Mohau Molutsi Civil Works (Pty) Ltd and Others v Nala Local Municipality and Others (3719/2023) [2023] ZAFSHC 296 (28 July 2023)

80 Reportability
Public Procurement

Brief Summary

Urgent application — Interim interdict pending review application — Applicants sought an interim interdict against the Nala Local Municipality regarding the award of a tender for road construction, alleging unlawful administrative action due to procedural irregularities in the tender evaluation process — First and second respondents opposed the application, denying the allegations — Court found that the applicants established a prima facie right and demonstrated potential irreparable harm if the project proceeded without an interdict — Interim interdict granted to prevent the commencement of the project pending the outcome of the review application.

Comprehensive Summary

Summary of Judgment


1. Introduction


This matter concerned an urgent application for an interim interdict pending the outcome of judicial review proceedings to be instituted under Rule 53 of the Uniform Rules of Court. The application was brought in the Free State High Court, Bloemfontein, and was heard on 27 July 2023 and delivered electronically on 28 July 2023.


The applicants were Mohau Molutsi Civil Works (Pty) Ltd, Tlhabo Ya Lestsatsi Trading & Projects 47 CC, and the joint venture between them. The principal respondents were Nala Local Municipality and its Municipal Manager. The third to fifth respondents were private entities associated with the tender award, including ZM & Nikiwenono Constructions CC, Tshemedi Lefika Patso (Pty) Ltd, and Tshemedi JV ZM & Nikiwenono Construction Joint Venture. The third to fifth respondents did not participate in the litigation, while the first and second respondents opposed the interim interdict.


Procedurally, the parties agreed at the commencement of the hearing that the matter was urgent, and it proceeded as such under Rule 6(12). The parties further agreed that condonation could be granted for the first and second respondents to file a further affidavit in the main application. The interim interdict was sought pending the determination of a review contemplated to be pursued as Part B of the overall application.


The dispute arose from a municipal procurement process concerning a tender for the construction of a paved road and stormwater channel along the Sebotsa and Monnamocho roads in Bothaville, Free State, and the applicants’ challenge to the award and implementation of that tender.


2. Material Facts


The Municipality advertised a tender in April 2023, identified as Tender No: NLM/TS/008/2022–2023, calling for bids for the construction of the stormwater channel (and related works described in the proceedings as the construction of a paved road and stormwater channel along specified roads). A compulsory briefing took place on 2 May 2023, and bids closed on 22 May 2023.


On or about 26 June 2023, the applicants learned that the fifth respondent had been appointed as the successful bidder. The applicants’ complaint, as articulated to the Municipality through their attorneys’ letter of 11 July 2023, was that the successful bidder (identified as Tshemedi Lefikapatso JV) had submitted a bid for R10 592 098.00, whereas the applicants had submitted a bid for R10 272 027.70.


The applicants alleged that, at the bid evaluation stage, the Municipality identified arithmetic errors in the successful bidder’s pricing and effected arithmetic corrections, changing the price from R10 592 098.00 to R10 185 969.75 (a reduction of R406 128.25). They further alleged that these corrections were made without following the applicable procedure, in that the successful bidder was allegedly not invited at the evaluation stage, adjudication stage, or prior to appointment to agree or disagree to the change in tender price.


The applicants also alleged that their tender was found responsive at evaluation stage but that, at adjudication stage, their bid was not considered: they contended that their name did not appear on the list of bidders adjudicated, and that their bid was effectively eliminated without lawful or logical reasons.


The first and second respondents denied unlawfulness and attempted to explain their actions in answering and further affidavits. However, the court treated as significant that arithmetic corrections were effected without following the applicable procedure and that the applicants were not invited to make input at evaluation, adjudication, or prior to appointment. The court expressly stated that the audi alteram partem dictum was not applied.


By the time of the urgent hearing, the court recorded as a practical reality that the fifth respondent had already taken custody of the site, and that resources might be wasted if the works continued and were later halted. The applicants had attempted an alternative step by requesting the Municipality to stop implementation pending the review, but the Municipality did not entertain that request.


The court further accepted that the project had to be finalised to serve the interest of the community, which required the dispute to be adjudicated expeditiously.


3. Legal Issues


The central question was whether the applicants had met the requirements for an interim interdict restraining the Municipality and the tender beneficiaries from proceeding with implementation of the tender pending the final determination of the contemplated review.


This required the court to determine, on the papers, whether the applicants had shown a prima facie right (even if open to some doubt) coupled to a threat of irreparable harm, whether the balance of convenience favoured interim relief, and whether there was an absence of satisfactory alternative remedy, applying the established approach to interim interdicts.


The dispute entailed a combination of the application of legal standards to facts (the interim interdict requirements) and an evaluative component (in particular, the balance of convenience and the appropriate scope and duration of interim relief in the context of a public procurement project). In addition, the matter implicated the constitutional-law context for interim interdicts affecting executive action, particularly the need to consider separation of powers concerns as described in the Constitutional Court’s jurisprudence.


4. Court’s Reasoning


The court located the governing framework for interim interdicts in the authorities it cited, particularly Webster v Mitchell 1948 (1) SA 1186 (WLD) and Setlogelo v Setlogelo 1914 AD 221, and it also relied on National Treasury and Others v Opposition to Urban Tolling Alliance and Others 2012 (6) SA 223 (CC) for the broader constitutional setting in which interim interdicts restraining governmental implementation must be approached.


Drawing from Webster v Mitchell, the court proceeded on the basis that, for interim relief, an applicant does not need to show a right on a balance of probabilities, but must show a prima facie right, though open to doubt, assessed by considering the applicant’s facts together with those respondent facts that cannot be disputed, and then evaluating contradictions and inherent probabilities. The court also emphasised that when a clear right is not shown, the balance of convenience becomes decisive.


From Setlogelo, as interpreted within the interim interdict context, the court noted the role of irreparable harm, particularly where the right is prima facie established but open to doubt, and the court must consider whether continuing the impugned conduct would cause irreparable injury to the applicant, and whether stopping it would cause irreparable injury to the other party.


The court further relied on National Treasury v Opposition to Urban Tolling Alliance to describe the “atmosphere in law” for cases of this nature, including the need to consider separation of powers when an interdict would affect executive or administrative implementation. The judgment specifically noted that, under OUTA, the Setlogelo requirements continue to apply in a constitutional democracy and that the prima facie right required is not merely the right to bring a review, but a right that will suffer imminent irreparable harm if not protected. It also recorded OUTA’s emphasis that an interdict is meant to prevent future conduct, not decisions already made, and that courts must be alert to the intrusion into executive terrain, especially where public resources and policy implementation are implicated.


On the facts, the court treated the procurement irregularity relied upon by the applicants as material. Although the Municipality denied wrongdoing and sought to explain its conduct, the court stated that arithmetic corrections were effected without following the applicable procedure and that the applicants were not invited to make input, with the result that audi alteram partem was not applied. This was treated as sufficient, at least at the interim stage, to ground the applicants’ contention of unlawful administrative action and to support the existence of a prima facie right needing protection pending review.


On irreparable harm, the court referred to the harm alleged and “averred and proven” by the applicants, namely severe financial harm linked to losing the opportunity to execute the project on their tendered amount, and the contention that, if construction continued, by the time the review was heard the project could be completed, with a “high possibility” that setting aside would become impractical. The court also accepted the applicants’ point that damages would not provide an adequate remedy because they would be confined to a damages claim and would face difficulty in establishing intentional wrongdoing to succeed in delict.


The court also considered practical and public-interest aspects relevant to the balance of convenience. It recorded as a reality that the fifth respondent had already taken custody of the site, and that continuing work only to have it stopped later could result in wasted resources. At the same time, the court accepted that the project must be finalised to serve the community’s interests, and that the dispute should therefore be resolved expeditiously.


This led to an evaluative limitation on the scope of the interim relief. The court considered it too broad for the interdict to operate pending a review without ensuring that the review was pursued within a defined period, since review proceedings could take “months; if not years,” potentially creating extensive prejudice. The court therefore crafted the interim order to include a directive that review proceedings be instituted within a specified timeframe, failing which the interim interdict would lapse automatically.


On costs, the court adopted an approach linking costs of the urgent interdict to the contemplated review proceedings: costs were directed to be costs in the review application if the review followed and was concluded, with leave to apply on the same papers to adjudicate costs if the interdict lapsed due to failure to institute the review in time.


5. Outcome and Relief


The court granted condonation for the matter to be enrolled urgently under Rule 6(12) and granted condonation for the first and second respondents to file a further affidavit under Rule 6(5)(e).


Pending the final determination of the review application to be brought under Part B, the court granted an interim interdict with immediate effect. The Municipality was interdicted from taking further steps to implement the tender, including concluding or implementing agreements with the third to fifth respondents and commencing or continuing construction. The first and second respondents were interdicted from handing over control of the site to the third to fifth respondents, and the third to fifth respondents were interdicted from implementing any agreement in respect of the tender or commencing or continuing construction.


The court ordered that the applicants must institute the review proceedings within 60 days of the order, failing which the interim interdict would lapse automatically. The parties were given leave to apply on the same papers, duly amplified, for a costs determination if the interdict lapsed; otherwise, costs were ordered to be costs in the review application.


Cases Cited


National Treasury and Others v Opposition to Urban Tolling Alliance and Others 2012 (6) SA 223 (CC).


Webster v Mitchell 1948 (1) SA 1186 (WLD).


Setlogelo v Setlogelo 1914 AD 221.


Legislation Cited


No legislation was cited in the judgment.


Rules of Court Cited


Uniform Rules of Court, Rule 6(12).


Uniform Rules of Court, Rule 6(5)(e).


Uniform Rules of Court, Rule 53.


Held


The court held that the matter was urgent and proceeded under Rule 6(12), with condonation also granted for the filing of a further affidavit by the first and second respondents under Rule 6(5)(e). It further held that interim relief was warranted pending a Rule 53 review, in circumstances where the Municipality had effected arithmetic corrections without following the applicable procedure and where the applicants were not afforded an opportunity to make input, with the result that the audi alteram partem principle was not applied.


The court granted an interim interdict restraining implementation of the tender and restraining the handover and continued control of the site to the tender beneficiaries, and restraining the tender beneficiaries from continuing construction. The interim relief was expressly made time-bound by requiring the applicants to institute review proceedings within 60 days, failing which the interdict would lapse automatically. Costs were directed to stand over for the review (or to be revisited if the interdict lapsed).


LEGAL PRINCIPLES


The judgment applied the established principles governing interim interdicts, including that an applicant must show a prima facie right (even if open to doubt), and that the assessment proceeds by considering the applicant’s version together with those respondent facts that cannot be disputed, before weighing contradictions and probabilities, as articulated in Webster v Mitchell 1948 (1) SA 1186 (WLD).


It reaffirmed that irreparable harm is a material consideration, particularly where the right asserted is prima facie but open to doubt, consistent with Setlogelo v Setlogelo 1914 AD 221. Where the right is not clear, the court must decide whether to grant interim protection by weighing irreparable harm and the balance of convenience.


In the context of interim interdicts affecting governmental implementation, the judgment adopted the Constitutional Court’s approach in National Treasury and Others v Opposition to Urban Tolling Alliance and Others 2012 (6) SA 223 (CC). This included that, while the Setlogelo requirements continue to apply in a constitutional democracy, the relevant prima facie right is not merely the right to bring a review, but a right that, if not protected, faces imminent irreparable harm. The judgment further reflected the principle that an interdict restrains future conduct rather than undoing decisions already made, and that courts must be mindful of the separation of powers implications where interim relief intrudes into executive implementation, especially in matters involving public projects and resource allocation.


Finally, the judgment illustrated that even where interim relief is justified, the scope and duration of an interim interdict may be tailored to avoid undue prejudice and delay, including by requiring that review proceedings be instituted within a defined period, failing which the interim relief will lapse.

About SAFLII
Databases
Search
Terms of Use
RSS Feeds
South Africa: Free State High Court, Bloemfontein
SAFLII
>>
Databases
>>
South Africa: Free State High Court, Bloemfontein
>>
2023
>>
[2023] ZAFSHC 296
|

|

Mohau Molutsi Civil Works (Pty) Ltd and Others v Nala Local Municipality and Others (3719/2023) [2023] ZAFSHC 296 (28 July 2023)

IN
THE HIGH COURT OF SOUTH AFRICA
FREE STATE PROVINCIAL
DIVISION
Not Reportable
Case no: 3719/2023
In the matter between:
MOHAU
MOLUTSI CIVIL WORKS (PTY) LTD
First
Applicant
TLHABO
YA LESTSATSI TRADING & PROJECTS 47 CC
Second
Applicant
MOHAU MOLUTSI CIVIL
WORKS (PTY) LTD//
TLHABO
YA LESTSATSI TRADING & PROJECTS 47 CC JOINT VENTURE
Third
Applicant
And
NALA
LOCAL MUNICIPALITY
First
Respondent
THE
MUNICIPAL MANAGER: NALA LOCAL MUNICIPALITY
Second
Respondent
ZM
& NIKIWENONO CONSTRUCTIONS CC
Third
Respondent
TSHEMEDI
LEFIKA PATSO (PTY) LTD
Fourth
Respondent
TSHEMEDI JV ZM &
NIKIWENONO
CONSTRUCTION
JOINT VENTURE
Fifth
Respondent
Coram:
Opperman, J
Heard:
27 July 2023
Delivered:
28 July 2023. This judgment was handed
down electronically by circulation to the parties’ legal
representatives
via
email and release to SAFLII on 28 July 2023. The date and time of
hand-down is deemed to be 15h00 on 28 July 2023
Summary:
Urgent application – interim
interdict pending review application
JUDGMENT
[1]
This is an urgent application for an
interim interdict pending the outcome of judicial review proceedings
to be instituted in terms
of Rule 53 of the Uniform Rules of Court.
[2]
The third to fifth respondents did not
participate in the litigation. The first and second respondents
oppose the application for
the interim interdict.
[3]
The parties were in agreement at the
commencement of the hearing of the matter that the application is
urgent and it was ordered
that the matter proceeded so and in terms
of Rule 6(12) of the Uniform Rules of Court.
[4]
The
parties also agreed that condonation may be granted to the first and
second respondents to file “a further affidavit”
[1]
in the main application.
[5]
The cause of the litigation is related to
the construction of a paved road and stormwater channel along the
Sebotsa and Monnamocho
roads in Bothaville: Free State Province and
the tender issued for the works thereon.
[6]
The Nala Local Municipality advertised a
tender calling for bidders to submit their bids for their possible
appointment for the
construction of the stormwater channel in April
2023 in Tender No: NLM/TS/008/2022-2023.
[7]
The compulsory briefing was scheduled for 2
May 2023 and the closing date for submission of bids was the 22
nd
of May 2023. On about the 26
th
of June 2023 the applicants learned of the appointment of the fifth
respondent as the successful bidder.
[8]
What
then followed was an allegation of unlawful administrative action as
articulated in a letter dated 11 July 2023
[2]
from the attorney for the applicants addressed to the first and
second respondents:
7.1 The successful bidder
is Tshemedi Lefikapatso JV which submitted a bid for the total amount
of R10 592 098.00 and our client
submitted a bid for R10 272 027.70;
7.2 At bid evaluation
stage, the committee found or identified arithmetic errors or
effected arithmetic corrections on the tender
pricing of Tshemedi
Lefikapatso JV of R10 592 098.00 and the price was changed to R10 185
969.75, in other words it was reduced
with the amount of R406 128.25;
7.3 The Municipality
effected the arithmetic corrections without following the procedure
applicable thereto in that Tshemedi Lefikapatso
JV was not invited at
evaluation stage or adjudication stage and even prior to the
appointment to either agree or not agree to
the change in the tender
price;
7.4 At bid evaluation
stage, our client’s tender was one of the responsive bidders or
tenders, or rather our client’s
tender was evaluated and it was
found to be responsive;
7.5 At bid adjudication
stage, our client’s tender was not part of the bidders which
were considered by the bid adjudication
committee, in fact our
client’s name does not even appear from the lists of bidders
whom their bids were adjudicated, in
other words our client’s
bid was never adjudicated and or was eliminated from participating
the bid adjudication committee
for no logical, lawful or sound
reasons.
8. It is based on the
above, that the award of the tender to Tshemedi Lefikapatso JV was
not only unlawful, but was also irregular,
and it is on this basis
that we request the Municipality to give us an undertaking before the
close of business today that having
regard to the irregularities
identified above, the commencement or implementation of the project
will not take place or is rather
suspended pending the filing of the
review application in the Free State Division Bloemfontein either by
our clients or the Municipality,
and in this regard we invite the
Municipality to give us a written undertaking before the close of
business today that the Municipality
will file the review application
against its own decision hereof within 30 days from date hereof.
9. Should we not receive
your written undertakings by the close of business today 11 July
2023, we have instructions to approach
the Free State Division,
Bloemfontein on an urgent basis with an urgent application to
interdict the Municipality from proceeding
with the implementation or
commencement of the project pending the filing of the review
application.
[9]
The first and second respondents denied the
allegation and endeavored to explain their actions in their answering
and further affidavits.
The fact remains that the Municipality
effected the arithmetic corrections without following the procedure
applicable thereto in
that the applicants were not invited at
evaluation stage or adjudication stage or even prior to the
appointment of the contractor;
to make an input. The
audi
alteram partem
dictum was not applied.
[10]
In
National
Treasury and others v Opposition to Urban Tolling Alliance and
others
2012 (6) SA 223 (CC) the
atmosphere in law in which cases that is of the nature
in
casu
must
be adjudicated, was stated.
HEADNOTE:
On
28 April 2012 the North Gauteng High Court granted an interdict
restraining the SANRAL (the government agency in charge of national

roads) from proceeding with its controversial 'e-tolling' system, an
electronic tagging-and-tolling system that was to be implemented
in
Gauteng province to finance SANRAL's upgrading of the province's
freeways. In an application for leave to appeal to the Constitutional

Court —
Held:
The high court interdict had the effect, for as long as it was in
place, of preventing the national executive from fulfilling
its
statutory and budgetary responsibilities. Before making an order of
such nature a court was obliged to consider — in
addition to
the usual common-law requirements for the granting of an interim
interdict — the doctrine of separation of powers,
which barred
the judiciary from meddling in executive or legislative matters
unless the intrusion was constitutionally mandated.
The court had to
take into account the interests of the government and the extent to
which the requested interdict would intrude
on executive terrain,
particularly if it interfered with the allocation of public
resources, which was a policy issue at the core
of the executive
domain. Such interference was unwarranted, except where there was
proof of unlawfulness, fraud or corruption.
In the present case the
high court had, by preventing SANRAL from performing its statutory
duties, meddled in fiscal affairs, and
done so without even touching
on the issue of separation of powers. The court had also ignored the
substantial financial harm the
interdict would cause the government.
The high court's deafening silence on the issue of separation of
powers, in conjunction with
the balance of convenience, justified
interference with the high court order. Interdict accordingly set
aside on appeal. (Paragraphs
[27], [44] – [47] and [65] –
[73] at 232B – E, 236E – 237D and 241B – 242I.)
[11]
In
Webster
v Mitchell
1948 (1) SA 1186 (WLD) the court articulated the
test for an interim interdict.
HEADNOTE:
In
an application for a temporary interdict, applicant’s right
need not be shown by a balance of probabilities; it is sufficient
if
such right is prima facie established, though open to some doubt. The
proper manner of approach is to take the facts as set
out by the
applicant together with any facts set out by the respondent which
applicant cannot dispute and to consider whether,
having regard to
the inherent probabilities, the applicant could on those facts obtain
final relief at the trial. The facts set
up in contradiction by the
respondent should then be considered, and if serious doubt is thrown
upon the case of applicant, he
could not succeed. In considering the
harm involved in the grant or refusal of a temporary interdict, where
a clear right to relief
is not shown, the Court acts on the balance
of convenience. If, though there is prejudice to the respondent, that
prejudice is
less than that of the applicant, the interdict will be
granted. Subject, if possible, to conditions which will protect the
respondent.
[12]
In
Setlogelo
v Setlogelo
1914
AD 221
at
page 227 Innes JA, dealing with the peremptory requirement to
demonstrate irreparable harm, ruled:
That
element is only introduced by him in cases where the right asserted
by the applicant, though prima facie established, is open
to some
doubt. In such a case the test must be applied where the continuance
of the thing against which an interdict is sought
would cause
irreparable injury to the applicant. If so, the better course is to
grant the relief if the discontinuance of the act
complained of would
not involve irreparable injury to the other party.
[13]
In
National
Treasury and others v Opposition to Urban Tolling Alliance and
others
2012 (6) SA 223 (CC) at paragraph [50]
it was ruled that the
Setlogelo
requirements
supra
,
in respect of an interdict, still found application within a
constitutional democracy.
Under
the Setlogelo test, the prima facie right that the claimant must
establish is not merely the right to approach a Court in
order to
review an administrative decision. It is a right to which, if not
protected by an interdict, irreparable harm would ensue.
An interdict
is meant to prevent future conduct and not decisions already made.
Quite apart from the right to review and to set
aside impugned
decisions, the applicants should have demonstrated a prima facie
right that is threatened by an impending or imminent
irreparable
harm. The right to review the impugned decisions did not require any
preservation
pendente lite
.
[14]
The irreparable harm
averred and proven by the applicants are that
30.
The applicants stand to suffer severe financial harm if they are not
granted the interim relief. They tendered to execute the
project for
an amount of
R10 272 027-70
.
31.
If the interim interdict is not granted and the construction in (sic)
left to proceed nonetheless, it is unlikely that during
the hearing
in due course, which might occur towards the end of the year, the
project would be completed with a high possibility
being that the
Court will not set aside the tender as it would be impractical to do
so.
32.
The applicants will thus be left with no alternative remedy to sue
for damages, because they will not be in a position to demonstrate

that there was intentional wrongdoing on the part of the municipality
to succeed in an action for delictual damages.
[15]
It is a reality of
this case that the fifth respondent has already taken custody of the
site and that resources may be wasted should
they continue and just
to be halted at a later stage. The applicants attempted alternative
remedies by, for instance, requesting
the first and second
respondents to stop the implementation of the project until final
determination of the review application.
The request was not
entertained.
[16]
It is also a fact
that the project must be finalized in order to serve the interest of
the community. The dispute between the parties
has to be adjudicated
expeditiously. The request that the interdict be operative pending
the finalization of the review is too
broad. It might take months; if
not years, and the prejudice to all the parties involved might be
extensive. The order of this
court will therefore include an
instruction on the institution of the review proceedings.
[17]
The costs for this
application will be costs in the review application if the review
application follows and is concluded.
[18]
ORDER
It is ordered that:
1.
Condonation is granted to the applicants to
enroll the application in terms of Rule 6(12) of the Uniform Rules of
Court.
2.
Condonation is granted for the filing of a
further affidavit by the first and second respondents in terms of
Rule 6(5)(e) of the
Uniform Rules of Court.
3.
Pending
the final determination of the review application, which is to be
brought under Part B of this application, it is ordered
that:
3.1
The
first respondent is interdicted from taking any further steps to
implement tender
NLM/TS/008/2022-23: Construction of paved
road and stormwater channel in Sebotsa and Monnamocho Road
,
including but not limited to concluding or implementing any agreement
in respect of the tender with the third to fifth respondents
or
commencing or continuing with any construction in terms thereof.
3.2  The first and
second respondents are interdicted and restrained from handing over
control of the site, which is a subject
of the tender, to the third
to fifth respondents.
3.3  The third,
fourth and fifth respondents are interdicted and restrained from
implementing any agreement in respect of the
tender with the first
respondent or commencing or continuing with any construction in terms
thereof.
4.
The relief granted in paragraph 3 above is
to operate as an interim order with immediate effect pending the
final determination
of the review to be sought in Part B of this
application.
5.
It is further ordered that the
applicants must institute litigation on the review application within
60 (sixty) days of the date
of this order. Failure of which the
interim interdict shall lapse automatically.
6.
The parties are granted leave to apply to
this court on the same papers, duly amplified, to adjudicate the
issue of costs should
the lapsing of the interim interdict in
paragraph 5 take effect. Otherwise, costs are to be costs in the
review application.
M OPPERMAN, J
APPEARANCES
For the applicants:
O.K. CHWARO
Instructed by:
Modiboa Attorneys
Incorporated
KLERKSDORP
c/o
McIntyre Van Der Post Attorneys
BLOEMFONTEIN
For the first &
second respondents:
L.A. ROUX
Instructed by:
Maritz – Willemse
Attorneys
WELKOM
c/o
Hill McHardy & Herbst Incorporated
BLOEMFONTEIN
[1]
The
Notice of Motion accompanied by the founding affidavit were served
on 18 July 2023, the Notice to Oppose and the answering
affidavit
were served on 24 July 2023, the replying affidavit followed on the
25th of July 2023 and the condonation application
for the further
affidavit on the 27th of July 2023.
[2]
Pages
67 to 72.