King Civil Engineering Contractors (Pty) Ltd and Another v Member of the Executive Council for the Department of Public Transport, Roads and Works of the Gauteng Provincial Government and Others (2009/12600) [2009] ZAGPJHC 102 (2 April 2009)

82 Reportability
Administrative Law

Brief Summary

Tender — Administrative action — Award of tender — Applicants sought an interim interdict to prevent the first respondent from allowing the second and third respondents to proceed with a construction contract pending review of the tender award decision — Applicants’ tender was disqualified despite being the lowest and highest-scoring tender due to a misinterpretation of eligibility criteria — Court found that the applicants established urgency and a prima facie right to relief, considering the requirements for an interim interdict, including the balance of convenience and potential irreparable harm.

Comprehensive Summary

Summary of Judgment


1. Introduction


The matter concerned an urgent application for an interim interdict. The applicants sought temporary relief pending the final determination of intended review proceedings in which they would seek to have the award of a provincial road-construction tender reviewed and set aside.


The parties were King Civil Engineering Contractors (Pty) Ltd and Ludonga Construction CC (as applicants, operating as a joint venture tenderer) on the one hand, and the Member of the Executive Council for the Department of Public Transport, Roads and Works of the Gauteng Provincial Government (the first respondent, an organ of state responsible for the tender process) together with Moseme Road Construction CC and Lonerock Construction (Pty) Ltd (the second and third respondents, as the successful tenderers) on the other hand.


Procedurally, the applicants moved on an urgent basis because they contended they only became aware of the reasons for the disqualification of their tender on 17 March 2009, issued the application on 24 March 2009, and it was heard on 31 March 2009. The interim interdict was sought to halt further performance under Contract No. 1514/10/2008 pending review proceedings aimed at setting aside the award decision.


The general subject-matter of the dispute was public procurement in the context of a government road construction tender, specifically the lawfulness and fairness of disqualifying the applicants’ tender and awarding the contract to other tenderers, and whether the circumstances justified interim relief restraining performance under an already-concluded public contract.


2. Material Facts


The court recorded that the material facts were largely common cause or undisputed.


On or about 14 November 2008, the Gauteng Department of Public Transport, Roads and Works published a Tender Notice and Invitation to Tender in the media for the construction of Beyers Naudé Drive to a dual carriageway between Peter Road and Juice Road. The published notice described evaluation criteria including a CIDB grading requirement expressed as “CIBD level 8CE PE or 9CE 90:10 point system”, together with a points breakdown allocating points for price, functionality, and preference/RDP goals.


At the relevant time, CIDB grading operated as a prerequisite for contractors tendering for state work. The court accepted as common cause that a contractor’s grading related to matters such as capital, turnover, and technical ability, and that level 9CE was the highest category. The first applicant was graded 8CE, while the second and third respondents were graded 9CE. The dispute emerged against the background that, in ordinary circumstances, 8CE contractors would not tender for contracts exceeding R100 million, subject to an exception for 8CE PE contractors.


The first applicant obtained the tender documents on 17 November 2008. The tender documents, incorporating a Tender Notice and Invitation to Tender, differed from the media publication: they referred to a “CIBD level 8CE or 9CE 90:10 point system”, rather than “8CE PE or 9CE”. At a compulsory site meeting on 21 November 2008, the first applicant’s managing director queried whether an 8CE contractor qualified to bid and was informed that contractors with 8CE or higher were eligible. An addendum issued on 2 December 2008 indicated that only contractors registered as 8CE or 7CE PE or higher should tender.


The applicants formed a joint venture and submitted a tender. The Department received seven tenders. The tender evaluation undertaken by consultants recommended that the contract be awarded to the applicants: their tender was the lowest acceptable tender amount and scored the highest points (tendered at R112,074,252.34, scoring 82.8 points). However, when the matter served before the Department’s Departmental Acquisition Council (DAC), the DAC took a different view, disqualified the applicants’ tender, and awarded the contract to the second and third respondents (tendered at R116,280,366.64, scoring 77.49 points). The second and third respondents’ 9CE grading matched the grading requirement as it appeared in the media advertisement. The acceptance of their tender was confirmed by letter dated 9 February 2009, with a contract period of 87 weeks, and the contract was concluded on 18 February 2009.


The first respondent’s evidence (through the DAC chairperson and the Director of Supply Chain Management) explained that the project had initially been budgeted at about R100 million, but that Supply Chain Management considered it could exceed that figure and therefore changed the published grading requirement to 8CE PE or 9CE. The tender documents ought to have been amended to reflect the published requirement, but this was inadvertently not done. The published grading requirement was treated as a minimum qualifying criterion serving to inform prospective tenderers whether they qualified to tender.


In consequence, the DAC regarded acceptance of the applicants’ 8CE tender as unfair to other 8CE contractors who were excluded by the published advertisement and may not have attended the site meeting (and thus would not have known of the later, lower stated criterion). The DAC described the award to the applicants, in those circumstances, as implicating unfair competition, and disqualified their tender for that reason.


As to the position at the time of the urgent application, it was common cause that the roadworks were urgent, with an 18-month completion timeline and an indication that a major section needed to be completed before the 2010 World Cup. It was also undisputed that performance under the contract had already materially commenced: employees had been employed or relocated, site establishment and preliminary earthworks had begun, and further contracts had been concluded in execution of the main contract. The second and third respondents were described as “innocent tenderers”, and the court accepted that the undisputed facts supported that characterisation.


3. Legal Issues


The central legal question was whether the applicants had satisfied the requirements for an interim interdict restraining further performance under the tender contract pending the institution and finalisation of review proceedings aimed at setting aside the award decision.


This required the court to determine, on the papers and within the constraints applicable to interim relief, whether the applicants had established a prima facie right (even if open to some doubt), whether there was a well-grounded apprehension of irreparable harm, whether there was no other satisfactory remedy, and whether the balance of convenience favoured interim relief.


The dispute primarily concerned the application of law to fact and the court’s value judgment/discretion inherent in interim relief, particularly in weighing competing prejudice and evaluating whether the tender process retained the constitutional attribute of fairness. While there were elements of contestation as to the implications of the discrepancy between the published invitation and the tender documents/addendum/site-meeting statements, the court treated the relevant factual foundation as largely undisputed and focused on the legal consequences for interim relief.


4. Court’s Reasoning


The court began by confirming that urgency was established, given the applicants’ asserted date of knowledge of the reasons for disqualification and the prompt launching and enrolment of the application.


The court then set out the governing principles for interim interdicts. It relied on Eriksen Motors (Welkom) Ltd v Protea Motors, Warrenton, and Another 1973 (3) SA 685 (A) (with reference to Setlogelo v Setlogelo 1914 AD 221) for the proposition that interim interdicts are an extraordinary remedy within the court’s discretion, requiring a prima facie right (open to some doubt), apprehension of irreparable harm, absence of other remedy, and a balance-of-convenience enquiry. It also adopted the approach to disputes of fact and prima facie right from Webster v Mitchell 1948 (1) SA 1186 (W) as qualified in Gool v Minister of Justice and Another 1955 (2) SA 682 (C).


Against that framework, the court situated the dispute within the constitutional and administrative-law context of public procurement. It held that the first respondent, as an organ of state, was bound by section 217 of the Constitution to procure through a process that is fair, equitable, transparent, competitive and cost-effective. Tender processes constituted administrative action and were therefore subject to section 33 of the Constitution and the Promotion of Administrative Justice Act 3 of 2000 (PAJA), together with the principle of legality, as reflected in the cited authorities.


The applicants’ case depended substantially on the Preferential Procurement Policy Framework Act 5 of 2000 (PPPFA) and the notion of an “acceptable tender”, contending that their tender complied with the tender document specifications, scored the highest points, and was the lowest acceptable tender, so that disqualification and award to a lower-scoring tenderer was unlawful or unreasonable. The applicants further characterised the DAC’s disqualification as unreasonable, arbitrary, and legally erroneous, and not rationally connected to the information before it.


The court considered the first respondent’s explanation for the disqualification. It accepted that the published tender invitation in the media stipulated a minimum grading of 8CE PE or 9CE and thus excluded other 8CE contractors. The DAC’s view was that awarding the tender to an 8CE contractor (the first applicant) would be unfair to those excluded contractors, particularly those who did not attend the site meeting and therefore would not have been aware of an alleged “lowering” of the qualifying criterion. The court aligned this with the constitutional requirement of fairness, referring to authority emphasising the centrality of fair process in tender adjudication and stating that acceptance of the applicants’ tender would have caused the tender process to lose the attribute of fairness.


In evaluating the applicants’ prospects, the court did not finally decide the merits of the intended review. It accepted that it might ultimately be held in review proceedings that fairness required the tender process to be started afresh when the irregularities became apparent. For purposes of interim relief, it was therefore prepared to accept that the applicants had established a prima facie right.


However, the court emphasised that the applicants’ prima facie right was open to some doubt. It noted the respondents’ reliance on the rationality threshold for the exercise of public power (as articulated in Pharmaceutical Manufacturers Association of South Africa: In re Ex parte President of the Republic of South Africa 2000 (2) SA 614 (CC)) and recorded that the decision to disqualify and award to the second and third respondents appeared to be founded on reasonable and justifiable grounds and was objectively rational, albeit ultimately a matter for determination in the review proceedings. It also considered that the applicants’ managing director had been aware of the discrepancy between the published criteria and the tender documents, which explained his question at the site meeting; and it recorded that the Department’s assertion that the official at the site meeting lacked authority to lawfully lower the qualification criterion after advertisement was not disputed.


The court then addressed the remaining interim interdict requirements. It accepted, without deciding, that the applicants had met the requirements of no other satisfactory remedy and an actual or well-grounded apprehension of irreparable loss if interim relief were refused.


The decisive consideration was the balance of convenience, assessed in light of the interdict principles and the remedial framework under section 8 of PAJA, which requires relief that is just and equitable. The court stressed the practical consequences of halting performance: the contract period and urgency of the works, the potential duration of review and possible appeal proceedings, and the fact that the contract had already been concluded and acted upon, with substantial mobilisation and commencement of works by the second and third respondents, who were treated as innocent tenderers on the undisputed facts.


In contrast, the prejudice asserted by the applicants—equipment earmarked and personnel being held available—was weighed against the fact that they had never been awarded the contract, and that they remained free to institute review proceedings regardless of whether the interim interdict was granted. The court also noted that the reviewing court would be empowered to craft just and equitable relief in all the circumstances, referencing the then-recent authority dealing with PAJA remedies in a tender context.


Having weighed these considerations, the court concluded that the balance of convenience did not support granting interim relief.


5. Outcome and Relief


The application for an interim interdict was dismissed.


The applicants were ordered to pay the first respondent’s costs, jointly and severally, including the costs of two counsel, one being senior counsel.


The applicants were also ordered to pay the second and third respondents’ costs, jointly and severally.


Cases Cited


Eriksen Motors (Welkom) Ltd v Protea Motors, Warrenton, and Another 1973 (3) SA 685 (A)


Setlogelo v Setlogelo 1914 AD 221


Webster v Mitchell 1948 (1) SA 1186 (W)


Gool v Minister of Justice and Another 1955 (2) SA 682 (C)


Logbro Properties CC v Bedderson NO and Others 2003 (2) SA 460 (SCA)


Millenium Waste Management v Chairperson, Tender Board 2008 (2) SA 481 (SCA)


Chairperson, STC and Others v JFE Sapela Electronics (Pty) Ltd and Others 2008 (2) SA 638 (SCA)


Minister of health and Another NO v New Clicks South Africa (Pty) Ltd 2006 (2) SA 311 (CC)


Affordable Medicines Trust and Others v Minister of Health and others [2005] ZACC 3; 2006 (3) SA 247 (CC)


The New Reclamation Group (Pty) Ltd v Eskom Holdings Ltd & Kwanda Ferro-Alloy African Resources (Pty) Ltd (WLD Case No. 07/27391, delivered on 14 May 2008) (unreported)


Metro Projects CC and Another v Klerksdorp Local Municipality and Others 2004 (1) SA 16 (SCA)


Pharmaceutical Manufacturers Association of South Africa: In re Ex parte President of the Republic of South Africa 2000 (2) SA 614 (CC)


Eskom Holdings Ltd v The New Reclamation Group (Pty) Ltd (358/08) [2009] ZASCA 8 (13 March 2009)


Legislation Cited


Constitution of the Republic of South Africa 108 of 1996, section 217; section 33


Promotion of Administrative Justice Act 3 of 2000


Preferential Procurement Policy Framework Act 5 of 2000


Preferential Procurement Regulations, 2001, regulations 4(4), 8(8), and 8(9)


Construction Industry Development Board Act 28 of 2000


Black Economic Empowerment Act, No 53 of 2003


Employment Equity Act, No 55 of 1988 (as referenced in the tender notice)


Rules of Court Cited


No rules of court were cited in the judgment.


Held


The court held that the applicants established urgency and, for purposes of interim relief, demonstrated a prima facie right, but that this right was open to some doubt given the apparent rational and fairness-based basis for the DAC’s disqualification decision and the surrounding procurement context.


The court accepted, without deciding, that the applicants satisfied the requirements of a lack of other satisfactory remedy and a well-grounded apprehension of irreparable harm. However, the court held that the balance of convenience did not favour interim relief, particularly because the contract had already been concluded and substantially implemented, the project was urgent, the successful tenderers were treated as innocent tenderers on the undisputed facts, and the applicants retained the ability to pursue review relief with the reviewing court empowered to craft just and equitable relief under PAJA.


Accordingly, the interim interdict was refused and the application dismissed with adverse costs orders against the applicants.


LEGAL PRINCIPLES


The judgment applied the orthodox requirements for an interim interdict pending final relief, namely a prima facie right (even if open to some doubt), a well-grounded apprehension of irreparable harm, the absence of another satisfactory remedy, and a discretionary assessment of the balance of convenience, with these considerations being interrelated and evaluated holistically.


In determining whether a prima facie right was established on motion papers where disputes might arise, the judgment applied the approach that the court considers the applicant’s version together with those respondent facts that cannot be disputed, and then assesses whether the applicant should obtain final relief at trial/review on those facts, recognising that serious doubt may justify refusing interim relief.


The judgment reaffirmed that public procurement by an organ of state is constrained by constitutional procurement standards, including the requirement of fairness under section 217, and that tender adjudication constitutes administrative action subject to PAJA and legality review.


The judgment applied the principle that the exercise of public power must satisfy a minimum threshold of rationality, and that a court may not substitute its preference for that of the empowered decision-maker where the decision is objectively rational, while recognising that the ultimate legality of the decision is a matter for review proceedings.


In considering interim relief affecting an ongoing tender contract, the judgment treated practical implementation, urgency of public works, and the position of “innocent tenderers” as central to the balance of convenience, and situated that assessment alongside PAJA’s remedial requirement that any order be just and equitable in the circumstances.

About SAFLII
Databases
Search
Terms of Use
RSS Feeds
South Africa: South Gauteng High Court, Johannesburg
SAFLII
>>
Databases
>>
South Africa: South Gauteng High Court, Johannesburg
>>
2009
>>
[2009] ZAGPJHC 102
|

|

King Civil Engineering Contractors (Pty) Ltd and Another v Member of the Executive Council for the Department of Public Transport, Roads and Works of the Gauteng Provincial Government and Others (2009/12600) [2009] ZAGPJHC 102 (2 April 2009)

SOUTH GAUTENG HIGH COURT,
JOHANNESBURG
Case No. 2009/12600
Date:02/04/2009
In the matter between:
KING CIVIL ENGINEERING CONTRACTORS
(PTY) LTD
.................
First
Plaintiff
LUDONGA
CONSTRUCTION
CC
..................................................
Second
Plaintiff
and
THE MEMBER OF THE EXECUTIVE COUNCIL
FOR THE
DEPARTMENT OF PUBLIC TRANSPORT, ROADS
AND
WORKS OF THE GAUTENG PROVINCIAL
GOVERNMENT
.....
First
Respondent
MOSEME ROAD CONSTRUCTION
CC
.................................
Second
Respondent
LONEROCK
CONSTRUCTION (PTY) LTD
................................
Third
Respondent
MEYER, J
[1] This is an urgent application for
an interim interdict. The first and second applicants seek relief
preventing the first respondent
from authorizing or permitting the
second and third respondents, and the second and third respondents
from performing, any further
work under contract no. 1514/10/2008,
which is a construction contract that involves the construction of a
double carriage way
on part of Beyers Naude Drive, pending the final
determination of an application reviewing and setting aside the
decision of the
first respondent to award the contract to the second
and third respondents.
[2] I am satisfied that the
requirement of urgency has been established. The applicants only
became aware of the reasons why their
tender was disqualified on 17
March 2009. This application was issued on 24 March 2009, and
enrolled for hearing and heard on
Tuesday, 31 March 2009.
[3] The facts are largely common cause
or undisputed.
[4] On about 14 November 2008, the
Gauteng Department of Public Transport, Roads and Works (‘the
Department’), published
a Tender Notice and Invitation to
Tender in various newspapers. Tenders were invited for the
construction of Beyers Naude Drive
to a dual carriage way between
Peter Road and Juice Road. The stipulated evaluation criteria were
the ‘CIBD level 8CE PE
or 9CE 90:10 point system’.
‘Price = 60 points, Functionality = 30 points, Preference RDP
Goals (10 pts) HDI = 4,
Gender = 3, Youth = 2 and Disability = 1’.
The 30 points allocated for ‘Functionality’ were
stipulated to be:
Skills 10 (Key staff relevant to the project
(Quantity Surveyor and Professional Registration Certificate)),
Experience 10 (Previous
projects – minimum Completion
Certificates), and Project Plan 10 (Time allocations; milestones;
cost projections; resources
(Human and Plant). The Tender Notice and
Invitation to Tender also stipulated that ‘[t]he Department is
committed to the
maximization of labour intensity on all construction
projects. We adhere to all relevant Acts, including the Black
Economic
Empowerment Act, No 53 of 2003
,
Preferential Procurement
Policy Framework Act, No 5 of 2000
and Employment Equity Act, No 55
of 1988.’ It also stated that “[t]enders will be awarded
on the basis of the principle
that work will be fairly or equitably
distributed amongst contractors/entities that have not been awarded
contracts.” Tender
documents could be obtained from 14
November 2008, a compulsory site meeting was set for 21 November
2008, and the tender closing
date was 10 December 2008.
[5] A contractor’s capital,
turnover, and general technical ability determines its CIBD level
rating in terms of its registration
under the provisions of the
Construction Industry Development Board Act 28 of 2000
. Such
registration and grading are prerequisites for contractors wishing to
tender for State work. At the relevant times to these
proceedings, a
level 8CE contractor would ordinarily not be entitled to tender for a
contract with an estimated value in excess
of R100 million beyond
which only level 9CE contractors were permitted to tender, which is
the highest category of registration.
An exception is the
entitlement of a level 8CE PE contractor to tender for a contract
with an estimated value in excess of R100
million. The first
applicant was graded an 8CE contractor and the second and third
respondents grade 9CE contractors.
[6] The first applicant obtained a
copy of the tender documents on 17 November 2008. The Tender Notice
and Invitation to Tender
incorporated in the tender documents
differed from the one published in the media. The evaluation
criteria were referred to as
the ‘CIBD level 8CE or 9CE 90:10
point system’ and not as the ‘CIBD level 8CE PE or 9CE
90:10 point system’.
The first applcant’s managing
director, Mr Louis van Iddekinge, attended the site meeting on 21
November 2008, where the
Department’s Mr BN Mhlanga presented
the scope of work. Iddekinge enquired whether an 8CE contractor
qualified to bid.
Mhlanga indicated that “[o]nly those
contractors who qualify according to the CIBD grade of 8CE or higher
are eligible to
tender. On 2 December 2008, the Department’s
Transport Infrastructure issued an addendum that was to be signed and
submitted
with the other tender documents by all tenderers. This
addendum
inter alia
provided
that ‘[o]nly contractors who are CIDB registered in the grade
8CE or 7CE PE or higher should tender.’
[7] The first applicant formed a joint
venture with the second applicant and they submitted a tender for the
Beyers Naude road construction
contract. The second and third
respondents also submitted a tender. The Department received seven
tenders in total.
[8] The tenders were evaluated and it
was recommended to the Department’s Departmental Acquisition
Council (‘DAC’)
that the contract be awarded to the
applicants. Their tender was the lowest acceptable tender amount and
scored the highest points.
The applicants’ tender was for the
amount of R112, 074, 252.34 and they were awarded 82,8 points by the
consultants, Nchebe
Consulting, who undertook the evaluation for the
Department. When the matter was put before the DAC, it took a
different view
and disqualified the tender of the applicants. The
tender price of the second and third defendants was R116, 280, 366.64
and they
were allocated 77,49 points. They had a CIDB grading of
9CE, which complied with the required evaluation criteria published
in
the media. Their tender was accepted. On 9 February 2009, they
received a letter from the first respondent in which the acceptance

of their tender was confirmed with a contract period of 87 weeks for
the execution of the works. The contract was concluded on
18
February 2009.
[9] A Court’s approach in a
matter for an interim interdict pending the finalisation of an action
or application for final
relief and the requirements that need to be
established by an applicant for the interim interdict, was thus
formulated in
Eriksen Motors
(Welkom) Ltd v Protea Motors, Warrenton, and Another
1973 (3) SA 685
(A), at p 691C-G:

The granting of an interim
interdict pending an action is an extraordinary remedy within the
discretion of the Court. Where the
right which it is sought to
protect is not clear, the Court’s approach in the matter of an
interim interdict was lucidly
laid down by Innes JA in
Setlogelo
v Setlogelo
1914 AD 221
at
227. In general the requisites are-
(a) a right which, “though
prima
facie
established, is open
to some doubt”;
(b) a well grounded apprehension of
irreparable injury;
(c) the absence of ordinary remedy.
In exercising its discretion the Court
weighs,
inter alia
,
the prejudice to the applicant, if the interdict is withheld, against
the prejudice to the respondent if it is granted. This
is sometimes
called the balance of convenience.
The foregoing considerations are not
individually decisive, but are interrelated; for example, the
stronger the applicant’s
prospects of success the less his need
to rely on prejudice to himself. Conversely, the more the element of
“some doubt”,
the greater the need for the other factors
to favour him. The Court considers the affidavits as a whole, and
the interrelation
of the foregoing considerations, according to the
facts and the probabilities…’
[10] The approach in deciding whether
the applicant for an interim interdict pending final relief has
established a
prima
facie
right
,
especially where there are disputes of fact, is as follows according
to
Webster v Mitchell
1948 (1) SA 1186
(W), at p 1189:

The proper manner of approach I
consider is to take the facts as set out by the applicant, together
with any facts set out by the
respondent which the applicant cannot
dispute, and to consider whether, having regard to the inherent
probabilities, the applicant
could on those facts obtain final relief
at the trial. The facts set up in contradiction by the respondent
should then be considered.
If serious doubt is thrown on the case of
the applicant he cannot succeed in obtaining the temporary relief,
for his right,
prima facie
established, may only be
open to “some doubt”. But if there is mere
contradiction, or unconvincing explanation, the
matter should be left
to trial and the right be protected in the meanwhile, subject of
course to the respective prejudice in the
grant or refusal of interim
relief.’
The criterion for the first branch of
the enquiry was considered too favourable towards an applicant for an
interim interdict in
Gool v
Minister of Justice and Another
1955 (2) SA 682
(C), at p 688E, and accordingly qualified to

should (not could) the
applicant on those facts obtain final relief at the trial.’
[11] The first respondent is an organ
of State and subject to the provisions of the Constitution relating
to such bodies. In terms
of s 217 of the Constitution of the
Republic of South Africa 108 of 1996, the first respondent is
required to procure goods and
services pursuant to a process which is
fair, equitable, transparent, competitive and cost effective. The
tender process implemented
by an organ of State constitutes
‘administrative action’ and is subject to the provisions
of s 33 of the Constitution
and the provisions of the
Promotion of
Administrative Justice Act 3 of 2000
. See
Logbro
Properties CC v Bedderson NO and Others
2003 (2) SA 460
(SCA), para 5;
Millenium
Waste Management v Chairperson, Tender Board
2008 (2) SA 481
(SCA);
Chairperson,
STC and Others v JFE Sapela Electronics (Pty) Ltd and Others
2008 (2) SA 638
(SCA), at p646I - J. The evaluation of a tender is
thus subject to the requirement of lawful and procedurally fair
administrative
action including the principle of legality. See
Minister of health and
Another NO v New Clicks South Africa (Pty) Ltd
2006 (2) SA 311
(CC), paras 92 – 105;
Affordable
Medicines Trust and Others v Minister of Health and others
[2005] ZACC 3
;
2006 (3) SA 247
(CC), paras 48 – 49.
[12] The applicants rely on the
provisions of the
Preferential Procurement Policy Framework Act 5 of
2000
.
S 1
of this Act defines an ‘acceptable tender’ as
one ‘which, in all respects, complies with the specifications
and
conditions of tender as set out in the tender document’.
This Act provides for the determination by an organ of State of
its
preferential procurement policy and for its implementation thereof
within the framework prescribed in s 2 thereof, which framework

includes the following of a point system and for a contract to be
awarded to the tenderer who scores the highest points, unless

objective criteria in addition to certain others contemplated in that
section justify the award to another tenderer. Regulations
4(4) and
8(8) of the Preferential Procurement Regulations, 2001 provide that
‘[o]nly the tender with the highest number of
points scored may
be selected.’ Regulation 8(9) provides that a contract may be
awarded to a tenderer that did not score
the highest number of points
only on reasonable and justifiable grounds. The applicants aver that
their tender complied in all
respects with the specifications and
conditions of tender as set out in the tender document, they
submitted the lowest tender,
were awarded the highest points, and
qualified in all respects.
[13] Adv S du Toit SC, who appeared
with Adv Q Leech for the applicants, submitted that by disqualifying
the applicants’ tender
the first respondent acted unreasonably,
was materially influenced by an error of law, took into account
irrelevant considerations,
acted arbitrarily, and its decision was
not rationally connected to the information before it.
[14] The Tender Notice and Invitation
to Tender published in the media only called for tenders from CIBD
level 8CE PE or 9CE contractors.
The DAC formed the view that to
accept the tender of the applicants, who are CIBD level 8CE
contractors, would be discriminatory
against those other CIBD level
8CE contractors who did not attend the site meeting on 21 November
2008 due to the fact that only
8CE PE or 9CE contractors were invited
to tender. In taking its decision the DAC also referred to this
exclusion of other potential
8CE contractors and an award of the
tender to the applicants as ‘unfair competition’. The
DAC accordingly disqualified
the applicants’ tender and awarded
the tender to the second and third respondents who had a CIDB grading
of 9CE, which complied
with the required evaluation criteria
published in the media.
[15] The Chairperson of the DAC, Mr
Noxolo Maninjwa, states in the first respondent’s answering
affidavit that the Department’s
Directorate Infrastructure
Capital Projects (“DICP”) identified the project and
estimated a budget of about R100 million
for it. Representations in
support of the approval of the project accompanied by a proposed
advertisement to be published in the
media were submitted by the DICP
to the Department’s Directorate Supply Chain Management
(“DSCM”) for its approval.
The undisputed evidence of
the Department’s Director of DSCM, Mr Molefi Mollo, is that he
considered that the project amount
could be more than R100 million as
estimated by the DICP and he accordingly changed the CIBD grading to
one of 8CE PE or 9CE.
The proposed advertisement to be published in
the media was accordingly changed to reflect such higher grading.
The advertisement
ultimately approved by the DAC was the one that was
published in the media on 14 November 2008, and a CIBD grading of 8CE
PE or
9CE was therein stipulated. The tender documents ought to have
been amended to reflect the published grading requirement, but it
was
inadvertently not done. The CIBD grading contained in the Tender
Notice and Invitation to Tender that was published in the
media
inter
alia
served to inform
prospective tenderers whether they qualify to tender and therefore
whether they should obtain tender documents
and submit tenders.
[16] S 217 of the Constitution
requires the tender process to be ‘fair’. In the as yet
unreported judgment of
The
New Reclamation Group (Pty) Ltd v Eskom Holdings Ltd & Kwanda
Ferro-Alloy African Resources (Pty) Ltd
(WLD Case No. 07/27391, delivered on 14 May 2008), Blieden J in paras
17 and 18 said that ‘[t]he overriding consideration
that
applies to every tender process is that of fairness.’ and
‘[t]he fair procedure is not a matter of secondary importance;

it goes to the very heart of the administrative process.’ In
Chairperson, STC and Others
v JFE Sapela Electronics (Pty) Ltd and Others
2008 (2) SA 638
(SCA), at p 646J, it was said that ‘[w]hat is
fair administrative process ‘depends on the circumstances of
each case’
(s 3(2)(a) of PAJA).’ In
Metro
Projects CC and Another v Klerksdorp Local Municipality and Others
2004 (1) SA 16
(SCA), para 13 it was held that ‘[w]hatever is
done may not cause the process to lose the attribute of fairness …’

To have accepted the applicants’ tender, would, in my view,
have caused the tender process ‘to lose the attribute
of
fairness’. The invitation to tender that was published set as
a minimum qualifying criterion contractors of an 8CE PE
or 9CE CIDB
grading. All other contractors were excluded. Those disqualified
who did not attend the site meeting would not have
known of the
lowering of the qualification criterion.
[17] Adv du Toit SC submitted that the
first respondent should have invited tenders afresh when it became
aware of the irregularities.
It should not have disqualified the
applicants and awarded the contract to the second and third
respondents instead. Iddekinge,
however, was aware of the discrepancy
between the evaluation criterion stipulated in the Tender Notice and
Invitation to Tender
that had been published and the one stipulated
in the Tender Notice and Invitation to Tender contained in the tender
documents.
This is why he asked at the site meeting whether a CIBD
graded 8CE contractor could qualify to bid. The statements by
Maninjwa
in the first respondent’s answering affidavit that the
applicants had participated in tendering processes before the one in

issue and had known or ought to have known that Mhlanga did not have
the authority or could not lawfully lower the CIBD qualification

criterion at the site meeting after the call for tenders had been
advertised, were not disputed by the applicants.
[18] However, it may ultimately in
review proceedings, once these issues are more fully canvassed and
considered, be held that fairness
under all the circumstances
required the tender process to have been started afresh, and I am
therefore prepared to accept, for
the purposes of determining this
application, that the applicant has established the requisite of a
prima facie
right.
[19] Adv Khoza SC, who appeared with
Adv Nxumalo for the first respondent, submitted that the decision to
award the contract to
a tenderer that did not score the highest
number of points was taken on reasonable and justifiable grounds and
was objectively
rational. In
Pharmaceutical
Manufacturers Association of South Africa: In re Ex parte President
of the Republic of South Africa
2000 (2) SA 614
(CC) 709, para 90, it was held:

Rationality in this sense is a
minimum threshold requirement applicable to the exercise of all
public power by members of the Executive
and other functionaries.
Action that fails to pass this threshold is inconsistent with the
requirements of our Constitution and
therefore unlawful. The setting
of this standard does not mean that the Courts can or should
substitute their opinions as to what
is appropriate for the opinions
of those in whom the power has been vested. As long as the purpose
sought to be achieved by the
exercise of public power is within the
authority of its functionary and as long as its functionary’s
decision viewed objectively,
is rational, a Court cannot interfere
with the decision simply because it disagrees with or considers that
the power was exercised
inappropriately. A decision that is
objectively irrational is likely to made only rarely but, if this
does occur, a Court has
the power to intervene and set aside the
irrational decision.’
[20] The decision to disqualify the
applicants’ tender and to award the contract to the second and
third respondents appear
to me to be founded on reasonable and
justifiable grounds and was objectively rational, but again these are
issues that will ultimately
be decided in the review proceedings. In
the present application for an interim interdict these considerations
open the applicants’
prima
facie
right to doubt.
[21] The applicants have, in my
judgment, established a
prima
facie
right, but it is, at
the very least, open to ‘some doubt’. There is not ‘mere
contradiction or unconvincing
explanation’ on the part of the
first respondent.
[22] I accept, without deciding, that
the applicants have satisfied the requirements of
no
other satisfactory remedy
and of
an actual or well
grounded apprehension of irreparable loss
if the interim interdict is not granted.
[23] I now turn to the requirement
whether the
balance of
convenience
favours the
granting of the interim interdict. In assessing the balance of
convenience, a court is required to weigh the prejudice
which an
applicant will suffer if the interim relief is not granted against
the prejudice which a respondent will suffer if the
interim interdict
is granted. See
Eriksen
Motors (Welkom) Ltd v Protea Motors, Warrenton, And Another
1973 (3) SA 685
(A), at p 691C-G. Moreover, s 8 of PAJA requires a
court to make an order that is ‘just and equitable’. In
Millenium Waste Management v
Chairperson, Tender Board
2008 (2) SA 481
(SCA), para 22, Jafta JA said that ‘[t]his
guideline involves a process of striking a balance between the
applicant’s
interests, on the one hand, and the interests of
the respondents, on the other.’
[24] The final resolution of the
review proceedings that the applicants intend to institute may
potentially take a considerable
time to complete even if I were to
abridge the time limits for the institution of the proceedings and
the filing of subsequent
affidavits as was suggested by Adv du Toit
SC in argument. Once the review application is heard the decision of
the first respondent
may or may not be set aside. If it is set aside
then the tender process is likely to start afresh. There is also the
potential
of appeal proceedings.
[25] It is common cause that the
commencement and execution of the works are urgent. The contract has
to be completed within 18
months, i.e. by the middle of 2010.
Iddekinge states in the applicants’ founding affidavit that it
had been made clear at
the site meeting that the major section of the
road construction had to be completed before the 2010 World Cup.
[26] The contract with the second and
third respondents is already in existence. The conclusion of the
contract with the second
and third respondents was acted upon almost
immediately and was followed by further contracts concluded by them
in executing the
contract. Employees have been employed and others
were relocated. Site establishment and preliminary earthworks have
begun.
Various other actions in executing the contract have been
taken. It was submitted by Adv West, who appeared for the second and

third respondents, that they were ‘innocent tenderers’.
The undisputed facts support this submission.
[27] It is stated in the applicants’
founding affidavit that they are prejudiced since ‘equipment
has been earmarked
for this project and personnel is being held
available for it.’ The applicants, however, have never been
awarded the contract.
They remain at liberty to institute their
intended review proceedings for final relief whether or not this
interim interdict is
granted. The court reviewing the first
respondent’s administration action is empowered to make an
order that is ‘just
and equitable’ in all the
circumstances. See
Eskom
Holdings Ltd v The New Reclamation Group (Pty) Ltd
(358/08
[2009] ZASCA 8
(13 March 2009).
[28] The balance of convenience, in my
judgment, does not support the interim relief sought.
[29] In the result the following order
is made:
1. The application is dismissed.
2. The applicants are ordered to pay
the first respondent’s costs of this application, jointly and
severally, which costs
include the costs attendant upon the
engagement of the services of two counsel, one of whom a senior
counsel.
3. The applicants are ordered to pay
the second and third respondents’ costs of this application,
jointly and severally.
P.A.
MEYER
JUDGE
OF THE HIGH COURT
2
April 2009