Nucon Construction Thaba Nchu (Edms) v Scholtz NO (A2/2010) [2010] ZAFSHC 141 (8 November 2010)

78 Reportability
Contract Law

Brief Summary

Contract — Subcontractor's claim for payment — Appellant sought payment of R222 205,61 based on an engineer's certificate issued for additional work on a construction project — Respondent disputed the validity of the certificate, claiming no variation order was issued and questioning whether the certificate was interim or final — Court a quo dismissed the appellant's application, citing factual disputes — On appeal, it was found that the engineer acted as the respondent's agent and that the certificate constituted a valid claim for payment, leading to the conclusion that the court a quo erred in its dismissal of the application.

Comprehensive Summary

Summary of Judgment


Introduction


The matter concerned an appeal to a Full Bench of the Free State High Court, Bloemfontein, against a judgment of Molemela J in which an application for payment was dismissed with costs. Leave to appeal to the Full Bench had been granted by the court a quo.


The appellant was Nucon Construction Thaba Nchu (Edms), who had been the applicant in the court a quo. The respondent was Mr Andrew George Scholtz N.O., who had been the respondent in the application proceedings.


The dispute arose from a subcontractor relationship on a construction project at “Barkley Road Shopping Complex” (Kimberley), relating to external services works and, specifically, the appellant’s claim for payment based on an engineer’s certificate issued under the governing contract conditions. The central controversy was whether the engineer’s payment certificate constituted an enforceable basis for immediate payment, and whether purported factual disputes justified the dismissal of the application.


Material Facts


It was common cause that the appellant had been appointed as a subcontractor for external works on the Barkley Road Shopping Complex project, and that the contractual framework comprised the special conditions of contract read together with the General Conditions of Contract for Construction Works (2004) (First Edition). It was also common cause that the relevant payment certificate was issued in terms of clause 49 of the general conditions, and that the engineer acted as the employer’s (respondent’s) agent under the contract.


The appellant’s cause of action was founded on an engineer’s certificate dated 14 February 2008, certifying that an amount of R222 205,61 was due by the respondent to the appellant. The certificate related to additional work that had been instructed by the engineer. The judgment further records that, consistent with the certificate, the appellant issued a tax invoice on 14 February 2008 to the respondent for the certified amount and sought payment.


The court a quo had treated certain matters as material factual disputes. These included whether the certificate was an interim or final certificate; whether, in the absence of a variation order, the certificate had been issued in accordance with the agreement between the parties; and whether, on the special conditions (including clauses identified as S1(d) and S1(z)), the appellant was entitled to payment for additional work not provided for in the bill of quantities without written authorisation.


On appeal, the Full Bench emphasised that the documentation, including the bill of quantities referred to in the papers, indicated a written instruction for the additional work by the engineer, and the certificate itself reflected that it related to additional work. The respondent, while asserting that as far as his knowledge went no written variation order had been issued, did not deny that additional work was required and at least partially performed. The respondent’s stance was also noted to be unsupported by any affidavit from the engineer, despite the engineer being the respondent’s agent and the issuer of the certificate.


Legal Issues


The principal legal question was whether the appellant was entitled, in motion proceedings, to judgment for payment on the strength of the engineer’s payment certificate, or whether the application had properly been dismissed due to genuine, material disputes of fact.


More specifically, the court had to determine whether the certificate was binding on the respondent as a debt due (in the absence of recognised grounds for impeaching such certificates), and whether the respondent’s reliance on the absence of a variation order and on the special conditions raised a dispute going to the validity of the certificate under the contract, or merely a non-material contention insufficient to defeat the claim.


The dispute therefore primarily concerned the application of established legal principles regarding the effect of engineers’/architects’ certificates to the facts and contractual context presented, together with an evaluative determination of whether the alleged disputes were real and material for purposes of deciding motion proceedings.


Court’s Reasoning


The Full Bench approached the matter by applying the legal position, drawn from the authorities cited, that an employer is generally bound by the act of its agent (here, the engineer) in issuing a certificate. The court relied in particular on the exposition in Smith v Mouton 1977 (3) SA 9 (W) (as approved on appeal in Mouton v Smith 1977 (3) SA 1 (A)) that a certificate functions similarly to an acknowledgment of debt, and that (subject to limited exceptions) it creates an obligation to pay the amount certified.


The court highlighted that the recognised exceptions include circumstances such as fraud, collusion between the agent and contractor to the employer’s detriment, or where the agent exceeded the mandate or issued certificates not in accordance with the written contract (with reference to Rudland and Son v Gwelo Municipality 1933 S.R. 119). It also accepted that the principle extends, in general, to interim/progress certificates, which are to be treated as virtually equivalent to cash, drawing support from the quotation referencing Dawnays Ltd v F.G. Minter Ltd (1971) 2 All ER 1389 (C.A.). The Full Bench also referenced Shelfearie Property Holdings v Midrand Shopping Centre 1995 (3) SA 187 (A) in support of the binding effect of certificates.


Applying these principles, the court found that none of the recognised impeaching grounds was present on the papers. There was no suggestion of fraud, collusion, or that the engineer lacked authority to issue certificates in terms of clause 49. The remaining question, therefore, was whether the certificate was issued pursuant to the parties’ agreement.


On that question, the court considered the cumulative effect of the common-cause contractual framework, the fact that additional work was contemplated and required, and the existence of documentation (described in the judgment as a bill of quantities attached to the replying affidavit) which, on the court’s reading, constituted written notification/instruction for the additional work. The court held that the certificate itself referred to “additional work” and that the engineer’s stance, as reflected by the issuance of the interim certificate, aligned with that conclusion. The respondent’s assertion that no written variation order existed “so far as his knowledge extended” was treated as inconsistent with the engineer’s certified position, particularly given the absence of any confirmatory evidence from the engineer.


The Full Bench further reasoned that, because the certificate was an interim payment certificate, questions such as whether the additional work had been completed were not decisive for the immediate enforceability of the interim payment obligation. In this framing, the court treated the perceived disputes identified by the court a quo as not amounting to genuine, material factual disputes that could justify dismissal of the application.


The court accordingly concluded that the court a quo had erred in dismissing the application on the basis of supposed disputes of fact.


Outcome and Relief


The appeal was upheld with costs.


The order of the court a quo was set aside and replaced with an order granting relief to the appellant in terms of prayers 1, 2 and 3 of the Notice of Motion. On the judgment’s description of the relief sought in the application, this entailed an order for payment of R222 205,61, together with interest and the costs of the application.


Cases Cited


Smith v Mouton 1977 (3) SA 9 (W).


Mouton v Smith 1977 (3) SA 1 (A).


Shelfearie Property Holdings v Midrand Shopping Centre 1995 (3) SA 187 (A).


Rudland and Son v Gwelo Municipality 1933 S.R. 119.


Dawnays Ltd v F.G. Minter Ltd (1971) 2 All ER 1389 (C.A.).


Legislation Cited


No legislation was cited in the judgment.


Rules of Court Cited


No rules of court were cited in the judgment.


Held


The Full Bench held that the engineer’s interim payment certificate issued under the governing construction contract conditions was binding on the respondent in the absence of fraud, collusion, lack of authority, or a demonstrated departure from the contract that would invalidate the certificate. It held further that the court a quo incorrectly treated the respondent’s contentions (including the alleged absence of a variation order and the characterisation of the certificate) as constituting genuine, material disputes of fact sufficient to defeat the application. The appellant was therefore entitled to the relief claimed on the papers.


LEGAL PRINCIPLES


An engineer’s or architect’s certificate issued by an agent administering a construction contract generally binds the employer in the same manner as an acknowledgment of debt, subject to ordinary agency-law exceptions and contract-based validity requirements.


The recognised grounds on which an employer may avoid being bound include fraud, collusion, or the agent exceeding the scope of authority, including issuing a certificate not in accordance with the written contract.


An interim/progress payment certificate is, in principle, to be treated as virtually equivalent to cash and must ordinarily be honoured; payment is not to be withheld merely due to countervailing allegations, unless the contract provides otherwise.

About SAFLII
Databases
Search
Terms of Use
RSS Feeds
South Africa: Free State High Court, Bloemfontein
SAFLII
>>
Databases
>>
South Africa: Free State High Court, Bloemfontein
>>
2010
>>
[2010] ZAFSHC 141
|

|

Nucon Construction Thaba Nchu (Edms) v Scholtz NO (A2/2010) [2010] ZAFSHC 141 (8 November 2010)

VRYSTAATSE HOË
HOF, BLOEMFONTEIN
REPUBLIEK VAN
SUID-AFRIKA
Appélnommer :
A2/2010
In
die appél van:-
NUCON
CONSTRUCTION THABA NCHU (EDMS)
.................
Appellant
en
MNR
ANDREW GEORGE SCHOLTZ N.O.
..........................
Respondent
CORAM:
HANCKE, R
et
MOCUMIE, R
et
MATLAPENG, WND R
AANGEHOOR OP:
8 NOVEMBER 2010
_____________________________________________________
UITSPRAAK DEUR:
HANCKE, R
_____________________________________________________
GELEWER OP:
8 NOVEMBER 2010
_____________________________________________________
[1]
Hierdie is ‘n appèl gerig teen ‘n uitspraak van
Molemela, R wat die appellant (applikant in die hof
a
quo
)
se aansoek van die hand gewys het met koste, nadat sy verlof verleen
het om na die volbank van hierdie afdeling te appelleer.
[2] Appellant het ‘n
aansoek onder saaknommer 1757/2009 uitgereik teen die respondent vir
die betaling van ‘n bedrag
van R222 205,61 tesame met rente en
koste van die aansoek, welke aansoek voortspruit uit ‘n
subkontrakteurskontrak, in terme
waarvan die applikant sekere werk
vir die respondent moes verrig te Kimberley, welke projek vir
eksterne dienste was ten aansien
van “Barkley Road Shopping
Complex”.
[3] Dit is belangrik om
daarop te let dat die appellant se skuldoorsaak gebaseer is op ‘n
ingenieursertifikaat, uitgereik
op 14 Februarie 2008 in terme waarvan
hy gesertifiseer het dat die bedrag verskuldig deur die respondent
aan die applikant R222
205,61 beloop.
[4]
Dit is gemene saak tussen die partye dat die applikant aangestel was
as die subkontrakteur ten aansien van eksterne werk ten
aansien van
die gemelde projek, dat die kontrak wat tussen die partye sou geld en
wat die aangeleentheid sou beheer, die spesiale
voorwaardes van die
kontrak was, gelees met die algemene kontraksvoorwaardes soos vervat
in die “General Conditions of Contract
for Construction Works
(2004) (First Edition)”; dat die sertifikaat ter betaling deur
die ingenieur uitgereik is in terme
van klousule 49 van die algemene
kontraksvoorwaardes. Verder is dit belangrik dat die ingenieur die
agent was van die respondent.
1
Dit is
gemene saak dat die sertifikaat wat uitgereik is as interim betaling
sertifikaat vir addisionele werk was wat deur die ingenieur
aan die
appellant opgedra is en dat die respondent verplig was tot betaling
van die appellant, as kontrakteur, van die gemelde
bedrag
gesertifiseer in die sertifikaat ooreenkomstig klousule 49.4 van die
algemene kontrakvoorwaardes, en wel binne 28 dae na
ontvangs daarvan
deur die werkgewer. Verder het die appellant ‘n
belastingfaktuur uitgereik op dieselfde datum as die datum
van die
sertifikaat, synde 14 Februarie 2008, aan die respondent vir betaling
van die bedrag gesertifiseer, dit wil sê R222
205,61.
[5]
Die hof
a
quo
het
die aansoek van die hand gewys met koste, welke bevinding daarop
gebaseer was dat die volgende wesenlike feitegeskille bestaan
het:
5.1 Eerstens, dat daar ‘n
dispuut was of die sertifikaat ‘n interim of finale sertifikaat
was;
5.2 Tweedens, aangesien
daar nie ‘n wysigingsopdrag was nie, daar ‘n dispuut was
of die sertifikaat wat uitgereik is,
geskied het in terme van die
ooreenkoms tussen die partye al dan nie.
5.3 Derdens, is bevind
dat klousule S1(d) van die spesiale kontraksvoorwaardes nie die
appellant geregtig maak op betaling vir addisionele
werke waarvoor
nie voorsiening gemaak is in die “Bill of Quantities”
nie, tensy skriftelike magtiging by wyse van wysigingsopdrag
vanaf
die kliënt verkry is nie. Hiermee saam dat klousule S1(z) gelees
met die “Bill of Quantities”, wat by die
repliek aangeheg
is, nie dieselfde “Bill of Quantities” is soos bedoel in
klousule S1(d) van die spesiale kontraksvoorwaardes
nie.
[6] Dit blyk egter dat
die “Bill of Quantities”, wat aangeheg is by die repliek,
aanduidend daarvan is dat dit ‘n
skriftelike opdrag aan die
appellant verteenwoordig vanaf die ingenieur vir die volvoering van
die addisionele werke. Dit word
verder bevestig deur die inhoud van
die sertifikaat wat deur die ingenieur uitgereik is. Verder is die
betalingsertifikaat wat
uitgereik is klaarblyklik ‘n interim
betalingsertifikaat en nie ‘n finale betalingsertifikaat nie.
Dit blyk verder
duidelik uit die stukke dat die appellant skriftelik
vir betaling versoek het by wyse van die uitreiking van ‘n
belastingfaktuur
aan die respondent.
[7] Ten opsigte van die
vraag of die addisionele werk voltooi is, is dit tans nie ter sake
nie, aangesien hier slegs ‘n “interim
payment” ter
sprake was. Dit is verder gemene saak tussen die partye dat daar ook
nie sprake was van ‘n “variation
order” nie.
Wat
betref skriftelike kennisgewing soos bedoel in S1(z) is dit belangrik
om daarop te let dat die respondent self meld dat die
sertifikaat
verwys na addisionele werk wat verrig moes word.
2
[8] Ten opsigte van die
bevinding dat daar nie ‘n wysigingsopdrag was nie, verklaar die
respondent die volgende:

Sover my
kennis strek is daar geen geskrewe wysigingsopdrag uitgereik vir
hierdie werk nie. Ek ontken egter nie dat addisionele
werk verrig
moes word en gedeeltelik wel gedoen is nie.”
[9] Daar is geen twyfel
dat die “Bill of Quantities” inderdaad skriftelike
kennisgewing aan die appellant daarstel vir
die verrigting van
addisionele werk deur die ingenieur. Verder is die sertifikaat wat
uitgereik is deur die ingenieurs ooreenkomstig
klousule 1(z) van die
ooreenkoms betrekking het op “Additional work”. Dit is
ook klaarblyklik die houding van die ingenieur
synde die respondent
se agent, wie die interim betalingsertifikaat uitgereik het. Die
respondent bevestig dat daar addisionele
werk gedoen moes word, maar
beweer dat sover sy kennis strek, daar geen gewysigde opdrag was nie,
welke bewering strydig is met
die inhoud van die sertifikaat van die
ingenieur, synde die respondent se agent. Dit is belangrik om daarop
te let dat die betrokke
ingenieur geen verklaring afgelê het,
namens die respondent, ter stawing van die respondent se weergawe in
die huidige saak
nie.
[10]
Wat die regsposisie betref, word dit volledig mee gehandel in
SMITH
v MOUTON
1977 (3) SA 9
(W)
te
p. 13 A – G:

2.
The
employer should be bound by the act of his agent in issuing a
certificate. The position is the same as if the employer himself
had
signed an acknowledgment of debt. The exceptions are those that apply
generally in the law of agency. For example, the employer
will not be
bound if there has been fraud or the architect has acted in collusion
with the contractor to the detriment of the employer.....
The
employer will also not be bound if the agent has exceeded his
mandate..... In
Rudland's
case
3
the engineer
issued certificates that were not drawn up in accordance with the
terms of the written contract between the parties,
but in terms of an
oral variation made by the engineer, which he was not authorised to
make. The relevant certificates were therefore
held to be invalid.
3. The employer is not entitled to
dispute the validity of a final certificate vis-à-vis the
contractor merely because he
alleges that the certificate was given
negligently or that the architect exercised his discretion wrongly.
This principle would
include cases where the architect has issued
final certificates for work which the employer considers to be
defective or which
are based on faulty measurements or faulty
calculations..... Subject to what is said below, the same principle
would appear to
apply in the case of an interim or progress
certificate.
4. In the absence of any of the
factors referred to in para. 2, the employer is bound to pay the sum
certified. This is why in the
cases an architect's certificate has
been said to create a debt due and has been said to be regarded as
the equivalent of cash.”
4
Gemelde beslissing word
bevestig en goedgekeur op appèl in
MOUTON v SMITH
1977 (3) SA 1
(A) veral te 8 G. Sien ook
SHELFAERIE PROPERTY
HOLDINGS v MIDRAND SHOPPING CENTRE
, 1995 (3) 187 (A) te 193 B
– C.
[11] In die huidige saak
is daar nie sprake van bedrog, of samespanning tussen die ingenieur
en die appellant of dat die ingenieur
ongemagtig opgetree het nie.
Die enigste oorblywende vraag is of die sertifikaat uitgereik is
ingevolge die ooreenkoms tussen die
partye. Dit is van belang om
daarop te let dat dit gemene saak is tussen die partye dat daar
inderdaad ‘n kontrak was ingevolge
waarvan die respondent
opdrag gegee is om as subkontrakteur op te tree ten aansien van
sekere werke te “Barkley Road Shopping
Complex”. Dit is
ook gemene saak dat daar addisionele werk verrig moes word deur die
applikant vir die respondent ten aansien
van hierdie projek. Verder
staan dit vas dat die ingenieur ‘n “Bill of Quantities”
uitgereik het vir daardie
addisionele werk wat deur die appellant
verrig moes word. Gevolglik is die afleiding onafwendbaar dat die
betrokke sertifikaat
uitgereik is ooreenkomstig die ooreenkoms tussen
die partye.
[12] Dit volg dus uit die
voorgaande dat die hof
a quo
fouteer het om die appellant se
aansoek van die hand te wys op grond daarvan dat daar sogenaamde
feitedispute sou bestaan het.
[13] Bygevolg slaag die
appèl met koste. Die hof
a quo
se bevel word vervang
met die volgende:
“’
n
Bevel word ten gunste van die applikant verleen ingevolge bedes 1, 2
en 3 van die Kennisgewing van Mosie.”
________________
S.P.B. HANCKE, R
Ek stem saam.
_______________
B.C. MOCUMIE, R
Ek stem saam.
______________________
D.I. MATLAPENG, WND R
Namens die appellant:
Adv. Paul Zietsman SC
In opdrag van:
Rossouws Prokureurs
BLOEMFONTEIN
(NUC9/0001-T2 (JHC/AB)
/sp
1
Klousule
2 handel met “engineer and engineers representative” en
lui klousule 2.1 soos volg: “The function of
the engineer is
to administer the contract as agent of the employer in accordance
with the provisions of the contract.”
2
Die
respondent verklaar in hierdie verband soos volg: “Dit moet
ook uitgewys word dat die betalingsertifikaat aangeheg tot
die
stukke duidelik verwys na addisionele werk en is dit inderdaad werk
wat addisioneel tot die aanvanklike kontrak gedoen moes
word.”
3
RUDLAND
AND SON v GWELO MUNICIPALITY
, 1933 S.R. 119 te pp. 130 -
133.
4

An
interim certificate is to be regarded virtually as cash, like a bill
of exchange. It must be honoured. Payment must not be
withheld on
account of cross claims, whether good or bad – except so far
as a contract specifically provides. Otherwise
any main contractor
could always get out of payment” (i.e. to a subcontractor) “by
making all sorts of unfounded
cross claims.” (
DAWNAYS
LTD v F.G. MINTER LTD
(1971) 2 ALL E.R. 1389
(C.A.) te 1393 b).