About SAFLII
Databases
Search
Terms of Use
RSS Feeds
South Africa: Supreme Court of Appeal
SAFLII
>>
Databases
>>
South Africa: Supreme Court of Appeal
>>
2013
>>
[2013] ZASCA 101
|
|
Eskom Holdings Soc Ltd v Hitachi Power Africa (Pty) Ltd and Another (139/2013) [2013] ZASCA 101 (12 September 2013)
Links to summary
THE
SUPREME COURT OF APPEAL OF SOUTH AFRICA
JUDGMENT
C
ase No:
139/2013
Reportable
In the matter between:
ESKOM HOLDINGS SOC LIMITED
.....................................
APPELLANT
and
HITACHI POWER AFRICA
(PROPRIETARY) LTD
.............................................
FIRST RESPONDENT
HITACHI POWER OF EUROPE
GMBH
.....................................................................
SECOND
RESPONDENT
Neutral citation:
Eskom
Holdings v Hitachi Power Africa
(139/2013)
[2013] ZASCA 101
(12
September 2013)
Coram:
Mthiyane AP, Brand,
Shongwe, Majiedt and Petse JJA
Heard: 15 August 2013
Delivered: 12 September 2013
Summary:
Interpretation
of a demand guarantee ─ Notice to contractor not necessary for
employer to present guarantee for payment to
the bank in the case of
an on demand or call guarantee.
_____________________________________________________________________
ORDER
On appeal from:
South
Gauteng High Court, Johannesburg (Kgomo J sitting as court of first
instance):
The appeal is upheld and the
order of the court below is set aside and replaced with the
following:
‘
The
application is dismissed.’
__________________________________________________________
JUDGMENT
MTHIYANE AP (BRAND, SHONGWE,
MAJIEDT AND PETSE JJA CONCURRING):
[1] The outcome of this appeal
turns on the interpretation of demand guarantees that were issued by
Mizhuo Corporate Bank Limited
of Japan (the Bank) in favour of the
appellant (Eskom) to secure performance by the respondents (Hitachi)
of their obligations
under a construction contract concluded between
Eskom and Hitachi during October 2007, for the construction of
certain of the Works
at the Medupi Power Station (Medupi). The
guarantees were issued at the instance of Hitachi. Medupi is a
massive new electrical
power generating station that is being
constructed in the North Western part of the Limpopo Province near
the rural town of Ellisras.
It is agreed between the parties that the
first of its six power generating plants should be online in 2013 and
the last of them
by July 2015.
[2] Hitachi has elected not to
oppose the appeal and to abide the decision of this court. In turn
Eskom is not seeking an order
for costs against Hitachi.
[3] In terms of the construction
contract, Hitachi provided six guarantees drawn on the Bank. Three of
these guarantees are in the
sums of R300 384 946.13, £21 273
236.13 and US$445 838.25, amounting in total to a South African Rand
equivalent of over
R600 million.
[4] On 12 February 2013, Eskom
presented these three guarantees to the Bank for payment. Before the
presentation of the guarantees
a number of disputes had arisen
between the parties concerning the performance by Hitachi of its
obligations under the construction
contract. Eskom alleged that
Hitachi had been guilty of material and ongoing breaches of the
construction contract. It complained
that Hitachi had delayed the
completion of the first operating unit at Medupi. It also claimed
that in view of the said material
breaches, it was entitled to demand
payment under the guarantees.
[5] The correspondence placed
before the high court revealed that since September 2012 there had
been on-going discussions between
the parties, aimed at averting the
calling up of the guarantees by Eskom. The disputes that ensued
culminated in Eskom addressing
a letter to Hitachi on 1 February
2013, accusing them of a failure to effect certain corrections to the
construction work. It alleged
that these corrective steps should have
been undertaken by 31 January 2013. Eskom complained that all these
failures affected its
ability to plan work timeously and negatively
impacted directly or indirectly on the work of other projects by
other contractors.
The letter recorded that Eskom was aware of
Hitachi’s specific challenges to correct all matters of quality
to Eskom’s
satisfaction in accordance with their obligations.
Eskom indicated that it was prepared to postpone its decision to
demand payment
of guarantees up to and until 28 February 2013, on
condition that in the meantime Hitachi remedied the breaches.
[6] In their response, Hitachi
disputed Eskom’s entitlement to demand payment of the
guarantees. In their letter of 8 February
2013, Hitachi denied the
allegations that they lacked clear direction about the management of
matters critical to Medupi. Referring
to earlier discussions between
the parties, that had taken place on 11 December 2012, 16 January
2013 and during the meeting of
6 February 2013 at which quality
issues were discussed, Hitachi expressed the hope that an agreement
with respect to quality would
be reached on or before 28 February
2013. Hitachi not only disputed that Eskom had the right to claim
against payment under the
guarantee but insisted on their alleged
claim being met by Eskom. Hitachi claimed that they had previously
called upon Eskom to
procure an engineer to determine all of its
outstanding claims which were long overdue. The letter is however
silent on Hitachi’s
attitude to the grace period extended by
Eskom not to present demand guarantees up to and until 28 February
2013.
[7] On 13 February 2013 at 23h00,
Hitachi launched an urgent application in the South Gauteng High
Court (Kgomo J), seeking a final
order (a) interdicting Eskom until
28 February 2013 from demanding payment of the guarantees; and (b) to
the extent that the guarantees
may have been paid, directing Eskom to
revoke the said demand and instruct the Bank accordingly and
ancillary relief.
[8] The application for an
interdict was founded on two propositions which are summarised in the
founding affidavit as being, first,
a failure on the part of Eskom to
comply with the terms of the construction contract, and second, a
breach of promise made by Eskom,
namely that it would not present the
guarantees prior to 28 February 2013. In respect of the first of
these causes of action, that
is, that the demand was made in
circumstances contrary to the contract, Hitachi relied on the
contention that prior to making demand,
Eskom was first required to
give Hitachi notice under sub-clause 2.5 of the construction
contract. The clause reads as follows:
‘
If the
Employer considers himself to be entitled to any payment under any
Clause of these Conditions or otherwise in connection
with the
Contract, the Employer or the Engineer shall give notice and
particulars to the Contractor. However, notice is not required
for
payments due under Sub-Clause 4.19 [
Electricity,
Water and Gas
],
under Sub-Clause 4.20 [
Employer’s
Equipment and Free-Issue Material
],
or for other services requested by the Contractor.
The particulars
shall specify the Clause or other basis of the claim, and shall
include substantiation of the amount to which the
Employer considers
himself to be entitled in connection with the Contract.
The Employer may set
off such amounts against moneys due to the Contractor (or to become
due) but only to the extent that such amounts
are liquid and payable
to the Employer by the Contractor under any Clause of these
Conditions or otherwise in connection with the
Contract. This amount
may, without limiting the Employer’s other rights to recover
amounts due to him from the Contractor
(including by having recourse
to the Performance Security and Retention Money or Retention Money
guarantee provided for in Sub-Clause
14.9 [Payment of Retention
Money]), be included as a deduction in the Contract Price and Payment
Certificates. Without limiting
or derogating from the Contractor’s
other rights under the Contract, if the Employer sets off any amounts
due to the Contractor
which are not due and/or payable the Employer
shall be liable to the Contractor for the interest thereon,
calculated at the Stipulated
Interest Rate.’
I will return to the
meaning and effect of sub-clause 2.5 later in the judgment. The
second cause of action was premised on the
proposition that Eskom had
in its letter of 1 February 2013 agreed to waive its rights to make
demand upon the guarantees up to
and until 28 February 2013.
[9] Hitachi’s contention in
respect of the first of these two causes of action found favour with
the high court, and the application
for an interdict as indicated in
paragraph 7, was granted in its favour. The finding was based on the
high court’s reading
of clause 2.5 as requiring Eskom to give
Hitachi notice of its intention to demand payment of the guarantees.
The sub-clause was
interpreted to mean that if Eskom considered
itself entitled to any payment under the contract or in connection
with the contract
it (Eskom) or its engineer should give notice and
particulars to Hitachi, except where sub-clauses 4.19 and 4.20 (which
are not
relevant here) are concerned. The court further found that
the sub-clause required Eskom to specify the clause or other basis of
the claim, and should include substantiation of the amount to which
the employer (Eskom) considers itself entitled in connection
with the
contract.
[10] The court concluded that in
its view, once negotiations break down or any indulgence granted was
withdrawn, Hitachi should
have been given proper and timeous notice
of Eskom’s intention to proceed with the presentation of the
guarantees for payment.
It rejected Eskom’s contention that it
was not required to give notice before calling up the demand
guarantees.
[11] As to Hitachi’s second
cause of action, relating to Eskom’s undertaking not to call up
demand guarantees up to
and until 28 February 2013, the court
rejected the argument advanced on Eskom’s behalf, that its
concession to postpone a
call on the performance securities until 28
February 2013 was merely a proposal that was to be responded to by
Hitachi. The court
favoured a construction contended for by Hitachi,
as to the meaning and effect of the concession, which was that Eskom
was prepared
to hold its horses up to and until 28 February 2013.
[12] Construction guarantees have
been the subject of discussion in a number of decisions of this court
and the high court.
1
It is necessary to establish at
the outset the nature of the guarantee involved in the present
matter. In
Minister of
Transport and Public Works, Western Cape, & another v Zanbuild
Construction
(Pty)
Ltd & another
2011
(5) SA 528
(SCA) para 14,
Brand
JA noted that our law is familiar with two types of guarantees: the
‘conditional guarantee’ and the ‘on
demand
guarantees’ (referred to in English law as ‘conditional
bonds’ and ‘on demand bonds’ respectively).
There
are differences between the two. A claimant under a conditional
guarantee is required, not only to allege but sometimes also
to
establish liability on the part of the contractor for the amount
claimed. An on demand guarantee requires no allegation of liability
on the part of the contractor under the construction contracts. All
that is required for payment is a demand stating the claimant’s
compliance with the terms of the guarantee.
[13] The question in this appeal
is whether the demand guarantee issued in favour of Eskom is, on a
proper interpretation of its
terms, an on demand guarantee or a
conditional guarantee.
[14] In
Lombard Insurance Co
Ltd v Landmark Holdings (Pty) Ltd & others
2010 (2) SA 86
(SCA), Navsa JA had occasion to discuss the nature of an ‘on
demand’ or ‘call guarantee’, where he said
the
following (para 20):
‘
The
guarantee by Lombard is not unlike irrevocable letters of credit
issued by banks and used in international trade, the essential
feature of which is the establishment of a contractual obligation on
the part of a bank to pay the beneficiary (seller). This obligation
is wholly independent of the underlying contract of sale and assures
the seller of payment of the purchase price before he or she
parts
with the goods being sold. Whatever disputes may subsequently arise
between buyer and seller is of no moment insofar as the
bank’s
obligation is concerned . . . The bank undertakes to pay provided
only that the conditions specified in the credit
are met. The only
basis upon which the bank can escape liability is proof of fraud on
the part of the beneficiary.’
[15] The demand guarantee in
question in this appeal has all the characteristics of an ‘on
demand’ or ‘call guarantee’,
which is independent
of the construction contract. The recital of its terms are set out in
clause 3 of the Performance Bond issued
by the Bank. The clause reads
as follows:
‘
3.
A demand for payment under this guarantee shall be made in writing at
the Bank’s address and shall:
3.1 be signed on
behalf of Eskom by the managing director of an Eskom division
(including, for the avoidance of doubt, the managing
director of
Eskom’s Enterprises Division or his successor in title or the
managing director of Generation Division or his
successor in title)
or by any board director of Eskom;
3.2 state the amount
claimed (“the Demand Amount”);
3.3 state that the
Demand Amount is payable to Eskom in the circumstances contemplated
in sub-clause (a), (b), (c) or (d), as applicable
of clause 4.2 of
the Contract.’
In terms of this clause Eskom is
not required to give notice nor is the Bank required to investigate
whether notice was given and
whether Eskom has complied with the
construction contract. In my view it makes business sense for the
terms of the guarantee not
to have required the Bank to embark on
this exercise. A bank is in the business of handling money, not
assessing and evaluating
the merits or demerits of contracts. The
interpretation contended for by Hitachi and endorsed by the court
below would have required
the bank, which was not even a party to the
proceedings, to traverse areas which fall outside the scope of its
authority. Giving
effect to the plain meaning of the clause, I do not
read it as imposing such an onerous duty on the Bank. It merely had
to satisfy
itself that the three requirements set out in clauses 3.1,
3.2 and 3.3 quoted above had been met. The high court’s
insistence
that Eskom should have given Hitachi notice before making
a demand guarantee was erroneous. Clause 4.2(d) of the construction
contract
entitled Eskom to claim under the guarantees in the event of
circumstances which entitled it to terminate the construction
contract
under clause 15.2 irrespective of whether notice of
termination had been given. In the letters of demand, under cover of
which
Eskom called upon the Bank to make payment under the guarantee,
Eskom invoked the provisions of clause 4.2. The clause reads as
follows:
‘
The
Employer shall not make a claim under a Performance Security, except
for amounts to which the Employer is entitled under the
Contract in
the event of:
(a) failure by the
Contractor to extend the validity of the Performance Security as
described in the preceding paragraph, in which
event the Employer may
claim the full amount of the Performance Security and retain the
proceeds as cash security,
(b) failure by the
Contractor to pay the Employer an amount due, as either agreed by the
Contractor or determined under Sub-Clause
2.5 [
Employer’s
Claims
] or Clause 20 [
Claims,
Disputes and Arbitration
], within 42 days
after this agreement or determination,
(c) failure by the
Contractor to commence to remedy a default within 42 days after
receiving the Employer’s notice requiring
the default to be
remedied and thereafter diligently continuing to pursue the remedy of
the default, or
(d) circumstances
which entitle the Employer to termination under Sub-Clause 15.2
[
Termination by Employer
],
irrespective of whether notice of termination has been given.
If it is determined
that the Employer has made a claim under a Performance Security that
it was not entitled to make, the Employer
shall refund the excess
amount claimed and pay interest thereon to the Contractor, calculated
at the Stipulated Interest Rate from
the date on which the amount was
paid to the Employer to the date on which it is refunded to the
Contractor.
The Employer shall
return each Performance Security to the Contractor within 21 days
after receiving a copy of the Performance Certificate
for the
applicable Section.’
[16] Clause 15(2)(a) to (g) of
the construction contract posit a number of discrete situations which
would entitle Eskom to terminate
the construction contract. The
grounds for termination include a material breach of the construction
contract by Hitachi together
with the failure on their part to remedy
such a breach within 30 days after Eskom giving notice of such event
or such longer period
as Eskom may determine. Eskom’s reliance
on sub-clause 15.2(g) and the uncontested allegations of material
breaches on the
part of Hitachi entitled it to call up the
guarantees. That clause reads as follows:
‘
The
Employer shall be entitled to terminate the Contract if the
Contractor:
. . .
(g) materially
breaches the Contract and fails to remedy the same within 30 days
after the Employer giving written notice of the
occurrence of such
event (or, if such remedy cannot be completed in such time, such
longer period as the Employer may determine).’
Clause 15.2 of the construction
contract provides that Eskom is entitled, on the happening of any of
the events described in clauses
15.2(a) to (g) coupled with the
giving of 30 days notice, to terminate the construction contract. On
the plain meaning of clause
4.2 the giving of notice was not a
requirement for the calling up of the guarantee. Similarly, the
requirement of notice under
clause 15.1
2
has no bearing in relation to the
material breach under clause 15.2(g).
[17] Finally under the
requirement of notice provisions of clause 2.5, it has relevance only
in relation to a claim under the guarantee
made in terms of
sub-clause 4.2(b),
dealing
with the circumstances entitling the employer to terminate under
sub-clause 15.2, irrespective of whether notice of termination
has
been given.
[18] The requirements of clause
2.5 are not to be read into the whole of clause 4.2 ─ as did
the high court ─ otherwise
the specific reference to clause 2.5
in sub-clause 4.2(b) would become tautologous. Eskom in this regard
makes no claim for payment
under the construction contract, but in
exercising a right which it has, under the construction contract, to
make demand upon the
Bank in terms of the guarantees themselves.
Hence the obligation to pay arises from the terms of the guarantee
and not from the
conditions of the construction contract to which the
Bank is not a party. Furthermore the provisions of the guarantees,
which gives
rise to an entirely separate cause of action to which
Hitachi is not a party, do not incorporate whether by reference or at
all,
clause 2.5 of the
construction contract nor any like provision.
[19] If one has regard to the
terms of the guarantee in question in the present matter,
the
threshold requirement that Eskom had to meet for claiming payment
under the demand guarantees was low. All that it was required
to show
in order to claim was that the demand for payment under the
guarantee: (a) was signed on behalf of Eskom by the Manager
or
Director of an Eskom Division (including for avoidance of doubt, the
Managing Director of Eskom’s Enterprise Division
or his
successor); (b) stated the amount claimed (the demand amount) and (c)
that the demand amount was payable to Eskom in the
circumstances
contemplated in sub-clauses (a), (b), (c) or (d), as applicable in
clause 4.2 of the contract. (See clauses 3.1,
3.2 and 3.3 of the
performance bond.) On the plain meaning of the clause it is clear
that what was required for a claim to be made
under the demand
guarantee was a signature on the demand guarantee, an indication of
the amount demanded and an assertion by Eskom
that the demand amount
is payable as set out in clause 3.1, 3.2 and 3.3 and this would have
been sufficient. It is clear why this
is so. Clause 4.2 of the
construction contract expressly contemplates that Eskom might make a
demand upon a guarantee in circumstances
where it is not entitled to
do so. On a proper interpretation of the demand guarantee,
Eskom’s entitlement to make
a call upon a guarantee need not be proven at the time the demand is
made. Clause 4.2 provides
instead that if Eskom makes a claim under a
guarantee and it is subsequently shown that it was not entitled to
make such a demand,
it would be obliged to refund the excess amount
claimed and to pay interest thereon to Hitachi, calculated at the
Stipulated Interest
Rate from the date on which the amount was paid
until it is refunded (see
Dormell
Properties 282 CC v Renasa Insurance Company & others NNO
2011
(1) SA 70
(SCA) para 42 where this court dealt with a demand
guarantee in which there was a similar provision). The plain meaning
of the
guarantee allows for no conclusion other than that the
guarantee in question in these proceedings is an on demand or call
guarantee
(see
Zanbuild
Construction
para 12).
The interpretation contended for by Hitachi, which found favour with
the high court, suggesting that Eskom was required
to give notice
before claiming payment upon a demand guarantee was erroneous and
flew in the face of the plain meaning of the terms
of the guarantee
as set out in clauses 3.1, 3.2 and 3.3 read with clause 4.2(d) of the
construction contract (see
Coopers
& Lybrand & others v Bryant
[1995] ZASCA 64
;
1995
(3) SA 761
(A) at 767E-768E).
[20] In my view the high court
misread the demand guarantee and imposed the requirement of notice
which was not provided for in
its terms.
[21] As to the reliance by
Hitachi on the undertaking given by Eskom not to call up the demand
guarantees up to and until 28 February
2013, it does not appear that
the high court made any specific finding in this regard but merely
made a passing reference by remarking
that Hitachi’s
interpretation of what was said about 28 February 2013 was more
plausible than Eskom’s interpretation
of the demand guarantee.
Nowhere does the high court say that Eskom was bound by the
undertaken given. If regard is had to the
wording of Eskom’s
letter of 1 February 2013 and Hitachi’s response to it, it
cannot be said that Eskom waived its
rights to claim on demand
guarantees up to and until 28 February 2013. Instead of indicating
that it was accepting Eskom’s
extension of time until 28
February 2013, Hitachi elected to unleash on Eskom a litany of
issues, comprising of denials and claims.
Hitachi never addressed
itself to the question whether it was prepared to rectify matters
raised by Eskom before the cut-off date
of 28 February 2013. I do not
think that it lies in the mouth of Hitachi to now rely on the
indulgence given by Eskom in order
to avoid the consequences of the
call up of a demand guarantee. It follows that Hitachi must also fail
on this cause of action.
[22] There is yet another
question that needs consideration, and that is the question of
mootness. The cut-off date (28 February
2013) by which the call up of
the guarantee had to be made has come and gone. It may be said that
the matter has therefore become
moot and that any judgment or order
that this court might make will have no practical effect. In terms of
s 21A(1) of the Supreme
Court Act 59 of 1959, this court is empowered
in those circumstances to dismiss an appeal on that ground alone.
There can be no
question however that it is in the public interest
for this court to pronounce on the question of guarantees in this
matter. Eskom
is a public body, dealing with a matter which is of
great public interest in this country ─ the supply of
electricity ─
and is currently involved in a number of similar
contracts. It is important for this court to offer guidance on the
interpretation
and application of similar demand guarantees Eskom has
concluded with other contractors. In my view despite the suggestion
that
this matter might be moot, there is a practical need for this
court to express a view on the interpretation of the demand
guarantees
in question in this appeal on a matter of wide public
interest. (Cf
Western Cape Education Department & another v
George
1998 (3) SA 77
(SCA) at 84E-E;
Natal Rugby Union v
Gould
[1998] ZASCA 62
;
1999 (1) SA 432
(SCA) at 24J.)
[23]
It also bears mention that
Hitachi sought and was granted a final interdict, in circumstances
where it failed to satisfy the requirements
for the granting of a
final interdict. In my view the application should have been
dismissed on that ground as well. The most obvious
missing elements
in Hitachi’s case was its failure to establish that it had
suffered ‘irreparable harm’ and ‘the
absence of any
other remedy or relief’, leaving aside the question of a ‘clear
right’ see
Director of Public Prosecutions (Western Cape) v
Midi Television (Pty) Ltd t/a E TV
2006 (3) SA 92
(C) para 34.
The high-water mark of Hitachi’s case on the requirement of
irreparable harm was that they would have had to
pay interest on the
guarantees. This part of Hitachi’s case, however, flounders in
the face of that portion of clause 4.2
which allowed Hitachi to
recover not only the capital amount paid out under the guarantees,
but additionally interest paid at the
stipulated rate. The contract
also made provision for dispute resolution mechanisms and there can
therefore be no question of Hitachi
having met the requirements of
absence of any other remedy or relief for them to claim entitlement
to a final interdict. In my
view Hitachi should have failed on all
fronts in the high court.
[24] In the result the appeal is
upheld and the order of the court below is set aside and replaced
with the following:
‘
The
application is dismissed.’
__________________
K K MTHIYANE
ACTING PRESIDENT
APPEARANCES
For Appellant: B E Leech SC (with
him E Mokutu)
Instructed by: Bowman Gilfillan
Inc, Sandton
Matsepes Inc, Bloemfontein
For Respondents: N J Roodt
(watching brief)
Instructed by: Fasken Martineau
(Incorporated in SA as Bell Dewar Inc), Sandton
Webbers Attorneys, Bloemfontein
1
Dormell
Properties 282 CC v Renasa Insurance Company Ltd & others NNO
2011 (1) SA 70
(SCA
);
Lombard Insurance Co Ltd v Landmark Holdings (Pty) Ltd & others
2010 (2) SA 86
(SCA);
Basil
Read (Pty) Ltd v Beta Hotels (Pty) Ltd & others
2001
(2) SA 760
(C).
2
‘
If
the Contractor fails to carry out any obligation under the Contract,
the Engineer may by notice require the Contractor to make
good the
failure and to remedy it within a specified reasonable time.’