Ejalk CC v Mangaung Metropolitan Municipality (5073/2017) [2022] ZAFSHC 189 (3 August 2022)

80 Reportability
Municipal Law

Brief Summary

Municipal Law — Occupancy Certificate — Review of decision to issue occupancy certificate — Applicant sought to set aside occupancy certificate for Mangaung Intermodal Transport Facility, alleging health hazards due to insufficient ventilation and noxious gas emissions — Respondent contended that the application was moot as the facility had not been operational since 2011 and that the attorney lacked authority to settle the dispute — Court found no reasonable interpretation of the correspondence indicated a compromise of the dispute and dismissed the application to set aside the occupancy certificate.

Comprehensive Summary

Summary of Judgment


1. Introduction


The proceedings were an application for judicial review of an administrative act under the Promotion of Administrative Justice Act 3 of 2000 (PAJA), directed at the respondent municipality’s decision to issue an occupancy certificate for a public transport facility in Bloemfontein. In addition, the applicant sought (as main relief) enforcement of an alleged settlement arrangement, alternatively a declarator that the underlying dispute had been compromised.


The parties were Ejalk CC (applicant), a close corporation operating in financial intermediation, insurance, real estate and business services, and Mangaung Metropolitan Municipality (respondent), the local authority responsible for the building and for issuing the occupancy certificate.


The application was originally issued in September 2017. The applicant initially sought an extension of time to bring the review and an order reviewing and setting aside the occupancy certificate issued on 31 October 2011. In August 2021, the applicant amended its notice of motion: the review relief became alternative relief, while the primary relief became an order making an alleged agreement between the parties an order of court under Uniform Rule of Court 41(4), alternatively a declarator that the dispute was compromised on the terms set out in the amended notice of motion.


The dispute concerned the lawfulness and validity of the occupancy certificate issued for the Mangaung Intermodal Transport Facility in the Bloemfontein CBD, with the applicant alleging that inadequate ventilation would allow harmful vehicle emissions (particularly carbon monoxide) to reach unsafe levels, rendering occupation dangerous and the issuing of the certificate unlawful.


2. Material Facts


The facility (also described as the “building” or “intermodal transport facility”) was built as a public transport hub intended for public transport vehicles to park, load and unload passengers, and to replace the existing taxi rank in the Bloemfontein CBD. After completion, the respondent issued an occupancy certificate on 31 October 2011 in respect of the building situated at Erf 26753, Bloemfontein. The certificate was issued under section 14 of the National Building Standards Act 103 of 1977, read with the National Building Regulations and Directives made under the Act.


The applicant alleged it had a direct and substantial interest because it was a tenant of the premises under a lease agreement concluded with the respondent on 28 November 2008, and it sublet portions to entities including a doctor, dentist, pharmacy and optometrist. The applicant’s case, as relied upon by the court for purposes of identifying the dispute, was that the building posed a health threat to the public because of allegedly inadequate ventilation and the potential accumulation of noxious gases from idling vehicles.


A significant factual dispute existed regarding whether the building’s ventilation was adequate and compliant. The applicant relied on expert reports, including a report by Mr BJP Rossouw (a mechanical engineer) concluding the ventilation was inadequate and posed a health threat, and a report by Dr Y Swart (a medical doctor with public health qualifications) addressing health risks associated with exposure to emissions and concluding the occupancy certificate should be withdrawn. The respondent disputed these conclusions and relied on confirmatory affidavits from members of the professional team involved in the building’s design, including evidence that the facility was designed for natural ventilation through openings compliant with SANS 10400-1990, and that mechanical extract fans were intended for smoke removal in a fire situation, not ordinary ventilation.


There was also a dispute relating to the status and effect of correspondence about conducting tests. The applicant relied on a “tender” recorded in the replying affidavit (attested on 19 February 2018) proposing that the applicant would fund tests to determine whether noxious gases exceeded safe limits and whether ventilation was sufficient, with costs consequences depending on the result. The applicant later relied on correspondence: its attorneys wrote on 29 June 2018 proposing testing (identifying Dr DJ van den Heever as an expert), followed by reminders on 27 July and 15 August 2018. The respondent’s then attorneys replied on 27 August 2018, indicating instructions had been received that the tests could proceed and confirming the applicant would be responsible for the costs of the tests and associated costs, and enquiring when the tests could be conducted. The applicant contended this amounted to acceptance of its proposal and a compromise of the dispute; the respondent denied any settlement or compromise and contended, in any event, that the correspondence could not be interpreted as settling the review dispute.


The respondent raised, as part of its opposition relevant to the court’s procedural approach, that the application was brought late under PAJA and that the facility had not been operating for its intended taxi-rank purpose since 2011 (save for a “test run” in 2012), contending the review was moot or academic. The applicant alleged it had not previously known the certificate was unlawful and referred to incidents such as people fainting and unpleasant conditions in the building, stating it only appreciated the unlawfulness after consulting experts.


3. Legal Issues


The court was required to determine, first, whether the applicant had established an enforceable settlement agreement or compromise on the terms set out in the amended notice of motion, such that it could be made an order of court under Uniform Rule 41(4) or declared to have compromised the dispute.


Second, the court had to decide whether the PAJA 180-day time period for launching the review should be extended (condonation), which required an evaluative determination in the interests of justice, including consideration of the explanation for delay and the public interest implications.


Third, the court had to decide how to deal procedurally with the merits of the review—namely the challenge to the lawfulness of issuing the occupancy certificate—given that the relief sought (review and setting aside) was final in nature and the papers disclosed material factual disputes concerning ventilation adequacy and health risks. This raised questions of application of law to contested facts and the appropriate procedural mechanism (final relief on affidavit, dismissal under the motion proceedings approach, or referral to trial), particularly in light of recent Constitutional Court guidance.


4. Court’s Reasoning


On the alleged settlement/compromise, the court examined the correspondence relied on by the applicant and concluded that, on a reasonable interpretation, it did not amount to a compromise of the dispute. The court accepted the respondent’s contention that the correspondence did not reflect an agreement resolving what would happen if the tests supported the applicant’s version. In particular, the court found no basis to infer that the respondent agreed—depending on the outcome of testing—that the occupancy certificate would be withdrawn or set aside. The reply of 27 August 2018 was interpreted as permitting tests to proceed and dealing with responsibility for the costs of testing, rather than as an agreement settling the review dispute. The court therefore dismissed the main relief seeking to enforce the alleged agreement or declare a compromise.


Although the respondent disputed its attorney’s authority to settle, the court stated it was unnecessary to decide that question given the conclusion that no settlement had been established on the content of the correspondence. The court nonetheless indicated that, had it been necessary, it would “in all probability” have found the attorney had authority, referring to Hlobo v Multilateral Motor Vehicles Accident Fund 2001 (2) SA 59 (SCA).


On the PAJA delay, the court approached the question with reference to authority recognising that a litigant cannot necessarily be expected to rush to court without investigating whether there is a case to bring. The court referred to Joubert Galpin Searle v Road Accident Fund 2014 (4) SA 148 (ECP), including the proposition that antecedent investigations may take time and that attempts to settle disputes may delay litigation. The court also referenced South African National Roads Agency Ltd v City of Cape Town 2017 (1) SA 468 (SCA) as an example where a delay was condoned in the interests of justice.


The court then framed the issue in public-law terms by adopting the principle that public bodies may act only when justified by positive law, citing R v Somerset County Council, ex parte Fewings and Others [1995] 1 All ER 513 (QB). The court emphasised the respondent’s role as a public body responsible for public safety. It reasoned that refusing condonation or dismissing the case purely because of the time lapse could fail to address potential prejudice to the public and could create the perception that any building shortcomings were effectively condoned by the court. Because the matter concerned a facility intended for public use, and because the true facts about safety needed adjudication, the court exercised its discretion to extend the time period for bringing the review to the date on which service of the application was effected.


On the merits of the review and the presence of factual disputes, the court recognised that the relief sought (review and setting aside) was final in effect and invoked the well-known motion proceedings approach from Plascon-Evans Paints (Pty) Ltd v Van Riebeeck Paints (Pty) Ltd 1984 (3) SA 623 (A). It noted that final relief may be granted on affidavit only if the admitted facts together with the respondent’s version justify the order, unless the respondent’s denials are so untenable that they can be rejected on the papers.


However, the court considered the Constitutional Court’s recent guidance in Mamadi and Another v Premier of Limpopo Province and Others [2022] ZACC 26 regarding review proceedings, stating that it is inappropriate simply to dismiss a review application on the basis of Plascon-Evans where disputes of fact cannot easily be resolved on the papers. The court connected this to the section 34 constitutional right to have disputes decided in a fair public hearing.


Applying these principles, the court held that the disputes in this matter fell within the category where a final determination could not responsibly be made on the papers, but also should not simply be dismissed. The court regarded a referral to trial as the appropriate procedural outcome on the remaining question, namely the validity of the issuing of the occupancy certificate. The court explained that trial procedures would allow experts to inspect and investigate in a way facilitated by the rules, to reach joint conclusions where possible, narrow the expert disputes, and permit a trial court to resolve the issues after hearing evidence.


On costs, the court treated costs as discretionary and considered it appropriate that costs should stand over for determination at the eventual trial.


5. Outcome and Relief


The court dismissed the applicant’s main relief based on the alleged agreement/compromise and the request to make it an order of court.


The court granted an extension of time for bringing the PAJA review, extending the period for applying to review and set aside the decision to issue the occupancy certificate to the date on which service of the application was effected.


The court referred the decision to issue the occupancy certificate dated 31 October 2011 to trial. It directed that the applicant’s founding affidavit would stand as a combined summons and that the respondent’s answering affidavit would stand as the plea, after which the Uniform Rules relating to further pleadings would apply.


The court ordered that costs stand over for later adjudication at the trial.


Cases Cited


Hlobo v Multilateral Motor Vehicles Accident Fund 2001 (2) SA 59 (SCA)


Joubert Galpin Searle v Road Accident Fund 2014 (4) SA 148 (ECP)


Scott and Others v Hanekom and Others 1980 (3) SA 1182 (C)


South African National Roads Agency Ltd v City of Cape Town 2017 (1) SA 468 (SCA)


R v Somerset County Council, ex parte Fewings and Others [1995] 1 All ER 513 (QB)


Plascon-Evans Paints (Pty) Ltd v Van Riebeeck Paints (Pty) Ltd 1984 (3) SA 623 (A)


Mamadi and Another v Premier of Limpopo Province and Others [2022] ZACC 26


Legislation Cited


National Building Standards Act 103 of 1977, section 14


Promotion of Administrative Justice Act 3 of 2000


Constitution of the Republic of South Africa, 1996, section 34


Rules of Court Cited


Uniform Rules of Court, Rule 41(4)


Uniform Rules of Court, Rule 53


Held


The court held that the correspondence relied upon by the applicant did not constitute a settlement agreement or compromise of the dispute, and therefore the relief seeking to have such an agreement made an order of court (or declared a compromise) was not established and had to be dismissed.


The court held that, notwithstanding the lapse of time since the issuing of the occupancy certificate, it was in the interests of justice—particularly given the public-safety implications and the respondent’s role as a public body—to extend the period for bringing the PAJA review to the date of service of the application.


The court held that the review could not properly be finally determined on the papers due to material disputes of fact, and that it would be inappropriate simply to dismiss the review on motion proceedings principles. The validity of the issuance of the occupancy certificate was therefore referred to trial, with affidavits standing as pleadings and costs reserved.


LEGAL PRINCIPLES


A public body may exercise powers only where justified by positive law, reflecting a foundational distinction between the legal position of public authorities and private persons. This principle informed the court’s approach to a challenge directed at a municipality’s decision concerning public safety and regulatory compliance.


In a PAJA review, the statutory time bar is not applied mechanically; a court may extend the period where the interests of justice require it, particularly where the dispute implicates significant public concerns and where refusal would risk leaving potentially unlawful administrative action effectively unexamined.


Where final relief is sought on affidavit and material disputes of fact exist, the Plascon-Evans approach ordinarily governs whether final relief can be granted on the papers. However, in review proceedings, and especially where disputes of fact cannot fairly or readily be resolved on affidavit, a court is not confined to either granting or dismissing the application; consistent with constitutional fair-hearing requirements (section 34) and recent Constitutional Court guidance, the court may adopt a procedural course such as referral to trial to ensure proper adjudication on evidence.


Costs remain within the court’s discretion, and where a matter is referred to trial because merits cannot be decided on affidavit, it may be appropriate for costs to stand over for determination by the trial court.

About SAFLII
Databases
Search
Terms of Use
RSS Feeds
South Africa: Free State High Court, Bloemfontein
SAFLII
>>
Databases
>>
South Africa: Free State High Court, Bloemfontein
>>
2022
>>
[2022] ZAFSHC 189
|

|

Ejalk CC v Mangaung Metropolitan Municipality (5073/2017) [2022] ZAFSHC 189 (3 August 2022)

IN
THE HIGH COURT OF SOUTH AFRICA,
FREE
STATE DIVISION, BLOEMFONTEIN
Case
No:
5073/2017
Reportable:

YES/NO
Of
Interest to other Judges: YES/NO
Circulate
to Magistrates:      YES/NO
In
the matter between:
EJALK
CC
Applicant
and
MANGAUNG
METROPOLITAN MUNICIPALITY
Respondent
CORAM:
C
REINDERS, ADJP et MATHEBULA, J
JUDGMENT
BY:
C REINDERS, ADJP
HEARD
ON:
14
FEBRUARY 2022
DELIVERED
ON:
3
AUGUST 2022
This
judgment was handed down electronically by circulation to the
parties’ representatives by email, and release to SAFLII.

The date and time for hand-down is deemed to be 15:00 on 3 August
2022.
[1]
The Mangaung Intermodal Transport Facility (hereafter interchangeably
referred to as the “building”
or “facility”)
in the Bloemfontein Central Business District (the “CBD”)
was built to serve as a hub for
public transport vehicles for the
purpose of parking, loading and unloading passengers. It was meant to
replace the old and existing
taxi rank in the CBD. After completion
of the building and on 31 October 2011 the respondent (at the time
known as Mangaung Municipality)
issued an occupancy certificate (the
“certificate”) in respect of the building situated at Erf
26753, Bloemfontein.
The certificate was issued in terms of the
provisions of s14 of the National Building Standards Act 103 of 1977
(the “Act”)
read with the National Building Regulations
and Directives (the “regulations”) made in terms of the
Act.
[2]
The application was originally issued in September 2017 and the
applicant (a close corporation operating
in the industry of financial
intermediation, insurance, real estate and business services) at the
time sought relief to extend
the period for applying to review and
set aside the decision to issue an occupancy certificate for the
facility and that the decision
to issue the certificate, be reviewed
(dated 31 October 2011) and set aside. In August 2021 the applicant
amended its notice of
motion by seeking the aforementioned relief
only in the alternative. As main relief it sought that an agreement
between the parties
(entered into ostensibly afterwards and which I
will deal here within later) be made an order of court in terms of
rule 41(4),
alternatively a declarator that the dispute was
compromised.
[3]
I deem it appropriate to deal at this stage with the relief sought in
respect of the alleged agreement
and/or compromise entered into
between the parties. I at the same time consider it to be appropriate
and for purposes of following
my reasoning to repeat verbatim the
relief in this respect as sought in the amended notice:

the
main relief is sought in the following terms:
A1.1
The applicant funds the costs of tests in the Mangaung Intermodal
Transport Facility to measure
and determine whether the volume of
noxious gases and fumes that build up exceeds a safe limit and
whether the ventilation in the
building is sufficient.
A1.2
If the tests confirm that volume of noxious gases and fumes that
build up exceeds a safe limit
and the ventilation in the building is
insufficient, the costs of the test’s forms part of the costs
of the application.
A1.3
If the applicant is proved wrong, it will withdraw the application
and pay the respondent’s
costs
A1.4
If the tests confirm that the volume of noxious gases and fumes that
build up exceeds a safe
limit and the ventilation in the building is
insufficient the application succeeds, be made an order of Court in
terms of the provisions
of Rule 41(4) and granting an order in terms
of prayer 1 and 3, the costs to include the costs occasioned by the
tests conducted
by Dr. DJ (Dawid) van den Heever and to the extent
necessary the qualifying expenses and preparation fees of the expert
witnesses
Dr. DJ (Dawid) van den Heever;
A2.
In the alternative to prayer A1 that it be declared that the parties
compromised the
dispute in terms set out in paragraph A1 and granting
an order in terms of prayer 1 and 3, the costs to include the costs
occasioned
by the tests conducted by Dr. DJ (Dawid) van den Heever
and to the extent necessary the qualifying expenses and preparation
fees
of the expert witnesses Dr. DJ (Dawid) van den Heever.”
[4]
The core reason for the relief sought is based on a tender that
applicant made and which the applicant
avers the respondent through
its attorney accepted in writing. The tender as contained in the
replying affidavit reads:

TENDER
The applicant is prepared
to fund the costs of a test in the building to measure and determine
whether the volume of noxious gases
and fumes that build up exceeds a
safe limit and naturally whether the ventilation in the building is
sufficient. If the applicant
is correct then the costs of the test
forms part of the costs of the application. If the applicant is
proved wrong it will withdraw
the application and pay the
respondent’s costs.”
The
replying affidavit was attested to on 19 February 2018.
4.1
In applicant’s further affidavit dated 2 October 2020 it is
explained
that on the 29
th
June 2018 a letter was addressed (by applicant’s attorneys) to
the attorneys acting on behalf of respondent at the time.
The letter
reads:

We refer to
previous correspondence regarding the conduct of tests to confirm /
refute the allegations contained in the papers regarding
dangerous
gasses in the building.
As far as we could
ascertain, the only local expert who can conduct the necessary tests
is Dr DJ Van den Heever of VDH Industrial
Hygiene CC.  We
approached him to determine if such tests are possible and if he
would be able to carry out same. Dr Van den
Heever wanted to
inspect
the building first to determine the feasibility
of carrying out the
tests which are usually required when faced with similar problems.
We attach Dr Van den
Heever’s response hereto from which you will note the type of
testing he suggests and the methodology
to carry out these tests.
It would be appreciated to receive your comments regarding the
contents of Dr Van den Heever’s
proposal.
We suggest that to
curtail costs, Dr Van den Heever act as an independent expert and
should you be in agreement in this regards,
you are welcome to
contact him to discuss any concerns or questions you may have
regarding the tests to be carried out.”
4.2
As no response came forth, the attorney of the applicant wrote
follow-up letters
on 27 July and 15 August 2018. This prompted a
reply on 27 August 2018 by respondent’s then attorney:

Ons het
instruksies ontvang dat daar voortgegaan kan word met ‘n toets
soos vervat in u skrywe van 29 Junie 2018. Ons wens
om te bevestig
dat u kliȅnt verantoordelik sal wees vir die kostes van die
toets sowel as enige gepaardgaande kostes.
Ons wens om te bevestig
dat ons kliȅnt van oordeel is dat enige een van die twee toetse
in orde sal wees vir die kostes van
die toets sowel as enige
gepaardgaande kostes.
Ons wens om te bevestig
dat ons kliȅnt van oordeel is dat enige een van die twee toetse
in order sal wees en is hulle van mening
dat die aangeleentheid so
spoedig moontlik afgehandel moet word, derhalwe verneem ons graag op
welke datums die toets kan geskied”
Loosely
translated the letter conveys that the aforementioned attorneys have
received instructions to the effect that the test referred
to in the
letter of 29 June 2018 may be proceeded with. Respondent confirmed
that applicant would be liable for the costs of the
afore mentioned
tests as well as any related costs. At the same time, it was
confirmed that respondent is of the view that any
one of the two
tests would be acceptable and that they were of the view that the
issue should be disposed of as speedily as possible
wherefore they
enquired on which dates the test could be done.
4.3
The applicant contends that the afore mentioned letter dated the 27
th
August 2018
constituted an acceptance of the applicant’s proposals,
compromising
all disputes between the parties and entitling it to the
verbatim relief referred to above.
[5]
In the respondent’s duplication/rejoinder Mr T Maine (at the
time the duly appointed Acting City
Manager of the respondent) stated
that the respondent did not at any stage through any of its officials
nor its legal representatives
enter into any settlement agreement or
compromise with the applicant. According to him the letter cannot be
interpreted as constituting
a settlement of the dispute. It was at
the same time averred that the attorney had no authority to bind the
municipality to settle
the dispute in the aforementioned manner.
[6]
It is not necessary to adjudicate the question whether respondent’s
attorney had the authority
to settle the matter – had it been
necessary I would have in all probability have concluded that he had
the necessary authority.
See:
Hlobo
v Multilateral Motor Vehicles Accident Fund
2001
(2) SA 59
(SCA) at para [11]
[7]
I have to agree with the respondent that on no interpretation of the
correspondence I can find that
the respondent compromised the dispute
which at the time (and still) exists between the parties. On no
reasonable interpretation
can I find how the matter was settled in
the event that the tests supported the applicant’s version –
in other words
I do not find that in such circumstances the
respondent agreed that its occupancy certificate by agreement was to
be set aside.
The letter dated 27 August 2018 refers in particular to
the attorney’s letter dated the 29
th
of June 2018 and the aforementioned letter did not suggest the
cancellation or withdrawal of the occupancy certificate in the event

of any findings made by an expert. I therefore have to conclude that
the main relief is to be dismissed.
[8]
The nub of the basis to set aside the certificate as contended by the
applicant is that the Act read
with the regulations do not authorise
the issuing of an occupancy certificate by the local authority where
the general safety,
health and convenience of the general public are
put in jeopardy and occupancy will probably or in fact be dangerous.
According
to the applicant, based on the evidence of its experts’
reports (hereafter the reports), such health hazard lies therein that

due to a lack of proper ventilation in the building, the volume of
noxious gases and fumes (more specifically carbon monoxide)
emitted
by vehicles in the building will exceed the prescribed safety limits
set by the applicable legislation. The certificate
could thus never
have been issued.
[9]
The deponent to the founding affidavit, the managing member of the
applicant, states that it has a direct
and substantial interest in
the issuing of the certificate as it is a tenant (subleasing portions
of the premises to a doctor,
dentist, pharmacy and optometrist) in
terms of a lease agreement it concluded with the respondent on 28
November 2008 (the lease
agreement). The building poses a health
threat to the public and should not be operated or occupied.
[10]
The respondent opposes the application. It is the respondent’s
case that the application constitutes an abuse
of the court’s
process. It avers that the true motive for the application is to
attack the issuing of the certificate as
it plays a vital role in the
determination of a pending dispute between the parties relating to
the termination/cancellation of
the lease agreement. Furthermore, the
relief in as far as it relates to a health hazard is moot, or at best
an academic exercise,
as the facility had not been operating for the
purpose it was intended for since 2011 (bar a “test run”
in 2012) and
the setting aside of the certificate would have no
practical effect. Respondent submits that there exist substantial
factual disputes
in the matter which should have been foreseeable and
anticipated by applicant. It complains that it is severely prejudiced
by the
proceedings on application.
[11]
According to the respondent there was indeed compliance with the
relevant statutory provisions and the certificate
was properly
issued. The building does not pose any health risk or hazard to the
public. Relying on confirmatory affidavits of
the professional team
and technicians who were involved in the design, development and
structure of the facility, respondent avers
that applicant’s
issue with these aspects is misplaced. Amongst others the designer of
the building and ventilation systems,
Mr MC Heunis (a senior
mechanical engineer employed at the time by IX Engineers) and Mr L
Delport, the director of Incline Architects
who was responsible for
the preparation of the architectural drawings for the development of
the facility, confirmed that the parking
and transportation areas
were specifically designed for natural ventilation by incorporating
openings in the building for this
purpose. The said openings complied
with the South African National Standard (SANS)’s prescripts
for proper ventilation at
the time (SANS 10400-1990). The respondent
accordingly avers that the openings not only comply with the said
requirements but there
was no necessity for the provision of
mechanical ventilation as the extract fans in the building were
installed for purposes of
removing smoke from areas during a fire
situation at the instance of the Mangaung Fire Department.
[12]
The respondent in its opposing affidavit disputes the findings and
conclusions in the reports of applicant’s
expert witnesses Mr
BJP Rossouw (a registered mechanical engineer practising as a
consulting engineer) and Dr Y Swart (a medical
doctor with
qualifications in Community and Public Health). The nub of the
conclusion by Mr Rossouw, after having studied the existing
building
plans, engineering drawings as well as a physical investigation on
site, is that the ventilation of the facility is not
adequate as
prescribed by SANS and poses a health threat to the public.
Respondent attacks the conclusions of Mr Rossouw on the
basis that it
was done on the wrong principles and requirements as there is no need
for mechanical ventilation in the building
due to natural
ventilation. More important, the respondent complains that it is
deprived of the opportunity to cross-examine Mr
Rossouw to test the
veracity of his report and opinion. The report of Dr Swart is
criticized on the basis that she did not physically
visit the
facility nor conducted any tests regarding the noxious omission of
gases. Dr Swartz relied on the report of Mr Rossouw
in dealing with
the severe health risks of exposure to carbon dioxide (including
danger to the unborn babies of pregnant women)
and concluded that the
certificate should be withdrawn. In respect of the report and
conclusions of the independent expert Dr van
den Heever (supporting
the conclusions reached by the applicant’s experts) the
respondent complains that the tests performed
by Dr van Den Heever (a
registered practising Occupational Hygienist) were not in accordance
with the agreed upon methods.
[13]
In reply the applicant contends that it is patently clear that the
facility is not merely a parking garage and
respondent’s
comparison with the closed parking garage at the Loch Logan
Waterfront basement parking (nor for that matter
the Mimosa Mall
complex) does not find application. The respondent’s admission
of the purpose for building the facility,
namely to serve as a hub
for public transport vehicles for parking, loading and unloading
passengers includes applicant’s
averment that the facility is
an enclosed area where vehicles are switched on and off and idle
whilst dropping and loading passengers.
Accordingly, the vehicles
using the facility will emit gases, amongst others carbon monoxide.
Respondent however persists that
the aforementioned is of no
relevance as the facility is not being used for the purpose as
intended due to a deadlock in negotiations
between several role
players. Bar a few tenants in the building, no taxis are operating at
the facilities and there are no commuters.
[14]
It is not contested by respondent that the relief sought constitutes
the review of an administrative action
and the Promotion of
Administrative Justice Act 3 of 2000 (“PAJA”) is
applicable. It rather avers that the application
for a review is
brought outside the prescribed time limits set by PAJA and applicant
tendered no convincing explanation for the
delay, taking into account
that it had occupation of the premises since 2011 when the
certificate was issued. Respondent states
that the applicant is vague
as to when he would have become aware of the fact that the
certificate was allegedly unlawful.
[15]
The applicant avers that it could not bring the review within 180
days from the date of issuing of the certificate
as prescribed by the
Act. It is stated that the applicant originally had no knowledge of
the facts and the respondent did not take
tenants into its confidence
and breached its duty towards the general public. Applicant avers
that numerous incidents occurred
where people fainted in the building
and more in particular the area where passengers are to be on and off
loaded. The garage area
is alleged to be uncomfortably warm and
smelling of exhaust fumes whilst the air is thick. In general it is
simply an uncomfortable
experience to be in the garage area.
Affidavits of four members of public confirming the aforementioned is
annexed to the papers.
Applicant describe itself as very vocal
regarding the conditions to such an extent that the applicant was
victimised and even spoliated.
Applicant identified qualified persons
and eventually consulted with Dr Swart who is properly qualified and
who expressed an opinion
on the matter. The applicant at no stage
before having been advised by the experts were aware that the
occupancy certificate was
issued contrary to the provisions of the
enabling act.
[16]
In this respect the conduct (and delay) of applicant is to be
adjudicated along the lines stated in
Joubert
Galpin Searle v Road Accident Fund
2014 (40 SA 148
(ECP)
where Plasket J stated:

[52]
It cannot be expected of an applicant that he or she rush to court to
review and set aside
administrative action without investigating and
attempting to determine whether he or she has a case. It is no answer
to say that
rule 53 enables an applicant to launch a review on the
thinnest of bases and then supplement his or her case when reasons
are provided,
if they are, and the record is furnished in due course.
[53]
In
Scott and Others v Hanekom and Others
1980 (3) SA 1182
(C)
at 192H
Marais AJ, although dealing with a different context,
stated:

The scope of
review proceedings is limitless. The antecedent investigations and
preparation of process may be simple or complex.
The time required
for this purpose may be short or it may be long. The parties may have
spent many fruitless months in attempting
to negotiate an acceptable
compromise or settlement before resorting to litigation’”
[17]
In
South African National Roads Agency Ltd
v Cape Town City
2017 (1) SA 468
(SCA) at
para [108] the Supreme Court condoned a delay, based on the interest
of justice.
[18]
I align myself with what was stated by Laws J in
R
v Somerset Country Council, ex parte Fewings and Others
[1995]
1 All ER 513
(QB) at 524 e-g:

Public bodies and
private persons are both subject to the rule of law; nothing could be
more elementary. But the principles which
govern their relationships
with the law are wholly different. For private persons, the rule is
that you may do anything you choose
which the law does not prohibit.
It means that the freedoms of the private citizen are not conditional
upon some distinct
and affirmative justification for which he must
burrow in the law book.  But for public bodies the rule is
opposite, and so
of another character altogether. It is that any
action to be taken must be justified by positive law. A public body
has no heritage
of legal rights which it enjoys for its own sake; at
every turn, all of its dealings constitute the fulfilment of duties
which
it owes to others; indeed, it exists for no other purpose.”
[19]
In
casu
the respondent
is a public body very much responsible for the safety of the public
making use of the amenities which the respondent
avers is safe and
complies with the necessary legislation and by laws. There is a real
concern in my mind in this respect and declining
to extend the time
limit or simply dismissing the application due to the time lapse in
my view could not be solving the real and
potential prejudice to the
public at large. It will create the impression that whatever the
shortcomings in the building, same
is water underneath the bridge and
condoned by court. This perception would be wrong as the true facts
need to be adjudicated in
the interest of the public making use (or
who will be making use) of the facilities and who are in fact are
invited by the respondent
to make use of the amenities on the
premises. In the circumstances I am prepared to grant the relief in
respect of the requested
extension of time sought in paragraph 2.1 of
the Amended Notice of Motion.
[20]
This leaves me with the final dispute, to wit the review and setting
aside of the occupancy certificate. The relief
sought is final in
nature. It is well established that such relief may be granted if the
facts averred by the applicant which had
been admitted by the
respondent together with the facts alleged by the respondent justify
such an order, unless the allegations
and denials by the respondents
are so far-fetched or untenable that he court is entitled to reject
the respondent’s version
merely on the papers.
See:
Plascon-Evans Paints (Pty) Ltd v Van
Riebeeck Paints (Pty) Ltd
1984 (3) at 634
H-I
[21]
Recently in
Mamadi and Another v Premier of
Limpopo Province and Others
[2022] ZACC
26
(delivered on 6 July 2022) the Constitutional Court in dealing
with Rule 53 proceedings directed it to be inappropriate to dismiss
a
review application simply on the basis of
Plascon-Evans
where a court finds it difficult to resolve the matter simply on the
basis of a dispute of facts which cannot easily be resolved
on the
papers.
It was held that a
court can refuse to render a final decision in a matter and thus on
the right in terms of section 34 of the Constitution
to have

any
dispute that can be resolved by the application of law decided in a
fair public hearing before a court”.
[22]
In my view this case and the disputes fall squarely within the ambit
of the directions issued by the Constitutional
Court. Whilst I find
myself unable on the papers to resolve the disputes and find in
favour of the applicant, I most definitely
cannot simply, based on
the Plascon-Evans Rule, dismiss the application. On the contrary, I
am of the view that a referral to trial
in respect of the only
question remaining, namely the validity of the issuing of the
occupancy certificate, is very much what is
called for. This will
and/or might hopefully lead thereto that the experts, through the
working of the court rules, can inspect
and investigate what they
deem appropriate for the final adjudication of this matter, come to
joint conclusions and narrow down
the real expert disputes which a
trial court on hearing evidence can finally adjudicate.
[23]
Costs are always in the discretion of the court. In my view it is
appropriate for costs to stand over for later
adjudication at the
main trial.
[24]
Consequently I make the following orders:
24.1
Prayers A1 and A2 of the notice of motion is
dismissed.
24.2
The period for applying to review and set aside
the decision to issue an occupancy certificate for the Mangaung
Intermodal Transport
Facility is extended to the date on which
service of the application was effected.
24.3
The decision to issue the occupancy certificate
for the Mangaung Intermodal Transport Facility, which certificate is
dated the 31
st
of
October 2011, is referred for trial.
24.4
The applicant’s founding affidavit shall
stand as combined summons.
24.5
The respondent’s answering affidavit shall
stand as the plea.
24.6
The rules as set out in the Uniform Rules of
Court for the filing of further pleadings will thereafter apply.
24.7
Costs to stand over for later adjudication.
C.
REINDERS, ADJP
I
agree
M.A.
MATHEBULA, J
On
behalf of the applicant:
Adv N Snellenburg SC
Instructed
by:                             Hendre

Conradie Inc
(Rossouws
Attorneys)
BLOEMFONTEIN
On
behalf of the respondent:     Adv LA Roux
Instructed
by:                             EG

Cooper Majiedt Inc
BLOEMFONTEIN