About SAFLII
Databases
Search
Terms of Use
RSS Feeds
South Africa: South Gauteng High Court, Johannesburg
SAFLII
>>
Databases
>>
South Africa: South Gauteng High Court, Johannesburg
>>
2018
>>
[2018] ZAGPJHC 583
|
|
Standard Chartered Bank, Johannesburg Branch v Blue Financial Services Limited and Another (20442/2014) [2018] ZAGPJHC 583 (31 August 2018)
REPUBLIC
OF SOUTH AFRICA
IN THE HIGH COURT OF SOUTH AFRICA
GAUTENG LOCAL DIVISION,
JOHANNESBURG
CASE NO: 20442/2014
In the matter
between:
STANDARD CHARTERED BANK,
JOHANNESBURG
BRANCH
Applicant
and
BLUE
FINANCIAL SERVICES
LIMITED
First
Respondent
BLUE FINANCIAL SERVICES (SOUTH
AFRICA)
(PTY)
LIMITED
Second
Respondent
J U D G M E N T
MAKUME,
J
:
[1] The dispute between the parties in
this matter has its genesis in two agreements the first being the
term loan and banking facility
agreement concluded between the
Applicant and the First Respondent during or about the 26
th
February 2009. The second agreement is the Debt Rescheduling
Agreement (DRA) entered into between the Applicant and the
Respondents as well as other companies which formed part of the Blue
Group of Companies. This second agreement was concluded
during
or about August/September 2010 at the time when it was common cause
that the Blue Group of Companies was having financial
difficulties in
meeting its obligations as set out in the term loan and banking
facility agreement.
[2] At the commencement of this
hearing I was addressed by both counsel on the number of affidavits
before me the issue being whether
I should or should not admit those
filed out of turn and without leave of the court. I deal
hereunder with the sequence and
contents of each affidavit as they
emerge from the record.
THE
FOUNDING AFFIDAVIT
[3] The founding affidavit which sets
out the cause of action in this matter was deposed to on the 5
th
June 2014. Attached to the founding affidavit are the following
documents:
(a)
The term loan agreement
between the Applicant and the First Respondent (Annexure SCB1).
(b)
The cession of debts
document (Annexure SCB2) concluded by the Second Respondent in favour
of the Applicant.
(c)
The guarantee document
(Annexure SCB3) by the First Respondent in favour of the Applicant.
(d)
The Debt Rescheduling
Agreement (DRA) concluded between the First Respondent, the Applicant
and Mayibuye Group (Annexure SCB5).
THE
RESPONDENTS’ ANSWERING AFFIDAVIT
[4] The Respondents’ answering
affidavit is dated the 9
th
July 2014 and was duly served
on the Applicant on the same day. In the answering affidavit Mr
Schalk van der Merwe on behalf
of the First and Second Respondents
(“
the Blue Group
”) raises the following issues:
(a)
That this application
should be dismissed on the basis that the Applicant failed to join
other interested parties as they appear
in the Debt Rescheduling
Agreement (“
the
DRA
”) in
particular Mayibuye and the Lender Committee referred to in the DRA.
(b)
That in terms of the
principles of the rescue package and the DRA the Applicant is bound
by the dispute resolution process contemplated
in the DRA.
(c)
That the Applicant knew or
ought to have known before it elected to proceed on motion that there
would be a dispute concerning the
proper interpretation of the DRA
which would necessitate the calling of oral evidence. In brief the
Respondents argue that this
matter cannot be resolved on the papers
and that the application should be dismissed.
THE
APPLICANT’S REPLYING AFFIDAVIT
[5] The Applicant filed and served its
replying affidavit dated the 6
th
August 2014 on the 7
th
August 2014. In that affidavit the Applicant denies that there
is a need to join the other parties stated in the DRA.
Secondly
the Applicant disputes that its claims are subject to dispute
resolution a process contemplated by the DRA. Lastly
the
Applicant maintains that it is not necessary to refer the dispute to
oral evidence.
APPLICANT’S
FIRST SUPPLEMENTARY AFFIDAVIT
[6] On the 4
th
December
2014 the Applicant filed this supplementary affidavit without leave
and no notice. All that the Applicant says in paragraph
4 of that
affidavit is that it should be admitted as evidence in these
proceedings as it is in the best interest of justice.
This
first supplementary affidavit deals with the issue that the
suspensive conditions contemplated in the subscription agreement
were
never complied with and therefore the DRA lapsed. The Applicant
further posed the issue that if it is so that the Respondents
did not
comply with the suspensive conditions then in that event the
Applicant’s claim is based solely on the term loan and
facility
agreement as well as the cession of debt. The Applicant
requested that Respondents provide information or confirmation
that
the suspensive condition was timeously fulfilled.
RESPONDENTS’
NOTICE OF MOTION DATED MAY 2017
[7]
7.1 On the 26
th
May 2017
some three years after the last affidavit the Respondents filed this
application requesting that they be granted leave
to deliver a
supplementary affidavit Annexure SVDM1.
7.2 As motivation for the filing of
that supplementary affidavit the Respondents say that subsequent to
the filing of its answering
affidavit a number of relevant events had
occurred which the Respondents deem appropriate that they be brought
to the attention
of the court.
7.3 In that affidavit the Respondents
through Schalk van der Merwe their Group Chief Legal Adviser and
Group Company Secretary say
that –
(a)
The Applicant in paragraph
24 of its founding affidavit did not dispute the validity of the DRA
and that it was surprising that
in the heads of argument the
Applicant now disputes the fulfilment of the conditions precedent to
the subscription agreement namely
the DRA. The Respondents
attached a document titled “
Fourth
Amendment and Restated Subscription Agreement
”
which was concluded on the 9
th
December 2010 between Mayibuye Group and Blue Financial Services
Limited. That document confirmed that the conditions precedent
had
been fulfilled and that both the subscription and the DRA had taken
effect.
(b)
Secondly the distribution
and conversion plan contemplated in the DRA was submitted and that
Applicant failed to disclose the nature
of its dispute to the
distribution and conversion plan. The Respondents concluded that the
only remedy open to the Applicant is
in terms of clause 7.24 of the
DRA.
(c)
Thirdly the Respondents in
this affidavit made reference to the findings of a Zambian court in
an action based on the DRA between
one of the lenders African Banking
Corporation again Blue Financial Services in which court it was found
that the DRA did not supplant
the loan facility agreement. All it did
was to amend the terms of the loan agreement as to the repayment
schedule.
[8] It is common cause that on the
15
th
June 2017 this Court granted the Respondents leave to
file this affidavit marked SVDM1.
APPLICANT’S
FURTHER AFFIDAVIT DATED 25 MAY 2017
[9]
9.1 This
was an
affidavit filed in response to the Respondents’ affidavit
marked SVDM1. It is deposed to by one Sirgitkhan Nadine
Bham.
In it the Applicant denies that Annexure SP1 being the fourth
amendment to the subscription agreement resolved the issue
of the
conditions precedent. The Applicant reiterated that the
Respondents have as at that date failed to provide proof of
the
timeous fulfilment of the suspensive condition.
9.2 Secondly in
that affidavit the Applicant disputes that the distribution and
conversion plan is of
relevance to the proceedings as in any
case such distribution and conversion plan was not submitted to the
Lender Committee timeously
as required by the DRA.
FURTHER
SUPPLEMENTARY AFFIDAVIT BY THE RESPONDENTS DATED 7
TH
SEPTEMBER 2017
[10]
10.1 This affidavit was filed without
leave of the court and sent by email to the Applicant’s
attorneys on the 7
th
September 2017. In it the
Respondent say this further supplementary affidavit is in response to
the further affidavit by
Sirgitkhan Nadine Bham. 10.2 Attached
to this affidavit is a copy of a bank statement in the name of Blue
Financial Services
Limited dated the 31
st
December 2010
from which it appears that on the 10
th
December 2010 an
amount of R150 million was credited to that account. Also attached to
that affidavit is a Purchase of Rights Agreement
between Mayibuye and
Pine Bridge Global evidencing how the balance of R13 million was
catered for to enable the fulfilment of the
condition precedent.
NOTICE
OF MOTION TO DELIVER FURTHER SUPPLEMENTARY AFFIDAVIT BY SECOND
RESPONDENT DATED 29 SEPTEMBER 2017
[11]
11.1 This notice of motion was set
down to be moved on the 7
th
February 2018 that is on the
day of the commencement of the hearing of this matter. In the
notice of motion the First and
Second Respondents seek leave to
deliver the further supplementary affidavit.
11.2 In this affidavit the Respondents
say that having briefed a new legal team they received advice to deal
with the issue of the
acceleration of the end date provided for in
the DRA and provide reasons why the Respondents were unable to meet
their commitments
to pay the DRA lenders their agreed interest.
11.3 The Respondents seek leave to
introduce new evidence of fraud that was perpetrated by the founders
of the Blue Group prior
to the conclusion of the DRA.
11.4 Significantly in this affidavit
the Respondents mention that during the three year term of the DRA
only interest accruing to
the existing claims was required to be
serviced by the borrowers and that failure to make any interest
payments qualified as an
acceleration event allowing the DRA lenders
to accelerate the end date.
11.5 The affidavit then goes at length
to describe the fraudulent acts by one of the founders of Blue Group
as well as by one Deon
Bekker which ultimately resulted in the
Respondents not being able to comply with its obligations to pay the
agreed debt.
To back up the fraud issue the Respondents
attached a forensic report by one Hatzikilson a Chartered Accountant.
APPLICANT’S
AFFIDAVIT IN RESPONSE TO RESPONDENTS’ NOTICE OF MOTION DATED 29
NOVEMBER 2017
[12]
12.1 This is an affidavit in reply to
the last affidavit in which the Respondents seek leave to amongst
others introduce new evidence
of fraud by the founders of the Blue
Group. That new evidence is tendered by way of an expert report.
12.2 The Applicant points out that
leave to file that affidavit should be refused as it seeks to
introduce new evidence which was
known to the Respondents at the time
of filing the answering affidavit.
12.3 The Applicant states that in any
case the Respondents do not tell the court the date on which this new
seminal information
came to their attention.
12.4 The Applicant says that they will
be prejudiced by the admission of this new evidence also that the
information by Van der
Merwe as at this stage was pure hearsay,
irrelevant 12.5 In addition the Applicant demonstrated that in a
separate rescission application
involving Mapula the Respondents
blamed the Applicant for the loss and said nothing about the
purported fraud.
THE
RULE AND PRACTICE RELATING TO FILING OF FURTHER AFFIDAVITS
[13] It is common and accepted
practice that three sets of affidavits are allowed. It is the
founding and supplementary affidavit,
the answering affidavits and
lastly the replying affidavits. (See
Bank of Africa v Wood
Bros
(1886) 4 SC 334
;
Transvaal Government v The Standerton
Farm Association
1906 TS 21
;
Rieseberg v Rieseberg
1926
WLD 59
;
Haywood v Gradwell
1932 EDL 305
;
Victor v Victor
1938 WLD 16.)
[14] I commence first with the notice
of motion dated September 2017 wherein the Respondents seek leave to
introduce the fraud evidence
perpetrated against the Blue Group by
amongst others Mr Van Niekerk. The Applicant is opposing that
application on the basis that
the Respondents have failed to
demonstrate when they came to know of the fraud in order to condone
their late introduction of such
evidence.
[15] The filing of supplementary
affidavits outside the regulated set of three can only be allowed in
exceptional circumstances.
The Applicant says that the
application to admit such evidence was brought late with no
explanation.
[16] I have after careful
consideration come to the conclusion that this affidavit in which the
Respondents seeks leave to introduce
new evidence of fraud should not
be allowed. Accordingly the application to admit such affidavit
is dismissed with costs.
[17] The Respondents object to the
Applicant’s first supplementary affidavit filed during December
2017. A period of
three years passed and it was only in
December 2017 that they responded to that affidavit and even then did
not raise any objection
to its admissibility. I have come to
the conclusion that leave be granted to file that affidavit and that
it be considered
in the determination of the issues before me.
[18] Having disposed of the issues
around the affidavits what now remains are two issues. The
first is whether the other signatories
to the DRA should or should
not have been joined in this application. The second is whether the
Applicant is entitled to its claim
or not irrespective of whether the
DRA became unconditional or not.
[19] I will deal first with the
Applicant’s claim which in my view depends on the
interpretation to be placed on clauses 3.5.6,
7.4, 7.28.1 and lastly
7.28.2 of the DRA. It is these clauses in the DRA which are
determinative of the issues in this matter.
[20] The Applicant’s claims 1, 2
and 5 are for payment of interest and not the capital amount referred
to in the term loan
as well as the overdraft facility agreement and
such payments are regulated by clauses 3.5.6, 7.4 as well as 7.2.8.
[21] To kick start I quote
verbatim
the contents of clause 3.5.6 of the DRA. It reads as follows:
“
No principal payment will be
made under the existing facilities for a period of 3 (three) years
(the standstill period) but interest
which accrues on the existing
facilities will be paid during that period.
”
[22] Clause 3.5.6 must be read in
conjunction with clause 7.5.1 and clause 12.14.1 of the DRA which
make it very clear that the
Respondents shall during the payment
period pay interest to the lenders in this case the Applicant.
[23] It is common cause that the
reasons and basis on which the parties concluded the DRA was to
achieve a structural debt rescheduling
instead of liquidating the
Blue Group for its failure to meet its obligations as set out in the
two loan agreements. To this
end the parties agreed on a
moratorium for payment of the capital which is a period of three
years (the standstill period) during
which period only the interest
that accrued to the loan amount was payable.
[24] Clause 3.5.2 of the DRA explains
the fundamental premises of the rescue package which was ultimately
to restore the Blue Group
to solvency and to prevent its winding up
and to provide its creditors with prospects of recovering money owing
to them.
[25] Payment of the interest became
due because the Respondents had defaulted with payments during the
standstill period and thus
triggering the end date in accordance with
clause 7.8 of the DRA which reads as follows:
“
If an acceleration event
occurs the Lender Committee shall be entitled to accelerate the end
date to such an earlier date as the
Lender Committee may determine
provided that:
7.8.1
the Lender Committee shall deliver written notice (Acceleration
Notice) to Blue in which the Lender Committee advises Blue
both of
the fact that the Lender Committee has elected to accelerate the end
date and on which the end date will occur.
”
[26] It is common knowledge that the
parties had appointed GMG Trust Company SA as the Lender Committee in
terms of clause 5.2 of
the DRA. On the 29
th
July
2013 and the 7
th
August 2013 GMG addressed letters to Blue
Financial Services in the following words:
“
Pursuant to clause 16.2 of
the DRA, acceleration events have occurred under the DRA. This
entitles the lenders under the DRA
to take action specified in clause
7.8 of the DRA. The Lender Committee has elected to accelerate
the end date. The Lender
Committee designates 6 September 2013 to be
the end date.
”
[27] The terminology used in this
agreement is not only repetitive but is also confusing for instance
measuring date and the effective
date are the same. The effective
dates outstanding were measured on the 1
st
January 2011.
It is common knowledge that the effective dates outstanding were
agreed in the sum of R85 million in respect of the
term loan and R51
million in respect of the banking facility or overdraft agreement as
on the 1
st
January 2011. This allegation which
appears in paragraph 38 of the Applicant’s founding affidavit
was not disputed
and was in fact admitted. It relates to claim 3 of
the application.
[28] Similarly in claim 4 the
Applicant claims for the difference between the sum of R234 million
and the value of the South African
book as on the last measuring date
or effective date being the 31
st
December 2013.
[29] Clause 16 which deals generally
with acceleration and the effect of non-payment more than emphasises
the fact that interest
on the amount advanced is treated separately
and as a distinct component from the capital amount.
[30]
The defences raised by the Blue Group as they emerge from their
papers is briefly that interest has not and does not become
payable
as it became part of the conversion plan contemplated in the DRA in
other words the Respondents say that whatever may be
due and owing is
not payable but is bound to be converted to
shares in favour
of the Applicant
. This
contention is in my view belied by the provisions of clause 16 of the
DRA which specifically describes non-payment
of interest as an event
that triggers action for immediate payment even before the expiry of
the moratorium period. Clause 16.2
is clear and unambiguous. It says
that any borrower who fails to pay interest which has become payable
under the DRA on account
of any existing facility on the due date
that constitutes a ground for acceleration. Clause 16.2 also
provides for the existing
facilities to remain intact and for
interest to be payable in terms of or on due date as arising from the
existing facilities.
[31] This document which is the
subject matter of the present dispute is descriptive in name. It was
meant to reschedule payments
due by the Blue Group to the Applicant
arising out of the term loan and the banking facility agreement.
The rescheduling
period is defined in clause 2.1.110 as the period
which commences on the effective date and ends on the end date.
The end
date marks not only the end of the rescheduling period. It
also marks the beginning of the payment period that date was
accelerated
to the 6
th
September 2013 as a result of
certain trigger events. Therefore the rescheduling period ran
from the 1
st
January 2011 up to the 6
th
September 2013.
[32] The distribution plan and
distribution principles which is what the Respondents rely on were
not accepted by the Applicant
and are not relevant for present
purposes. It is common cause that the dispute about the
conversion plan is ongoing between
the parties.
BREACH
OF THE DRA
[33] It is common knowledge that
during July 2013 already the Applicant informed Blue Group that a
breach of the DRA terms had taken
place as contemplated in clause
16.2. That was followed by another letter dated the 7
th
August 2013 which reiterated that the acceleration event as
contemplated in clause 16.2 had occurred and that the Applicant was
now entitled to take action as specified in clause 7.8 of the DRA.
It is common knowledge that the Respondents’ Blue
Group
admitted that event and also that failure to pay interest constitute
an acceleration event. What then remained was
for the
Respondents to file a distribution plan within ten days from the date
of acceleration. The Respondents failed to do so.
Instead it provided
a conversion plan.
THE
AMOUNT OWING
[34] On the 5
th
June 2014 a
certificate of indebtedness was issued by the Applicant indicating
outstanding indebtedness in respect of interest
due under the term
loan and facility up to the 6
th
September 2013 in the
amount of R9 762 765,47. This amount is not disputed.
It is the amount in claim 1 of the
notice of motion.
[35] On the 29
th
November
2013 the Applicant addressed a letter to the Respondents and said the
following:
“
In the acceleration notice
the Lender Committee advised that it had elected to accelerate the
end date. The Lender Committee
advised BFS that it had elected
6 September 2013 to be the end date. BFS was required in terms
of clause 7.13 of the DRA
to deliver a distribution plan to the
Lender Committee by no later than 10 business days after the end
date. To date no distribution
plan has been delivered. Under the
circumstances BFS is in default of its obligations under the DRA.
Clause
7.28 of the DRA entitles the lenders to realise security which they
enjoy under the existing security if the borrowers fail
to comply
with their obligations under clause 7 of the DRA. In view of
the default by BFS, SCB intends exercising its rights
under the
existing security on the basis set out below.
”
[36] Blue Group the Respondent replied
to this letter on the 4
th
December 2013 and basically
denied liability adding that the Applicant was aware and had been
kept abreast with reasons why the
distribution plan referred to in
clause 7.13 had not as yet been circulated. The
Respondents added that any claim that
may exist in favour of the
Applicant in terms of the provisions of clause 7.28 would be limited
to an amount calculated in terms
of the remainder of the provisions
of clause 7 of the DRA. Blue Group made further reference to
clause 12.14.1 of the DRA
as being in support of their contention.
[37] I respectfully disagree with the
Respondents’ conclusion. Once the Respondents failed to
circulate a distribution
plan the interest became payable both in
terms of the term loan as well as in terms of the DRA. This the
Applicant made clear
in a letter addressed to the Respondents dated
the 10
th
December 2013 which letter was in response to the
Respondents’ letter of the 4
th
December 2013.
In paragraph 4 of its letter the Applicant says the following:
“
Clause 7.28 of the DRA
entitles the lenders to realise security which they enjoy under the
existing security if the borrowers fail
to comply with their
obligations under clause 7 of the DRA.
”
[38] This default by the Respondents
entitled the Applicant to realise the security which it enjoys which
is the cession and the
guarantee in relation to the amounts owed to
it under the DRA and the term loan and banking facility.
[39] In an attempt to belatedly comply
with the provisions of clause 7.21 of the DRA on the 11
th
December 2013 the Respondents wrote to the Applicant and said this:
“
We are happy to report that
Blue Financial Services has delivered a conversion plan as envisaged
in clause 7.21 of the Debt Rescheduling
Agreement (DRA) to Mr Brendon
Harms of GMG Trust as chairman of the Lender Committee.
”
[40] The Respondents firstly failed to
forward the conversion plan within the prescribed period stipulated
in clause 7.2.1.
Secondly the purpose of the DRA would have
been defeated had the Applicant agreed to convert what is due in
terms of clause 7 into
equity. That was never the intention of
the parties and it is accordingly not a proposal worth giving
consideration to. The
meaning that Blue Group wants to give to this
concession plan is contrary to what clause 16, 7 and 12.4.1 provide
for. It
is that the existing facilities remain intact. In any
event the DRA does not oblige the Applicant under any circumstances
to accept
the concession plan. It is within their discretion.
The Applicant made this clear to the Respondent in their letter dated
the 24
th
February 2014 addressed to Blue Group.
[41] It is common cause and not in
dispute that one of the factors controlling the existence of this
special loan facility was the
so-called Country Cover ratio.
This was determined at the commencement of the transaction to be the
sum of R234 million.
It was agreed that once the Country Cover
ratio dropped from R234 million in December 2010 to R113 million in
July 2013 this called
for the submission of the conversion plan.
[42] In the correspondence and in its
affidavit Blue does not dispute that payment is due in respect of the
Country Cover ratio
but says that such payment should be dealt with
in terms of the conversion plan. I have already indicated that
the said conversion
plan was not only late but it was never meant to
be compulsory and was in my view correctly rejected by the Applicant.
THE
RESPONDENTS’ CASE
[43] The Respondents confirm that as
at the 31
st
December 2010 its claims as constituted by its
microloans to its clients amounted to R234 million. This was
available to the Respondents
as its total claims against borrowers.
[44] When concluding the DRA the
purpose was to collect that amount from the borrowers and to pay it
to the lenders i.e. the Applicant
and others. All other claims
or assets generated after the 1
st
January 2011 were
excluded from the DRA. So the existing book as at 31 December
2010 was to be collected.
[45] As on the 31
st
October
2010 the capital amount owing to the Applicants was the sum of R143
million. The R234 million was in fact the entire
value of the
Johannesburg book on the South African book.
[46] In terms of the DRA the Applicant
had to be paid interest that was owing to them over a period of three
years and thereafter
other arrangements would be made. It is common
cause that as at 2010 Blue Group was in s state of commercial and
technical insolvency
hence DRA as it was regarded a safer option than
liquidation.
[47] Mayibuye came in and made the
following proposals to Applicant and other lenders:
(i)
Don’t liquidate we
will collect the existing R234 million for all of you.
(ii)
They will achieve this by
reducing the overhead expenses.
(iii)
They will bring expertise
to the process of collecting the R234 million.
(iv)
They will do it vigorously
that is in collecting the existing loan.
(v)
They will invest R163
million to enable Blue to generate new loans going forward.
(vi)
The R163 million that they
will introduce or invest in Blue is to be ring-fenced and will not be
part of the DRA.
(vii)
DRA excludes future claims
from its ambit i.e. Blue with Mayibuye assisting will collect the
book as it existed on the 1
st
November 2011.
(viii)
Once collected those
amounts would be paid over to the Applicant and other lenders.
It was a continuous winding-up of that
book instead of liquidation.
This entire process would depend on the successful collection of the
book.
(ix)
DRA provided that during
the three years still period the lenders or the Applicant must be
paid interest then the process will stop.
This was the bait to
prevent liquidation.
[48] On the happening of the end date
whether on the agreed anniversary of a day before the third
anniversary or if accelerated
in terms of clause 7.8 by the Lender
Committee all assets of the existing book that existed on 1
st
January 2011 would all be liquidated and the money distributed to the
various lenders.
[49] It would appear that Mayibuye
gave itself a period of three years within which it would vigorously
using their expertise collect
the total debt of R234 million plus
interest from the borrowers and then pay all to lenders and close
that book i.e. till end of
December 2013.
[50] In the event of a shortfall after
what shall have been distributed
pro rata
then the shortfall
lenders like the Applicant will then have an option to convert its
debts to shares in the Blue Group i.e. debts
to equity exchange.
If not it will then rely on Blue effecting future payments on the bad
claims, non-performing claims.
[51] There was no time limit to the
collecting of the non-performing accounts as at a given date when the
debt would be written
off. This is like the structure of the old
African Bank which created the good book and the bad book.
[52] Applicant agreed to participate
in the bad book. The good book acquired by Mayibuye in the
creation of new loans or business
was not available to the Applicant.
[53] Only income generated from the
R234 million was the only amount contemplated to be used to pay the
Applicant (clause 2.1.49
excluded claims that is the Mayibuye issue).
[54] The purpose of the DRA was to
enable Blue to continue to collect on the existing claims and to pay
for the first three years
interest to the lenders and thereafter to
distribute all available cash so that the entire existing claims are
extinguished.
[55] The Applicant did receive
interest for close 24 months at the rate of R1,5 million per month.
[56] It is common cause that in the
event of Blue failing to collect on the existing book then the
Applicant has the right of remedy
as prescribed in clause 12.2.5 that
is acceleration of the end date. Such acceleration will have
the effect that the distributed
cash will be collected and paid to
the lender.
[57] Respondents submit that the
purpose of the acceleration of the end date is to stop the entire
process.
[58] In the view that the Respondents
hold the issue is whether this claim for interest which Applicant
says should have been paid
to them prior to the end date is an
independent claim or whether that claim falls within the payment and
distributable process
concluded in clause 7 of the agreement.
[59] The Respondents say that this
claim falls within the distributable process whilst Applicant says it
is a separate and independent
claim.
[60] Respondents say it is why it
allowed for acceleration because there is no money being collected
and it would have been futile
to continue to attempt to recover funds
which are simply non-existent.
[61] In my view the interpretation and
understanding of the Respondents is flawed on the following grounds:
(i) Clause 3.5 reads as follows: “but
interest which accrues on the existing facilities will be paid during
that period”.
(ii) It does not say that interest
will be paid as part of the end date distributable cash.
[62] The Respondents concede that
during the three years interest is payable but if there are no
payments resulting in the non-payment
of interest then the end date
is accelerated and then a different distribution principle kicks in
and is regulated as set out in
clause 3.5.9 of the DRA. The
Respondents argue that clause 3.5.9 requires that collection on
account of existing claims will
be utilised first to pay operating
costs and then to interest on account of existing claims. This
clause that the Respondents
rely on is contradicted by clause 3.5.6
which clearly sets out that no principal payments will be made under
the existing facilities
for a period of three years (the standstill
period) but that interest which accrues on the existing facilities
will be paid during
that period.
[63] There is evidence to which the
Respondents conceded that in fact since the inception of the
moratorium period being the 1
st
January 2011 to the 6
th
September 2013 (the accelerated date) the Respondents had been paying
interest as required. In fact clause 3.5.8 read together
with
clause 3.5.10 puts paid the Respondents’ argument. Clause
3.5.8 reads as follows:
“
During the standstill period
the borrower will use all commercially reasonable endeavours to
collect the existing claims.
”
Clause 3.5.10 reads as follows:
“
To the extent to which those
collections are not needed to pay interest and operating costs they
will be used to create further
claims or to purchase liquid
instruments.
”
[64] The Applicant is not only a
secured lender but falls within the category of shortfall lenders at
the end of the standstill
period. Clauses 7.4 read with 7.5 and
7.6 envisages payment of interest over two different periods.
First it is interest
payable during the rescheduling period which is
the still period and then interest payable during the payment
period. Payment
period as defined in clause 2.1.97 as the
period which commences on the end date and which ends on the date on
which all the capital
account instruments and all the performing
included claims (as at the end date) have either been collected by
the applicable group
companies or finally written off as
irrecoverable in terms of the provisional policy and with the consent
of the Lender Committee
as envisaged in clause 7.20.
[65] It is accordingly not correct
therefor as argued by the Respondents that the whole purpose of the
DRA was to achieve a situation
that after the end date all of the
lenders’ claims shall either have been discharged over the
three years period or by the
conversion of shares or lastly by
writing off the amount as not being collectable. In any event
the Respondents do not have
carte blanche authority to write off that
debt. It has to seek the permission of the Lender Committee as stated
in clause 7.20
of the DRA. Clause 7.20.2 reads as follows:
“
The Lender Committee shall
in its discretion determine whether or not that liquid instrument or
claim must be written off and Blue
shall give effect to the Lender
Committee’s decision.
”
[66] The Respondents maintain further
that post the end date no interest is payable and rely on the
provisions of clause 7.11.
I do not agree with that. The
heading preceding clause 7.11 reads “
Principal Payments
”.
It has nothing to do with interest. In any case in paragraph 29
of the answering affidavit the Respondents
agree and say the
following:
“
During the period between
the effective date and the end date interest will be paid to the
lenders based on the available cash as
contemplated in the DRA.
”
[67] Then there is an interpretation
placed on clause 7.2.12 of the DRA by the Respondents who maintain
that on the happening of
the end date the lenders will be paid cash
amounts whether in respect of interest, principle or cash held by the
borrowers. In
this instance the Respondents in their capital account
and once that is done it is the end of the matter because the
existing claims
will no longer exist. In my respectful view this
interpretation is not correct. The DRA was meant to create a
moratorium
on existing claims for a period of three years so that the
Respondents re-organises itself and improve on its collection and
recovery
methods. It was never meant to extinguish claims. That
interpretation does not make business nor economic sense. It will be
tantamount to reckless trading by whoever is in control of the
Applicant.
[68] It is equally not correct that
excluded claims include existing claims. Quite to the contrary clause
2.1.49 says that excluded
claims means any claim other than existing
claims and the capital account claims. Excluded claims would be
those claims generated
after Mayibuye injected funds into the Blue
Group. Clause 2.1.51 supports this view. Existing claims
are also included
claims (see clause 2.1.66).
[69] A proper reading of the several
clauses of the DRA never intended to extinguish the existing claims.
The intention was
that after three years the
status quo ante
would be reverted to otherwise I see no reason why there are
guarantees including cession of debts in favour of the Applicant if
what the Respondents say is correct. Again I hold the view that
the Respondents’ contention makes no economic sense.
THE
RATIO CERTIFICATE
[70] This is the claim in prayer 3 of
the notice of motion. It is governed by clauses 12.8 and 12.9
of the DRA. It is
as correctly stated by the Respondents
complicated clauses that require certain events to take place prior
to establishing a claim
under those clauses. The Respondents maintain
that the Applicant has not established any of the requirements which
must be met
before clause 12.9 can be invoked.
[71] In prayer 3 the Applicant seeks
an order directing the First Respondent to produce a ratio
certificate as contemplated by the
DRA with reference to the last
measuring date being the 31
st
December 2013 showing the
value and calculation of the South African book as contemplated by
clause 12.5.2 of the DRA.
[72] It is common cause that the last
Country Cover ratio or certificate is that which appears on page 402
of the papers which determines
the cover ratio of South Africa to be
R234 million.
[73] In order for the Applicant to
succeed with claims 4 and 5 there is need to determine if the Country
Cover ratio is lower than
the initial level of R234 million and that
the Respondents have failed to restore same to its initial level
within a period of
twelve months. Therefor to enable the Appellant to
be able to claim prayers 4 and 5 it is incumbent on the Respondents
to produce
a ratio certificate.
[74] Clause 12.6 is clear an reads as
follows:
“
12.6 Blue shall within 10
days after each measuring date deliver to the Lender Committee a
Certificate (Ratio Certificate) which
sets out:
12.6.1
The total costs ratio and each Country Cover ratio as at the
applicable Measuring Date, and the manner in which Blue has
calculated those dates.
”
[75] The Respondents have failed to do
so within 10 days after the measuring date that fell after the
initial measuring date to
deliver a ratio certificate when in fact
that is familiar and is within the knowledge of the Respondents.
The Applicant is
entitled to be furnished with the ratio certificate
to enable it to proceed with its claim as prayed for in prayers 4 and
5.
[76] It is common cause that what the
Country Cover ratio seeks to prevent is that assets or cash of the
Blue Group from one country
being utilised to pay liabilities of Blue
in South Africa. Clause 12.9 contemplates that if assets in
South Africa fell below
the initial ratio then Blue had to top up the
assets or pay the liabilities. It is accordingly correct that
in order to enable
the Appellant to claim in terms of clause 12.9 the
requirement of clause 12.8 should first be exhausted. That
could not happen
because the Respondents have not furnished the ratio
certificate as required by clause 12.6. Accordingly it is only
fair
that the relief sought in prayers 4 and 5 be suspended pending
the furnishing of a ratio certificate by the Respondents. I
say
this because payment of the amount claimed in prayers 4 and 5 depends
on what is in the ratio certificate. The Respondents
must
furnish the ratio certificate. It is nonsensical that same can
only be claimed by the Lender Committee.
[77] The reason why the Applicant
could not comply with the circumstances envisaged in clauses 12.8 and
12.9 is because there was
never a reduction of the debt the country
cover ratio remained same. There was no need to re-measure or to
level ratio as there
was no payment.
[78] The relief in prayers 4 and 5
will largely depend on what is in the ratio certificate.
Therefore an opportunity should
be afforded the Applicant to approach
this Court once it has been determined what the difference is between
the value of the South
African book in terms of the certificates and
the sum of R234 million. That amount once determined will entitle the
Applicant to
payment of a specific amount plus interest.
[79] Prayer 7 of the notice of motion
the Applicant seeks an order that it be granted unimpeded access to
the Second Respondent’s
debtor books so as to enable the
Applicant to call up and collect the debts due from the Second
Respondent’s debtors.
[80] At the conclusion of the loan and
banking facility agreement the Second Respondent signed a cession of
its debtors as security
in favour of the Applicant. It is the
document market Annexure SCB4 and is dated the 26
th
February 2009.
[81] On the 29
th
November
2013 the Applicant addressed a letter to the Second Respondent in
accordance with clause 6.2.5 of the cession of debtors’
agreement and requested the Second Respondent to provide it with a
schedule of debts. Instead of complying with the request
the
Second Respondent clearly avoided this issue and referred to the
provision of clause 7 of the DRA and made no reference at
all to the
cession of debt agreement which was still in force. On the 10
th
December 2013 the Applicant addressed a letter to the Second
Respondent paragraph 4 of that letter reads as follows:
“
Clause 7.2 of the DRA
entitles the lenders to realise security which they enjoy under the
existing security if the borrowers fail
to comply with the obligation
under clause 7 of the DRA … BFS SA has failed to make payment
under the guarantee as required
by a letter of 29 November 2013. SCB
is accordingly now exercising its rights as set out in clause 10 of
the cession in relation
to the Receivables including its rights in
terms of clause 10.2.2 of the cession.
”
[82] In answer to prayer 7 and in
argument the Respondents failed to give any reason why it should not
be compelled to give the
Applicant access to the debtor books.
The Respondents only say that the list of debtors were no longer
necessary as this
related to the cover ratios which are only relevant
up to the end date counsel for the Second Respondent added that the
Second
Respondent’s debtor book is only relevant in the event
that this Court finds in favour or grants relief in respect of prayer
1.
[83] I have already found in favour of
the Applicant in respect of prayer 1 and there being no plausible
reason advanced by the
Second Respondent this prayer is also granted
in favour of the Applicant.
[84] I am of the view and satisfied
that on the papers the Applicant has made out a case in regards
claims 1, 2, 3, 4, 5 and 7.
It is so that prayer 6 was
abandoned so was the alternative claim and in view of the abandonment
of the alternative claim the issue
of the non-joinder raised by the
Respondents falls off and I make no ruling.
[85] There is nowhere in the heads of
argument as well as in the oral submissions before me where the
Respondents advances any argument
why this matter should have been
referred to oral evidence instead of it being decided on motion. I
will likewise not deal with
that and I presume that the Respondents
have abandoned same.
[86] In the result I hereby grant
judgment in favour of the Applicant and I make the following order:
(a)
The First Respondent
alternatively the Second Respondent is ordered to pay to the
Applicant the sum of R9 762 765,47 the
one paying the other
to be absolved.
(b)
Payment of interest on the
said amount in (a) above at the rate of 15,5% per annum from the date
of mora to date of payment.
(c)
The First Respondent is
directed and ordered to produce a ratio certificate as contemplated
in the DRA with reference to the last
meeting date being 31
st
December 2013 showing the value and calculation of the South African
book as contemplated by clause 12.5.2 of the DRA (the South
African
Book).
(d)
To enable the Applicant to
prove its claim as prayed for in prayers 4 and 5 of the notice of
motion the Applicant is hereby granted
a right to approach this Court
on the same papers duly amended once it has been determined what the
difference is between the value
of the South African Bank in terms of
the ratio certificate and the sum of R234 million.
(e)
The Applicant is granted
immediate unimpeded access to the Second Respondent’s debtors
book so as to enable the Applicant
to call up and collect debts due
from the Second Respondent’s debtors and to have the proceeds
realized paid into an account
designated by the Applicant.
(f)
The Respondents are
ordered to pay costs of this application on an attorney and client
scale.
DATED at JOHANNESBURG on this the day
of AUGUST 2018.
________________________________________
M
A MAKUME
JUDGE OF THE
HIGH COURT
GAUTENG LOCAL DIVISION,
JOHANNESBURG
Dates of hearing: 7
th
and
8
th
February 2018
Date of judgment
APPEARANCES
For Applicant: Adv Daniels
Instructed by: Messrs Norton Rose
Fulbright South Africa Inc
Sandton
Tel: (011) 685 8872
For Respondents: Adv Mundell
Instructed by: Meiring and Partners
Bryanston
Tel: (011) 241 8900