About SAFLII
Databases
Search
Terms of Use
RSS Feeds
South Africa: Kwazulu-Natal High Court, Pietermaritzburg
SAFLII
>>
Databases
>>
South Africa: Kwazulu-Natal High Court, Pietermaritzburg
>>
2016
>>
[2016] ZAKZPHC 53
|
|
Carmel Nurseries CC v Dube Tradeport Corporation (7660/2014) [2016] ZAKZPHC 53 (21 June 2016)
IN THE HIGH COURT OF SOUTH
AFRICA
KWAZULU-NATAL DIVISION,
PIETERMARITZBURG
CASE
NO: 7660/2014
DATE:
21 JUNE 2016
In the matter between:
CARMEL NURSERIES
CC
....................................................................................................
Applicant
And
THE
DUBE TRADEPORT
CORPORATION
....................................................................
Respondent
In
re:
CARMEL
NURSERIES
CC
.......................................................................................................
Plaintiff
And
THE
DUBE TRADEPORT
CORPORATION
......................................................................
Defendant
Coram:
Koen J
Heard:
8 June 2016
Delivered:
21 June 2016
O
R D E R
The application is dismissed with costs.
J U D
G M E N T
KOEN J
[1] On 19
September 2014 the Registrar of this court granted default judgment
against the Applicant for:
‘
(a)
Payment in the sum of R 2 299 736.82;
(b)
Payment in the sum of R182 005.40;
(c)
Interest on the aforesaid amounts
a tempore morae
at the rate
of 9% per annum from the date of judgment to date of payment;
(d)
Costs in the amount of R650.00 plus Sheriff’s fees.’
The
judgment in the sum of R2 299 736.82 was in respect of
arrear and unpaid rental, electricity and water charges, and
interest
thereon. These arose from the terms of a written lease agreement
concluded between the Applicant and the Respondent dated
20 February
2012. The judgment in the sum of R182 005.40 relates to the
costs to repair and restore the leased premises to
the condition they
were in at the commencement of the lease, after the Applicant vacated
the leased premises. The judgment
was granted by default after
the Applicant had failed to deliver its plea timeously and had been
properly barred from delivering
such plea.
[2] Before
the default judgment was granted a letter dated 29 August 2014 was
addressed by the Applicant’s then attorneys
to the Respondent’s
attorneys the relevant part whereof read as follows:
‘
1 …
2. We confirm
that our client is not of the intention to further litigate in this
matter. It is for this reason that our client
did not file any Plea
or Counterclaim.
3. We
trust you find the above in order and would be pleased to hear from
you once your client has provided you with further instructions
subsequent to Judgment granted.’
[3] On 30
June 2015 the Applicant launched the current application in which it
claims that:
‘
1.
The judgment of the Respondent in this matter granted by default on
or about 9 September 2014
[1]
is rescinded
2.
The Applicant is granted leave to defend the action.
3.
The Respondent shall pay the costs of this application.’
[4] In
amplification of the legal basis on which the application is pursued,
Mr Wilson for the Applicant explained that the relief
claimed was
more appropriately:
(a) for a
reconsideration of the judgment granted by the Registrar pursuant to
the provisions of rule 31(5)(d); alternatively
(b) for
the rescission of the judgment at common law.
[5] Rule
31(5)(d) provides that:
‘
Any
party dissatisfied with a judgment granted or direction given by the
Registrar may, within 20 days after such party had acquired
knowledge
of such judgment or direction, set the matter down for
reconsideration by the court.’
[6] A
Registrar may grant judgment only in respect of claims for a ‘debt
or liquidated demand…’ The judgment
for R2 299 736.82
was clearly such a judgment whereas the one for R182 005.40,
being
prima facie
for damages, was not. It was contended that
‘the reconsideration’ contemplated by rule 31(5)(d) is
not confined to
a reconsideration of the judgment for R182
005.40 but would include a reconsideration of the entire judgment.
The argument
would relate inter alia to the legal nature of such a
‘reconsideration’ and whether it is confined to a
judgment which
might not be legally competent, or whether it is a
‘reconsideration’ akin to that contemplated by Rule
6(12)(c) where
‘a person against whom an order was granted in
his absence in an urgent application may by notice set down a matter
for reconsideration
of the order’.
Erasmus Superior Court
Practice
2
nd
Edition by van Loggerenberg in the
commentary on Rule 31(5)(d) states as follows:
‘
Sub-rule
[31(5)(d)] has, however, elicited conflicting judgments. In
Bloemfontein
Board Nominees Ltd v Benbrook
[1996
(1) SA 631
(O) at 633 H] it was held that the “reconsideration”
of a default judgment granted by the Registrar in terms of the
sub-rule did not mean that the court substituted its discretion for
that of the Registrar, but that the court would interfere with
the
judgment for direction given by the Registrar only if it was of the
opinion that the Registrar had erred. In
Pansolutions
Holdings Limited v P & G General Dealers and Repairers CC
[2011 (5) SA 608
(KZD) at 610 H – I] it was held that the power
accorded to the court under this sub-rule was that of substituting
it’s
discretion for that of the Registrar. In addition, it was
held that the “good cause” criteria applicable under Rule
31(2)(b) be applicable when a court, in terms of this sub-rule,
reconsidered a default judgment granted by the Registrar. It is
submitted that the latter view is to be preferred.
Alternatively, a default judgment granted by the Registrar could be
set
aside by the court in the exercise of its common law powers or
its inherent jurisdiction referred to above.’
[7] In
view of the conclusion to which I have come, it is unnecessary to
resolve the aforesaid issues. I shall assume in favour
of the
Applicant that the test is no different to that which founds a
rescission. ‘Good cause’ must however be shown
to exist
whether a ‘reconsideration’ in terms of rule 31(5)(d), or
a rescission at common law, is sought.
[8] The
requirement of ‘sufficient’ or ‘good cause’,
lying at the heart of either a reconsideration in terms
of rule
31(5)(d) or a rescission at common law, requires:
(a) a reasonable and acceptable
explanation for an Applicant’s default; and
(b) the disclosure of a
bona
fide
defence with
prima
facie
prospects of success.
[2]
[9] The
only additional requirement of significance in the context of the
present application between rule 31(5)(d) finding application
or a
rescission being claimed at common law, is that in the case of the
former, the application for reconsideration must be brought
within 20
days, whereas an application for rescission only needs to be pursued
within a reasonable time. The application was clearly
launched way
beyond the 20 day period. The applicant has applied, based on
allegations advanced in the founding affidavit, although
not claimed
as a separate prayer
[3]
in the Notice of Motion, for any delay, whether beyond the 20 day
period or beyond a reasonable time, to be condoned. In
either
instance though, a reasonable explanation for delay must be advanced
and it is trite law that it must cover the entire period
or periods
of delay.
[4]
[10] The
explanation tendered by the Applicant for condonation, whether for
the failure to pursue an application in terms of Rule
31(5)(d) within
20 days or in only pursuing the application on the 30
th
June 2015, is inadequate and unacceptable. The reasons advanced by
the Applicant in the founding affidavit are as follows:
’
28
…the Applicant could no longer afford to incur any further
legal costs in defending the Respondent’s action…
29
… William Minne who was the general manager of the Applicant
at the time, and the only person dealing on behalf of the
Applicant
with engagement with the Respondent, was immobilised in August 2014
owing to a knee operation he had to undergo. During
the period
September 2014 up until December 2014, Mr Minne was rendering
consultancy services to a greenhouse operation in New
York, USA,
while out of the RSA, and as such, was unaware that the default
judgment had actually been taken against the Applicant.
30
Notwithstanding the above, in and during the period February 2015 to
March 2015. Mr Minne came to learn through perusing various
articles
and various different newspaper publications that the Respondent’s
CEO at the time, namely Saxen van Coller had
acted fraudulently in
that
inter alia
she lied about her identity and her
qualifications.
31
I immediately thereafter sought further legal advice because it was
the conduct of the Respondents CEO Saxen van Coller, that
had been
the cause of the Applicant losing the crucial Holland contract.
32
Upon seeking alternative legal advice on this issue, I was informed
that the Applicant indeed has a counter claim against the
Respondent
in the amount of R38 559 776.00 as a result of the
Respondents breaches of contract.’
[11]
The aforesaid explanation does not begin to explain why, where the
Applicant inevitably must have been aware that judgment
would follow
as recognized in its attorney’s letter dated 29 August 2014, an
application for rescission was not brought earlier.
The explanation
relating to the absence of Mr Minne and his physical incapacity, does
not detract from him being able to give telephonic
instructions to an
attorney to rescind the judgment if that was in fact the intention.
Furthermore, the fact that Mr Minne
and the deponent to the finding
affidavit had come to hear of the alleged fraud of Saxen van Coller,
also does not provide an explanation
for the delay in pursing the
application. Mr Wilson in argument fairly conceded that the
reports regarding Ms Van Coller
was at best simply a reminder to the
Applicant of its dealings with the Respondent and not specifically
alerted it to any alleged
defence it previously would not have known
of, or the existence of a counterclaim.
[12]
The explanation that until seeking legal advice, the Applicant was
not aware of a counterclaim that it alleges it had, is also
contradicted by the contents of the letter from the Applicant’s
attorneys dated 29 August 2014. That letter was clear in
its terms
that the Applicant had no intention to further litigate in the matter
and it was for that reason that it ‘did not
file any plea or
counterclaim’
(my underlining). That statement in the letter is consistent with the
possibility of a counterclaim having been considered and
instructions
thereafter being given not to file any counter claim. The Applicant
has not in any of the affidavits filed on its
behalf dealt with this
conflict between the instruction given to its attorney and expressed
in that letter, and what is contended
in the affidavits regarding
knowledge of the alleged counterclaim which its only member alleges
it only gained subsequently and
which it now wishes to pursue. There
is not even a suggestion in the papers that what the attorney
recorded in the letter to the
Respondent’s attorneys was
contrary to the instructions of the Applicant and therefore written
in error. Indeed, the affidavits
do not deal with the letter at all.
The Applicant simply has not advanced any evidence on the basis of
which condonation can be
granted. Nor is there any basis on which it
can be concluded, even accepting the correctness of the Applicant’s
version that
it only became aware during February to March 2015 of
the counter claim it wishes to pursue, that the delay until the
application
was launched at the end of June 2015 was reasonable and
excusable.
[5]
[12]
Not only has there been no reasonable and acceptable explanation for
the aforesaid delays, but there is also no reasonable
and acceptable
explanation for the Applicant’s default in the first place. On
29 August 2014 the unequivocal communication
was that the Applicant
would not be filing any plea or counterclaim. If the Applicant had a
bona fide
defence with a
prima facie
prospect of success it should have pursued it at the time.
[13] In
support of its contention that the Applicant has a defence, the
deponent to the founding affidavit states:
‘
27
In regards to the Respondents claim against the Applicant the
Applicant initially disputed the amount claimed by the Respondent
in
that:
27.1
Cleaning costs were charged to the Applicant’s account, however
the Applicant had cleaned the premises prior to vacating
the
premises;
27.2
An amount was charged to the Applicant for lighting, however, part
of this amount had already been settled by the Applicant;
27.3
The electricity meter readings were incorrect. Therefore, the
amounts charged in respect of the Applicant’s alleged
electricity consumption were incorrect.
28
Notwithstanding the above at the time of the above, owing to the fact
that the Applicant had not been able to secure the contract
mentioned
above, the Applicant could no longer afford to incur any further
legal costs in defending the Respondent’s action…”
[14]
Elsewhere in the affidavit the deponent apart from referring to the
cleaning costs, the amount wrongly charged for lighting
and the
electricity metres allegedly reading incorrectly, also contends that
‘an amount of approximately R208 000.00
was paid to the
Respondent by means of a bank guarantee which was called up by the
Respondent, which amount has not been credited
to the Applicant’s
account.’ During argument Mr Wilson fairly conceded that
the statement that the payment was
not reflected was incorrect and
that the payment of R208 000.00 had in fact been credited to the
Applicant’s account.
[15]
Not only were the alleged defences regarding the alleged cleaning
costs and electricity charges known at the time, but no particularity
is provided in the affidavits in the application as to what cleaning
costs were allegedly unnecessarily incurred and for which
judgment
had been granted, or to what extent the electricity meter readings
were incorrect, resulting in excessive charges, and
hence to what
extent, if any the Applicant might have been overcharged and the
judgments should be reduced. The lack of such particularity
strikes
at the
bona fides
of any defence that could be advanced.
[16] Mr
Wilson conceded that there was a lack of particularity but
nevertheless urged me to exercise my discretion to recognise
that
there might be some defence which could be advanced which would
entitle the Applicant to rescission of the judgment. I am
not
prepared to do so. It is incumbent on the Applicant to set out
details of a defence, including the extent of such defence,
which if
proved at the trial would constitute a
bona
fide
defence with
prima
facie
prospects of success. It has not
done so. I am not persuaded that the Applicant has made out a
bona
fide
defence with
prima
facie
prospects of success which would
entitle it to rescission.
[17]
All that remains to be considered then is the contention that the
Applicant has a substantial counterclaim which would extinguish
the
amount of the judgment granted in favour of the Respondent.
[18] I do not
intend repeating the extensive allegations advanced in the affidavits
which it was argued would give rise to such
a counter claim.
Suffice it to say that any such claim which the Applicant might have
would be one for contractual damages
and that if regard is had to the
allegations as to when the alleged breaches of the composite
agreement the Applicant contends
for occurred, that such claims would
have arisen during or about October 2012 to January 2013 (in respect
of claim A) and
somewhere during 2011 (in respect of claim B)
and similarly in regard to claim C, where at best for the Applicant
such claims could
also only have arisen it seems, by the latest by
January 2013. There is a very real likelihood that these claims have
all prescribed,
a fact confirmed by the Applicant having also
instituted a separate action under case number 8337/15 based on the
same causes of
action and for similar amounts as would be pursued in
respect of the counterclaim, to interrupt prescription.
[19]
The claim being one for damages, and the Respondent being an organ of
state established in terms of s 2 of the KwaZulu-Natal
Dube Tradeport
Corporation Act 2010, the provisions of the Institution of Legal
Proceedings Against Certain Organs of State Act
2002 (‘the
Act’) were required to be complied with. No notice as
required in terms of that Act has been sent
to the Respondent in
respect of the alleged counter claim.
[20] No
such notice was sent to the Respondent in respect of the action under
case no. 8337/15 either. Consequently an application
was brought in
that action in which the Applicant sought an order in terms of the
provisions of sub-section 3(4)(a) of that Act
for condonation for the
late delivery of its notice in terms of sub-section 3(1)(a).
That application came before Lopes J
who on 3
rd
June 2016 found that there was no reasonable explanation for the
delay in pursuing this claim, and consequently that condonation
should not be granted. The application was dismissed with costs.
[21] Mr
Wilson submitted that the refusal of condonation in respect of that
action would not be fatal to the intended counterclaim.
He argued,
with reference to the decision in
Dauth
and others v Minister of Safety and Security and others
[6]
that the Legislature did not intend a ‘premature’ summons
devoid of such notice to be ineffective or void. That case
however
held that once condonation was granted, the legal proceedings
instituted remain effective as from the date of inception
(date of
issue) and no further order for the resurrection of those proceedings
was required. I accept the correctness of that judgment.
It
however did not deal with the situation where condonation is refused
and whether the institution of that action would then still
interrupt
prescription. I not believe that it will. Unless and until a legal
process is instituted following the requisite notice
being given, or
until condonation for the failure to give such notice is granted,
prescription will not be interrupted.
[22]
Argument was also addressed before me as to whether where a
counterclaim is pursued, such notice would be required to be given.
The provisions of s 3 referred to ‘institute’. With
reference to the provisions in the Small Claims Court Act
No 61 of
1984, also dealing with the meaning of the word ‘institute’,
Hurt J in
Raman v Barlow Motor
Investments (Pty) Ltd t/a Natal Motor Industries, Prospecton, and
others
[7]
held, in the context of that Act that a counterclaim in the Small
Claims Court could be instituted without being preceded by the
requisite notice required in terms of the provisions of the Small
Claims Act. That position is in my view to be distinguished from
the
facts in this matter. The provisions of the
Institution of Legal
Proceedings Against Certain Organs of State Act are
there to provide
timeous notification, within 6 months of any event giving rise to a
claim for damages, to the relevant organ of
state in order to secure
evidence, preserve documents and to ensure that the necessary
investigations are done when the facts are
still fresh in the minds
of potential witnesses. If this notice is not given, then in
the absence of condonation being granted,
a complete defence in
abatement is afforded to the Defendant. Were an action to be
instituted and a counterclaim is filed
within the 6 month period, the
failure to provide such notice will readily be condoned. The
position is however entirely
different where a party having a claim
available to it against an organ of State, does nothing for the
period of 6 months stipulated
in the Act and beyond, but when
fortuitously sued by the particular organ of State thereafter, then
wishes to pursue a counterclaim
for damages. It would be absurd that
in such an instance it can validly pursue a claim by way of a counter
claim, where if it wished
to institute a separate action (as the
Applicant in
casu
did)
a notice would be required and if not given, or the failure not to
give such notice is not condoned, it has no valid action.
It seems to
me that the denial of condonation by Lopes J is not only fatal to the
separate claim for damages sought to be pursued
by the Applicant
under case number 7660/14, but would also, if condonation was sought
in respect of any proposed counterclaim to
be lodged beyond the six
month period, be highly unlikely to be granted. That casts
serious doubts on whether the Applicant
would have a counter claim
with
prima facie
prospects of success.
[23] In
any event it appears, as alluded to briefly earlier, that on the
Applicant’s own version and its reasons for pursuing
the
separate action under case number 8337/15, that any counterclaim it
might wish to pursue in the future could be met successfully
by a
special plea of prescription, and hence that such counterclaim would
not have
prima facie
prospects
of success.
[24] I
am accordingly of the view that the Applicant has not shown that it
has a
bona fide
counterclaim with
prima facie
prospects
of success which could extinguish the Applicant’s claims
for which judgment had already been obtained.
[25]
The Respondent has also raised other defences including that on the
provisions on the lease, notably clause 30.1 which is to
the effect
that the written lease ‘embodies the entire agreement between
the parties relating to the matters dealt with herein
and no
representations, warranty, undertakings or promises were made except
as incorporated herein’, precludes reliance on
an alleged
‘composite agreement’ contended for by the Applicant
which is partly written and partly oral. The terms
on which the
Applicant would rely for any counterclaim are oral terms not embodied
in the written lease document. This might also
detract from a valid
counterclaim. In view of the conclusion to which I have come earlier
I do not express any definite view on
this argument.
[26] In
the circumstances, the application is dismissed with costs.
KOEN J
Appearances
For the Plaintiff: Adv. A J Dickson SC
Instructed by: PKX Attorneys
Tel.: 033 347 5354
Ref.: M Potgieter
For the Defendant: Adv. A D Wilson
Instructed by: Spellas Lengert Kubler Braun Inc
c/o Jon White Attorneys
Tel.: 033 342 0280
Ref.: Jon White
[1]
The date is incorrect and should read ‘19
September 2014’.
[2]
Chetty v Law Society, Transvaal
1985 (2) SA 756
(A) at 764J to 765F.
[3]
The absence of a separate prayer in the Notice of
Motion is not fatal to the Applicant’s case. Such formalism
and technicality
are not required nor encouraged – see
Pangbourne Porperties Ltd v Pulse
Moving CC and Another
2013 (3) SA 140
(SGJ).
[4]
Ethekwini Municipality v Ingonyama Trust
2014 (3) SA 240
(CC) at para 28.
[5]
The effect of this finding is that the judgment for damages granted
by the Registrar, which would otherwise be beyond the powers
of the
Registrar, stands. That is an inevitable consequence of an
inexcusable delay and the ideal that legal certainty should
be
achieved, just as unlawful administrative action stands as valid
unless and until successfully challenged – see
Oudekraal
Estates (Pty) Ltd v City of Cape Town and others
2010 (1) SA 333
(SCA) para 33 ffg.
[6]
[2008] ZANCHC 26
;
2009 (1) SA 189
(NC).
[7]
1999 (4) SA 606
(D) at 608B.