About SAFLII
Databases
Search
Terms of Use
RSS Feeds
South Africa: Free State High Court, Bloemfontein
SAFLII
>>
Databases
>>
South Africa: Free State High Court, Bloemfontein
>>
2013
>>
[2013] ZAFSHC 105
|
|
MVD Xariep-Mol Procon Joint Venture and Others v Dihlabeng Local Municipality and Others (2059/2013) [2013] ZAFSHC 105 (20 June 2013)
FREE STATE HIGH
COURT, BLOEMFONTEIN
REPUBLIC OF SOUTH
AFRICA
Application No.:
2059/2013
In
the application between:-
MVD XARIEP-MOL
PROCON JOINT VENTURE
...............
1
st
Applicant
MVD XARIEP
CONSULTING ENGINEERS CC
.................
2
nd
Applicant
MOL PRO CONSULTING
(PTY) LTD
..................................
3
rd
Applicant
and
DIHLABENG LOCAL
MUNICIPALITY
.
...........................
1
st
Respondent
DIKGATO CONSULTING
ENGINEERS
.........................
2
nd
Respondent
MUNICIPAL MANAGER:
DIHLABENG LOCAL
MUNICIPALITY
...............................................................
3
rd
Respondent
MASHININI
ENTERPRISE
..............................................
4
th
Respondent
MAPITSI CIVIL WORKS
.................................................
5
th
Respondent
_____________________________________________________
HEARD ON
13
JUNE 2013
JUDGMENT BY:
ZIETSMAN, AJ
_____________________________________________________
DELIVERED ON:
20 JUNE 2013
_____________________________________________________
[1] This is an urgent
application by the applicants for interim relief and therefore an
interim interdict pending a review of a
decision by the first,
alternatively the third respondents, appointing the second, fourth
and fifth respondents to continue with
the project called
“Construction of sewer reticulation in Fateng Tse Ntsho”.
[2] Although the
application was initially brought on an urgent basis on 28 May 2013
and enrolled for hearing on 31 May 2013, the
respondents filed a
notice of opposition, and on 31 May 2013 the parties agreed that the
application be postponed until 13 June
2013, opposing and replying
affidavits to be filed, as well as heads of argument, in order that
the application can be argued on
13 June 2013.
[3] In this application
the applicants aver that they have been contracted during or about
2007/2008 by the first respondent on
a contract called “Construction
of sewer plant and reticulation: Paul Roux”, and that after
various business plans
for the aforementioned sewerage works, as well
as working drawings were drawn by the applicants, and even after an
amount of more
than R1 million have been paid in the interim to the
applicants, the projects were put on hold due to lack of bulk water.
A bulk
water supply line had to be established from Bethlehem to Paul
Roux, which had to be completed by the first respondent, before the
project in which the applicants are involved, could resume. During or
about December 2012, the applicants became aware that the
aforementioned bulk water supply line was near completion, and
therefore enquired from the first respondent regarding the resumption
of the project by the applicants. Although the first respondent
acknowledged receipt of the letter of the applicants dated 4 December
2012, the applicants received no further response thereto.
[4] On or about 23 April
2013, the applicants became aware of the fact that other contractors
are busy with construction works on
the project to which the
applicants were the appointed contractors, and raised their concerns
with the first respondent by way
of an urgent letter dated 23 April
2013. In the last-mentioned letter dated 23 April 2013, the
applicants’ attorneys stated
the following:
“
4. This
project was thus approved by for MIG-funding, but due to the shortage
of adequate bulk water to complete the project, the
project was
shelved until such time that the provision of adequate bulk water in
the Paul Roux area could be established.
5. During December 2012 our client
addressed a letter to yourselves enquiring about the continuance of
this project and when the
bulk water supply line from Bethlehem to
Paul Roux is completed.
6. Our client has not received any
response to this letter, but has learned last week that your
municipality appointed another consulting
engineer that is currently
working on this very same project that our client was appointed on.
7. Our client furthermore noticed on
22 April 2013 that the contractor is busy with preparation work to
start with certain sewer
installations in this regard, which project
should have been administered by our client, since our client was
appointed on this
project as the consulting engineers.
8. It is our view that your actions of
appointing of another group of consultants to attend to this project
is contrary to the appointment
that our client holds and that our
client is suffering damages each day that this project is continuing
without our clients.”
[5] Thereafter the
present application was held in abeyance until 28 May 2013, after the
first respondent indicated that a meeting
of a petitions committee,
which obviously would have investigated the averments by the
applicants, was to be held, which meeting
eventually was postponed
until 16 May 2013.
[6] On 17 May 2013, the
deponent on behalf of the applicants, Mr Steyn, came across an
advertisement in the press wherein the first
respondent calls for
tenders,
inter alia
, for the construction of the waste water
treatment works in Paul Roux. Thereafter, and up until the date that
the application was
lodged, no response had been received from the
first respondent in this regard, nor has any decision been taken by
the first respondent
as to the applicants’ grievances.
[7] In the opposing
affidavit, the third respondent, who also acts on behalf of the first
respondent, denies that any agreement
exists between the applicants
and the first respondent. The third respondent furthermore avers that
after a diligent search, no
documentation could be found with the
first respondent indicating that an agreement came into existence
between the applicants
and the first respondent or that any tender
process had been followed in the appointment of the applicants on the
project as averred.
The third respondent also avers that since 29 May
2008, and in terms of the
Local Government Municipal Finance
Management Act, 36 of 2003
, a municipal supply chain management
policy was in place with the first respondent which policy is also
attached to the opposing
papers. The third respondent furthermore
indicated that even before the adoption of the policy by the council
of the first respondent,
the procurement of goods and services by
municipalities was governed by regulations issued in terms of the Act
and promulgated
on 13 May 2005 (the Act, with reference to the
Local
Government Municipal Finance Management Act 56 of 2003
). During
argument it was conceded by Mr Heymans, on behalf of the applicants,
that a supply chain management policy was in place
even before 2008.
[8] The third respondent
also avers that the applicants have furnished the scantiest of
information regarding the contracts on which
they rely on. He
furthermore avers that no service delivery agreement is relied upon,
no agreement whatsoever is attached to the
founding papers, there are
no averments as to when the agreements commenced, when the works had
to be completed, if penalties were
applicable and how payment had to
be made.
[9] Although the third
respondent also indicated that if a proper procurement process was
followed by the applicants, and that they
were appointed as such in
terms of such proper procurement process, the applicants are invited
to provide proof of that fact. The
applicants did not answer to such
an invitation in reply.
[10] In reply, Mr Steyn
on behalf of the applicant, amongst others, indicated that the
applicants’ appointment emanated from
paragraph 289 of the
supply chain management policy which, amongst others, and what is
relevant in this matter, determines as follows:
“
DEVIATION
FROM THE PROCUREMENT PROCESSES
General
289. The municipal manager may
dispense with the official procurement processes established by this
policy, and procure any required
goods or services through any
convenient process, which may include direct negotiation, but only in
respect of:
289.1. any contract relating to an
emergency (as described in clauses 291 and 292 below) where it would
not be in the interest of
the municipality to invite bids…”
[11] The applicants
therefore aver in replication that they were appointed by the first
respondent in such an emergency situation
described in paragraph 289
read with paragraphs 291 and 292 of the aforesaid policy.
[12] The requisites for
the right to claim an interim interdict, which is trite law, are:
A
prima facie
right;
A well-grounded
apprehension of irreparable harm if the interim relief is not
granted and ultimate relief is eventually granted;
That the balance of
convenience favours the granting of an interim interdict; and
That the applicant has
no other satisfactory remedy.
See Harms:
Civil
Procedure in the Superior Court
, p A-40;
Setlogelo v
Setlogelo
1914 AD 221
at 227.
[13] With reference to
the
prima facie
right,
Harms,
supra
,
describes the requisite as follows:
“
The degree
of proof required has been formulated as follows:
The right can be
prima facie
established even if it is open to some doubt. A mere acceptance of
the applicant’s allegations is insufficient but the weighing
up
of the probabilities of conflicting versions is not required. The
proper approach is to consider the facts as set out by the
applicant
together with any facts set out by the respondent which the applicant
cannot dispute, and to decide whether, with regard
to the inherent
probabilities and the ultimate onus, the applicant should on those
facts obtain final relief at the trial. The
facts set up in
contradiction by the respondent should then be considered, and if
they throw serious doubt on the applicant’s
case he cannot
succeed.”
See Harms:
supra
,
p A-41.
[14] It is also trite law
that a court has a discretion in this regard to allow or refuse an
interim interdict, even if the required
requisites have been
established. In this regard Harms states as follows:
“
A court
always has a wide discretion to refuse an interim interdict even if
the prerequisites had been established. This means that
the court is
entitled to have regard to a number of disparate and incommensurable
features in coming to a decision, and not that
the court has a free
and unfettered discretion. The discretion is a judicial one, which
must be exercised according to law and
upon facts. On the other hand,
a court has no discretion to grant an interim interdict if the
requirements have not been established.”
See Harms:
supra
,
p A-43.
[15] In this regard it
must first be established whether the applicant or applicants have
made out a clear right, or at least a
prima facie
right
although open to some doubt. Such a
prima facie
right entails
that the applicants must prove that, on the facts, they have
established the existence of a right in terms of substantive
law.
See
Edrei
Investments 9 Ltd (In Liquidation) v Dis-Chem Pharmacies (Pty) Ltd
2012 (2) SA 553
(ECP).
[16] On the facts of this
matter it is clear that if the applicants have established an
existing contract with the first respondent,
it might very well be
that at least a
prima facie
right in substantive law has been
made out, although open to some doubt. The question that begs to be
answered in this matter,
is whether the applicants have produced
evidence as to the existence of a binding contract, validly concluded
with the first respondent.
According to the Appellate Division, it is
established law that in motion proceedings the affidavits constitute
not only the evidence,
but also the pleadings. In other words, the
affidavits need to be evaluated on the basis of the question whether
a contract, validly
entered into, existed between the applicants and
the first respondent at any stage before the application was lodged.
See
Transnet Ltd v
Rubenstein
2006 (1) SA 591
(SCA) on 600 par [28]. See also
Absa Bank Ltd v Kernsig 17 (Pty) Ltd
2011 (4) SA 492
(SCA) on 499A – D.
[17] If the founding
affidavit is evaluated, it is clear that although the applicants
performed certain work on the Paul Roux project,
no formal oral
and/or written agreement between the applicants and the first
respondent has been proved.
17.1. There are not even
averments as to what the terms were of an oral agreement (if such an
oral agreement was concluded).
17.2. There are
appointment letters from project managers called SVP Quantity
Surveyors dated 18 January 2007 on the aforesaid project,
whereby MVD
Xariep was appointed to the project for engineering services (which
included application for funds at MIG).
17.3. There is
furthermore a confirmation of the appointment by the first respondent
that at 18 August 2008 (annexure “E”
to the founding
papers) which states that the applicants’ appointment has
reference, and which instructed the applicants
to commence with the
implementation of the project as soon as possible. No further
documentation exist as between the applicants
and the first
respondent.
17.4. Although it
furthermore seems that it is common cause that the applicants have
been paid until a certain stage for work done,
it is not common cause
by whom payment was effected. The applicants aver payment by the
first respondent, however no details are
provided in confirmation of
such payment and/or payments.
17.5. The third
respondent also deny that the first respondent ever had an agreement
with the aforesaid SVP Quantity Surveyors,
who appointed the
applicants.
17.6. It is also common
cause that no tender process had been followed when the applicants
have been appointed, nor is there any
evidence of whatsoever nature
how the appointment came about, who were consulted before the
appointment was made, whether the appointed
was made fairly, openly
and/or equitable, competitive or cost-effective.
[18] In this instance it
is necessary to refer to the Supreme Court of Appeal’s decision
in
Municipal Manager: Qaukeni Local Municipality and Another v
FV General Trading CC
2010 (1) SA 356
(SCA) par [11], which
reads as follows:
“
In
considering the validity or otherwise of the written contract ZEV 2,
it is necessary to recall that s 217(1) of the Constitution,
couched
in peremptory terms, provides inter alia that an organ of State
in the local sphere (such as a municipality) which
contracts for
goods and services 'must do so in accordance with a system which is
fair, equitable, competitive and cost-effective'
(my emphasis). This
constitutional imperative is echoed in both the
Local Government:
Municipal Systems Act 32 of 2000
and the Local Government:
Municipal Finance Management Act 56 of 2003 (the Financial Management
Act), as will become apparent
from what is set out below.”
[19] Again with reference
to the aforementioned Supreme Court of Appeal matter, and even if a
supply chain management policy is
not in place, it is still required
in terms of the Constitution read with the
Local Government:
Municipal Systems Act 32 of 2000
and the
Local Government: Municipal
Finance Management Act 56 of 2003
, that when a municipality (in this
instance the first respondent) contracts for goods and services it
must do so in accordance
with a system which is fair, equitable,
competitive and cost-effective. The failure to implement a supply
chain management policy
does not mean that a municipality contracting
with an external supplier is therefore relieved of the obligation to
act transparently
and to follow the aforesaid requisites, namely to
be fair, competitive and cost-effective through a bidding process.
[20] With reference to
the aforesaid, no factual averments by the applicants are made that
the agreement they concluded with the
first respondent during or
about 2007 was transparent, fair, competitive, cost-effective or of
an urgent nature.
[21] The aforesaid
Supreme Court of Appeal matter found the contract between the parties
to be unlawful if the agreement did not
comply with the aforesaid
prerequisites.
[22]
If there are no factual averments as to the fact or facts that the
aforementioned prerequisites were complied with, even if
there was an
agreement concluded between the applicants and the first respondent
during or about 2007 and/or 2008 (which is in
itself not clear) such
an agreement would have been invalid in the circumstances. If the
applicants have not established a validly
concluded agreement between
themselves and the first respondent, no clear right or even
prima
facie
right can exist.
[23] This is also a case
in which the applicants clearly have an alternative remedy if they
can prove a valid concluded agreement.
The applicants will always
have the right to claim damages, which in my view will not be
impossible to prove, if they have established
that a validly binding
contract came into existence between the first respondent and the
applicants.
[24] I am thus of the
view that the requirements for an interim interdict have not been
established and that in that instance I
have no discretion to grant
the interim relief sought. Even if all requisites have been
established, I am not prepared to exercise
my discretion in granting
the interim interdict in this instance as prayed for. The fact that I
am not satisfied to grant interim
relief, does not mean that the
applicants cannot still establish a validly concluded agreement when
they approach this Court for
a review of the decisions of the first,
alternatively the third respondents, in appointing the second, fourth
and fifth respondents
to proceed with or to fulfil the contractual
obligations that they have been appointed for in the circumstances.
[25] For the reasons of
my finding in this regard, it is in my view not necessary to deal
with the arguments relating to the urgency
of the application in the
circumstances. I therefore do not make any finding as to urgency.
[26] In the aforesaid
circumstances I am not satisfied that a case had been made out by the
applicants for the relief claimed regarding
an interim interdict, and
I therefore make the following order:
The application with
reference to part A referred to in the Notice of Motion, is dismissed
with costs.
_______________
P. ZIETSMAN, AJ
On behalf of applicants:
Adv P J Heymans
Instructed by:
E G Cooper Majiedt
BLOEMFONTEIN
On behalf of first and
third
respondents: Adv J P de
Bruin SC
Instructed by:
Symington & De Kok
BLOEMFONTEIN
/spieterse