LDM Consulting v South African National Roads Agency Society Ltd (SANRAL) (1490/17) [2017] ZAKZPHC 8 (7 March 2017)

80 Reportability
Public Procurement

Brief Summary

Tender — Interpretation of tender conditions — Applicant sought interim relief to interdict the award of a tender for construction pending a review — The court considered the interpretation of a specific condition (Q14) regarding the participation of key persons in multiple tenders — The respondent disqualified the applicant's tender based on the participation of a key person in another consortium bid — The applicant argued that the condition was ambiguous and unreasonable — The court held that Q14 was not ambiguous, irrational, or unreasonable, and the respondent's rejection of the applicant's tender was justified, leading to the dismissal of the application with costs.

Comprehensive Summary

Summary of Judgment


Introduction


This was an urgent interlocutory application for interim interdictory relief in a public procurement context. The applicant, LDM Consulting, sought an order interdicting the South African National Roads Agency Society Ltd (SANRAL) from awarding a tender scheduled for 10 March 2017 relating to the construction of SANRAL’s office building, pending the outcome of a review application which LDM Consulting indicated it intended to launch.


The matter came before the KwaZulu-Natal Division of the High Court, Pietermaritzburg, and was decided by Pillay J. The relief sought was interim in nature and was directed at preserving the status quo in the tender process until the contemplated review could be determined.


Although framed as an interim interdict, the judgment records that the singular issue the court was required to determine for purposes of the urgent relief was the interpretation and application of a tender clarification (referred to as Q14) governing whether the same “key person” may be proposed in different tenders, and whether SANRAL’s disqualification of the applicant’s bid on that basis was justified on the papers placed before the court.


Material Facts


SANRAL issued a tender for the construction of its office building. During the tender process, a clarification question and answer (Q14) was recorded in the following terms:


Q – Can the same key person be proposed in different tenders?

A – A key person may only be proposed in different tenders if the person is sub-consulting in each of the tenders and not submitting a tender in his/her own name or the name of his/her company where the person is employed.


It was common cause that LDM Consulting submitted a tender in which it included LSG International as a sub-consultant, and that Mr D Govender (from LSG) was nominated as the relevant key person in LDM Consulting’s bid.


It was also common cause that another bidder, Aecom Consortium, submitted a separate tender. Aecom’s tender also involved LSG, although (on the judgment’s account) LSG’s participation in Aecom’s bid was not initially obvious and became apparent when SANRAL called for clarification. Aecom then provided a letter disclosing that it would enter into a joint venture arrangement should it succeed in its bid, with Aecom SA proposed as lead consultants and LSG included as a consultant for the project. Mr D Govender signed that letter on behalf of LSG as the “principal partner.”


SANRAL disqualified both LDM Consulting and Aecom. By letter dated 7 December 2016, SANRAL informed LDM Consulting that it had failed to meet minimum quality criteria and that its financial offer was returned unopened. LDM Consulting requested further reasons by email on 12 January 2017, and SANRAL responded (a few hours later) that the disqualification was because the mechanical engineer key position in LDM Consulting’s tender was sub-consulted to Mr Govender of LSG, but Mr Govender had also “submitted another tender in his own name/name of his company” as part of a consortium/joint venture partnership. SANRAL stated that, as clarified in Addendum 2 (which included Q14), this was not permitted and both tenders were declared non-responsive.


The dispute relevant to the outcome concerned whether, on a proper interpretation of Q14, Mr Govender’s involvement through LSG in Aecom’s consortium/joint venture bid fell within what Q14 prohibited. LDM Consulting contended that Mr Govender did not tender in his own name or in the name of a company in which he was employed; it argued that the tender was in the name of Aecom Consortium, and that Q14 did not preclude a key person from being a sub-consultant in one tender and participating in another tender as an employee of an entity that was a member of a consortium.


The judgment notes LDM Consulting’s submission that it had tendered at a lower price than at least one competitor and had good prospects, but the court treated pricing and ranking as not material to SANRAL’s stated reason for rejection and therefore did not determine that issue.


Legal Issues


The central legal question was one of interpretation and application of a procurement condition: whether Q14, properly construed in context, prohibited the same key person (Mr Govender) from being proposed in LDM Consulting’s tender while also participating in Aecom’s tender through LSG’s role in Aecom’s consortium/joint venture arrangement.


Closely connected to this were evaluative challenges raised by LDM Consulting that Q14 was ambiguous, irrational, and unreasonable, and that no reasonable tenderer could have understood it to disqualify the circumstances presented. LDM Consulting linked this contention to the constitutional requirement that procurement systems be fair, equitable, transparent, competitive and cost-effective under section 217 of the Constitution.


The dispute primarily concerned law and the application of law to fact: the proper meaning of Q14 as part of the tender regime, and whether SANRAL’s decision to treat both tenders as non-responsive on that basis was justified on the limited record before the court in urgent proceedings. It also involved a value judgment in assessing alleged ambiguity and reasonableness in the procurement setting and whether the tender condition could serve its anti-corruption and anti-collusion objectives.


Court’s Reasoning


The court approached Q14 contextually and purposively, emphasising that it arose from a question-and-answer clarification process rather than a fully drafted contractual clause with comprehensive definitions and enumerations. The judgment noted that Q14 did not exhibit all the formal hallmarks typically associated with tender conditions, and specifically that the word “company” was used loosely rather than as a technical reference only to a registered company under company law. On this approach, the absence of express mention of entities such as consortiums was not treated as determinative. The court considered that insisting on exhaustive identification of every possible tendering structure would be formalistic and inconsistent with the practical context in which Q14 was generated.


A significant component of the reasoning was the court’s understanding of the purpose of Q14. The court held that the rationale for the condition was to prevent corruption and collusive practices, including price fixing. While acknowledging the applicant’s point that sub-consultants could still potentially communicate with one another, the court drew what it considered to be the critical distinction built into Q14: the difference between a person acting as a sub-consultant (permitted in multiple tenders) and a person participating in a manner akin to a consultant/own business tenderer (prohibited across multiple tenders). The court reasoned that a sub-consultant is only one of several influences on a tender price, whereas a consultant (individually or within a tendering entity) has a more direct role in determining the contract price and bid content. On this view, Q14 was directed less at the formal structure of the tendering entity and more at the level of participation and influence exercised by the key person in each bid.


In applying this purposive interpretation, the court concluded that there could be no real doubt in procurement law about Q14’s anti-corruption aim, and that tender participants were expected to be sensitive to such objectives. The court therefore preferred an interpretation that would limit the scope for corruption and collusion over one that would not. It found that LDM Consulting’s interpretation would have little or no prospect of advancing the integrity-enhancing purpose of the clause.


The court also rejected reliance on the subjective views of interested participants as proof of ambiguity. It treated the opinions of those involved (including the key person) as carrying little weight because they were not independent and were influenced by financial interests in securing work. The court further stated that the key person had a duty to disclose his participation in both tenders to both tendering entities, and that it was his participation in Aecom in a more direct tendering role (as characterised on the papers) that disqualified him from simultaneously serving as a sub-consultant key person for LDM Consulting under Q14. The court emphasised that SANRAL was obliged to apply Q14 consistently, which it did by disqualifying both LDM Consulting and Aecom.


The judgment expressly stated that it was not required to determine whether collusion or corruption in fact occurred. Instead, it reasoned that SANRAL’s task was to apply procurement ground rules strictly, consistently, and predictably to secure a corruption- and collusion-resistant process. In that light, the court held that the onus rested on tenderers to comply strictly with tender conditions, and where ambiguity or doubt existed, tenderers should err on the side of caution in favour of an interpretation that protects the integrity of the tender process.


Finally, the court considered that if LDM Consulting had any doubt about Q14’s meaning, it had an available mechanism to seek clarification before the tender closed, but did not do so. The court also invoked the principle that courts should be slow to strike down tender terms as irrational or unreasonable, recognising that the primary discretion lies with the relevant administrative body unless it is shown that the rule cannot serve the ends for which it was intended. On the information placed before the court for urgent relief, it found that Q14 could serve its integrity-protecting purpose and that SANRAL’s reason for rejecting LDM Consulting’s tender was reasonable and justified.


Outcome and Relief


The court dismissed the application for interim interdictory relief. The tender award was therefore not interdicted pending review on the basis advanced in this urgent application.


An order was made that the application is dismissed with costs.


Cases Cited


Allpay Consolidated Investment Holdings (Pty) Ltd and Others v Chief Executive Officer, South African Social Security Agency and Others [2013] ZACC 42; 2014 (1) SA 604 (CC).


GVK Siya Zama Building Contractors (Pty) Ltd v Minister of Public Works and Others [2007] JOL 20439 (D).


Haw and Inglis Civil Engineering (Pty) Ltd v MEC of Police, Roads & Transport (Free State Province) [2010] ZAFSHC 51.


Minister of Social Development v Phoenix Cash & Carry [2007] SCA 26.


Dr J.S Moroka Municipality and Others v Bertrum (Pty) Ltd and Another 2014 (1) ALL SA 545 (SCA).


Legislation Cited


Constitution of the Republic of South Africa, 1996, section 217.


Rules of Court Cited


No rules of court were cited in the judgment.


Held


The court held that tender clarification Q14 was not ambiguous, irrational, or unreasonable when interpreted purposively in the procurement context and with due regard to its anti-corruption and anti-collusion rationale.


On the limited information before the court in urgent interim proceedings, SANRAL’s decision to treat LDM Consulting’s tender as non-responsive—because the same key person was involved in another tender in a manner prohibited by Q14—was held to be reasonable and justified, and SANRAL was entitled to apply the tender condition consistently to both affected tenders.


LEGAL PRINCIPLES


A tender condition or clarification arising in a procurement process must be interpreted contextually and purposively, with due regard to the constitutional and statutory objectives of public procurement, including fairness, transparency, competitiveness, and cost-effectiveness, as well as integrity-based concerns aimed at preventing corruption and collusion.


In assessing whether a procurement condition is ambiguous, irrational, or unreasonable, a court should not adopt an unduly formalistic approach that insists on exhaustive definitional precision where the context indicates a broader, practical meaning, particularly where the clause is designed to protect the integrity of the tender process.


Courts should be slow to strike down tender terms or conditions as irrational or unreasonable; deference is afforded to the procuring authority’s formulation and application of procurement ground rules unless it is shown that the condition cannot serve the legitimate ends for which it was intended.


Tenderers bear the responsibility to comply strictly with tender conditions. Where there is uncertainty, tenderers should act cautiously in a manner that protects the integrity of the tender process, and they should seek clarification within available timeframes rather than proceed on an interpretation that increases the risk of compromised procurement integrity.

About SAFLII
Databases
Search
Terms of Use
RSS Feeds
South Africa: Kwazulu-Natal High Court, Pietermaritzburg
SAFLII
>>
Databases
>>
South Africa: Kwazulu-Natal High Court, Pietermaritzburg
>>
2017
>>
[2017] ZAKZPHC 8
|

|

LDM Consulting v South African National Roads Agency Society Ltd (SANRAL) (1490/17) [2017] ZAKZPHC 8 (7 March 2017)

IN
THE HIGH COURT OF SOUTH AFRICA
KWAZULU-NATAL
DIVISION,
PIETERMARITZBURG
CASE
NO: 1490/17
In the matter between:
LDM
CONSULTING                                                                                           APPLICANT
and
THE SOUTH AFRICAN
NATIONAL ROADS
AGENCY SOCIETY LTD
(SANRAL)                                                             RESPONDENT
ORDER
The following order is
granted:
The
application is dismissed with costs.
JUDGMENT
D.
PILLAY J
[1]
The
applicant seeks interim relief interdicting the award of a tender on
10 March 2017 for the construction of the respondent’s
office
building pending the outcome of a review to be launched. The singular
issue for the court to determine is the interpretation
of a condition
of the tender contained in the following question and answer referred
to as Q14:

Q –
Can the same key person be proposed in different tenders?
A – A key
person may only be proposed in different tenders if the person is
sub-consulting in each of the tenders and not
submitting a tender in
his/her own name or the name of his/her company where the person is
employed.’
[2]
The
applicant included LSG International as a sub-consultant in its bid.
Mr D Govender was the key person from LSG in that bid.
Unknown to the
applicant another entity Aecom Consortium also submitted a bid which
included LSG as a member of the consortium.
LSG’s participation
in the Aecom bid was not obvious until the respondent called for
clarification. Aecom responded with
a letter disclosing that it would
enter into a joint venture contract should it succeed in its bid.
Aecom SA proposed to be the
lead consultants and would include LSG as
a consultant for the project. Mr D Govender signed the letter on
behalf of LSG as the
principal partner.
[3]
The
respondent disqualified the applicant and Aecom. By letter dated  7
December 2016 the respondent informed the applicant
of its reasons
for doing so. The applicant had failed to meet the minimum criteria
for quality and consequently the respondent
returned its financial
offer unopened. By email dated 12 January 2017 the applicant
requested reasons for its bid failing to meet
the minimum criteria. A
few hours later the respondent gave the following reasons:

The
mechanical engineer key position in the LDM tender was sub-consulted
to Mr D Govender of LSG International Engineers. However,
Mr D
Govender also submitted another tender in his own name/name of his
company as part of a consortium/JV partnership. As clarified
in
Addendum 2, this is not allowed and both tenders were declared
non-responsive.’
[4]
The
applicant challenged the rejection of its bid on the following
grounds: Mr Govender did not tender in his own name or in the
name of
any company in which he was employed. The tender was in the name of
Aecom Consortium. LSG which employed Mr Govender was
a member of the
consortium. Q14 does not prevent a key person from participating in a
tender as a sub-contractor and in another
tender as the employee of
the entity that is a member of a consortium that tenders for the same
award.
[5]
Furthermore
the applicant had submitted the second lowest tender after Aecom.
Therefore it had good prospects of success. Whether
the applicant’s
tender was the lowest was not a consideration when the respondent
rejected its tender. Therefore I need say
nothing more on this issue.
[6]
The
main thrust of the applicant’s argument was that the wording of
Q14 was ambiguous, irrational and unreasonable. No reasonable
person
could have understood Q14 to preclude Mr Govender serving as a key
person in both tenders. Section 217 of the Constitution
requires a
tender to be fair, equitable, transparent and competitive.
[1]
Furthermore the Supreme Court of Appeal stated in
Allpay
Consolidated Investment Holdings (Pty) Ltd & others v Chief
Executive Officer, South African Social Security Agency &
others
[2013]
ZACC 42
;
2014 (1) SA 604
(CC) para 92
that:
a.

the
purpose of the tender is not to reward bidders who are clever enough
to decipher unclear directions. It is to elicit the best
solution
through a process that is fair, equitable, transparent cost effective
and competitive.’
[7]
Is
Q14 ambiguous, irrational and unreasonable? Q14 arose in the context
of a question and answer session to clarify the terms and
conditions
of the tender and the proposed award. It was an impromptu response
and does not have all the hallmarks and caveats that
characterise
conditions of tender. For instance, a comprehensive list of excluded
entities does not follow the word ‘company’;
more
specifically, consortiums are not expressly excluded. The word
‘company’ is used loosely to refer not only to
an entity
that is registered in terms of company law but to include a
partnership or any other entity or association that is not
a natural
person. To insist on every possible entity being identified would be
formalistic, artificial and insensitive to the context.
[8]
The
rationale for condition Q14 is to prevent corruption and collusive
practices including price fixing. The applicant correctly
pointed out
that allowing sub-consultants to participate in more than one tender
would not preclude them from speaking to one another.
However, the
primary difference between what is permitted in the first clause and
what is prohibited in the second clause of the
condition is between
sub-consulting and own business tenders. The difference between the
position of a sub-consultant and a consultant
is that the
sub-consultant is one of several influences on the tender price. In
contrast a consultant determines the contract price
individually or
as a participant with other consultants. The emphasis in Q14 is
therefore not on the form or structure of the tendering
party but the
position or level of participation and degree of influence of the key
person in the entity submitting the tender.
[9]
In
the context of procurement law no one can be in any doubt of the
purpose of Q14. In particular the plaintiff who has participated

other tenders must have been acutely sensitive to the anti-corruption
aims that the conditions of tender seek to achieve.

Consequently all interested persons must adopt a purposive
interpretation to clauses of the conditions of tender and the rules

for procurement. Adopting a purposive interpretation to Q14 and one
that has greater prospects of limiting the scope for corruption
and
collusion should always be preferred than one that has little or no
such prospects. The applicant’s interpretation has
no such
prospects whatsoever.
[10]
Q14
is not sufficient on its own to safeguard the integrity of the tender
process. Amongst other conditions tenderers have to certify
that they
did not collude with any competitors. The certification could be
strengthened if it was made under oath. Still it is
a deterrent
against contaminating the integrity of the tender.
[11]
As
evidence of the alleged ambiguity Counsel for the applicant submitted
that the applicant as an experienced company in the construction

industry, Mr Pillay and Aecom could not all have misinterpreted Q14.
Their opinion of whether the condition is ambiguous carries
little if
any weight. They are not independent. Mr Pillay has a compelling
financial interest in securing work either as a sub-consultant
or as
a consultant; he would therefore seek to place an interpretation that
best favours his personal position. He had a duty to
disclose his
participation in both tenders to both the applicant and Aecom. It is
his participation in Aecom as a consultant that
disqualified him from
also sub-consulting for the applicant. The respondent has to adopt a
consistent approach to all tenders.
Hence it applied Q14 not only to
the applicant and also to Aecom.
[12]
Whether
there was collusion or corruption is not an enquiry I need to make.
However assuming in favour of all parties that they
had no plans to
engage in any prohibited practices the task of the respondent is to
apply the ground rules for the procurement
strictly, consistently and
consequently predictably with the primary aim of achieving a
corruption and collusion free tender process.
[13]
It
follows that the onus rests on every participant in every tender to
observe the terms and conditions of the tender strictly.
Furthermore
in the case of ambiguity or doubt tenderers must err on the side of
caution and adopt an interpretation that assures
of a sanitised
tender process rather than one that opens itself to the slightest
doubt about its integrity.
[14]
If
the applicant had any doubt about the interpretation of Q14 it had
seven days before the closing date for the tender to seek
and obtain
clarification. It did not do so.  Mr Govender in particular
should have sought such clarification because of his
position in both
tenders.
[15]
A
court must be slow in striking down a term or condition of a tender
as irrational or unreasonable. That primary discretion rests
upon the
tribunal or administrative organ, unless it fails to show that the
rule or condition as a means cannot serve the ends
for which it was
intended.
[2]
[16]
In
conclusion I find that Q14 is not ambiguous, irrational or
unreasonable. The respondent’s reason for rejecting the
applicant’s
tender is reasonable and justified on the limited
information in this application before me for urgent relief.
[17]
Order
:
The
application is dismissed with costs.
_____________________
D. Pillay J
APPEARANCES
Counsel
for the Applicant

:          I Pillay
Instructed
by

:           Cox
Yeats
Tel:
(031) 031 536 8514
Ref:
P. Barnard
Counsel
for the Respondent

:           R. G
Mossop SC
Instructed
by

:           Edward
Nathan Sonenbergs
Tel:
(031) 536 8609
Ref:
M Domingos
Date of Hearing

:           6 March
2017
Date of
Judgment

:           07
March 2017
[1]
GVK Siya Zama Building Contractors
(Pty)Ltd v Minister of Public Works & Others
[2007]
JOL 20439
(D);
Haw and
Inglis Civil Engineering (Pty) Ltd v MEC of Police,
Roads & Transport (Free
State Province)
[2010]
ZAFSHC 51
;
Minister  of
Social Development v Phoenix Cash & Carry
[2007] SCA 26 [2]
[2]
Dr J.S Moroka Municipality &
Others v Bertrum (Pty) Ltd & Another
2014 (1) ALLSA 545
SCA para
10