MEC: Free State Provincial Government: Department of Police, Roads and Transport v Sedtrade (Pty) Ltd (1845/2022) [2023] ZAFSHC 243 (19 June 2023)

80 Reportability
Contract Law

Brief Summary

Execution — Rescission of consent order — Applicant sought rescission of consent order for unpaid invoices based on common law ground of iustus error, claiming mistaken belief that respondent completed roadworks — Court found applicant's reliance on iustus error unsustainable as the applicant failed to demonstrate that the alleged mistake affected the conclusion of the settlement agreement — Court held that the applicant's defense carried some prospects of success and rescinded the consent order, ordering costs on a punitive scale against the applicant due to its reprehensible conduct in the proceedings.

Comprehensive Summary

Summary of Judgment


1. Introduction


The proceedings were an opposed application in the High Court of South Africa (Free State Division, Bloemfontein) in which the applicant sought the rescission or variation of a consent order previously granted in favour of the respondent.


The applicant was the MEC: Free State Provincial Government: Department of Police, Roads and Transport, and the respondent was Sedtrade (Pty) Ltd.


The procedural history was that the respondent, as plaintiff in action proceedings, had sued the applicant for unpaid invoices arising from a road upgrading contract. On 23 June 2022, the parties settled that action and a consent order was granted by agreement. The applicant later launched the present application to rescind or vary that order, contending that the consent was given under a mistaken belief regarding completion of the works. The respondent opposed the rescission and contended the application was motivated by an ulterior purpose to avoid payment.


The dispute concerned payment obligations under a public works contract for the upgrading of the road between Deneysville and Heilbron, and specifically whether the consent judgment should stand notwithstanding alleged non-completion of works and the circumstances in which the settlement was concluded.


2. Material Facts


A contract was concluded between the parties on 13 September 2016 for the upgrading of the road between Deneysville and Heilbron. The respondent later instituted action proceedings against the applicant for unpaid invoices connected to that work.


On 23 June 2022, judgment was granted against the applicant by agreement (a consent order). The consent order recorded that the applicant would pay the respondent R7 332 809.60 and R8 060 952.12, and that each party would pay its own costs.


The applicant’s case in the rescission application was that its Acting Director of Legal Services, Mr Monyane, authorised the applicant’s attorney to consent to the settlement under the belief that the respondent had completed the works and was entitled to payment. The applicant alleged that only afterwards, when Mr Monyane motivated for payment, he became aware that the respondent had not completed the works, and that the applicant’s project manager, Mr Ndaba, had also refused to sign a certificate of completion for that reason. The applicant relied on photographic material suggesting approximately a kilometre of roadworks remained incomplete.


It was not disputed on the papers (as the court framed the matter) that about a kilometre of roadworks was incomplete and that, on the completed part, there were snags not attended to by the respondent. The parties did, however, dispute why the works were incomplete. The applicant’s stance was that paying under the consent order would cause fruitless and wasteful expenditure because the contractual payment would be exhausted while the project remained incomplete.


The respondent’s opposition proceeded on the basis that the applicant sought to evade a valid obligation to pay, particularly because the applicant made no payment after the consent order, prompting the respondent to issue a warrant of execution on 1 September 2022. The respondent also contended that the issues now raised (incomplete works and the absence of a completion certificate) existed before the settlement, were discussed by the applicant’s officials, and that Mr Ndaba attended a meeting where the settlement was concluded and later reduced to writing by the applicant’s head of department.


The respondent further disputed the adequacy of the photographs as a reflection of the road and maintained that the outstanding kilometre related to an “extra” portion requiring Provincial Treasury authorisation, which the applicant had not obtained; on that version, the respondent contended it could not build that portion without such authorisation.


3. Legal Issues


The central legal questions were whether the applicant had established grounds in the common law for rescission (or variation) of a consent order, and if so, on what basis.


The court was required to determine whether the consent order could be rescinded on the ground of iustus error (a vitiating mistake) and, alternatively, whether rescission was justified on the basis of justa causa (good and sufficient cause), which in this context required demonstrating a bona fide defence that prima facie carried prospects of success on the merits.


These questions involved a combination of legal standards (the requirements for rescission of a consent order at common law) and their application to the factual matrix (the circumstances of the settlement and whether there was a bona fide defence based on alleged non-completion and the absence of a completion certificate). The costs question required an evaluative judgment concerning litigation conduct and the appropriate scale of costs.


4. Court’s Reasoning


The court stated that, at common law, a consent order may be rescinded on the basis of iustus error where it is shown that the party denying liability laboured under a mistake. The court also recognised rescission on justa causa, described as a good and sufficient cause warranting rescission, namely where there is a bona fide defence which prima facie has some prospect of success on the merits.


On iustus error, the court was not persuaded that the applicant’s reliance on mistake was legally sustainable. The court considered that the background leading to settlement did not support the contention that Mr Monyane laboured under a mistake when authorising the settlement. Instead, the court characterised his conclusion of a settlement agreement—resulting in payment of a disputed debt—as reflecting a neglect of obligations to manage legal risks, including the risk of fruitless and wasteful expenditure of public funds. On this reasoning, the court rejected rescission grounded on iustus error, treating the relevant conduct as negligence rather than a vitiating mistake that undermined genuine consent in the manner required.


However, on justa causa, the court’s analysis took a different turn. It accepted that, on the papers, it was not in dispute that there was an incomplete portion of the roadworks (about a kilometre), and that even the completed part had outstanding snags. While the parties disagreed about the cause of incompleteness, the court considered the legal consequences of incomplete performance in the context of final payment.


The court held that a contractor is not entitled to final payment until the building project is complete, and that the onus rested on the respondent (as claimant under the contract) to allege and prove that everything required by the contract had been done. In light of the incomplete works and outstanding snags, the court concluded that, prima facie, the applicant’s defence to the respondent’s claim carried some prospects of success on the merits.


The court further considered the bona fides of the application and accepted that the applicant was desirous of being heard in the main action. For these reasons, the court concluded that the applicant had shown just cause for rescission, notwithstanding the earlier rejection of iustus error.


On costs, the court drew a distinction between the respondent’s entitlement to oppose and the applicant’s role in creating the circumstances leading to the consent order. The court was not persuaded that the respondent should bear costs for opposing rescission, given that the respondent had obtained a consent judgment after protracted negotiations. Conversely, the court viewed the applicant’s conduct in shaping the settlement and resulting consent order as reprehensible, and of a kind warranting a punitive costs order, as contended for by the respondent. The court therefore awarded costs against the applicant on an attorney and client scale.


5. Outcome and Relief


The court rescinded the consent order dated 23 June 2022.


The applicant was ordered to pay the respondent’s costs on the attorney and client scale.


Cases Cited


Dalinga Belleggings (Pty) Ltd v Antina (Pty) Ltd 1979 (2) SA 56 (A)


Legislation Cited


No legislation was cited in the judgment.


Rules of Court Cited


No rules of court were cited in the judgment.


Held


The court held that the applicant did not establish rescission on the ground of iustus error, because the settlement was not shown to have been concluded under a legally cognisable vitiating mistake; rather, the relevant conduct was characterised as neglect in concluding settlement of a disputed debt.


The court nevertheless held that rescission was warranted on the basis of justa causa, because it was not in dispute that a portion of the roadworks was incomplete and that snags remained, and because a contractor is not entitled to final payment before completion. The respondent bore the onus to prove full contractual performance, and the applicant accordingly demonstrated a bona fide defence with prima facie prospects of success.


The consent order was rescinded, but the applicant was ordered to pay punitive costs (attorney and client scale) due to its reprehensible conduct, while the respondent was found to have been entitled to oppose the application.


LEGAL PRINCIPLES


A consent order may be rescinded at common law on the basis of iustus error, where a party’s consent was vitiated by a mistake of the kind recognised in law as undermining true agreement. Mere negligence or a failure to properly assess litigation risk, without more, does not necessarily constitute such a vitiating mistake.


A consent order may also be rescinded on justa causa upon good and sufficient cause, which in this context entails demonstrating a bona fide defence that prima facie has prospects of success on the merits.


In contractual claims for final payment in a building or construction-type project, the principle applied was that a contractor is not entitled to final payment until completion, and the onus lies on the claimant contractor to allege and prove that all work required by the contract has been done.


A party may be entitled to oppose rescission where it obtained a consent judgment after extended negotiations, but punitive costs may be awarded where the opposing party’s conduct in bringing about the consent order is found to be sufficiently reprehensible to justify an attorney and client scale.

About SAFLII
Databases
Search
Terms of Use
RSS Feeds
South Africa: Free State High Court, Bloemfontein
SAFLII
>>
Databases
>>
South Africa: Free State High Court, Bloemfontein
>>
2023
>>
[2023] ZAFSHC 243
|

|

MEC: Free State Provincial Government: Department of Police, Roads and Transport v Sedtrade (Pty) Ltd (1845/2022) [2023] ZAFSHC 243 (19 June 2023)

IN
THE HIGH COURT OF SOUTH AFRICA,
FREE
STATE DIVISION, BLOEMFONTEIN
Case
number: 1845/2022
Reportable:

YES/NO
Of
Interest to other Judges:   YES/NO
Circulate
to Magistrates:        YES/NO
In
the matter between:
MEC:
FREE STATE PROVINCIAL GOVERNMENT:
Applicant
DEPARTMENT
OF POLICE, ROADS AND TRANSPORT
And
SEDTRADE
(PTY) LTD
Respondent
HEARD
ON:
09
FEBRUARY 2023
JUDGMENT
BY:
DANISO, J
DELIVERED
ON:
This judgment
was handed down electronically by circulation to the parties'
representatives by email and by release to SAFLII. The
date and time
for hand-down is deemed to be 19 JUNE 2023 at 14H00.
[1]
On 23 June 2022 judgment was granted against the applicant by
agreement between the
parties (consent order) pursuant to action
proceedings instituted by the respondent as plaintiff against the
applicant as defendant
for unpaid invoices relating to the upgrading
of the road between Deneysville and Heilbron in terms of a contract
concluded between
the parties on 13 September 2016.
[2]
In terms of the said consent order the parties agreed that:

1.
The defendant is to pay to the plaintiff the amount of R7 332 809.60;
2.
The defendant is to further pay to the plaintiff the amount of
R8 060 952.12;
3.
Each party to pay its own costs.”
[3]
In this opposed application, the applicant seeks an order for the
rescission or variation
of the consent order based on the common law
ground of
iustus
error
and
this is due to the fact that the applicant’s acting director of
Legal Services Mr Monyane, authorised the applicant’s
attorney
to consent to the order under the mistaken belief that the respondent
had completed the works and thus entitled to the
payment. It was only
after Mr Monyane submitted a motivation for the payment that he
became aware that the respondent had not completed
the works and that
the applicant’s project manager Mr Ndaba had also refused to
sign the certificate of completion for that
reason. The photographs
taken at the site
[1]
depicts
about a kilometre of incomplete road works.
[4]
It is the applicant’s case that the consent order ought to be
rescinded for
the reason that if the respondent is paid as per the
consent order, that would amount to fruitless and wasteful
expenditure as
all the contractual payment would be exhausted whilst
the project is incomplete. The court is also entitled rescind the
order on
just and equitable grounds to guard against an abuse of
public funds.
[5]
The respondent opposition is premised on the grounds that the
application is motivated
by an ulterior purpose. The applicant simply
seeks to avoid a perfectly valid obligation to pay the respondent
because, pursuant
to the consent order no payment was made by the
applicant with the result that approximately two months later on 1
September 2022
the respondent had to issue a warrant of execution for
the enforcement of the consent order.
[6]
The respondent explains that the defences relied upon by the
applicant namely, incomplete
works and unsigned completion
certificate existed before the consent order was issued. The matter
was discussed between the applicant’s
officials before the
settlement agreement was concluded and Mr Ndaba was present together
with other applicant’s officials
at the meeting where the
settlement agreement was ultimately concluded and later reduced into
writing by the applicant’s
head of department. Mr Monyane’s
error if any, it did not have an effect in the conclusion of the
settlement agreement which
resulted in the consent order therefore it
does not vitiate the consent order. There is also no evidence that
there purported error
was induced by misrepresentation on the part of
the respondent.
[7]
As regards the photographs depicting the incomplete work, the
respondent states that
the photos are not an adequate reflection of
the road. The outstanding work is actually in relation to the extra
one kilometre
which the applicant had first to obtain authorisation
from the Provincial Treasury and since no authorisation was obtained
by the
applicant the respondent could not build that road. According
to the respondent, the application is both morally and legally
repugnant
it must accordingly be dismissed with costs on a punitive
scale.
[8]
In terms of the common law a consent order may be rescinded on
justus
err
or
where it can be shown that the denier of liability laboured under a
mistake alternatively on
justa
causa
based on a good and sufficient cause shown warranting the rescission
namely, there is bona fide defence which
prima
facie
carries
some prospect of the applicant succeeding on the merits.
[2]
[9]
The background facts leading to the conclusion of the settlement
agreement which resulted
in the consent order do not support the
applicant’s contention that Mr Monyane laboured under a mistake
when he authorized
the applicant’s attorney to conclude a
settlement agreement with the respondent. His haphazard conclusion of
a settlement
agreement which resulted in the consent order to pay a
debt which was disputed was merely a pure neglect of his obligations
to
ensure that the applicant averts the legal risks including the
risk of fruitless and wasteful expenditure of public funds. I am
thus
not persuaded that the applicant’s reliance on
justus error
is legally sustainable.
[10]
On the papers, it is not in dispute that roadworks in relation to
about a kilometre of the road
is incomplete and that with regard to
the complete part of the road there are snags which have not been
attended to by the respondent.
The parties are in disagreement with
regard to the reasons for the incomplete works. A contractor is not
entitled to the final
payment until the building project is
complete.
[3]
The onus is on the
respondent to allege and prove that ‘everything was done that
had to be done in terms of the contract’
on which they rely for
its claim. For this reason, it does appear that
prima
facie,
the
applicant’s defence to the respondent’s claim carries
some prospects of success. The application is also
bona
fide
as
the applicant is desirous to be heard in the main action accordingly,
the applicant has made out a case for the rescission of
the consent
order on the basis of just cause.
[11]
Turning to the issue of costs. Notwithstanding the conclusion that I
have come to, I am not persuaded
by the applicant’s contention
that the respondent should be saddled with the costs based on its
opposition of the application.
The respondent had a judgment granted
in its favour by consent after a protracted period of settlement
negotiations the respondent
was therefore entitled to oppose the
application.
[12]
On the other side, the applicant’s conduct and how it shaped
the proceedings which resulted
in the consent order being granted has
been reprehensible, it is indeed a conduct which is well within the
type of conduct considered
to warrant a punitive cost order as
asserted by the respondent.
[13]
In the result,
I
make the
following order:
(1)
The court order dated 23 June 2022 is hereby rescinded.
(2)
The applicant shall pay the costs on attorney and client scale.
N.S. DANISO, J
APPEARANCES:
Counsel on behalf
of Applicant:
Adv. B.S. Mene SC
Instructed by:
State Attorney
BLOEMFONTEIN
Counsel on behalf
of Respondent:
Adv. S. Grobler
(SC)
Instructed by:
Raees Chothia
Attorneys
C/O Honey Attorneys
BLOEMFONTEIN
[1]
Annexure “DPRT6” of the applicant’s founding
affidavit.
[2]
D E Van
Loggerenberg et al Er
a
smus
:
Superior Court Practice 2nd edition (2015) at B1–308.
[3]
Dalinga
Belleggings (Pty) Ltd v Antina (Pty) Ltd
1979
(2) SA 56
(A).