P Gerolomou Constructions (Pty) Limited v Van Wyk (2011 (4) SA 500 (GNP)) [2010] ZAGPPHC 258; A1462/05 (22 November 2010)

80 Reportability
Contract Law

Brief Summary

Contract — Settlement agreement — Allegation of undue influence — Plaintiff claimed payment for subcontracting work done for the defendant, asserting that he signed a settlement document under compulsion and without genuine consent — Defendant contended that the signed document constituted a full and final settlement of all claims — Court found that the plaintiff did not accept an offer of settlement as he was coerced into signing the document, which was not intended to create a binding agreement — Appeal dismissed, upholding the magistrate's finding that the plaintiff was entitled to the claimed amount.

Comprehensive Summary

Summary of Judgment


1. Introduction


The matter concerned an appeal from a magistrates’ court decision. The appeal was heard in the North Gauteng High Court, Pretoria. The appellant in the appeal was the defendant at trial, and the respondent was the plaintiff at trial.


The plaintiff (a subcontractor) sued the defendant (a construction company) for payment for subcontracting work performed during April to June 2002 pursuant to oral agreements. The work related to the design, construction (through an outside contractor), and installation of the four highest corners of the Nan Hua Temple in Bronkhorstspruit.


The procedural history was relevant to the extent that the trial commenced on 4 November 2004 with both parties legally represented, but on resumption on 8 August 2005 the plaintiff’s attorney withdrew and the plaintiff thereafter conducted his own case. The defendant remained represented (its initial representative having been replaced). Judgment in the magistrates’ court was delivered on 19 August 2005. On appeal, the appellant was represented by counsel, and there was no appearance for the respondent.


The general subject-matter of the dispute on appeal was narrowed to the defendant’s reliance on a document signed by the plaintiff which allegedly recorded “full and final settlement”, and the plaintiff’s response that the document did not bind him (and, in the alternative, that it was procured by undue influence/duress).


2. Material Facts


The magistrate found as an initial matter that the plaintiff had properly performed the subcontracting work. Although the appellant had placed performance in issue, the magistrate accepted the plaintiff as a very good witness, found the defendant’s witnesses false, and rejected the defences raised by the defendant. These credibility and performance findings were not challenged on appeal.


The appeal therefore turned on facts surrounding a document signed on 16 October 2002, described in the judgment as the “full settlement document”. On the plaintiff’s version (accepted by the magistrate), after completing the work he sought payment of retention money in the amount of R48 523,54 that the defendant was withholding. He was under financial pressure, including pressure from his workers whom he needed to pay, and he required payment from the defendant to do so.


After delays, the plaintiff met at the site on the morning of 16 October 2002 with Nicholson (described as the plaintiff’s foreman), Kruger (the defendant’s project manager), and a quantity surveyor. At that meeting Kruger produced a draft “final account” document. The plaintiff’s evidence was that he was told that contra charges were being raised against him and that he would receive no money at all unless he signed the document. The plaintiff protested that signing would be unfair (“onregverdig”), but was told in clear terms that without signature, the defendant would not pay him anything.


The document itself was headed “Final account for Derek van Wyk”. It listed retentions totalling R48 523,54. It then listed contra charges totalling R29 231,84, resulting in a stated balance of R19 291,70. The concluding clause stated that the plaintiff accepted payment of R19 291,70 “in full and final settlement of all accounts, claims etc” that he or his workers might have on the project from the defendant, followed by the plaintiff’s signature and the date 16 October 2002.


The defendant pleaded that during about October 2002 the plaintiff accepted the final payment of R19 291,70 in full and final settlement of all amounts due, and that the plaintiff had been paid that amount. The plaintiff’s replication admitted signing but asserted he was not bound because his signature had been obtained by improper influence, pleaded in terms consistent with the recognised elements of undue influence.


3. Legal Issues


The central legal questions were whether the signed “full settlement document” had the legal effect contended for by the defendant, and if so, whether it could be avoided.


More specifically, the court was required to determine, as a matter of application of law to fact, whether the document constituted a binding agreement of compromise/settlement (or any contract at all), given the circumstances of its presentation and signature. This required consideration of whether there had been offer and acceptance, and whether the “full settlement” language operated as a compromise or merely as part of payment of an admitted liability.


In the further alternative (addressed on the assumption that there was a compromise), the court had to decide whether the plaintiff proved undue influence/duress sufficient to avoid the agreement. This involved a value-laden inquiry into whether the defendant’s conduct was unconscionable in the sense required by the law of undue influence, based on the facts accepted by the magistrate.


A further issue, treated as significant by the appeal court, was whether the defendant’s pleaded case properly raised a contract of compromise at all, given that the plea relied on “full and final settlement” and payment but did not plead a written agreement of compromise in terms.


4. Court’s Reasoning


The court began by identifying that the magistrate had upheld three of the plaintiff’s claims and rejected the defendant’s defences, and that the appeal focused on the defence derived from the pleaded “full and final settlement” document.


Contract formation and the nature of the “full settlement” document


The court applied the basic principle that a contract requires offer and acceptance. It examined the factual context in which the document was presented and signed and concluded that, on the evidence, there was no indication that the defendant was making an offer of settlement capable of acceptance in the sense required to form a compromise. The document was presented on the footing that the plaintiff would not receive even what the defendant admitted was due unless he signed an acknowledgment relating to the defendant’s contra charges.


The court reasoned that the plaintiff made clear at the meeting that he did not admit owing the contra charges, and that to the knowledge of the defendant’s representatives he signed solely to obtain payment of what the defendant admitted owing, rather than to settle the dispute about contra charges. On this approach, the defendant could not be said to have been led to believe that the plaintiff was accepting an offer to compromise, and therefore no issue of quasi-mutual assent arose.


The court also attached significance to the pleaded case. It held that even though the plaintiff in replication characterised the document as a contract, this could not assist the defendant because it was not the defendant’s pleaded case that the document constituted a contract or that a compromise had been concluded. On this basis, the defendant could not rely on the plaintiff’s characterisation to supply a missing pleaded foundation.


“In full settlement” and the distinction between compromise and admitted liability


The court nonetheless considered the alternative position, namely that if the document were to be treated as an offer, it was necessary to determine the nature of what was offered and accepted. Drawing on authority analysed in Christie and specifically on ABSA Bank Ltd v Van der Vyver (with reference to Harris v Pieters and Karson v Minister of Public Works), the court treated the effect of “in full settlement” as depending on context. It accepted that the phrase imports a condition that acceptance leaves no further claim, but that whether it constitutes a compromise or merely a payment of an admitted liability is fact-dependent.


Applying that framework, the court evaluated what the defendant’s representatives had done: they calculated a balance by deducting disputed contra charges from retention money that the defendant in fact admitted owing, arriving at the tendered balance of R19 291,70. The court emphasised that the “admission” in the document was not merely that “something” was due; it was that the tendered balance was due after deductions the plaintiff disputed.


The court articulated the factual substance of the defendant’s position as an ultimatum: payment of what the defendant accepted it owed would be made only if the plaintiff acknowledged in writing the defendant’s full contra charges, failing which the defendant would pay nothing. The court treated this not as an offer aimed at compromising the actual dispute (the contra charges), but as a conditional payment of an admitted debt designed to extract an admission from the plaintiff by threatening continued non-payment.


In distinguishing Be Bop A Lula Manufacturing & Printing CC v Kingtex Marketing (Pty) Ltd, the court accepted that a compromise may exist even where some liability is admitted, but found that the essential difference in the present matter lay in the defendant’s stance that it would withhold even the undisputed portion and force litigation to recover what was admitted to be due. That posture undermined characterisation of the document as a bona fide compromise of a dispute limited to contra charges.


Undue influence/duress (addressed in the further alternative)


Proceeding on the assumption that the document did constitute a compromise (which the court considered incorrect), the court then addressed the plaintiff’s pleaded case of undue influence (described as having been characterised at trial as duress). It applied the established elements for rescission on the ground of undue influence as articulated in Patel v Grobbelaar: the other party must have gained influence; the influence must have weakened resistance and made the will malleable; and the influence must have been used unconscionably to procure a prejudicial transaction that would not otherwise have been concluded.


On the facts accepted by the magistrate, the court held there was no doubt the defendant had gained influence over the plaintiff. It grounded this conclusion in the defendant’s knowledge of the plaintiff’s financial pressure and need to pay his workers, the disparity in economic power, and the defendant’s knowledge that the plaintiff could not afford a protracted dispute while the defendant could.


The court also held that the defendant took advantage of the situation to procure an outcome to the plaintiff’s disadvantage, particularly given that the plaintiff protested the unfairness of the transaction. The remaining question was whether the defendant’s conduct met the requirement of unconscionability.


In addressing unconscionability, the court noted that the concept had appeared in South African jurisprudence notably in relation to the exceptio doli, referring to the suppression of the exceptio in Bank of Lisbon and South Africa Ltd v De Ornelas, while treating the body of case law as providing guidance on what courts regard as unconscionable. The court described unconscionability as involving substantial unscrupulousness, an intention to oppress, or departure from the values of right-thinking persons in context. It referred, for comparative illumination, to the approach in Commercial Bank of Australia Ltd v Amadio, in which unconscientious conduct was linked to unfair advantage taken of superior bargaining power where the other party was under a special disadvantage such as financial need.


The court then drew an evaluative distinction. It accepted that exploiting economic weakness may be permissible where there is a genuine settlement of a disputed indebtedness, but considered it materially different where a stronger party withholds what is admittedly owing in order to secure commercial advantage. The court linked this conclusion to constitutional values of freedom and human dignity, referencing Barkhuizen v Napier, and further held that such conduct trenched upon the weaker party’s constitutional right to have disputes resolved by a fair legal process under section 34 of the Constitution. On that evaluative basis, the court concluded that the plaintiff established the required element of unconscionability; accordingly, if a compromise had existed, the plaintiff would have been entitled to avoid it.


5. Outcome and Relief


The court held that the magistrate’s decision should stand and that the appeal should fail. The appeal was dismissed.


The judgment, as reported, did not expressly set out a separate order as to the costs of the appeal beyond the dismissal of the appeal.


Cases Cited


ABSA Bank Ltd v Van der Vyver 2002 (4) SA 397 (SCA)


Harris v Pieters 1920 AD 644


Karson v Minister of Public Works 1996 (1) SA 887 (E)


Be Bop A Lula Manufacturing & Printing CC v Kingtex Marketing (Pty) Ltd 2008 (3) SA 327 (SCA)


Patel v Grobbelaar 1974 (1) SA 532 (A)


Bank of Lisbon and South Africa Ltd v De Ornelas 1988 (3) SA 580 (A)


Commercial Bank of Australia Ltd v Amadio [1983] HCA 14; (1983) 151 CLR 447


Barkhuizen v Napier 2007 (5) SA 323 (CC)


Legislation Cited


Constitution of the Republic of South Africa, 1996 (section 34)


Rules of Court Cited


No rules of court were cited in the judgment.


Held


The High Court held that, on the accepted evidence, the “full settlement document” was not shown to constitute a binding compromise because the defendant’s conduct did not amount to an offer of compromise accepted by the plaintiff; rather, it reflected an attempt to withhold payment of an admitted debt unless the plaintiff made an acknowledgment regarding disputed contra charges.


In the alternative, assuming a compromise had been concluded, the court held that the plaintiff established undue influence in the pleaded sense, including unconscionable conduct, because the defendant leveraged its superior economic position and the plaintiff’s financial need by withholding amounts it admitted were due in order to procure an agreement prejudicial to the plaintiff, in circumstances implicating constitutional values and the right of access to courts.


LEGAL PRINCIPLES


A contract requires offer and acceptance, and whether a document constitutes a compromise depends on whether it objectively reflects the conclusion of an agreement to settle a dispute, rather than a coerced acknowledgment extracted as a condition for payment of an admitted debt.


The phrase “in full settlement” does not operate uniformly; whether it effects a compromise or merely accompanies payment of an admitted liability depends on context. Where the tender is a payment of what is admitted to be owing, a creditor may be entitled to retain payment and still sue for the balance; where the tender is a genuine compromise of a disputed claim, acceptance concludes the compromise.


A party seeking rescission/avoidance on the ground of undue influence must establish that the other party gained influence, that the influence weakened resistance and made the will malleable, and that the influence was used unconscionably to procure a prejudicial transaction that would not have been concluded with normal freedom of will.


In assessing unconscionability for purposes of undue influence, the court treated substantial unscrupulousness and oppressive exploitation of a position of disadvantage as central indicators, and considered it materially different to leverage economic power in a genuine dispute settlement versus withholding amounts admittedly due to extract commercial advantage, particularly where such conduct implicates constitutional values and section 34 access to court.

About SAFLII
Databases
Search
Terms of Use
RSS Feeds
South Africa: North Gauteng High Court, Pretoria
SAFLII
>>
Databases
>>
South Africa: North Gauteng High Court, Pretoria
>>
2010
>>
[2010] ZAGPPHC 258
|

|

P Gerolomou Constructions (Pty) Limited v Van Wyk (2011 (4) SA 500 (GNP)) [2010] ZAGPPHC 258; A1462/05 (22 November 2010)

REPORTABLE
IN
THE NORTH GAUTENG HIGH COURT,
PRETORIA
REPUBLIC OF SOUTH AFRICA
CASE
NO: A1462/05
DATE:22/11/2010
In
the matter between:
P
GEROLOMOU CONSTRUCTIONS (PTY)
LIMITED
.................................................
Appellant
and
DERRICK
VAN
WYK
...............................................................................................
Respondent
JUDGMENT
Tuchten
J:
1.
This is an appeal from a decision by a magistrate. I shall refer to
the parties as they were described at the trial. The plaintiff

claimed payment for certain subcontracting work carried out by the
defendant during the period April to June 2002 pursuant to oral

agreements between the parties. The work required the plaintiff to
design the four highest corners of the Nan Hua Temple in
Bronkhorstspruit
according to a plan and, after they had been
constructed from wood by the plaintiff through an outside contractor,
to instal them.
The trial began on 4 November 2004. At that stage
both parties were legally represented. The trial resumed on 8 August
2005. On
that date the attorney for the plaintiff withdrew from the
case and the plaintiff, a legal layman, proceeded to represent
himself.
Up till that date, the plaintiff had enjoyed legal
representation both in regard to the preparation of the pleadings and
the conduct
of the trial. The lawyer who represented the defendant on
the first day of the trial also withdrew but was replaced by another
legal representative on 8 August 2005. Judgment was given on 19
August 2005. At the appeal, the appellant was represented by counsel

but there was no appearance for the respondent.
2.
Although the appellant placed the work done by the plaintiff in
issue, the magistrate found that the plaintiff had done the work

properly. She found that the plaintiff was a very good witness and
the version given by the defendant's witnesses was false. She

rejected all the defences raised by the defendant, including those
with which I shall shortly deal. She upheld three of the plaintiff's

claims, together with interest and costs. The defendant appeals
against the magistrate's decision. The issues for decision on appeal

concern those which arose from paragraphs 4.2.2 and 4.3 of the
appellant's plea:
4.2.2
During or about October 2002, the Plaintiff accepted a final payment
in the amount of R19 291,70 in full and final settlement
in respect
of all amounts due to the Plaintiff for the works. A copy of the
signed acceptance for the aforesaid payment is annexed
hereto as
"DW3".
4.3
The plaintiff has been paid the amount in terms of annexure "DW3".
3.
The plaintiff replied to these paragraphs as follows:
Die
Eiser erken dat hy die kontrak geteken het maar ag homself nie
gebonde aan die kontrak, aangeheg aan die Verweerder se Pleit
en
gemerk aanhangsel "A", nie aangesien die Eiser se
handtekening bekom is deur middel van onbehoorlike beinvloeding.
Die
Eiser is onbehoorlik be'i'nvloed deurdat die Verweerder:
1.
'n Invloed oor horn gekry het;
2.die
invloed het die eiser se teenstandsvermoe verswak en sy wil plooibaar
gemaak;
3.
en dat die verweerder hierdie invloed op gewetenlose wyse gebruik het
om toe te stem tot 'n transaksie wat:
a)
tot sy nadeel strek; en
b)
wat hy met normale wilsvryheid nie sou aangegaan het nie.
4.
The plaintiff went on in his reply to allege that he had suffered
damages of R104 280, 40 as a result of the influence which
the
defendant had gained over him and that the defendant had made the
plaintiff's will malleable by being for a considerable time
in
default of performance which in context means not paying the
plaintiff what the plaintiff says he was owed for the work he did.
5.
The trial was conducted on the basis that the document referred to in
the passage from the defendant's plea which I have quoted
("the
full settlement document") was indeed an agreement of
settlement, although the defendant did not plead that the
full
settlement document did constitute a written agreement of any kind.
In my view, the full settlement document was not intended
by the
defendant, on which the onus in this regard lay, to constitute an
agreement of any kind.
6.
The evidence of the plaintiff was that he signed the full settlement
document under compulsion. After he had completed the work
he went to
Nicholson, the plaintiffs foreman to negotiate the payment to the
plaintiff of retention money of R49 523, 54 which
the defendant was
withholding. The plaintiff was under pressure from his workers to pay
them and the plaintiff could only do this
with money paid to him by
the defendant. After considerable delays engineered by the defendant,
the plaintiff, Nicholson and Kruger,
the defendant's project manager
and quantity surveyor respectively, met for this purpose at the site
during the morning of 16 October
2002.
7.
Kruger produced a draft of the full settlement document. He told the
plaintiff that the defendant had raised contra charges
against him
and that the plaintiff must sign the full settlement document or he,
the plaintiff, would not get any money at all.
The plaintiff
protested, saying that he could not sign the full settlement document
because it was unfair ("onregverdig").
Kruger made it plain
to the plaintiff that if he did not sign the full settlement
document, the plaintiff would not get any money
at all.
8.
The full settlement document itself does not purport to be a
memorandum of an agreement. It is headed "Final account for

Derek van Wyk". It begins with a list of money retained and the
dates of each such retention. The total of the retentions
is R48
523,54. There follows a section identifying the contra charges raised
by the defendant for repairing damaged materials,
removal of material
and stripping out "tsuantzees". The total of the contra
charges is R29 231, 84. On the final page
of the full settlement
document, the contra charges are deducted from the retention monies,
leaving a balance of R19 291,70.
9.
The full settlement document then concludes:
I,
Derek van Wyk, herewith accept the payment in the amount of R19
291-70 in full and final settlement of all accounts, claims etc
that
I or any of my workers may have on the Nan Hua Temple in
Bronkhorstspruit from Gerolemou [sic] Construction.
(sad)
....................................................
16.10.002
DEREK
VAN WYK
...............................
DATE
10.
It is trite that a contract is formed by an offer and an acceptance.
I see no indication on this evidence that the defendant
was making
the plaintiff any offer at all. The draft full settlement document
was presented to the plaintiff for signature on the
footing that the
plaintiff would not get what the defendant admitted was due to the
plaintiff unless the plaintiff in his turn
signed an admission that
he owed the defendant what the defendant was demanding in respect of
contra charges. The plaintiff made
it clear at the meeting that he
admitted no such thing. To the knowledge of the defendant's
representatives, the defendant signed
the full settlement document to
obtain payment of what the defendant admitted owing him and not to
put an end to the dispute between
the parties which was whether the
plaintiff owed the defendant anything at all in respect of contra
charges and, if so, how much.
So the defendant was not led to believe
that the plaintiff was accepting an offer of settlement made by the
defendant and no issue
of quasi-mutual assent arose.
11.
The fact that the plaintiff, in his reply, characterised the full
settlement document as a contract cannot in my view assist
the
defendant because it was not the defendant's pleaded case that the
document constituted a contract or that a contract of compromise
had
been concluded between the parties. As the defendant did not assert a
contract of compromise, it cannot be said that the defendant
admitted
that there was such a contract.
12.
But if I am wrong, then one must determine what the offer was that
the plaintiff accepted. Christie
1
analyses the cases and points out
2
that the words "in full settlement" are ambiguous. In ABSA
Bank Ltd v Van der Vyver
3
,
in the context of a pre-existing dispute, the executrix of an
erstwhile customer of the bank sent the bank a cheque for the amount

she said was owing after deduction of certain countercharges. In the
letter accompanying the cheque, the executrix said that the
amount
tendered was "in voile en finale vereffening". After an
analysis of the relevant case law the court held, with
reference to
Harris v Pieters,
4
as follows:
5
What
the judgment of Innes CJ in Harris at 649-50 does serve to show
clearly, in my view, is that the expression 'in full settlement'
is
not in itself ambiguous but that its effect differs depending on the
context in which it is used: Karson v Minister of Public
Works 1996 1
SA 887 E at 895F-G. It is not inherently ambiguous because it always
serves to do no more, legally speaking, than
import the condition
that on acceptance the creditor has no further claim to any balance
of the debt. But, as a matter of language,
and with regard to the two
different situations in which it is employed, it is a question of
fact whether the payment made is intended
to effect a compromise or
to pay an admitted liability. In the former situation the condition
is binding if the offer is accepted.
If the offer is rejected the
money should be returned. In the case of a payment of an admitted
liability the condition is not binding.
The creditor may keep the
money and sue for the balance. [My emphasis]
13.
The judgment continues:
6
Sending
one's creditor a cheque 'in full settlement' coupled with a denial of
liability would almost certainly signify an offer
of compromise. But
there may be an offer of compromise if there is simply no admission
of liability accompanying the payment. And
one may have to do with an
offer of compromise even if there is an admission of liability. In
the latter instance the line between
an offer of compromise and
payment of an admitted liability would naturally be finer than in the
other two cases. In Paterson Exhibitions,
for example, the admission
was, in effect, no more than that something was owing, but without
admitting how much or that the payment
offered represented the
admitted indebtedness. [Again, my emphasis]
14.
It is clear from the evidence that when the defendant's
representatives framed the full settlement document, the defendant
had made a calculation, deducting from what it in fact admitted that
it owed the plaintiff a sum which the defendant had calculated
was
owed to it by the plaintiff for contra charges and concluding
arithmetically that after deduction of what the defendant claimed
was
owed to it, the balance owed to the plaintiff was R19 291,70. The
admission made by the defendant in favour of the plaintiff
in the
full settlement document was not merely that "something"
was owing but that the very balance tendered, R19 291,
70, was owing.
In my view, if the document constituted an offer to the plaintiff,
then the offer, seen in its factual matrix, was
this:
We
both know that you are owed R48 523,54 by us for retention monies,
that you dispute owing us anything at all by way of contra
charges
and that when the amount of the disputed contra charges is deducted
from our admitted indebtedness to you of R48 523,54
there is a
balance due to you of R19 291,70. We offer to pay you what we owe you
on our version, ie R19291,70, only if you acknowledge
in writing that
you owe us the full amount of the contra charges which we claim. If
you do not so acknowledge in writing, we shall
pay you nothing, not
even the amount we admit owing you.
15.
Counsel referred in argument to Be Bop A Lula Manufacturing &
Printing CC v Kingtex Marketing (Pty) Ltd
7
.
In that case, a dispute had arisen as to the quality of T-shirts
which were sold by the respondent to the appellant and the discount,

if any, to which the appellant was entitled arising from the alleged
defects. The appellant sent the respondent a letter headed
"Credit
Request", proposing a discount of something over half of the
balance of the purchase price in dispute, together
with a cheque for
he balance. The cheque was marked on its face with the words "full
and final settlement of account".
With the letter, the appellant
also sent the respondent a letter headed "Final Reconciliation".
The court considered
8
whether the cheque was intended to effect a compromise or pay an
admitted liability and came to the conclusion, on the facts, that
the
words "full and final settlement" on the cheque can only
amount to an offer to the respondent to settle their dispute
by
payment of that amount which the latter could have accepted or
declined, but on acceptance of which the dispute between the
parties
would be compromised. The fact that the appellant admitted liability
in a certain amount is no bar to the proposal being
construed as an
offer of compromise. [Footnotes omitted]
16.
I think the essential difference between the factual situations in Se
Bop A Lula and the present case is that in the present
case the
defendant made it clear that it would not pay what it owed and would
therefore force the plaintiff to go to court to recover
not only the
portion of the plaintiff's claim disputed by the defendant but also
that portion of the plaintiff's claim which the
defendant did not
dispute.
17.
That, in my view, is not an offer to compromise the dispute which
only existed in relation to the contra charges but an offer
(if it
was an offer at all) to pay what was owing only if the plaintiff made
the admission demanded, failing which the defendant
would not pay the
plaintiff what it owed the plaintiff even though the defendant had,
and knew it had, no basis in law for withholding
such payment.
18.
Finally I turn to the issue raised in the reply of undue influence
or, as it seems to have been characterised at the trial,
duress. I do
so on the assumption, which I have concluded is ill-founded, that the
full settlement document constitutes a contract
of compromise. It is
correct that the onus to establish that there was undue influence
rests on the plaintiff but as the magistrate
accepted the plaintiff's
evidence and rejected that presented on behalf of the defendant, a
finding which was not challenged on
appeal, the question resolves
itself into
an
enquiry whether the plaintiff's evidence establishes undue influence.
19.
A litigant who claims rescission of a contract through undue
influence must establish precisely what the plaintiff pleaded:
that
the other party to the contract gained an influence over him, that
this influence weakened his resistance and made his will
malleable
and that the other party used that influence in an unconscionable
manner to persuade him to agree to a transaction which
operated to
his prejudice and which he in normal circumstances would not have
concluded.
9
20.
There can be no doubt that the defendant gained an influence over the
plaintiff. This is established by the facts that the defendant
knew
the plaintiff was underfinancial pressure and needed the money owed
to him by the defendant to pay his workers who were waiting
outside
to be paid, the disparity in their respective economic powers and the
defendant's knowledge that the plaintiff could not
afford a
protracted dispute with the defendant while the defendant could well
afford such a dispute. The defendant knew well that,
as the plaintiff
said:
Op
daardie moment was ek in so 'n probleem, in so 'n probleem die mense
buitekant hulle wag vir my buitekant, hulle soek hulle se
gelde wat
ek nog verskuldig is.
21.
There can further be no doubt that the defendant took advantage of
the plaintiff's situation to persuade him to conclude a transaction

which was to his disadvantage and the manifest unfairness of which
the plaintiff urged, in vain, upon the defendant's representatives.

There remains but one element of the defence of undue influence which
requires examination: that the defendant acted unconscionably
(op
gewetenlose wyse).
22.
The notion of a party acting unconscionably has come before the
courts most noticeably but not exclusively in the context of
the
exceptio doli. Although the exceptio now rests in a peace imposed
upon it by the Appellate Division,
10
the decisions of the courts in exceptio doli cases, as well as other
decisions, provide a guideline for what the courts will regard
as
unconscionable. Common to them all is a substantial degree of
unscrupulousness, an intention to oppress or a departure from
the
values to which right thinking people subscribe in the relevant
context.
23.The
courts of common law jurisdictions have long exercised a power to set
aside or otherwise mitigate contracts in which one
party has acted
unconscionably. Our courts do not of course have such powers but it
is instructive to have regard to what a common
law court would hold
to be unconscionable. In Commercial Bank of Australia Ltd v Amadio,
11
a decision of the High Court of Australia on appeal from a decision
in the Supreme Court of South Australia, Gibbs CJ held
12
that a transaction will be unconscientious within the meaning of the
relevant equitable principles only if the party seeking to
enforce
the transaction has taken unfair advantage of his own superior
bargaining power, or of the position of disadvantage in
which the
other party was placed. The principle of equity applies "whenever
one party to a transaction is at a special disadvantage
in dealing
with the other party because illness, ignorance, inexperience,
impaired faculties, financial need or other circumstances
affect his
ability to conserve his own interests, and the other party
unconscientiously takes advantage of the opportunity thus
placed in
his hands"...
24.
I have no doubt that it is entirely permissible for one party to
exploit the economic weakness of the other when a genuine settlement

of a disputed indebtedness is involved but it is quite another thing
when an economically powerful party withholds what is admittedly

owing to an economically weaker party in order to seek commercial
advantage. Pacta sunt servanda is a prescription that is intimately

connected with the constitutionally protected values of freedom and
human dignity.
13
It follows that to use the threat of breaching a contract to induce
an economically less powerful contractual counterpart to act
to his
disadvantage in relation to an accrued contractual right, the
enforcement of which is not contrary to public policy, is
subversive
of freedom and human dignity. In the present case, the defendant's
conduct furthertrenched upon the plaintiff's constitutional
right to
have his dispute with the defendant adjudicated by fair legal or
other process.
14
In my view the plaintiff has established the element of
unconscionability required. If there were a contract of compromise,
the
plaintiff was entitled to avoid it. Accordingly, the rejoinder of
undue influence must be sustained.
25.
I would dismiss the appeal.
I
agree. It is so ordered.
RD
CLAASSEN
Judge
of the High Court
15
November 2010
For
the appellant:Adv JJ Bitter,
Instructed
by Biccari Bollo Mariano Inc
Johannesburg
No
appearance for the respondent
1
The
Law of Contract in South Africa,
5th
ed.
2
At
p459
3
2002
4 SA 397 SCA
4
1920
AD 644 per Innes CJ.
5
Para
16
6
Para
18
7
2008
3 SA 327 SCA
8
Para
11
9
Patel
v Grobbelaar
1974
1 SA 532 A 533-534
10
Bank
of Lisbon and South Africa Ltd v De Ornelas
1988
3 SA 580 A
11
1983]
HCA 14; (1983) 151 CLR 447
12
Para
18
13
Barkhuizen
v Napier
2007
5 SA 323 CC para 57
14
Section
34 of the Constitution