Belize Freelance Construction Joint Venture v Member of the Executive Council for the Department of Roads And Public Works: Northern Cape Province (183/2013) [2014] ZANCHC 18 (24 October 2014)

80 Reportability
Contract Law

Brief Summary

Contract — Specific performance — Claim for payment of outstanding contract amount — Plaintiff alleging improper withholding of payment by MEC for Department of Roads and Public Works — Defendant raising special plea regarding lack of timeous notice under the Institution of Legal Proceedings Against Certain Organs of State Act, 40 of 2002 — Court finding that plaintiff's claim is for damages rather than specific performance, as it involves penalties and disputes over contract compliance — Plaintiff's failure to comply with notice requirements of the Act resulting in dismissal of claim.

Comprehensive Summary

Summary of Judgment


1. Introduction


The proceedings were a High Court action in which the plaintiff claimed payment of an amount withheld by a provincial department under a construction contract. The matter came before the Northern Cape Division, Kimberley, with the defendant raising a special plea based on statutory non-compliance with pre-litigation notice requirements applicable to claims against organs of state.


The parties were Belize/Freelance Construction Joint Venture (plaintiff/applicant), being a joint venture between Belize Construction (Pty) Ltd and Freelance Construction (Pty) Ltd, and the Member of the Executive Council for the Department of Roads and Public Works: Northern Cape Province (defendant/respondent), cited as the MEC.


Procedurally, the plaintiff instituted action on 1 February 2013 for payment of R747 840.00 (being R656 000.00 plus VAT) together with interest. The MEC responded by raising a special plea in terms of section 3(2)(a) of the Institution of Legal Proceedings Against Certain Organs of State Act 40 of 2002, alleging that the plaintiff failed to serve the required notice within six months after the “debt” became due. The matter was heard on 26 August 2014 and judgment was delivered on 24 October 2014.


The general subject-matter of the dispute concerned whether the plaintiff’s claim was properly characterised as specific performance (payment of a contractual balance) or damages, because that characterisation determined whether the plaintiff was obliged to comply with the statutory notice requirements for “debts” recoverable from an organ of state.


2. Material Facts


It was common cause that the plaintiff and the MEC concluded a written construction contract under which the plaintiff constructed a Secure Care Centre in De Aar for the Department of Social Services. The tendered and approved project amount was R22 847 880.00.


The plaintiff alleged that it completed the work in accordance with the specifications and performed its contractual obligations. It further alleged that the MEC improperly withheld R656 000.00 from the contract price as a penalty deduction. The MEC denied that the deduction was improper.


The plaintiff’s pleaded case relied materially on contractual provisions dealing with extensions of time and the procedure for advancing and determining delay-related claims. The plaintiff pleaded that it was entitled to revisions of the date for practical completion for certain categories of delays and that claims were to be submitted to, and determined by, the principal agent within specified time periods. The pleaded contractual scheme included that if the principal agent failed to act within the stipulated period, the claim would be deemed to be refused, and that unresolved disagreements could be escalated into a contractual “dispute” to be adjudicated by litigation.


The plaintiff maintained that it lodged 16 delay claims with the principal agent, that the principal agent failed to take a decision or convey a decision timeously, and that the plaintiff thereafter gave notice to resolve the disagreement and ultimately declared a dispute in terms of the contract.


For purposes of the special plea, the following facts were treated as common cause and were central to the outcome. The plaintiff served notice of its intention to institute legal proceedings only on 7 June 2011. The MEC alleged (and the matter proceeded on that footing) that the debt became due and payable on 11 May 2010, with the consequence that the notice was served more than six months after the debt became due. It was also common cause that the plaintiff did not apply for condonation for its failure to serve notice timeously, and that the MEC did not give written consent to the institution of proceedings without such notice.


The critical disputed characterisation was not a dispute of primary fact, but rather whether the plaintiff’s pleaded claim was, in substance, a claim for specific performance of a contractual payment obligation or a claim for damages arising from breach and/or wrongful imposition of penalties.


3. Legal Issues


The central legal question was whether the plaintiff’s claim fell within the statutory concept of a “debt” under the Institution of Legal Proceedings Against Certain Organs of State Act 40 of 2002, thereby triggering the requirement to give notice within six months in terms of section 3(2)(a).


That enquiry depended on a further question of legal characterisation: whether, properly construed from the pleadings and the contractual context, the claim was one for specific performance (payment allegedly due under the contract) or one for damages (compensation flowing from breach or wrongful conduct in applying penalties and refusing extensions).


The dispute was therefore predominantly one of law and the application of law to the pleaded facts, namely the interpretation and application of the statutory definition of “debt” and the classification of the nature of the plaintiff’s claim based on its pleaded case.


4. Court’s Reasoning


The court approached the matter by identifying that the “crucial question” was whether the claim was for specific performance or for damages, because the statutory definition of “debt” in section 1 of the Act includes, as an element, that it is a liability “for which an organ of state is liable for payment of damages”.


The plaintiff’s contention was that it sought payment of an outstanding balance under the contract and that this constituted specific performance, not a “debt” under the Act. In support of the proposition that “debt” should be interpreted as confined to damages, the plaintiff relied on Nicor IT Consulting (Pty) Ltd v Northwest Housing Corporation 2010 (3) SA 90 (NWM) and Thabani Zulu & Co (Pty) Ltd v Minister of Water Affairs and Another 2012 (4) SA 91 (KZN), where it was held (in the quoted passages) that the statutory definition confines “debt” to claims for damages.


The MEC accepted that it is possible, in principle, to claim payment of money by way of specific performance, but argued that the plaintiff’s own pleadings indicated a damages claim. The MEC pointed to the manner in which the claim was framed, including allegations that penalties were applied and deducted “without consideration to the provisions of the contract and the delayed claims” and that, had the principal agent complied with its obligations, the delays and working days would have been granted and the plaintiff would not have been liable for penalties. The MEC’s case was that these allegations reflected a claim founded on breach and consequential financial prejudice, rather than enforcement of an accrued contractual payment entitlement.


In analysing the nature of the claim, the court referred to Farmers’ Co-op (Reg) v Berry 1912 AD 343 for the principle that a party to a binding agreement, ready to perform, is prima facie entitled to demand performance. The court also referred to Ras and Others v Simpson 1904 TS 254, where the availability of alternative relief (including damages) in relation to specific performance was discussed. The court understood these authorities as supporting the MEC’s contention on the characterisation of the plaintiff’s pleaded case.


On the court’s assessment, the plaintiff had declared a dispute concerning penalties levied in a particular certificate and the amount payable to it, and this posture was treated as inconsistent with a straightforward claim to what was contractually due as of right. The court reasoned that there was no contractual clause requiring that, once a dispute is declared, the plaintiff becomes entitled to payment merely because the principal agent refused (or failed) to grant the delays. On that basis, the court concluded that the plaintiff’s claim was “therefore not what [it] is entitled to in terms of the contract”, and that the claim was properly characterised as one for damages, not specific performance.


Having found that the claim was for damages, the court held that the plaintiff was obliged to comply with the Act’s notice requirement. The court then applied the uncontested procedural facts: notice was not served within six months of the alleged due date, there was no written consent by the organ of state to proceed without compliant notice, and no application for condonation had been brought. In those circumstances, the statutory bar operated and the special plea had to succeed.


5. Outcome and Relief


The court upheld the MEC’s special plea based on non-compliance with the notice requirements in section 3 of the Institution of Legal Proceedings Against Certain Organs of State Act 40 of 2002, on the basis that the plaintiff’s claim was a claim for damages and thus constituted a “debt” for purposes of the Act.


The plaintiff’s claim was dismissed.


The plaintiff was ordered to pay the defendant’s costs on the party-and-party scale.


Cases Cited


Nicor IT Consulting (Pty) Ltd v Northwest Housing Corporation 2010 (3) SA 90 (NWM).


Thabani Zulu & Co (Pty) Ltd v Minister of Water Affairs and Another 2012 (4) SA 91 (KZN).


Farmers’ Co-op (Reg) v Berry 1912 AD 343.


Ras and Others v Simpson 1904 TS 254.


Legislation Cited


Institution of Legal Proceedings Against Certain Organs of State Act 40 of 2002.


Rules of Court Cited


No rules of court were cited in the judgment.


Held


The court held that the plaintiff’s pleaded claim, although framed as a claim for payment, was in substance a claim for damages arising from the allegedly improper imposition and deduction of penalties and the principal agent’s failure to grant delay-related claims.


Because the claim was one for damages, it constituted a “debt” under the Institution of Legal Proceedings Against Certain Organs of State Act 40 of 2002, and the plaintiff was required to serve a compliant notice within six months of the date on which the debt became due. The plaintiff’s notice was out of time, there was no written consent by the MEC to proceed without notice, and no condonation application had been made. The special plea was accordingly upheld, the action dismissed, and costs awarded against the plaintiff.


LEGAL PRINCIPLES


A party to a binding contract who is ready and able to perform is, as a general principle, entitled to demand performance in terms of the contract (specific performance), subject to what is possible in the circumstances, as reflected in the authority cited from Farmers’ Co-op (Reg) v Berry 1912 AD 343.


The classification of a claim as specific performance or damages turns on the substance of the pleaded cause of action and the nature of the entitlement asserted, rather than on the label attached to the remedy. In this matter, the court treated allegations directed at the wrongful deduction of penalties and the consequences of non-compliance by the principal agent as indicative of a damages claim.


Under section 3 of the Institution of Legal Proceedings Against Certain Organs of State Act 40 of 2002, legal proceedings for the recovery of a “debt” (as defined) may not be instituted against an organ of state unless proper and timeous notice is given, or the organ of state gives written consent to proceed without such notice. Where notice is not served within six months of the debt becoming due, and no consent or condonation is present, the organ of state’s special plea based on statutory non-compliance is dispositive of the claim.

About SAFLII
Databases
Search
Terms of Use
RSS Feeds
South Africa: High Court, Northern Cape Division, Kimberley
SAFLII
>>
Databases
>>
South Africa: High Court, Northern Cape Division, Kimberley
>>
2014
>>
[2014] ZANCHC 18
|

|

Belize Freelance Construction Joint Venture v Member of the Executive Council for the Department of Roads And Public Works: Northern Cape Province (183/2013) [2014] ZANCHC 18 (24 October 2014)

IN THE HIGH COURT OF
SOUTH AFRICA
(NORTHERN CAPE HIGH
COURT, KIMBELEY)
Case No: 183/2013
DATE: 24 OCTOBER 2014
In the matter between:
BELIZE FREELANCE CONSTRUCTION JOINT
VENTURE
............
APPLICANT/PLAINTIFF
AND
MEMBER OF THE EXECUTIVE
COUNCIL
................................
RESPONDENT/
DEFENDANT
FOR THE DEPARTMENT OF ROADS
AND PUBLIC WORKS:
NORTHERN CAPE PROVINCE
JUDGMENT
HEARD ON: 26/08/2014
DELIVERED: 24/10/2014
PAKATI J
[1] The plaintiff/applicant is Belize/
Freelance Construction Joint Venture, a joint venture concluded
between Belize Construction
(Pty) Ltd, and Freelance Construction
(Pty) LTD, a company duly incorporated and registered, with its
principal place of business
situated at 54 Fritz Stockenström
Street, East End, Bloemfontein. The defendant is the Member of the
Executive Council for
the Department of Roads and Public Works,
Northern Cape Province (“the MEC”).
[2] The plaintiff and the defendant
entered into a written contract in terms of which the plaintiff
constructed a Secure Care Centre
in De Aar for the Department of
Social Services. The amount tendered and approved for the project was
R22 847 880-00. The plaintiff
asserts that it completed the work
according to the specifications and performed all its obligations in
terms of the contract.
The plaintiff maintain further that the
defendant improperly withheld an amount of R656 000-00 of the
contract price as a penalty
deduction. This accusation is denied by
the defendant.
[3] The plaintiff has, for the reasons
set out in para 2 (above), instituted action against the defendant on
01 February 2013 for
payment of R747 840-00 (R656 000-00 plus 14%
VAT) with interest at 15% per annum a tempora morae to date of
payment. According
to the plaintiff the defendant was not entitled to
withhold any payment due to it.
[4] The defendant raised a special plea
in terms of s 3 (2) (a) of the Institution of Legal Proceedings
Against Certain Organs of
State Act, 40 of 2002 (“the Act”),
that the plaintiff did not give timeous notice in writing of its
intention to institute
legal proceedings. It gave notice only on 07
June 2011 whereas it was claimed that the debt became due and payable
on 11 May 2010
more than six months after its claim was due. This
computation shows that the notice happened. It is common cause that
the plaintiff
has not applied for condonation for its failure to
serve such notice timeously in compliance with the Act. It is further
common
cause that the MEC has not given consent in writing for the
initiation of legal proceedings without such notice. The defendant
submitted that I should uphold the special plea and dismiss the
plaintiff’s claim with costs.
[5] The plaintiff asserts that the
cause of action is not for a ‘debt’ as contemplated in s
3 (1) of the Act, but for
the balance amount outstanding in terms of
the written contract. The plaintiff therefore disputes its obligation
to comply with
s (3) (2) (a) of the Act to give notice within six
months from the date on which the debt became due. It submits that
its claim
falls outside the definition of ‘debt’ and
characterised it as compelling specific performance and not claiming
for
damages.
[6] In Clauses 4.5.7, 4.5.10, 4.5.11,
4.5.12 and 4.5.14 of the plaintiff’s Particulars of Claim the
plaintiff pleads:
“4.5.7 The plaintiff is entitled
to a revision of the date for practical completion, and for which
revision the principal
agent shall not adjust the contract value, for
delays inter alia caused by inclement weather; inability to obtain
materials and
goods and default by a nominated subcontractor;
4.5.10 [T]he plaintiff shall, within 60
working days of the delay ceasing, submit such claim to the principal
agent, failing which
the plaintiff shall forfeit such claim;
4.5.11 [T]he principal agent shall, in
writing, within 20 working days after receipt of a claim grant,
reduce or refuse the working
days’ claim and determine the
revised date for practical completion in relation to work days
granted;
4.5.12 [W]here the principal agent
fails to act in terms of clause 29.7, the claim shall be deemed to be
refused;
4.5.13 [S]hould any disagreement arise
between the plaintiff and the defendant or its principal agent(s), as
to any matter arising
out of or concerning the agreement, either
party may give notice to the other to resolve such disagreement;
4.5.14 [W]here such disagreement is not
resolved within 10 working days of receipt of such notice it shall be
deemed to be a dispute
which shall be adjudicated by litigation.”
[7] Clause 29.7 alluded to in para 4.5
12 (above) provide that:
“29.7 The principal agent shall,
in writing, within twenty (20) working days after receipt of a claim
in terms of 29.6 Grant,
reduce or refuse the working days claimed.”
[8] The plaintiff maintains that 16
delayed claims were lodged with the principal agent. However, the
principal agent failed to
take a decision or to convey it within the
allocated period of 20 working days as set out above (para 4.5.11).
After having given
notice in terms of clause 40.1 of the contract to
resolve the disagreement, which remained unresolved after 10 days,
the plaintiff
declared a dispute in terms of clause 40 of the
contract.
[9] Clause 40.1 of the contract
stipulates that:
“40.1 Should any disagreement
arise between the employer or his principal agent or agents and the
contractor as to any matter
arising out of or concerning this
agreement either party may give notice to the other to resolve such
disagreement.”
[10] Adv Williams, for the plaintiff,
insisted that the defendant is under an obligation to make payment in
terms of the contract.
Specific performance is the recourse to take
in a claim sounding in money. He contended that the defendant could
not justify the
refusal to pay. The plaintiff in its argument relied
on the case of NICOR IT CONSULTING (PTY) LTD v NORTHWEST HOUSING
CORPORATION
2010 (3) SA 90
(NWM) where it was held in paras 29 and
30:
“[29] When a right is adversely
affected by legislation and particularly when such right is one
contained in the Constitution,
the offending provision must be
interpreted restrictively. If in interpreting the definition of
‘debt’ para (b) qualifies
the whole of para (a), then the
notice contemplated in s 3 of the Act would only have to be given
when the claim is one for damages.
If on the other hand para (b)
qualified only (i) and (ii) of para (a), then any action would be
subject to the provisions of s
3 of the Act.
[30] On a careful reading of the
definition of ‘debt’ contained in the Act, it is clear
that para (b) qualifies para
(a) as a whole. This in my view is the
‘ordinary and natural meaning’ of the words as they are
set out in the definition
of ‘debt’ in the Act. Nothing
that the defendant has raised has persuaded me otherwise. This
‘ordinary and natural’
meaning has been considered within
the context and purpose of the Act and I find that it does not offend
against the purpose of
the Act. More significantly, this ‘ordinary
and natural’ meaning makes fewer inroads into the rights of
access to courts
and equality enshrined in the Bill of Rights in the
Constitution. As such, this ordinary and natural meaning is to be
preferred
above the wider interpretation of the definition of ‘debt’
contended for by the defendant. Accordingly, I find that
para (b) of
the definition of ‘debt’ in the Act qualifies para (a) of
such definition, and consequently a ‘debt’
for the
purposes of the Act is confined to a claim for damages, however such
claim arose.”
The plaintiff also referred to the case
of THABANI ZULU & CO (PTY) LTD v MINISTER OF WATER AFFAIRS AND
ANOTHER
2012 (4) SA 91
(KZN) where the principle in Nicor’s
case was applied.
[11] Adv Danzfuss SC, on behalf of the
MEC, conceded that it is possible for the plaintiff to claim payment
of money by way of specific
performance. However, the fact that the
plaintiff added clauses 7.4 and 7.5 in its Particulars of Claim,
which clauses are normally
inserted in a claim for breach of
contract, is indicative of the fact that it is a claim for damages.
Counsel contended that the
plaintiff ignores the refusal by the
principal agent to pay the amount which was given rise by the breach
of the contract. Clauses
7.4 and 7.5 state:
“7.4 [T]he penalties have been
applied and deducted without consideration to the provisions of the
contract and the delayed
claims;
7.5 [H]ad the principal agent complied
with its obligations in terms of the agreement, the principal agent
would have granted the
delays and working days claimed, from which
the plaintiff would not have been liable for any penalties.”
[12] The crucial question that arises
is whether this claim is for specific performance or one for damages.
S 1 of the Act defines
a debt as follows:
“ ‘Debt’ means any
debt arising from any cause of action –
(a) Which arises from delictual,
contractual or any other liability, including a cause of action which
relates to or arises from
any –
(i) Act performed under or in terms of
any law; or
(ii) Omission to do anything which
should have been done under or in terms of any law; and
(b) For which an organ of state is
liable for payment of damages, whether such debt became due before or
after the fixed date.”
[13] S 3 (1) and (2) (a) of the Act
provide as follows:
“3. Notice of intended legal
proceedings to be given to organ of state. ---
(1) No legal proceedings for the
recovery of a debt may be instituted against an organ of state unless

(a) The creditor has given the organ of
state in question notice in writing of his or her or its intention to
institute the legal
proceedings in question; or
(b) The organ of state in question has
consented in writing to the institution of that legal proceedings-
(i) Without such notice; or
(ii) Upon receipt of a notice which
does not comply with all the requirements set out in subsection (2).
(2) A notice must –
(a) Within six months from the date on
which the debt became due, be served on the organ of state in
accordance with section 4 (1);
and
(b) Briefly set out –
(i) The facts giving rise to the debt;
and
(ii) Such particulars of such debt as
are within the knowledge of the creditor.”
[14] Innes CJ in FARMERS’ CO-OP
(REG) v BERRY
1912 AD 343
at 350 stated:
“Prima facie every party to a
binding agreement who is ready to carry out his own obligation under
it has a right to demand
from the other party, so far as it is
possible, a performance in terms of the contract.”
See also RAS AND OTHERS v SIMPSON
1904
TS 254
at 256 where the learned Judge enunciated:
“But if specific performance had
been asked for and decreed, and had not been carried out, it would
have been competent for
the plaintiffs in another action to have
asked, in lieu of that decreed, for cancellation of the contract and
damages. And if they
could obtain that relief by means of a second
action, I can see no reason in law why they should not ask
alternatively for it in
this action.”
[15] In my view the cases supra support
the contention of the defendant that the plaintiff’s claim is a
claim for damages.The
plaintiff declared a dispute with regards to
the penalties levied in Certificate 21 and the specified amount
payable to it. This
negates the refusal to grant the delays. There is
no clause in the contract which requires that when the plaintiff
declares a dispute
it is entitled to payment only if the principal
agent refuses to grant the delays. The plaintiff’s claim is
therefore not
what he is entitled to in terms of the contract.
[16] In my view the plaintiff’s
claim is for damages and not specific performance. The plaintiff was
obliged to give notice
within the prescribed six months from the date
on which the debt became due in terms of s 3 (2) (a) of the Act.
It is common
cause that the defendant did not consent in writing that
legal proceedings be instituted without the required notice as
alluded
to earlier. The special plea must therefore be upheld with
costs.
[17] The defendant sought the following
relief under the special plea:
“Therefore the defendant pleads
that [the] plaintiff’s claim be dismissed with costs.”
In the circumstances I grant the
following order:
1. The special plea raised by the
defendant, the Member of the Executive Council for the Department of
Roads and Public Works: Northern
Cape is upheld.
2. The plaintiff’s claim is
dismissed.
3. The plaintiff, Belize/Freelance
Construction Joint Venture, is ordered to pay costs on party and
party scale.
BM PAKATI
JUDGE
On Behalf of the Plaintiff: ADV
WILLIAMS
Instructed by: CJ DE JAGER ATTORNEYS
On Behalf of the Defendant: ADV
DANZFUSS (SC)
Instructed by: HAARHOFFS INC