About SAFLII
Databases
Search
Terms of Use
RSS Feeds
South Africa: Supreme Court of Appeal
SAFLII
>>
Databases
>>
South Africa: Supreme Court of Appeal
>>
2021
>>
[2021] ZASCA 132
|
|
Framatome v Eskom Holdings SOC Ltd (357/2021) [2021] ZASCA 132; 2022 (2) SA 395 (SCA) (1 October 2021)
THE
SUPREME COURT OF APPEAL OF SOUTH AFRICA
JUDGMENT
Reportable
Case
No: 357/2021
In
the matter between:
FRAMATOME APPELLANT
and
ESKOM
HOLDINGS SOC
LIMITED RESPONDENT
Neutral
Citation:
Framatome v
Eskom Holdings SOC Ltd
(357/2021)
[2021] ZASCA 132
(1 October 2021)
Coram:
MATHOPO,
MOLEMELA, MAKGOKA, MBATHA and MOTHLE JJA
Heard:
13
September 2021
Delivered:
This
judgment was handed down electronically by circulation to the
parties' representatives by email, publication on the Supreme
Court
of Appeal website and release to SAFLII. The date and time for
hand-down is deemed to be 10h00 on 1 October 2021.
Summary:
Construction
contract – contract providing for dispute resolution process
through adjudication – adjudicator’s
award final and
binding on the parties until and unless set aside on review –
High Court erred in not enforcing the award.
ORDER
On
appeal from
: Gauteng Division of the
High Court, Johannesburg (Coppin J sitting as court of first
instance):
1 The
appeal is upheld with costs which costs shall include the costs of
two counsel.
2 The
order of the high court is set aside and replaced with the following:
‘
1 It
is declared that Eskom is in breach of the New Engineering Contract
3: Engineering and Construction
Contract (June 2005) with Option A
concluded between Framatome and Eskom for the replacement of the
Steam Generators at Koeberg
Nuclear Power Station, Unit 1 and 2 (the
Contract).
2 Eskom
is directed to adhere and fully recognise and implement the decision
delivered
by the adjudicator on 23 July 2019.
3 It
is declared that the contractual key dates 15, 16, 17, 18 and 19
relating to the replacement
of the steam generators at the Koeberg
Nuclear Power Station, Units 1 and 2, are:
3.1 In
respect of Koeberg Power Station, Unit 1, 11 November 2018, 18 May
2019, 26 April 2020, 16 January
2020 and 14 February 2020,
respectively.
3.2 In
respect of Koeberg Power Station, Unit 2, 19 May 2019, 23 November
2019, 1 November 2020, 23 July
2020 and 21 August 2020, respectively.
4 It
is declared that the contractual sectional completion dates for each
section of the
Works (as defined in the Contract) have been revised
so that the sectional completion date 1 is 3 June 2020, sectional
completion
date 2 is 9 December 2020 and sectional completion date 3
is 22 June 2021.
5 It
is declared that the contractual completion date for the whole of the
Works is 22
June 2021.
6 Eskom
is ordered to pay Framatome additional costs of:
6.1 EUR
2 706 146.00 which are subject to the price adjustment
pursuant to Secondary Option Clause X1
of the Contract and pursuant
to clause 51.4 of the Contract, the interest thereon calculated at
the LIBOR rate being the 6 month
London Interbank Offered Rate quoted
under the caption “Money Rates” in The Wall Street
Journal for the applicable
currency or if no rate is quoted for the
currency in question then the rate for United States Dollars, and if
no such rate appears
in The Wall Street Journal then the rate as
quoted by the Reuters Monitor Money Rates Service (or such service as
may replace the
Reuters Monitor Money Rates Service) on the due date
for the payment in question, adjusted
mutatis
mutandis
every 6 months thereafter and
as certified, in the event of any dispute, by any manager employed in
the foreign exchange department
of the Standard Bank of South Africa
Limited, whose appointment it shall not be necessary to prove;
6.2 EUR
2 706 146.00 which is subject to the price adjustment
pursuant to Secondary Option Clause
X1 of the Contract and pursuant
to clause 51.4 of the Contract, interest thereon calculated at the
LIBOR rate (described in paragraph
6.1.1) applicable at the time for
amounts due in other currencies from 17 February 2019 to date of
payment (inclusive of both dates);
6.3 EUR
1 353 073.00 which is subject to the price adjustment
pursuant to Secondary Option Clause X1
of the Contract and pursuant
to clause 51.4 of the Contract, interest thereon calculated at the
LIBOR rate (described in paragraph
6.1.1) applicable at the time for
amounts due in other currencies from 24 September 2019 to date of
payment (inclusive of both
dates);
6.4 R
36 595 611.00 which is subject to the price adjustment
pursuant to Secondary Option Clause X1 of
the Contract and pursuant
to clause 51.4 of the Contract, interest thereon calculated at a rate
of zero percent above publicly
quoted prime rate of interest
(calculated on a 365 day year) charged from time to time by Standard
Bank of South Africa (as certified,
in the event of any dispute, by
any manager of such bank, whose appointment it shall not be necessary
to prove) from 12 August
2018 to date of payment (inclusive of both
dates);
6.5 R
36 595 611.00 which is subject to the price adjustment
pursuant to Secondary Option Clause
X1 of the Contract and pursuant
to clause 51.4 of the Contract, interest thereon calculated at a rate
of zero percent above the
publicly quoted prime rate interest (as
described in paragraph 6.1.5) applicable at the time for amounts due
in other currencies
from 17 February 2019 to date of payment
(inclusive of both dates);
6.6 R
18 297 805.00 which is subject to the price adjustment
pursuant to Secondary Option Clause X1 of
the Contract and pursuant
to clause 51.4 of the Contract, interest thereon calculated at a rate
of zero percent above the publicly
quoted prime rate interest (as
described in paragraph 6.1.5) applicable at the time for amounts due
in other currencies from 24
September 2019 to date of payment
(inclusive of both dates) within 10 days from the date of this order;
7 The
respondent is ordered to pay the costs, such costs to include the
costs of two counsel.’
JUDGMENT
Mathopo
JA (Molemela, Makgoka, Mbatha and Mothle JJA concurring):
[1] This
appeal raises two questions: first, whether the decision (referred to
as Decision 11) made by the adjudicator,
Mr T Mahon (the
adjudicator), in favour of the appellant, Framatome (Framatome)
following an adjudication in terms of a construction
contract that
was entered into between the parties should be enforced. Secondly,
whether as contended by the respondent, Eskom
Holdings SOC Limited
(Eskom), Decision 11 cannot be enforced because it is predicated on
Decision 7 which, according to Eskom,
is invalid since the
adjudicator allegedly exceeded his powers when he made a finding in
relation to Dispute 7 which was not notified
or referred as per the
terms of the agreement.
[2] Those
questions have arisen in this way. On 5 September 2014, Eskom
concluded a written NEC3 Engineering and
Construction Contract
(with
amendments of June 2006)
with Areva NP for the
replacement of the steam generators at Koeberg Nuclear Power Station,
Units 1 and 2, located in Cape Town.
(the Contract). Areva NP later
ceded the Contract to Framatome. Under the Contract, Framatome is the
contractor and Eskom is the
employer, represented by the Project
Manager.
[3] The
Contract is based on the NEC3 Engineering and Construction Contract
(ECC), which is a standard contract
used within the construction
industry; in terms of which parties can select certain clauses which
govern their rights and obligations
and regulate the completion of a
project.
[4] The
Contract also envisages the role of a Project Manager who is
appointed by the employer (ie Eskom). The
Project Manager’s
role is to manage the contract on behalf of the employer. The
Contract places substantial authority on
the Project Manager and
assumes that they have the employer’s authority to carry out
the actions and make decisions required
of them.
[5] The
Contract comprises four parts: (i) Part C1 – Agreements &
Contract Data; (ii) Part C2 –
Pricing Data; (iii) Part C3 –
Scope of Work; (iv) Part C4 – Information. Under the
‘Agreements & Contract
Data’ clause, the parties
selected as the conditions of the Contract the core clauses and the
clauses for Option A (Priced
Contract with activity schedule); the
dispute resolution Option W1; identified secondary Options
(x-clauses); and certain additional
clauses (called z-clauses) of the
ECC. These general conditions, as amended by the parties, are
hereinafter referred to as the
Conditions.
[6] The
Contract makes provision for what is called ‘compensation
events’ which allows the contractor,
Framatome, in essence, to
claim additional payment and extra time to do the work from the
employer. Compensation events are events
which, should they occur,
and provided they do not arise from the contractor’s fault,
entitle the contractor to be compensated
for any effect the event has
on the prices and the contractual sectional completion date(s) or key
date(s). The assessment of a
compensation event is always in respect
of its effect on the prices, the completion date and any key date(s)
affected by the relevant
compensation event in question. The Contract
contains a process whereby the assessment of a compensation event is
achieved by agreement
between the parties, determined by the Project
Manager or deemed to be approved if there is inaction on the part of
the Project
Manager.
[7] There
was a compensation event for which Framatome provided a quotation.
Sub-clause 64.1
[1]
of
the Conditions compels the Project Manager to perform an assessment
of the compensation event. Sub-clause 65.1 prescribes what
is to
occur when a compensation event is implemented. It envisages three
possible scenarios, namely when: (a) the Project Manager
accepts the
quotation; (b) the Project Manager notifies the contractor of his own
assessment or; (c) when a contractor’s
quotation is treated as
having been accepted by the project manager (clause 64.4).
[8] On
29 May 2017, the Project Manager notified Eskom of a compensation
event which had risen as a consequence
of the agreed need for the
‘redefinition of Key Dates for Key Dates 2, 14 and 24’.
Following the Project Manager’s
notification and assessment of
the compensation event, a dispute arose between the parties. This was
in relation to the Project
Manager’s decision regarding the
consequences of the changed key dates mentioned above and more
particularly, whether the
Project Manager’s aforementioned
notification amounted to a compensation event.
[9] On
11 December 2018, pursuant to clause W1 of the Contract, Framatome
referred the dispute to adjudication
as ‘Adjudication no. 7’.
Included in the Framatome’s referral notice was a quotation
setting out Framatome’s
assessment of the impact of the revised
key dates 2, 14 and 24 on the remaining key dates (15 to 19),
sectional completion dates,
the completion date and the prices.
Clause W1 dictates that the adjudicator may only decide disputes
which have been notified and
referred to him in accordance with the
provisions of the Contract. The provisions of the Contract also place
specific time periods
within which such disputes have to be notified
and referred. Put simply, an adjudicator would have no jurisdiction
to decide a
dispute which: (a) has not been notified; (b) if
notified, has not been notified within the prescribed time period;
and (c) has
not been referred to the adjudicator within the
prescribed period. The adjudicator’s determination is not
exhaustive of the
disputes, it may be taken on arbitration or
overturned during the final stage of dispute resolution.
[10] The
adjudicator described the dispute before him as follows:
‘
The
first issue on which I am required to give a decision is whether the
Project Manager failed to make the assessment of the Compensation
Event of Changed Key Dates 2, 14 and 24 in due time as directed by
the Adjudicator’s decision of 26
th
February 2019 and if not what the consequences of this are.’
[11] In
response, Framatome, in its redress, sought a decision that:
‘
[The
appellant] seeks a decision by the Adjudicator that: The Project
Manager failed to make the full assessment of the compensation
event
of changed Key Dates 2, 14, 24 in due time and as directed by the
Adjudicator’s decision of February 26
th
,
2019; as a consequence, the Contractor’s quotation contained in
the Contractor’s referral of December 11
th
,
2018 (paragraphs 135 to 171 and appendices 6 and 7) shall be deemed
accepted. . . ’
[12] On
26 February 2019, the adjudicator issued his decision as ‘Decision
no. 7’ which recorded that
the project manager’s
instruction of 29 May 2017 was indeed a compensation event and
summarised the dispute as being about
‘the manner in which
[the] compensation event was implemented which needs to be
evaluated’. Eskom did not give notice
of its dissatisfaction
with the decision in terms of sub-clause W14(2) of the Conditions
read together with sub-clause W3.10. It
must be emphasised that in
its referral and submission in the adjudication of Dispute 7,
Framatome included a section which set
out its assessment and
quotation of the compensation event and requested the adjudicator to
direct the implementation of the compensation
event in accordance
with that assessment. After Decision 7 was issued, the Project
Manager did not assess the compensation event.
Acting in terms of
sub-clause 64.4
[2]
of
the Conditions, Framatome notified the Project Manager on 20 March
2019 that he had failed to assess the compensation event.
Despite
this notification, the Project Manager still failed to make any
assessment. The consequence of such a failure is that the
provisions
of sub-clause 64.4 were triggered with the concomitant result that
Framatome’s quotation was deemed to be acceptable.
[13] On
23 April 2019, Framatome notified the Project Manager and Eskom of a
dispute regarding the Project Manager’s
assessment. The
dispute, referred to as ‘Dispute 11’, was referred to the
adjudicator. Framatome requested the adjudicator
to determine whether
the Project Manager had made a full assessment of the compensation
event in due time, as directed by Decision
7 and whether the
Projector Manager had properly assessed the impact of the change to
key dates 2, 14 and 24 on the sectional completion
dates, the
completion date, the prices, and whether Framatome’s quotation
was deemed accepted by Eskom in terms of sub-clause
16.4.
[14] In
his findings, referred to as ‘Decision 11’, the
adjudicator determined that Eskom had failed,
within the Project
Manager’s assessment, to make a full assessment of the
compensation event in due time as directed by Decision
7 and also as
required by clauses 63 and 64 of the Contract. The adjudicator
concluded that Framatome’s quotation was deemed
to have been
accepted by Eskom. The effect of this decision was that the adjusted
key dates, sectional completion dates, completion
dates, activity
schedule and payments of the quotation became contractually binding
upon the parties.
[15] Aggrieved
with that decision, Eskom notified the adjudicator of its
dissatisfaction. Additionally, it raised
various grounds for refusing
to give full effect to Decision 11. This prompted Framatome to
institute enforcement proceedings in
the Gauteng Division of the High
Court, Johannesburg (the high court).
[16] The
high court dismissed Eskom’s challenge to Decision 7 on the
basis that the dispute fell within the
jurisdiction of the
adjudicator and that Eskom neither objected to that decision nor gave
notice of its intention to refer the
decision to arbitration. It
upheld Eskom’s argument on Decision 11 on the ground that the
adjudicator did not decide the
dispute that was referred to him under
the Contract by the parties. Essentially, the high court found that
there was no mention
at all in the referral about whether the Project
Manager
timeously
issued the assessment. It concluded that the adjudicator answered the
wrong question, and held that the impugned decision was not
binding
on the parties and was thus unenforceable. Additionally, it held
further, that Eskom had good prospects of successfully
establishing
at the arbitration, that the adjudicator acted outside his
jurisdiction. The high court refused leave to appeal. This
appeal is
with the leave of this Court.
[17] Before
us, Eskom argues that Decision 11 was taken by the adjudicator
outside the terms of his jurisdiction
as it was not a dispute that
had been notified and referred to him. It submits that in Decision
11, the adjudicator sought to enforce
his previous decision in
Decision 7. It contends that Decision 11 can only be considered valid
if Decision 7 was within the adjudicator’s
jurisdiction.
Principally Eskom asserts that the question before the adjudicator
was not whether the Project Manager had timeously
issued the
assessment or had an assessment at all, but rather, whether the
assessment was correct or not. Drawing the link between
Decisions 7
and 11, Eskom asserts that the adjudicator had no regard to the
notice of dispute and the extent to which the dispute
was notified.
By reverting to the event of 19 May 2017, the adjudicator erred,
because such an event could not have been subject
of the notice of
dispute in Decision 7 of 13 November 2018. Therefore, Eskom contends
that the adjudicator had no power to issue
a decision and
consequently, such a decision was a nullity.
[18] It
advances three propositions in support of its contention, first it
says the decision was not in respect
of the dispute notified.
Secondly, the dispute in respect of the project manager’s
notification of the event could only have
been notified and referred
to the adjudicator in terms of the Contract. Thirdly, it submitted
that, by deeming the quotation as
being acceptable, the adjudicator
purported to vary the terms of the Contract, which it did not have
the power to do. It also contended
that the quotation was not one
contemplated in clause 64.4 of the Contract. Eskom submits that the
quotation was a calculation
of the relief which Framatome sought in
adjudication proceedings of Dispute 7 and it was not submitted to the
Project Manager in
terms of clauses 62.1
[3]
and
62.3.
[4]
[19] Framatome
contends that the judgment of the high court must be overturned and
the adjudicator’s award
be enforced. It submits that courts
have, over the years, repeatedly confirmed that an adjudicator’s
decision is final and
binding until set aside by the tribunal. It
contends that the judgment of the high court has impermissibly
introduced a subjective
judicial discretion into the enforcement of
adjudicator’s awards by concluding that ‘a very good
prospect of successfully
establishing that an adjudicator acted
outside his jurisdiction in respect of Decision 11 and that the
decision is not binding
upon the parties and is unenforceable.’
Accordingly, it urges upon us to set the decision aside.
[20] Against
this background, I turn to the issue whether the high court correctly
declined the order of enforcement.
The principles applicable to this
issue have been set out in numerous cases. In
Radon
Projects (Pty) Ltd v NV Properties (Pty) Ltd & Another
,
[5]
this
Court describes the process of adjudication as follows:
‘
[3]
Construction contracts most often require disputes to be resolved by
arbitration, but at the same time postpone arbitration
until the
works have been completed, so as to avoid interruption. Earlier
contracts in common use made an exception in certain
limited
circumstances. That was the case in Britain under the JCT1 Standard
Form of Building Agreement (1980 edition), and in this
country under
the General Conditions of Contract 1982 for use in connection with
Works of Civil Engineering Construction (Fifth
Edition). In both
cases an arbitration could not be opened until after completion of
the works, except on limited issues that,
by their nature, demanded
earlier resolution, in particular disputes concerning payment
certificates.
[4]
It has now become common internationally – in some countries by
legislation – for disputes to be resolved provisionally
by
adjudication. In
Macob Civil Engineering
Ltd v Morrison Construction Ltd
adjudication was described, in the context of English legislation, as
“
.
. . a speedy mechanism for settling disputes [under] construction
contracts on a provisional interim basis, and requiring the
decision
of adjudicators to be enforced pending the final determination of
disputes by arbitration, litigation or agreement. .
..But Parliament
has not abolished arbitration and litigation of construction
disputes. It has merely introduced an intervening
provisional stage
in the dispute resolution process.”
[5]
The authors of Hudson’s Building and Construction Contracts
observe that under New Zealand construction legislation
adjudication
“is regarded as essentially a cash flow measure implementing
what has been colloquially described as a “quick
and dirty”
exercise to avoid delays in payment pending definitive determination
of litigation”.’
[21] In
the forefront of his argument counsel for Eskom submitted that
because Decision 11 is predicated on an
invalid Decision 7, the award
by the adjudicator is unenforceable and not binding. I pause to state
that no attack was taken against
Decision 7. The closest Eskom did
was to cross-appeal that decision before the high court. During
argument before us, it was conceded
that the cross-appeal was
abandoned. In my view, if Eskom wished to challenge the validity of
Decision 7, it had an election to
do so. One course open to it was to
treat Decision 7 as a decision falling within the powers of the
adjudicator and refer the dispute
to arbitration. The respondent
contends that if the adjudicator exceeds his jurisdiction no referral
to arbitration should be made.
The other option was to contend that
it was a nullity and challenge it. In this case, at no stage did
Eskom complain that Dispute
7 referred to the adjudicator was outside
his jurisdiction. I am not aware of any authority that supports the
proposition that
a lack of jurisdiction in relation to an earlier
adjudication is a recognised ground for challenging an adjudicator’s
jurisdiction
in a subsequent adjudication that relies on the findings
of the challenged jurisdiction prior to any challenge being made
good.
As a matter of fact, it participated in the adjudication
process.
[22]
It
is clear that the attack on the enforcement of Decision 11 is an
attack on its merits and the merits of Decision 7 which preceded
it.
The argument on Decision 7 was rightly rejected by the high court and
it is not open to Eskom to resuscitate it here in this
appeal.
Accordingly, there is no merit in us entertaining it. One answer to
this submission can be found in the provisions of Clause
W1.3(10),
which states that:
‘
The
adjudicator’s decision is binding on the Parties unless and
until revised by the tribunal and is enforced as a matter
of
contractual obligation between Parties and not as an arbitral award.
The Adjudicator’s decision is final and binding if
neither
Party has notified the other within the times required by this
contract that he is dissatisfied with a decision of the
Adjudicator
and intends to refer the matter to the tribunal.’
It is clear that only the
arbitration is the appropriate forum. In argument before us, Eskom
conceded that the dispute has been
referred to arbitration.
[23] If
the interpretation contended for by Eskom is correct, it will
substantially undermine the effectiveness
of the scheme of
adjudication. It is plain that the purpose of adjudication was to
introduce a speedy mechanism for settling disputes
in construction
contracts on a provisional interim basis and requiring the decisions
of adjudicators to be enforced pending the
final determination of
disputes by arbitration. As far as the procedure is concerned,
adjudicators are given a fairly free hand.
They are required to act
impartially and permitted to take the initiative in ascertaining the
facts and the law. Sight should not
be lost of the fact that
adjudication is merely an intervening, provisional stage in the
dispute resolution process. Parties still
have a right of recourse to
litigation and arbitration. Only a tribunal may revise an
adjudicator’s decision. As that decision
has not been revised,
it remains binding and enforceable. Eskom cannot partially comply
with the award and decline to give full
effect to the payment portion
of the award. What Eskom is asking the Court to do is to interrogate
the merits, an aspect which
falls within the purview of the
arbitrator.
[24] Another
compelling reason which militates against the submission of Eskom is
that in paragraph 13 of its answering
affidavit, Eskom stated as
follows:
‘
The
whole of the Adjudicator’s decision in dispute 11 therefore
forms the subject of the Respondent’s notice of dissatisfaction
of 5 August 2019 and will be reconsidered by the arbitration
tribunal. (A copy of the notice of dissatisfaction in terms of Clause
W1.3(10) and W1.4(2) is attached hereto and marked “AA2”).’
A reading of this
paragraph makes it clear that Eskom accepted that the dispute falls
within the remit of the arbitrator and had
agreed to participate in
the contemplated arbitration proceedings. To my mind, no justifiable
reason exists for not fully giving
effect to the adjudicator’s
award. Refusing to comply with the payment award of the adjudicator
is disingenuous. I will deal
with Eskom’s defences shortly.
[25] The
submission that the adjudicator exceeded his jurisdiction and that
the proper procedure was not followed
does not entitle Eskom not to
comply with the adjudicator’s award. The adjudicator formulated
the dispute with the understanding
and appreciation of what the
parties contemplated. It is trite that if upon an application for
enforcement of an adjudication decision,
it is found that the
adjudicator did not have the requisite jurisdiction, his decision
will not be binding or enforceable. At no
stage did Eskom contend
that the dispute referred to the adjudicator was outside his
jurisdiction. It cannot avail Eskom to raise
issues relating to
Framatome’s quotation. The adjudicator dealt with this aspect
in its finding in Decision 11. It is an
aspect that I now turn to
because it formed the cornerstone of Eskom’s submission.
[26] The
quotation is challenged on the basis that it does not constitute one
in terms of the Contract and that
the procedure provided for in
clause 64.4 of the Contract by which the quotation is deemed to be
acceptable was not followed. This
argument has no merit. Clause 64.4
provides:
‘
If
the Project Manager does not assess a compensation event within the
time allowed, the Contractor may notify the Project Manager
to this
effect. If the Contractor submitted more than one quotation for the
compensation event, he states in his notification which
quotation he
proposes is to be accepted. If the Project Manager does not reply
within two weeks of this notification the notification
is treated as
acceptance of the Contractor’s quotation by the Project
Manager.’
The quotation in terms of
clause 64.4 was submitted together with Framatome’s
submissions. To this end, Eskom did not object
to Framatome’s
alleged quotation which was embodied in the submissions to the
adjudicator in the referral notice. A determination
of whether or not
Framatome’s quotation was valid under the Contract and whether
the process for the deemed acceptance of
that quotation requires an
analysis of the facts. This is an issue which the arbitrator will
deal with in due course. That said,
it is clear that the decision of
the adjudicator is binding and enforceable.
[27] Eskom
resisted the payment to the applicant on three bases. First, it
contended that the amounts claimed are
not due and payable. Secondly,
the proposal to change the payment did not and could not form part of
the quotation under the Contract.
Thirdly, in deeming the
contractor’s quotation as acceptable, the payment provisions of
the Contract were changed and this
was outside the jurisdiction of
the adjudicator. These arguments have no merit.
[28] In
terms of Decision 11 the amounts claimed were due and payable as a
result of the contractor’s quotation
which was deemed
acceptable by the project manager. The quotation provided various
payment provisions in terms of the Contract
and all these payments
were in line with the activity schedule. It cannot be contended that
the contractor is not entitled to propose
changes to the activity
schedule. In my view, any change or amendment to the activity
schedule is permitted under Contract. The
Contract recognises that
the project management and other costs will be incurred by the
contractor during the course of the works
and throughout the duration
of the project. What has been claimed by Framatome is consistent with
the contractual provisions that
govern such payments. The Contract in
particular envisages that interim payments must be made and are
subject to a revision by
the tribunal in due course.
[29] In
the final analysis, the question to be asked is whether the
adjudicator’s determination is binding
on the parties. The
answer to that question turns on whether the adjudicator confined
himself to a determination of the issues
that were put before him by
the parties. If he did so, then the parties are bound by his
determination, notwithstanding that he
may have fallen into an
error.
[6]
The
finding of the high court that the adjudicator answered the wrong
question is not borne out by the facts. The adjudicator formulated
the dispute as it was referred to him. At no stage did he depart from
the real dispute between the parties. He decided the dispute
in
accordance with what the parties had contemplated and appreciated. It
would seem to me that the high court focused its attention
on the
words ‘timeously or in due course’ in the adjudicator’s
award and concluded that the adjudicator exceeded
his jurisdiction.
This approach is wrong.
[30] It
is necessary that the dispute be looked at holistically taking into
account how the parties conducted themselves.
What the high court did
was to isolate the words ‘timeously’ or ‘in due
time’ from the context of the main
dispute. During adjudication
proceedings, Eskom did not contend that the notified dispute has been
varied. It being obvious to
all the parties that the dispute remained
the same and the adjudicator consequently rendered a sound decision
based on the facts.
Before the high court was an enforcement of a
provisional or interim payment due to Framatome in terms of the
Contract. The provision
that payment must be made even before
arbitration is a strong indication of the ousting of a court’s
jurisdiction to review
the award. The parties knew when they
contracted with each other that the disputes may arise and a
temporary solution in the form
of interim payments is provided to
ensure the completion of the Contract within the agreed specified
period. The high court erred
in its conclusion that the wrong
question was answered. As stated in
Hudson’s
Building and Engineering Contracts
:
‘
It
should only be in rare circumstances that the courts will interfere
with the decision of an Adjudicator, and the courts should
give no
encouragement to an approach which might aptly be described as
“simply scrabbling around to find some argument, however
tenuous, to resist payment”.’
[7]
[31] All
the aforegoing demonstrate that the appeal must succeed. I make the
following order:
1 The
appeal is upheld with costs which costs shall include the costs of
two counsel.
2 The
order of the high court is set aside and replaced with the following:
‘
1 It
is declared that Eskom is in breach of the New Engineering Contract
3: Engineering
and Construction Contract (June 2005) with Option A
concluded between Framatome and Eskom for the replacement of the
Steam Generators
at Koeberg Nuclear Power Station, Unit 1 and 2 (the
Contract).
2 Eskom
is directed to adhere and fully recognise and implement the decision
delivered
by the adjudicator on 23 July 2019.
3 It
is declared that the contractual key dates 15, 16, 17, 18 and 19
relating to the replacement
of the steam generators at the Koeberg
Nuclear Power Station, Units 1 and 2, are:
3.1 In
respect of Koeberg Power Station, Unit 1, 11 November 2018, 18 May
2019, 26 April 2020, 16 January
2020 and 14 February 2020,
respectively.
3.2 In
respect of Koeberg Power Station, Unit 2, 19 May 2019, 23 November
2019, 1 November 2020, 23 July
2020 and 21 August 2020, respectively.
4 It
is declared that the contractual sectional completion dates for each
section of the Works
(as defined in the Contract) have been revised
so that the sectional completion date 1 is 3 June 2020, sectional
completion date
2 is 9 December 2020 and sectional completion date 3
is 22 June 2021.
5 It
is declared that the contractual completion date for the whole of the
Works is 22
June 2021.
6 Eskom
is ordered to pay Framatome additional costs of:
6.1 EUR
2 706 146.00 which are subject to the price adjustment
pursuant to Secondary Option Clause X1
of the Contract and pursuant
to clause 51.4 of the Contract, the interest thereon calculated at
the LIBOR rate being the 6 month
London Interbank Offered Rate quoted
under the caption “Money Rates” in The Wall Street
Journal for the applicable
currency or if no rate is quoted for the
currency in question then the rate for United States Dollars, and if
no such rate appears
in The Wall Street Journal then the rate as
quoted by the Reuters Monitor Money Rates Service (or such service as
may replace the
Reuters Monitor Money Rates Service) on the due date
for the payment in question, adjusted
mutatis
mutandis
every 6 months thereafter and
as certified, in the event of any dispute, by any manager employed in
the foreign exchange department
of the Standard Bank of South Africa
Limited, whose appointment it shall not be necessary to prove;
6.2 EUR
2 706 146.00 which is subject to the price adjustment
pursuant to Secondary Option Clause
X1 of the Contract and pursuant
to clause 51.4 of the Contract, interest thereon calculated at the
LIBOR rate (described in paragraph
6.1.1) applicable at the time for
amounts due in other currencies from 17 February 2019 to date of
payment (inclusive of both dates);
6.3 EUR
1 353 073.00 which is subject to the price adjustment
pursuant to Secondary Option Clause X1
of the Contract and pursuant
to clause 51.4 of the Contract, interest thereon calculated at the
LIBOR rate (described in paragraph
6.1.1) applicable at the time for
amounts due in other currencies from 24 September 2019 to date of
payment (inclusive of both
dates);
6.4 R
36 595 611.00 which is subject to the price adjustment
pursuant to Secondary Option Clause X1 of
the Contract and pursuant
to clause 51.4 of the Contract, interest thereon calculated at a rate
of zero percent above publicly
quoted prime rate of interest
(calculated on a 365 day year) charged from time to time by Standard
Bank of South Africa (as certified,
in the event of any dispute, by
any manager of such bank, whose appointment it shall not be necessary
to prove) from 12 August
2018 to date of payment (inclusive of both
dates);
6.5 R
36 595 611.00 which is subject to the price adjustment
pursuant to Secondary Option Clause
X1 of the Contract and pursuant
to clause 51.4 of the Contract, interest thereon calculated at a rate
of zero percent above the
publicly quoted prime rate interest (as
described in paragraph 6.1.5) applicable at the time for amounts due
in other currencies
from 17 February 2019 to date of payment
(inclusive of both dates);
6.6 R
18 297 805.00 which is subject to the price adjustment
pursuant to Secondary Option Clause X1 of
the Contract and pursuant
to clause 51.4 of the Contract, interest thereon calculated at a rate
of zero percent above the publicly
quoted prime rate interest (as
described in paragraph 6.1.5) applicable at the time for amounts due
in other currencies from 24
September 2019 to date of payment
(inclusive of both dates) within 10 days from the date of this order;
7 The
respondent is ordered to pay the costs, such costs to include the
costs of two counsel.’
R
S Mathopo
Judge of Appeal
APPEARANCES:
For
appellant: B Berridge
SC (with him D Van Zyl)
Instructed
by: Webber Wentzel,
Johannesburg.
Webbers
Attorneys, Bloemfontein.
For
respondent: PHJ Van Vuuren SC
Instructed
by: Edward Nathan
Sonnenbergs Inc., Johannesburg.
Lovius
Block Inc., Bloemfontein.
[1]
If
the Project Manager does not access a compensation event within the
time allowed, the Contractor may notify the Project manager
to this
effect. If the Contractor submitted more than one quotation for the
compensation event, he states in his notification
which quotation he
proposes is to be accepted. If the Project Manager does not reply
within two weeks of this notification the
notification is treated as
acceptance of the Contractor’s quotation by the Project
Manager.
[2]
See
fn 1.
[3]
Clause
62.1 provides as follows: ‘After discussing with the
Contractor different ways of dealing with the compensation event
which are practicable, the Project Manager may instruct the
Contractor to submit alternative quotations. The Contractor submits
the required quotations to the Project Manager and may submit
quotations for other methods of dealing with the compensation event
which he considers practicable.’
[4]
Clause 62.3 states: ‘The Contractor submits quotations within
three weeks of being instructed to do so by the Project Manager.
The
Project Manager replies within two weeks of the submission. His
reply is:
· an
instruction to submit a revised quotation,
· an
acceptance of a quotation,
· a
notification that a proposed instruction will not be given or a
proposed change decision will
not be made, or
· a
notification that he will be making his own assessment.’
[5]
Radon
Projects (Pty) Ltd v NV Properties (Pty) Ltd & Another
[2013]
ZASCA 83
;
[2013] 3 All SA 615
(SCA);
2013 (6) SA 345
(SCA)
(31
May 2013)
para
3-5.
[6]
See
Carillion
Construction Limited v Devonport Royal Dockyard Ltd
[2005]
EWHC 778
(TCC) para 63.
[7]
R
Clay and N Dennys
Hudson's
Building and Engineering Contracts
14
ed (2021) at 11-010.