1
REPUBLIC OF SOUTH AFRJCA
'(!)'\.l>t,,,
~ 1-
.... ✓
- -;
,: -~ ,,. V /t ...ii ~
;, &.... .... ,,..._:.;;.'..a ~
~ ~
4 ( JJ \l "-\ ,,
IN THE HIGH COURT OF SOUTH AFRICA
LIMPOPO DIVISION, POLOKWANE
(1)
(2)
(3) REPORTAB LE: Yaie/NO
OF INTEREST TO THE JUDGES: Y~/NO
REVISED· Yli8/NO
,do ,l ?<> ?-5°
DATE............ SIGNATURE ..
In the matter between:
RISIMATI STEVEN CONSTRUCTION CC
(Registration number: 2002/023245/23)
and
UNIVERSITY OF VENDA
IN RE:
UNIVERSITY OF VENDA
and
RISIMATI STEVEN CONSTRUCTION CC
(Registration number: 2002/023245/23) CASE NO: 1872/2023
APPLICANT/DEFENDANT
RESPONDENT/ PLAINTIFF
PLAINTIFF
DEFENDANT
Heard
Delivered
Coram
Pjllay AJ
I ntroductjon: 2
16 October 2024
20 February 2025 by circulation to the parties' legal
representativ es
PILLAY AJ
JUDGEMENT
[1] The plaintiff instituted proceedings in the Limpopo High Court Polokwane for payment
of funds flowing from latent defects penalties and unlawful extensions of the contract
against the defendant. The summons was served on 28 February 2023. The
defendant filed a notice in terms of Rule 30A of the uniform rules of court. In terms of
this notice the defendant in the application sought the following orders;
[1.1] Setting aside of the plaintiff's combined summons as an irregular step.
[1.2] Costs of the application .
Brief Background:
[2] The parties entered into a service agreement in which the defendant was responsible
for the construction of a building called Health Sciences. A dispute between the parties
arose resulting in the defendant referring the dispute for arbitration. The appointed
arbitrator held pre-arbitration meetings with the parties to identify issues in dispute
3
between the parties and the procedure to be followed. At the onset the plaintiff
indicated that the issue pertaining to jurisdiction in so far as the authority of the
arbitrator needed ventilation , in relation to the disputed issues.
[3] Parties were directed to file written heads of argument in respect of the issue of
jurisdiction and the arbitrator's ruling was received on the 26 January 2023 wherein
the arbitrator ruled:
[3.1] The defendant's (plaintiff in these proceedings) jurisdictional objection is
dismissed .
[3.2) The parties are directed to attend a further pre-arbitration meeting to be held
on a date and time to be agreed with the parties and failing agreement on a
date and time as directed by the arbitrator.
[3.3] The defendant is ordered to pay the claimant's (defendant ) costs relating to the
defendant's jurisdictional objection (recording that this does not include any
cost of the arbitrator who was acting pro bono in this matter).
[4] At paragraph 61[1] the arbitrator indicated, "in the present case, applying the
aforementioned dicta, it seems to me that I have not yet "entered upon the reference "
and consequen tly the four-month period prescribed by section 23 of the arbitration act
has not yet commenced. The inquiry into the merits of the dispute referred to this
arbitration has not yet commenced(my underlining) . All that has occurred is a hearing
of the jurisdictional objection to obtaining a ruling as contemplated by article 24(1) of
the rules of the Association of arbitrators. "
4
[5] The plaintiff issued summons against the defendant on 28 February 2023 wherein
various claims for breach of contract and damages were sought. The summons was
served on the defendant on 1 March 2023. The defendant filed noticed of intention to
defend on 14 March 2023. The defendant thereafter brought an application in terms
of rule 30 A of the uniform rules of court, which was dated 29 March 2023, served on
the plaintiff on the 29 March 2023 and date stamped the 3 April 2023 by the registrar.
[6] The defendant served and filed the Rule 30 A (2) interlocutory application on the 9
May 2023. The defendant relying on the arbitrator's ruling, as being binding on the
parties, indicated that the combined summons constituted an irregular step, which
stood to be set aside. In support of this argument the defendant highlighted that the
plaintiff had not instituted a judicial review in relation to the arbitrators ruling which was
binding on the parties. The defendant noted that the ambit of the dispute as contained
in the combined summons was identical to the dispute that was to be determined in
the arbitration and therefore stood to be determined by the arbitrator, in the arbitration
proceedings. Therefore , the defendant sought that the summons be set aside on the
basis that it constituted an irregular step.
[7] The application was opposed and the plaintiff in its answering affidavit filed two points
in limine;
[7 .1] That the defendant failed to comply with the provisions of Rule 30 of the uniform
rules of court in light of the allegation that the issuing of the summons
constituted an irregular or improper step. The notice was brought in terms of
Rule 30(A), and the subsequent application in terms of Rule 30 (A) (2) of the
uniform rules of court. The relief sought by the defendant does not fall within
5
the ambit of Rule 30 (A). Amidst the allegations pertaining to an irregular step
which is dealt with under the provisions of Rule 30 the defendant was obliged
to comply with the rules applicable to the provisions of Rule 30(1) in respect of
notice prior to approaching the court. On this basis the application should be
dismissed with costs.
[7.2] That the application in terms of Rule 30(A)(2) was brought out of time without
the required application for condonation in terms of the rules. The defendant
served the notice in terms of Rule 30(A) on or about the 30 March 2023. The
contents of both the notice and the application seek relief provided for in terms
of Rule 30. Under Rule 30, the defendant ought to have brought the application
to set aside the summons on the grounds of irregular step within 15 days after
the expiry of the 10 days reserved for the plaintiff. The relief sought is in terms
of Rule 30 and as such the defendant was obliged to comply with the rule.
Therefore , the application should be dismissed with costs.
[8] In respect of the merits of the application , the plaintiff indicated that the issuing
summons is the institution of proceedings. Prior the summons there was no
proceedings. Therefore , the irregular step as alleged by the defendant , could not be
sustained if proceedings had not yet been instituted. The reliance on an irregular step,
under the provisions of Rule 30(A) is confusing and not clear, as to what process and
which rule the defendant sought to rely upon, in respect of the application and same
should be dismissed with cost.
[9] In respect of the arbitration proceedings , the plaintiff indicated that the arbitrator had
made a ruling in respect to jurisdiction only. That the allegation by the defendant that
6
there was a pending arbitration was an overstatement of the facts as a period of more
than a year has lapsed, since the referral by the defendant for arbitration , and to date
a statement of claim in the arbitration proceedings, had not yet been filed. The plaintiff
took note that the defendant conceded , that this court had jurisdiction, to entertain this
matter amidst the arbitration proceedings, however the defendant sought that this
court relinquish its jurisdiction, in favour of the arbitration process, which was
unsustainable . The circumstances of the plaintiff's case included claims for damages
flowing from the poor workmanship by the defendant which resulted in the contract
being terminated. The plaintiff had to employ other contractors to complete the work,
resulting in the issuing of the summons . The plaintiff indicated that nothing barred the
defendant from pursuing the arbitration proceedings especially as the time frame of
six weeks for the review process had lapsed and that after March2023 there was no
possibility to institute review proceedings as it was out of time.
[1 0] The plaintiff indicated that the date of the termination of the contract was 4 March
2020. That summons was issued shortly before the lapse of the three-year period
applicable for a claim to prescribe. There was no statement of claim that had the
potential to interrupt prescription and there was no claim for payment of damages on
account of latent defects, before any arbitrator for determination.
[11] The plaintiff noted that the contents of the written contract did not contain an
agreement between the parties that disputes pertaining to a claim for damages, after
the conclusion of the agreement, is to be the subject of arbitration. Clause 40.1 of the
agreement under the description of a disagreement, was not capable of including the
complaint by the plaintiff in respect of the various issues. This provision is not a bar to
7
the jurisdiction of this court and as such, the arbitration process cannot supersede this
litigation before this court.
[12] The plaintiff cited various case law in their heads of argument [2] supporting the point
that this court's jurisdiction was not barred from entertaining the matter and that the
process of arbitration did not oust this court of its jurisdiction. The plaintiff indicated
that a notice is not a pleading and as such the plaintiff was not prevented from serving
a notice of bar on the defendant, as a notice in terms of Rule 30A did not constitute a
pleading as contemplated in terms of Rule 22(1 ). The plaintiff cited various cases in
support of this argument.
[13] The plaintiff highlighted that the defendant failed to comply with Rule 30(2)(b). If the
defendant was relying upon the alleged irregular step, then when the summons was
served on the defendant on 1 March 2023, the defendant in compliance with Rule 30
had 1 0 days in which to serve the notice on the plaintiff on or about 15 March 2023.
The notice in terms of Rule 30 A was served on or about the 29 March 23. This was
out of time and not in compliance with the Rule 30. The defendant's admission of the
mistake seeking to blame the plaintiff for placing form above substance is misguided,
the defendant lost sight of the fact that in terms of our law and practice, the parties are
held strictly to the pleaded case. There was no application to amend nor was there
any application for condonation in respect of the non-compliance with the rules, in
respect of the time frames applicable to Rule 30, various cases were cited in
motivation of this argument [3]. It is for the above-mentioned reasons that the
application sought by the defendant should be dismissed with costs.
8
[14] In reply the defendant conceded that it had mistakenly referenced Rule(30)(A) and
Rule(30)(A)(2) of the uniform rules of court in its notice to remove the cause of
complaint, and subsequent irregular step application. The defendant submitted that at
all material times, the substance of the defendant's complaint was clear and
unambiguous. The defendant indicated that it was impermissible to place form over
substance, and that the technical argument raised by the plaintiff was baseless. The
defendant drew the courts attention to the various case law pertaining to the fact that
litigation was not a game [4], and that the plaintiff was well aware of the nature of the
complaint, and the case that the plaintiff had to meet. The plaintiff was not prejudiced
by the incorrect reference to Rule 30(A) instead of Rule 30. This point in limine should
be rejected as it has no merit.
[15] The defendant highlighted that it complied with the timelines provided for in an
application for an irregular step. On or about 29 March 2023 the defendant served and
filed its notice to remove cause of complaint which was within time and thus the
defendant need not seek condonation. The defendant indicated that because of the
public holiday on the 21 March 2023, the notice was filed within the court timelines and
this point should also be dismissed.
[16] The defendant indicated that the issue was whether this court should proceed to
consider this matter in light of, the ongoing arbitration proceedings between the
parties, and the award made by the arbitrator, which was binding on the parties, unless
it is set aside in review proceedings. The defendant sought that this court decline to
exercise its inherent jurisdictio n to entertain this matter.
9
[17] According to the defendant the plaintiff had sought to institute a judicial review in
relation to the arbitration ruling, and that the arbitration proceedings were stayed,
pending the finalisation of this ruling, and therefore the defendant had not filed a
statement of case.
[18] The defendant drew the courts attention to the various case law [5] concerning the
sanctity of contracts and the arbitration process, and why this court should be reluctant
to interfere, in light of the fact that, the parties had agreed to the arbitration route, as
a means of resolving their dispute. The plaintiff had only one option and that was to
institute review proceeding , if the plaintiff wished to challenge the jurisdictional ruling
of the arbitrator. The plaintiffs election to institute this proceeding , constituted an
irregular step, by ignoring the very agreement to resolve the disputes by arbitration
proceedings. In the premise the plaintiff's combined summons stands to be set aside
as an irregular step, and the defendant be awarded costs in respect of this application .
The Issues to be considered:
[19.1] Whether the plaintiff summons served on the defendant constituted an irregular step
or proceedings under Rule 30A of the uniform rules of court.
[19.2] Whether the arbitration proceedings, and the agreement by the parties to refer the
proceedings to arbitration , oust the jurisdiction of this court.
[19.3] Whether the defendant correctly applied Rule 30 A for the relief sought under Rule 30
and whether these two rules are interchangeable , and whether the procedural
requirements for Rule 30A and or Rule 30 were complied with.
[19.4) Whether the plaintiffs claim should be struck off based on the provisions of Rule 30A.
10
Legal Principles and its Applicab ility:
[20] Rule 30A of the Uniform Rules of Court: Non-compliance with Rules and Court Orders
(1) Where a party fails to comply with these Rules or with a request made or notice
given pursuant thereto, or with an order or direction made by a court or in a judicial
case management process referred to in rule 37 A, any other party may notify the
defaulting party that he or she intends, after the lapse of 10 days from the date of
delivery of such notification , to apply for an order--
(a) that such rule, notice, request, order or direction be complied with; or
(b) that the claim or defence be struck out.
(2) Where a party fails to comply within the period of 10 days contemplated in subrule
(1 }, application may on notice be made to the court and the court may make such
order thereon as it deems fit.
[21] Rule 30 of the Uniform Rules of Court: Irregular proceedings
(1) A party to a cause in which an irregular step has been taken by any other party may
apply to court to set it aside.
(2) An application in terms of subrule (1) shall be on notice to all parties specifying
particulars of the irregularity or impropriety alleged, and may be made only if.-
( a) the applicant has not himself taken a further step in the cause with
knowledge of the irregularity .
(b) the applicant has, within 10 days of becoming aware of the step, by
written notice afforded his opponent an opportunity of removing the
cause of complaint within 10 days.
(c) the application is delivered within 15 days after the expiry of the
second period mentioned in paragraph(b) of subrule (2).
(3) If at the hearing of such application the court is of opinion that the proceeding or step
is irregular or improper, it may set it aside in whole or in part, either as against all the
11
parties or as against some of them, and grant leave to amend or make any such
order as to it seems meet.
(4) Until a party has complied with any order of court made against him in terms of this
rule, he shall not take any further step in the cause, save to apply for an extension of
time within which to comply with such order.
[22] In Afrocentrics Projects and Services (Pty) Ltd tla Innovative Distribution v State
Information Technology Agency (SITA) SOC Ltd and Others [6], the Constitutional
Court placed the purport of Rule 30 in context where it said:
"[26} Rule 30(3) contemplates a two-stage process. A court must first satisfy itself
that the proceedin g or step is irregular or improper. If it is so satisfied, it has the
wide power to set the proceeding aside in its entirety or in part, grant leave to
amend or make any order as it deems fit. These are, no doubt, wide powers.
Following its conclusion that a step or proceeding is irregular or improper, a
court however, is required to make an order.
[23] As noted above, this court must first determine when considering the
application sought by the defendant , that the proceedings or step was irregular or
improper in terms of Rule 30(3). Before this court can ventilate this issue it needs to
have regard to the said notice. Both Rule 30 and Rule 30A makes provision for
various steps and dies to be complied with before the consequential orders will follow.
The defendant correctly concedes that its notice was in terms of Rule 30 A, although
the procedure as contained in Rule 30 A was not complied with. The defendant
indicates that it sought to proceed in terms of Rule 30 utilising the procedure as
contained in Rule 30. It is clear from the concession made, that the defendant
interchanged the two processes with the heading of one and the procedure of another.
Instead of seeking an amendment to fix the conundrum , in so far as which rule was
12
being sought to be relied upon, the defendant required this court to disregard the
points in limine as raised by the plaintiff, as being inconsequential, and to consider
substance above form. This unfortunately is not the circumstances when dealing with
Rule 30 proceedings .
(24) In Bloem and Another v NWK Limited (7) The court noted the following:
"The Uniform Rules seek to regulate procedure (form) and not substance. Any
complaint raised in terms of Rule 30 therefore speaks to an alleged procedural
irregularity in the conduct of the litigation. It therefore follows axiomatically that if a
court finds that the procedural steps taken by a party were irregular, a court is
vested with wide powers to either set aside the proceeding in its entirety or in part or
make any other order the Court may deem fit. The order which will generally follow in
applications of this nature, if a court finds a particular step to be irregular, is to afford
the party against whom the complaint is raised an opportunity to remove the cause of
complaint. "
(25) The defendant fails to consider the fact that a party stands or falls by their papers, and
curing of the application and founding affidavit, cannot be done in reply especially as
both these rules refer to specific time frames, to be complied with. Rule 30A (2) speaks
of 1 0 days whilst Rule 30(2) speaks of three different time frames to be complied with
before the irregular proceedings complained of, will be ventilated by court. The court
took note of the discrepanc ies in respect of the dies, with specific reference to when
notice of the irregular step, was to be brought to the attention of the opponent. I
align myself with the plaintiff's argument that the defendant had received the
summons, which is alleged to be the irregular step, on the 1 March 2023. The Rule
13
30(1) ten-day period was due on the 15 March 2023, same was only issued on the
29 March 2023, in noncompliance with the Rule 30 procedure . The application was
defective without an application to amend as well as an application for condonation.
On this basis alone this application stands to fail.
[26] In respects of the merits of this application regard was had to the record of
proceedings in the arbitration . The arbitrator had to adjudicate an ancillary issue
concerning jurisdiction. At paragraph 61 [1] the arbitrator indicated, "in the present
case, applying the aforementioned dicta, it seems to me that I have not yet "entered
upon the reference" and consequently the four-month period prescribed by section 23
of the arbitration act has not yet commenced. The inquiry into the merits of the dispute
referred to this arbitration has not vet commenced (my underlying). All that has
occurred is a hearing of the jurisdictional objection to obtaining a ruling as
contemplated by article 24(1) of the rules of the Association of arbitrators. "
[27] From the plain reading of this ruling the merits of the dispute were not entertained and
any rulings made thereon. Moreover, the defendant conceded that it had not filed its
statement of case yet, and blamed the plaintiff for this delay, as it was accommodating
the plaintiff's review application. This argument cannot hold weight, as the six-week
time frame had long lapsed, with nothing being done by the plaintiff, allowing the
defendant to approach the arbitrator, for another pre arbitration date to be set. This
was not done. Moreover, as indicated the arbitration proceedings was still in the early
stages and there is nothing preventing the parties from pursuing this route. However,
had the plaintiff not instituted the combined summons , the claim for damages would
most likely have prescribed , and because of the early stages of this arbitration
14
proceedings no protection could be afforded the plaintiff for the alleged damages
claim.
[28] In Aveng (Africa)Ltd formally Grinaker-LTA Ltd tla Grinakar-LTA Building East v
Midros lnverstments (Pty)Ltd [BJ the court held as follows;
"It is now well-established that an arbitration agreement does not oust the jurisdiction
of the courts. 1 Where a party to an arbitration agreement commences legal
proceedings against the other party to that agreement , the defendant is entitled
either to apply for a stay of the proceedings pursuant to s 6 of the Arbitration Act 42
of 1965 or to deliver a special plea relying upon the arbitration clause. Whichever
course it adopts the onus then rests on the claimant to persuade the court to
exercise its discretion to refuse arbitration . This requires a very strong case to be
made out."
[29] The court takes note of the argument raised by the plaintiff in respect to the entitlement
of the defendant to file a special plea wherein this issue of the Jurisdiction of this court
could be ventilated in so far as the pleadings is concerned . The defendant there would
also be afforded the opportunity to plead to the merits as well as to pray that these
proceedings , be stayed pending the outcome of the arbitration process.
[30] From the papers before this court, the irregular step process that was sought by the
defendant in this application , were riddled with too many errors which were unable to
be cured and were not technical. It is for those above-mentioned reasons that this
application sought by the defendant in respect of having the plaintiff's combined
summons set aside as an irregular step must fail.
1 The Rhodesian Railways Limitedv Mackintosh 1932 AD 359 at 375.
15
Costs
[31] It is by normal course that costs follow the successful party, and there is no reason to
order differently. During arguments the defendant sought costs on high court scale C
if successful in having its application granted. The plaintiff in response sought costs
for the two counsel on high court scale C and argued that the matter was intricate, to
justify the services of two counsel. It is for the above reason that cost will be awarded
to the successful party as sought in both parties address to court.
Order:
[32.1] The Application sought by the Defendant to set aside the Plaintiff's Combined
Summons as an irregular step is dismissed.
[32.2] The Defendant is ordered to pay the cost of the Application which includes costs of
two counsel on High Court scale C.
APPEARANCES
FOR THE APPLICANT/ DEFENDANT :
INSTRUCTED BY
FOR THE RESPONDENT/ PLAINTIFF :
INSTRUCTED BY
DATE OF HEARING PILLAY KL
ACTING JUDGE OF THE HIGH COURT,
POLOKWANE; LIMPOPO DIVISION
Adv AJ Glendinning
E Taylor Attorneys
Adv MM Mojapelo SC and Adv R Sibara
Mphaphuli Mudzunga Tshinetsise Attorneys
16 October 2024
16
DATE OF JUDGEMENT: 20 February 2024
(1) See page 115 of the documents attached to the founding affidavit.
(2) See page 12 to 14: Aveng(Africa) Ltd formerly Grinaker-L TA ltd tla Grinaker-L TA Building East v Midros Investments
(Pty)Ltd 2011 (3)SA 631 (KZD; Transnet Durban(pty)ltd v e Thekwini Municipality and Another 2024JDR 0087 (KZD).
(3) See page20 to 21: Mand M Quantity Surveyors (C v Ovall Corporate Designs (Pty)Ltd (84202119) [2021JZAGPPHC
343;Bester N.O and Others v Target Brand Orchards (Pty)Ltd and Others [2020}ZAWCHC183 .
(4) See page 11 and 12 of HOA of Defendant: Nieuwoudt v Joubert 1988(3) SA 84; Cadac (PTY)L TD v Weber -Stephen
Products Co and Others [2010JZASCA 10; ABSA Limited v Cromet[2020]JOL 53247.
(5) See pages 14 to 22 of heads of argument of the defendant .
[6] [2023) ZACC 2
[7J (75012021) [2024) ZANWHC 83 (20 March 2024)
(8) 2011 (3) SA 631(KZD)