About SAFLII
Databases
Search
Terms of Use
RSS Feeds
South Africa: Eastern Cape High Court, Port Elizabeth
SAFLII
>>
Databases
>>
South Africa: Eastern Cape High Court, Port Elizabeth
>>
2013
>>
[2013] ZAECPEHC 28
|
|
Goosen v van Blerk NO (3123/1999) [2013] ZAECPEHC 28 (11 June 2013)
REPORTABLE
IN THE HIGH COURT OF SOUTH AFRICA
(EASTERN CAPE, PORT ELIZABETH)
Case No: 3123/1999
In the matter between:
GERHARD GOOSEN
...........................................................................................
Plaintiff
And
BERNARDUS PIETER VAN BLERK N.O
.......................................................
Defendant
Coram:
Chetty J
Date Heard:
16 May 2013
Date Delivered:
11 June 2013
Summary:
Contract
–
Rectification
– Onus – Party seeking rectification not establishing
prior agreement on balance of probabilities –
Action dismissed
– Counterclaim – Defective workmanship – Claim
upheld
________________________________________________________________
JUDGMENT
________________________________________________________________
Chetty, J
Introduction
[1] This matter has a long and
checkered history. It commenced in November 1999 when the plaintiff
instituted action against one
J.S Ferreira
(the deceased) in
which he claimed payment,
ex contractu
, and other ancillary
relief. The plaintiff’s cause of action was founded upon a
written agreement concluded between them.
The agreement, signed by
the parties, recorded the following: -
“
Kliënt
Kontrakteur
Mr J.S. Ferreira Triple
“G” Grondwerke
Stilwerus 9
Koningstraat
Humansdorp Jeffreysbaai
DD 04/02/99
Dambou en Aanvullende
Grondwerke Ooreenkoms
Hiermee kom bo-genoemde
kliënt: J S Ferreira en kontrakteur Triple “G”
Grondwerke as volg ooreen in verband met
die volgende werk.
Dam van ±
160 000m³ volgens SABS standaarde (1:3 Helling waterkant
1:2 Helling droë kant)
Skoonmaak van ‘n
pompgat van ±4000m³
Grawe van pypsloot van
dam tot by pivot (centre)
Lewering van
vulmateriaal vanaf dam terrain na Nowestall
Afbreek en wegruim van
twee volkshuise
Die bedrag vir
bogenoemde werk is R280, 000.00 (Twee Honderd en Tagtig Duisend Rand)
en sluit brandstof in. Die bedrag sluit nie
BTW in nie. Betaling sal
maandeliks geskied en die finale betaling sal nie later as 30 dae na
voltooiing wees nie”
[2] It wil be gleaned from the
aforegoing that the material terms of the contract, of relevance
herein, obligated the plaintiff
to construct a dam in conformity with
SABS standards - the reservoir and forepart of the embankment at an
angle of inclination
of 1:3 and 1:2 respectively, and a capacity of
160 000 cubic meters.
[3] The deceased
died on 8 February 2000. Four (4) years later, in January 2004, a
plea, incorporating two special pleas
1
emerged. Therein,
the defendant, the executor in the deceased estate, admitted the
terms of the agreement but denied the breach
and contended that the
plaintiff had breached the contract by initially building a dam with
a capacity of 87 000m³, and,
although its volume was
subsequently increased to 124 500m³, it was still
substantially less than the 160 000 cubage
as per the
agreement
2
.
It pleaded further that the work had been performed in an
unprofessional and slovenly manner and provided details of the
defective
manner in which the dam had been constructed. He
furthermore annexed a report from a firm of consulting engineers,
Ninham
Shand
,
dated 20 November 2000, which,
inter
alia
,
highlighted the structural deficiencies in the construction of the
dam and the projected cost of repairs. Simultaneously therewith,
the
defendant filed a counterclaim, mirroring the allegations in his
plea, and sought damages in the sum of R252 000.00. The
action
once more entered a state of hibernation. In March 2011, after a
further hiatus of approximately seven years, it awoke from
its
slumber by the filing of a notice of intention to amend the
particulars of claim, which was duly effected in due course.
The amended particulars
[4] In the amended particulars of
claim, the plaintiff alleged that during the negotiations which
preceded the written agreement,
the parties jointly paced the
proposed site and agreed that the plaintiff would construct a five
(5) meter high embankment wall,
which, they erroneously concluded,
would yield a dam capacity of 160 000m³. He further alleged
that by virtue of a common
mistake, the written agreement merely
recorded certain of the specifications, viz a capacity of 160 000m³,
whereas the
true agreement envisaged the construction of a dam, the
embankment wall of which would be five (5) metres high. Consequently,
and
by virtue of what he contends was a material omission, to wit, a
term relating to the five (5) meter high embankment wall, he seeks
rectification of the written agreement to record the true contract.
The plea for rectification is resisted by the defendant who
steadfastly maintains that the written agreement records all its
material terms. He can understandably provide no direct evidence
to
substantiate his claim given the death of the deceased on 8 February
2000, but, as I shall in due course elucidate, the deceased’s
untimely death provided the catalyst for the plea for rectification.
[5] As adumbrated,
on completion, the capacity of the dam was substantially less than
the agreement stipulated, and, despite certain
remedial work
performed by the plaintiff, its volume was substantially below
160 000m³. It is not in issue that once
the additional work
to increase the dam capacity had been effected
3
,
the deceased paid an amount of R191 456, 41 to the plaintiff.
Aggrieved at what he considered to be underpayment, and a breach
of
the agreement, the plaintiff’s attorney, on 23 July 1999,
addressed a letter of demand to the deceased wherein payment
of the
balance of the contract price was demanded.
[6] The terms of the letter are
important, both, for its content, and omissions. Its reads as
follows: -
“
Ons rig die
skrywe namens mnr G Goosen h.a. Triple “G” Grondwerke van
Koningstraat 9, Jeffreysbaai. Dit is ons opdrag
dat ons kliënt
die begin van Februarie 1999 ‘n ooreenkoms met u gesluit het.
In terme van die ooreenkoms sou ons kliënt
sekere
konstruksiewerke verrig teen die ooreengekome bedrag van R280 000.00
wat BTW uitsluit. Die werke wat onder andere verrig
sou word, was die
bou van ‘n gronddam met ‘n kapasitieit van ongeveer
160 000m² (
sic
),
die skoonmaak van ‘n pompgat van ongeveer 40 000m²
(
sic
)
en die grawe van ‘n pypsloot vanaf die dam tot by die “pivot”.
Dit is ons opdrag dat
na sluit van die ooreenkoms ons kliënt met die konstruksiewerke
in terme van die ooreenkoms begin het.
Verder, na sluit van die
ooreenkoms, het die partye ooreengekom dat die pompgat nie ‘n
wal sou kry nie, maar sou ons kliënt
ekstra skoonmaakwerk aan
die rivierbedding by die pompgat verrig.
Ons kliënt het die
konstruksiewerk in terme van die ooreenkoms, soos gewysig, die einde
van April 1999 voltooi. In terme van
die ooreenkoms sou u ook
maandeliks betalings gemaak het, met ‘n finale betaling nie
later as 30 dae na voltooiing van die
konstruksiewerk nie. Soos
voormeld, het ons kliënt sy verpligtinge einde April 1999
voltooi. U het in total egter R191 456,14
betaal.
Dit is ons opdrag dat u
die balans van R88 543.86 plus BTW aan ons kliënt veskuldig
is, welke bedrag betaalbaar en opeisbaar
is. Aangesien u gemelde
bedrag op die laaste einde Mei 1999 moes betaal het, is u teenoor ons
kliënt aanspreeklik vir betaling
van rente op gemelde uitstaande
bedrag.
Tensy gemelde bedrag
binne (14) veertien dae na datum hiervan aan ons kliënt betaal
is, het ons opdrag om voort te gaan met
die instel van regstappe vir
die invordering van gemelde bedrag, tesame met rentes en kostes.”
[7] It will be gleaned from the
aforegoing that the letter merely records the terms of the written
agreement. The deceased’s
response, encapsulated in a letter
from his attorneys, was that the plaintiff had breached the terms of
the written agreement.
It recorded the following: -
“
Ons tree op
namens Mnr J Ferreira, wie u skrywe van 23 Junie 1999 aan ons
oorhandig het met die opdrag om daarop te antwoord.
Ons instruksies is dat
ons kliënt die terme van die ooreenkoms erken. Ons kliënt
ontken egter dat u kliënt sy verpligtinge
in terme van die
ooreenkoms nagekom het.
In terme van die
ooreekoms, moes u kliënt:
‘
n Gronddam met
‘n kapasitieit van ongeveer 160 000 kubieke meter bou.
Volgens ‘n onafhanklike deskundige opinie
deur ons kliënt
ingewin is die kapasiteit van die dam slegs 124 500 kubieke
meter, inaggenome 1 meter vir vryboord.
‘
n Pompgat met
‘n kapasitiet van ongeveer 40 000 kubieke meter bou. Die
kapasitiet van die pompgat is egter slegs ongeveer
10 000
kubieke meter.
Die dam moes verder
voldoen aan SABS standaarde, wat huidiglik ook nie die geval is nie.
Ons vesuim on volledig
met ‘n iedere en elke bewering in u skrywe te handel, moet nie
beskou word as ‘n erkenning van
sodanige bewerings nie. Ons
kliënt se reg om op ‘n latere stadium volledig met
sodanige bewerings te handel, word voorbehou.
Uit hoofde van
voorafgaande, ontken ons kliënt dat hy enige bedrae aan u kliënt
verskuldig is. Ons instruksies is dat
die bedrag, reeds deur ons
kliënt betaal, meer as die billike vergoeding vir die werk deur
u kliënt verrig, behels.
Enige aksie wat deur u
kliënt ingestel mag word, sal verdedig word.”
[8] The letter elicited no response.
Instead, six months later, the plaintiff issued summons out of this
court in which he sought
payment in the sum of R127 743, 86,
being the balance of the contract price. In October 2001, the
plaintiff’s attorneys
addressed a letter to the deceased’s
attorneys, ostensibly in an attempt to settle the dispute. It reads
as follows: -
“
Bogenoemde
aangeleentheid vewys.
Voordat ons met enige
verdere stappe moet voortgaan wil ons graag hierdie aanbod aan u
kliënt maak.
Ons kliënt is
bereid om die damwal te kompakteer en te herstel soos oorspronklik
tussen hom en u kliënt se vader ooreengekom.
Die uitstaande
balans aan hom verskuldig moet egter by u Trust inbetaal word voordat
ons kliënt gaan begin met die werk of
‘n waarborg gegee
word dat die geld beskikbaar is. Sodra die nodige vondse wel
beskikbaar is of beskikbaar gestel word en
die werk voltooi is kan
ons dan bymekaar kom en die nodige eksperts by om vas te stel of die
werk na behore uitgevoer is. Indien
hulle dan tevrede sou wees moet
die geld wat by u inbetaal is dan aan ons kliënt oorbetaal word.
Ons verneem dringend u
kliënt se houding hieroor.”
[9] In paragraph [6] hereinbefore I
prefaced the introduction of the pre-litigation correspondence as
part of the judgment with
the remark that their terms were important,
both as regards content, and omissions. Although the terms of the
contract are extensively
canvassed therein, there is no suggestion
whatsoever, of any oral agreement pertaining to the five (5) meter
high embankment wall.
It first emerged, almost eleven (11) years
later, by the filing of a notice in terms of Rule 28 of the Uniform
Rules of Court to
amend the plaintiff’s particulars of claim.
As I shall in due course advert to, the revelations encapsulated in
the notice
to amend went to the very root of the plaintiff’s
cause of action. Its omission, not only in the original particulars,
but
more importantly, in the correspondence reproduced hereinbefore,
is inexplicable. The probabilities are overwhelming that had the
purported oral agreement in fact been concluded, its terms would, at
the earliest opportunity, been divulged and not lain dormant
for
approximately eleven (11) years.
[10] It is trite law that the onus
rests on the plaintiff to prove that the written agreement stands to
be rectified. To discharge
the onus the plaintiff relied primarily on
his own testimony. The plaintiff is, by his own admission, an expert
in dam construction
and his evidence must accordingly be evaluated
against the backdrop of his professed status. In terms of his notice
filed pursuant
to the provisions of Rule 36 (9) (a) and (b) of the
Uniform Rules of Court, he vaunted his expertise as a dam builder,
contending
that he had been engaged in the industry for approximately
twenty-seven (27) years during which he had constructed more than one
hundred (100) dams. It seems meet therefore, to accept, that the
deceased solicited those skills for the construction of the
contemplated
dam. The plaintiff’s evidence in chief, tendered,
to provide the evidential basis for the claim, that prior to the
conclusion
of the agreement, the parties had reached consensus that
the dam wall would be five (5) meters high, was to the following
effect:
-
“
Ja
wat gebeur het is dat Leon het my gevra om te kom help om vir
hom
‘n dam te bou van ‘n sekere grootte wat dan nou wel dié
grootte is
en
ons het gaan kyk vir ‘n terrein om die dam dan nou te bou wat
uit die pad uit sal wees van ‘n “pivot”
of enigiets
anders dat hy die grond kan gebruik. Toe het ons hom uitgetree daar.
Daar is ‘n pad wat oploop na die huis toe
en dan is daar ‘n
teerpad aan die onderkant, dan is daar ‘n “pivot”
aan die onderkant, een van hierdie
besproeiings-“pivots”.
Dis basies al waar jy hom kon inpas.
Daar
was nie ander plek gewees nie en om by die kapasiteit te kom het ons
hom uitgemeet, 250 meter lank en 150 meter wyd en met
‘n
beperking van vyf meter walhoogte kon ons toe werk op ‘n
gemiddelde diepte van water van 4,5 meter dat daar nog
‘n halwe
meter vryboord is en soos ek kan sê, die dam is bo-op ‘n
bult.
U moet net bietjie
stadiger. Sy Edele moet nota’s maak mnr Goosen. --- Goed. Die
ding was bo-op ‘n bult gebou en daar
word gepomp in hom in so
hy is nie in ‘n kloof of iets nie en as ‘n mens 250 meter
lengte vat en jy vat 150 meter breedte
en jy vat ‘n 4,5 meter
diepte dan gaan
jy
op 168 000 kubieke meter volume kom en dit is hoe ons die ding
uitgemeet het en saam
besluit het ons gaan hom so bou. Daar was in elk geval nie ‘n
ander terrein wat gevestig of geskik sou
wees vir die grootte van die
dam nie.
En verwys u na die
hoogte van die damwal, wat het u ooreengekom? --- Nee ons het
ooreengekom dat hy moet binne die wet wees en dit
is vyf meter.”
(my emphasis)
[11] It will be gleaned from the
aforegoing response to the question concerning the specifications
encapsulated in paragraph 1 of
the written agreement that the answer
provided failed to provide the evidential basis for the claim for
rectification. It was immediately
followed by the following question:
-
“
En
verwys u na die hoogte van die damwal, wat het u ooreengekom?”
The anticipated answer was however not
forthcoming, the reply merely being: -
“
Nee
ons het ooreengekom dat hy moet binne die wet wees en dit is vyf
meter.”
[12] It is evident
from the aforegoing that, save for the remark that the height of the
embankment wall had to conform to legislative
prescripts, the
plaintiff omitted all reference to the alleged prior oral agreement
relating thereto. Consequently, and to afford
corroboration for the
contention that a five (5) meter high embankment wall was a specific
term of the oral agreement, the plaintiff
was referred to the
National
Water Act
4
and the now
repealed
Water
Act
5
.
Recourse to the aforegoing legislation does not avail the plaintiff.
Both section 117 of the
National
Water Act
and
its predecessor, section 9 (C) (1) of the
Water
Act
define
a
“
dam
with a safety risk”
as
being one
“
which
has a wall of a vertical height of more than five meters”
.
The control measures delineated in section 118 of the
National
Water Act
only
apply to a dam wall of more than five (5) meters in height. On the
plaintiff’s own version the height of the dam wall
did not
exceed five (5) meters and there could consequently have been no
reason whatever for any discussion thereanent and to include
it as a
term of the agreement.
[13] Under cross-examination the
plaintiff was referred to his evidence in chief, in particular, the
formula he had applied to construct
a dam with a holding capacity of
160 000m³. He reiterated that, applying the formula, 250m x
150m x4.5m, the length,
width and depth respectively, the dam would
have a cubage of 168 750, approximating the deceased’s
requirements. He
further testified that he thereafter sought the
advice of a certain Mr
Arthur Olivier
to calculate the volume
of the material which would have to be excavated, but was amazed
that, on completion, the capacity was
only 87 000m³. He was
referred to the correspondence adverted to hereinbefore and in
particular, the letters addressed
to the deceased by his attorney,
which omitted all reference to an embankment dam wall height of five
(5) meters. The plaintiff
could, understandably, proffer no
explanation for such omission.
[14] As adumbrated hereinbefore, the
plaintiff bears the onus to prove, on a balance of probabilities,
that the common intention
of the parties was that the plaintiff would
build a five (5) meter high embankment wall. The fact that the
applicable legislation
contained such a prescript does not advance
the plaintiff’s case. The relevant correspondence omits all
reference thereto
and the plaintiff’s own testimony moreover
fails to provide the evidential basis for the claim for
rectification. The evidence
adduced is wholly insufficient to
establish that the written agreement, through common mistake,
incorrectly records the agreement
which they intended to express. The
plaintiff is not entitled to rectification and the application must
therefore be refused. Consequently,
the need to determine the
validity of either of the special pleas does not arise. It follows
from the aforegoing that as the plaintiff
failed to fulfill his
contractual obligations, his cause of action can therefore not be
sustained and is dismissed.
The counterclaim
[15] The counterclaim is predicated
upon the unprofessional and slovenly manner in which the dam had been
constructed. Apart from
the substantial reduced cubage, the defendant
alleged that erosion occurred as a result of defective compaction of
the earth fill,
the embankment was to steep and the crest width, only
0.5 meters, instead of three (3) meters. Particularity concerning the
deficiencies
in the construction of the dam appear from the
Ninham
Shand
report referred to hereinbefore. During his
cross-examination,
the plaintiff was referred thereto and
was constrained to accept the findings, conclusions and
recommendations therein. It follows
that he is liable for the costs
of repair, which the parties are agreed, amount to R250 000.00.
[16] In the result the following
orders will issue:
The plaintiff’s claim for
rectification is refused and the action dismissed.
The counterclaim succeeds and the
plaintiff is ordered to pay the defendant the sum of R250 000.00
together with interest
thereon at the legal rate of 15.5% per annum
a
tempore morae
.
The plaintiff is ordered to pay the
defendant’s costs of suit, together with interest thereon, at
the rate of 15.5% per
annum, from date of taxation to date of
payment.
The costs are to include the reserved
costs, the costs of the defendant’s expert witness, Mr J
Kritzinger and the costs
of the pre-trial inspection
in loco
.
__________________________
D. CHETTY
JUDGE OF THE HIGH COURT
Appearances:
On behalf of the Plaintiff: Adv B.
Pretorius
Instructed by Van Rooyen &
Efstratiou
57 Sixth Avenue, Newton Park
Port Elizabeth
Ref: Shakira
Tel: (041) 365 2844
On behalf of the Defendant: Adv L.A
Schubart SC
Instructed by Greyvensteins
104 St George’s House, Park
Drive
Port Elizabeth
Ref: Greg Parker
Tel: (041) 5015500
1
Prescription
and undue delay in effecting the amendment.
2
The
remaining breach is not relevant for the purposes of this judgment.
3
The
plaintiff contended that he carried out the additional work at his
own cost.
4
Act
No, 36 of 1998
5
Act
No, 54 of 1956