Twenty-Third Century Systems (Pty) Ltd and Another v SAP Africa Region (Pty) Ltd (172/2023) [2025] ZASCA 51 (30 April 2025)

82 Reportability
Contract Law

Brief Summary

Contract — Repudiation — Survival of contract terms after repudiation — Appellants claimed damages for loss of profit following the respondent's repudiation of a service agreement — High Court upheld respondent's special pleas, finding that exclusion of damages and time bar clauses survived termination of the agreement — Legal issue centered on whether a party can rely on contract terms post-repudiation — Court held that the exclusion of damages and time bar clauses are secondary obligations that survive termination, allowing the respondent to invoke them as a defense against the appellants' claims.

Comprehensive Summary

Summary of Judgment


1. Introduction


The proceedings were an appeal to the Supreme Court of Appeal of South Africa against an order of the Gauteng Division of the High Court, Johannesburg. The High Court had upheld two special pleas raised by the respondent and, on that basis, dismissed the contractual damages claims advanced by the appellants.


The appellants were Twenty-Third Century Systems (Pty) Ltd (the first appellant, a Zimbabwean company) and Twenty-Third Century Systems Global (Pty) Ltd (the second appellant, a Botswanan company wholly owned by the first appellant). The respondent was SAP Africa Region (Pty) Ltd, a South African company providing information technology services.


The procedural history was that the appellants (as plaintiffs) issued summons in the High Court claiming substantial damages (a combined sum exceeding US $68 million) said to arise from SAP’s alleged repudiation of a suite of agreements. SAP delivered a plea that included two special pleas founded on contractual provisions, namely an exclusion of damages clause (precluding loss of profits claims) and a one-year time bar clause. The High Court upheld both special pleas and dismissed the claims. The appellants appealed with leave of the Supreme Court of Appeal.


The general subject-matter of the dispute concerned the post-termination enforceability of particular contractual provisions—specifically whether SAP could rely on the limitation of liability (including an exclusion of loss of profits) and time bar clauses after the agreement had come to an end following repudiation and acceptance, and whether reliance on those clauses amounted to impermissible approbation and reprobation.


2. Material Facts


SAP and the appellants’ corporate group had an established relationship in terms of which Systems acted as a service provider of SAP products in territories in Sub-Saharan Africa outside South Africa. The appeal, however, concerned a particular suite of three written agreements concluded simultaneously on 30 May 2016 between Global and SAP. For purposes of the appeal, those three agreements were treated as a single agreement.


The agreement included a component termed SAP PartnerEdge, structured into definitions and interpretation, Part 1 (general terms with 17 articles), and Part 2 (country-specific terms with 12 articles). Of particular significance were the following provisions in Part 2, Article 1: a clause excluding liability for (among other things) loss of profits, and a clause requiring claims to be instituted within one year from when the partner knew or should have known (after reasonable investigation) of the facts giving rise to the claim.


Between 1 and 22 July 2019, the parties exchanged correspondence about termination. On 1 July 2019, SAP informed Global that it was terminating the agreements “for good cause”. Global’s attorneys responded on 15 July 2019 asserting that SAP’s conduct amounted to repudiation, which Global accepted. It was common cause that the agreement had ended, although the parties disputed who was in breach (SAP contending good-cause termination and the appellants alleging SAP repudiation).


The appellants instituted action on 30 November 2020 claiming damages for loss of profit arising from SAP’s repudiation. Although Systems was the claimant seeking relief, Global was cited as a second plaintiff (and became the second appellant), on the pleaded basis that Global acted as Systems’ agent to SAP’s knowledge.


It was undisputed (and accepted for purposes of the appeal) that the agreement contained (i) an exclusion precluding damages for loss of profits, and (ii) a one-year time bar applicable to any claims arising out of or relating to any part of the agreement and its subject matter.


In their replication, the appellants denied that SAP could rely on these clauses after repudiating the agreement. They contended that SAP’s reliance on the clauses would amount to approbation and reprobation, because SAP would be seeking to both disavow the agreement (by repudiation) and benefit from it (by invoking its protections). They also denied that the time bar had been triggered more than a year prior to summons.


For purposes of the appeal, the parties agreed that the special pleas were to be assessed on the assumption that SAP had repudiated the agreement (and that the repudiation had been accepted), so the key question became whether the clauses relied upon nevertheless remained operative.


3. Legal Issues


The central legal questions were whether, after repudiation and acceptance (bringing the agreement to an end in the relevant sense), SAP could still rely on:


the exclusion of damages / limitation of liability clause precluding loss of profits claims; and


the one-year time bar clause.


A further issue was whether SAP’s reliance on those clauses, despite being assumed to have repudiated, was barred by the doctrine of approbation and reprobation (i.e., whether SAP was impermissibly taking inconsistent positions by both repudiating and relying on the contract).


The dispute primarily concerned the application of legal principles to largely common-cause contractual facts, together with an issue of contractual interpretation (notably the scope and effect of the survival clause and related termination provisions). The appeal did not turn on resolving factual disputes about who was in breach, because it proceeded on the assumption that SAP repudiated.


4. Court’s Reasoning


The court approached the matter by identifying the applicable contractual principles relating to the effect of repudiation and acceptance, and the distinction between different categories of contractual terms that may or may not persist after termination. It considered authority addressing whether a party who has repudiated may nonetheless rely on certain contractual provisions (such as arbitration clauses), and then applied those principles to limitation and time bar provisions, particularly where the contract contains an express survival clause.


The court noted that in Johannesburg Municipal Council v D Stewart & Co (1902) Ltd and Others Lord Shaw expressed the view that it did not appear sound to permit a person to repudiate a contract and then rely on a term in that contract. However, the court emphasised that later authority—particularly Heyman and Another v Darwins Limited—drew an important distinction between repudiation and termination, and between obligations directed to performance and provisions that govern the consequences of breach and dispute resolution.


In adopting the approach from Heyman, as applied in South African law, the court reiterated that repudiation constitutes a breach but does not, by itself, terminate the contract. Termination occurs when the innocent party accepts the repudiation, thereby ending the parties’ primary obligations to perform. That step does not erase the contract for all purposes; rather, the contract may “survive” for purposes such as measuring and resolving claims arising from the breach, and certain provisions may remain operative.


The court relied on South African authority applying these principles, including Scriven Bros v Rhodesian Hides & Produce Co Ltd and Others and Atteridgeville Town Council and Another v Livanos t/a Livanos Brothers Electrical, which recognised that certain provisions—classically, arbitration clauses—can survive repudiation and acceptance because they are directed at the resolution of disputes or the consequences of breach rather than the reciprocal performance obligations. The court further referred to the distinction between primary and secondary obligations as articulated in Photo Production Ltd v Securicor Transport Ltd, and the characterisation of repudiation as a breach and acceptance as the exercise of a right to cancel in Datacolor International (Pty) Ltd v Intamarket (Pty) Ltd.


Applying these principles, the court treated the exclusion of damages clause and the time bar clause as secondary in nature: they were not “purposes” of the agreement in the sense of performance objectives, but provisions regulating liability and the enforcement of claims following a dispute or breach. On the court’s analysis, acceptance of repudiation ends primary performance duties but activates secondary consequences; clauses governing liability and claim enforcement are consistent with that secondary framework.


The court then considered the agreement’s express wording on survival. It held that Article 17(13) expressly provided that several provisions would “survive any termination of any part of this Agreement,” including Part 2 – Article 1 (Limitation of Liability), which encompassed the clauses on which SAP relied. The court interpreted “any termination” to include termination resulting from acceptance of repudiation. It reasoned that this was the sensible interpretation of the word “any” in context, and that if the parties intended to exclude termination arising from repudiation, they would have said so.


The court rejected the appellants’ contention that the survival clause applied only to termination “for good cause” under Article 10(2). It examined Articles 10 and 11, observing that Article 11 dealt with the effects of termination in broad terms, including scenarios where the PartnerEdge model is “terminated, rescinded or ended in any other way.” The court construed these provisions as indicating that the contract contemplated multiple modes by which the agreement could come to an end, and that post-termination consequences (including restrictions on use of intellectual property and obligations such as payment of fees) were intended to apply irrespective of how termination occurred. The court further reasoned that adopting the restrictive interpretation advanced by the appellants would undermine the function of Articles 10, 11, and 17(13), and would produce unbusinesslike results inconsistent with the contract’s evident structure.


On the appellants’ reliance on approbation and reprobation, the court accepted SAP’s characterisation that it was not seeking to take inconsistent positions, but to invoke obligations that (on the proper construction and application of contractual principles) survived termination. Once the court concluded that the clauses survived, SAP’s reliance on them operated as reliance on surviving contractual terms rather than as a disallowed attempt to both repudiate and benefit from performance provisions.


On that basis, the court held that SAP was entitled to rely on both the exclusion of damages clause and the time bar clause as defences. It followed that the special pleas were properly upheld and that the appeal could not succeed.


5. Outcome and Relief


The Supreme Court of Appeal dismissed the appeal.


The effect was that the High Court’s order upholding SAP’s two special pleas stood, with the result that the appellants’ claims against SAP were dismissed.


The court ordered that the first appellant pay SAP’s costs of appeal, including the costs of two counsel where employed, finding such employment reasonable given the amount claimed and the issues raised.


Cases Cited


Johannesburg Municipal Council v D Stewart & Co (1902) Ltd and Others [1909] UKHL 20 (06 July 1909); 47 ScotLR 20, [1909] UKHL 20.


Heyman and Another v Darwins Limited [1942] 1 All ER 337 (HL).


Scriven Bros v Rhodesian Hides & Produce Co Ltd and Others 1943 AD 393.


Atteridgeville Town Council and Another v Livanos t/a Livanos Brothers Electrical 1992 (1) SA 296 (A); [1992] 1 All SA 274 (A).


Photo Production Ltd v Securicor Transport Ltd [1980] 1 All ER 556; [1980] AC 827; [1980] UKHL 2.


Datacolor International (Pty) Ltd v Intamarket (Pty) Ltd 2001 (2) SA 284 (SCA); [2001] 1 All SA 581 (A).


Hlatshwayo v Mare and Deas 1912 AD 242.


Legislation Cited


No legislation was cited in the judgment.


Rules of Court Cited


No rules of court were cited in the judgment.


Held


The court held that, on the assumption that SAP repudiated the agreement and the repudiation was accepted, the acceptance brought the parties’ primary performance obligations to an end but did not negate the operation of secondary contractual provisions dealing with liability and enforcement.


It held that the exclusion of damages / limitation of liability clause (precluding loss of profits) and the one-year time bar clause were secondary in nature and, in any event, were expressly preserved by the agreement’s survival clause (Article 17(13)), which applied to “any termination,” including termination resulting from repudiation and acceptance.


It further held that SAP was therefore entitled to rely on these clauses as defences, and the appeal against the upholding of the special pleas was dismissed with costs.


LEGAL PRINCIPLES


Repudiation constitutes a breach of contract; it does not itself terminate the contract. Termination occurs when the innocent party accepts the repudiation, thereby electing to cancel and bringing primary obligations of performance to an end.


A distinction is drawn between primary obligations (reciprocal performance duties) and secondary obligations (consequences and mechanisms that arise upon breach or termination, including provisions regulating liability, remedies, dispute resolution, and enforcement).


Upon acceptance of repudiation, the contract may remain operative for purposes including the measurement and settlement of claims arising from breach, and secondary provisions may continue to apply.


Contractual provisions may expressly be preserved post-termination through a survival clause. Where a contract provides that specified terms survive “any termination,” that language is interpreted to include termination resulting from repudiation and acceptance, unless the contract clearly indicates otherwise.


Clauses such as an exclusion of damages (including loss of profits) and a time bar for instituting claims can operate as post-termination defences where they are properly construed as surviving termination, whether by their nature as secondary provisions or by express survival wording.



THE SUPREME COURT OF APPEAL OF SOUTH AFRICA
JUDGMENT

Reportable
Case no: 172/2023

In the matter between:

TWENTY -THIRD CENTURY
SYSTEMS (PTY) LTD FIRST APPELLANT

TWENTY -THIRD CENTURY
SYSTEMS GLOBAL (PTY) LTD SECOND APPELLANT

and

SAP AFRICA REGION (PTY) LTD RESPONDENT

Neutral C itation: Twenty -Third Century Systems (Pty) Ltd and Another v SAP
Africa Region (Pty) Ltd (172/2023) [20 25] ZASCA 51
(30 April 2025 )
Coram: MOCUMIE, KGOELE and KATHREE -SETILOANE JJA and
WINDELL and BLOEM AJJA
Heard: 14 March 2025
Delivered: This judgment was handed down electronically by circulation to the
parties’ representatives by email, publication on the Supreme Court of Appeal
website, and released to SAFLII. The date and time for hand down is deemed to
be 30 April 2025 at 11h00.

2
Summary: Law of c ontract – whether a contracting party can rely on the terms
of a contract after the termination of the contract – distinction between primary
and secondary terms of a contract after the acceptance by the innocent party of
the repudiation (breach) of the cont ract – interpretation of the contract – effect of
survival clauses in a contract – whether the doctrine of approbation and
reprobation applies .























3
_______________________________________________________________

ORDER
_________________________________________________________

On appeal from : Gauteng Division of the High Court, Johannesburg (Manoi m J,
sitting as court of first instance ):
1 The appeal is dismissed.
2 The first appellant shall pay the respondent ’s costs, such costs to include the
costs of two counsel, where so employed.


JUDGMENT


Bloem AJA (Mocumie, Kgoele and Kathree -Setiloane JJA and Windell AJA
concurring) :

[1] The appellants issued summons against the respondent in the Gauteng
Division of the High Court, Johannesburg (the high court), wherein the first
appellant claimed payment of the combined sum of US $68 034 351.49, interest
thereon and costs from the respond ent. The respondent raised two special pleas
to the appellants’ particulars of claim. The high court (Mano im J) upheld the
special pleas and dismissed the claims against the respondent. It is w ith the leave
of this Court that the appellants appeal against the high court’s order .

[2] The first appellant is Twenty -Third Century Systems (Pty) Ltd ( Systems ),
a company incorporated in Zimbabwe, where it has its principal place of business.
The second appellant is Twenty -Third Century Systems Global (Pty) Ltd
(Global ), a company incorporated in Botswana, where it has its principal place of
business. Global is wholly owned by Systems . I shall refer to them collectively
4
as the appellants. The respondent is SAP Africa Region (Pty) Ltd (SAP) , a
company registered an d incorporated in South Africa, with its principal place of
business in Gauteng.

[3] SAP is a prominent international provider of information technology
services. Over the years, Systems entered into agreements with SAP in terms of
which Systems was appointe d as a service provider of SAP’s products in certain
territories. This entailed selling various information technology services offered
by SAP to its customers. Systems developed a customer base for SAP’s products
across various territories in Sub -Saharan Africa, excluding South Africa.

[4] This appeal concerns a suite of three written agreements which Global and
SAP concluded simultaneously on 30 May 2016. For purposes of this appeal, the
three agreements will be treated as a single agreement (the agreement) . Of
relevance to this appeal is the portion of the agreement termed the ‘SAP
PartnerEdge ’. It consists of three sections. The first section consists of
‘Definitions and Interpretations ’. The second section consists of Part 1, being the
general terms and c onditions of the SAP PartnerEdge . Part 1 has 17 Articles. The
third section consists of Part 2, being the country specific terms and conditions of
the SAP PartnerEdge . Part 2 has 12 Articles.

[5] Between 1 and 22 July 20 19, SAP and the appellants (and later their
respective attorneys) exchanged letters regarding the termination of the
agreement. I n a letter dated 1 July 2019 , SAP informed Global that ‘SAP herewith
terminates the Agreements for good cause ’. SAP also advised its customer base
that neithe r Systems nor Global was accredited to sell, service or maintain SAP
software because neither of them was a SAP licensee. In a letter dated
15 July 2019 , Global’s attorneys informed SAP’s attorneys that, through its
conduct, SAP had repudiated the agreement, which Global accepted. It was
5
accordingly common cause that the agreement had ended , albeit that the parties
did not agree on who breached the agreement.1

[6] On 30 November 2020, the appellants instituted an action against SAP in
the high court for loss of profit arising from its (SAP’s) repudiation of the
agreement . Although it is only Systems which claim s relief against SAP in the
action, System s cited Global as the second plaintiff, now the second appellant. It
appears that Systems joined Global because its case is that, when the agreement
was concluded and thereafter, Global, to SAP’s knowledge, acted as its
(Systems’) agent.

[7] It is undisputed that the agreement precludes a claim for damages for loss
of profit and that it limits the period within which to institute a claim to one year,
where such a claim arises out of or relates to any part of the agreement. The one -
year period runs from the dat e when a partner knew or should have known, after
reasonable investigations, of the facts giving rise to the claim(s).

[8] Except for denying liab ility to Systems in its plea, SAP also raised two
special pleas. In the first special plea SAP alleged that the l oss of profit claim is
precluded by clause 2 of Article 1 of Part 2 of the agreement . In the second special
plea SAP, relying on clause 4 of Article 1 of Part 2, alleged that the loss of profit
claim is time barred, and that Systems was precluded from institut ing the claim
against it at that late stage .

[9] Clause 2 (b) of Article 1 of Part 2 of the agreement deals with SAP ’s right
to collect fees owed under or in connection with any part of the agreement. The
relevant parts of clause 2 (b) read as follows:

1 It needs to be emphasised that t he parties did not agree to terminate the agreement.
6
‘Exclusion of Damages; Limitation of Liability. Anything to the contrary herein
notwithstanding, except for:
a) …; or
b) …,
under no circumstances and regardless of the nature of any claim will SAP, its licensors or
partner be liable to each other or any other person or entity … or be liable to any amount for
special, incidental, consequential, or indirect damages, loss of good will or profits, work
stoppage, data loss, computer failure or malfuncti on, attorneys ’ fees, court costs, interest or
exemplary or punitive damages. ’

[10] Clause 4 of Article 1 of Part 2 of the agreement reads as follows:
‘Time bar. Partner must initiate a cause of action for any claim(s) arising out of or relating to
any part of this Agreement and its subject matter within one year from the date when Partner
knew, or should have known after reasonable investigations, of the facts giving rise to the
claim(s). ’2

[11] In their replication, t he appellants den ied that SAP was entitled to rely on
either the exclusion of damages clause or the time bar clause . They allege d that,
because SAP had repudiated the agreement, SAP was precluded from relying on
the limitation of liability clause. They contend ed that SAP cannot breach the
agreement and , thereafter , rely on the very same breached agreement to draw a
benefit from it , by precluding them from pursuing their claims for loss of profit
(the doctrine of approbation and reprobation) . The appellants also denied that they
knew or ought reasonably to have known of the facts giving rise to the ir loss of
profit claims one year prior to the service of the summons in this action .


2 In terms of the agreement , the term “Partner” , as used in the SAP Partner Code of Conduct, comprises all
Technology -, Solution -, Service - (for example, consulting, implementation, system integration, hosting and
education), Channel - (value added reseller, distributor and other reseller) and all other Partners collaborating with
SAP; and being p art of any Partner program of SAP after having been offered global or local partnership by SAP
in any strategic business area or for any customer need in all market segments; and then being nominated as
Partner by SAP. The term Partner also includes a Part ner’s employees . The appellants were at all times material
hereto SAP’s partners.
7
[12] The high court found that the two clauses in question survive d the
termination of the agreement , upheld both special pleas and dismissed the claims
against SAP . In this Court, the parties agreed that, for purposes of the appeal, it
must be accepted that the high court determined the special pleas on the
assumption th at SAP had repudiated the agreement. The appeal was argued before
us on that same basis.

[13] The appellants contend ed that if SAP were allowed to rely o n those two
clauses a fter it had repudiat ed the agreement , this would constitute approbation
and reprobation .3 They contended that the high court failed to engage with the
doctrine of approbation and reprobation and that, had it done so , it would have
dismissed the special pleas. SAP, on the other hand, contended that it was not
seeking to approbate and reprobate , but merely to rely on obligations that
survived the termination of the agreement . Nonetheless, SAP submitted that the
appeal must nevertheless fail, because of the express provisions of the exclusion
of damages clause a nd the time bar clause. The central issue in this appeal is
whether SAP can, to avoid liability, rely on the exclusion of damages clause and
the time bar clause , despite having repudiated the agreement.

[14] The issue of whether a contracting party who has repudiated a contract is
entitled to rely on a clause of the repudiated contract was raised in Johannesburg
Municipal Council v D Stewart & Co (1902) Ltd and Others.4 Lord Shaw took
the view that it did not appear ‘to be sound law to permit a person to repudiate a
contract, and thereupon specifically to found upon a term in that contract which
he has thus repudiated ’.

3 Although this Court was dealing with waiver in Hlatshwayo v Mare and Deas 1912 AD 242, the principle in the
following statement at 259 is the same insofar as approbation a nd reprobation is concerned, namely, that ‘. . . no
person can be allowed to take up two positions inconsistent with one another, or as is commonly expressed to
blow hot and cold, to approbate and reprobate ’.
4 Johannesburg Municipal Council v D Stewart & Co (1902) Ltd and Others [1909] UKHL 20 (06 July 1909) ; 47
ScotLR 20, [1909] UKHL 20 .
8
[15] In Heyman and Another v Darwins Limited (Heyman ),5 which was also
concerned with whether an arbitration clause survives termination, Lord
Macmillan did not agree with the above statement by Lord Shaw. His view is
essentially that repudiation does not terminate the contract, although it may
relieve the inn ocent party of any further obligation to perform what he, for his
part, has undertaken in the contract. In this regard, he drew a distinction between
the arbitration clause in a contract and the executive obligations undertaken by
each party to the other.

[16] What is clear from Heyman is that , although the performance of obligations
to each other under the contract may cease , repudiation does not terminate the
contract . It therefore stands and t he innocent party still has his right of action for
damages under the contract which has been breached. The terms of the contract
which provide the measures of those damages survive the breached contract. This
could , for example, be an arbitration clause w hich ha s nothing to do with the
performance of obligations under the contract but rather provid e a mechanism to
address the consequences of the failed contract. In this regard, Lord Macmillan
stated that a contract , where the innocent party has accepted th e repudiation ,
‘…survives for the purpose of measuring the claims arising out of the breach, and
the arbitration clause survives for determining the mode of their settlement. The
purposes of the contract have failed, but the arbitration clause is not one o f the
purposes of the contract ’.6

[17] Heyman was applied by this Court in Scriven Bros v Rhodesian Hides &
Produce Co Ltd and Others (Scriven )7 where a contract contained an arbitration
clause. This Court did not sustain the submission of Scriven Bros that, since

5 Heyman and Another v Darwins Limited [1942] 1 All ER 337 (HL).
6 Ibid at 373-374.
7 Scriven Bros v Rhodesian Hides & Produce Co Ltd and Others 1943 AD 393.
9
Rhodesian Hides & Produce Co Ltd repudiated the contract, it was not entitled to
avail itself of the arbitration clause. It found that the repudiation of a contract does
not destroy the efficacy of the arbitration clause, as its purpose was to provide
suitable machinery for the settlement of disputes arising out of or in relation to
the contract. That being the purpose of the arbitration clause, this Court found
that it was reasonable to infer that the contracting parties intended the arbitration
clause to operate after the contract had come to an end. The arbitration clause
accordingly survived the repudiation of the contract by one of th e parties.

[18] This Court was again confronted with the same issue in Atteridgeville Town
Council and Another v Livanos t/a Livanos Brothers Electrical.8 It was submitted
that, because both parties claimed that the other party had repudiated the
agreements, the legal relationship between them had been dissolved, and the
arbitration clause had fallen away. Smalberger JA did not sustain that submission.
He drew a distinction between primary and secondary obligations of a contract
and the effects of repudiation or the acceptance of the repudiation on those
obligations.

[19] Smalberger JA followed the reasoning in Scriven that the real purpose of
the arbitration clause was to provide suitable machinery for the settlement of
disputes between Livanos and the Council arising from the agreements and that
it was reasonabl e to infer that the parties intended the provisions of th e arbitration
clause to operate even after their primary obligations to perform had come to an
end. The arbitration clause was consequently found to have survived the
repudiation of the agreements. The distinction between primary and secondary
obligations of the agreement is thus important in the enquiry whether a party is

8 Atteridgev ille Town Council and Another v Livanos t/a Livanos Brothers Electrical 1992 (1) SA 296 (A) ; [1992]
1 All SA 274 (A) (Atteridgeville Town Council ).
10
entitled to rely on a provision of a contract where the repudiation has been
accepted.

[20] Lord Diplock drew a distinction between primary and secondary
obligations under a contract in Photo Production Ltd v Securicor Transport Ltd.9
Primary obligations are those obligations that are directed at the discharge of
performance under the contract. For example, in the case of sale, it is the primary
obligation of the seller to deliver the merx to the purchaser; and the purchaser has
the primary obligation to pay for the merx. Secondary obligations under a
contract, are activated when primary obligations are not performed. In such a
case, the party who breached the contract might have a duty to make restitution
and, for instance, pay damages.

[21] This Court stated in Datacolor International (Pty) Ltd v Intamarket (Pty)
Ltd10 that the better approach to viewing repudiation is that it is a breach of the
contract in question. The acceptance of the repudiation does not complete the
breach but is simply the exercise by the innocent party of his right to terminate
the contract. In other words, when the innocent party accepts the repudiation, he
brings an end to the primary obligations of the parties to perform in terms of their
contract and activates certain secondary obligations.

[22] Based on the above authorities, t he established law is that, when a party
repudiates a contract, he breaches that contract. The repudiation of the contract
does not terminate the contract. The innocent party has a choice of keeping the
contract alive and enforcing it, or of cancelling it by accepting the repudiation. If
he accepts the repudiation, he manifests an intention neither to accept further

9 Photo Production Ltd v Securicor Transport Ltd [1980] 1 All ER 556 ; [1980] AC 827 ; [1980] UKHL 2 .
10 Datacolor International (Pty) Ltd v Intamarket (Pty) Ltd 2001 (2) SA 284 (SCA) ; [2001] 1 All SA 581 (A)
para 1.
11
performance under the contract from the party who repudiated the contract, nor
to further perform his own obligations under the contract, thereby resiling from
it. By accepting t he repudiation, the innocent party brings to an end the duty of
the parties to perform their primary obligations under the contract . The effect of
bring ing an end to the primary obligations is t he activat ion of certain secondary
obligations.11

[23] The application of the above contractual principles to the facts of this case
sustains a finding that SAP is entitled to rely on the exclusion of damages clause
and the time bar clause. When Global accepted the repudiation, it brought the
primary obligations of the parties to perform under the agreement to an end and
activated the secondary obligations.

[24] In the circumstances, t he exclusion of damages clause and the time bar
clause are not purposes of the agreement . They are secondary o bligations of the
agreement. As such, they survive d the termination of the agreement. That this is
so, is clear from the terms of the agreement, which indicated that these clauses
survive d termination. Article 17(13) itself, when read in context of the entire
agreement, makes this clear.

[25] Article 17( 13) provides for the survival of certain provisions of the
agreement after the termination of the agreement. It reads as follows:
‘Survival. Part 1 – Artic le 2 (Confidentiality) , Part 1 – Article 9 (Audit) , Part 1 – Article 11
(Effects of Termination) , Part 1 – Article 17 no. 1 (Retention of data) , Part 1 – Article 17 no. 4
(Partial Invalidity) , Part 1 – Article 17 no. 10 (Waiver of Jury Trial) , Part 2 – Article 1
(Limitation of Liability) , Part 2 – Article 2 (Third Party Claims) , Part 2 – Article 3
(Performance Warranty) , Part 2 – Article 4 (Reservation of title, rights and interest) , Part 2 –

11 Atteridgeville Town Council at 304B -D.
12
Article 12 (Governing Law and Jurisdiction) will survive any termination of any part of this
Agreement.’

[26] The survival clause refers to several clauses in the agreement , including
the limitation of liability clause. It expressly states that these clause s, ‘. . . will
survive any termination of any part of this Agreement ’. This can only be sensibly
interpreted to mean all types of termination, including termination as a result of
a repudiation. If the parties intended to exclude termination, there would have
been no need to include the word ‘any’ in Article 17(13). They would have simply
provided expressly for such an exclusion.

[27] There is accordingly no merit in the appellants ’ submission that the survival
clause only applies where the agreement is terminated on ‘good cause ’ in terms
of Article 10(2) thereof and not when it is repudiated. This much is evident from
Articles 10 and 11 of the agreement. In terms of Article 10(1) (a) a party may
terminate the agreement if the other party does n ot make payment on the due date.
Article 10(2) gives either party the right to terminate the agreement for ‘good
cause ’ (however, without limitation) for all the reasons cited in (a) to (f) thereo f,
including amongst others, repeated non -payment, material breach, insolvency,
change of control, etc.

[28] Article 11 then deals specifically with the effect of termination.
Articles 11(2) and (3) provide for the consequences that might follow on the
parties ’ rights in relation to , amongst others, thee use of intellectual property and
confidential information if an SAP PartnerEdge Model ‘is terminated, rescinded
or ended in any other way ’. Properly construed, the words ‘termin ate’ and
‘rescind ’ mean at the instance of either party. The words ‘ended in any other way ’
mean for every other conceivable end to the agreement. This would not be at
13
either party ’s instance but rather , should it be found to be unenforceable because
it is unlawful, void, etc.

[29] Article 11(4) provides that termination does not relieve SAP ’s partners
from their obligation to pay any fees that remain unpaid. Termination in this
context is clearly intended to include every termination, no matter how it occurs.
This would include ‘ended in any other way ’. As I see it, if the appellants ’
submissions are correct, namely, that a party cannot rely on any term of the
agreement once it has been terminated and that the termination of the agreement
can happen only for go od cause, it would render Article 11 meaningless.

[30] The appellants ’ contentions cannot be sustained for the further reason that ,
to interpret the agreement restrictively, as suggested by them, would undermine
the purpose of Articles 10, 11 and 17(13) or le ad to unbusinesslike results. It could
not have been the intention of the parties that a partner would, after the
termination of the agreement, for instance, be entitled to use SAP ’s trademarks,
documentation, other materials or confidential information. T hey specifically
agreed that those clauses would operate after the termination of the agreement.
The purpose of those clauses was to regulate what would happen to SAP ’s
products, logos and other trademarks and other material after the termination of
the ag reement.

[31] To reiterate, in Article 17(13) of Part 1, the survival clause, the parties
specifically agreed , inter alia , that Article 11 and the limitation of liability
provisions, inclusive of the concerned clauses, ‘. . . will survive any termination
of any part of this Agreement ’. Against the above interpretation of Articles 10, 11
and 17(13) of Part 1, I conclude , therefore, that the limitation of damages clause
and the time bar clau se survived the termination of the agreement. Since the se
clauses survived the termination of the agreement, SAP was entitled to rely on
14
them as a defence to claims for loss of profit s, which claims were instituted more
than one year from the date when the appellants knew or should have known,
after reasonable i nvestigations, of the facts giving rise to the claims. In the
circumstances, the appeal must fail.

[32] There is no reason why costs should not follow the result. Both parties
employed two counsel. Regard being had to the amount claimed and the issues
raised in the appeal , the employment of two counsel was a reasonable
precautionary measure taken by the parties .

[33] For the reasons set out above , the following order is made :
1 The appeal is dismissed
2 The first appellan t shall pay the respondent ’s costs, such costs to include
the costs of two counsel, where so employed.



____ ____________ ________ _
G H BLOEM
ACTING JUDGE OF APPEAL
15
Appearances

For the appellant s: A E Bham SC and I S Cloete
Instructed by: Stein Scop Attorneys Inc, Sandton
Honey Attorneys , Bloemfontein

For the respondent: M du P van der Nest SC and E van Heerden
Instructed by: Nortons Inc , Parkhurst
McIntyre van der Post , Bloemfontein