About SAFLII
Databases
Search
Terms of Use
RSS Feeds
South Africa: Kwazulu-Natal High Court, Durban
SAFLII
>>
Databases
>>
South Africa: Kwazulu-Natal High Court, Durban
>>
2021
>>
[2021] ZAKZDHC 24
|
|
Kwadukuza Municipality v Build-Rite Properties (Pty) Ltd and Others (D10675/2019) [2021] ZAKZDHC 24 (12 August 2021)
IN THE HIGH COURT OF
SOUTH AFRICA
KWAZULU-NATAL LOCAL
DIVISION : DURBAN
CASE
NO: D10675/2019
In
the matter between:
KWADUKUZA
MUNICIPALITY APPLICANT
and
BUILD-RITE
PROPERTIES (PTY) LTD FIRST
RESPONDENT
MARLIN
NAIDOO SECOND
RESPONDENT
MOHSIN
GANI THIRD
RESPONDENT
ORDER
1.
(a) The
application against the second and third respondents is dismissed.
(b) The
applicant shall pay such additional costs as may have been incurred
by the inclusion of the second and
third respondents as parties to
the litigation.
2.
The
order of 27 January 2020 is discharged.
3.
(a) The
application for the interdict set out in paragraph 2 (c) of the order
prayed in the notice
of motion is dismissed.
(b) The
counter application is granted in the following terms.
“
It
is declared that the Core Mixed Use (MUC 3) zoning currently applied
to Erf 220, CBD Stanger situate at 63 Balcomb Street, KwaDukuza
permits the operation of a wholesale hardware shop or hardware shop
within a shop building situate on the said Erf 220.”
(c) The
costs of the counter application shall be paid by the applicant.
4.
As
to the costs of the main application not already dealt with in
paragraph 1 of this order,
(a)
those
incurred up to and including 27 January 2020 shall be paid by the
first respondent; and
(b)
those
incurred after 27 January 2020 shall be paid by the applicant.
JUDGMENT
Delivered on:
Thursday, 12 August 2021
OLSEN
J
[1] This
application was launched by the KwaDukuza Municipality on 13 December
2019, accompanied by a certificate
of urgency recording a contention
that a hearing of the application on 18 December 2019 was justified.
The papers cited the first
respondent, Build-Rite Properties (Pty)
Limited, as the owner of Erf 220, CBD Stanger (“Erf 220”).
The second respondent,
Marlin Naidoo, was cited as a person “who
conducts business from or is employed at Erf 220”. The third
respondent,
Mohsin Gani, was similarly cited.
[2] The
application is all about the construction of a building by the first
respondent on Erf 220. It should have
been perfectly clear to the
applicant that the party responsible for the construction was the
owner of Erf 220, the first respondent.
The second respondent is
employed as the project manager for the works in question. The third
respondent is a director of the first
respondent. Although the relief
sought by the applicant in its notice of motion was expressed to be
against each of the respondents,
no case has been made out for the
proposition that it was justified, or might be justified, to seek
such relief against the second
and third respondents. Erf 220 belongs
to the first respondent. The construction works were undertaken at
the instance of the first
respondent. Any deviation from lawful
conduct in connection with the construction was the responsibility of
the first respondent.
[3] Counsel
for the applicant advanced its argument on the footing that there are
no material disputes of fact
evident on the papers. Counsel for the
respondents correctly challenged that notion. The respondents’
papers challenge and
contradict a number of the facts stated in the
founding papers. I have concluded that some of these disputed facts
have a material
bearing on one aspect of this case, and in those
instances I must accept the respondents’ version where the
challenge is
bona
fide
and real.
[4] In
summary the notice of motion sought the following relief.
(a)
Firstly
an order directing the respondents to vacate Erf 220, and
interdicting the respondents from causing or allowing occupation
thereof before a certificate of occupancy is issued.
(b)
An
order interdicting and restraining the respondents from carrying out
any further building work on the property other than the
construction
of a retaining wall
(i)
under
the direct supervision of a “certified and licenced civil
engineer”, and in accordance with the design of such
an
engineer for the retaining wall; or
(ii)
strictly
in accordance with approved building plans for the retaining wall.
(c)
An
order restraining the use of Erf 220 as a hardware store, a builder’s
supply yard, or in any other way in conflict with
the zoning of the
property under the KwaDukuza Land Use Management Scheme. (The
founding papers specify no such alternative use.)
[5] The
relief sought in this case is of two types. The interdicts concerning
occupancy and construction works
seek to restrain the respondents
(and of course in particular the first respondent) from proceeding
with either occupation or construction
without certain conditions
being met. The relief sought is conditional and does not seek to
interfere with the respondents rights
on a permanent basis. The
second type is in the nature of a permanent interdict against
particular uses of Erf 220. It is not sought
conditionally. The
relief is final in nature and whether it should be granted or refused
turns upon the proper construction of
the provisions of the KwaDukuza
Land Use Management Scheme (the “Scheme”).
THE
FACTS
[6] In
giving an account of the facts I will as far as possible confine
myself to the essentials.
[7] In
May 2019 the applicant approved building plans for what it describes
as a “warehouse type building”
on Erf 220. The
applicant’s papers do not disclose what features of the
building or the plans cause it to describe the building
as of a
“warehouse type”. It seems likely that the label flows
from the fact that the plans depict a steel frame mode
of
construction. However the respondents point out that the resolution
of the first respondent which was required to be submitted
with the
plans referred to an intention for the property to be used as a
hardware store, a fact which was confirmed by a sign board
erected by
the first respondent on the boundary of the property indicating its
intended use as a hardware store, which sign would
have been visible
to municipal officials throughout the building period.
[8] In
September 2019 a building inspector employed by the applicant, Mr
Nkwakhwa was passing Erf 220 and noticed
that earthworks were
underway. He saw that they had reduced the ground level of Erf 220 to
“considerably below” the
level of adjacent properties.
But he did not regard it at that stage as unusually dangerous.
[9] On
15 October 2019 Mr Nkwakhwa conducted an inspection and claims to
have established that the earthworks on
Erf 220 had undermined the
property and a building on the adjacent Erf 221. He claimed to have
seen a collapsed wall, but the respondents
deny that any wall had
collapsed.
[10] The
applicant’s Manager : Building Control, Mr Vilakazi, inspected
the site on 15 October 2019. The
approved plans make no provision for
retaining walls, but that physical inspection made it clear that such
would be necessary.
Mr Vilakazi prepared a report for submission to
the applicant’s Economic Development Planning Portfolio
Committee which would
apparently be considered on 30 October. The
concerns he noted regarding the site were of two types, one
concerning work place safety
and the other the unretained excavated
embankment which had been created towards the rear of Erf 220. Mr
Vilakazi met with Mr T
Singh of JVT Consulting Engineers (Pty)
Limited later on 15 October 2019 when the former requested the latter
to produce a remedial
action report and the proposed design of the
retaining wall. It was noticed that on 21 October 2019 construction
work had resumed
on the site but that at that stage the required
designs had not been received. The respondents’ account of the
meeting of
15 October 2019 is somewhat different. It is to the effect
that the applicant’s officials placed the blame for the
conditions
then prevailing in a rainy season on the owners of the
neighbouring properties who had consistently failed properly to
control
storm water run-off from their properties. According to the
respondents the wall which the applicant’s officials regarded
as having collapsed had in fact been taken down in a controlled
manner on the instruction of the first respondent’s engineer,
because of the excessive flow of storm water from the higher
properties onto Erf 220. As I understand the explanation, the
engineer’s
view would have been that the wall would have
collapsed, perhaps in a dangerous fashion, if it was not removed, as
it could not
withstand the pressure from the water emanating from the
higher neighbouring properties. According to the respondents it was
agreed
at the meeting of 15 October 2019 that the first respondent
could construct a wall to retain its rear boundary.
[11] According
to the principal founding affidavit (attested to by the applicant’s
Director: Development
Enforcement, Mr F R Naidoo), the applicant’s
approach to the matter following the inspection of 15 October 2019
was as follows.
“
The
unstable excavation required urgent or emergency intervention. In
part because the second respondent represented that an engineer
has
been appointed, the applicant did not issue a “stop work”
notice, nor did it insist on building plans for a retaining
wall
being approved before further work, but rather issued a notice of
violation which was meant to compel the respondents to remedy
the
situation.”
[12] Jumping
ahead a little in time, the founding affidavit (attested to on 13
December 2019) states in part explicitly,
and in part by implication,
that the claim by the respondents that the required retaining
structures were to be dealt with by an
engineer were too vague to be
relied upon, and that no engineer’s drawings had been received.
That assertion has been shown
to be false beyond doubt. The
engineer’s drawings for the retaining structures were sent to
Mr Vilakazi on 22 October 2019.
They did not feature in his report to
the council’s committee, despite the fact that when he asked
for them he did so because
he was preparing the report. Mr Vilakazi
signed a confirmatory affidavit which was delivered with the founding
papers. Copies of
the engineer’s drawings were put up with the
replying affidavit. It is not suggested that there is anything wrong
with the
design. Neither is there any explanation why the designs
were not dealt with in the founding affidavit. The drawings were sent
electronically, and Mr Vilakazi acknowledged receipt of them.
[13] According
to the founding papers further visits to Erf 220 were undertaken by
representatives of the applicant
on 13 November 2019, 6 December 2019
and 10 December 2019. The allegation is made that at these times the
retaining structures
had not yet been built. The site is said to have
been in a condition “essentially as it was previously”.
This characterisation
of the state of affairs upon Erf 220 in late
November 2019 and early December 2019 elicited what amounts to a bare
denial by the
respondents. There are however photographs of the
situation which obtained on the property at the time, and it is fair
to say that
what they reveal is that little if anything had been done
to execute the works which had been depicted in the design drawings
by
the engineer. A notice of violation delivered by the applicant to
the first respondent drew attention to the dangerous site conditions.
There was a further one on 6 December 2019 drawing attention to
occupation without a certificate (I will revert to this), and the
absence of approved plans and of adequate protection for the public.
On the same day (6 December 2019) the applicant gave notice
of an
intended prosecution for “operating a hardware (Build-Rite
Hardware)” on a site at which such use was prohibited.
[14] According
to the respondents the first time that the issue of plans for the
retaining structures was raised
was on 6 December 2019 when the
second respondent advised the applicant that plans could be submitted
on 7 December 2019. According
to the respondents this proposal was in
effect rejected because the applicant had already closed “for
plan submissions”
until 13 January 2020.
[15] According
to the respondents the principal issue at and around 6 December 2019
was the applicant’s contention
that the use of Erf 220 for a
hardware store was not in accordance with the scheme. The second
respondent pointed out that similarly
zoned properties in the town
accommodated hardware stores, but it does not seem that at that stage
the particular provisions of
the scheme relied upon by the applicant
were considered or debated.
[16] The
founding papers assert that on 6 December 2019, with the building
itself on Erf 220 still incomplete,
and no occupation certificate
having been issued, the building was being “stocked with
building materials and supplies, and
to this extent the respondents
have taken partial occupation by using the building. It was apparent
that they were intent on taking
full occupancy.” In the
answering affidavit it was contended that the first respondent was
not in occupation of the property
and certainly not trading there. I
do not understand the latter contention to be disputed. Neither party
has provided any particularity
regarding the extent to which any
items which might be regarded as the stock of a hardware store had
been placed in the building
on Erf 220 as at 6 December 2019.
[17] The
founding papers reveal that on 11 December 2019 the second respondent
visited Mr F R Naidoo and orally
undertook that the first respondent
would not take further steps with regard to occupying the building
without a certificate of
occupancy; and that the hardware store would
not be opened. Mr Naidoo asked for this undertaking to be given in
writing, but it
was not. Later on the same day Mr Naidoo saw an
advertisement in the local newspaper for the “grand opening”
of the
hardware store on 16 December 2019. The respondents explain in
answer that the advertisement was placed about a month prior to it
appearing, it having been anticipated at that time that the business
would open on 16 December 2019, and that the third respondent
simply
forgot to cancel the advertisement.
[18] The
next day (12 December 2019) at 13h03 a letter from the applicant’s
attorney’s (erroneously
dated 20 November 2019) was delivered
by hand to the second respondent. It drew attention to the proposed
opening on 16 December
2019 of an illicit hardware store, and the
construction of a retaining wall without building plans. The letter
continued.
“
In
the circumstances we are instructed to give you notice, as we hereby
do, not to allow occupation of the building or to commence
the
operation of a hardware store on the property. Unless you give us a
written undertaking to that effect by 4pm today (12 December
2019),
our instructions are to proceed to launch an urgent application in
the High Court on Tuesday, 17 December 2019 for an order
interdicting
you from doing so.”
The
first respondent replied by letter of 13 December 2019 delivered at
08h32.
“
Having
sought advice, we will not be opening the store on 16 December 2019
as advertised. There is accordingly no need for any unnecessary
urgent court application to be launched.”
[19] Notwithstanding
that, this application was launched on a founding affidavit dated 13
December 2019, and was
set down for 18 December 2019. Concerning the
undertaking which preceded the signature of the founding affidavit,
the deponent
to that document said that the “undertaking does
not mean that occupancy won’t be taken or that the store won’t
be opened after 16 December 2019 and does nothing to resolve the
problems of the dangerous excavation.”
[20] On
18 December 2019 the matter was adjourned to the unopposed roll of 27
January 2020 with directions as to
the delivery of further
affidavits. The respondents made certain undertakings, the ones which
remain material being the following.
(a)
An
affidavit from the engineer, Mr K Govender would be delivered
disclosing his qualifications and confirming that he would supervise
the construction of the retaining structures. That was to be done by
Monday, 23 December 2019.
(b)
Except
for completing the building works and for the continued storage of
building materials on site, there would be no further
occupation of
Erf 220 without a certificate authorising occupation.
(c)
There
would be no building work conducted on Erf 220 besides the
construction of the retaining wall either under the direct
supervision
of a certificated and licenced civil engineer in
accordance with the drawing which had been issued and supplied to the
applicant,
or in accordance with approved plans for those structures.
[21] Matters
took a turn for the worse with the delivery of the applicant’s
replying affidavit dated 20 January
2020. Mr F R Naidoo, speaking for
the applicant, asserted that the required affidavit from the engineer
had not been delivered.
He asserted that the respondents’ case
was “entirely undermined by their failure to comply with the
undertaking recorded
to court to provide the affidavit from the
engineers.” That central premise was false. In turns out that
the affidavit required
had been delivered on 23 December 2019 by
email. It had gone to the central email of the applicant’s
attorneys and unfortunately
had not reached the attorney dealing with
the case.
[22] A
new case was sought to be made, or certainly new material was sought
to be placed before the court, in that
replying affidavit. It was
asserted that as a matter of fact the work was not being done in
accordance with the engineer’s
drawings which were now
acknowledged to have been received in October 2019. It was asserted
that the deviations from the construction
drawings signified a danger
to the public. Accordingly the applicant claimed a right to interim
relief on 27 January 2020 when
the case was to feature on the
unopposed motion roll. On 27 January 2020 the third respondent
attested to a short affidavit opposing
the grant of any urgent
relief. Besides confirming the applicant’s error in believing
that the first respondent had not complied
with the undertaking to
deliver the engineer’s affidavit by 23 December 2019, the
affidavit objected to the short notice
given of the intention to seek
such relief, asserting that the matter was not urgent. The
respondents also relied on another affidavit
by the engineer, Mr K
Govender, who attested to the fact that he was overseeing the
activities on Erf 220, that the construction
of the retaining wall
was being supervised by him, and that what was there did not pose any
danger to members of the public or
construction personnel on site. He
gave an undertaking irrevocably and unconditionally to comply with
the first respondent’s
undertaking by continuing to supervise
the construction of the retaining wall, and to copy written
instructions and drawings issued
by him to the applicant.
[23] In
the event interim relief essentially in accordance with the
undertaking originally recorded was granted
on 27 January 2020. I do
not know in what circumstances the order was made.
SUBSEQUENT
EVENTS
[24] Later
on the first respondent delivered an affidavit to support a
counterclaim that it should be entitled
to run a “wholesale
hardware shop” on Erf 220. The affidavit set out the argument
for the proposition, and again made
reference to the fact that
similar businesses are conducted under the same zoning controls
elsewhere in the town. Accordingly the
issue of the proper
construction of the scheme is the subject of both a request for a
permanent interdict by the applicant, and
a favourable declaratory
order by the first respondent. I will turn to that issue as the final
one.
[25] The
applicant otherwise asks that the interim relief granted on 27
January 2020 be made final. The respondents
argue that no such relief
should be granted to the applicant, essentially on the basis that the
papers reveal that the application
should never have been launched,
and that there was no need for the interim relief granted on 27
January.
[26] I
assume that the delay in what followed is largely attributable to the
breakdown in administrative and court
performance as a result of the
pandemic which swept through our country after 27 January 2020. The
first respondent complains that
when it asserted that its works were
complete, the applicant failed to conduct the requisite inspection in
order to determine whether
an occupation certificate could be
granted. The first respondent launched a separate application to
compel compliance with those
obligations of the applicant. I am told
that there was subsequently such an inspection and that the applicant
declined to certify
the building ready for occupation. The issue as
to why that was done, and whether it was lawfully done, is not before
me. The result,
however, is that the apparently complete building
(and completed retaining structures) are in place, but the building
remains unoccupied.
THE
CONDITIONAL INTERDICTS REFERRED TO IN PARAGRAPH 4 (a) and (b) ABOVE
[27] These
interdicts are in essence the subject of the interim orders made on
27 January 2020. Although counsel
for the applicant, Mr
Goddard
SC
,
asked that final orders should be made along the lines of the interim
ones of January 2020, I did not understand him to contradict
the
proposition that as matters stand, there is little or no reason to
suppose that the interdictory relief would now have any
purpose.
Matters concerning Erf 220 are presently being dealt with as the law
requires, and there is no evidence of the first respondent
having
extended or threatened to extend the level of so-called “occupation”
of the building which the applicant sought
to interdict in the
original founding papers in December 2019.
[28] In
my view the position is that the factual analysis I have been
compelled to set out in this judgment is
relevant only to the
questions of costs which the parties have asked me to decide. I
approach that issue upon the footing that
there is certainly no need
now for any final relief along the lines of the interim relief
granted in January 2020.
[29] Some
of my views which have a bearing on costs have already been dealt
with or expressed in the course of
furnishing an account of what has
transpired in this matter. I think particularly of the applicant’s
initial attempt to present
a case for the proposition that whilst it
was satisfied that it was in order for the retaining structures to be
built in accordance
with a design and under the supervision of an
engineer, the first respondent was proceeding otherwise than with
such supervision
without submitting engineering designs to the
applicant. Mr
Aboobaker
SC
,
who appeared for the respondents, has argued that what this evidences
is an unnecessary rush to court.
[30] On
the other hand, the photographs of the site put up in the papers
illustrate that there was indeed a dangerous
situation which, it is
common cause, required remedial work in the way of retaining
structures. I am unimpressed with the first
respondent’s more
or less bare denial of the fact that little if anything had been done
to implement the engineering designs
by mid-December. Such dangerous
circumstances justifiably induce a sense of anxiety in municipal
officials who are responsible
for seeing to it that there is
compliance with the laws which require that construction work be
carried out safely.
[31] Whilst
the applicant’s missteps (failing to disclose the submission of
engineering drawings and asserting
the non-delivery of an engineer’s
affidavit by 23 December 2019) were material, so too is the fact that
it is clear on these
papers that the first respondent did not take
the unsafe conditions on its site as seriously as it ought to have
done. I find that
the first respondent’s contention in its
papers, that in fact the unsafe conditions must be laid at the door
of the owners
of the adjacent properties, is contradicted by the
first respondent’s acceptance of its own responsibility to
build retaining
structures. The photographs in the papers illustrate
that the excavations undertaken on Erf 220 had the effect of
undermining whatever
lateral support was previously in place on Erf
220 for the benefit of adjacent properties.
[32] I
do not think that the fact that matters have subsequently been
brought into conformity with the law relating
to such works (eg the
subsequent approval of plans for the retaining works which have
actually been constructed) establishes that
the first respondent was
“in the right”, and I did not understand Mr
Aboobaker
SC
to argue otherwise.
[33] I
conclude that it is possible, but not necessarily so, that if this
litigation had not been instituted the
first respondent would have
brought its works into conformity with the law in much the same way
as matters turned out during the
course of litigation. However it
strikes me that the applicant litigated in performance of its public
duty, even if one can see
that more determined efforts on the part of
the applicant to engage with the first respondent might have avoided
the need for litigation.
[34] Both
parties were at fault in connection with their conduct “on the
ground” and this litigation.
I conclude that there should be a
more nuanced costs order than is customary, a subject I will deal
with at the end of this judgment.
THE
ZONING ISSUE
[35] The
parties prepared a joint statement of issues in dispute and to be
dealt with at the hearing. They define
the zoning issue as follows.
‘
Whether
a “builder’s hardware shop” alternatively a “tile
and décor” store as proposed by the
respondents is
permitted or prohibited by the provisions of the KwaDukuza Land
Management Scheme and whether the interdict sought
by the applicant
or the relief sought by the respondent should accordingly be granted,
and associated costs.’
Both
parties prepared more detailed heads of argument on the zoning issue
for the purpose of the hearing. Whilst their argument
over the
material already discussed above took a little time as it involved an
analysis of the facts and how the litigation unfolded,
the zoning
issue was ultimately the most important one as, if the applicant was
correct in its contentions, the building on Erf
220 could never be
employed for its intended purpose.
[36] Erf
220 is zoned “Mixed Core Use 3 (MUC3)”. The scheme lists
(a) freely
permitted uses for Zone MUC3 under the headings “Environment
and Recreation”,
“Commercial”, and “Industrial”;
(b) uses
in the zone which may be sanctioned by municipal consent.
The
building and land uses not appearing in either part of the table of
uses are prohibited.
[37] A
“shop” is listed under the “Commercial”
heading in the table of freely permitted
uses. A warehouse and a
wholesale shop are the two entries in the table of freely permitted
uses under the heading “Industrial”.
[38] The
first respondent intends the building on Erf 220 to be used as a
hardware shop. A hardware shop is a shop.
A shop is a permitted use.
It does not appear to me to matter, when considering the dispute,
whether one regards the hardware shop
as a “
builder’s
hardware shop” or a “wholesale hardware shop” (a
term also used by the first respondent to identify the intended
use).
Describing the proposed enterprise as a “wholesale”
enterprise simply puts it under the industrial heading in
the list of
permitted uses, whereas it would fall under the commercial heading
“shop” in the list of permitted uses
if described as a
hardware shop for builders.
[39] The
applicant seeks to avoid this analysis of matters by referring to the
use “builders supply yard”
which features in the scheme.
That use is defined. It means “premises which is used for the
storage or sale of building material
and equipment”. The first
respondent claims no right to use any of the vacant land around its
building on Erf 220 for the
storage or sale of building material and
equipment. The applicant argues that the word “premises”
includes buildings,
and accordingly that a hardware shop falls within
the definition of a builder’s yard because such a shop
inevitably stocks
and sells material and goods and equipment which
can and are used in the building industry. Accordingly, argues the
applicant,
although a hardware shop may be a shop, it is of a
specific type which falls within the prohibited use “builder’s
supply
yard”. The applicant seems quite insensitive to the
question as to whether this is a sensible construction or an
insensible
misconstruction of the relevant provisions of the scheme.
[40] Counsel
for the applicant has argued with reference to
Natal
Joint Municipal Pension Fund v Endumeni Municipality
2012
(4) SA 593
SCA at paragraph [18] that any contrary interpretation of
the scheme must be one which fails to attribute meaning to the words
of the scheme, fails to identify the mischief the scheme is aimed to
prevent and which involves impermissibly ignoring the duty
to
interpret all the words in the scheme relevant to the enquiry. In my
view there is no merit in these arguments.
[41] The
word “premises” can, depending on context, mean land or
buildings or both land and buildings.
The applicant argues that the
word “premises” in the present context must mean land and
buildings, primarily, as I
understand the argument, because use zones
and the like apply to both the use of land and of buildings on the
land. I think that
as a generalisation this argument is correct.
[42] However
if it is obvious that the word “premises” is being used
with respect to what might be
called “open land” –
land not built upon in the ordinary sense of that word (ie enclosed
by walls and covered
by a roof) - can one say that the use of the
word “premises” brings about that for the purpose of the
provision in
question, a building must be regarded as “open
land”? I think not.
[43] The
definition upon which the applicant relies is a definition of a
“yard”. I know of no use of
the word “yard”,
certainly in the ordinary language I have come across, which conveys
that a building (properly so-called)
can be regarded as a “yard”.
[44] The
Oxford South African Concise Dictionary gives the primary meaning of
the word “yard” as
‘
a
piece of uncultivated ground adjoining a building, typically one
enclosed by walls → an area of land used for a particular
purpose or business:
a
builder’s yard
.’
When
one speaks of one’s “back yard”, the term denotes a
piece of undeveloped land to the rear of a dwelling –
that is
to say on the opposite side of the house to the road frontage. It is
ordinarily delineated by the property boundaries and,
in South Africa
in any event, also by a fence or wall. It is a common term. It always
denotes land uncovered by roofing, although
not necessarily enclosed
by walls as suggested in the dictionary definition.
[45] Counsel
for the applicant argues that these observations regarding the
ordinary use of the word “yard”
cannot affect the meaning
of the word “premises” where it appears in the definition
of a “builder’s yard”.
As I understand the argument
it is that the word “premises” appears as part of the
defining element. It determines
what “yard” means. The
use of the word “yard” does not determine what the word
“premises” means.
I appreciate the logic of that
argument, but it cannot be carried so far as to bring about that the
thing which is the subject
of the definition ceases to be what we all
know it is. To give an example: if a drafter is silly enough in the
rules of a sectional
title scheme to define the word “cat”
as a four-legged domesticated animal, and then records that cats are
not allowed
within the boundaries of the scheme, is it logical to
then conclude that dogs are also not allowed because they are
four-legged
domesticated animals, despite the fact that they are not
cats?
[46] In
my view the answer lies in appreciating the purpose of the defining
words in the definition relied upon
by the applicant. The purpose of
the definition is not to define what a yard is. It is to establish
what the term “builder’s
supply yard” means, as
opposed to any other yard. The definition is aimed at the use of the
yard “for the storage or
sale of building material and
equipment”. The use of the word “premises” in the
definition is merely incidental,
and it makes no sense to regard the
word as bringing about that a “builder’s supply yard”
may not be a yard at
all.
[47] A
hardware shop is all about the business of selling of goods. Some of
them will undoubtedly be building material
and equipment. Bearing in
mind the wide range of goods which are to be found in any ordinary
hardware shop, much of which could
be regarded as items or material
used in or in the course of building work (from, for instance, nails
and hammers through to a
pocket of cement), and given the
self-evident popularity of, and the need of ordinary people
(non-builders) to access, the materials
and tools and the like sold
in a hardware shop, it is wrong to give the excluded use (builder’s
supply yard) so broad a meaning
as to exclude the operation of a
hardware shop inside a building on a property governed by a zoning
such as that attributed to
Erf 220.
[48] Builder’s
supply yards, being open land and normally quite large pieces of
land, can accommodate the
storage and sale of industrial scale
quantities of such items as sand, stones, bricks and so on, and
therefore attract a significant
flow of industrial type traffic in
the way of heavy vehicles both delivering materials to the yard and
picking material up from
the yard for delivery to building sites.
That sort of traffic generation and activity would be a considerable
obstacle to the enjoyment
of the public amenities which are supposed
to be available in an area zoned MUC3. The level of storage and trade
- generated interference
with public amenities by a facility such as
a hardware shop contained within a building cannot be compared to
that generated by
a builder’s yard.
[49] I
accordingly conclude that the applicant’s contention with
regard to whether the proposed use of Erf
220 is permissible under
the scheme is wrong, and that the counter application must succeed.
[50] In
KwaDukuza
Municipality v Stangvest Investments (Pty) Limited and Others
,
case number 1006/2019 in this Division, Kruger J reached the same
conclusion as I have on the zoning issue raised in this case.
The
applicant argued that I should not regard myself as bound to follow
that decision as it was clearly wrong and not supported
by the
reasons given for it by the learned Judge. I have, on the contrary,
decided that the conclusion reached in
Stangvest
Investments
was
correct.
COSTS
[51] In
dealing with the issue of costs I will not repeat the considerations
I have already identified as relevant
to the enquiry. The general
rule that costs follow the result is sometimes a blunt instrument. In
this case the employment of that
general rule is difficult with
regard to the relief summarised in paragraphs 4 (a) and (b) of this
judgment. No final order has
been made in favour of the applicant. It
is arguably so that this outcome is the product of the passage of
time, and the events
on the ground during that passage of time,
between when the interim order was made in January 2020 and the
presentation of the
case to court for a final decision.
[52] The
basic principle which underlines all orders for costs, even when the
order simply follows the result or
outcome of the case, is that the
court has a discretion which must be exercised judicially upon a
consideration of all the facts.
As between the parties “in
essence it is a matter of fairness to both sides”. (See
Ward
v Sulzer
1973 (3)
SA 701
(A) at 706.)
[53] In
my view it is fair to say that the order granted on 27 January 2020
evidences substantial success on the
part of the applicant up to that
date in its pursuit of the relief set out in paragraphs 4 (a) and (b)
of this judgment. Although
some costs were incurred in respect of
those two issues after January 2020, the central issue since then has
been the zoning issue
on which the applicant has not achieved
success. Just as costs were incurred before and after January 2020 on
the issues set out
in paragraphs 4 (a) and (b) of this judgment, so
too were costs incurred before and after January 2020 in connection
with the zoning
issue.
[54] I
take the view that in considering what is fair in circumstances like
the present a court should be aware
and take account of the
complications which may arise in the taxation of costs. Mr
Aboobaker
SC
has asked that
the first respondent should be allowed all costs incurred in respect
of the zoning issue. That would entail extracting
drafting and
perusal costs from the founding and answering papers and an argument
over how much of the costs which post-dated January
2020, especially
those incurred in connection with the preparation for and
presentation of argument before me, is attributable
to the zoning
issue. In my view fairness to the parties, and between the parties,
dictates that such debates should be avoided
as far as possible. It
is better simply to fix a date up to which the costs in the main
application will be paid by the first respondent;
after which date
the costs in the main application must be borne by the applicant.
[55] The
same problems do not seem to me to arise in connection with the
counter application, as it post-dated
January 2020.
[56] I
accordingly formulate the order for costs as fairly as I can manage
applying the above principles.
I
make the following order.
1.
(a) The
application against the second and third respondents is dismissed.
(b) The
applicant shall pay such additional costs as may have been incurred
by the inclusion of the second and
third respondents as parties to
the litigation.
2.
The
order of 27 January 2020 is discharged.
3.
(a) The
application for the interdict set out in paragraph 2 (c) of the order
prayed in the notice
of motion is dismissed.
(b) The
counter application is granted in the following terms.
“
It
is declared that the Core Mixed Use (MUC 3) zoning currently applied
to Erf 220, CBD Stanger situate at 63 Balcomb Street, KwaDukuza
permits the operation of a wholesale hardware shop or hardware shop
within a shop building situate on the said Erf 220.”
(c) The
costs of the counter application shall be paid by the applicant.
4.
As
to the costs of the main application not already dealt with in
paragraph 1 of this order,
(a)
those
incurred up to and including 27 January 2020 shall be paid by the
first respondent; and
(b)
those
incurred after 27 January 2020 shall be paid by the applicant.
OLSEN
J
APPEARANCES
Date of
Hearing: 26
and
27 May 2021
Date of
Judgment: Thursday,
12 August 2021
Plaintiff’s
Counsel: Mr
G D Goddard SC
Instructed
by: Shepstone
& Wylie Attorneys
Applicant’s
Attorneys
24
Richefond Circle
Ridgeside
Office Park
Umhlanga
Rocks
Durban
(Ref:
V Nkosi/kwad7135.852)
(Tel:
031 – 575 7000)
(Email:
douglas@wylie.co.za
smkhize@wylie.co.za
)
Defendants’
Counsel: Mr TN
Aboobaker SC with Mr B Houston
Instructed
by: Amod’s
Attorneys
Respondents’
Attorneys
Suite
900, Nedbank House
Durban
(Ref:
AA/ps/G111/20001)
(Tel:
031 – 307 7862)
(Email:
admin2@amodsattorneys.co.za
)