About SAFLII
Databases
Search
Terms of Use
RSS Feeds
South Africa: Johannesburg Labour Court, Johannesburg
SAFLII
>>
Databases
>>
South Africa: Johannesburg Labour Court, Johannesburg
>>
2018
>>
[2018] ZALCJHB 350
|
|
Armaments Corporation of South Africa (Pty) Ltd v Commission for Conciliation, Mediation and Arbitration and Others (JR 42/2016) [2018] ZALCJHB 350 (30 October 2018)
IN
THE LABOUR COURT OF SOUTH AFRICA, JOHANNESBURG
Not
Reportable
Case
no: JR 42/2016
In the
matter between:
ARMAMENTS
CORPORATION OF
SOUTH
AFRICA (SOC) LTD Applicant
and
COMMISSION FOR
CONCILIATION
MEDIATION AND
ARBITRATION First
Respondent
L DEKKER
N.O
Second
Respondent
SOLIDARITY Third
Respondent
KRIGE GERHARDUS
BREEDT Fourth
Respondent
Heard: 23
November 2017
Delivered:
30 October 2018
JUDGMENT
TLHOTLHALEMAJE,
J:
Introduction and
background:
[1] The applicant
(Armscor), seeks an order reviewing and setting aside the arbitration
award dated 11 December 2015 issued
by the second
respondent (Commissioner) acting under the auspices of the first
respondent, the Commission for Conciliation Mediation
and Arbitration
(CCMA). In the arbitration award, which followed upon a referral of
an alleged unfair dismissal dispute by the
third respondent
(Solidarity) on behalf of the fourth respondent (Breedt), the
Commissioner found that the dismissal of Breedt
by Armscor was
procedurally fair but substantively unfair.
[2] The Commissioner
ordered that Breedt be reinstated effective from 22 October 2014 with
backpay in the amount of R720 000.00,
and that he be issued with
a final written warning effective for 12 months. Breedt’s claim
of a performance bonus for the
financial year 2013/2014 was
dismissed. The review application is opposed.
[3] Armscor is a
public entity created in terms of the Armaments Corporation of South
Africa Limited Act
[1]
and Schedule 2 of the Public Finance Management Act
[2]
(The PFMA), and is mandated to
inter alia
, service the
National Department of Defence with regard to programme management
and acquisition of goods and services for the South
African National
Defence Force (SANDF).
[4] Breedt was
employed with effect from January 1989 and had 25 years of service at
the time of his dismissal. He was based at
Armscor’s premises
in Erasmuskloof, Pretoria and had occupied the position of Technical
Manager/Armscor Programme Manager
(APM). He was effectively the
Project Manager responsible for the management and technical aspects
of procurements contracts on
behalf of Armscor. In accordance with
his position, it was expected of Breedt to conduct prescribed tender
evaluation procedures
in a professional, fair, equitable,
transparent, competitive and cost effective manner, and to strictly
observe protocol and demonstrate
ethical and professional conduct
from the moment the Request for Offer (RFO) was issued, until a
contract was awarded to a successful
bidder.
[5] Armscor has in
place, policies, practices, procurement structures and procedures
that ought to be observed and followed in ensuring
that procurement
processes were at all times fair and transparent. The relevant rules
and practices forming the basis upon which
Breedt was charged and
dismissed are the Disciplinary Practice; the Practice for the
Selection of Contractual Sources; the Contract
Management Practice;
the Rules Applicable to Prospective Contractors, and the BBBEE
Practice.
[6] Breedt was
dismissed on 22 October 2014 following upon a disciplinary
enquiry into allegations of misconduct. According
to Armscor, the
incidents alleged essentially boiled down to a manipulation of its
tender-evaluation processes by Breedt in favour
of a bidder. The
allegations against him were;
Charge
1:
You conducted
yourself in a grossly irregular, improper and unethical manner by
directly communicating with Fire Raiders (Pty) Ltd,
an offeror for a
RFO-ESPV/2013/392 during the tender process. Your inappropriate
communication was about the significant aspects
of the tendering
process. Your conduct was in breach of clause 5.5.1.3 of the Armscor
Practice for the Selection of Contractual
Sources, A-Prac 1034, Issue
002 and A-Pac 1020 clause 4.5 and 4.7, Issue 001. In terms of the
clause, which you are aware of, you
were required to demonstrate
ethical and professional conduct by avoiding communicating with the
offerors you were obliged to do
so through a bidders conference or
via the Procurement Secretariat. Your conduct was in breach of
Armscor’s standard procedure
and is viewed as a serious
offence.
Charge
2:
You conducted
yourself in a grossly irregular, improper and unacceptable manner in
that you deliberately deviated from Armscor’s
standard practice
by soliciting the BEE Certificate from Fire Raiders (Pty) Ltd outside
the tender process and inserted the same
in the tender documents and
you used the same certificate to compile the BEE score card and gave
an incorrect impression that the
new BBBEE Certificate was duly
submitted with the offer by inserting such certificate in the tender
file.
Charge
3:
You conducted
yourself in a grossly irregular, improper and unacceptable manner by
manipulating the tendering process in favour
of Fire Raiders (Pty)
Ltd in that you;
a)
Communicated directly
with Fire Raiders (Pty) Ltd to obtain reference details while the
evaluation process was in progress, consequently
misleading the
evaluation team about the information on references hence Fire
Raiders (Pty) Ltd was successfully evaluated to comply
with the
critical criteria;
b)
Extended the closing date
without sound factual reasons but at the request of the offeror;
c)
Delaying the BBBEE
balanced score sign off for about six weeks pending the finalisation
of an inappropriately obtained certificate
by Fire Raiders (Pty) Ltd
and,
d)
Used the inappropriately
obtained certificate to compile the BBBEE balanced score card on
behalf of the BEE Division
[7] The charges
originated in April 2014 when the Black Economic Empowerment
Division of Armscor embarked on a process of considering
and
evaluating offers for compliance with the BEE requirements in respect
of Tender 392 that Fire Raiders had submitted its bid.
The BEE
division had reason to believe that the official tender documents in
respect of that tender may have been tampered with
after its closing
date. Armscor’s Internal Audit Division was then requested to
investigate the matter, and it had made certain
findings and issued a
report which had led to the above-mentioned charges against Breedt.
[8] It was common
cause that Breedt had at the internal disciplinary enquiry, which
took place over nine days, partially pleaded
guilty to charge 3(a)
related to communicating with Fire Raiders (Pty) Ltd to obtain
reference details whilst the evaluation of
the tender in question was
in progress. He had nonetheless disputed the other part of that
charge and all the others. The chairperson
of the enquiry had not
made a ruling in respect of charge 1 as a stand-alone charge, as it
was bound up with the other charges.
Breedt was however found guilty
on charges 2 and 3.
[9] The matter
having been referred to the CCMA, the arbitration proceedings took
place over 8 days between June and November 2015.
The record of
the arbitration proceedings contains some 3 500 pages and the
Commissioner’s arbitration award is some
72 pages long. Other
than the extensive record of the disciplinary proceedings which the
parties had agreed constituted a correct
reflection of what had
transpired in those proceedings, evidence was also led at the
arbitration proceedings, which was followed
by equally extensive
written heads of arguments submitted at the conclusion of those
proceedings.
[10] In these
proceedings, Armscor took issue with the manner with which the
Commissioner’s arbitration award was crafted.
This was in
circumstances where it was agreed between the parties at the
conclusion of the arbitration proceedings that written
heads of
argument were to be submitted in editable word format, to enable the
Commissioner to cut and paste from. I share Armscor’s
concerns
that the award is indeed unusually crafted, and it must be added that
it is definitely not meant for easy reading. The
Commissioner had
merely cut and pasted large portions of the parties’ written
heads of argument rather than summarising them.
By way of example,
Armscor also made reference to paragraph 26 of the arbitration award
consisting of ten pages made up of 9½
pages cut and pasted
from the heads of argument, and from which half a page consisted of
the Commissioner’s findings. A further
example is that in some
instances, the cut and pasted portion in the award would refer to
certain paragraphs which the Commissioner
had omitted to restate,
leading to a position where this cross-referencing did not make sense
to the reader
[3]
.
[11] One appreciates
the voluminous nature of the record and the evidence the Commissioner
was expected to sift through in an attempt
to make sense of the
merits of the matter. At the most though, it would have been expected
of him to make an attempt in the award,
to enable the reader to
distinguish between what his own summary and assessment of the
evidence and the arguments were, from the
copied and pasted portions.
Reading through the 72 paged award in order to make sense of the
Commissioner’s reasoning at
most times proved to be a challenge
because of that omission, and these concerns cannot simply be
dismissed as clutching at straws
as argued on behalf of Breedt and
Solidarity.
[12] To put the
allegations against Breedt into context, the relevant procurement
structures and processes at Armscor are that;
a) The Procurement
Secretariat compiles, despatches and receives feedback from the
Request for Offer (RFO) according to specific
strictly controlled
tender procedures.
b) Upon receipt of
tenders by the Procurement Secretariat, the tenders are opened,
registered and forwarded to the APM (Breedt).
c) The APM would be
responsible for compiling a schedule comparing the tenders in order
to facilitate their evaluation.
d) The APM is also
responsible for compiling a BEE scorecard (which is based on the BEE
certificate submitted with the tender).
e) The BEE Division
is responsible for verifying those scores.
f) The collated
information would then be presented before the evaluation committee,
which in turn undertakes the evaluation and
thereafter recommends a
successful bidder/contractor.
g) The
recommendation guides the APM’s submissions, which would then
be authorised by the Authorisation Committee. Upon that
authorisation, a contract would then be concluded with the successful
bidder.
[13] From the
charges as they were preferred, the Commissioner captured their
essence as being that Breedt was accused of having
conducted himself
in a grossly irregular, improper and unacceptable manner by
manipulating Tender 392 process in favour of Fire
Raiders, in respect
of three aspects,
viz
;
i. Extension of the
closing date of the tender
ii. Direct
communication with Fire Raiders, and
iii. Obtaining
(solicitation) and use of BEE Certificate
[14] It is accepted
that all the charges emanate from the events surrounding Tender 392.
Flowing from the award, Armscor relies
on four main grounds in
seeking that it be reviewed and set aside,
viz
:
a) That the
Commissioner misconstrued the charges;
b) Misconstrued the
inquiry and the evidence;
c) His conduct gave
rise to a reasonable apprehension of bias; and
d) Had committed
various factual errors and misdirections in his assessment of the
evidence, the distorting effect of which was
the production of an
unreasonable result.
[15] Submissions
made on behalf of Breedt and Solidarity were to the effect that
Armscor’s grounds of review are akin to an
appeal; that Armscor
could not simply attempt to dissect the arbitration award and try and
make out a case; that this Court will
not approach the review
application on a piecemeal basis
[4]
;
and that no case had been made out to support the review application.
[16] The test on
review is trite. It is whether the
Commissioner’s
decision was one to which no reasonable arbitrator could come
[5]
.
In the light of the opposing contentions in this case, specifically
where an allegation is made that the commissioner failed to have
regard to, or had ignored certain material evidence
,
the principles stated in
Gold Fields Mining South Africa
(Pty) Ltd v CCMA (Gold Fields)
remains apposite,
i.e
.;
‘
Where
the arbitrator fails to have regard to the material facts it is
likely that he or she will fail to arrive at a reasonable
decision.
Where the arbitrator fails to follow proper process he or she may
produce an unreasonable outcome. But again, this is
considered on the
totality of the evidence not on a fragmented piecemeal analysis. As
soon as it is done in a piecemeal fashion,
the evaluation of the
decision arrived at by the arbitrator assumes the form of an appeal.
A fragmented analysis rather than a
broad based evaluation of the
totality of the evidence defeats review as a process. It follows that
an argument to the failure
to have regard to material facts have
potential result in a wrong decision has no place in review
applications. Failure to have
regard to material facts must actually
defeat the constitution imperative that the award must be rational
and reasonable –
there is no room for conjecture and guess
work.’
[6]
[17] In
Belloord
28 CC v CCMA Johannesburg and Another
[7]
,
Van Niekerk J having considered the review test as restated in
Head
of the Department of Education v Mofokeng and Others,
[8]
further summarised the test as follows;
“
[10]
What this analysis
requires is that the review court determine first whether the
arbitrator perpetrated any ‘defect’
or irregularity
contemplated by s 145 (2). Secondly, the court must have regard to
the distorting effect that the error may have
had on the outcome of
the arbitrator’s award. Thirdly, if it is reasonably clear that
but for the identified error relied
upon the award would have been
different or cannot stand on its own reasoning, then the award is
prima facie
an unreasonable award. Finally, the court must have regard to the
issues and the evidence as a whole to determine whether or not
the
outcome is nevertheless capable of being sustained on the
Sidumo
test. Put more plainly, the review court must ask whether but for the
defect, a reasonable decision-maker could have come to the
conclusion
reached in the award on the same material.”
[18] Armscor has
identified various aspects of the evidence placed before the
Commissioner which it contends he had ignored or failed
to evaluate,
thus leading to an unreasonable outcome. The essence of Armscor’s
pleaded complaint is that the Commissioner
construed in particular,
charge 3 against Breedt too narrowly by focusing on its paragraphs
(a) to (d) and ignored the substance
of the charge, which was that
Breedt had engaged in manipulating the tendering process in favour of
Fire Raiders. To the extent
that the Commissioner had done so, it was
submitted that he had effectively misconstrued the nature of the
enquiry and watered
down the severity of the charges, both of which
constitute reviewable irregularities.
The evidence, the
Commissioner’s conclusions and evaluation:
[19] For the sake of
expedience, I will deal with the evidence presented at the
arbitration proceedings in respect of each individual
charge, the
Commissioner’s conclusions, the parties’ submissions, and
evaluate these accordingly. This approach bears
in mind that to a
large extent, the principal complaint remains that that Breedt had
manipulated the tendering process in favour
of Fire Raiders. In
addition, I will refer to the evidence led at the arbitration
proceedings and the disciplinary enquiry in general
terms, and where
necessary, and to the extent that there were material disputes of
fact, I will specifically refer to witnesses’
testimony.
The allegations
pertaining to the extension of the closing date of the tender:
[20] The conclusions
of the Commissioner in regard to this charge are not seriously
challenged by Armscor. However, by way of further
background, it was
common cause that in 2011, Fire Raiders was awarded a three-year
contract (Tender KT026) related to the repair
of SANDF’s fire
and rescue vehicles. That contract was supervised by Breedt, who had
also authorised its payments. On 12 December 2013,
the same
contract, valued at R45m over three years, was put out to tender
(EVSPV/2013/329, Referred to as ‘Tender 329’).
The
closing date was set as 20 January 2014. On
20 December 2013, Fire Raiders had requested a copy of the
tender, which was sent to it on 23 December 2013.
[21] On
7 January 2014, Fire Raiders sent an email to Procurement
Secretariat requesting an extension of the closing date
from
20 January 2014 to 14 February 2014 due to the
company having closed during the Christmas season. Breedt
had on
8 January 2014, approved the extension of the closing date
to 14 February 2014.
[22] On
14 February 2014, Fire Raiders had then submitted its bid
for tender documents. The required BEE Certificate accompanying
the
bid had expired on 28 January 2014. Attached to the bid however
was a BEE Audit Request confirming that a request for
a new BEE
Certificate was in progress. Upon its submission, this tender was
perforated, to ensure that new documents could not
be added to the
file once the tender was received and closed.
[23] On the same
date that the tender was received, Fire Raiders’ 2011 contract
came to an end, and Breedt had authorised
payments in respect of the
final invoice submitted. Fire Raiders followed their original bid for
the new tender with further correspondence
on 18 February 2014,
and submitted a BEE verification certificate issued on
14 February 2014, which was valid
until 13 February 2015.
[24] At the
arbitration proceedings, it was not in dispute that Breedt had the
necessary authority to grant the extension of the
closing date.
Armscor however questioned whether Breedt had applied his mind prior
to granting the extension, as it was not clear
whether he had
interrogated the reasons the extension was sought. Armscor further
pointed out that Breedt in granting the extension
had not sought the
consent of the client (SANDF), and had not considered or determined a
reasonable duration of the extension in
view of the client having
regarded the matter as urgent. According to Armscor, and further
based on the conclusions reached by
the chairperson of the
disciplinary enquiry, the real reason that Fire Raiders sought an
extension was that its BEE certificate
had expired at the closing
date of the tender, and it was therefore merely buying time.
[25] The
Commissioner’s conclusions in regard to the transgression was
that it could not be found that the granting of an
extension to Fire
Raiders was part of a manipulation of the tender process in respect
of Tender 239 on the grounds
inter alia
that Breedt had the
authority to consider the request.
[26] In opposing the
this review application, Breedt contends that the Commissioner’s
conclusions and reasoning in regards
to the charge in question cannot
be faulted. Armscor, as it was correctly pointed out on behalf of
Breedt, does not in its pleadings
or submissions, appear to contest
the Commissioner’s conclusions with any vigour or at all.
Allegations
pertaining to Direct Communication with Fire Raiders:
[27] Armscor further
contested the Commissioner’s findings in regards to the
allegation that Breedt had directly communicated
with Fire Raiders
during the tender process, which conduct it regarded as improper and
contrary to standing rules and procedures
[9]
.
The specific rules in this regard are Paragraph 4.7 of Armscor
Contract Management Practice in this regard provides that;
“
Conduct
Pre-Contract Negotiations/Discussions
In
terms of proper business ethics Armscor personnel are not allowed to
have any discussions with any contractor in a multi-source
situation,
from the time the RFO has been issued until the committee has
authorised the order.”
[28] A further
provision is clause 5.3.1.3 of the BBBEE Practice, which states that;
“
Companies
with active orders must be monitored on a quarterly basis to ensure
that they have valid verification certificates and
that they hold on
to or improve their level of compliance. A supplier must be remined
to submit new certificate at least three
months before the expiry of
the current one. Companies whose certificates have expired must be
notified and requested to remedy
the situation within a period of 60
days, failing which payments could be withheld until breach is
certified”
[29] Two sets of
facts are related to this alleged transgression. The first is that
Fire Raiders and another entity (Marce Projects)
had submitted their
bids for the same Tender 392. One of the critical requirements was
that the bidder must submit written proof
of how long it had serviced
the fire fighting vehicle maintenance/repair business. A reference
list with contact details of clients
serviced should be provided for
Armscor to contact, and written proof must be submitted in that
regard.
[30] Fire Raiders
had submitted a list of previous clients without their contact
details. Outstanding information in regard to Marce
Projects
pertained to confirmation of previous work done with its other
clients. The Critical Criteria Evaluation Committee held
its meeting
on 17 March 2014, and Breedt’s task flowing from that
meeting was to obtain the outstanding information
(references) from
the bidders
via
the Procurement Secretariat. Breedt had
however directly contacted the Director of Fire Raiders, Mr. Hans
Muller by telephone to
seek the outstanding information. Muller had
responded in an email on the same date confirming the telephonic
communication with
Breedt and had provided the information. Breedt
had in turn forwarded the information to the Procurement Secretariat,
further stating
in his email that the information was urgent and that
an urgent response would be appreciated.
[31] Armscor’s
case was that the telephonic communication with Fire Raiders was in
breach of the no contact rule, and that
the provision of references
was a ‘critical criteria’, the absence of which ought to
technically have excluded/disqualified
Fire Raiders from the bidding
process. It was further pointed out that despite the outstanding
information, Breedt had curiously
on 12 March 2014,
compiled his functionality criteria scoring sheet, indicating that
Fire Raiders had complied with that
criteria, when that was not the
case. Armscor had contended that Breedt had a propensity to break the
rules when it came to Fire
Raiders, and had a cosy relationship with
that entity.
[32] Breedt had
acknowledged that he was in the wrong by directly contacting Muller,
contending that he did so in order to safe
time. He had apologised
for his conduct and pointed out that in the past, two other employees
were issued with final written warnings
for similar misconduct. He
had denied that he had misled the panel with the submission that Fire
Raiders complied with the functionality
criteria when that was not
the case. His contention was that he had given Fire Raiders the
benefit of the doubt as it had executed
similar work for SANDF
via
Armscor in the previous six years. This he had contended, was
permissible under the provisions of Practice for the Selection of
Contractual Sources.
[33] The
Commissioner in regard to this charge concluded that a final written
warning in accordance with Armscor’s Disciplinary
Practice
[10]
was the appropriate sanction for the following reasons;
a) Breedt had
acknowledged that he had directly contacted Fire Raiders to obtain
further information required, in circumstances
where he as acting
secretary of the Critical Evaluation Committee, had recorded that the
bidder should be contacted via the Procurement
Secretariat. Breedt
had however disregarded his own instruction and Armscor’s
policies.
b) Breedt’s
explanation that he had contacted the bidder in order to safe time
was not acceptable.
c) There was however
no evidence to suggest that Breedt had misled the Critical Evaluation
Committee when he indicated that Fire
Raider’s bid complied
with critical criteria, as the same information was still outstanding
from Marce, which was bidding
for the same contract.
[34] Again, from
Armscor’s pleaded case and heads of arguments, it does not
appear that the Commissioner’s conclusions
in regard to this
charge are contested.
[35] Central to
Armscor’s complaints is the second set of facts in regard to
direct communication with Fire Raiders, which
pertained to Breedt’s
exchange of various emails with Muller between 10 February 2014
and 26 March 2014.
Armscor viewed the conduct as highly
irregular and contrary to standing rules and practices, as the
exchange of emails was part
of the attempts to solicit a BEE
Certificate from Fire Raiders outside of the tender process, and thus
constituting a manipulation
of the process.
[36] It is not
necessary to re-state the full contents of the emails, other than to
point out that the exchanges made references
to one ‘Prince’,
an employee of Fire Raiders who was responsible for obtaining BEE
certificates through Cenfed (A Sanas
registered BEE verification
agency that produces BEE certificates); the fact that Breedt had not
heard from Prince; Breedt enquiring
about the progress in that
regard; and Muller’s invitation to Breedt to have coffee/tea.
[37] To recap, Fire
Raiders had submitted the first BEE verification certificate on
14 February 2014 which had expired.
A second BEE
certificate was submitted on 18 February 2014. A third
certificate dated 1 April 2014 was hand
delivered to
Armscor on 2 April 2014 in an envelope marked for the
attention of Breedt and Van Zyl.
[38] Armscor’s
case was that the exchange of emails with Muller was highly
irregular, as information from bidders could not
be solicited outside
of the tender process, nor could there be communication with bidders
during that process. Breedt’s explanation
however was that the
communication was merely in regard to obtaining a valid BEE
certificate from Fire Raiders in order to close
down the old contract
(KT542026) and effect any outstanding payments as was required by
Armscor’s policies. He had testified
that due to Armscor’s
slow administrative processes, the closing down of the old contract
was delayed for several months
after the final delivery date in
February 2014. He had referred to the email of 24 March 2014
he had sent to Muller,
which made reference to ‘
IV for Samil
50 that was delivered”
, which were code names for Issue
Voucher and a type of military vehicle, which all related to the old
contract. His contention
was that the communication was permissible
within the context of Armscor’s BEE Practice, and further that
he had displayed
discretion and avoided communication with one Mr.
Trevor Fiford, Fire Raiders’ Managing Director, who was
responsible for
signing the new tender documents on its behalf.
[39] Armscor however
contended that the emails could not have been related to the 2011
contract as it had expired on 14 February 2014,
and since
its last payment was authorised by Breedt on 17 February 2014.
In that regard, evidence was led to demonstrate
that Fire Raiders
presented its last invoice for the 2011 contract, which had indicated
an overspending on that contract. That
overspending was cleared
through credit notes issued by Fire Raiders on 14 February 2014
and passed the following day,
resulting in payment being authorised
and made on 17 February 2014.
[40] It had further
been argued on behalf of Armscor that during the arbitration
proceedings, Breedt’s contention was that
he had solicited the
BEE Certificate for the purposes of the old contract to ensure
payment, but had in the same vein, conceded
under cross-examination
that the certificate received on 2 April 2014 was
eventually not used to process the payment
of the old contract. It
was further pointed out that undisputed evidence led by Mr Motha on
behalf of Armscor was that the certificate
in question was not found
in the old contract file, which implied that it was not used in that
respect.
[41] Armscor’s
view was that the BEE certificates which were the subject of the
emails was for the new contract/bid, and that
the certificate
submitted on 2 April 2014 BEE was solicited in order to
populate the BBBEE scorecards for the purposes
of the new bid, as it
had now reflected a black ownership of 27.94%, whilst the certificate
issued earlier and handed in as part
of the initial bid reflected
black ownership of 26%.
[42] In regard to
the above alleged transgression, the Commissioner concluded that
Breedt could not be found guilty in that;
a) The email he sent
to Muller on 24 March 2014, which made reference to Armscor’s
financial system closing down in the first
week of April to obtain
funds for payments in respect of work done in terms of existing
contracts, supported his version;
b) On the face of
it, reference by Breedt to Cenfed in his emails dealt with the
execution and closing down of the existing contract;
c) The BEE
certificate dated 1 April 2014 was used to populate the scorecard for
the new tender as it was no longer needed for the
old contract. The
email exchange however dealt simultaneously with the old contract and
its closing down, but not with the new
bid.
d) Muller was
responsible for dealing with the execution of the old contract, and
his correspondence and communication with Breedt
did not relate to
the new bid. On the other hand, Fire Raiders’ Mr. Fiford’s
communication was in respect of the new
bid and the certificate
required. This was evident from his correspondence of 18 February
2014 in terms of which had submitted
the new certificate. Fiford thus
had no communication whatsoever with Breedt.
[43] It was
submitted on behalf of Breedt that the Commissioner’s
conclusions as above could not be faulted as the email communication
was clearly in reference to the old contract, and despite it being
common cause that the contract had come to an end on
14 February 2014,
payment took time to be effected, and
thus Breedt acted within the rules as they required that where a BEE
certificate had expired,
a service provider like Fire Raiders must
first obtain a new one failing which outstanding payment may be
withheld, as further
conceded by Motha on behalf of Armscor.
[44] There are
obvious inherent difficulties with the contentions made on behalf of
Breedt for reasons which I agree with as outlined
by Armscor. Any
conclusion that the email communication was merely meant to
facilitate the closure of the old contract is unsustainable
and falls
outside the bounds of reasonableness. The only reasonable conclusion
that could have been reached given the facts and
timeline of the
events, is that indeed a third certificate was solicited purely for
the purposes of enhancing Fire Raiders’
bid. In this regard;
a) It was common
cause that Fire Raider’s initial bid submitted on
14 February 2014 was accompanied by an expired
BEE
certificate and a letter from Cenfed indicating that a BEE audit was
in progress. Furthermore, Breedt had directly communicated
with
Muller in respect of outstanding information in respect of the new
contract, a transgression for which the Commissioner had
found that a
final written warning was appropriate.
b) In the same token
however, it escaped the Commissioner’s attention when
addressing the charges in relation to the second
aspect of
communication, that it was always Breedt’s contention that he
had at all material times avoided direct communication
with Muller in
respect of the new contract, and that he had only communicated with
Fiford. This contention is nonetheless belied
by that very first
telephonic communication with Muller when enquiring about outstanding
information in respect of the new bid.
c) On
18 February 2014, a new BEE certificate was submitted by
Fire Raiders, which reflected a BEE ownership of 26%, down
from the
previous certificate which reflected 27.92%.
d) In my view, even
if there was a need for a new certificate for the purposes of closing
the old contract as Breedt had alleged,
that second certificate had
already been submitted, and there could not have been any need for a
further certificate. As it was
correctly pointed out on behalf of
Armscor, the probabilities that this second certificate could not
have come to Breedt’s
attention are nil, more particularly
since Muller said nothing about it in the email exchange. The
probabilities that this second
certificate could have been sent to
the Procurement Secretariat which had in turn said nothing about it
to Breedt are equally remote.
In the absence of an explanation as to
how the second certificate reached the Procurement Secretariat, I did
not understand it
to be Breedt’s case that the certificate was
not valid or sent by Fire Raiders. In fact, the chairperson of the
disciplinary
enquiry had found that Breedt’s denial of
knowledge of that certificate was merely bare, as evidence led at
that enquiry
revealed that upon its receipt, the Procurement
Secretariat had forwarded it to him.
e) The third
certificate could not merely have been solicited for the purposes of
closing down the old contract. That contract in
any event had been
closed down and payments authorised in that regard as far back as
February 2014. Even if payments took
long to be finalised, any
suggestion that the new certificate was required to make final
payments is belied by the fact that Breedt
had already authorized its
payment, credit notes had been issued; the account sat at zero
balance, and there was no evidence to
suggest that Armscor’s
finance department needed that certificate. Further on the
uncontested version of Motha, there was
no evidence that could be
gleaned from the file in respect of the old contract that the third
certificate had been filed or used
at all in respect of that
contract.
f) It was common
cause that following the email communication, a third BEE certificate
was submitted on 1 April 2014 indicating
a BEE ownership of
27.94%, and was promptly forwarded by Breedt to the Procurement
Secretariat with a specific request for the
matter to be urgently
attended to. In other words, for the tender documents to now be
forwarded to the BEE division for evaluation.
g) The urgency with
which Breedt sought the matter to be attended to in the light of
previous delays clearly had to raise alarm
bells. The obvious concern
was that in accordance with the rules and practice, once tender
documents had been received and perforated
upon the closure of the
tender, no further documents would be permissible in respect of that
bid.
h) In the end, no
other reasonable conclusion could have been reached other than that
Breedt indeed solicitated the submission of
the third certificate in
his direct email communication with Fire Raiders, in clear
contravention of standing rules and policies.
The use of
inappropriately obtained BEE Certificate to compile the BEE
scorecards on behalf of the BEE Division:
[45] Armscor’s
BBBEE Practice requires that all companies must submit valid
certified verification certificates or auditor’s/accounting
officers’ letter in terms of the BBBEE Codes of Practice with
their tenders, and any supplier who fails to do so would be
disqualified.
[46] Armscor
contends that significant events pointing to Breedts’
manipulation of the tender process in favour of Fire Raiders
took
place upon the receipt of the third certificate that he had solicited
from Fire Raiders. The certificate as hand delivered
to Armscor
was marked for the attention of Breedt and Van Zyl. Breedt upon its
receipt had forwarded it to Van Zyl for processing.
There was a
dispute as to what had happened after the certificate reached Van Zyl
in view of the tender documents having been perforated,
and whether
Fire Raiders’ bid ought to be disqualified.
[47] Upon the BEE
scorecard being completed with the new certificate, it was then
according to Breedt, sent to the BEE office to
seek advice. It was
common cause that such advice was not sought in writing as would have
been the norm, and ordinarily, it would
have been expected of the
scorecard to have been populated based on the perforated certificate,
which it was expected would have
been valid.
[48] What was
further common cause was that Breedt had upon the scorecard having
been completed, taken the file to the BEE office
for Manyoni to
process and sign off. Manyoni had upon perusing the file,
accidentally spilt coffee on the scorecard which was placed
on top of
the file and had requested a clean copy from Breedt. The significance
of this piece of evidence is that Breedt delivered
a clean copy to
Manyoni, without raising with him, any concerns about the use of the
third BEE certificate to populate the scorecard
or use in the new
tender.
[49] Evidence led on
behalf of Armscor by Motha and Manyoni, and as further confirmed by
Van Zyl was that documents received outside
of the tender process
could not be used for evaluation of a tender. In this regard, it was
improper for Breedt to have used Fire
Raiders’ certificate
submitted on 2 April 2014, which he had handed over to Van
Zyl to populate a BBBEE scorecard,
which was then forwarded to the
BEE Division on the same date for the purposes of evaluating the BEE
requirements for the tender
in question.
[50] A further
significant factor in this case pertains to the evidence of Van Zyl
who had not testified at the disciplinary enquiry,
but was subpoenaed
by Breedt at the arbitration proceedings. The Fire Raider’s
file was given to Van Zyl on 12 March 2014
to prepare the
BEE scorecard pending outstanding information. After the third
certificate was brought to him on 2 April 2014,
the
instruction from Breedt was to compile the scorecard.
[51] Van Zyl’s
testimony was that Breedt upon receipt of the certificate on
2 April 2014, handed it over to him
and instructed him to
compile the BBBEE scorecards, which he did. Van Zyl was however
uncertain whether the new certificate received
on 2 April 2014
could be used to populate the BBBEE scorecard in the tender. In
accordance with normal practice, Van
Zyl wrote a note on a yellow
sticker to Manyoni, to seek his advice in the matter. The yellow
sticker with the note was placed
on the file. Having compiled
the scorecard, and prior to the file reaching Manyoni, Van Zyl handed
the file with the yellow
sticker to Breedt, to take to the BEE
office. Van Zyl had specifically drawn Breedt’s attention to
the yellow sticker and
made him aware of what was noted on it.
According to Van Zyl, if no yellow stickers with notes were placed on
a file when taken
to the BEE office, everything would be assumed to
be above board with the bid.
[52] It was not in
dispute that when the file reached the BEE office, the yellow sticker
had mysteriously disappeared. Armscor contends
that the only
inference to be drawn was that Breedt had removed it, as he wanted
the BEE office to assume that everything with
the BBBEE scorecard and
Fire Raiders’ tender bid was above board. It was contended that
Breedt had effectively tampered with
the tender documents
en route
to the BEE office by removing the yellow sticker from the file, thus
misrepresenting that the BBBEE scorecard was populated with
a valid
certificate submitted on 14 February 2014, when that was
not the case.
[53] It was
submitted on behalf of Breedt that neither he nor Van Zyl could give
an explanation as to what had happened to the yellow
sticker, and
that furthermore, the BEE office would have picked up any problems
with the tender and sent it back to Breedt or Van
Zyl, prior to it
being signed off. It was further submitted that rather than
Manyoni escalating the matter to his superiors,
he should have
returned the file to Breedt, as there was nothing untoward regarding
his or Van Zyl’s actions, and that at
best, they could only be
accused of having committed procedural errors and/or minor
transgression of Armscor’s policies and
procedures.
[54] Breedt’s
further responses to these allegations at the arbitration proceedings
was that they were a mere duplication
of elements of charge 2, and an
attempt by Armscor to create new charges, or to amend the original
charges that were not in the
notice of enquiry. He had contended that
there was no basis for a conclusion to be reached that he had
manipulated the tender process
in favour of Fire Raiders.
[55] The
Commissioner’s conclusions in regard to these specific
transgressions are incoherent and at worst extraordinary.
His
starting point was to refer to the December 2011 Preferential
Procurement Regulations issued by the Minister of Finance
[11]
,
which are applicable to Armscor as a public entity listed in Schedule
2, 3A-3D of the PFMA. He also referred to Paragraph 4 of
the
Implementation Guide pertaining to the 2011 Regulations, which deals
with BBBEE status level certificates, and which provides
that
bidders are required to submit original and valid B-BBEE Status Level
Verification Certificates or certified copies together
with their
bids to substantiate their B-BBEE rating claims, and that bidders who
do not submit such certificates or who are non-compliant
contributors
to B-BBEE do not qualify for preference points, but should
nonetheless not be disqualified from the bidding process,
and be
allocated points out of 90 or 80 for price only, and zero
points out of 20 for BBBEE.
[56] In the light of
these provisions, the Commissioner concluded that the Armscor’s
Practice should have been amended/updated
to be in line with the 2011
Regulations. The Commissioner took into account that Amscor’s
witness, Mgwaya, the Divisional
Manager of the BEE Division, had
confirmed that the update or amendment had not been effected as at
2014.
[57] To the extent
that one may make sense of the Commissioner’s other or ultimate
conclusions on this charge, the following
can be gleaned
[12]
;
a) The allegation
that Breedt had used an inappropriately obtained BEE certificate
overlapped with the charge related to direct
communication with a
bidder via emails between February and March 2014, and to that
end, the factual findings made were that
those emails related to the
closing down of the old contract, and further that the communication
was in line with Armscor’s
policies and practices, to ensure
that Fire Raiders was BEE compliant;
b) Breedt had not in
any event inappropriately obtained the third BEE certificate on
2 April 2014, nor had he compiled
the BEE scorecard.
c) Since both the
expired and perforated BEE certificate that was submitted on
14 February 2014 and the 1 April 2014
non-perforated certificate were on file, it would have been clear to
any qualified Armscor official that only the perforated BEE
certificate was submitted together with the tender documents on
14 February 2014, and Manyoni upon receipt of the
unperforated
certificate had disqualified Fire Raiders’ bid.
(It is not clear what the Commissioner was attempting to convey);
d) Had Armscor
updated its policy to bring it in line with the 2011 Regulations, the
decision to disqualify Fire Raiders’
bid on 5 May 2014
should not have been taken, at it (Fire Raiders), ought to have been
but allocated zero points for
BEE preferential points out of 20.
e) The Commissioner
found it to be ironic that Armscor prosecuted Breedt for allegedly
not complying with its BEE Practice, whilst
it (Armscor) as a Major
Public Entity had not complied with the Preferential Procurement
Regulations 2011, which it was required
to comply with.
f) Since Breedt did
not inappropriately obtain a BEE certificate on 2 April 2014;
had not compiled the BEE scorecard,
and further since the scorecard
was not compiled on behalf of the BEE Division, but for the
consideration/evaluation of the BEE
Division, it had not been proven
that Breedt was guilty of the charges.
[58] It is apparent
from the conclusions reached by the Commissioner in regard to this
charge that he had clearly misconstrued the
nature of the enquiry or
had gone about the enquiry in a wrong manner. He had further failed
or ignored material evidence that
was placed before him, and the
distorting effect thereof was clearly to arrive at an unreasonable
conclusion. The submissions further
made on behalf of Breedt also
completely miss the point.
[59] An obvious
misdirection is the Commissioner’s reference to National
Treasury Implementation Guide and the Regulations,
and I fail to
appreciate the reliance placed thereon when the charges preferred
against Breedt mainly pertained to non-compliance
with Armscor’s
own practices, policies and rules. Whether those rules and policies
were not in line with the Regulations
was not an issue before him.
[60] Armscor’s
BBBEE Practice Code is clear as well known to Breedt. It was
abundantly clear to him that he and Van Zyl had
acted contrary to
standing rules and practices by completing the BEE scorecard
utilising the third certificate which was not part
of the original
tender documents. For Breedt to therefor seek to shift the blame to
the BEE office as the ultimate decision maker
is disingenuous.
[61] The
consequences of the transgression ought to be considered within the
context of the overall allegation that Breedt was intent
on
manipulating the tender process in favour of Fire Raiders. In this
regard, the contention that the email communication between
Breedt
and Muller was merely for the purposes of closing the old contract,
or that Breedt had avoided any communication with Muller
in respect
of the new contract had been found to be without merit. It follows
that the Commissioner’s conclusions that there
was an overlap
between the complaint surrounding Breedt’s communication on the
two different occasions or that this particular
charge was a
duplication as argued on behalf of Breedt cannot be sustainable. The
first communication with Muller pertained to
the extension of the
closing date of the tender or enquiry surrounding outstanding
information, whilst the second set of communication
via the emails
related to the solicitation of the third BEE certificate, in
circumstances where there was already a second certificate.
[62] Breedt, upon
the receipt of the third certificate, which incidentally now had a
higher BEE ownership percentage, and which
was clearly the subject of
the email exchange, had taken every means to expedite the processing
of the tender, and went out of
his way to present that the tender was
above board when that was not the case. Thus once the scorecard was
populated with the third
certificate which was unperforated and
contrary to rules and policies, Breedt on the face of it,
deliberately failed to enquire
with Manyoni as to whether the use of
that certificate was permissible when he had the opportunity to do
so. For reasons that remain
inexplicable, the yellow sticker in terms
of which Van Zyl sought advice from Manyoni went missing, and the
invariable impression
created would have been that the file was above
board and ready for processing.
[63] It is not for
Breedt to suggest that in any event, the BEE office would have picked
up the problems as it had the final say
as to accept the populated
BEE scorecard in its then current form or not. Both Breedt and Van
Zyl knew that it was impermissible
in accordance with the known rules
and policies, to populate the BEE scorecard with an unperforated BEE
certificate. Van Zyl was
clearly concerned and had raised the issue
with Breedt, who it cannot be doubted, knew that what they were doing
was not permissible.
The fact of the matter remains that in
accordance with his obligations and mandate as AMP, Breedt was tasked
with ensuring that
such procedural lapses did not occur, and on the
face of it, he appeared to have been prepared to overlook, if not
conceal them.
[64] In the absence
of any explanation as to what had happened to the critical yellow
sticker placed on the file by Van Zyl for
the attention of Manyoni,
the only probable inference to be drawn from his consistent conduct
was that Breedt had removed it, as
further fortified by his omission
to enquire from Manyoni whether the use of the third certificate was
permissible, when clearly
that was a critical issue in ensuring that
all procedures, policies and rules were complied with. These were not
ordinary or innocuous
procedural lapses. They were deliberate and had
clearly impacted on the need for transparency, integrity and fairness
of the tender
process. They can also not simply be wished away where
they reveal a bias and unusual indulgence in favour of a bidder to
the prejudice
of other bidders.
[65] It follows from
the above that the Commissioner failed to apply his mind to the
obvious facts that revealed that Breedt had
contrary to established
rules and policies, communicated with Fire Raiders for the purposes
of soliciting a more favourable BEE
certificate with a higher BEE
ownership score to advance its tender bid, and further failed to
disclose or bring it to the attention
of the BEE office that an
incorrect certificate was utilised to support the bid. The
Commissioner’s conclusions in this regard,
cannot therefore be
said to be falling within a band of reasonableness.
The charge
pertaining to Manipulation of the tender process in favour of Fire
Raiders by delaying the BBBEE balanced score sign
off for six weeks
pending the finalisation of an inappropriately obtained BEE
certificate by Fire Raiders:
[66] Armscor alleged
that Breedt took a period of six weeks between 14 February 2014
when the tender was received, until
2 April 2014 when it
was submitted to the BEE office, to undertake the BEE scorecard
process. The Commissioner had appreciated
that tender processes must
be fair, equitable and transparent. Further in the light of the
urgency of the repair and maintenance
work to be done to SANDF’s
military vehicles, the tender process was to be dealt with
expeditiously as possible. The Commissioner
referred to the
timelines, being 14 February 2014 when the closing date was
extended; 12 March 2014 when the
Critical Criteria
Evaluation Committee sat and required further information; 17, 30,
and 31 March 2014 when some or all
of the information was
received, and 2 April 2014 when the BEE certificate was
received and processed. In support of
the allegation that the tender
process was manipulated, the Commissioner referred to incidents
identified by Armscor in accordance
with the timelines.
[67] Breedt’s
contention was that there was no rule or policy that regulated the
timeline for the finalisation of the tender
process or for the
signing off of the balanced score card, and that such timelines
varied according to the complexities of the
specific tender,
administrative processes and his workload. His evidence was further
that at the time that tender in question was
being processed, he was
also given other tasks such as ‘Project Bandsman’ and the
procurement of aviation refuelers
to prioritise by his superiors,
Messrs Griesel and Magagula. He had contended that his version was
corroborated Van Zyl.
[68] Breedt had
further denied that he had delayed the process in that upon receipt
of the new tender on 17 February 2014,
he had scheduled the
Critical Criteria Evaluating Panel meeting on 5 March 2014.
Despite the Procurement Secretariat
having received the second BEE
certificate from Fire Raiders on 18 February 2014, it was
only brought to his attention
on 7 March 2014, and he could
not be held responsible for that delay. The Critical Criteria
Evaluating Panel meeting
took place on 12 March 2014, and
he had requested further information from the Procurement Secretariat
on 17 March 2014,
but it was given to him on 31 March 2014.
Further delays in the scheduling of the evaluation panel was
occasioned by the non-availability
of panel members. He had also
disputed that he was responsible for completing the BBBEE score card.
[69] The
Commissioner accepted that on the facts, and the documentation
presented;
a) it had not been
proven that Breedt had deliberately postponed the processing of
Tender 329 in order to wait for Fire Raiders
to obtain the BEE
Certificate, and that the delay in processing the tender was due to a
variety of factors including further delays
in the processing of the
second phase of the tender evaluation; the Project Bandsman which had
to be given priority due to its
value (R550m); further
information requested on 12 March 2014 which was only
received at the end of March 2014,
and the receipt of the third BEE
certificate from Fire Raiders on 2 April 2014.
b) The Commissioner
further took into account that the outstanding information from the
other bidder, Marce, was also only obtained
at the end of March 2014.
[70] Armscor
criticises the Commissioner’s conclusions as above on the
grounds that:
a) Breedts’
contention that he was busy with other projects or that he had
forgotten about the Fire Raiders’ tender
was contrived, as he
had left the tender file with Van Zyl on 12 March 2014 on
the basis that the BEE information was
outstanding;
b) It takes about
twenty minutes to compile the BEE scorecard, and it would have taken
no time to enter a no-return on the basis
that Fire Raiders had not
submitted a valid certificate at the time that the tender was closed;
c) Despite having
acted leisurely between 14 February 2014 and 2 April 2014,
Breedt had acted with speed upon
receipt of the third certificate on
2 April 2014, indicating that the delay had nothing to do
with other work alleged
by Breedt, and that he had deliberately held
off on the BEE evaluation pending the receipt of the new certificate,
and thus assisting
Fire Raiders’ bid;
d) The only
reasonable conclusion to be drawn was that Breedt had engaged in
manipulating the tender evaluation process in favour
of Fire raiders,
by delaying the BEE scorecard process to ensure that the bid was not
disqualified before submitting a valid certificate.
[71] In defending
the Commissioner’s conclusions, it was submitted on behalf of
Breedt that the allegations in charge 3(c)
were in any event framed
in a problematic fashion as the BEE scorecard was never
‘inappropriately obtained’ by Fire
Raiders. This
submission has merit in that on the face of it, the allegation
appears to be that Fire Raiders inappropriately obtained
the
certificate. In my view however, the argument is more about form than
substance.
[72] It was further
submitted that it had not been proven that Breedt had deliberately
postponed the processing of the tender to
wait for Fire Raiders’
certificate, particularly since as late as 31 March 2014,
certain information regarding
the functionality of the other bidder
was only received by email.
[73] The argument
that it might have been inappropriate on the part of Fire Raiders to
have submitted the certificate after the
close of the tender, but
that it was not Breedt’s doing that Fire Raiders had decided to
procure a fresh BEE certificate
loses sight of the fact that whether
the certificate was obtained inappropriately or not is clearly not
the issue. The issue as
per the charge,
albeit
framed in a
problematic fashion, is that Breedt delayed the BBBEE balanced score
sign in for about six weeks whilst waiting for
that certificate. This
much is clear from Van Zyl’s evidence that upon the file being
handed over to him, he was informed
that there was outstanding
information. That outstanding information could only have been the
new certificate, which upon its receipt,
Breedt had requested the
Procurement Secretariat to attend to it urgently. For Breedt
therefore to simply wash his hands off the
matter by contending that
it was not his doing that Fire Raiders decided to procure that
certificate cannot be correct. As already
pointed out elsewhere in
this judgment, he had indeed solicited that certificate, despite the
tender having closed on 14 February 2014.
[74] Ordinarily, and
in accordance with the strict application of Armscor’s policies
and practices, once the tender documents
were received, perforated,
and the tender had closed, any other documentation ought not to have
been accepted. This means
that the second and third
certificates submitted by Fire Raiders ought not to have been
accepted. By implication, since the initial
BEE certificate submitted
with the tender had expired, Fire Raiders’ bid as it was common
cause, ought to have been disqualified.
In my view, that ought to
have been the end of the matter. In the light of these conclusions,
it follows that all the other excuses
as to the reason it took long
to process the tender are indeed secondary if not superfluous, as the
tender bid was not in compliance
with the rules and requirements in
the first instance.
[75] The other
conclusions reached by the Commissioner related to the overall
allegation that Breedt had a motive to tamper with
the tender process
in favour of Fire Raiders, and was willing to bend all the practices
and rules in its favour. The Commissioner
found that Armscor’s
contentions in that regard had no merit, as no evidence was led to
demonstrate that Breedt would have
gained anything personally from
Fire Raiders’ bid being successful, and thus no motive was
proven.
[76] Again, the
Commissioner sadly missed the point. The issue of whether Breedt had
gained anything or would have gained anything
from Fire Raiders’
bid being successful was not the primary enquiry. Even if no such
motive was established, for the purposes
of sanction in the light of
the conclusions reached, what remained the focus of the charges was
whether Breedt’s conduct
evinced a manipulation of the
tendering process in favour of Fire Raiders.
Conclusions:
[77] In the light of
the findings made in this judgment in regards to factors such as
Breedt’s email communication with Muller
between February and
March 2014 contrary to standing rules, practices and procedures;
the prohibited communication with Muller
during the tendering process
for which the Commissioner found that a final written warning was
appropriate; the conclusion reached
in regards to the deliberate
delay in processing the BEE scorecard; the use of the third BEE
certificate to compile the scorecard,
and the failure to bring that
fact to the attention of the BEE office knowing well that such use
was impermissible, it follows
that the nature of these transgressions
clearly pointed to an overall manipulation of the tendering process
in favour of Fire Raiders.
These transgressions were patently gross
enough to warrant a sanction of dismissal. Thus, all the other
factors surrounding Breedt’s
personal circumstances paled into
insignificance.
[78] It therefore
ought to be concluded that the Commissioner’s decision in
regards to all these factors, cannot for reasons
further advanced on
behalf of Armscor, be said to be capable of being sustained on the
Sidumo
test. On a totality of the issues and the evidence, it
is apparent that the Commissioner failed have regard to material
facts, which
failure invariably defeated the constitutional
imperative that the arbitration award must be rational and
reasonable. But for these
defects, a reasonable decision-maker could
not have come to the conclusion reached in the award on the same
material.
[79] As it was
correctly pointed out on behalf of Armscor, this matter has gone
through two extensive processes as is evident from
the voluminous
nature of the record. In the light of my conclusions on all aspects
of the charges that led to Breedt’s dismissal,
no purpose would
be served by remitting the matter to the CCMA. The Court is therefore
placed in a position to substitute the Commissioner’s
award.
[80] In regards to
costs, the facts and circumstances of this case are such that it
cannot be said that there was no basis for Solidarity
and Breedt to
defend an award that was in their favour. Accordingly, the
requirements of law and fairness dictate that no order
as to cost
should be made.
[81] Accordingly,
the following order is made;
Order:
1. The arbitration
award issued by the Second Respondent under case number GATW1448/14
dated 20 November 2015 is reviewed
and set aside.
2. The above
arbitration award is substituted with an order that the dismissal of
Krige Gerhardus Breedt was substantively fair.
3. There is no order
as to costs.
E Tlhotlhalemaje
Judge of
the Labour Court of South Africa
APPEARANCES
:
For the
Applicant:
A Myburgh SC
Instructed
by: Bowman
Gilfillan INC
For the
Respondent:
W
Bekker
Instructed
by:
Serfontein
Viljoen & Swart
[1]
Act 51 of 2003
[2]
Act 1 of 1999
[3]
See paragraph 25.2.3 of the award
[4]
Herholdt v Nedbank Limited
2013
(6) SA 224
SCA;
Goldfields Mining South
Africa (Pty) Ltd (Kloof Gold Mine) v CCMA and others
2014 (1) BLLR 15
LAC
[5]
Sidumo and Another v Rustenburg Platinum Mines and Others
2008 (2) SA 24 (CC).
[6]
(2014) 35 ILJ 943 (LAC) at para 21.
[7]
(
JR1499/17) [2018] ZALCJHB 112 (15 March 2018)
[8]
[2015] 1 BLLR 50
(LAC); (2015) 36 ILJ 2802 (LAC)
[9]
Paragraph 5.5.1.3 of the Practice for the
Selection of Contractual Sources
[10]
Paragraph 18, which deals with Willful disregard
(serious) of company policy and procedures.
[11]
In terms
section 5
of the
Preferential
Procurement Policy Framework Act 5 of 2000
[12]
Paragraph 25.2.5 of the award