Sydney-On-Vaal Property Ass and Another v Theta Mining Mining and Others (415/2018) [2018] ZANCHC 73 (26 October 2018)

78 Reportability

Brief Summary

Interdict — Final interdict — Applicants sought to restrain respondents from mining on farm pending rezoning — Court determined that applicants were seeking a final interdict rather than an interim one — Applicants failed to establish a clear right necessary for a final interdict. Applicants, Sydney-on-Vaal Property Association and Scarlet Sun 15 (Pty) Ltd, sought an interdict against Theta Mining (Pty) Ltd and Lonrho Mining SA (Pty) Ltd to prevent mining activities on the farm Drooge Veldt until it was rezoned for such use. The court found that the nature of the relief sought constituted a final interdict and that the applicants did not meet the requisite legal standard for such relief.

Comprehensive Summary

Summary of Judgment


Introduction


The matter concerned an urgent application for interdictory relief aimed at restraining mining activities on the farm Drooge Veldt No. 292 in the administrative district of Barkly-West. The substantive relief sought was an interdict against the first and second respondents from conducting mining on the farm pending the “final zoning” (rezoning) of the property to allow mining operations.


The first applicant was the Sydney-on-Vaal Communal Property Association (CPA) and the second applicant was Scarlet Sun 15 (Pty) Ltd. The principal respondents were Theta Mining (Pty) Ltd (the holder of the mining right) and Lonrho Mining SA (Pty) Ltd. Additional respondents included the relevant municipality and state functionaries, including the Minister of Public Works, the relevant MEC, and functionaries within the Department of Mineral Resources. The fourth respondent (Minister of Public Works) did not oppose and indicated it would abide the court’s decision.


Procedurally, the application was not the first attempt to obtain the same relief: the court noted that this was the third application (by one or both applicants) seeking the same relief on the same grounds over a period exceeding two years. Although the matter was brought as urgent, the first and second respondents did not oppose on the basis of lack of urgency, and the court accordingly decided the matter on its merits.


The dispute fell within the intersection of mining law and land use planning law, specifically whether, in the absence of a municipal land use scheme or formal zoning, mining could lawfully proceed without rezoning, given the transitional provisions of the Spatial Planning and Land Use Management Act 16 of 2013 (SPLUMA).


Material Facts


The CPA’s community acquired rights to the farms Mozib 279, Than 280, and Drooge Veldt 292 through a land claims process. The applicants described the CPA as the beneficial owner and occupier of those farms. The farms, however, remained registered in the name of the Republic of South Africa at the time of the hearing, with transfer to the CPA not yet completed. The farm previously formed part of the Vaalbos nature reserve. The fourth respondent’s affidavit indicated that transfer delays were attributable to turbulence in the community, and that the process had been initiated but not finalised.


The applicants’ case proceeded on the footing that, before mining could lawfully occur, the farm had to be rezoned for mining. They alleged that immediately prior to SPLUMA commencing on 1 July 2015, the land was being used for agricultural/game farming purposes, and contended that this historic use translated into a legally relevant zoning position.


A mining right in respect of Drooge Veldt existed in favour of Theta Mining. It was common cause that the mining right was executed on 12 August 2015, and the applicants relied on this timing in arguing that mining could not be treated as a lawful pre-SPLUMA use.


The applicants relied on two documents characterised as zoning certificates. One, issued by the Dikgatlong Municipality (dated 19 October 2016), described the property as “Agricultural Zone” and purported to be issued under the Land Use Planning Ordinance 15 of 1985 (LUPO). Another, emanating from the Sol Plaatjie Municipality (dated 18 February 2013) purported to treat the property as agricultural in terms of the “Sol Plaatjie Land Use Management Scheme 2008,” despite the farm being in Barkly-West (under Dikgatlong’s administration). The court treated the circumstances of these certificates, including their provenance and jurisdictional basis, as materially problematic.


The applicants’ own town-planning evidence (through an affidavit by Mr N Haarhoff, a town planner) indicated that within the Dikgatlong Municipality there was no land register, no prescribed plan, and no zoning map as required under LUPO, and that a new land use scheme had been compiled but never promulgated. The absence of these instruments was central to the court’s findings on whether the land was zoned or could be regarded as having a “deemed” zoning.


In reply, the applicants also sought to rely on Regulation 18 promulgated under SPLUMA, contending it supported their interpretation of SPLUMA’s transitional provisions. The argument was raised late, and the court permitted additional written submissions to ensure procedural fairness.


Legal Issues


The court was required to determine, first, whether the interdict sought was properly characterised as an interim interdict or a final interdict, because that characterisation would determine the standard of proof and the requirements the applicants needed to satisfy.


The central substantive issue was the interpretation and application of section 26(3) of SPLUMA in circumstances where no town planning scheme or land use scheme applied to the land. Specifically, the court had to decide whether, during SPLUMA’s transitional period, land could be used for mining only if it was actually lawfully used for mining immediately before 1 July 2015 (as the applicants contended), or whether it could also be used for mining if it could lawfully have been used for mining immediately before that date, provided the use fell within Schedule 2 (as the respondents contended).


Closely linked questions included whether the farm had ever been formally zoned, whether it could be treated as having a “deemed zoning” under section 14(1) of LUPO, and what (if any) probative or legal effect attached to the zoning certificates relied upon by the applicants, including whether those certificates constituted administrative action or could be treated as proof of underlying administrative decisions.


A further issue, raised by the applicants, concerned alleged non-compliance with section 5A of the Mineral and Petroleum Resources Development Act 28 of 2002 (MPRDA), and whether that allegation could sustain the relief sought on the applicants’ pleaded case.


The dispute primarily concerned questions of law and statutory interpretation, with the application of those interpretive conclusions to largely common-cause structural facts (notably the absence of a land use scheme and the execution of the mining right). Where factual disputes arose (such as the status and reliability of the zoning certificates), the court treated them as relevant insofar as they affected whether the applicants had established a clear right (or even a prima facie right) for interdictory relief.


Court’s Reasoning


On the nature of the interdict, the court accepted the respondents’ submission that, despite the interdict being framed as operating “pending” rezoning, it was final in substance and effect. Relying on Airoadexpress (Pty) Ltd v Chairman, Local Road Transportation Board, Durban, the court treated an interim interdict as relief intended to hold the position pending a final judicial (or analogous) determination of rights. Here, the contemplated “final” step was not a court determination but an administrative rezoning process, involving public participation and a discretionary municipal decision whether to rezone. The court reasoned that granting the interdict would entail a final judicial determination that mining could not lawfully occur absent rezoning, and therefore the application had to meet the requirements for a final interdict.


Having classified the relief as final, the court restated that the applicants bore the onus to establish a clear right, an interference, and the absence of an adequate alternative remedy. The court further held that, even if it were wrong on the final/interim classification, the application would still fail because the applicants had not established even a prima facie right open to some doubt.


The court then addressed the interpretive disputes concerning SPLUMA and land use regulation. It rejected reliance on Regulation 18 as an interpretive aid for SPLUMA itself, reasoning that regulations are delegated legislation and do not provide binding context for construing the empowering statute, particularly where the regulation was promulgated after the statute. The court treated Regulation 18 as, at most, an expression of departmental opinion as to what SPLUMA meant, rather than an authoritative aid to interpretation.


The court also declined to uphold the applicants’ attempt to rely on section 5A of the MPRDA. It held that the founding affidavit contained only a bare allegation of non-compliance (a single sentence) without specifying the respects in which Theta Mining allegedly failed to comply, while the heads of argument later developed the point at length. Given that motion proceedings require the founding affidavit to contain the case the respondent must meet, the court held the allegation was inadequately pleaded. On the papers as framed, the respondents’ attachment of a notice to the owner/occupier and an environmental authorisation was treated as sufficient to meet the vague allegation, and the court also noted that the section 5A point did not conceptually align with the way the Notice of Motion was framed.


A substantial portion of the reasoning addressed whether Drooge Veldt was zoned or could be regarded as having a deemed zoning. The court held that the zoning certificates relied upon were not administrative action in themselves, following Jacobs and Another v Transand and Another and Magalies-Bromberg Property Owners Association v City of Tshwane. The administrative action would be the underlying municipal decision or resolution, and the applicants provided no proof of such underlying decisions. Beyond that doctrinal point, the court found that both certificates were beset by defects undermining their probative value. The Sol Plaatjie certificate raised jurisdictional concerns because the farm fell outside that municipality’s area, and the certificate’s notation purporting to rely on “demarcation” did not identify a legal basis authorising such certification. The Dikgatlong certificate’s reliability was undermined by features including language inconsistent with the alleged statutory basis (“Agricultural Zone”), signature discrepancies when compared to another document allegedly signed by the same official, and—most decisively—the applicants’ own evidence that the municipality lacked the LUPO-required register, plan, and zoning map necessary to support lawful issuance.


The court then considered whether there was a deemed zoning under section 14(1) of LUPO, which deems land to be zoned in accordance with its utilisation “as determined by the council concerned.” The applicants’ argument effectively relied on utilisation alone, but the court held that the statutory text required an actual determination by the relevant council. Applying the interpretive principle that effect must be given to every word (citing Attorney-General, Transvaal v Additional Magistrate for Johannesburg), the court concluded that, because there was no evidence that the relevant municipal council had ever determined the utilisation of the farm at the time LUPO commenced, the farm did not have a deemed zoning under section 14(1).


With that foundation, the court interpreted section 26(3) of SPLUMA as a transitional mechanism operating alongside the obligation in section 24(1) for municipalities to adopt a land use scheme within five years of SPLUMA’s commencement. The court preferred the respondents’ construction: where no scheme applies, the land may be used for purposes in Schedule 2 for which the land was lawfully used or could lawfully have been used immediately before SPLUMA commenced. The court rejected the applicants’ reading as strained because it effectively ignored the “could lawfully have been used” language.


In evaluating the competing interpretations, the court treated the respondents’ approach as a practical response to the reality that “wall-to-wall” municipalities are relatively recent and that many properties historically fell outside formal planning control. The respondents’ interpretation was said to constrain land use in two ways: the use must fall within the finite list in Schedule 2, and it must be lawful in the sense that no legal impediment (including title deed restrictions or other prohibitory laws) prevents it. On the facts, with no established zoning, no applicable land use scheme, no proven prohibition in the title deed, and mining being a Schedule 2 use, the court concluded that rezoning was not required before mining could lawfully take place.


Because the applicants’ interdictory case depended on establishing a right to insist that mining could not occur absent rezoning, and because the court found rezoning unnecessary on a proper interpretation of SPLUMA in the circumstances, the applicants failed to establish a clear right (and even failed to establish a prima facie right). That conclusion made it unnecessary to analyse the remaining requirements for interdictory relief.


Outcome and Relief


The application was dismissed. The court ordered that the applicants pay the respondents’ costs jointly and severally, the one paying the other to be absolved. The costs order expressly included the costs of the postponement on 9 March 2018.


Cases Cited


Airoadexpress (Pty) Ltd v Chairman, Local Road Transportation Board, Durban [1986] ZASCA 6; 1986 (2) SA 663 (A).


Maccsand (Pty) Ltd v City of Cape Town and Others [2011] ZASCA 141.


Maccsand (Pty) Ltd v City of Cape Town and Others [2012] ZACC 7.


Oudekraal Estates (Pty) Ltd v City of Cape Town and Others 2004 (6) SA 222 (SCA).


Hangklip Environmental Action Group v MEC for Agriculture, Environmental Affairs and Development Planning, Western Cape, and Others 2007 (6) SA 65 (CPD).


Jacobs and Another v Transand and Another [2014] ZAWCHC 172 (14 November 2014).


Magalies-Bromberg Property Owners Association v City of Tshwane [2016] ZAGPPHC 534 (9 March 2016).


Attorney-General, Transvaal v Additional Magistrate for Johannesburg 1924 AD 421.


Legislation Cited


Spatial Planning and Land Use Management Act 16 of 2013.


Land Use Planning Ordinance 15 of 1985 (Cape of Good Hope Province).


Northern Cape Planning and Development Act 7 of 1998.


Mineral and Petroleum Resources Development Act 28 of 2002.


Promotion of Administrative Justice Act 3 of 2000.


Rules of Court Cited


No rules of court were cited in the judgment.


Held


The court held that the interdict sought, although framed as operating “pending” an administrative rezoning outcome, was final in substance and effect, because it would finally determine that mining could not lawfully occur absent rezoning, without a subsequent judicial determination of the parties’ rights.


On the merits, the court held that Drooge Veldt had not been shown to be formally zoned, and it did not have a deemed zoning under section 14(1) of LUPO because there was no evidence that the relevant council had determined the land’s utilisation as required by the statute. The zoning certificates relied upon were treated as having no probative value in the circumstances, and they did not constitute administrative action in themselves.


Interpreting section 26(3) of SPLUMA as a transitional provision, the court held that, where no land use scheme applies, land may be used for purposes listed in Schedule 2 for which it was lawfully used or could lawfully have been used immediately before SPLUMA commenced, provided no legal impediment exists. Because mining is included in Schedule 2 and no lawful prohibition was established, the court held that rezoning was not required for mining to proceed in the relevant interim context.


Accordingly, the applicants failed to establish a clear right (and even a prima facie right) to the relief sought, and the application was dismissed with costs.


LEGAL PRINCIPLES


The judgment applied the principle that an interdict framed as “temporary” or “pending” a future event may nonetheless be final in nature and effect if it results in a final determination of legal rights without a later judicial (or equivalent) adjudication of those rights, consistent with the approach in Airoadexpress (Pty) Ltd v Chairman, Local Road Transportation Board, Durban.


It reaffirmed that a final interdict requires proof of a clear right, an interference with that right, and the absence of an adequate alternative remedy. Where a litigant fails to establish the right component, a court need not determine the remaining requirements.


In statutory interpretation, the judgment applied the canon that a court should, where possible, give effect to every word of a statutory provision and should not treat words as superfluous except as a last resort, as expressed in Attorney-General, Transvaal v Additional Magistrate for Johannesburg. This principle materially informed the court’s interpretation of section 14(1) of LUPO by requiring effect to be given to the words “as determined by the council concerned.”


On administrative-law characterisation, the court applied the principle that zoning certificates do not in themselves constitute administrative action; rather, they are reflective (if at all) of underlying administrative decisions. Where the underlying decisions are not proven, and where the certificates’ reliability is undermined, the certificates may be accorded no probative weight, consistent with Jacobs and Another v Transand and Another and Magalies-Bromberg Property Owners Association v City of Tshwane.


The judgment also applied a motion-proceedings principle that affidavits serve as both pleadings and evidence, requiring an applicant to set out its case with sufficient particularity in the founding affidavit to enable the respondent to answer it. A vague allegation, later expanded in heads of argument, was treated as an inadequate basis to sustain relief.


Finally, the court applied SPLUMA’s transitional structure by treating section 26(3), read with section 24(1), as an interim arrangement that permits land use for listed Schedule 2 purposes where the land was lawfully used or could lawfully have been used immediately before SPLUMA commenced, provided that no independent legal impediment prohibits such use.

About SAFLII
Databases
Search
Terms of Use
RSS Feeds
South Africa: High Court, Northern Cape Division, Kimberley
SAFLII
>>
Databases
>>
South Africa: High Court, Northern Cape Division, Kimberley
>>
2018
>>
[2018] ZANCHC 73
|

|

Sydney-On-Vaal Property Ass and Another v Theta Mining Mining and Others (415/2018) [2018] ZANCHC 73 (26 October 2018)

IN
THE HIGH COURT OF SOUTH AFRICA
NORTHERN
CAPE DIVISION, KIMBERLEY
Case
No: 415/2018
In the
matter between:
SYDNEY-ON-VAAL
PROPERTY ASSOCIATION                                          1
st
Applicant
SCARLET
SUN 15 (PTY)
LTD                                                                          2
nd
Applicant
and
THETA
MINING (PTY)
LTD                                                                             1
st
Respondent
LONHRO
MINING SA (PTY)
LTD                                                                   2
nd
Respondent
DIKGATLONG
MUNICIPALITY                                                                      3
rd
Respondent
MINISTER
OF PUBLIC
WORKS                                                                      4
th
Respondent
MEC FOR
THE DEPARTMENT OF AGRICULTURE,
LAND
REFORM AND RURAL DEVELOPMENT
NORTHERN
CAPE

5
th
Respondent
MINISTER
OF MINERAL
RESOURCES

6
th
Respondent
THE
REGIONAL MANAGER, NORTHERN CAPE REGION,
DEPARTMENT
OF MINERAL
RESOURCES

7
th
Respondent
Coram: Lever AJ
JUDGMENT
Lever
AJ
1.
The applicants’ brought an urgent
application essentially to restrain the first and second respondents
from exercising a mining
right held by the first respondent on the
farm Drooge Veldt. There is really only one substantive prayer in the
relevant Notice
of Motion dated 20 February 2018. This is prayer 2 of
the said Notice of Motion, which reads as follows:

That
pending the final zoning of the farm Drooge Veldt No. 292 in the
administrative district of Barkly-West to allow mining operations
to
be performed on the said farm, the first and second respondents are
interdicted and restrained from conducting any mining activities
on
the farm Drooge Veldt;”
2.
Initially, prayer 2 of the said Notice of Motion
read somewhat differently and first and second respondents, correctly
took the
point that the relief sought by applicants was nonsensical.
At the hearing hereof, applicants moved for an amendment which is
reflected
in prayer 2 as quoted above. First and second respondents
did not oppose such amendment, which was duly granted with no order
as
to costs.
3.
The present application was the third application
by either one or both of the applicants for the same relief based on
the same
grounds in a period extending over more than two years.
However, the first and second respondents did not oppose the
application
on the basis of a lack of urgency. Accordingly, I will
not deal with the present application on that basis and will decide
the
matter on the merits of the application.
4.
There is a long and involved history of
litigation between the applicants and the first and second
respondents. For present purposes,
it is not necessary for me to deal
with this history. The first applicant is the Sydney-on-Vaal Communal
Property Association (“the
CPA”). The second applicant is
a corporate entity with the name Scarlet Sun 15 (Pty) Ltd (“Scarlet
Sun”). The
first respondent is Theta Mining (Pty) Ltd (“Theta”)
and the second respondent is Lonrho Mining SA (Pty) Ltd (“Lonrho”).

These are the active participants in the present litigation. Where it
is necessary to identify one of the parties by name I shall
use the
shortened form of such name set out above.
5.
At the hearing of the present application a
representative of the State Attorney’s office appeared on
behalf of the fourth
respondent and handed up what was described as
an explanatory affidavit. The fourth respondent re-iterated that it
would abide
the decision of the court and that it was not opposing
the relief sought. The said affidavit did not take the matter further
and
it is not necessary to deal with such affidavit in any detail.
6.
As can be seen from the material part of the
Notice of Motion set out above, applicants seek an interdict pending
the rezoning of
the farm Drooge Veldt for mining purposes. The first
question to be decided is whether the applicant seeks a final
interdict or
an interim interdict. The relevance of this question is
that it determines what the applicants have to prove and how they
have
to prove it. Mr Van Heerden, for the applicants, submitted that
the applicants merely sought an interim interdict. Mr Lazarus SC
who
appeared for the first and second respondent’s (“the
opposing respondents”) submitted that applicants were
in fact
seeking a final interdict.
7.
Mr Van Heerden, on behalf of the applicants
argued that the actual use of the property and the legislation
applicable did not expressly
provide for the mining of the property
and that before mining could lawfully take place on the said farm it
had to be rezoned.
Mr Lazarus on behalf of the opposing respondents
argued that by virtue of the fact that there was historically no
specific zoning
of the farm Drooge Veldt. That there was also no
applicable land use scheme in place and that on a proper reading of
s26(3) of
the Spatial Planning and Land Use Management Act
[1]
(SPLUMA) no rezoning was required in order to lawfully mine on the
farm Drooge Veldt.
8.
Mr Van Heerden, in his reply, raised for the
first time, regulation 18
[2]
promulgated under SPLUMA, in support of his argument that s26(3) of
SPLUMA required a formal rezoning application before mining

operations could commence on the farm Drooge Veldt. The said
regulation was published under the provisions of s54 of SPLUMA. In

order to give Mr Lazarus a fair chance to deal with this argument
raised at the last minute, I allowed him to submit written
representations
to me on this question. I also allowed Mr Van Heerden
an opportunity to respond to these written submissions. Both Mr
Lazarus and
Mr Van Heerden submitted their written submissions within
the respective time-period granted to each of them for this purpose.
These submissions will be dealt with at the appropriate place in this
judgment.
9.
Having regard to the fact that applicants seek an
interdict against the opposing respondents, it would be convenient to
first consider
the question as to whether the relief sought by
applicant is in fact a final or an interim interdict.
10.
Mr Lazarus for the opposing respondents argued
that the interdict sought by the applicants in the present
circumstances was final,
since the relief is not sought pending a
final determination of a court of law. In making this submission Mr
Lazarus relied upon
the authority of AIROADEXPRESS (PTY) LTD v
CHAIRMAN, LOCAL ROAD TRANSPORTATION BOARD, DURBAN
[3]
.
11.
Mr Van Heerden, apart from taking a literal
approach did not have an answer to Mr Lazarus’ argument.
12.
Van Heerden JA in the AIROADEXPRESS case set out
the position as follows:

According
to Van der Linde
Institutes
2.1.4.7, an applicant for an interdict who is unable to prove a clear
right may obtain interim relief in order to enable him to
establish
his right ‘in een vollediger Regtsgeding’. The author
therefore envisages a later and final determination
of the existence
of the right in question. Hence, as is stated in Joubert
The
Law of South Africa
vol 11 at 297, an interim
interdict does not involve a final determination of the rights of the
parties and does not affect such
a determination. In short, an
interim interdict serves to adjust the applicant’s interests
until the merits of the matter
are finally resolved. That final
decision has to be arrived at by a court of law or, conceivably
another body or person such as
an arbitrator. Consequently, a
temporary injunction does not necessarily constitute interim relief
in the above sense: if an applicant
seeks an interdict which is to be
operative for a fixed or determinable period, it may still be final
in its nature and effect:”
[4]
(references omitted)
13.
Even though the interdict applicants seek is for
a determinable period, what the applicants seek in the present
proceedings is an
injunction, where the merits of the further process
envisaged by the applicants will not be finally determined by a court
or an
arbitrator, but by an administrative body in a process that
will include in one form or another, a public participation process

and an enquiry, where in the final analysis such administrative body
will exercise a discretion to either rezone Drooge Veldt farm
or not.
The process of rezoning would not ascertain and determine legal
rights in a judicial process.
14.
In other words, what this court is being asked to
do is determine that mining may not lawfully take place on Drooge
Veldt unless
a further administrative process determines that the
relevant land may be used for mining. To my mind, this would be a
final determination
of legal rights by this court. Thus, in both
substance and effect, what applicants seek in the present process is
a final interdict.
15.
Even if I am wrong in this conclusion, for the
reasons set out below I have also reached the conclusion that
applicants have not
even set out a
prima facie
right though open to some doubt, being the first leg of the inquiry
into the requirements for an interim interdict.
16.
The significance of the conclusion that applicant
in both substance and effect seeks a final interdict is that in these
proceedings,
applicants will have to fulfil the requirements of a
final interdict before this court will grant the envisioned
interdict.
17.
The requirements for a final interdict are well
established and applicants must establish a clear right, an act of
interference
and that there is no other satisfactory remedy.
[5]
The question of whether or not applicants have met this standard will
be considered in due course.
18.
Both Mr Van Heerden and Mr Lazarus researched and
set out the history of the relevant legislation that dealt with the
zoning and
use of land.
19.
The community that now forms the CPA, in a land
claims process had been awarded the farms Mozib 279, Than 280 and
Drooge Veldt 292
all situated in the District of Barkly West. The
first applicant describes itself as the beneficial owner and the
occupier of such
farms. The said farms are still registered in the
name of the Republic of South Africa. Prior to the successful land
claim of the
group that now forms the CPA, the said farms formed part
of the Vaalbos nature reserve.
20.
The explanatory affidavit handed up on behalf of
the fourth respondent sets out that the process of transferring the
said farms
to the CPA had been delayed due to turbulence in the
community. That at the time that the said affidavit was deposed, that
the
fourth respondent had now started the process of transferring
such farms to the CPA. At the time that this matter was heard the

transfer had not yet taken place.
21.
In order to determine if applicants have
established a ‘clear right’, it is important to establish
if the law presently
applicable requires that the farm Drooge Veldt
needs to be zoned specifically for mining. The right that applicants
seek to enforce
is that they entitled to insist that the opposing
respondents mine lawfully on the farm Drooge Veldt, which applicants
occupy.
The applicants would like me to approach this issue from the
perspective of ‘is mining a legitimate use of the relevant
farm,’
vis-a-vie the applicable zoning legislation. The
opposing respondents, by contrast would like me to approach this
issue from the
perspective of ‘is there anything that would
prevent it from mining on the said farm,’ in the circumstances.
In my
view nothing really turns on the starting point or the
perspective from which I commence my enquiry. The answer is a matter
of
interpreting the relevant legislative provisions.
22.
The applicants proceed from the position that
they had actually been conducting the business of game farming on the
farm Drooge
Veldt immediately prior to 1 July 2015, the date when
SPLUMA came into effect. The applicants then proceed to contend that
ss 14
and 8 of the Land Use Planning Ordinance
[6]
(“LUPO”) are relevant in this regard. Then Mr Van Heerden
submitted that by virtue of the provisions of LUPO, the farm
Drooge
Veldt was deemed to be zoned in accordance with its actual
utilisation.
23.
Then applicants contend that for the purposes of
s26(3) of SPLUMA that the farm Drooge Veldt had actually been zoned
for agricultural
purposes. In support of this contention applicants
rely on two zoning certificates. The first one annexed to their
founding affidavit
being annexure “FA7” and emanating
from the Dikgatlong Municipality is dated 19 October 2016. The
District of Barkly
West, where the farm Drooge Veldt is located,
falls under the administration of the Dikgatlong Municipality. The
second zoning
certificate, curiously emanates from the Sol Plaatjie
Municipality. It is dated the 20 February 2013 and is annexed to the
replying
affidavit as annexure “RA7”.
24.
The many curious features and circumstances
surrounding both of these documents will be considered in due course,
together with
the question as to whether they constitute
‘administrative action’ or not.
25.
The applicants also appointed a town planner, a
certain Mr N Haarhoff (“Haarhoff”), whose affidavit is
annexed to the
founding papers as annexure “FA9”, to
investigate the position regarding zoning in the Dikgatlong
Municipality. Haarhoff
attaches a letter from the then acting
Municipal Manager to the effect that the Dikgatlong Municipality is
still using LUPO, that
they do not have a Land Register or a Zoning
Map. The letter further states that they had compiled a new ‘land
use scheme’
but that this was never promulgated.
26.
Haarhoff then confirmed that on his visit to the
Dikgatlong Municipality he found that: there was no land register in
terms of LUPO;
there was no plan as prescribed in LUPO; and there is
no zoning map as required in LUPO. Haarhof then expressed the opinion
that
in terms of the general provisions of LUPO, if there is no
zoning scheme then the land remains zoned as agriculture. Haarhoff
then
also expressed the opinion that if a company did not have a
mining right before 1 July 2015 when SPLUMA came into effect then
mining
was not a lawful use of the property concerned.
27.
Mr Van Heerden then submitted that based on the
Maccsand
[7]
principle, the zoning certificates referred to above and established
facts, that Drooge Veldt had been zoned for agricultural purposes.

Further, that if the opposing respondents disputed the said zoning
certificates, based on the Oudekraal
[8]
principle, such certificates would have to be set aside first.
28.
Mr Van Heerden submitted that in order for the
court to interpret s26(3) of SPLUMA and to interpret the zoning
legislation generally,
cognisance should be taken of what actually
happened on the farm Drooge Veldt factually before 1 July 2015. That
Theta did not
lawfully use Drooge Veldt for the purpose of mining
immediately before 1 July 2015.
29.
Mr Van Heerden vaguely suggested that the
Regulations published by the Administrator under the provisions of s8
of LUPO
[9]
for land that fell outside of existing town-planning schemes would be
zoned according to their utilisation. However, his main support
for
this contention was almost exclusively based on s14 of LUPO. In fact,
the said scheme regulations published by the Administrator
under the
provisions of s8 of LUPO refer back specifically to s14(1) of LUPO.
Again, Mr Van Heerden emphasised that Drooge Veldt
was used for
agricultural purposes.
30.
Mr Van Heerden argued that in terms of the
provisions of s14(1) of LUPO the farm Drooge Veldt was zoned as
agricultural land in
accordance with its utilisation. Further, that
the commencement of SPLUMA did not have any effect on that zoning.
31.
Mr Van Heerden then submitted that even if I find
against the arguments set out above, I should find that Drooge Veldt
should be
deemed to be for agricultural purposes, because:
31.1.
SPLUMA commenced operation on the 1 July 2015;
31.2.
If no zoning has taken place s26(3) of SPLUMA
should be applied;
31.3.
In terms of applicants’ interpretation of
s26(3) of SPLUMA the actual land usage of Drooge Veldt immediately
prior to 1 July
2015 was agricultural. That the opposing respondents
could not lawfully commence mining before the 1 July 2015 as the
amendments
to the MPRDA set out that the effective date of their
mining right was the date that the mining right was executed. That
the mining
right itself set out that the effective date would be the
date of execution of the mining right. It is common cause that the
mining
right was executed on the 12 August 2015. That Drooge Veldt
can only be used for agricultural purposes unless it is rezoned.
32.
Mr Van Heerden also contended that regulation 18
promulgated in terms of SPLUMA, referred to above, supported the
interpretation
applicants’ put forward in respect of s26(3) of
SPLUMA that rezoning was required. Again, Mr Van Heerden relied on
the Maccsand
judgment referred to above.
[10]
33.
In the further written submissions made on
applicants’ behalf on regulation 18, promulgated under SPLUMA,
Mr Van Heerden submitted
that it supported applicants’
interpretation of s26(3) of SPLUMA. Paragraph 4 of the written
submissions reads as follows:

Applicant
submits that the interpretation of the words ‘land may be used
only for purposes permitted’ in Section 25(2)
(sic) and the
words ‘only’ and ‘immediately prior’ in
Section 26(3) is underpinned by Section 58(1)(b)
and (c) read with
Regulation 18”
34.
Presumably the reference in the passage quoted
above to s25(2) is meant to refer to section 26(2) otherwise, these
submissions would
make no sense at all. Reference to s58 of SPLUMA
refers to the ‘penalties’ provision in the said Act.
35.
Further, Mr Van Heerden argued that the
interpretation of s26(3) of SPLUMA must be restrictive, that it is
intended to make a final
determination on the meaning of ‘lawful
use’ and ‘could lawfully have been used’
immediately before the
commencement of SPLUMA. He then submits that
the relevant date is 1 July 2015. Mr Van Heerden then contends, “If
the interpretation
of Respondents is accepted then the words
immediately before are irrelevant and have no meaning.”
Accordingly, Mr Van Heerden
submits that Regulation 18 is relevant
and assists with the interpretation of s26 of SPLUMA.
36. Mr
Van Heerden then went on to contend in a lengthy argument that the
opposing respondents had not complied with s5A of the
MINERAL,
PETROLEUM AND RESOURCES DEVELOPMENT ACT
[11]
(“MPRDA”). The appropriateness of this contention in the
circumstances will be considered later in this judgment.
37.
Mr Lazarus on behalf of the opposing respondents,
contended that the Maccsand
[12]
case is distinguishable from the facts of the present case. He
pointed out that in the Maccsand case there was in fact a zoning
for
the relevant piece of land that precluded mining. This was not the
case on the facts presently before the court. He submitted
that the
farm Drooge Veldt had never be zoned.
38.
Mr Lazarus referred me to the work of Dale
[13]
where the learned author set out a process of enquiry to determine
whether a particular piece of land needed to be rezoned in order
for
mining to take place on such land.
39.
The process proposed by Dale is to make the
following enquiries:
39.1.
Has a town planning scheme been promulgated over
the relevant land?
39.2.
If yes, has the land in fact been zoned?
39.3.
If yes, does the zoning permit mining?
39.4.
If not, does the scheme contain an exemption for
mining?
39.5.
If not, is there an existing use provision which
permits mining to continue?
39.6.
If not, the land would have to be rezoned to
permit mining.
[14]
40.
Mr Lazarus submitted that if the answer to the
first question posited by Dale was “no”, that would be
the end of the
enquiry. This would be true for the second question as
well. He then submitted that the farm Drooge Veldt had never been
zoned.
In support of this contention he pointed to the evidence of
Haarhoff, the town planner, who submitted an affidavit on applicants’

behalf.
41.
Mr Lazarus then contended that Drooge Veldt could
also not have a deemed zoning under s14(1) of LUPO. He made this
contention on
the authority of the judgment of Thring J in the case
of HANGKLIP ENVIRONMENTAL ACTION GROUP v MEC FOR AGRICULTURE,
ENVIRONMENTAL
AFFAIRS AND DEVELOPMENT PLANNING, WESTERN CAPE, AND
OTHERS
[15]
where it was held that s14(1) envisages a two-stage approach where
the local council concerned must factually determine the actual
use
of the relevant land and then it issues the most restrictive zoning
under the provisions of s14(3) of LUPO. Mr Lazarus then
pointed out
that there was no evidence to suggest that the Dikgatlong
municipality had ever determined what the actual use of the
farm
Drooge Veldt was at the time that LUPO came into effect on 1 July
1986.
42.
Mr Lazarus then informed the court that the
Northern Cape Planning and Development Act
[16]
came into effect on the 1 June 2000. This act repealed LUPO in the
Northern Cape. Although in terms of s39 of the said act, the
existing
zoning or planning schemes made or deemed to have been made in terms
of LUPO shall remain in force until a new scheme
is approved in terms
of s41 of the Northern Cape Act. He then pointed out that although
schedule E of the Northern Cape act lists
a scheme for Barkly West
under the provisions of s8 of LUPO, there is no evidence that this
applied to Drooge Veldt.
43.
Mr Lazarus then deals with SPLUMA and points out
that s26(3) read with s24(1) of SPLUMA is clearly a transitional
arrangement. It
will hold sway for a period of 5 years from the
commencement of SPLUMA, being 1 July 2015. He then points to the
affidavit of Haarhoff,
which confirms that the Dikgatlong
municipality does not have a land use scheme under SPLUMA.
44.
Mr Lazarus argues that s26(3) of SPLUMA allows
for land use to continue where the land was being used for that
purpose immediately
prior to the commencement of SPLUMA on the 1 July
2015. However, he contends that s26(3) goes further than that and
allows for
the land to be used for certain purposes where the land
concerned was not actually being used for that purpose but could
lawfully
have been used for that purpose at that time. In other
words, provided the land was capable of being used for a purpose
listed
in schedule 2 to SPLUMA, such land use could continue.
45.
Mr Lazarus submitted that there being no actual
zoning for Drooge Veldt and no prohibition of mining activity on
Drooge Veldt in
the relevant title deed or in any legislation, and
mining being specifically included in schedule 2 of SPLUMA that
rezoning was
not required for mining to take place on Drooge Veldt.
46.
In respect of the zoning certificates being
annexure “FA7” to the founding affidavit and annexure
“RA7”
to the replying affidavit. Mr Lazarus pointed out
that there were multiple difficulties with each of them. He also
contended that
on the authority of JACOBS AND ANOTHER v TRANSAND AND
ANOTHER
[17]
and MAGALIES-BROMBERG PROPERTY OWNERS ASSOCIATION v CITY OF
TSHWANE
[18]
that a
prima facie
right cannot be established by such certificate. That in and of
themselves such certificates do not constitute administrative action

in that issuing such certificates does not involve the taking of a
decision. The underlying decision by the relevant authority

constitutes the administrative action. That there is no evidence of
such underlying decision, whether deemed or granted in respect
of
either certificate tendered by the applicants.
47.
In respect of the argument made by the applicants
in relation to s5A of the MPRDA Mr Lazarus points out that applicants
in their
founding affidavit have merely alleged non-compliance with
the said section of the MPRDA. They have not informed respondents in

what manner they have failed to comply with the provisions of s5A of
the MPRDA and that in such circumstances the opposing respondents

could not be expected to do more than annex their notice to the
landowner and/or occupier and their environmental authorisation
to
their answering affidavit.
48.
In respect of the reference to Regulation 18
under the regulations issued under SPLUMA the opposing respondents
contend that such
regulation is not relevant because they do not wish
to change the purpose of the land use from one lawful purpose to
another, nor
do they wish to formalise an existing land use. This
submission rests on the contention that Drooge Veldt has never been
zoned
and that it also does not have a ‘deemed’ zoning.
49.
In dealing with the arguments raised by the
applicants and the opposing respondents, it would be convenient to
start with the submissions
made on the applicability of Regulation
18. Whilst both applicants and the opposing respondents have made
written submissions on
this aspect, in my view they have both
overlooked a fundamental difficulty. Regulations are made under
delegated authority, and
it creates certain difficulties if such
regulations are used to aid in the interpretation of the empowering
statute itself.
50.
The function of this court is to interpret the
empowering act. This must be done with reference to the content and
context of the
relevant Act. Accordingly, Regulation 18 is no more
than an opinion by the appropriate government department on what
Parliament
intended in enacting SPLUMA. The regulations do not give
context to SPLUMA because the regulations were promulgated some two
years
after Parliament passed SPLUMA.
51.
This approach was adopted by the author
Kellaway
[19]
relying on English authorities. In my view, this is the appropriate
approach to take and I find as Regulation 18 was not contemporaneous

with SPLUMA, it cannot lend context to the act. It is no more than an
opinion of what the relevant department thinks that SPLUMA
means. It
is not binding on this court and for the reasons set out above I find
that it does not lend context to SPLUMA. Accordingly,
I will not be
using the said regulation 18 as an aide in interpreting s26(3) of
SPLUMA.
52.
If I am wrong in this approach I find for the
reasons set out below that the farm Drooge Veldt has not been zoned
and does not have
a deemed zoning. Therefore, the opposing
respondents attitude is quite correct, Regulation 18 is not relevant
because the opposing
respondents do not wish to and are not required
to change the use of the farm Drooge Veldt under the provisions of
SPLUMA nor do
they wish to and are furthermore not required to
formalise the existing use under SPLUMA.
53.
Turning next to the reliance of applicants on the
provisions of s5A of the MPRDA as a basis for their relief. The
opposing respondents
complain that applicants have not pertinently
set out in what respects they have not complied with the said s5A.
The opposing respondents
are quite correct in this complaint. In the
whole of the applicants’ founding affidavit, there is exactly
one sentence that
deals with the said s5A. This reads as follows:
“Theta has not complied with s5A of the MPRDA and is not
entitled to commence
mining operations on this basis alone.”
54.
By way of contrast, four and a half pages of the
applicants Heads of Argument are devoted to this issue. Having regard
to the nature
of applications where affidavits form both the
pleadings and the evidence tendered in support of such case, the
founding affidavit
must appraise the respondent of the case it has to
meet. In this context, the applicants had an obligation to set out
pertinently
in what respects Theta had not complied with s5A of the
MPRDA so that the opposing respondents were properly appraised of the
case
it had to meet.
55.
In these circumstances I find that by attaching
the notice sent to the owner/occupier and the Environmental
Authorisation the opposing
respondents have properly met the case
they were called upon to deal with in applicants’ founding
affidavit. Accordingly,
I will not uphold s5A of the MPRDA a basis
for the relief claimed in the applicants’ Notice of Motion.
56.
I have another difficulty with this aspect of
applicants’ case, conceptually having regard to the manner in
which the applicants
have framed their Notice of Motion this, as a
ground for the relief claimed, simply does not fit in. At the hearing
of this application
save for the amendment to paragraph 2 already
dealt with above, applicants did not seek to amend their Notice of
Motion further.
57.
It is not the place of this court to make a case
for the applicants and re-cast the applicants’ Notice of Motion
in a way
that might accommodate the inclusion of s5A of the MPRDA as
a ground for the relief claimed or as a ground for different relief.

To attempt to do so would be unfairly prejudicial to the opposing
respondents.  For this reason as well, I cannot hold that
s5A of
the MPRDA provides a basis for the relief claimed in the applicants’
Notice of Motion.
58.
Turning now to the certificates being annexure
“FA7” to the founding affidavit and annexure “RA7”
to the
replying affidavit and the question whether in and of
themselves they have any probative value as well as the question as
to whether
the constitute ‘administrative action’ in the
sense contemplated in the Promotion of Administrative Justice Act
[20]
(“PAJA”).
59.
Dealing first with the certificate issued by the
Sol Plaatjie Municipality annexed to the replying affidavit as
annexure “RA7”.
This certificate is dated 18 February
2013. Although this certificate purports to be issued by the Acting
Chief Town Planner, one
Motseoa Fumane Phatedi (“Phatedi”),
it was not signed by the said Phatedi. The letters ‘pp’
precede an
illegible signature. On the face of the document, there is
nothing to show that the actual signatory had the authority to sign
and issue the relevant certificate. This issue was not dealt with in
the applicants’ replying affidavit.
60.
The second difficulty with this document is that
it purports to show that the farm Drooge Veldt is zoned agricultural
in terms of
‘the Sol Plaatjie Land Use Management Scheme 2008.
As Mr Lazarus pointed out having regard to the chronology the Sol
Plaatjie
Land Use Management Scheme 2008 must have been promulgated
under the Northern Cape Act
[21]
.
Mr Lazarus pointed out that there was nothing in the said Northern
Cape Act that allowed for extra-territorial jurisdiction. I
could
find nothing in the said Act authorising extra territorial
jurisdiction for the Sol Plaatjie Municipality or any other local

authority. Mr Van Heerden also did not refer me to any such authority
in the Northern Cape Act or in any other legislation that
would
authorise such authority.
61.
The third difficulty with the certificate being
annexure “RA7” is that it carries the following
notation:”

#Although
farm is in Barkly West this certificate is issued in terms of the
2011 Demarcation in which it resides as included in
the Sol Plaatjie
Local Municipality map (map provided by the Francis Baard District
Municipality) Property had no notation indicated
in the previous
zoning register. If actual zoning differs from above the onus lies
with the owner to provide documentation to the
local authority
proving the contrary.”
62.
The difficulty with the said notation as pointed
out by Mr Lazarus is that no legal basis is set out or established
for making it.
Indeed, Mr Van Heerden had no response to this
contention in his submissions in reply.
63.
I find that no legal basis has been set out for
making such notation and furthermore, no legal basis has been set out
or established
by applicants for the Sol Plaatjie Municipality to
issue such certificate in the first place, the relevant farm being
outside their
area of jurisdiction.
64.
Turning now to the second certificate, being
annexure “FA7” to the founding affidavit. The certificate
is issued by
the Dikgatlong Municipality and it is dated 19 October
2016. There are a number of curious features to this document as
well. Firstly,
the farm Drooge Veldt is referred to as “Agricultural
Zone”, this is a strange choice of language in the context.
Usually,
reference would be made to “agricultural land”.
65.
Secondly, this certificate purports to be signed
by the Acting Municipal Manager, one Kgotso Moeketsi. The same Acting
Municipal
Manager then purported to write a letter to the Department
of Mineral Resources approximately one month after issuing the said
certificate. This document is annexed to the founding affidavit as
annexure “FA8”. The signatures on both of these documents

purporting to come from the same person are so fundamentally
different that the veracity of one or both of these documents are

called into question. Although Mr Lazarus raised these issues in his
argument, Mr Van Heerden did not deal with them in reply.
66.
Thirdly, this certificate purports to have been
issued under LUPO, yet on the evidence of Haarhoff as supported by
the letter of
the acting Municipal Manager dated 24 January 2018,
Dikgatlong municipality does not have a ‘land register’,
a plan
or a zoning map. All of which are required by LUPO.
Accordingly, there can be no lawful factual basis for issuing “FA7”

on the 19 October 2016. In such circumstances annexure “FA7”
could never have been lawfully issued.
67.
Dealing now with the question as to whether “FA7”
or “RA7” constitute ‘administrative action’.

On the authority of both JACOBS AND ANOTHER v TRANSAND AND
ANOTHER
[22]
and MAGALIES-BROMBERG PROPERTY OWNERS ASSOCIATION v CITY OF
TSHWANE
[23]
the certificates themselves do not constitute ‘administrative
action’. The underlying Council decisions and resolutions
would
constitute the ‘administrative action’.
68.
On the applicants’ papers in the present
application there is absolutely no proof of any such underlying
decisions or resolutions
of the Council. On the contrary, the
evidence of Haarhoff that there was no register, plan or map as
required under LUPO would
tend to support the conclusion that no such
decisions or resolutions were ever taken by the Dikgatlong
municipality.
69.
At best the said certificates might be
prima
facie
proof of the existence of such
administrative action, although the MAGALIES-BROMBERG
[24]
case would not support this view. However, taking into account the
difficulties with both such certificates, as well as the fact
that on
applicants’ own evidence in the form of Haarhoff’s
affidavit, no register, plan or map exists as required by
LUPO, in my
view such certificates cannot even be considered as
prima
facie
proof of such administrative action.
70.
The consequence of my conclusion that such
certificates are not in and of themselves ‘administrative
action’, and also
that in the circumstances referred to above
they cannot even be regarded as
prima facie
proof of such ‘administrative action’, is that there is
nothing that needs to be set aside by the opposing respondents.
The
practical effect of such conclusions in the present circumstances are
that I will simply regard “FA7” and “RA7”
as
having absolutely no probative value in the present circumstances.
71.
The next question that needs to be considered is
whether the farm Drooge Veldt can be said to have a deemed zoning
under the provisions
of s14(1) of LUPO. Section 14(1) of LUPO reads
as follows:

14(1)
With effect from the date of commencement of this Ordinance all land
referred to in section 8 shall be deemed to be
zoned in accordance
with the utilisation thereof, as determined by the council
concerned.”
72.
As set out above Mr Van Heerden points to
evidence of the actual utilisation of the farm Drooge Veldt and his
interpretation of
s14(1) of LUPO ends at the comma and omits the
phrase “…, as determined by the council concerned.”
Mr Lazarus
points out that there is no evidence that the council
concerned, in this case the Dikgatlong municipality ever determined
the actual
usage of the farm Drooge Veldt on the 1 July 1986 when
LUPO commenced.
73.
Mr Lazarus is correct there is a well-known canon
of interpretation that a court must, if possible, give meaning to
every word in
a statute unless necessity determines otherwise. The
position was set out by Kotze JA in the case of ATTORNEY-GENERAL,
TRANSVAAL
v ADDITIONAL MAGISTRATE FOR JOHANNESBURG
[25]
as follows:

A
statute should be so construed that, if it can be prevented, no
clause, sentence or word shall be superfluous, void or insignificant.

To hold certain words occurring in a section of an Act of Parliament
as insensible, and as having been inserted through inadvertence
or
error, is only possible as a last resort.”
[26]
(references omitted)
74.
There is no case made out that to give effect to
these words would undermine the intention of the provincial
legislature that enacted
LUPO. There is also nothing to suggest that
this would be the result of giving effect to the ordinary meaning of
the phrase “…,
as determined by the council concerned.”
There is no ambiguity in the phrase itself, nor is any ambiguity
created by its
insertion into s14(1) of LUPO. In the circumstances, I
must give effect to the ordinary meaning of such phrase.
75.
Indeed, there is no evidence that the Dikgatlong
municipality ever determined what the actual utilisation of Drooge
Veldt was before
1 July 1986 when LUPO came into effect. The
consequence of this is that Drooge Veldt does not have a deemed
zoning under the provisions
of s14(1) of LUPO.
76.
The next question to be determined is how s26(3)
of SPLUMA is to be interpreted. Section 26(3) must be read in
conjunction with
s24(1) of SPLUMA because it shows that s26(3) is an
interim arrangement that will only hold sway for a period of 5 years.
Section
24(1) of SPLUMA reads as follows:

24(1)
A municipality must, after public consultation, adopt and approve a
single land use scheme for its entire area within five
years from the
commencement of this Act.”
77.
Section 26(3) of SPLUMA reads as follows:

26(3)
Where no town planning or land use scheme applies to a piece of land,
before a land use scheme is approved in terms of this
Act such land
may be used only for the purposes listed in Schedule 2 to this Act
and for which the land was lawfully used or could
lawfully have been
used immediately before the commencement of this Act.”
78.
Section 26(3) also has to be read in the context
of schedule 2 of SPLUMA because this constitutes a finite list of the
uses that
land which has not been zoned and is not subject to a land
use scheme may be used. Depending upon how one reads and interprets
s26(3) may also be the list of lawful uses for which the relevant
land could have been used immediately before the commencement
of
SPLUMA.
79.
In short, Mr Van Heerden contended that s26(3)
required that the land concerned must actually have been used for the
relevant purpose
immediately before the commencement of SPLUMA. In
effect his interpretation of the relevant sub-section stopped after
the word
“used” in s26(3), although he tried to interpret
the phrase that followed the word “used” in a manner that

would be consonant with his interpretation, the result was a strained
and unnatural construction of the language used. Mr Van Heerden’s

contention was that the land was used for agriculture immediately
prior to SPLUMA coming into effect therefore Drooge Veldt could
only
lawfully be used for agriculture unless it was rezoned.
80.
Mr Lazarus contended that s26(3) meant that the
land must have been used for the purpose concerned “or”
was at least
capable of being used for that purpose immediately
before the commencement of SPLUMA. The effect of Mr Lazarus’
interpretation
is that if there was no legal impediment and the land
concerned was capable of being used lawfully for any purpose set out
in Schedule
2, then no rezoning or zoning was required in this
interim period. Mr Lazarus pointed out that Drooge Veldt had never
been zoned,
consequently s26(3) applied. He further pointed out that
Drooge Veldt had no impediment to it being used for mining. That
there
was nothing in the title deed of Drooge Veldt that would
prohibit or restrict mining. Mining was a land use that was
specifically
included in Schedule 2. He also pointed out that there
was nothing in the relevant legislation that prohibited mining on
Drooge
Veldt in these circumstances. Finally, he pointed out that the
mining right itself was proof that the farm Drooge Veldt was capable

of lawfully being used for the purpose of mining.
81.
Mr Van Heerden in his response to Mr Lazarus’
submissions on regulation 18 included a further argument. Although
strictly
speaking Mr Lazarus hasn’t had an opportunity to
respond to it, for the sake of completeness I am going to consider
it. This
argument was to the effect that if I adopt Mr Lazarus’
interpretation of s26(3) it would render everything that precedes the

phrase “…or could lawfully have been used immediately
before the commencement of this Act.”, irrelevant and

meaningless.
82.
What Mr Van Heerden loses sight of is that s26(3)
is clearly an interim arrangement. That ‘wall to wall’
municipalities
only came into existence in 2002. That s26(3) was
intended to deal with a situation where a large flood of properties
that were
previously not affected by town planning and associated
zoning would have to be accommodated in the system. Mr Lazarus’
interpretation
is both a practical and pragmatic way to deal with
this flood of new properties into the system. It restricts the use of
such land
in two ways. Firstly, it confines the use of the land to a
use listed in Schedule 2. Secondly, the use of the land must be
lawful
in other words there must be no legal impediment to such use
either in the title deed of in respect of any other law. Finally, one

must not lose sight of the fact that this is an interim arrangement
to cater for a transitionary period.
83.
In my view parliament must have foreseen this
problem because s26(3) provides a practical and pragmatic way to deal
with this transitionary
period. Accordingly, I find that it is not
necessary to zone or rezone the farm Drooge Veldt before mining can
take place on the
property.
84.
Mr Lazarus’ argument follows the process
suggested by Dale, as set out above. In the present circumstances I
believe it is
an appropriate process to follow. The evidence shows
that Drooge Veldt was never factually zoned up to the launch of the
present
application and for the reasons set out above cannot be said
to have a ‘deemed zoning’. Accordingly, it would not be

necessary to rezone Drooge Veldt for mining to lawfully take place on
the said farm.
85.
It follows from these conclusions that applicants
have not proved a clear right or even a
prima
facie
right as a basis for the relief that
they claim. In the circumstances, it is not necessary to deal with
the other requirements
for a final or even a temporary interdict and
the application stands to be dismissed.
86.
The last remaining issue is the issue of costs.
Both Mr Van Heerden and Mr Lazarus adopted the approach that costs
should follow
the result. Indeed, neither party made out a case to
depart from this general rule. In the circumstances, costs will
follow the
result. Such costs will include the costs of the
postponement on the 9 March 2018.
In the
circumstances, the following order is made:
1)
The application is dismissed.
2)
The applicants are to pay the costs of this
application jointly and severally, the one paying the other to be
absolved. Such costs
shall include the costs of the postponement on
the 9 March 2018.
Lawrence
Lever AJ
Northern
Cape Provincial Division
Representation:
Applicants:
Mr C N
van Heerden oio Van de Wall Inc
1
st
and 2
nd
Respondents:
Mr P
Lazarus SC oio Duncan & Rothman Inc.
Date of
Hearing: 28 March 2018
Judgment
handed down on:
26 October 2018
[1]
Act 16 of 2013.
[2]
These regulations were published as GNR239 of 23 March 2015 and
published in Government Gazette 38594. Such regulations came
into
operation on the 13 November 2015 in terms of GN1126 published in
Government Gazette 39415.
[3]
[1986] ZASCA 6
;
1986 (2) SA 663
(A) at 681 D-F.
[4]
AIROADEXPRESS case, above at 681 D-F.
[5]
PREST., THE LAW AND PRACTICE OF INTERDICTS., Juta & Co., 1996.,
Chapter 4 pp 42-47.
[6]
Ordinance 15 of 1985 for the Cape of Good Hope Province.
[7]
Maccsand (Pty) Ltd v The City of Cape Town and Others
2011 ZASCA 141
and the Constitutional Court Judgment 2012 ZACC 7.
[8]
Oudekraal Estates (Pty) Ltd v City of Cape Town & Others
2004
(6) SA 222
(SCA) at para [26].
[9]
As published in P.N. 353 of 1986.
[10]
Maccsand case., above.
[11]
Act 28 of 2002.
[12]
Above.
[13]
Dale, South African Mineral and Petroleum Law, Lexis Nexis Issue 23,
MPRDA 202.
[14]
Dale, above.
[15]
2007 (6) SA 65
(CPD) at 72 D-H.
[16]
Act 7 of 1998.
[17]
[2014] ZAWCHC 172
(14 November 2014) at para [18].
[18]
[2016] ZAGPPHC 534 (9 March 2016) at para [25].
[19]
Kellaway EA., PRINCIPLES OF LEGAL INTERPRETATION, Statutes, Contacts
& Wills., Lexis Nexis., 1995 at pp 208-209.
[20]
Act 3 of 2000.
[21]
Fn 16 above.
[22]
[2014] ZAWCHC 172
(14 November 2014) at para [18].
[23]
[2016] ZAGPPHC 534 (9 March 2016) at para [25].
[24]
Above, at para [25].
[25]
1924 AD 421.
[26]
Above at 436.