Dolce Domus CC v Herholdt and Another (742/2021) [2022] ZAECPEHC 5 (24 February 2022)

80 Reportability
Contract Law

Brief Summary

Contract — Sale of immovable property — Dispute regarding cancellation of sale agreement — Applicant seeks order for transfer of property following alleged compliance with contractual obligations — First respondent claims valid cancellation due to applicant's breach — Legal issue revolves around the validity of the cancellation and the applicant's compliance with the agreement — Court held that the applicant's late provision of a guarantee constituted a breach; however, the first respondent did not validly cancel the agreement prior to the application, thus the applicant is entitled to seek specific performance for the transfer of the property.

Comprehensive Summary

Summary of Judgment


1. Introduction


The proceedings were an application for specific performance arising from a written agreement of sale of immovable property, coupled with a counter-application seeking a declarator of cancellation (or, alternatively, cancellation) of that agreement. A further interlocutory dispute arose from the first respondent’s application to strike out substantial portions of the applicant’s affidavits as allegedly irrelevant or impermissibly argumentative.


The applicant was Dolce Domus CC (the purchaser). The first respondent was Elmarie Herholdt (the seller). The second respondent was the Registrar of Deeds, King Williams Town, cited in relation to the transfer process.


Procedurally, the applicant launched the application in March 2021 seeking an order compelling the first respondent to sign transfer documents and take all steps necessary to transfer the property into the applicant’s name. The first respondent opposed the relief, asserted that the contract had already been cancelled, and brought a counter-application seeking confirmation of cancellation (or cancellation in the alternative). She additionally brought an application to strike out various portions of the applicant’s founding and replying affidavits.


The general subject matter of the dispute was whether, notwithstanding the purchaser’s substantial delay in furnishing a bank guarantee, the seller had validly cancelled the sale agreement (or could still cancel it), or whether the purchaser remained entitled to enforce the agreement and compel transfer.


2. Material Facts


On 27 December 2019, the parties concluded a written sale agreement in terms of which the first respondent sold Erf 223 Newton Park to the applicant for R2.3 million, payable upon transfer. Clause 1.2 permitted the purchaser, as security for payment, to furnish a bank/financial institution guarantee within a specified period, and clause 1.2.1 required that the guarantee be “irrevocably expressed” and immediately payable upon written notification of registration of transfer. The applicant’s conveyancers were Glyn Marais Incorporated.


An inspection contemplated in clause 16.3 occurred on 31 January 2020 (outside the 30-day period, but the court recorded that nothing turned on this). During February and March 2020, the parties completed transfer-related documentation: the first respondent on 12 February 2020 and the applicant on 12 March 2020.


It was common cause that the applicant did not furnish a bank guarantee within the period contemplated by clause 1.2. Following this, on 30 March 2020 the first respondent’s attorneys (Slabbert Attorneys) addressed a letter to the applicant giving notice of breach based on failure to comply with clause 1.2, demanding delivery of acceptable guarantees or payment of the purchase price within seven days.


The subsequent communications occurred against the background of the declared National State of Disaster and lockdown restrictions due to Covid-19, which the applicant invoked as a reason to seek suspension while assessing business impact. Correspondence in May 2020 reflected that the seller’s attorneys still regarded the purchaser as in breach and sought instructions and a response, but no clear evidence of a communicated election to cancel emerged from that period.


The first respondent alleged that the agreement was later cancelled by an email sent by her husband (acting as agent), but no copy of the alleged cancellation email could be produced, allegedly because the relevant computer data could not be retrieved. The applicant and staff at Glyn Marais denied receipt of any notice of cancellation. The first respondent relied instead on inferential reliance from later correspondence concerning return of the original title deed and later references indicating the seller no longer wished to sell.


On 1 December 2020, the applicant obtained an Investec bank guarantee, and on 2 December 2020 it was furnished to Slabbert Attorneys. On 9 December 2020, Slabbert Attorneys responded, enclosing an email from Mr Herholdt stating that the guarantee was more than a year late, that the first respondent no longer wished to sell, and that the title deeds had been returned.


In the first respondent’s answering affidavit (which also served as founding affidavit in the counter-application), she raised an additional defence that the Investec guarantee did not comply with clause 1.2.1 because it was not “irrevocably expressed.” As an alternative basis, she purported to give (further) written notice in terms of clause 12 (the default clause) calling upon the applicant to comply, failing which the agreement would be cancelled.


In reply, the applicant procured and delivered a further guarantee dated 13 May 2021 that expressly stated it was irrevocable, and indicated that this guarantee replaced the first. The first respondent then launched an application to strike out substantial portions of the applicant’s affidavits, largely on the premise that the “replacement” guarantee rendered references to the first guarantee irrelevant and that the new guarantee constituted a new case in reply.


3. Legal Issues


The court was required to determine, centrally, whether the sale agreement had been validly cancelled by the first respondent, either through an alleged communicated cancellation following the purchaser’s breach, or through acceptance of an alleged repudiation. This required a determination of the legal requirements for cancellation (including election and communication) and whether those requirements were met on the evidence.


A related legal issue was whether the applicant’s late furnishing of a bank guarantee could nonetheless cure the breach, and whether any alleged non-compliance in the terms of the guarantee (specifically the absence of an “irrevocable” expression) entitled the first respondent to treat the breach as continuing without further notice, or whether it constituted a further breach requiring a fresh notice procedure under the contract.


A further issue concerned the procedural and evidential question whether the first respondent had raised a genuine dispute of fact sufficient to prevent final relief on motion in relation to cancellation, including the application of principles concerning the treatment of disputes of fact in motion proceedings.


Finally, the court had to decide the application to strike out, which turned on questions of relevance, whether a new case was made in reply, and whether any prejudice was established.


These issues involved a combination of law, the application of law to fact, and evaluative judgment on whether the evidential material sufficed to discharge the onus resting on the first respondent to establish cancellation.


4. Court’s Reasoning


The court first addressed the strike-out application. It characterised the first respondent’s core premise—that because a later guarantee “replaced” the earlier one, the earlier guarantee “no longer exists” and all references to it were irrelevant—as logically fallacious. The court drew a distinction between the factual existence of the earlier guarantee and its potential legal effect or continued utility as security. The replacement did not erase the earlier document’s factual existence, nor did it automatically determine whether the purchaser had complied with its contractual obligations at any relevant time.


The court further reasoned that the later guarantee (of 13 May 2021) was furnished in response to a ground advanced in the counter-application, namely that the earlier guarantee itself did not comply with clause 1.2.1 because it was not “irrevocably expressed.” On the court’s view, the applicant was entitled to meet that case, and providing a guarantee addressing the objection did not amount to impermissibly making out a new case in reply. The court accepted (without deciding) that certain passages of the replying affidavit were argumentative, but held that the first respondent had not established prejudice. The strike-out application was therefore dismissed, with a punitive costs order due to its lack of merit.


Turning to cancellation, the court treated it as decisive that, even where a party is entitled to cancel due to breach, cancellation is not automatic. The aggrieved party must elect to cancel and must communicate that election to the defaulting party. The court held that the first respondent bore the onus to establish that cancellation occurred by proper notice.


On the facts, the first respondent’s evidence of cancellation was materially deficient. The alleged cancellation email could not be produced; no details were provided as to when it was sent, to whom it was addressed, or why it would have been sent by the husband rather than by the instructed attorneys who had already issued the breach notice. The court noted substantial gaps in the narrative after the May 2020 correspondence from Slabbert Attorneys, which had indicated that they would advise their client on exercising rights. The court found it unexplained why a cancellation would not then have been clearly effected through those attorneys, and why the alleged cancellation later occurred via an email by the husband.


The first respondent attempted to rely on inferences drawn from later correspondence (including the title deed being returned and communications suggesting a new sale discussion). The court held that the inferences did not establish effective cancellation, particularly given that, when the guarantee was later delivered in December 2020, the response did not clearly assert a prior cancellation; instead, it emphasised lateness and unwillingness to sell. The court did not accept that the available correspondence compelled the conclusion that a cancellation had been communicated to the purchaser.


In evaluating whether a genuine dispute of fact existed regarding cancellation, the court relied on the approach in Wightman t/a J W Construction v Headfour (Pty) Ltd and Another concerning the need for a party raising a dispute to seriously and unambiguously engage with the disputed facts. The court emphasised that important contextual facts within the first respondent’s knowledge were not addressed. This supported a robust approach to the alleged factual dispute and reinforced the conclusion that the onus to prove communicated cancellation was not met.


The court also rejected the repudiation-based defence on the same foundational basis. Even if the purchaser’s ongoing non-performance could be treated as repudiation, the seller still had to accept the repudiation by electing to cancel and communicating that election. The court held that this was not established on the evidence.


The court then considered the first respondent’s alternative reliance on the alleged defect in the terms of the December 2020 guarantee. The court reasoned that the original breach notice required the applicant to deliver “acceptable guarantees” or pay the purchase price into trust. The delivery of the Investec guarantee, as a factual matter, cured the specific breach identified at that stage, namely the failure to furnish any guarantee within time. If the guarantee was not “irrevocably expressed” or not in a form acceptable to the seller under clause 1.2.1, that could amount to a further breach, but it could not be ignored as though no guarantee had been furnished at all. On the court’s approach, such a further breach would require the seller to follow the contractual notice procedure before becoming entitled to cancel on that ground.


The court noted that the first respondent in fact attempted to do precisely this by giving notice in the counter-application based on the alleged non-compliance of the guarantee’s terms. However, the court considered this stance inconsistent with the primary case that the agreement had already been cancelled earlier, and it regarded this inconsistency as reinforcing the conclusion that no prior cancellation had been proved.


Finally, the court held that once the first respondent’s notice regarding the “irrevocable” wording was raised, the applicant was entitled to remedy the alleged breach. The applicant did so by delivering the second guarantee dated 13 May 2021, expressly framed as irrevocable. The court held that this cured the alleged further breach within the operative notice framework, with the consequence that the first respondent was not entitled to cancel on that basis.


Having found that cancellation was not proved and that the counter-application failed, the court concluded that the applicant was entitled to the relief compelling transfer.


On costs, the court held that the usual rule that costs follow the result applied to the main dispute, but that the strike-out application warranted punitive costs because it was founded on fallacious reasoning and lacked substance and merit. The court emphasised that punitive costs are a mark of disapproval of litigation conduct, not a sanction for mere lack of success.


5. Outcome and Relief


The court dismissed the first respondent’s strike-out application and ordered costs on the scale as between attorney and client in relation to that interlocutory application.


The court dismissed the first respondent’s counter-application with costs.


The court granted the applicant substantive relief compelling the first respondent to take all steps necessary to effect transfer of Erf 223 Newton Park to the applicant, including obtaining municipal rates clearance certificates contemplated by section 118(1) of the relevant statute and obtaining electrical compliance certificates for the seven dwelling units in accordance with the applicable regulations.


The court ordered the first respondent to appoint a conveyancing attorney within five days, failing which the applicant could appoint Glyn Marais Incorporated to prepare the transfer documentation. The first respondent was directed to sign all documents within 14 days, failing which the Sheriff was authorised to sign and take necessary steps on her behalf to effect transfer.


The first respondent was ordered to pay the costs of the main application (in addition to the separate punitive costs order for the strike-out application and the costs order on the counter-application).


Cases Cited


Plascon-Evans (Pty) Ltd v Van Riebeeck Paints (Pty) Ltd [1984] (3) SA 623 (A).


Wightman t/a J W Construction v Headfour (Pty) Ltd and Another [2008] ZASCA 6; 2008 (2) SA 371 (SCA); [2008] 2 All SA 512 (SCA).


Tuckers Land and Development Corporation (Pty) Ltd v Hovis 1980 (1) SA 645 (A).


Ponisamy and Another v Versailles Estates (Pty) Ltd 1973 (1) SA 372 (A).


Salwedle v Roath 1956 (2) SA 160 (E).


Legislation Cited


Disaster Management Act 57 of 2002.


Local Government: Municipal Systems Act 32 of 2000 (section 118(1)).


Occupational Health and Safety Act 85 of 1993.


Rules of Court Cited


No rules of court were cited in the judgment.


Held


The court held that the first respondent did not discharge the onus of proving that the agreement of sale had been cancelled, because effective cancellation required a clear election and communication of cancellation to the applicant, and the evidence did not establish that such notice was delivered.


The court further held that the applicant’s late delivery of a bank guarantee cured the initial breach identified in the earlier breach notice, and that any alleged defect in the guarantee’s wording (particularly the absence of an express “irrevocable” formulation) could at most constitute a further breach requiring proper notice and an opportunity to remedy. Once that issue was raised, the applicant remedied it by delivering a second guarantee expressly irrevocable, with the consequence that the first respondent was not entitled to cancel on that ground.


The court held that the strike-out application was without merit and justified punitive costs. The applicant was granted orders compelling transfer, with mechanisms to ensure signature of documents and authorisation for the Sheriff to act if necessary.


LEGAL PRINCIPLES


A contractual entitlement to cancel for breach does not, without more, terminate the contract. Cancellation requires an election by the aggrieved party and communication of that election to the defaulting party, and the party asserting cancellation bears the onus of proving that effective notice of cancellation was delivered.


In motion proceedings, a party alleging a dispute of fact must seriously and unambiguously engage with the facts said to be disputed. A purported dispute that fails to grapple with material aspects within that party’s knowledge may not be treated as a genuine dispute sufficient to defeat final relief, consistent with the approach articulated in Wightman t/a J W Construction v Headfour (Pty) Ltd and Another.


Where a notice of breach requires a party to perform a specified obligation (such as furnishing a guarantee), subsequent performance may cure the particular default identified. If the form of performance is alleged to be non-compliant with contractual requirements, that may constitute a further breach, which ordinarily must be addressed through the contractual default mechanism (including notice and an opportunity to remedy) before cancellation may be invoked on that basis.


Punitive costs may be awarded to mark disapproval of litigation conduct where an application is lacking in substance and merit, and is founded on fallacious reasoning, even where punitive costs are not justified for the litigation as a whole.

About SAFLII
Databases
Search
Terms of Use
RSS Feeds
South Africa: Eastern Cape High Court, Port Elizabeth
SAFLII
>>
Databases
>>
South Africa: Eastern Cape High Court, Port Elizabeth
>>
2022
>>
[2022] ZAECPEHC 5
|

|

Dolce Domus CC v Herholdt and Another (742/2021) [2022] ZAECPEHC 5 (24 February 2022)

IN
THE HIGH COURT OF SOUTH AFRICA
(EASTERN
CAPE LOCAL DIVISION, GQEBERHA)
Not Reportable
Case
No: 742/2021
In
the matter between:
DOLCE
DOMUS
CC                                                                                   Applicant
AND
ELMARIE
HERHOLDT                                                                First

Respondent
REGISTRAR
OF DEEDS, KING WILLIAMS TOWN Second Respondent
JUDGMENT
GOOSEN
J:
[1]
The
applicant and the first respondent concluded a written agreement of
sale of an immovable property. The applicant seeks an order
directing
the first respondent to sign the transfer documents and to effect
transfer of the property into the name of the applicant.
[2]
The
first respondent opposes the transfer on the basis that she has
cancelled the sale agreement. The first respondent counter-applies

for a declarator that the agreement has been validly cancelled. In
the alternative, she seeks an order that the agreement be cancelled.

In addition, the first respondent seeks an order striking out large
sections of the applicant’s founding affidavit and replying

affidavit on the basis that the averments contained therein are
irrelevant.
[3]
In order to
appreciate the issues which require adjudication it is necessary to
set out the facts in some detail.
[4]
The
agreement, in terms of which the first respondent sold Erf 223 Newton
Park for the sum of R2,3 million was concluded on 27 December
2019.
The applicant was represented by Dean Colley who was authorised by
resolution of the applicant. The first respondent acted
personally.
The purchase price was payable upon transfer of the property. Clause
1.2 of the agreement reads:

As
security for the payment of the purchase price, the PURCHASER may
elect, within 30 days of acceptance of this offer by the SELLER
or 30
days after fulfilment of the special condition referred to in 16.3
(whichever is the later date), to either –
1.2.1   furnish the
PURCHASER’S Conveyancers with a Bank or Financial Institution’s
guarantee securing
payment of the Purchase Price. The guarantees
shall be irrevocably expressed to be immediately payable to the
SELLER on written
notification of the PURCHASER’S Conveyancers
of registration of transfer and in a form reasonably acceptable to
the SELLER;
or
1.2.2   make payment in
cash of an amount equal to the Purchase Price into the PURCHASER’S
Conveyancers trust
bank account and provide proof of payment thereof
to the SELLER.”
[1]
[5]
The
applicant’s appointed conveyancer is Glyn Marais Incorporated
(Glyn Marais). Clause 16.3 provided that the applicant conduct
an
inspection of the property “by no later than 30 days after both
parties have signed this offer”. In the event that
the
applicant was not satisfied with the outcome of the inspection, it
could notify the first respondent, whereafter the agreement
would
lapse.
[6]
It is
common cause that the inspection was conducted on 31 January 2020.
Although this was outside of the 30-day period provided
in the
agreement, nothing turns on this. On 12 February 2020, the first
respondent completed several documents
required
to give transfer of the property. Similar documents were completed by
the applicant on 12 March 2020.
[7]
On
24 March 2020, the first respondent’s husband (Mr Herholdt)
sent an email to Glyn Marais requesting them to notify the
applicant
that it is in breach of the sale agreement. The email does not state
in what respect the applicant was alleged to be
in breach. On 27
March 2020 Glyn Marais wrote to the first respondent advising that,
in light of the professional relationship
between the applicant and
Glyn Marais, it is conflicted. Glyn Marais advised the first
respondent to seek alternative legal representation.
[8]
On
30 March 2020 Slabbert Attorneys, representing the first respondent,
emailed Glyn Marais attaching the seller’s (first
respondent’s)
“written cancellation of his mandate with your office”.
The attached document, headed “CANCELLATION
OF MANDATE”
states that the first respondent

cancel[s]
and/or terminate[s] my mandate . . . with Glyn Marais Incorporated
regarding the transfer of my property . . . in terms
of the Deed of
Sale dated 27
th
of December 2019.”
It
further provided that any funds held in trust with regards to the
transaction must be paid over to Slabbert Attorneys
.
[9]
On the same
date, Slabbert Attorneys addressed a letter to the applicant in which
they gave notice of breach of the agreement. The
letter stated that
the applicant had failed to make payment of the purchase price as
provided in Clause 1.2 of the agreement. It
stated that:

We
have been instructed to demand, which we hereby do, that you deliver
acceptable guarantees or make payment of the full purchase
price . .
. to our trust account with 7 (seven) days from the date hereof,
failure of which the Seller’s rights are reserved
to institute
formal legal action for the recovery thereof and/or to claim damages
suffered due to your breach of contract.”
[10]
The events
which followed occurred against the background of a National State of
Disaster which was declared to combat the coronavirus
(Covid-19)
global pandemic.
[2]
Regulations
were promulgated to restrict the movement of persons and goods.
[3]
These regulations imposed a national lockdown in five distinct alert
levels. It is not in dispute that the lockdown imposed very

significant restrictions upon the movement of persons and goods and
caused disruptions of normal business and commercial activity.
[11]
The
applicant states that as a result of the national state of disaster,
it wanted to assess the impact the lockdown might have
upon its
decision to invest in the property. Accordingly, in response to an
email dated 6 April 2020 in which Slabbert Attorneys
advised that
said date was the last day for delivery of the guarantee, Glyn Marais
requested that performance in terms of the agreement
be suspended.
Slabbert Attorneys replied, also on 6 April 2020, that the applicant
remained in breach but that instructions were
awaited from the first
respondent. It was suggested that further communication occur after
16 April 2020.
[12]
On 6 May
2020 Slabbert Attorneys wrote to Glyn Marais placing on record that
no communication had been received since 6 April 2020.
The email
re-iterated the alleged breach of contract and required a response by
7 May 2020. On 12 May, a further email was sent.
It appears that Mr
Slabbert had been in telephonic contact with an assistant employed by
Glyn Marais. The email requested Mr Brian
Frank, who was dealing with
the matter at Glyn Marais, to respond to the earlier email.
[13]
On 13 May
2020 Mr Frank replied to the email dated 6 May. The reply was to the
effect that Mr Colley, of the applicant, would address
the issue
after the lockdown has been lifted. This elicited a response from
Slabbert Attorneys on 15 May 2020 in which an appeal
was made to
obtain telephonic instructions. The letter records the following:

Our
instructions are that there is a contract, with terms and conditions
and your client does not adhere to those conditions.
Your
client was placed on terms and at present he is in breach of
contract.
Our
client reserved his rights in full,
and
we now need to advise our client the way forward to exercise his
rights
.”
(emphasis
added)
[14]
No further
communication occurred until 8 September 2020. It is, however,
alleged that Mr Herholdt addressed an email to the applicant

cancelling the agreement. I shall return to this aspect later in this
judgment. On 8 September, the original deed of transfer in
respect of
the property and a copy of the plan was dispatched to the first
respondent. On 17 September 2020 Mr Herholdt sent an
email to a Ms
Nundlal at Glyn Marais under the subject title “Return of
Serene original title deed”. It stated that
it had been a month
since previous correspondence regarding the request, but that they
had still not received the title deed. Ms
Nundlal replied on 18
September enclosing confirmation of delivery. On 22 September, Mr
Herholdt confirmed that it had been received
but been mislaid.
[15]
On 5
October 2020 an email was sent to Slabbert Attorneys by Glyn Marais
under the subject title “E HEROLDT // DULCE DOMUS
CC ERF 223
NEWTON PARK”. It reads:

Our
Brian Frank has been trying to get a hold of you to no avail. He is
working from his farm in Mookgophang (Naboomspruit) and
has trouble
with his reception, as a result he is only able to make and take
calls on his mobile phone.
Mr
Frank would like to discuss the abovementioned matter with you and
would like to ascertain whether your client, would like to
entertain
our client’s offer.
Please
feel free to email Mr Frank who is copied herein or call him on his
mobile phone on . . .”
[16]
On 8
October 2020 Slabbert Attorneys replied as follows:

Sorry
to learn you find it difficult to get hold of us. Our phone numbers
have not changed, herewith the email address.
You
are welcome to contact our client directly as we have closed our file
in this matter.”
[17]
On 12
October, Slabbert Attorneys sent a further email. It reads:

We
refer to the abovementioned matter and the emails below.
Our
client is prepared to enter into discussions for the sale of his
property. However, he requests a NON-REFUNDABLE deposit of
R10 000
(TEN THOUSAND RAND) prior to any discussion.”
No
replying correspondence has been put up by the applicant in relation
to this exchange.
[18]
On 1
December 2020 the applicant obtained an Investec Bank guarantee as
security for payment of the purchase price. It was provided
to
Slabbert Attorneys under cover of a letter dated 2 December 2020. The
letter averred that the purported cancellation of Glyn
Marais’
conveyancing mandate was unlawful. In the light of the applicant’s
compliance with the terms of the agreement
of sale, it was indicated
that the transfer process was proceeding.
[19]
On 9
December 2020 Slabbert Attorneys responded, enclosing an email
received from Mr Herholdt. The email pointed out that the guarantee

was more than a year late; that the first respondent does not wish to
sell the property any longer, and that the title deeds had
been
returned to him.
[20]
The present
application was commenced in March 2021. The applicant’s case
is premised upon enforcement of the agreement of
sale. It alleges
that it has complied with its obligations, in particular that it has
furnished a guarantee as security for payment
of the purchase price
upon transfer. It is not in dispute that the aforementioned guarantee
was only furnished to the first respondent
on 2 December 2020
notwithstanding the requirement contained in clause 1.2 of the
contract. The applicant contends that although
it was in breach of
its obligations, the first respondent did not elect to cancel the
agreement and no notice of cancellation was
delivered to it. On this
basis the applicant, now having met its obligations, is entitled to
an order compelling performance in
accordance with the agreement.
[21]
The first
respondent’s case is, in the first instance, that the agreement
was cancelled. Notice of cancellation was dispatched
to the applicant
by way of an email written by Mr Herholdt. No copy of the email is
available, since the data cannot be retrieved
from Mr Herholdt’s
computer.
[22]
The first
respondent raises two additional defences. The first is that the
guarantee, belatedly furnished by the applicant, does
not comply with
clause 1.2 of the agreement since it is not “irrevocably
expressed”. The second is that the applicant,
by its ongoing
failure to comply with its obligations, repudiated the agreement.
This repudiation was accepted when the first respondent
insisted that
the titled deeds be returned.
[23]
As an
alternative the first respondent’s answering affidavit, which
served also as her founding affidavit in the counter-application
to
declare the agreement cancelled, contained the following averments:

12.17 Even if it is
accepted that by the time that the Investec Guarantee was furnished
there was not yet a cancellation or
a repudiation and acceptance (all
of which is denied), then and since the guarantee fails to comply
with the contract, the furnishing
thereof did not purge the
applicant’s mora and since I have at various stages complied
with the notice requirement in clause
1.2 of the agreement the
contractual right to cancel remained, which my husband as my agent,
through my attorney carried out as
set out in paragraph 8.12 of the
founding affidavit.
[4]
12.18  Further and in any
event, and even if there have never been a valid mora notice, nor
valid cancellation, nor repudiation
which was effective (all of which
are denied) I hereby give written notice in terms of clause 12 of the
agreement that the applicant
has failed to comply with clause 1.2 of
the agreement and that if it fails to properly comply with that term
of the agreement within
the period referred to in clause 12 that the
agreement will the, without further notice be legally cancelled. I
refer to my counter-application.”
[24]
As
indicated, the first respondent’s affidavit served a dual
purpose, namely as answer to the main application and as a founding

affidavit to the counter-application. The applicant’s reply
similarly served a dual purpose. The matters canvassed in reply
will
be addressed when dealing with the submissions made by the parties.
Insofar as the answer to the counter-application is concerned,
only
one aspect need be highlighted at this stage.
[25]
In response
to paragraph 12.18 quoted above, in which the first respondent gave
notice of her intentions to cancel the agreement
in terms of clause
12 thereof, the applicant obtained and presented a new letter of
guarantee dated 13 May 2021. The new letter
of guarantee expressly
stated that it is irrevocable. The covering letter stated that the
first guarantee is withdrawn and is replaced
by the second guarantee.
[26]
In response
to the filing of the applicant’s dual purpose replying
affidavit, the first respondent launched an application
to strike out
substantial portions of the applicant’s founding affidavit and
portions of the replying affidavit.
[27]
The
application to strike out portions of the founding affidavit and the
replying affidavit is premised upon three contentions.
Based upon the
fact that the applicant has put up a new Investec guarantee in
response to the first respondent’s alternative
claim for
cancellation and that this guarantee replaces the first guarantee,
the first respondent contends:
[1]       that
the first guarantee “no longer exists” and therefore
every allegation
referring thereto in the founding and replaying
affidavits is irrelevant and falls to be struck out.
[2]       that
the presentation of a new guarantee in reply amount to making out a
new case in
reply and for this reason all reference to the new
guarantee ought to be struck out.
[3]       that
there are some passages in the reply which are argumentative and
ought to be struck
out.
[28]
The first
two contentions amount to sophistry. At the heart of the argument
lies the assertion that the first guarantee has ceased
to “exist”.
The assertion is fallacious. It asserts the term “exist”
in a manner that is ambiguous and
thereupon equates it with the
notion of “validity” or “enforcement”. The
fallacious reasoning is compounded
by the assertion that the
“replacement” or “substitution” of the
guarantee by another establishes that
the first was not
“irrevocable”. And since it was not irrevocable the legal
consequences must be that the applicant
remained in breach and the
first respondent was/is entitled to cancel.
[29]
The letter
of guarantee dated 13 May 2021 was furnished in response to the first
respondent’s notice of intention to cancel
the agreement,
raised for the first time, in her counter-application seeking
cancellation of the agreement. The notice called upon
the applicant
to remedy an alleged breach inasmuch as the first guarantee was not
“irrevocably expressed”. This latter
averment was denied
but
ex
abundanti cautela
the applicant procured a guarantee which would meet the objection.
Two important things flow from this. First, the applicant was
quite
within its rights to respond to the notice of breach (pleaded as an
alternative) in
answering
the first respondent’s counter-application. Second, the 13 May
2021 guarantee was not the presentation of a new case in reply.
The
applicant’s case was always that it had complied with its
obligations and is entitled to an order compelling transfer.
The
first respondent’s case in her counter-application changed tack
inasmuch as she pleaded a new ground upon which to cancel
the
agreement, namely that the guarantee itself was a breach of the
agreement. The applicant was quite within its rights to meet
this
case.
[30]
There is
accordingly no basis to strike out these allegations on the basis
relied upon by the first respondent.
[31]
As I have
already indicated the very basis upon which the striking out
application is based rests upon a logical fallacy. The replacement
of
the original guarantee with the new guarantee does not expunge the
existence of the earlier guarantee. It exists as a matter
of fact.
Its replacement by a new letter of guarantee may mean that the first
guarantee can no longer be relied upon as security
for the payment of
the purchase price on transfer. A new guarantee is available for that
purpose. The question is could the first
guarantee be relied upon as
signifying the applicant’s compliance with its obligations?
That is a question to be answered
with reference to the terms of that
guarantee. If the answer is yes, then the applicant would be entitled
to the order sought in
its notice of motion. If, on the contrary, the
first guarantee was provided at a stage when the cancellation of the
agreement had
already occurred, then the terms would (subject to what
is set out later in this judgment) be relevant.
[32]
The
application to strike out all reference to the first guarantee in the
founding affidavit cannot succeed. So too, the application
to strike
out reference to the new guarantee. What remains to be considered is
the contention that certain passages in the replying
affidavit
consist of argument. I shall accept, without deciding, that the
passages complained of are framed in argumentative terms.
However,
the first respondent did not content for prejudice in any manner and
I am not able to discern what prejudice could flow
should these
passages not be struck out.
[33]
In the
circumstances, the application to strike out must be dismissed with
the usual costs order. This brings me to the issues to
be decided
upon. They are three. The first is whether it is established that the
agreement was cancelled. Closely related is the
question whether the
applicant’s conduct constituted a repudiation of the agreement
and whether the first respondent elected
to accept and cancel. If
these questions are answered in the affirmative it disposes of the
application. In the event that they
are answered in the negative, the
second and third issues arise. The first of these is whether,
notwithstanding the delivery of
the guarantee dated 1 December 2020,
the first respondent was (is) entitled to cancel because the
guarantee does not comply with
the terms of the agreement. The second
is the effect of the delivery of a notice of breach in the first
respondent’s counter-application.
The
alleged cancellation of the agreement of sale
[34]
It is not
in dispute that the applicant did not furnish a letter of guarantee
as security for payment of the purchase price within
the time
stipulated in clause 1.2 of the agreement. Clause 12 of the agreement
deals with default. It provides that:

If
after acceptance hereof either party fails to fulfil any of the
conditions hereof, and remains in default for a period of 7 (seven)

days after written notice has been given by the other party or his
agents, then the aggrieved party shall be entitled without prejudice

to any other right of law, to claim performance or cancellation of
this contract and damages. An amount not exceeding 10% (ten
percent)
of the PURCHASE PRICE paid by the purchaser may be forfeited as a
pre-estimate of damages should this contract be cancelled
as a result
of the purchaser’s breach.”
[35]
The first
respondent states that the failure by the applicant to deliver a
guarantee for payment of the purchase price within the
stipulated
period, resulted in it being placed in
mora
.
The notice of breach in terms of clause 12 was dispatched by Slabbert
Attorneys on her behalf on 30 March 2020. Upon failure to
remedy the
breach, the first respondent was entitled to cancel the agreement.
She asserts that the agreement was in fact cancelled.
[36]
It is
alleged that her husband cancelled the agreement and requested that
the original title deed be returned. No detail of the
cancellation is
provided and no correspondence reflecting the cancellation is
furnished. The reason for this is the assertion that
Mr Herholdt’s
email sever has lost much of its content and the particular email is
irrecoverable. This averment is confirmed
by Mr Herholdt.
[37]
In support
of the cancellation, reliance is placed upon correspondence which
passed between Mr Herholdt and Glyn Marais regarding
the return of
the title deed and the subsequent attempts to proceed with the sale.
[38]
In relation
to the title deed it is common cause that Mr Herholdt wrote to Ms
Nundlal, a conveyancing secretary at Glyn Marais on
17 September
2020. The email states that.

It is now a month since my
previous correspondence with you re the above. And still we have not
received the original title deed
of Serene back from you.
[39]
It is not
in dispute that the original title deed had in fact been couriered to
Mr Herholdt on 10 September 2020 under cover of
a letter dated 8
September. According to the applicant this was sent back in error.
[40]
It was
argued that the reference by Mr Herholdt to his earlier
correspondence, supports the conclusion that he had, in such earlier

correspondence, cancelled the agreement. The cancellation of the
agreement precipitated the returning of the title deed. Reliance
was
placed on the correspondence between Glyn Marais and Slabbert
Attorneys in October 2020 in which reference was made to the

applicant’s offer and by Slabbert Attorneys, that they had
closed their file. This, it was suggested, supports a finding
that
the agreement had been cancelled. It was further argued that inasmuch
as there is a factual dispute regarding cancellation,
the dispute
must be determined in favour of the first respondent by reason of the
rule in
Plascon-Evans
(Pty) Ltd v Van Riebeeck Paints (Pty) Ltd
.
[5]
[41]
The
difficulty with the latter argument is that there is much about the
alleged cancellation of the agreement, a central feature
of the first
respondent’s case, that is not explained. Mr Herholdt does not
state when he cancelled the agreement; to whom
the notice of
cancellation was addressed; nor why he undertook this task when
Slabbert Attorneys were instructed to deal with the
alleged breach.
If the first respondent’s inferential argument is to be
accepted the cancellation occurred in or about August
2020 possibly
in July 2020. Yet, there is no explanation of what transpired in the
period after May 2020.
[42]
According
to the correspondence from Slabbert Attorneys, they were still
attempting to establish, during May 2020, whether the applicant
was
going to remedy its breach. The correspondence on 15 May 2020
indicated that is the light of the continuing breach. Slabbert

Attorneys would “advise our client the way forward to exercise
his rights”. Nothing is said about whether such advice
was
furnished nor what the first respondent elected to do. In the light
of this, it is surprising that the cancellation did not
then occur
and that Slabbert Attorneys apparently played no role at all in
giving notice of the cancellation. Instead, the cancellation
is said
to have occurred by way of an email written by Mr Herholdt on an
undisclosed date.
[43]
This
alleged cancellation must, however, be considered in the light of
facts alleged by the applicant in relation thereto. Not only
does the
applicant deny that any notice of cancellation was given to it, each
of the professional staff at Glyn Marais deny having
received any
notice of cancellation by email from Mr Herholdt. These allegations
cannot be disputed by the first respondent. They
form part of the
factual matrix to be considered.
[44]
In
Wightman
t/a J W Construction v Headfour (Pty) Ltd and Another
[6]
it was said:

[13]
A real, genuine and
bona
fide
dispute of fact can exist only where the court is satisfied that the
party who purports to raise the dispute has  in his affidavit

seriously and unambiguously addressed the fact said to be disputed.
There will of course be instances where a bare denial meets
the
requirement because there is no other way open to the disputing party
and nothing more can therefore be expected of him. But
even that may
not be sufficient if the fact averred lies purely within the
knowledge of the averring party and no basis is laid
for disputing
the veracity or accuracy of the averment. When the facts averred are
such that the disputing party must necessarily
possess knowledge of
them and be able to provide an answer (or countervailing evidence) if
they be not true or accurate but, instead
of doing so, rests his case
on a bare or ambiguous denial the court will generally have
difficulty in finding that the test is
satisfied. I say 'generally'
because factual averments seldom stand apart from a broader matrix of
circumstances all of which needs
to be borne in mind when arriving at
a decision. A litigant may not necessarily recognise or understand
the nuances of a bare or
general denial as against a real attempt to
grapple with all relevant factual allegations made by the other
party. But when he
signs the answering affidavit, he commits himself
to its contents, inadequate as they may be, and will only in
exceptional circumstances
be permitted to disavow them. There is thus
a serious  duty imposed upon a legal adviser who settles an
answering affidavit
to ascertain and engage with facts which his
client disputes and to reflect such disputes fully and accurately in
the answering
affidavit. If that does not happen it should come as no
surprise that the court takes a robust view of the matter.”
[45]
There are,
as I have indicated, a number of circumstances pertaining to the
cancellation of the agreement which go beyond the inability
to
produce a written record thereof. These facts fall within the
knowledge of the first respondent, Mr Herholdt and their attorney.

They might well have allowed the court to come to a different
conclusion in relation to this crucial issue in the case. They were

not addressed.
[46]
Mr Marais,
for the first respondent, argued that the only inference which can be
drawn from the available correspondence including
that in October and
December 2020 is that the agreement had in fact been cancelled as
alleged by the first respondent. In cannot
agree, even assuming that
is a proper approach to adopt. One example suffices. As is recorded
earlier in the judgment, the response
to the delivery of the Investec
guarantee of 1 December 2020 made no reference to the cancellation.
All it said was that the guarantee
was a year late and that the first
respondent no longer wishes to sell. One might have expected some
clear and unequivocal statement
then that the agreement has already
been cancelled because of the applicant’s breach.
[47]
In order
for cancellation of the contract to be effective, it is necessary
that a notice of cancellation be delivered to the recalcitrant
party.
The fact that the first respondent may have been entitled to cancel
because of the applicant’s default does not assist
her. She was
required to exercise an election and to communicate it to the
applicant. In this regard, she bore an onus. The available
evidence
does not discharge such onus.
The
alternative pleas
[48]
The first
respondent’s reliance upon the applicant’s continuing
failure to remedy its breach as amounting to a repudiation
of the
agreement does not assist. If it is accepted, for the present, that
the failure to deliver the letter of guarantee timeously
and the
failure to do so after the notice of breach amounts to repudiation on
the part of the applicant, the first respondent must
have exercised
her election to cancel and have communicated it to the applicant.
[7]
This the applicant did not do. The further alternative defence poses
still further difficulties for the first respondent’s
reliance
upon an alleged cancellation.
[49]
As
indicated earlier in the judgment the first respondent contends that
the bank guarantee furnished on 1 December 2020 (the first
guarantee)
was not “irrevocable in its terms”. Accordingly, so it
was alleged, it did not cure the breach and the applicant
remained in
mora
.
For this reason, she was, despite its delivery, entitled to cancel.
She accordingly prayed for cancellation of the agreement.
[50]
However,
she went further in her counter-application to give notice of breach
based upon the fact that the guarantee was not “irrevocable
in
its terms” and called upon the applicant to remedy such breach.
[51]
The
assertion that the delivery of the first guarantee did not remedy the
breach because of its terms, is not sustainable. Clause
1.2.1 of the
agreement of sale required the delivery of a guarantee “irrevocably
expressed to be immediately payable to the
seller on written
notification of the purchaser’s conveyance of registration of
transfer.”
The
notice of breach required that the applicant deliver “acceptable
guarantees” or make payment of the purchase price
into a Trust
account. The delivery of the first guarantee cured the breach the
applicant was then required to remedy, namely that
it had not
presented a letter of guarantee within the stipulated time period.
The document dated 1 December 2020 which was presented
to cure the
applicant’s breach is, as a matter of fact, a letter of
guarantee issued by a financial institution to secure
payment of the
purchase price upon registration of transfer. To the extent that the
guarantee did not comply with clause 1.2.1,
either because it was not
irrevocably expressed or was not in a form acceptable to the first
respondent, may constitute a further
breach. The first respondent is
not entitled to simply ignore it. She would have to give notice of
the further breach before she
could elect to cancel on the basis that
the guarantee does not comply with the requirements stipulated in
clause 1.2 of the agreement.
[52]
This is, of
course, what she elected to do in her counter-application. However,
in doing so, she pleaded and purported to rely upon
an election which
is in conflict with an alleged prior cancellation of the
agreement.
[8]
Such conduct
strengthens the conclusion, already reached, that the agreement was
not cancelled.
[53]
If it is
accepted that the agreement was not cancelled, as it must be, then
the first respondent could rely upon the further breach
arising from
the terms of the first guarantee. In other words, the first
respondent could assert that by reason of non-compliance
with clause
1.2.1 the first guarantee is not in terms acceptable to her. Once she
did so, the applicant was equally entitled to
remedy the alleged
breach. If remedied within the stipulated notice period, the first
respondent’s entitlement to elect to
cancel does not arise.
[54]
That is the
effect of the delivery of the second guarantee which is framed in
terms that expressly render it “irrevocable
in its terms”.
The delivery of the second guarantee cured the further alleged
breach. In these circumstances, the first respondent
is not entitled
to cancel the agreement. Her counter-application seeking a declarator
of cancellation, alternatively an order cancelling
the agreement,
must therefore fail.
[55]
These
aspects, latterly addressed, relate to the alternative defences
raised by the first respondent. As indicated, the first respondent’s

primary defence, which was premised upon a prior cancellation, is not
established on the evidence. It follows therefore that the
applicant
is entitled to an order compelling transfer of the property.
[56]
What
remains is the question of costs. The costs should, in accordance
with the usual rule, follow the result. It was, however,
argued that
the costs ought to be awarded on a punitive scale. In support of this
it was submitted that the first respondent’s
conduct of the
litigation warranted such order. The application to strike out was,
it was submitted, vexatious and an abuse of
the process. It was
calculated, without any basis, to strike out the applicant’s
case in its entirety. Given the nature of
the application, the
applicant was put to unnecessary expense in prosecuting its case.
[57]
There is,
in relation to the application to strike out, considerable force in
the argument. The application was founded upon entirely
fallacious
reasoning and was, without substance and merit. In my view, a
punitive costs order in relation to the application to
strike out is
warranted. That, however, does not mean that a punitive costs order
should be made in relation to the case as a whole.
A punitive costs
order reflects disapproval of the conduct of the litigation or an
aspect of the litigation. It is not a sanction
for lack of success.
The usual costs order is designed to meet such circumstances.
[58]
In the
result, I make the following order:
1.
The
first respondent’s application to strike out is dismissed with
costs, such costs to be paid on the scale as between attorney
and
client.
2.
The
first respondent’s counter-application is dismissed with costs.
3.
The
first respondent is compelled to take all steps necessary to pass
transfer of ownership of Erf 223, Newton Park, Province of
the
Eastern Cape, and held by the first respondent under Deed of Transfer
T46801/2016CTN (the “property”) to the applicant

including obtaining, inter alia:
3.1
municipal
rates clearance certificates issued by the local authority in terms
of
section 118(1)
of the
Local Government: Municipal Systems Act, No.
32 of 2000
; and/or
3.2
valid
electrical compliance certificates in respect of each of the 7
(seven) dwelling units situated on the property, in accordance
with
the provisions of the Electrical Installations regulations, as
published in Government Notice R242, government Gazette 31975
of 6
March 2009, under the Occupation Health and Safety Act, No. 85 of
1993.
4.
The
first respondent shall, as a step contemplated in prayer 3 above,
forthwith appoint a conveyancing attorney of her choosing
to attend
to the preparation of all documents necessary to effect the aforesaid
transfer and shall advise the applicant of such
appointment within 5
(five) days of this order.
5.
Should
the first respondent fail to comply with prayer 2 above timeously,
the applicant shall appoint Glyn Marais Incorporated to
prepare all
documents necessary to pass transfer of ownership of the property to
the applicant.
6.
The
first respondent is directed to sign all documents necessary to
effect the transfer of the property prepared by the conveyancing

attorney appointed by herself, or Glyn Marais Incorporated as the
case may be, within 14 (fourteen) days of this order.
7.
That,
if the first respondent fails to comply with prayer 6 timeously, then
the Sheriff of the Court is authorised to take such
steps and to sign
all such documents as are necessary on the first respondent’s
behalf, in order to effect transfer of ownership
of the property to
the applicant.
8.
The
first respondent pay the costs of this application.
_______________________
G.G
GOOSEN
JUDGE
OF THE HIGH COURT
Appearances:
Obo the
Applicant      :
Adv J J Nepgen
Instructed
by         :          Glyn

Marais Incorporated c/o Joubert Galpin & Searle, 173 Cape Road,
Mill Park, Gqeberha
Obo the First
Respondent:     Adv P.T Marais
Instructed by
:         DSSG
Attorneys & Conveyancers c/o
Morne Struwig, 11 Carstens Street,
Kamma  Ridge, Gqeberha
Heard:

:           18
November 2021
Delivered
:
24
February 2022
[1]
The further portion of clause 1.2.2 is not
reproduced here, since it is not germane to the issues.
[2]
The national state of disaster was declared in
terms of the
Disaster Management Act, 57 of 2002
on 26 March 2020.
[3]
The Covid-19 Regulations, first promulgated in
Government Gazette Notice No. 318 on 18 March 2020 were amended from
time to time
as the lockdown, established thereby, was adapted to
meet changing circumstances related to the Covid-19 pandemic.
[4]
The reference is to the email included in the
correspondence of Slabbert Attorneys of 9 December 2020 in which Mr

Herholdt states that the first respondent does not want to sell the
property any longer. See par [20] above.
[5]
[1984]
(3) SA 623 (A)
[6]
[2008] ZASCA 6
;
2008 (2) SA 371
(SCA);
[2008] 2 All SA 512
(SCA)
at par
[13]
.
[7]
Tuckers Land and Development Corporation (Pty)
Ltd v Hovis
1980 (1) SA 645
(A) at 642G; Ponisamy and Another v
Versailles Estates (Pty) Ltd
1973 (1) SA 372
(A) at 387B.
[8]
Salwedle v Roath
1956 (2) SA 160
(E) at 163D.