About SAFLII
Databases
Search
Terms of Use
RSS Feeds
South Africa: Free State High Court, Bloemfontein
SAFLII
>>
Databases
>>
South Africa: Free State High Court, Bloemfontein
>>
2015
>>
[2015] ZAFSHC 252
|
|
Pro - Care Contracting (Pty) Ltd v Noqhaka Local Municipality and Others (3685/2015) [2015] ZAFSHC 252 (14 August 2015)
IN
THE
HIGH COURT OF SOUTH AFRICA
(FREE
STATE
DIVISION,
BLOEMFONTEIN)
Case
number: 3685/2015
In
the matter between:
PRO-
CARE
CONTRACTING
(PTY)
LTD
Applicant
and
MOQHAKA
LOCAL MUNICIPALITY
1
st
Respondent
THE
MUNICIPAL MANAGER: MOQHAKA
LOCAL
MUNICIPALITY
2
nd
Respondent
LOHAN
CIVIL
(PTY)
LTD
3
rd
Respondent
JUDGMENT:
MOCUMIE, J
HEARD
ON:
13 AUGUST 2015
DELIVERED
ON:
14 AUGUST 2015
Ex
Tempore Judgment: Urgent Application
1.
The opposing and replying papers in this matter were filed on 13
August 2015, immediately after Motion court whiich adjourned at
11h00. The arguments were heard from 12h00 until
16h50.The judgment that follows will not be as comprehensive as it
would have been had there not been serious time constraints
prevailing. Judgments referred to by both counsel will not be
specifically
highlighted due time constraints but the principles
encapsulated in those judgments albeit not all will be considered
from time
to time when..certain points are made. The applicant,
represented by Mr Louw, has approached this court
on an urgent basis to seek interim relief against the 1st, 2nd
and 3rd respondents pending institution of a review in terms
of R53
of the Practice Rules of this court. The 3rd respond is the
successful bidder in the tender in dispute; cited only as an
interested party. Mr Lauw submitted that the applicant became aware
albeit it not through the 1st respondent that its bid was
unsuccessful sometime in June 2015. It then sought such decision from
the 1st respondent without success. By 14 July, the 1st respondent
sent communication informing it of its decision but without full
reasons. As a result, it approached this court on 21 July 2015
for an
order compelling the 1st respondent to provide it with more details
and relevant documentation including any recommendations
made
by the relevant Committees responsible for the evaluation and
adjudication of tenders. Such order was granted on the same
day. The
applicant could only have insight of all these documentation after
this court order by 28 July 2015. Only then could it
appreciate what
had happened and brief counsel to challenge the decision(s) of the
respondents. Thus this application.
2.
Mr Ayayee, appearing on behalf of the 1st respondent,
argued that there was no urgency in the matter as the applicant had
failed to make out a case for urgency as required by Rule 6(12) (b)
in that by 14 July 2015 the applicant was aware of the fact
that it
was unsuccessful and the reasons for its exclusion including that its
bid was unresponsive. Notwithstanding the sparse
details provided as
it alleged, he submitted, the applicant
should have approached this
court
then. He submitted
further
that the applicant had failed to satisfy the requirements for the
granting of an interim interdict as set out in
Setlogelo v
Setlogelo
1
which are: (a) a prima facie right ;(b) a well-grounded
apprehension or irreparable harm if the interim relief is not granted
and
the ultimate relief is eventually granted; (c) a balance of
convenience in favour of the granting of the interim relief; (d) the
absence of any other satisfactory remedy. These requirements
have been confirmed recently by the Constitutional
Court in
National Treasury
and
Others
v
Opposition
to
Urban
Tolling
Alliance and Others
2
.
3.
The authoritative case on urgent applications is the old but
still reliable case of
Luna Meubelvervaardigers
(Edms)
Bpk
v Makin
(t
l
a Makin's
Furniture
Manufacturers)
3
where the court stated:
'The
following
factors
must
be
borne
in mind
.
They are stated
thus
,
in ascending
order of
urgency
:
1.
The question
is
whether
there must
be
a
departure
at
all from the times prescribed
in Rule
6
(5)
(b)
.
Usually
this
involves
a
departure
from
the
time
of seven
days
which
must
elapse
from
the
date
of
service
of
the papers
until
the
stated
day
for
hearing.
Once
that
is
so
,
this
requirement may
be
ignored and
the
application may
be
set
down
for hearing
on
the
first
available
motion
day
but
regard
must
still
be
had
to the necessity
of
filing
the papers
with the
Registrar
by
the preceding
Thursday so
that
it can
come
onto
the following
week's motion
roll
which
will be prepared
by
the
Motion Court Judge
on duty for that week
.
2.
Only if
the matter
is so
urgent
that the applicant
cannot
wait for
the next
motion
day
,
from
the point
of
view
of
his
obligation
to
file
the papers
by
the
preceding Thursday
,
can he consider
placing
it on the
roll for the
next
Tuesday, without having
filed his papers
by the previous
Thursday.
3.
Only if the urgency be such that the applicant
dare
not
wait even for the next
Tuesday,
may he set
the matter
down for hearing
in the next
Court day
at the
normal time of
10
.
00
a.m.
or for
the same day if the Court has not yet
adjourned.
4.
Once
the
Court
has
dealt
with
the
cases
for
that
day and
has
adjourned,
only
if
the
applicant
cannot
possibly wait
fdr
the
hearing
until
the
next
Court
day
at
the normal time
that
the
Court
sits
,
may
he
set
the
matter
down
forthwith for
hearing at
any
reasonably
convenient
time,
in consultation
with the Registrar
,
even if that be at night
or during
a
weekend
.
Practitioners
should
carefully
analyse the facts
of each
case
to determine,
for the
purposes of
setting
the
case
down
for
hearing,
whether
a
greater
or
lesser
degree
of relaxation
of the Rules
and of
the ordinary practice
of the
Court
is
required.
The degree of
relaxation
should
not
be
greater
than the
exigency
of
the
case
demands.
It must
be
commensurate
therewith.'
4.
The authoritative decision on interim and final interdicts remains
the decision of
Setlogelo
v
Setlogelo
4
to
which both the Supreme Court of Appeal and the Constitutional Court
also refer and rely upon.
5.
Mr Ayayee submitted that the applicant has failed to satisfy any of
the
Setlogelo
requirements, highlighting the requirement of
'balance of convenience' as expanded and adapted by the
Constitutional Court recently
in
National
Treasury
and
Others v Opposition
Urban Tolling
Alliance
5
.
6.
Having considered the requirements set out in
Luna Meubels
above, I was satisfied that the application was urgent because
the application could not be allowed to have been set down in
accordance
with the normal court roll. Firstly, it could not be
expected of the applicant to rush to court without anything in
writing from
the respondents. But not only something in writing, but
in particular the decision(s) of the 1st respondent and the relevant
Committees
and other relevant documents which indicate why its bid
was found to be unresponsive. This would enable it to determine
whether
to challenge the decision(s) of the 1st respondent or accept
same. Had it come to court without such details, surely this court
would have had to say the application.was premature and unfounded.
This is so, taking into account that the successful bidder had
already moved on site to start with the work tendered for; which is
in dispute between the applicant and the respondents. To treat
the
matter as an ordinary application would have frustrated the very
purpose of an urgent application in the prevailing circumstances.
I
was also of the considered view that the ve.r.y crux of this
application was to allow the parties to be heard by a court
of law on
whether the decision of the 1st and 2nd respondent should be set
aside, if such decisions are found to have been made
unlawfully and
contrary to the provisions of s217 of the Constitution and relevant
legislations governing municipalities including
the 1st respondent.
None of that could have been properly dealt with until we had
,proverbially , jumped over the first hurdle
i.e until a ruling had
been made that the application was urgent. For these reasons I
granted prayer 1 of the Notice of Motion.
7.
I will revert to prayer 2 hereafter.
Prima
facie right
8.
As far as the first
Setlogelo
requirement (prima
facie right) is concerned , I am satisfied that the applicant has
established a prima facie right. It formed
part of a number of
bidders who were considered for a particular bid. The decision
that found its bid to be unresponsive
is an administrative one
subject to be reviewed by a court of law. This was the agreed premise
from which this case proceeded.
Irreparable
harm
9.
The second requirement caused no consternation between the parties
suffice to say that parties made their submissions clear.
Mr Louw
indicated that the harm the applicant will suffer will of course be
financia l. The applicant is in business. To the extent
that its
livelihood had been adversely affected, it had every right to
approach this court. Mr Ayayee made the point that the 1st
respondent
will not only suffer financially by being exposed to possible 'Stay
In' costs from the 3
rd
respondent for the period it would
not have worked pending the review application ; but the community it
serves will continue suffer
harm in that the sewerage spillage
complained of may contaminate the river from which the community gets
its water supply.
10.
As alluded to earlier on, the sewerage problem 1st respondent
complained about, it is common knowledge that this problem has
plagued 1st respondent for a long time. To use that now in these
proceedings as leverage to prevent the applicant from seeking
relief
from this court is neither fair nor justifiable in the circumstances.
The work to be done, as it stands unrefuted, is for
renovation of
existing work. No more harm than already suffered can be expected in
the time it will take this court to dispose
of the review
application. 1st respondent is in any event expected to put interim
measures in place which can alleviate the plight
of the community
such as putting up tanks which can be used later for some other
project(s).
Balance
of Convenience
11.
With regard to prayer 3, taking into account what the Constitutional
court has said in the
Urban Tolling
6
case
on how the enquiry on 'the balance of convenience' should be
conducted under our constitutional dispensation;
I
am conscious that once work is stopped, it will have adverse
consequences on the community and reflect badly on the 1st
respondent; and create the impression that 1st respondent was not
taking its responsibility to provide its community with a safe
and
healthy environment seriously . However not to interdict 1st and 3rd
respondent from commencing with work flowing from a highly
contested
bid will lead to the same situation in which the Constitutional Court
found itself in
AllPay
7
where work of 20 months complicated the resolution of the case
after the Constitutional Court found that the bid was unlawful and
unconstitutional. Similar cases are well known in this Division and
other Divisions across the country. Surely the Constitutional
Court
cannot be understood to say or suggest and encourage courts not to
consider each case on its own facts.
12.
On the issue that the applicant will not succeed in court on its
application as submitted by Mr Ayayee, I am not persuaded that
such a
blanket assumption can be made. It is only upon a thorough perusal of
the papers laid bare by the 1st respondent and made
available to a
panel of two Judges upon application by the applicant that such a
conclusion or a different one for that matter
can be reached. To make
the assumption at this stage that the applicant has no prospects of
success will literally amount to shutting
the door of this court to
the applicant; which is in direct conflict with its constitutional
right to access to courts provided
for in s34 of the Constitution of
our country.
Alternative
remedy
13.
On the submission that the applicant in any event has an alternative
remedy in the form of damages, I do not wish to engage
in this
possibility that such claim may be lodged. Even if the applicant was
to pursue that route, the 1st respondent would suffer
financial
prejudice either way. The fad that the 1st respondent may lose funds
already allocated in this financial year for this
purpose can be
dealt with within its own finance management structures. As I see it,
the funds have already been ring-fenced for
this purpose and cannot
be used for any other purpose especially as this matter ought to be
resolved by this court in less than
three months. Without preempting
the outcome of the court of review, the consideration of the
alternative remedy which the applicant
may institute later may
just legitimize conduct which may be found to be unlawful by that
court. That cannot be the correct
approach.
14.
To show that this court has indeed given attention to all the factors
placed before it particularly the prejudice the 1st respondent
has
submitted it will suffer, ie that the community will be adversely
affected by any delay of this matter, and that the funds
may be taken
back by the provincial financial authority, this matter will receive
preferential treatment. It will, in consultation
with the Judge
President of this Division, be placed on the roll on any Monday
during this term. In that way the R53 review can
be expedited and
disposed of finally with all parties able to move on without any
doubt in their minds. For these
reasons I am
inclined to grant prayer 3 of the Notice of Motion.
15.
I now revert to prayer 2 of the Notice of Motion. In my considered
view ,based on the conclusion I have come to in respect of
prayers 1
and 3 ,it would make no sense at all not to grant prayer 2 as well
for the simple reason that not doing so would fly
in the face of the
findings I have already made. I am thus inclined to grant prayer 2 as
well. From the discussion above, I am
satisfied that the applicant
has satisfied all the
Setlogelo
requirements.
16.
Finally, on these facts, the applicant came timeously to court; ie
before the horse had already bolted. No work has commenced
yet.
Without putting too much emphasis on the sewerage problem which has
plagued Moqhaka municipality for a very long time; in
my considered
view; the balance of convenience favours the applicant, to have this
matter resolved once and for all by a court
of law; conscious of the
separation of powers between the different arms of government as
always; and deferring that which should
be deferred to the relevant
arm of government if and when necessary.
17.
In so far as costs are concerned the general rule applicable is well
known and need no repeat suffice to say that I have no
reason to
deviate from it.
18.
In the result I grant the following order:
ORDER
1.
An order is granted in terms of prayers 1, 2, 3 and 4 of the Notice
of Motion.
2.
The applicant is to enroll the application in terms of Rule 53 within
10 days from the date of
this order, on 28 August 2015.
3.
The 1st and 2nct respondents to file their replying affidavit within
5 days from the date on which the applicant
would have filed the
application in terms of Rule 53, on 4 September 2015.
4.
The applicant to file its replying affidavit within 5 days from the
date on which the respondents would have filed
their answering
affidavit, on 11 September 2015.
5.
The application in terms of Rule 53 to receive preferential
allocation and be enrolled on any Monday during this
term, in
consultation with the Judge President of this Division.
6.
Costs of the application to be costs in the cause.
__________________
B.C.
MOCUMIE, J
APPEARANCES
On
behalf of the appellant:
Adv Louw (FS Bar)
Instructed by:
Payper Attorneys
Bloemfontein
On
behalf of the respondent:
Adv Ayayee (Jhb Bar)
Instructed by:
Majavu Incorporated
Johannesburg
1
Setlogelo v Setlogelo
19
.
14
AD 221 at 227. See also
Eriksen
Motors
Welkom Ltd
v Protea
Motors
,
Warrenton and Another
1973 (3) SA 685
(A) at 691
C-E.
2
National
Treasury
and
Others
v Opposition
to
Urban
To
il
ing
Alliance
and
Others
2012
(6) SA 223
(CC).
3
Luna
Meubelvervaardigers
(Ed
m
s
)
Bpk
v Makin
(tla Makin 's Furniture
Manufacturers)
1977 (4)
SA
135
(W)
at
136
H
-137F
.
4
Setlogelo v Setlogelo
above.
5
National
Treasury
and Others v Opposition
to
Urban
Tolling
Alliance
and
others
above
.
6
National
Treasury
and Others v Opposition to Urban
Toll
ing
Alliance
and
others
above
.
7
All Pay
Consolidated
Investment Holdings
(Pty) Ltd and Others v Chief
Executive
Officer
of the South African
Social
Security Agency
and
Others
2014 (1) SA 604 (CC).