the Direct Payment
Agreement, so as to justify the granting of summary judgment prayed for.
[24.] Another important issue that needs to be addressed, is the authenticity of the
two Acknowledgement letters, referred to as Annexure AX1 and AX2, which
were issued by the Ward 14 Councillors . The deponent to the Defendant's
Confirmatory affidavit, Kenneth Mkhonto, disputes that he wrote the
document, and states that it is not his signature appearing thereon.
12
(25.) The veracity of the contents of the Confirmatory affidavit is however disputed
by the director of the Plaintiff, Louis Wessels, basing his contention on the fact
that Mr Mkhonto is still in the employ of the Defendant and would therefore
secure his employment. This is no doubt speculative.
[26.] In my view, whether the two Councillors were authorised to make the kind of
financial commitments appearing in Annexures AX1 and AX2, can only be
established by having regard to the statutory powers they have.
[27.) Section 79 A(1) of the Municipal Structures Act, which was referred to by the
Defendant's Counsel, provides for the establishment of the Municipal Public
Accounts Committee, whose functions, as stipulated in subsection(3) thereof,
are inter alia, to review the Auditor-General's reports and comments, and
make recommendations to the Municipal Council based thereon; to initiate and
develop oversight report on annual reports, and investigate reports on any
matter affecting the Municipality.
[28.J In terms of Section 60 of the Municipal Finance Management Act, and as
correctly contended on behalf of the Defendant, it is only the Municipal
Manager, as the accounting officer, who is authorised to make financial
decisions on behalf of the Defendant, and not the Municipal Public Accounts
Committee or Councillors.
[29.] In my view, the contention by Plaintiffs Counsel that the two Councillors made
an assurance to the Plaintiff that the payment was approved by the Municipal
Public Accounts Committee , is binding on the Defendant, is not sustainable ,
13
based on the fact that they are not authorised to make financial decisions in
terms of the provisions of the Municipal Finance Management Act.
[30.] Plaintiffs Counsel further referred this Court to the case of Hippo Quarrine
(Tvl) (Pty) Ltd v Eardley1, where a Cession agreement was described as "an
essential link in the Plaintiff's case" and to the case of Johnson v Incorporated
General Insurance LtcP, where the Court held that:
"Cession, in our modern law, can be seen as an act of transfer to enable
the transfer of a right to claim ... to take place".
[31.] In this regard, I am of the view that whether the tripartite agreement entered
into by the parties on 06 April 2023 constitutes a Cession agreement or not,
ex facie the document, the inquiry should be limited to whether the Defendant
has entered appearance to defend the Plaintiff's claim, solely for the purpose
of delay.
[32.] It is undoubtedly so that Summary judgment enables a Plaintiff to obtain
judgment against a Defendant without resorting to trial when a Defendant has
no defence to a claim based on a liquid document, or for a liquidated amount
of money.
(33.] The Defendant's Counsel, in my view, correctly so, referred this Court to the
judgment in the case of Majola v Nitro Securitisation 1 (Ply) Lt<fJ, where it was
held that:
1 Hippo Quarrine (Tvl) (Pty) Ltd v Eardley, 1992(1) SA 867 (A) at 873 D
2 Johnson Incorporated General Insurance Ltd 1983 (I) SA 3 I 8 (A)
3 Majola v Nitro Securitisation I (Pty) Ltd 2012 (I) SA 226 (SCA)
14
"The procedure is not intended to shut out a defendant who can show
that there is a friable issue applicable to the claim as a whole, from laying
his defence before the Courf'4.
Applicable Law
(34.) Rule 32(1) entitles the Plaintiff to apply to Court for Summary judgment on
each of such claims in the summons as is only-
"(a) on a liquid document;
(b) for a liquidated amount in money;
(c) for delivery of specified movable property;
( d) for ejectment"
[35.] In the case of Rossouw and Another v First Rand Bank Ltd t/a FNB Homeloans
(formerly First Rand Bank of South Africa Ltd5, the Court defined a liquidated
amount of money as "an amount which is either agreed upon or which is
capable of speedy and prompt ascertainmenr.
[36.] The landmark judgment of Corbett JA in the case of Maharaj v Barclays
National Bank Ltd6, outlines the principles and requirements for opposing
Summary judgment. It specifically explains what a Defendant has to
demonstrate to successfully resist a Summary judgment application, requiring
him/her to show a bona fine defence to the claim.
4 At 232 F-G
s Rossouw and Another v First Rand Bank Ltd Ila FNB Homeloans (formerly First Rand Bank of South Africa
Ltd 2010 (6) SA 439 (SCA)
6 Maharaj v Barclays National Ltd 1976 (l) SA 418 (A)
15
[37.] In essence, the Maharaj judgment sets the standard for how a Defendant can
effectively oppose a Summary judgment application by presenting a credible
and legally sound defence.
[38.] The rationale and requirements for the grant or refusal of Summary judgment
are trite and were summarised by the Supreme Court of Appeal, relying on the
Maharaj judgment supra in the case of Joob Joob Investments (Pty) Ltd v
Stocks Mavundla Zek Joint Venture7, to which the Defendant's Counsel
correctly referred this Court to, as follows:
Findings "Our Courts, both of first instance and at appellate level, have during that
time rightly been trusted to ensure that a defendant with a friable issue
is not shut out. In the Maharaj case at 425 G-426 E, Corbett JA was
keen to ensure, first, an examination of whether there has been sufficient
disclosure by a defendant of the nature and grounds of his defence and
the facts upon which it is founded. The second consideration is that the
defence so disclosed must be both bona fide and good in law. A Court
which is satisfied that this threshold has been crossed is then bound to
refuse Summary judgment" .
(39.) It has been contended on the Plaintiff's behalf, that the cause of action against
the Defendant is based on the Direct Payment Agreement , which is a Cession
agreement.
1 Joob Joob Investments (Ply) Ltd v Stocks Mavundla Zek Joint Venture 2009 (5) SA I (SCA)
16
(40.) As I have already evaluated this submission, it does not absolve the
Defendant from the obligation of satisfying this Court that the claim is based
on a liquid document, or is for a liquidated amount of money.
[41.) I have also expressed my view regarding the Plaintiffs reliance on Annexures
AX1 and AX2, which, it was contended, was an assurance of indebtedness
signed by the two Councillors in Ward 14 of the municipality. This does not
accord with the provisions of the Municipal Finance Management Act.
[42.] Lastly, there has not been any compliance with Clause 4.2 of the Direct
Payment Agreement , in that there is no Certificate submitted by an Engineer
certifying such progress payment to be properly due to the Plaintiff. Instead,
the Plaintiff relies on the Final approval certificate, sent by MJ Mthombeni
Construction which, according to the Defendant is insufficient to warrant
payment.
[43.) It is trite that where the defence is based upon facts which dispute the material
facts alleged by the Plaintiff in the Summons, the Court cannot decide those
issues or determine whether or not there is a balance of probabilities in favour
of one of the parties. The Court, in those circumstances, is obliged to enquire
firstly, whether the Defendant has fully disclosed the nature and grounds of
his/her defence, and the material facts on which it is founded; and secondly,
whether on the facts so disclosed, the Defendant appears to have a defence
which is bona fide and legally sound.
[44.) I am therefore of the view that the Defendant should successfully resist
Summary judgment prayed for by the Plaintiff on the basis that there is a
17
reasonable possibility that the defence advanced by the Defendant, as set out
in the Answering affidavit, may succeed on trial.
[45.] In the light of the disputes raised by the Defendant and the bona tide defence
disclosed , I am of the view that the Plaintiffs claim is not liquidated, nor is it
based on a liquid document. In the circumstances the Plaintiff has not met the
threshold set in Rule 32(1) for Summary judgment to be granted.
(46.) Having regard to the afore-stated legal principles, I am satisfied that the
Summary judgment application should be dismissed .
(47.] The Defendant has prayed for an order for costs to be awarded on a punitive
scale. I am however not persuaded that there is any factual and legal basis
that justifies the award of costs against the Plaintiff on a punitive scale, in the
absence of any facts pleaded by the Defendant to that effect, in its Answering
affidavit.
ORDER
[48.) In the result, this Court makes the following Order:
48.1. The application for Summary judgment is dismissed with costs;
48.2. Costs of suit to be paid by the Plaintiff on a party and party scale.
18 L.M. MONTSHO-MOLOISANE
ACTING JUDGE OF THE HIGH COURT
MPUMALANGA DIVISION , MBOMBELA
Date heard
Judgment delivered
electronically by circulation to all parties :
Appearances
Counsel for the Plaintiff
Instructed by
Counsel for the Defendant
Instructed by
19 07 March 2025
23 May 2025
Adv A.A. Milazi
Milazi AA Incorporated
Mbombela
Ms Xolile Ngwenya
Xolile Ngwenya Attorneys
Mbombela