Dexalinx (Pty) Ltd v Municipal Manager c/o City of Tshwane Metropolitan Municipality (23/075060) [2023] ZAGPPHC 711 (21 August 2023)

80 Reportability
Municipal Law

Brief Summary

Municipal Law — Township Development — Certificates — Municipality unilaterally declaring previously issued certificates invalid without self-review — Developer sought approvals for township planning, with certificates issued confirming development approval — Municipality's action amounted to self-help and disregarded due process — Court declared certificates valid and binding, ordering municipality to process applications and take necessary administrative steps.

Comprehensive Summary

Summary of Judgment


Introduction


The matter concerned an urgent application in the Gauteng Division, Pretoria, in which a private developer sought relief against a municipality arising from the municipality’s attempt to treat its own prior administrative approvals as invalid without approaching a court. The proceedings were framed around the validity and continued operative effect of municipal decisions taken in the course of a township development process, and the consequences flowing from the municipality’s subsequent refusal to process further steps premised on those decisions.


The applicant was Dexalinx (Pty) Ltd, a developer engaged in the township planning process for the proposed townships Peach Tree Extensions 21–25. The respondent was the Municipal Manager, City of Tshwane Metropolitan Municipality, cited in that capacity.


Procedurally, the application was brought on an urgent basis under Uniform Rule 6(12). The court was asked, first, to grant declaratory relief confirming the validity and binding effect of the municipality’s prior decision to issue certificates in terms of the applicable municipal by-law, and secondly to grant consequential mandatory relief compelling the municipality to process later-stage applications and take administrative steps necessary to advance the town planning process and enable building plan approvals.


The general subject-matter of the dispute was the rule-of-law requirement that an organ of state may not unilaterally disregard or “reverse” its own administrative decisions (even if allegedly defective), but must instead follow proper process—typically by instituting self-review proceedings—to have them set aside by a court.


Material Facts


Dexalinx (Pty) Ltd was involved in a lengthy township planning process in which it sought and obtained a series of municipal approvals from the City of Tshwane. As part of this process, the City issued four certificates in terms of section 16(10) of the Tshwane Land Use Management By-law, 2016. The certificates recorded that, from the City’s side, the development had been approved to the point where the applicant could proceed to submit final building plans. The certificates were conveyed to the applicant in December 2022, after the required gazetting approving the townships.


After the certificates were issued and conveyed, the applicant took subsequent steps premised on their validity. In particular, it registered title deeds and notarial ties and submitted final building plans. The judgment treated these steps as having been taken on the footing that the section 16(10) certificates were valid and operative, and as having been “perfected” in reliance on them.


The City itself also acted on the premise that the certificates were valid. It required the applicant to apply for a correction and an exemption under sections 13, 24 and 28 of the By-law, which were described as steps that arise subsequent to the granting of the section 16(10) certificates. Both sides therefore proceeded, for a period, on the basis that the certificates lawfully formed part of the continuing town planning process.


In mid-July 2023 the City changed course. On 17 July 2023 it informed the applicant that it would disregard the certificates, and on 18 July 2023 it maintained an intractable stance that it regarded them as invalid. The City’s stated explanation was that the wrong municipal department had issued the certificates: the City contended that the Legal Department issued them, but that the function properly resided in the Land Planning/City Planning Department.


The court distinguished the City’s asserted justification from a properly established factual foundation. It recorded that the answering affidavit contained a conclusory assertion that the wrong department issued the certificates, without adequate supporting facts. The certificates themselves reflected that they were signed by an official in the Legal Department and recorded that the issuance was “duly authorised” in terms of a Council Delegation dated 11 September 2020. The court stated that it was not provided with evidence sufficient to make a factual finding that the wrong department had issued the certificates.


Following the City’s refusal to recognise the certificates, it halted the consideration and processing of later-stage applications. The applicant delivered applications in terms of sections 13 and 23 of the By-law relating to certain buildings alleged to have been built across boundary lines. The judgment recorded that, on 26 May 2023, the City’s Planning Department confirmed that the City had approved the applications, yet the City was refusing to process them. The applicant also sought that the City process a section 28(9) application linked to the registration of a new sectional title scheme, and sought an order compelling the updating of the City’s computer system and initiation of a linking process between internal departments to enable building plan approvals contemplated in section 28(11).


On urgency, the court relied on the timing of the City’s “about-turn” in mid-July 2023 and the speed with which the applicant acted thereafter. It also relied on the applicant’s allegations of significant and compounding financial harm (including price reductions claimed by tenants due to delays, quantified to date at about R7 million), the alleged risk of the entire development collapsing, and evidence of concern from the Gauteng Growth and Development Agency that the investor might withdraw and pursue an alternative site outside the province due to delays.


Legal Issues


The central legal question was whether the City could lawfully treat its own prior administrative decision as invalid and ignore it in practice, thereby halting further processing, without first having that decision reviewed and set aside by a court. This was principally a dispute about law, rooted in the rule-of-law constraints on public power, and specifically the doctrine that administrative acts continue to have effect until properly set aside.


A subsidiary issue concerned whether it mattered, for purposes of the relief, that the City alleged the certificates were issued by the “wrong department”. This raised a question of application of law to fact: even accepting alleged defectiveness, the court had to determine what legal consequences followed from the City’s failure to institute a self-review.


Further issues concerned whether the applicant had made out a case for urgency under the Uniform Rules, and whether the applicant was entitled to mandatory relief compelling the City to process later-stage applications and take administrative steps, in circumstances where the City’s refusal was based on its stance that the certificates could be disregarded.


Court’s Reasoning


The court approached the matter from the premise that administrative decisions may not simply be ignored without recourse to a court of law, and that even when the state seeks to correct its own error, it generally may not take a shortcut by unilaterally treating its decision as void. Drawing on Constitutional Court authority, the judgment emphasised that the requirement that government must apply to court to set aside its own decisions “springs from deep within the Constitution’s scrutiny of power”, and is rooted in legality and the rule of law.


The reasoning proceeded on the basis that, absent a statutory power authorising unilateral reversal, an organ of state that wishes to undo its own administrative act must do so by self-review, following a fair process, and obtaining an order setting the decision aside. Until then, the decision remains extant “in fact” and cannot be overlooked. The court treated the City’s conduct—purporting to disregard the certificates without court process—as impermissible self-help.


On the City’s explanation that the wrong department issued the certificates, the court reasoned in two steps. First, it found that the City had not laid a sufficient factual basis in its answering papers for the asserted lack of authority, while the certificates themselves recorded a council delegation authorising issuance by the Legal Department. Secondly—and decisively—the court held that even if the certificates were defective, that would not change the legal requirement that the City could not simply disregard them: it still had to approach a court to have them set aside. In this respect, the judgment applied the principle articulated in Kirland, namely that government should generally be held to the “pain and duty of proper process”, because a defective decision may have consequences that make it undesirable or even impossible to set aside, and those consequences must be weighed through proper judicial process.


Having concluded that the City improperly disregarded its own decision, the court found that the applicant was entitled to a declaration that the decision to grant the certificates was valid and binding until reviewed and set aside. The court then addressed the consequential relief. It reasoned that the City’s refusal to process subsequent applications was founded on an unlawful premise (that the certificates could be ignored). The City offered no sustainable basis to oppose the mandamus relief beyond that premise. The court therefore held that the applicant was entitled to an order compelling the City to process the relevant applications and to take administrative steps to move the remaining town planning process forward within the timeframes sought, noting that no argument had been advanced that the proposed time periods were unreasonable.


On urgency, the court rejected the contention that it was self-created. It reasoned that the applicant and City acted consistently with the validity of the certificates until 17 July 2023, and that the applicant moved quickly once the City’s stance crystallised on 18 July 2023. The court considered the asserted financial harm, the risk of investor withdrawal and project collapse, and the stagnation of the development. It also weighed the constitutional significance of the dispute as one involving the vindication of the rule of law and resistance to self-help. While the court stated that none of the urgency considerations, viewed individually, was decisive, it held that they cumulatively justified urgent enrolment.


On costs, the court reasoned that the applicant had been substantially successful and had been compelled to litigate to vindicate fundamental rights, including fair administrative action. It accepted that the matter justified the employment of two counsel, but declined to award costs on a punitive scale because it found no adequate basis for such an order in the manner the matter was prosecuted.


Outcome and Relief


The court enrolled and heard the matter as one of urgency, dispensing with the ordinary forms and service under Uniform Rule 6(12).


It granted declaratory relief that the respondent’s decision dated 7 December 2022, contemplated in section 16(12)(i) read with section 16(10)(b) of the Tshwane Land Use Management By-law, 2016, pertaining to the proposed townships Peach Tree Extensions 21–25, was valid and binding.


The court ordered the respondent to process the applicant’s approved/issued applications in terms of sections 13 and 23 of the By-law within two weeks, to update its computer system and initiate a linking process between relevant municipal departments to enable the building plan process contemplated in section 28(11) within one month, and to take all administrative steps necessary to process the remaining town planning process.


The respondent was ordered to pay the costs of the application, including the costs of two counsel, but punitive costs were not awarded.


Cases Cited


MEC for Health, Eastern Cape and Another v Kirland Investments (Pty) Ltd (CCT 77/13) [2014] ZACC 6; 2014 (5) BCLR 547 (CC); 2014 (3) SA 481 (CC) (25 March 2014).


Oudekraal Estates (Pty) Ltd v The City of Cape Town and others (25/08) [2009] ZASCA 85.


Department of Transport v Tasima I(Pty) Limited [2016] ZACC 39; 2017 (2) SA 622 (CC); 2017 (1) BCLR 1 (CC).


Khumalo v Member of the Executive Council for Education, KwaZulu Natal [2013] ZACC 49; 2014 (5) SA 579 (CC); 2014 (3) BCLR 333 (CC).


City of Cape Town v Aurecon South Africa (Pty) Limited [2017] ZACC 5; 2017 (4) SA 223 (CC); 2017 (6) BCLR 730 (CC).


State Information Technology Agency SOC Limited v Gijima Holdings (Pty) Limited [2017] ZACC 40; 2018 (2) SA 23 (CC); 2018 (2) BCLR 240 (CC).


Legislation Cited


Constitution of the Republic of South Africa, 1996.


Promotion of Administrative Justice Act 3 of 2000.


Tshwane Land Use Management By-law, 2016.


Rules of Court Cited


Uniform Rules of Court, Rule 6(12).


Held


The court held that the City of Tshwane could not lawfully disregard or treat as invalid its own previously issued section 16(10) certificates without first instituting proper proceedings to have the underlying administrative decision reviewed and set aside. In the absence of such a self-review, the decision to issue the certificates remained extant and operative, and the municipality’s unilateral “about-turn” amounted to impermissible self-help.


The court further held that, because the City’s refusal to process subsequent town planning applications was based on this unlawful stance, the applicant was entitled to consequential mandatory relief compelling the City to process the later-stage applications and to take administrative steps to move the town planning process forward. Urgency was held to be established on a cumulative assessment of the timing of events, the ongoing harm alleged, and the constitutional significance of vindicating the rule of law.


LEGAL PRINCIPLES


An administrative act by an organ of state may not be ignored or treated as non-existent merely because the state regards it as defective; it continues to have effect in fact until it is set aside through proper legal process.


Where an organ of state seeks to undo or withdraw its own administrative decision, it is generally required to do so through a self-review in a court of law, following fair procedure, rather than through unilateral reversal. Absent empowering statutory authority, unilateral disregard of prior decisions constitutes impermissible self-help.


The requirement that government follow proper process when correcting its own decisions is grounded in the principle of legality and the Constitution’s scrutiny of public power, and it applies even where the Promotion of Administrative Justice Act 3 of 2000 may not apply.


Where a public authority’s refusal to act is founded on an unlawful premise (such as unlawfully disregarding an extant administrative decision), a court may grant mandatory relief compelling the authority to process applications and take administrative steps within reasonable time periods, particularly where no basis is advanced that the time periods are unreasonable.


In determining urgency, the court may consider the timing of the impugned conduct, the practical consequences of delay, the risk of irreparable or unquantifiable harm, and the constitutional importance of preventing self-help; these factors may cumulatively justify urgent enrolment even if none is individually decisive.

About SAFLII
Databases
Search
Terms of Use
RSS Feeds
South Africa: North Gauteng High Court, Pretoria
SAFLII
>>
Databases
>>
South Africa: North Gauteng High Court, Pretoria
>>
2023
>>
[2023] ZAGPPHC 711
|

|

Dexalinx (Pty) Ltd v Municipal Manager c/o City of Tshwane Metropolitan Municipality (23/075060) [2023] ZAGPPHC 711 (21 August 2023)

FLYNOTES:
MUNICIPALITY – Township development –
Certificates

I
ssuing
certificates and developer proceeding – Municipality later
unilaterally deciding the certificates were no longer
valid –
No self-review and amounting to self-help – Financial harm
from delays and danger of development collapsing

Requirement of urgency satisfied – Declared that the
municipality’s decisions pertaining to the proposed

townships are valid and binding – Municipality ordered to
process the issued applications and is to take all administrative

steps necessary to process the remaining town planning process.
IN
THE HIGH COURT OF SOUTH AFRICA
(GAUTENG
DIVISION, PRETORIA)
Case No. 23/075060
(1)
REPORTABLE:  NO
(2)
OF INTEREST TO OTHER JUDGES: NO
(3)
REVISED: NO
DATE: 21 August 2023
SIGNATURE
In the matter between:
DEXALINX
(PTY)
LTD
Applicant
and
THE MUNICIPAL MANAGER
C/O CITY OF
TSHWANE
METROPOLITAN MUNICIPALITY
Respondent
JUDGMENT
DE
VOS AJ:
1
Administrative
decisions may not simply be ignored without recourse to a court of
law.
[1]
Even when the
state is acting on the side of angels and wishes to correct its own
error, it cannot take a short-cut. It must
apply to Court to review
the decision – after having followed a fair procedure. This
principle is clear and longstanding.
[2]
2
The
reasons for this, as identified by the Constitutional Court in
Kirland
,
“spring from deep within the Constitution’s scrutiny of
power”.
[3]
The
Constitution regulates all public power. Perhaps the most important
power it controls is the power the state exercises over
its subjects.
If the government wishes to undo a decision, the affected subject is
entitled to proper notice and to be afforded
a proper hearing on
whether the decision should be set aside:

Government
should not be allowed to take short-cuts. Generally, this means that
government must apply formally to set aside the
decision. Once the
subject has relied on a decision, government cannot, barring specific
statutory authority, simply ignore what
it has done.”
[4]
3
If an organ of state wishes to undo its own administrative
actions, it must self-review its decision in a court of law. It
cannot
unilaterally backtrack. If it does so, absent an empowering
statutory provision, its conduct amounts to self-help.
4
In this case, that is exactly what happened. The applicant is
a developer. It sought several approvals in the lengthy township
planning
process. The City, all along, approved the various
applications. As part of this process, the City issued four
certificates. The
certificates were issued in terms of section 16(10)
of the
Tshwane Land Use Management By-law, 2016
(“the certificates”).
The certificates confirm
that, from the City’s side, the development is approved for the
stage of submitting the final building
plans. Section 16(10) requires
the City must be satisfied of a host of technical and engineering
aspects of the development. The
City’s decision in terms of
section 16(10), with the certificates, was conveyed to the applicant
in December 2022, subsequent
to the required promulgation in the
government gazette approving the townships.
5
The City then unilaterally decided the certificates were no
longer valid. It did so without an application for self-review of its

original decision to issue the certificates. It did so eight months
after it had conveyed the decision to the applicant. By which
stage,
subsequent steps had been taken. In particular, the applicant
registered the titles of deeds, notarial ties and submitted
the final
building plans. All these steps, founded on these certificates, were
perfected.
6
The City took further steps based on the validity of these
certificates. The City required the application to apply for a
correction
and an exemption based on sections 13, 24 and 28 of the
By-law. These steps come into play subsequent to the granting of the
certificates.
Both the applicant and the City had relied on these
certificates, and both had taken subsequent steps premised on their
lawfulness.
7
The City's position is legally impermissible. Its decision to
issue the certificates stands until reviewed and set aside by a court

of law. Unless then, they exist, in fact, and cannot simply be
overlooked.
8
The City contends that the wrong Department issued the
certificates. The Legal Department issued the certificates. The City
submits
the Land Planning Department ought to have issued the
certificates.
9
The City’s answering affidavit contains only the
conclusion that the wrong Department issued the certificate and
failed to
lay a factual foundation for this point. The highest the
City places the debate is a one-liner where it states –
"that
function resides with City Planning Department, and it had not
issued” the certificates.
The Court is provided with
nothing on which it can make this factual finding other than the
City's say-so. On the contrary, the
certificates issued themselves
contain more of a factual foundation that it is the Legal Department
that has the requisite authority
to issue the certificates. The
certificates are signed by Advocate DM Motseo on behalf of the
Council of the City in her capacity
as the Acting Group Head: Group
Legal and Secretarial Service. The authorisation of the Legal
Department to issue the certificate
appears from the certificate,
which states that the issuance is “duly authorised in terms of
a Council Delegation dated 11
September 2020”.
10
But
in this case, it does not truly matter if the City can prove the
wrong Department issued the certificates. I have not been provided

with the evidence to sustain such a finding. But even if I had such
facts, the outcome would not alter. In principle, in
Kirland
is clear:  even where the decision is defective – as the
evidence suggested in
Kirland
– government should generally not be exempt from the forms and
processes of review. It should “be held to the pain
and duty of
proper process”.
[5]
It
must apply formally for a court to set aside the defective decision
so that the Court can properly consider its effects on those
subject
to it. The Court in
Kirland
held that the decision, despite being defective, may have
consequences that make it undesirable or even impossible to set it
aside.
That demands a proper process in which all factors for and
against are properly weighed. This did not happen in this case.
11
In
Kirland
,
the Court held that this requirement originates in the principle of
legality and applies even if PAJA does not. The purpose is
not to
stymie government in "senseless formality". Rather, the
requirement that the state must generally self-review
is an
insistence on due process, from which there is “no reason to
exempt government”. As the state is the “Constitution’s

primary agent. It must do right, and it must do it properly”.
[6]
12
The Court, therefore, concludes that the City improperly
disregarded its own decision, and the decision stands until reviewed
and
set aside. On this basis, the applicant is entitled to a
declarator that the decision to grant the certificates is valid and
stands
until reviewed and set aside.
13
The applicant asks for relief consequential on a finding that
the certificates are valid. If the decision to grant the certificates

stand, then the applicant contends it is entitled to demand the City
consider its subsequent applications. The City halted the

consideration of all subsequent decisions on the premise that the
certificates could be ignored. As this is legally impermissible,
the
applicant asks the Court to compel the City to consider the
subsequent applications.
14
From this relief, the applicant seeks the processing of the
subsequent approvals. The subsequent applications relate to sections

13, 24 and 28 of the By-laws. They follow a section 16(10)
certificate. In particular, the applicant seeks to review and set
aside
the City’s failure to make a decision on the applications
in terms of sections 13 and 23 pertaining to the proposed Township
of
Peach Tree Extensions 21- 24 and to consider the applicant’s
section 28(9) application for the registration of a new Sectional

Title Scheme.
15
Prior to its reversal on the certificates, the City informed
the applicant that certain of its buildings were built across
boundary
lines. This required an application to be considered by the
City in terms of sections 13 and 23 of the By-laws. The applicant
delivered
these applications. On 26 May 2023, the City's Planning
Department confirmed that the City had approved the applications. It
appears
that the City has already approved the applications in terms
of sections 13 and 23 but is refusing to process these
applications.
16
Lastly, the applicant requests that the Land Use Department of
the respondent be compelled to update the respondent's computerised

system by virtue of initiating the linking process between them and
the Building Plans Department to enable the ensuing process
of
obtaining approved Building Plans by the applicant.
17
The City has provided no basis to oppose this relief other
than seeking impermissibly to reverse the section 16(10)
certificates.
This is, for reasons set out above, unlawful. The basis
on which the City has refused to process these applications is
unlawful.
The applicant is entitled to mandamus in this regard. The
City must process these applications within a reasonable time. No
argument
has been presented to the Court that the time periods
presented by the applicant are unreasonable.
18
The applicant has approached this Court on an urgent basis.
The City contends that the urgency was self-created. The facts
indicate
differently. The City's about-turn came about in mid-July
2023. Until 17 July 2023, the applicant and the City both acted in
accordance
with an understanding that the certificates were valid and
even took subsequent steps based on this understanding. Until 17 July

2023, things were going swimmingly. It was in an email of 17 July
2023 the City informed the applicant it would disregard the
certificates. The applicant wrote back on the same day, explaining
the situation. The City’s response the following day, 18
July
2023, was intractable: it viewed the certificates as invalid. This
was the moment the applicant knew it would have to approach
the
courts for assistance. The following day the applicant approached its
lawyer, and the application was launched within a week
and set down
within two – permitting the City time to respond. The urgency
was not self-created.
19
The applicant presents three factual foundations for its claim
for urgency. First, it is suffering significant financial harm. Four

tenants have exercised options for the properties to be built. They
are entitled to a reduction in the purchase price for delays
suffered
in the finalisation of the development. The current damages the
applicant has suffered, to date, in this regard, is an
amount of
about R 7 million. These damages, of course, compound daily. There is
also no end in sight to these damages as the City's
intractable
position means that the process must start afresh, and the applicant
must re-apply for its certificates. There is no
clear basis on which
it will be able to claim this damage from a court of law at a
subsequent date, particularly in light of the
limited scope of
damages based on the inappropriate exercise of administrative power.
20
Second, there is the danger of the development in its entirety
collapsing. The City contends that this danger is not real. However,

the Court has an email from the Gauteng Growth and Development Agency
expressing alarm that the investor for this development has
not only
expressed its intention to withdraw but has also indicated it is
looking for an alternative site for this development
outside the
province. The Gauteng Growth and Development Agency is concerned with
the loss of development that might result from
the withdrawal from
the investor. The Agency says three important things. First, the
"project is KEY in unlocking investments
in the northern
corridor". Second, the investor is seeking to take its money
outside the province. Three, the Agency views
the issue as serious
enough to escalate it to the National Agency. The Agency states that
the withdrawal is caused by the delay
and the failure to resolve the
matter speedily. The timing of this letter fits with the applicant's
chronology, and it would appear
it was sent the same day the City
took its position that it would not move the application along and
require the reconsideration
of the entire application in relation to
the section 16(10) certificate.
21
In essence, the applicant contends that its development and
the economic advantages, including job creation, that flow from such

a big development, are at risk. These rights are not easily
vindicated in the ordinary course, and the harm is not quantifiable

in a measure that can result in legal relief.
22
Three, the development is stagnant. It cannot move forward
whilst the City refuses to consider any subsequent approvals –
premised on its disregard of the certificates. In this regard, as
well, the applicant is suffering harm.
23
The Court considers the fact that the core of the application
concerns the vindication of the rule of law and a defence against
self-help. The principle which has been departed from is one of the
cornerstones of the Constitution. The City's reason for its
departure
is weak. This presses on the scale in favour of urgency. The reason
for the City's about-turn is, on the City's explanation,
a result of
the two departments, the Legal Department and the Planning
Department, not communicating with each other. This was
acknowledged
in oral submissions. It also appears from the City's answering
affidavit. In the answering affidavit, the City's Planning
Department
states that it has not received any "real correspondence"
from the Legal Department. The explanation for the
City not complying
with its constitutional obligations is not, as in
Kirland
, an
attempt to correct an error but rather a lack of communication
between two departments. This is unfortunate and, more importantly,

not legally defensible.
24
None of these considerations, individually, create the
conditions necessary to sustain a claim of urgency. However, when
viewed
cumulatively rather than individually, the Court is satisfied
that the requirement of urgency is satisfied.
25
The Court considers the issue of costs. The applicant has had
to approach the Court to vindicate fundamental rights. It has been

substantially successful. It is entitled to its costs on the
principle that the costs follow the result and on the premise that
it
was asserting the fundamental right to fair administrative action.
The matter involved multiple town planning applications and
was
brought under pressure. It is appropriate that the applicant enlisted
the assistance of two counsel in this matter and that
the City be
ordered to pay these costs. The applicant has requested that costs be
granted on a punitive scale. I find no basis,
in the manner the
matter was prosecuted, to grant costs on a punitive scale.
Order
26
The Court dispenses with the forms and services provided for
in the Uniform Rules of Court and allows the matter to be heard as
one of urgency under Uniform Rule 6(12).
27
The Court declares that the respondent's decision, dated 7
December 2022, as contemplated in section 16(12)(i) read with section

16(10)(b) of the Tshwane Land Use Management By-law, 2016 (“the
By-law”) pertaining to the proposed townships of Peach
Tree
Extensions 21- 25 (“the properties”) are valid and
binding.
28
The respondent is ordered to process the applicant’s
approved/issued applications for the properties, in terms of sections

13 and 23 of the By-law, within two weeks of this order.
29
The respondent is to update its computer system in accordance
with this order and to initiate the linking process between the Land

Use Scheme Department and the Building Plans and Inspection
Management Department, to enable the ensuing process of obtaining
approved Building Plans, contemplated in section 28(11) of the By-law
within a month of this order.
30
The respondent is ordered to take all administrative steps
necessary to process the remaining Town Planning Process.
31
The respondent is to pay the costs of the application,
including the costs of two counsel.
I
DE VOS
Acting
Judge of the High Court
This
judgment was prepared by Acting Judge, Irene de Vos. It is handed
down electronically by circulation to the parties or their
legal
representatives by email, by uploading it to the electronic file of
this matter on Caselines, and by publication of the judgment
to the
South African Legal Information Institute. The date for hand-down is
deemed to be 15 August 2023.
HEARD
ON:

16 August 2023
DECIDED
ON:

21 August 2023
For
the Applicant:

MC Erasmus SC with DJ van Heerden
Instructed by DP Du
Plessis Inc
For
the Respondent:

M
Ka-Siboto
Instructed
by Mothle Jooma Sabdia
[1]
MEC for Health, Eastern Cape and Another v Kirland Investments (Pty)
Ltd (CCT 77/13)
[2014] ZACC 6
;
2014 (5) BCLR 547
(CC);
2014 (3) SA
481
(CC) (25 March 2014) (“Kirland”)
[2]
Oudekraal Estates (Pty) Ltd v The City of Cape Town and others
(25/08)
[2009] ZASCA 85
;
Department
of Transport v Tasima I(Pty) Limited
[2016] ZACC 39
;
2017 (2) SA 622
(CC);
2017 (1) BCLR 1
(CC) ("Tasima I"); Khumalo v Member
of the Executive Council for Education, KwaZulu Natal
[2013] ZACC
49
;
2014 (5) SA 579
(CC);
2014 (3) BCLR 333
(CC) ("Khumalo");
Member of the Executive Council for Health, Eastern Cape v Kirland
Investments (Pty) Limited t/a
Eye and Lazer Institute
[2014] ZACC 6
;
2014 (3) SA 481
(CC);
2014 (5) BCLR 547
(CC) ("Kirland");
City of Cape Town v Aurecon South Africa (Pty) Limited
[2017] ZACC
5
;
2017 (4) SA 223
(CC);
2017 (6) BCLR 730
(CC) ("Aurecon");
State Information Technology Agency SOC Limited v Gijima Holdings
(Pty) Limited
[2017] ZACC 40
;
2018 (2) SA 23
(CC);
2018 (2) BCLR 240
(CC) ("Gijima")
[3]
Kirland
(above) para 65.
[4]
Id.
[5]
Kirland
(above) para 64.
[6]
Kirland
(above) para 82.