MVD Xariep-Mol Procon Joint Venture and Others v Dihlabeng Local Municipality and Others (2059/2013) [2013] ZAFSHC 105 (20 June 2013)

80 Reportability
Public Procurement

Brief Summary

Interim Interdict — Requirements for interim relief — Applicants sought interim interdict to prevent appointment of new contractors for sewer project — Applicants claimed prior appointment by municipality and substantial payments made — Respondents denied existence of contract and proper procurement process — Court considered prerequisites for interim interdict: prima facie right, irreparable harm, balance of convenience, and absence of alternative remedy — Applicants failed to establish a clear right or prima facie case due to lack of evidence of a binding contract — Application for interim interdict dismissed.

Comprehensive Summary

Summary of Judgment


Introduction


The proceedings took the form of an urgent application for interim relief, in which the applicants sought an interim interdict pending a review of a municipal decision. The review was directed at a decision by the Dihlabeng Local Municipality (cited as the first respondent) or alternatively its Municipal Manager (the third respondent), to appoint other parties to proceed with a municipal infrastructure project.


The applicants were MVD Xariep-Mol Procon Joint Venture, MVD Xariep Consulting Engineers CC, and Mol Pro Consulting (Pty) Ltd. The respondents were Dihlabeng Local Municipality, Dikgato Consulting Engineers, the Municipal Manager, Mashimini Enterprise, and Mapitsi Civil Works. The essential complaint was that the municipality had appointed the second, fourth and fifth respondents to continue with works on a project which, according to the applicants, had previously been awarded to them.


In procedural terms, the matter was initially brought on an urgent basis on 28 May 2013 and enrolled for hearing on 31 May 2013. The respondents filed a notice of opposition and, by agreement between the parties, the matter was postponed to 13 June 2013 for the filing of further affidavits and heads of argument, and was then argued. Judgment was delivered on 20 June 2013.


The dispute concerned the applicants’ attempt to establish a basis for interim interdictory relief by asserting an existing contractual appointment in relation to the “Construction of sewer reticulation in Fateng Tse Ntsho” project (with the background of sewer works in Paul Roux) and challenging the municipality’s appointment of other contractors/consultants to proceed with the works.


Material Facts


The applicants alleged that, during or about 2007/2008, they were contracted by the first respondent in relation to sewerage works (described in the papers as “Construction of sewer plant and reticulation: Paul Roux”). They stated that they produced business plans and working drawings, and that more than R1 million had been paid to them for work done. On their version, the project was later put on hold due to a lack of bulk water, pending completion of a bulk water supply line from Bethlehem to Paul Roux.


The applicants further alleged that, in December 2012, they became aware that the bulk water supply line was near completion and they enquired about resumption of the project. Although the municipality acknowledged receipt of their letter dated 4 December 2012, the applicants said they received no substantive response.


On or about 23 April 2013, the applicants alleged that they discovered other contractors were busy with construction works on the project which they contended had been awarded to them, and they addressed an urgent letter raising concerns that the municipality had appointed another consulting engineer and that work was continuing without their administration. The matter was then held in abeyance while the municipality indicated that a petitions committee would consider the grievance, but the contemplated meeting was postponed.


On 17 May 2013, the applicants’ deponent said he came across a press advertisement calling for tenders, including for construction of waste water treatment works in Paul Roux, and the applicants contended that no decision had been taken on their grievance.


The material disputes, as identified by the court, centred on whether a binding contract existed at all and whether any such contract was validly concluded. In the opposing affidavit, the third respondent (also acting on behalf of the first respondent) denied the existence of any agreement between the applicants and the municipality. He stated that after a diligent search, no documentation could be found indicating that an agreement came into existence or that any tender process had been followed in appointing the applicants. The respondents also relied on the existence of a municipal supply chain management policy (and the statutory and constitutional procurement framework) as the governing regime for procurement of goods and services by a municipality.


The court treated as significant that the applicants’ founding papers did not attach a contract, did not set out the terms of any oral agreement, and did not provide key contractual details (such as commencement and completion dates, penalties, and payment terms). The court further regarded it as material that it was common cause that no tender process had been followed in the applicants’ appointment, and that the applicants did not provide proof when invited to do so.


In reply, the applicants attempted to locate their appointment within a deviation provision of the supply chain management policy, alleging that they were appointed in an emergency situation as contemplated by that policy. The court considered this allegation in light of the broader procurement requirements applied to municipal contracting.


Legal Issues


The central legal question was whether the applicants satisfied the requirements for an interim interdict pending review, with particular emphasis on whether they had established a clear right or at least a prima facie right (though open to some doubt).


This required determination of mixed issues of fact and law. Factually, the court had to assess whether the applicants’ affidavits established the existence of a contract concluded with the municipality. Legally, the court had to consider whether, even if some form of agreement existed, it could be regarded as valid and enforceable in light of constitutionally and statutorily mandated procurement requirements applicable to municipalities, and whether the absence of compliance-related averments undermined the claimed right.


A further issue concerned the availability of an alternative remedy, namely a damages claim, and the role that availability played in the interim interdict analysis. The court also referred to its discretion in interim interdict matters, while making clear that it had no discretion to grant such relief where the prerequisites had not been established.


Court’s Reasoning


The court began by setting out the settled requirements for interim interdictory relief, namely a prima facie right, a well-grounded apprehension of irreparable harm, a favourable balance of convenience, and the absence of an alternative satisfactory remedy, with reference to Setlogelo v Setlogelo 1914 AD 221 and the approach described in Harms, Civil Procedure in the Superior Court. It emphasised the accepted formulation that a prima facie right may exist even if open to doubt, but that a court must consider the applicant’s allegations together with those respondent facts that cannot be disputed, and must evaluate whether the respondent’s contradictory allegations throw serious doubt on the applicant’s case.


Applying these principles, the court treated the existence of a valid contract as pivotal to the claimed prima facie right. It reasoned that if a valid contract existed, the applicants might have established at least a prima facie right in substantive law. However, the court concluded that the applicants had not produced sufficient evidence in their affidavits to prove that a binding contract, validly concluded with the municipality, existed.


In reaching that conclusion, the court relied on the principle that in motion proceedings the affidavits serve as both pleadings and evidence, and therefore must contain the material necessary to establish the contractual right relied upon. It referred to Transnet Ltd v Rubenstein 2006 (1) SA 591 (SCA) and Absa Bank Ltd v Kernsig 17 (Pty) Ltd 2011 (4) SA 492 (SCA) for the proposition that the affidavits must be evaluated on whether they establish the contract alleged. The court found the applicants’ founding affidavit deficient because it did not set out the terms of any oral agreement, did not attach any written contract, and provided limited documentation beyond appointment-related letters. It also considered it material that, while payment for some work appeared to have occurred, it was not common cause who made payment and the applicants provided no confirmatory details supporting their assertion that the municipality paid them.


The court also assessed the asserted appointment against the procurement framework binding on municipalities. It referred to Municipal Manager: Qaukeni Local Municipality and Another v FV General Trading CC 2010 (1) SA 356 (SCA) and the constitutional requirement in section 217(1) that organs of state must contract for goods and services in accordance with a system that is fair, equitable, competitive and cost-effective. The court treated these requirements, echoed in the Local Government: Municipal Systems Act 32 of 2000 and the Local Government: Municipal Finance Management Act 56 of 2003, as applicable regardless of whether a supply chain management policy existed at the time, and held that the absence of a compliant procurement process could render a contract unlawful.


Against that framework, the court found there were no factual averments by the applicants that their alleged appointment in 2007/2008 complied with the constitutional and statutory procurement requirements, or that it was transparently and properly concluded as an emergency deviation. The court reasoned that, even if an agreement had been concluded (which it did not accept was sufficiently established), it would in any event be invalid if it did not comply with the mandatory procurement prerequisites. On that basis the court concluded that the applicants had not established the required prima facie right.


The court further held that the applicants had an alternative remedy. It stated that if the applicants could prove a valid contract, they would have a claim for damages, and it considered that such damages would not be impossible to prove. This supported the conclusion that interim interdictory relief was not justified on the papers before it.


On discretion, the court reiterated that it had no discretion to grant an interim interdict where the requirements were not met. It added that even if the requisites were assumed to be present, it would not have exercised its discretion to grant the interim interdict in the circumstances. The court expressly noted that refusing interim relief did not preclude the applicants from attempting to establish a valid agreement in subsequent proceedings, including the contemplated review.


Finally, because the application failed on the interim interdict requirements, the court considered it unnecessary to address urgency and made no finding on urgency.


Outcome and Relief


The court dismissed the application insofar as it related to Part A of the notice of motion, being the application for interim interdictory relief, and ordered that it be dismissed with costs.


No relief was granted restraining the municipality or the appointed respondents from proceeding with the project pending the contemplated review.


Cases Cited


Setlogelo v Setlogelo 1914 AD 221.


Edrei Investments 9 Ltd (In Liquidation) v Dis-Chem Pharmacies (Pty) Ltd 2012 (2) SA 553 (ECP).


Transnet Ltd v Rubenstein 2006 (1) SA 591 (SCA).


Absa Bank Ltd v Kernsig 17 (Pty) Ltd 2011 (4) SA 492 (SCA).


Municipal Manager: Qaukeni Local Municipality and Another v FV General Trading CC 2010 (1) SA 356 (SCA).


Legislation Cited


Constitution of the Republic of South Africa, 1996, section 217(1).


Local Government: Municipal Systems Act 32 of 2000.


Local Government: Municipal Finance Management Act 56 of 2003.


Rules of Court Cited


No rules of court were cited in the judgment.


Held


The court held that the applicants failed to establish the requirements for an interim interdict because they did not demonstrate, on the affidavits, the existence of a validly concluded and enforceable contract with the municipality that could found a prima facie right. The applicants’ papers lacked material averments and documentation to prove the contractual terms and validity, and did not allege facts showing compliance with mandatory municipal procurement requirements derived from section 217(1) of the Constitution and the relevant local government statutes.


The court further held that the applicants had an alternative remedy in the form of a damages claim if they could later prove a valid contract, and it therefore declined to grant interim relief. The application for interim relief was dismissed with costs, and the court made no determination on urgency.


LEGAL PRINCIPLES


The judgment applied the established requirements for an interim interdict, namely a prima facie right (even if open to some doubt), a reasonable apprehension of irreparable harm, a balance of convenience in favour of the applicant, and the absence of another satisfactory remedy. The court treated these requirements as cumulative, and reiterated that where they are not established, a court has no discretion to grant interim interdictory relief.


In evaluating whether a prima facie right had been established in motion proceedings, the judgment applied the principle that affidavits constitute both pleadings and evidence, and therefore must contain sufficient averments and supporting material to establish the substantive right relied upon. A party relying on contract must, on the papers, set out the basis for the contract’s existence and enforceability in a manner enabling the court to determine whether final relief could ultimately be obtained.


The judgment further applied the principle that a municipality’s contracting for goods and services is constrained by constitutional and statutory procurement imperatives, particularly the requirement that procurement be conducted under a system that is fair, equitable, competitive and cost-effective. Where an alleged municipal contract is not shown (on the papers) to have been concluded in compliance with those imperatives, its validity is placed in serious doubt, undermining any asserted contractual right for purposes of interim interdictory relief.


Finally, the judgment treated the availability of a damages claim as an important consideration in assessing whether interim relief is appropriate, supporting a conclusion that an interim interdict should not be granted where an adequate alternative remedy exists on the facts presented.

About SAFLII
Databases
Search
Terms of Use
RSS Feeds
South Africa: Free State High Court, Bloemfontein
SAFLII
>>
Databases
>>
South Africa: Free State High Court, Bloemfontein
>>
2013
>>
[2013] ZAFSHC 105
|

|

MVD Xariep-Mol Procon Joint Venture and Others v Dihlabeng Local Municipality and Others (2059/2013) [2013] ZAFSHC 105 (20 June 2013)

FREE STATE HIGH
COURT, BLOEMFONTEIN
REPUBLIC OF SOUTH
AFRICA
Application No.:
2059/2013
In
the application between:-
MVD XARIEP-MOL
PROCON JOINT VENTURE
...............
1
st
Applicant
MVD XARIEP
CONSULTING ENGINEERS CC
.................
2
nd
Applicant
MOL PRO CONSULTING
(PTY) LTD
..................................
3
rd
Applicant
and
DIHLABENG LOCAL
MUNICIPALITY
.
...........................
1
st
Respondent
DIKGATO CONSULTING
ENGINEERS
.........................
2
nd
Respondent
MUNICIPAL MANAGER:
DIHLABENG LOCAL
MUNICIPALITY
...............................................................
3
rd
Respondent
MASHININI
ENTERPRISE
..............................................
4
th
Respondent
MAPITSI CIVIL WORKS
.................................................
5
th
Respondent
_____________________________________________________
HEARD ON
13
JUNE 2013
JUDGMENT BY:
ZIETSMAN, AJ
_____________________________________________________
DELIVERED ON:
20 JUNE 2013
_____________________________________________________
[1] This is an urgent
application by the applicants for interim relief and therefore an
interim interdict pending a review of a
decision by the first,
alternatively the third respondents, appointing the second, fourth
and fifth respondents to continue with
the project called
“Construction of sewer reticulation in Fateng Tse Ntsho”.
[2] Although the
application was initially brought on an urgent basis on 28 May 2013
and enrolled for hearing on 31 May 2013, the
respondents filed a
notice of opposition, and on 31 May 2013 the parties agreed that the
application be postponed until 13 June
2013, opposing and replying
affidavits to be filed, as well as heads of argument, in order that
the application can be argued on
13 June 2013.
[3] In this application
the applicants aver that they have been contracted during or about
2007/2008 by the first respondent on
a contract called “Construction
of sewer plant and reticulation: Paul Roux”, and that after
various business plans
for the aforementioned sewerage works, as well
as working drawings were drawn by the applicants, and even after an
amount of more
than R1 million have been paid in the interim to the
applicants, the projects were put on hold due to lack of bulk water.
A bulk
water supply line had to be established from Bethlehem to Paul
Roux, which had to be completed by the first respondent, before the

project in which the applicants are involved, could resume. During or
about December 2012, the applicants became aware that the

aforementioned bulk water supply line was near completion, and
therefore enquired from the first respondent regarding the resumption

of the project by the applicants. Although the first respondent
acknowledged receipt of the letter of the applicants dated 4 December

2012, the applicants received no further response thereto.
[4] On or about 23 April
2013, the applicants became aware of the fact that other contractors
are busy with construction works on
the project to which the
applicants were the appointed contractors, and raised their concerns
with the first respondent by way
of an urgent letter dated 23 April
2013. In the last-mentioned letter dated 23 April 2013, the
applicants’ attorneys stated
the following:

4. This
project was thus approved by for MIG-funding, but due to the shortage
of adequate bulk water to complete the project, the
project was
shelved until such time that the provision of adequate bulk water in
the Paul Roux area could be established.
5. During December 2012 our client
addressed a letter to yourselves enquiring about the continuance of
this project and when the
bulk water supply line from Bethlehem to
Paul Roux is completed.
6. Our client has not received any
response to this letter, but has learned last week that your
municipality appointed another consulting
engineer that is currently
working on this very same project that our client was appointed on.
7. Our client furthermore noticed on
22 April 2013 that the contractor is busy with preparation work to
start with certain sewer
installations in this regard, which project
should have been administered by our client, since our client was
appointed on this
project as the consulting engineers.
8. It is our view that your actions of
appointing of another group of consultants to attend to this project
is contrary to the appointment
that our client holds and that our
client is suffering damages each day that this project is continuing
without our clients.”
[5] Thereafter the
present application was held in abeyance until 28 May 2013, after the
first respondent indicated that a meeting
of a petitions committee,
which obviously would have investigated the averments by the
applicants, was to be held, which meeting
eventually was postponed
until 16 May 2013.
[6] On 17 May 2013, the
deponent on behalf of the applicants, Mr Steyn, came across an
advertisement in the press wherein the first
respondent calls for
tenders,
inter alia
, for the construction of the waste water
treatment works in Paul Roux. Thereafter, and up until the date that
the application was
lodged, no response had been received from the
first respondent in this regard, nor has any decision been taken by
the first respondent
as to the applicants’ grievances.
[7] In the opposing
affidavit, the third respondent, who also acts on behalf of the first
respondent, denies that any agreement
exists between the applicants
and the first respondent. The third respondent furthermore avers that
after a diligent search, no
documentation could be found with the
first respondent indicating that an agreement came into existence
between the applicants
and the first respondent or that any tender
process had been followed in the appointment of the applicants on the
project as averred.
The third respondent also avers that since 29 May
2008, and in terms of the
Local Government Municipal Finance
Management Act, 36 of 2003
, a municipal supply chain management
policy was in place with the first respondent which policy is also
attached to the opposing
papers. The third respondent furthermore
indicated that even before the adoption of the policy by the council
of the first respondent,
the procurement of goods and services by
municipalities was governed by regulations issued in terms of the Act
and promulgated
on 13 May 2005 (the Act, with reference to the
Local
Government Municipal Finance Management Act 56 of 2003
). During
argument it was conceded by Mr Heymans, on behalf of the applicants,
that a supply chain management policy was in place
even before 2008.
[8] The third respondent
also avers that the applicants have furnished the scantiest of
information regarding the contracts on which
they rely on. He
furthermore avers that no service delivery agreement is relied upon,
no agreement whatsoever is attached to the
founding papers, there are
no averments as to when the agreements commenced, when the works had
to be completed, if penalties were
applicable and how payment had to
be made.
[9] Although the third
respondent also indicated that if a proper procurement process was
followed by the applicants, and that they
were appointed as such in
terms of such proper procurement process, the applicants are invited
to provide proof of that fact. The
applicants did not answer to such
an invitation in reply.
[10] In reply, Mr Steyn
on behalf of the applicant, amongst others, indicated that the
applicants’ appointment emanated from
paragraph 289 of the
supply chain management policy which, amongst others, and what is
relevant in this matter, determines as follows:

DEVIATION
FROM THE PROCUREMENT PROCESSES
General
289. The municipal manager may
dispense with the official procurement processes established by this
policy, and procure any required
goods or services through any
convenient process, which may include direct negotiation, but only in
respect of:
289.1. any contract relating to an
emergency (as described in clauses 291 and 292 below) where it would
not be in the interest of
the municipality to invite bids…”
[11] The applicants
therefore aver in replication that they were appointed by the first
respondent in such an emergency situation
described in paragraph 289
read with paragraphs 291 and 292 of the aforesaid policy.
[12] The requisites for
the right to claim an interim interdict, which is trite law, are:
A
prima facie
right;
A well-grounded
apprehension of irreparable harm if the interim relief is not
granted and ultimate relief is eventually granted;
That the balance of
convenience favours the granting of an interim interdict; and
That the applicant has
no other satisfactory remedy.
See Harms:
Civil
Procedure in the Superior Court
, p A-40;
Setlogelo v
Setlogelo
1914 AD 221
at 227.
[13] With reference to
the
prima facie
right,
Harms,
supra
,
describes the requisite as follows:

The degree
of proof required has been formulated as follows:
The right can be
prima facie
established even if it is open to some doubt. A mere acceptance of
the applicant’s allegations is insufficient but the weighing
up
of the probabilities of conflicting versions is not required. The
proper approach is to consider the facts as set out by the
applicant
together with any facts set out by the respondent which the applicant
cannot dispute, and to decide whether, with regard
to the inherent
probabilities and the ultimate onus, the applicant should on those
facts obtain final relief at the trial. The
facts set up in
contradiction by the respondent should then be considered, and if
they throw serious doubt on the applicant’s
case he cannot
succeed.”
See Harms:
supra
,
p A-41.
[14] It is also trite law
that a court has a discretion in this regard to allow or refuse an
interim interdict, even if the required
requisites have been
established. In this regard Harms states as follows:

A court
always has a wide discretion to refuse an interim interdict even if
the prerequisites had been established. This means that
the court is
entitled to have regard to a number of disparate and incommensurable
features in coming to a decision, and not that
the court has a free
and unfettered discretion. The discretion is a judicial one, which
must be exercised according to law and
upon facts. On the other hand,
a court has no discretion to grant an interim interdict if the
requirements have not been established.”
See Harms:
supra
,
p A-43.
[15] In this regard it
must first be established whether the applicant or applicants have
made out a clear right, or at least a
prima facie
right
although open to some doubt. Such a
prima facie
right entails
that the applicants must prove that, on the facts, they have
established the existence of a right in terms of substantive
law.
See
Edrei
Investments 9 Ltd (In Liquidation) v Dis-Chem Pharmacies (Pty) Ltd
2012 (2) SA 553
(ECP).
[16] On the facts of this
matter it is clear that if the applicants have established an
existing contract with the first respondent,
it might very well be
that at least a
prima facie
right in substantive law has been
made out, although open to some doubt. The question that begs to be
answered in this matter,
is whether the applicants have produced
evidence as to the existence of a binding contract, validly concluded
with the first respondent.
According to the Appellate Division, it is
established law that in motion proceedings the affidavits constitute
not only the evidence,
but also the pleadings. In other words, the
affidavits need to be evaluated on the basis of the question whether
a contract, validly
entered into, existed between the applicants and
the first respondent at any stage before the application was lodged.
See
Transnet Ltd v
Rubenstein
2006 (1) SA 591
(SCA) on 600 par [28]. See also
Absa Bank Ltd v Kernsig 17 (Pty) Ltd
2011 (4) SA 492
(SCA) on 499A – D.
[17] If the founding
affidavit is evaluated, it is clear that although the applicants
performed certain work on the Paul Roux project,
no formal oral
and/or written agreement between the applicants and the first
respondent has been proved.
17.1. There are not even
averments as to what the terms were of an oral agreement (if such an
oral agreement was concluded).
17.2. There are
appointment letters from project managers called SVP Quantity
Surveyors dated 18 January 2007 on the aforesaid project,
whereby MVD
Xariep was appointed to the project for engineering services (which
included application for funds at MIG).
17.3. There is
furthermore a confirmation of the appointment by the first respondent
that at 18 August 2008 (annexure “E”
to the founding
papers) which states that the applicants’ appointment has
reference, and which instructed the applicants
to commence with the
implementation of the project as soon as possible. No further
documentation exist as between the applicants
and the first
respondent.
17.4. Although it
furthermore seems that it is common cause that the applicants have
been paid until a certain stage for work done,
it is not common cause
by whom payment was effected. The applicants aver payment by the
first respondent, however no details are
provided in confirmation of
such payment and/or payments.
17.5. The third
respondent also deny that the first respondent ever had an agreement
with the aforesaid SVP Quantity Surveyors,
who appointed the
applicants.
17.6. It is also common
cause that no tender process had been followed when the applicants
have been appointed, nor is there any
evidence of whatsoever nature
how the appointment came about, who were consulted before the
appointment was made, whether the appointed
was made fairly, openly
and/or equitable, competitive or cost-effective.
[18] In this instance it
is necessary to refer to the Supreme Court of Appeal’s decision
in
Municipal Manager: Qaukeni Local Municipality and Another v
FV General Trading CC
2010 (1) SA 356
(SCA) par [11], which
reads as follows:

In
considering the validity or otherwise of the written contract ZEV 2,
it is necessary to recall that s 217(1) of the Constitution,
couched
in peremptory terms, provides inter alia that an organ of State
in the local sphere (such as a municipality) which
contracts for
goods and services 'must do so in accordance with a system which is
fair, equitable, competitive and cost-effective'
(my emphasis). This
constitutional imperative is echoed in both the
Local Government:
Municipal Systems Act 32 of 2000
and the Local Government:
Municipal Finance Management Act 56 of 2003 (the Financial Management
Act), as will become apparent
from what is set out below.”
[19] Again with reference
to the aforementioned Supreme Court of Appeal matter, and even if a
supply chain management policy is
not in place, it is still required
in terms of the Constitution read with the
Local Government:
Municipal Systems Act 32 of 2000
and the
Local Government: Municipal
Finance Management Act 56 of 2003
, that when a municipality (in this
instance the first respondent) contracts for goods and services it
must do so in accordance
with a system which is fair, equitable,
competitive and cost-effective. The failure to implement a supply
chain management policy
does not mean that a municipality contracting
with an external supplier is therefore relieved of the obligation to
act transparently
and to follow the aforesaid requisites, namely to
be fair, competitive and cost-effective through a bidding process.
[20] With reference to
the aforesaid, no factual averments by the applicants are made that
the agreement they concluded with the
first respondent during or
about 2007 was transparent, fair, competitive, cost-effective or of
an urgent nature.
[21] The aforesaid
Supreme Court of Appeal matter found the contract between the parties
to be unlawful if the agreement did not
comply with the aforesaid
prerequisites.
[22]
If there are no factual averments as to the fact or facts that the
aforementioned prerequisites were complied with, even if
there was an
agreement concluded between the applicants and the first respondent
during or about 2007 and/or 2008 (which is in
itself not clear) such
an agreement would have been invalid in the circumstances. If the
applicants have not established a validly
concluded agreement between
themselves and the first respondent, no clear right or even
prima
facie
right can exist.
[23] This is also a case
in which the applicants clearly have an alternative remedy if they
can prove a valid concluded agreement.
The applicants will always
have the right to claim damages, which in my view will not be
impossible to prove, if they have established
that a validly binding
contract came into existence between the first respondent and the
applicants.
[24] I am thus of the
view that the requirements for an interim interdict have not been
established and that in that instance I
have no discretion to grant
the interim relief sought. Even if all requisites have been
established, I am not prepared to exercise
my discretion in granting
the interim interdict in this instance as prayed for. The fact that I
am not satisfied to grant interim
relief, does not mean that the
applicants cannot still establish a validly concluded agreement when
they approach this Court for
a review of the decisions of the first,
alternatively the third respondents, in appointing the second, fourth
and fifth respondents
to proceed with or to fulfil the contractual
obligations that they have been appointed for in the circumstances.
[25] For the reasons of
my finding in this regard, it is in my view not necessary to deal
with the arguments relating to the urgency
of the application in the
circumstances. I therefore do not make any finding as to urgency.
[26] In the aforesaid
circumstances I am not satisfied that a case had been made out by the
applicants for the relief claimed regarding
an interim interdict, and
I therefore make the following order:
The application with
reference to part A referred to in the Notice of Motion, is dismissed
with costs.
_______________
P. ZIETSMAN, AJ
On behalf of applicants:
Adv P J Heymans
Instructed by:
E G Cooper Majiedt
BLOEMFONTEIN
On behalf of first and
third
respondents: Adv J P de
Bruin SC
Instructed by:
Symington & De Kok
BLOEMFONTEIN
/spieterse