Steinhoff Timber Group (Pty) Ltd v Cachecorp Procument (Pty) Ltd (9962/08) [2009] ZAKZPHC 56 (25 September 2009)

80 Reportability
Contract Law

Brief Summary

Contract — Conditional counterclaim — Defendant's counterclaim based on alleged contract with entities other than the Plaintiff — Plaintiff excepted to counterclaim on grounds of vagueness and embarrassment — Court found that the counterclaim failed to clearly identify the contracting party and the basis for the claim against the Plaintiff — Exception upheld as the Defendant's allegations did not sustain a claim against the Plaintiff, rendering the counterclaim vague and embarrassing.

Comprehensive Summary

Summary of Judgment


1. Introduction


These proceedings were an exception to a pleading, brought in the High Court of South Africa, KwaZulu-Natal Division, Pietermaritzburg. The plaintiff, Steinhoff Timber Group (Pty) Ltd, had instituted action against the defendant, Cachecorp Procurement (Pty) Ltd, for payment allegedly arising from the supply of timber poles. The defendant delivered a plea in which it denied any contractual relationship with the plaintiff and, together with its plea, delivered a conditional counterclaim for damages arising from alleged non-delivery of timber.


The plaintiff delivered a Rule 23(1) notice and thereafter excepted to the conditional counterclaim on three grounds. At the hearing it was accepted that the first ground was the principal complaint, although the plaintiff did not abandon the remaining grounds. The matter therefore came before Govindasamy AJ for determination of whether the counterclaim, as pleaded, was excipiable.


The dispute, in general terms, concerned the identity of the contracting party (whether the defendant contracted with the plaintiff or with other “Steinhoff” entities), and whether the defendant’s counterclaim was pleaded with sufficient clarity to enable the plaintiff to plead to it, particularly in circumstances where the counterclaim was framed as conditional upon the plaintiff proving it was the contracting entity.


2. Material Facts


The defendant’s conditional counterclaim was expressly pleaded as being premised on the plaintiff proving that it was the entity which contracted with the defendant, because the defendant alleged it had only one contract to purchase timber for export from a company or companies bearing “Steinhoff” in their names. The defendant then pleaded that, in late 2005, it entered into a partly oral and partly written supply agreement with a group of Steinhoff companies, identified as Steinhoff Timber Industries, Steinhoff African Sourmilling (Pty) Ltd, Steinhoff Southern Cape Ltd, and PG Bison, which were collectively described in the counterclaim as “the supplier”. The defendant annexed communications (Annexures “A1” to “A14”) as written components of that alleged supply agreement.


The defendant pleaded further express, implied, or tacit terms relating to volumes of timber poles to be supplied, places of origin, delivery arrangements linked to export requirements, and payment of agreed or reasonable prices. The defendant alleged that, as a result of the supplier’s failure to deliver timber in accordance with the agreement and the defendant’s requests, it suffered damages quantified at R20,296,382.74.


In considering whether the counterclaim was vague and embarrassing, the court had regard to the plaintiff’s pleaded case in the main action. From the particulars of claim, the court understood the plaintiff to allege a credit application involving Steinhoff Africa Holdings (Pty) Ltd (as a holding company) and its subsidiaries, described collectively as “the Supplier”, with standard terms that contemplated that future contracts for goods might be concluded with any of the subsidiaries. The plaintiff pleaded further that a subsequent contract for delivery of poles was concluded specifically between the defendant and the plaintiff (as one such subsidiary), with the consequence that the right to payment vested in the plaintiff.


The defendant, in its plea, denied that it contracted with the plaintiff or purchased any goods from it. Notwithstanding that denial, and while making its counterclaim conditional on the plaintiff proving it was the contracting entity, the defendant’s counterclaim nevertheless pleaded a contract with entities none of which included the plaintiff. The court treated this as a material feature in assessing whether the counterclaim clearly identified the alleged contracting party and the party against whom damages were claimed.


3. Legal Issues


The central question was whether the conditional counterclaim was excipiable as vague and embarrassing, particularly because it appeared to oscillate between a premise that the plaintiff might be the contracting party and a pleaded agreement identifying different Steinhoff entities as “the supplier”. This was principally a question concerning the adequacy and clarity of pleading (a procedural and legal assessment), coupled with an evaluative inquiry into whether any lack of clarity caused prejudice to the plaintiff in pleading.


Additional issues arose from the second and third grounds of exception. The second was whether the defendant failed to plead material facts necessary to sustain its counterclaim, specifically regarding the allegation that deliveries would occur after reasonable notice and whether such notice was pleaded. The third was whether the defendant’s damages were pleaded with sufficient particularity to enable the plaintiff reasonably to assess quantum. These issues concerned the application of pleading requirements to the pleaded allegations and whether any deficiency justified upholding an exception.


4. Court’s Reasoning


On the principal exception, the court evaluated the internal coherence of the conditional counterclaim against the background of the plaintiff’s pleaded structure of contracting arrangements (involving a holding company, subsidiaries, and standard terms contemplating future supply contracts). The court accepted that while the plaintiff was part of the Steinhoff group, it did not follow that a contract concluded for sale of timber with one subsidiary would automatically create legal relationships with all subsidiaries in the group. The court treated this as a key point undermining the defendant’s apparent approach in its counterclaim.


The court considered that the defendant’s conditional counterclaim purported to accept, conditionally, that the plaintiff might be the contracting party, yet it pleaded the relevant agreement as being concluded with a defined “supplier” consisting of multiple named entities not including the plaintiff. In the court’s assessment, this created uncertainty as to whom the defendant alleged it contracted with and, correspondingly, against whom it alleged a breach and claimed damages. The court highlighted this lack of clarity by reference to the defendant’s allegation that it “requested delivery” in terms of the agreement, without making clear from whom delivery was requested, and noted that the pleading could not, on its face, be interpreted as referring to the plaintiff in light of how “the supplier” was pleaded.


Applying the standard for an exception for vagueness and embarrassment, the court held that the plaintiff was entitled to complain because the conditional counterclaim was vague and embarrassing to the extent that it prejudiced the plaintiff in pleading. Having reached that conclusion, the court considered it unnecessary to address every subsidiary complaint articulated under the first exception, because the central prejudice-producing vagueness had been established.


In relation to the second exception, the court addressed the contention that the defendant had not pleaded that it gave the supplier reasonable notice to make deliveries. The defendant relied on an allegation in the counterclaim that there had been repeated demands for specific deliveries, which it submitted was wide enough to cover the notice requirement. The court agreed with that submission and held that the exception could not be upheld on this ground.


As to the third exception concerning the formulation of damages, the court noted that it was not seriously pursued in argument. The court recorded that certain outstanding information had subsequently been provided and that the plaintiff’s counsel conceded that, in the ordinary course, a complaint of this nature was better pursued through procedural mechanisms dealing with irregular proceedings. The court therefore declined to uphold the exception on this basis.


On costs, the court concluded that the plaintiff had been substantially successful because the main exception succeeded. The court accepted the request that the costs of senior counsel be included, and further that the costs should include those related to the drafting of the Rule 23(1) notice, given the importance and complexity of the exception for both parties.


5. Outcome and Relief


The court upheld the exception with costs. The defendant (as respondent in the exception proceedings) was granted twenty (20) days to amend the conditional counterclaim if so advised. The costs order included the costs of engaging senior counsel in respect of the exception and the costs of drafting the Rule 23(1) notice.


Cases Cited


No cases were cited or relied upon expressly in the judgment.


Legislation Cited


No legislation was cited expressly in the judgment.


Rules of Court Cited


The Uniform Rules of Court, Rule 23(1) was cited and applied in relation to the exception procedure.


Held


The court held that the defendant’s conditional counterclaim was vague and embarrassing in a manner that prejudiced the plaintiff in pleading, because it conditionally premised liability on the plaintiff being the contracting party while simultaneously pleading a contract with other identified entities as “the supplier”, without clarifying the identity of the contracting party against whom breach and damages were alleged. The exception was therefore upheld, with the defendant afforded an opportunity to amend, and with a costs order that included senior counsel’s costs and the costs of the Rule 23(1) notice.


LEGAL PRINCIPLES


A pleading may be struck by exception where it is vague and embarrassing in a manner that causes prejudice to the opposing party, including prejudice in formulating a proper plea.


A conditional pleading does not in itself render a claim excipiable; however, the conditional formulation must still plead a cause of action with sufficient clarity, including clear identification of the contracting parties and the basis on which liability is alleged.


The fact that entities form part of a corporate group does not mean that a contract concluded with one entity automatically establishes contractual relationships with other group entities; clear pleading is required to identify which entity contracted and is alleged to have breached the contract.


An exception based on an alleged failure to plead a material fact will not succeed where the pleading, properly interpreted, sufficiently covers the requirement complained of, and where the court is satisfied that the pleading is not deficient in a manner justifying the striking out of the claim.


Complaints concerning the particularity of damages may, depending on their nature, be more appropriately addressed through procedural mechanisms dealing with irregularities, rather than by exception, particularly where the issue is not pursued and/or information is subsequently provided.

About SAFLII
Databases
Search
Terms of Use
RSS Feeds
South Africa: Kwazulu-Natal High Court, Pietermaritzburg
SAFLII
>>
Databases
>>
South Africa: Kwazulu-Natal High Court, Pietermaritzburg
>>
2009
>>
[2009] ZAKZPHC 56
|

|

Steinhoff Timber Group (Pty) Ltd v Cachecorp Procument (Pty) Ltd (9962/08) [2009] ZAKZPHC 56 (25 September 2009)

IN THE HIGH COURT
OF SOUTH AFRICA
KWAZULU-NATAL,
PIETERMARITZBURG
CASE NO:
9962/08
In the matter
between:
STEINHOFF TIMBER
GROUP (PTY) LIMITED PLAINTIFF
and
CACHECORP
PROCUREMENT (PTY) LIMTED DEFENDANT
J U D G E M E N
T
GOVINDASAMY AJ:
This matter comes
before me on exception.
The
Defendant
filed a conditional counterclaim together with its plea.
The
material paragraphs of the
Defendant’s
counterclaim relevant for the purpose of determining this exception
are as follows:
“
1. The
Defendant’s counterclaim is premised on the Plaintiff proving that
it is the entity which contracted with it as alleged,
for it had but
one contract to purchase timber for export from a company (or
companies) bearing as part of its name the word
“Steinhoff”.
2. During or
about late 2005, the Defendant represented by T Tomaszewski entered
into a partly oral, partly written agreement with
a group of
Steinhoff companies which consisted of Seinhoff Timber Industries,
Seinhoff African Sourmilling (Pty) Ltd, Steinhoff
Southern Cape Ltd
and PG Bison, represented by their duly authorized representatives,
in terms of which these entities (the supplier)
would supply the
Defendant (as purchaser and exporter) with timber, against payment of
the agreed prices (the supply agreement).
Copies of
the communications between the parties evidencing part of the supply
agreement in writing are annexed hereto marked
“A1”
– “A14”.
Further material, express,
alternatively implied, alternatively tacit, terms of the supply
agreement were:
The
supplier would supply timber poles to the Defendant during 2006 in
the following volumes:
20,000m³ from Point Noire
30,000m³ from Langmore
Plantation and Woodlines (to be delivered to Port Elizabeth for
export).
The
deliveries would take place as and when required by the Defendant,
after reasonable notice to the supplier, so as to allow
export by
sea.
The
Defendant would pay the agreed alternatively reasonable prices for
the timber.”
The
Defendant then pleaded that as a result of the failure by the
supplier to deliver timber in accordance with the supply agreement

and requests the Defendant suffered damages in the sum of
R20,296,382.74.
The
Plaintiff excepted to the Defendant’s counterclaim. The Plaintiff
excepted on three grounds but it was agreed at the hearing
that the
first exception was the “main exception”. The Plaintiff did not,
however, abandon the remaining exceptions.
The first ground
of exception is set out as follows:
“
1.
The
defendant’s conditional counterclaim proclaims in its paragraph 2
to be
‘premised
on the Plaintiff proving that it (the Plaintiff) is the entity which
contracted with’
the
defendant.
However, in
paragraph 3 of the conditional counterclaim the defendant pleads an
agreement between the
Defendant
and entities other than the Plaintiff and refers to such entities as
‘the
supplier’.
In the
subsequent paragraphs of the conditional counterclaim the
Defendant
pleads the terms of the agreement pleaded in paragraph 3 of its
conditional counterclaim and alleges breaches of that
agreement as a
result of which it is alleged the Defendant has suffered damages at
the hands of
‘the
supplier’.
If the
agreement was one between the
Plaintiff
and the Defendant, which is the premise upon which the conditional
counterclaim is based, then the Defendant does not
have a claim for
damages against the Plaintiff because the Defendant’s claim as
pleaded is a claim against those entities described
as
‘the
supplier’.
The
conditional counterclaim is vague and embarrassing in that the
Plaintiff
does not know whether the Defendant relies upon a contract between
the Plaintiff and the Defendant, or a contract between
the Defendant
and those entities described in paragraph 3 of the conditional
counterclaim as
‘the
supplier’.
Further,
Annexure
“B” to the conditional counterclaim purports to set out the
components of the Defendant’s damages. In that annexure,
it is
alleged that:
The
defendant worked with
‘Steinhoff
Southern Cape and Woodline…’;
‘
Steinhoff
entered into the following
contracts
with Cachecorp…’;
(i)
The
Defendant was to be paid a commission
‘…
for facilitating the transaction in a JV …’;
(ii) Steinhoff
had entered into a contract for the delivery of poles from Port
Elizabeth;
‘
Steinhoff
reneged on their delivery on both
contracts
…’
It is not
clear from Annexure “B” whether, or how, the contract or
contracts referred to there relate to the Defendant’s
claims
against
‘the
supplier’
or the Plaintiff, particularly in light of the allegation in
paragraph 2 of the conditional counterclaim to the effect that the

Defendant ‘…
had
but one contract to purchase timber …’
The allegations in the
conditional counterclaim do not sustain a claim for commission and
to that extent Annexure “B” is incompatible
with the conditional
counterclaim.
Further,
and in any event, the documents (Annexures “A1” to “A14”)
annexed to the conditional counterclaim as being
‘communications
…evidencing part of the supply agreement …’
do not reasonably allow for an identification of the terms of the
alleged agreement to be made.
The
Defendant’s conditional counterclaim is therefore vague and
embarrassing in the respects set out above.”
At
the hearing Mr Kemp SC for the Defendant submitted that on a proper
reading of the counterclaim it cannot be faulted as being
vague and
embarrassing. His submissions in this regard went along the
following lines:-
The
Defendant denies that it is liable to the Plaintiff for the
purchase price of timber poles.
The
Defendant did not contract with the Plaintiff.
The
Defendant contracted with other corporate entities which also bear
the name “Steinhoff” as part of their names.
The
Defendant
only concluded one contract to purchase timber and its counterclaim
is based on that contract.
If
the Plaintiff is that contracting party the counterclaim arises out
of that contract.
In
dealing with the criticism levelled at paragraph 3(a) of the
counterclaim, the Defendant’s submission is effectively captured
in
its heads of argument as follows:
“
The
Defendant
then indeed pleads the identity of such other party or parties which
underlies its defence of not having contracted with
the Plaintiff but
simply pleads that if it is mistaken about that, it contracted with
the Plaintiff and its counterclaim lies against
the Plaintiff. There
is nothing vague about this and nothing embarrassing about this.
Indeed, the Defendant’s case cannot be
clearer. A condition does
not introduce vagueness or embarrassment.”
At this point it
is perhaps appropriate to have a proper understanding of the
Plaintiff’s allegations.
It
would appear from the particulars of claim that there are two
relevant relationships. The first is between Steinhoff Africa

Holdings (Pty) Ltd (“the holding company”) and its subsidiary
companies and the Respondent. This relationship arises from
the
credit application. The holding company and its subsidiaries are
described as “the Supplier”.
The
standard conditions of
that
agreement provide in the preamble that:
“
These terms and conditions
shall apply to any contract for the sale of any goods and rendering
of any services by the Supplier to
the Applicant, whether that
contract arises out of:
any offer made by the Supplier
and accepted by the Applicant, or
any offer made by the
Applicant and accepted by the Supplier, or
any such offer made by the
Applicant in response to a quotation from the Supplier”.
The
standard conditions contemplate the conclusion of contracts
in
future
for the supply of goods. That contract
could
be concluded
with any of the subsidiaries.
The
Plaintiff alleges in p
aragraph
8 of the particulars of claim that a contract was
then
concluded
between the Plaintiff (a subsidiary of the holding company) for the
delivery of poles. The effect of that allegation must be that
the
right to receive payment for the poles vested in the Plaintiff and
not in the holding company.
In its plea the
Defendant pleaded that it had no contractual relationship with the
Plaintiff, did not purchase any goods from it
and did not owe it any
money.
In
amplification of its counterclaim and notwithstanding that it
conditionally accepted the Plaintiff as the contracting party the

Defendant pleads a contract with various entitles none of which
includes the Plaintiff. Now while it is correct that the Plaintiff

is part of the Steinhoff Group it does not follow that any contract
actually concluded for the sale of timber with any of the
subsidiaries automatically created legal relationships with each and
every subsidiary. It seems to me that this is precisely where
the
Defendant has it wrong. That much appears further in paragraph 5 of
the Counterclaim where the Defendant states that:
“
The Defendant requested the
delivery of timber in terms of the agreement, but in respect of the
Point Noire Timber no deliveries
took place and in respect of Port
Elizabeth only 5,3930.57m³ were delivered.”
The
Defendant certainly does not make it clear who exactly he requested
delivery from. Was it the holding company? Was it any
one or more
of the subsidiaries? Its allegations cannot by any interpretation
mean the Plaintiff, having regard to the Supplier
defined in
paragraph 3 of the Particulars of Claim.
In
my view the Plaintiff is entitled to complain that the conditional
counterclaim is vague and embarrassing to the extend that
it is
prejudiced in pleading thereto. That being the case I do not
consider it necessary to deal with all the additional complaints
set
out in the first exception.
The remaining
exceptions became largely academic following upon the finding in
respect of the first exception. I nevertheless deal
with them
briefly.
The second
exception is that the Defendant has not alleged all the material
facts necessary to sustain the conditional counterclaim.
The
exception arises from the Defendant’s failure to specifically plead
that reasonable notice was given to the Supplier to make
deliveries
having regard to paragraph 4(b) of the conditional counterclaim.
In
this regard Mr Kemp
submitted
that this exception should not be upheld on the following grounds:
In
paragraph 7 of the conditional counterclaim the Defendant alleged
that there were repeated demands for specific deliveries
of timber
and therefore that allegation should be interpreted widely enough to
comply with paragraph 4(b); and
In
any event the failure to make the specific allegation does not
prejudice the Defendant.
I agree with Mr
Kemp in this regard. Accordingly the exception cannot be upheld on
this ground.
The third ground
of exception is based on a failure by the Defendant to set out its
damages in such a manner as to enable the Plaintiff
reasonably to
assess the quantum thereof.
Both
counsel
did not seriously pursue this ground in argument. Mr Kemp pointed
out that certain outstanding information was subsequently provided.
In
any event Mr Marnewick properly conceded that in the normal course
the proper approach in respect of a complaint of this nature
was to
invoke the rules regarding irregular proceedings.
I
therefore need say no more save to confirm that I would not uphold
the exception on this ground.
As regards costs I
am satisfied that the Plaintiff has been substantially successful.
Mr Marnewick argued that I specifically direct
that the costs of
senior counsel should be awarded in respect of the exception
including the costs of the Rule 23(1) Notice. Mr
Kemp did not object
thereto. In my view the determination of the exception was important
to both parties and sufficiently complex
to warrant the services of
senior counsel.
In
the
circumstances
I make the following order:
The exception is
upheld with costs;
The Respondent is
granted twenty (20) days to amend the Conditional Counterclaim if it
is so advised; and
The
costs referred to in paragraph (a) shall include the costs of
engaging senior counsel in respect of the exception and the
drafting
of the Rule 23(1) Notice.
M GOVINDASAMY
AJ
Date of hearing : 7
September 2009
Date of
delivery : 25 September 2009
Counsel for
Plaintiff : Advocate CG Marnewick SC
Instructed
by : Woodhead Bigby & Irving Inc
c/o Stowell & Co.
Counsel for
Defendant : Advocate KJ Kemp SC
Instructed
by : Lister & Co.
c/o Dawsons Attorneys