Optipower a trading division of Murray & Roberts Limited v Goldwind 4RE SA (Pty) Ltd (016154-2022) [2023] ZAGPJHC 794 (17 July 2023)

80 Reportability
Civil Procedure

Brief Summary

Arbitration — Stay of proceedings — Special plea — Plaintiff sought summary judgment for payment under certified interim payment certificate; defendant raised special plea invoking arbitration clause, claiming entitlement to set off for delay damages — Court held that summary judgment application must be determined first, as it concerns a liquid claim, while the defendant's claim for delay damages is subject to arbitration — No factual disputes regarding the plaintiff's claim; the dispute centers on whether the amount claimed is due and payable in light of the defendant's arbitration proceedings.

Comprehensive Summary

Summary of Judgment


1. Introduction


The proceedings comprised two interlocutory applications set down for hearing on the same date in pending action proceedings in the Gauteng Division, Johannesburg. The first application was the plaintiff’s application for summary judgment. The second was the defendant’s application in terms of Uniform Rule 33(4) for the separation of a special plea and, in addition, the determination of that separated special plea.


The parties were Optipower, a trading division of Murray & Roberts Limited (plaintiff/applicant in the summary judgment application) and Goldwind 4RE SA (Pty) Ltd (defendant/respondent in the summary judgment application and applicant in the separation application). For convenience, the court referred to the parties as “plaintiff” and “defendant”.


The underlying action was instituted by the plaintiff on 19 August 2022 for payment of a certified interim payment certificate (“IPC 20”) issued under a written electrical balance of plant contract concluded in November 2018 for the Golden Valley Wind Energy Power Project. The defendant raised the arbitration issue by way of a special plea delivered on 20 September 2022, relying on the contract’s arbitration clause and seeking a stay of the action. Separately, the defendant applied to have that special plea separated and determined first.


The general subject-matter of the dispute concerned the enforceability in court (including by summary judgment) of a certified interim payment certificate that was common cause to be liquid, in circumstances where the defendant asserted an arbitrable delay liquidated damages claim which (if upheld) might defeat or extinguish the plaintiff’s claim, and where overlapping issues were already before an arbitration tribunal.


2. Material Facts


A written contract governing the works was concluded between the parties during November 2018. Under that contract, an interim payment certificate, IPC 20, was issued and certified on 17 December 2020 in the amount of R25 134 704.89 (including VAT). Following certification, the plaintiff issued tax invoice 2132, and it was common cause that payment under IPC 20 fell due on 1 February 2021.


The court treated as undisputed the conclusion of the contract, the relevant contractual terms for interim certification, the issuing and certification of IPC 20 for the amount claimed, and the fact that IPC 20 was a liquid document. It was also common cause that the plaintiff issued the required invoice, and that there were no factual disputes directed at the validity, authenticity, or correctness of IPC 20 as certified.


The dispute arose from the defendant’s contention that the plaintiff had delayed completion of various contractual sections by a total exceeding 3000 days, triggering delay liquidated damages calculated at 0.1% of the contract price per day, capped at 20% of the contract price. The defendant asserted it was entitled to R58 722 429.00 (the contractual cap) and delivered a tax invoice to the plaintiff on 16 February 2021 reflecting payment due on 19 March 2021.


The defendant instituted arbitration proceedings in respect of the delay damages claim on 15 August 2022. The plaintiff disputed that claim and delivered counterclaims on 7 October 2022, including a dispute about the contract price and a monetary claim (including ancillary relief) in an amount stated in the judgment as R69 763 792.84, and elsewhere reflecting that in the arbitration the plaintiff claimed R96 763 792.84 as owing. The arbitration was pending before a tribunal of three arbitrators.


In the action, the defendant did not bring a timeous application for a stay under section 6(1) of the Arbitration Act 42 of 1965 before pleading. Instead, it delivered a special plea invoking the contract’s arbitration clause (clause 22) and seeking an order that the plaintiff’s claim be stayed pending arbitration, alternatively pending determination of the defendant’s delay damages claim in the arbitration.


It was not disputed that IPC 20 had also been raised in the arbitration pleadings and that the plaintiff’s counterclaim in arbitration included the amount reflected in IPC 20, with the contract price itself being in dispute in the arbitration.


3. Legal Issues


The court was required to determine, first, the procedural sequencing of the two enrolled applications: whether the summary judgment application should be determined before the defendant’s Rule 33(4) separation application and special plea adjudication, or vice versa.


On the merits, the central questions were whether the defendant’s special plea and the existence of the arbitration dispute disclosed a bona fide defence or triable issue sufficient to defeat summary judgment, notwithstanding that the plaintiff’s claim was founded on a certified interim payment certificate accepted to be a liquid document.


After the separation application succeeded, the court further had to decide the separated special plea: whether the plaintiff’s court claim was one “in respect of any matter agreed to be referred to arbitration” and, if so, whether the court should grant a stay of the action under section 6 of the Arbitration Act 42 of 1965. This entailed an evaluative assessment of whether there was “sufficient reason” not to stay the court proceedings, and whether the overlap between the action and arbitration justified a stay.


The dispute thus involved a combination of application of legal principles to largely common-cause facts (summary judgment requirements; the effect of an arbitration clause; the discretion to stay proceedings), and a case-management/value judgment as to convenience under Rule 33(4) and the appropriateness of a stay to avoid inconsistent determinations across forums.


4. Court’s Reasoning


The court first addressed the order in which the applications should be heard. Although the parties accepted they should be heard together, they disagreed on sequencing. The court treated the applications as “separate and distinct” and considered that deciding summary judgment first would allow the defendant to rely on the content of its summary judgment opposing affidavit. The court reasoned that, if the separation and special plea were determined first, the defendant would be confined to the special plea’s content. On that basis, the court determined that the summary judgment application should be decided first, and only if it failed would it be necessary to determine the separation application (though, as the judgment unfolded, the separation application was then dealt with after summary judgment was refused).


In considering summary judgment, the court applied the established principle that summary judgment is not designed to deprive a defendant with a triable issue or sustainable defence of a trial. The court reiterated that it was not required to decide the probabilities or finally determine the merits of the defence. The enquiry was whether the defendant had fully disclosed the nature and grounds of the defence and the material facts upon which it was founded, and whether the defence was bona fide and good in law.


The court accepted as common cause that a certified interim payment certificate is a liquid document, equated in effect to an acknowledgement of debt, and further accepted that the existence of an arbitration clause does not, in itself, bar summary judgment. The court nevertheless located the real controversy in whether IPC 20 was presently due and payable given the pending delay damages dispute and the defendant’s set-off contentions.


The defendant relied on the broadly framed arbitration clause (clause 22), together with the definition of “dispute” in clause 1.2.66, which encompassed any question, controversy, or matter arising under or in connection with the contract, including interpretation. The court considered that the interpretative issues and the delay damages claim were arbitrable disputes, and that those issues were already before the arbitration tribunal.


While the plaintiff argued that the defendant’s delay damages claim was irrelevant to the plaintiff’s liquid claim because it was not yet “fixed and payable” (and thus could not operate as set-off), the court did not regard that contention as decisive at the summary judgment stage. The court reasoned that, even if set-off did not presently apply (and even if the liquid/illiquid character of the delay damages claim remained to be determined in arbitration), the delay damages claim and associated interpretation disputes could materially affect whether the plaintiff was entitled to immediate payment, and could potentially defeat the plaintiff’s claim if the claim were ultimately extinguished. This sufficed to establish a triable issue.


The court further took into account that IPC 20 and related monetary issues featured in the arbitration pleadings, and that the contract price was in dispute in arbitration. The court regarded there as being merit in the defendant’s concern that two different forums were being asked to determine overlapping questions about the parties’ obligations and liabilities, creating a risk of inconsistent findings between the court and the arbitral tribunal if the action proceeded. In that context, and applying the summary judgment threshold, the court held the defendant had disclosed a defence that was bona fide and legally tenable for purposes of resisting summary judgment.


Turning to the Rule 33(4) separation application, the court set out the text and purpose of Rule 33(4), namely the separate determination of a question of law or fact where it may be conveniently decided apart from others, to shorten proceedings. The court applied the approach that a separation should be granted unless the questions cannot conveniently be decided separately, with “convenience” understood as fairness and appropriateness to all parties. Given that the special plea raised a distinct question of law and fact, and that this was undisputed, the court was persuaded that it was convenient to separate and determine it.


On the separated special plea, the court identified the central issues as whether the plaintiff’s claim had to be referred to arbitration or whether it should be stayed pending arbitration. The court emphasised that the defendant had not availed itself of section 6(1) in the procedural manner contemplated (having taken further steps), but accepted that raising the issue by special plea was permissible while also noting that this meant the defendant did not challenge the court’s jurisdiction.


The court rejected the defendant’s contention that the plaintiff’s claim itself should be referred to arbitration on the basis that non-payment of an undisputed certified amount did not, merely by itself, create a “dispute” that required referral to arbitration. The court observed that, if a claim were referred, it would be for the arbitrators to determine jurisdiction and propriety of referral. The court then treated the real question as whether a stay should be granted.


In assessing the stay, the court referred back to its earlier discussion (in the summary judgment context) concerning the overlap of issues and the pending arbitral determination of delay damages and set-off-related interpretation questions. The court also noted that because the action was launched after the arbitration was instituted, the defendant could not invoke Uniform Rule 22(4) to have a counterclaim determined together with the claim in the action, which the court treated as contributing to a tactical imbalance in favour of the plaintiff. The court accepted that this tactical advantage was a factor supporting a stay.


The court stressed that the merits and prospects of success of the delay damages claim were not for it to decide, and that the arbitration tribunal would determine the interpretational issues and whether set-off was available to defeat the plaintiff’s claim. On that basis, the court upheld the special plea in its alternative form and granted a stay of the action pending arbitration on the defendant’s delay liquidated damages entitlement.


5. Outcome and Relief


The court refused the plaintiff’s application for summary judgment, holding that the defendant had disclosed a bona fide defence and triable issue arising from the pending arbitrable delay damages dispute and the risk of inconsistent findings across forums. Costs followed the result.


The court granted the defendant’s application under Rule 33(4), ordering that the defendant’s special plea be separated for determination. The plaintiff was directed to pay the costs of the separation application.


The court upheld the defendant’s special plea (in its alternative formulation) and stayed the plaintiff’s claim in terms of section 6(1) of the Arbitration Act 42 of 1965 pending determination by arbitration of the defendant’s entitlement to delay liquidated damages. Costs were awarded against the plaintiff.


Cases Cited


Joob Joob Investments (Pty) Ltd v Stocks Mavundla Zek Joint Venture 2009 (5) SA 1 (SCA).


Maharaj v Barclays National Bank Ltd 1976 (1) SA 418 (A).


PLC Consulting (Pty) Ltd t/a Phillips Consulting SA v Tresso Trading 119 (Pty) Ltd 2009 (4) SA 68 (SCA).


Capricorn Beach Home Owners Association v Potgieter (752/2012) [2013] ZASCA 116 (19 September 2013).


Schierhout v Union Government (Minister of Justice) 1926 AD 286.


Lappeman Diamond Cutting Works (Pty) Ltd v MIB Group (Pty) Ltd (No 1) 1997 (4) SA 908 (W).


Legislation Cited


Arbitration Act 42 of 1965, section 6(1) and section 6(2).


Rules of Court Cited


Uniform Rule of Court 33(4).


Uniform Rule of Court 22(4).


Held


The court held that, despite the plaintiff’s reliance on a certified interim payment certificate accepted to be a liquid document, the defendant’s disclosure of a pending arbitrable delay liquidated damages dispute and associated set-off and interpretation issues raised a bona fide defence and triable issue sufficient to defeat summary judgment.


The court held further that it was convenient under Rule 33(4) to separate and determine the defendant’s special plea, and that while the plaintiff’s claim was not ordered to be referred to arbitration as such, the action should be stayed under section 6(1) of the Arbitration Act 42 of 1965 pending the arbitration’s determination of the defendant’s entitlement to delay liquidated damages.


LEGAL PRINCIPLES


A defendant resisting summary judgment is not required to prove its defence on a balance of probabilities. The defendant must disclose fully the nature and grounds of the defence and the material facts upon which it is founded, and the court must be satisfied that the defence is bona fide and good in law, without deciding the merits.


The existence of an arbitration clause does not, in itself, preclude summary judgment. However, where the defendant raises an arbitrable dispute that bears on whether the plaintiff’s claim is due and payable, and where that dispute may ultimately defeat or extinguish the claim, this can constitute a triable issue sufficient to refuse summary judgment.


A certified interim payment certificate was treated as a liquid document, comparable in effect to an acknowledgement of debt; nonetheless, disputes concerning contractual entitlements (including delay liquidated damages and any set-off implications) may still bear on enforceability and timing of payment.


Under Uniform Rule 33(4), a court should order the separate determination of a question of law or fact if it may conveniently be decided separately, with “convenience” understood as fairness and appropriateness to the parties and the efficient conduct of proceedings.


Section 6 of the Arbitration Act 42 of 1965 empowers a court to stay legal proceedings brought in respect of a matter agreed to be referred to arbitration if there is no sufficient reason not to refer the dispute to arbitration, and the court may impose terms it considers just. Where overlapping issues are already before an arbitration tribunal and there is a risk of inconsistent determinations, a stay may be justified pending arbitration.

About SAFLII
Databases
Search
Terms of Use
RSS Feeds
South Africa: South Gauteng High Court, Johannesburg
SAFLII
>>
Databases
>>
South Africa: South Gauteng High Court, Johannesburg
>>
2023
>>
[2023] ZAGPJHC 794
|

|

Optipower a trading division of Murray & Roberts Limited v Goldwind 4RE SA (Pty) Ltd (016154-2022) [2023] ZAGPJHC 794 (17 July 2023)

REPUBLIC OF SOUTH
AFRICA
IN THE HIGH COURT OF
SOUTH AFRICA
GAUTENG DIVISION,
JOHANNESBURG
CASE NUMBER:
016154-2022
NOT REPORTABLE
NOT OF INTEREST TO
OTHER JUDGES
NOT REVISED
In
the matter between:
OPTIPOWER
A TRADING DIVISION OF MURRAY & ROBERTS
LIMITED
APPLICANT
And
GOLDWIND
4RE SA (PTY) LTD
RESPONDENT
JUDGMENT
Delivered:
This
judgment was handed down electronically by circulation to the
parties’ legal representatives by e-mail. The date and
time for
hand-down is deemed to be 10h00 on the 17th of July 2023.
DIPPENAAR J
:
[1]
For ease of reference the parties will be referred
to as plaintiff and defendant. There are two applications which have
been enrolled
for hearing on the same date. A summary judgment
application launched by the plaintiff and an application launched by
the defendant
for the separation of its special plea under r 33(4).
In addition to the separation of its special plea, the defendant
seeks its
adjudication.
[2]
These applications concern action proceedings
instituted by the plaintiff against the defendant for payment of a
certified interim
payment certificate (“IPC 20”) issued
on 17 December 2020. The certificate was issued in relation to a
written electrical
balance of plant contract pertaining to the Golden
Vally Wind Energy Power Project, concluded between the parties during
November
2018. IPC 20 was issued and certified in an amount of
R25 134 704.89 (inclusive of VAT). Pursuant to the
certification
of the amount as due, owing and payable, the plaintiff
issued tax invoice 2132 for payment of such amount.
[3]
The background facts are not contentious and are
by and large common cause. The conclusion of the contract, its terms
and the certification
of IPC 20 in the amount claimed are common
cause. There are no factual disputes between the parties pertaining
to the plaintiff’s
claim. The parties are in agreement that IPC
20 is a liquid document and that the amount reflected therein fell
due for payment
on 1 February 2021, pursuant to the issuing of an
invoice for payment of the amount. It is also common cause that the
plaintiff
issued an invoice as required by the contract.
[4]
Disputes arose between the parties pertaining to
the defendant’s entitlement to delay liquidated damages (“delay
damages”)
under the contract. The defendant’s case is
that the plaintiff delayed in achieving the completion dates for each
of the
sections of the contract by a total amount in excess of 3000
days. The formula in the contract is that if the works are late,
delay
damages would be calculated at 0.1% of the contract price per
day, subject to a cap of 20% of the contract price. The defendant

contends that the amount due to it is R58 722 429.00,
representing the 20% contractual cap. A tax invoice was delivered
to
plaintiff on 16 February 2021 for that amount, stating that payment
was due to the defendant on 19 March 2021.
[5]
The
defendant instituted arbitration proceedings in respect of that claim
on 15 August 2022. The plaintiff disputed the claim and
instituted
various counterclaims on 7 October 2022 in terms of which it denies
liability for the delay damages. The plaintiff
inter
alia
,
seeks
[1]
an award determining
the contract price to be R336 003 038.79, payment of an
amount of R69 763 792.84 and ancillary
relief. The
arbitration proceedings are pending before a tribunal of three
arbitrators.
[6]
The
present action was launched by the plaintiff on 19 August 2022. The
defendant did not immediately apply for a stay of proceedings
[2]
under s 6(1) of the Arbitration Act
[3]
.
Instead, it raised the arbitration issue by means of special plea on
20 September 2022. The nub of the special plea is that the
defendant
invokes reliance on clause 22 of the contract which contains an
arbitration clause. It seeks an order that the plaintiff’s

claim falls to be stayed in terms of s 6(1) of the Arbitration Act
[4]
pending the referral of the plaintiff’s claim to arbitration,
alternatively pending the determination of its claim for delay

damages in the arbitration proceedings.
[7]
The plaintiff’s case in sum is that IPC 20
constitutes a separate cause of action and that there is no dispute
in relation
thereto which can be referred to arbitration. It argues
that as the defendant’s claim is not liquidated, no set off can
take
place as it would only exist if and when an award is made in the
defendant’s favour in the arbitration.
[8]
Defendant’s case in sum is that the
plaintiff’s claim for payment under IPC 20 is not due or
payable, which is a dispute
within the meaning of clause 1.2.66 of
the contract and that, as such it should have referred its claim to
arbitration. It argues
that the amount due by the plaintiff to it in
respect of the delay damages exceeds the value of IPC 20 and the
defendant enjoys
the principles of set off. After set off of the
delay damages, the plaintiff would be indebted to it in an amount of
R6 214 552.06
and the plaintiff’s claim would be
extinguished. As its claim is presently subject to arbitration, it
was not raised as a
counterclaim. It is argued that even if the
defendant is wrong, judgment on its claim falls to be stayed until
the determination
of the delay damages claim. Lastly, the defendant
contends that the plaintiff’s claim under IPC 20 is already
part of the
arbitration proceedings, given that IPC 20 has been
raised in the pleadings and the plaintiff has claimed the difference
between
the contract price and the amount paid therein in its
counterclaim and has in the process claimed payment of IPC 20
therein. The
contract price is in dispute between the parties in the
arbitration proceedings.
[9]
The first issue to determine is the order in which
the applications are to be determined. Whilst the parties are in
agreement that
the applications must be heard together they are in
dispute as to the order in which the applications should be heard.
The plaintiff
contends that the summary judgment should be heard
first as it was lodged first in time and that the separation
application is
incompetent, subverts the summary judgment procedure
and constitutes a delaying tactic.
[10]
The defendant on the other hand argues that the
special plea raises a distinct issue of law and fact which
conveniently should be
decided separately. It further contends that
to avoid delay, the special plea should be determined first and only
thereafter the
summary judgment application insofar as the special
plea is not upheld. The defendant argues that the question whether
the plaintiff’s
claim should be referred to arbitration is a
serious question requiring resolution prior to the court hearing the
summary judgment
application and that if it ought to be so referred,
the defendant has a legal right to have the claim so referred and to
have the
arbitration question decided first before any enquiry into
summary judgment.
[11]
It must be borne in mind that the applications are
separate and distinct. Although the separation application is
referred to by
the defendant in the summary judgment agreement, that
does not constitute a defence to the plaintiff’s claim. That
much is
undisputed.
[12]
Having considered all the facts, I conclude that
it is appropriate that the summary judgment application must be
determined first,
so that the defendant may rely on the contents of
the affidavit delivered in opposition thereto. Only if that
application is unsuccessful,
would the separation application require
determination. Were the separation application be determined first
and, if granted, the
special plea, the defendant could only rely on
the content of the special plea.
The summary judgment
application
[13]
The
summary judgment procedure is not intended to deprive a defendant
with a triable issue or a sustainable defence of its day in
court.
[5]
In the context of summary
judgment, the special plea must be considered as to whether it raises
a
bona
fide
defence
to the plaintiff’s claim or raises a triable issue. In those
proceedings, a court does not attempt to decide those
issues or
determine whether there is a balance of probabilities in favour of
the defence raised. All a court enquires into is whether
the
defendant has fully disclosed the nature and grounds of his defence
and the material facts upon which it is founded and whether
on the
facts so disclosed the defence is both
bona
fide
and
good in law.
[6]
[14]
The plaintiff contends that the defendant’s
claim for delay damages is irrelevant to its liquid claim. It argues
that the
defendant’s claim can only be set off insofar as the
defendant brings itself within the ambit of the terms of the
contract.
Its case is that the contract expressly envisages that any
deductions to which the defendant is entitled are to be accounted for

in the amount certified, otherwise it is to be catered for in
subsequent interim payment certificates. It further argues that
insofar as defendant seeks to invoke the defence of set off outside
the interim payment certificate, an entitlement to its claim
for the
delay damages is being pursued in arbitration and it is not yet fixed
as payable. The claim would only be payable if and
when the
arbitration tribunal issues an award on its claim. It argues that as
the defendant has failed to demonstrate compliance
with clauses 5.6.3
and 5.6 4 and has not made the necessary averments on this issue in
its affidavit, the defendant has not illustrated
a bona fide defence
to plaintiff’s claim.
[15]
It is
well established that a dispute has to exist before it can be
referred to arbitration
[7]
and
that the existence of an arbitration clause is no bar to summary
judgment.
[8]
It is common cause
that a certified interim payment certificate is a liquid document,
the equivalent of an acknowledgement of debt.
[9]
[16]
Whilst there are no factual disputes regarding the
plaintiff’s claim under IPC 20 and its validity, authenticity
and correctness,
the dispute centres around whether IPC 20 is due and
payable, given that the defendant has raised a claim for delay
damages in
the arbitration.
[17]
The defendant relies on clause 22 of the contract
concluded between the parties which contains an arbitration clause in
terms of
which either party may refer a dispute of any kind
whatsoever in connection with or arising out of the contract to
arbitration
in terms of clause 22.3 pursuant to the provisions of
clause 22. It argues that its entitlement to set off is a dispute as
envisaged
by the clause. It further argues that its interpretation of
the contract pertaining to delay damages is an arbitrable dispute.
The latter contention is not disputed and that claim is already the
subject matter of the arbitration.
[18]

Dispute” is defined in clause 1.2.66
of the agreement as:

any
question, claim, controversy, matter, dispute or difference of
whatever nature howsoever arising under, out of in connection
with
the contract, including breach, effectiveness, validity,
interpretation or termination hereof”.
[19]
The clause is widely worded. It is not for present
purposes necessary or appropriate to determine the defendant’s
argument
that its delay damages claim is a liquidated debt as it is
capable of easy calculation, based on an exercise in interpretation
of the contract and that set off operates automatically under clause
7.13 of the contract. I agree with the defendant that the
interpretation issue and its claim for delay damages are arbitrable
disputes.
[20]
Although
the interpretation issue is relevant to the defendant’s claim
and not to that of the plaintiff, it is relevant to
the issue whether
the plaintiff is entitled to payment of the amount claimed in the
present action and thus whether the plaintiff’s
claim is due
and payable. Even if the delay damages claim is not liquidated and
set off does not presently apply
[10]
and such issue is to be determined in the arbitration proceedings, it
will have an impact on the plaintiff’s entitlement
to payment
of IPC 20. Even if the claim is not liquidated, it may still
ultimately defeat the plaintiff’s claim if that claim
is
extinguished. That raises a triable issue.
[21]
It can thus not be concluded, as argued by the
plaintiff, that the defendant has not raised any
bona
fide
defence or triable issue, because
the claim for delay damages is irrelevant to its liquid claim as it
is not yet fixed and payable.
It is not appropriate to comment on the
issues which will be determined in the arbitration or the various
arguments raised by the
respective parties. It is open to the parties
to raise such arguments in the arbitration proceedings.
[22]
It must further be borne in mind that the
defendant further relied on the plaintiff’s claim already
forming part of the pleadings
in the arbitration proceedings. It was
not disputed by the plaintiff that IPC 20 has been raised in its plea
in those proceedings
and that the amount claimed by it as one of its
counterclaims includes the amount set out in IPC 20. In those
proceedings the contract
price is in dispute and the plaintiff claims
an amount of R96 763 792.84 as owing to it. The plaintiff
delivered its
statement of defence and counterclaims after the
defendant delivered its plea in the present proceedings.
[23]
There is thus merit in the defendant’s
argument that two different forums are called upon to determine the
various disputes
and that the issues which the plaintiff seeks the
court to determine in its summary judgment application are already
before the
arbitration tribunal. Thus, unless the action is stayed,
there is a risk of different findings by the arbitration tribunal and
the court on the issues raised in the claims and counterclaims as to
the obligations and liabilities of the parties to each other.
[24]
It must be borne in mind that for purposes of
summary judgment, the defendant is not obliged to prove its claim on
the probabilities.
It merely has to fully disclose the nature and
grounds of its defence and the material facts upon which it is
founded. It must
for present purposes be concluded that on the facts
so disclosed, the defence is both
bona
fide
and good in law.
[25]
For these reasons I conclude that the summary
judgment application must fail. There is no reason to deviate from
the normal principle
that costs follow the result
The separation
application.
[26]
Rule 33(4) in relevant part provides:

If
in any pending action…..it appears to the court…that
there is a question of law or fact which may conveniently
be decided
separately from any other question, the court may make an order
directing the disposal of such question in such manner
as it may deem
fit and may order that all further proceedings be stayed until such
question has been disposed of, and the court
shall on the application
of any party make such order unless it appears that the questions
cannot conveniently be decided separately”.
[27]
Where a party applies for a separation, a court
must grant an order for separation unless it appears that the
questions cannot conveniently
be decided separately. The purpose of
the rule is to shorten the trial proceedings.
[28]
The
defendant argues that separation is convenient and in the interests
of judicial economy. It is trite that “convenience”

denotes fairness and appropriateness to all the parties
concerned.
[11]
[29]
It is undisputed that the special plea raises a
distinct question of law and fact, which may be conveniently decided
separately.
[30]
Considering the facts, I am persuaded that it is
convenient to have the special plea determined separately.
[31]
It
follows that the application must succeed. There is no reason to
deviate from the normal principle that costs follow the result.
The defendant’s
special plea
[32]
The central issues are whether the plaintiff’s
claim must be referred to arbitration or whether the plaintiff’s
claim
should be stayed pending the determination of the arbitration
proceedings.
[33]
Section 6 of the Arbitration Act provides:

6(1)
If any party to an arbitration agreement commences any legal
proceedings in any court (including any inferior court) against
any
other party to the agreement in respect of any matter agreed to be
referred to arbitration, any party to such legal proceedings
may at
any time after entering appearance but before delivering any pleading
or taking any other steps in the proceedings, apply
to that court for
a stay of such proceedings.
(2) If on any such
application the court is satisfied that there is no sufficient reason
why the dispute should not be referred
to arbitration in accordance
with the agreement, the court may make such an order staying such
proceedings subject to such terms
and conditions as it may consider
just”.
[34]
In the
present instance, the defendant did not avail itself of s 6(1) but
rather took further steps in the proceedings and raised
the issue by
way of special plea. That is permissible
[12]
but means that the defendant did not challenge the court’s
jurisdiction.
[35]
I do not agree with the defendant’s argument
that the plaintiff’s claim should be referred to arbitration.
The defendant’s
failure to pay the undisputed amount reflected
in IPC 20 itself does not itself constitute a dispute that requires
the issue of
payment to be referred to arbitration.  If the
claim is referred to arbitration, it is for the arbitrators to
determine whether
they have jurisdiction to entertain it and whether
such issue was properly referred to them.
[36]
The real issue is whether the plaintiff’s
claim should be stayed as sought by the defendant in the alternative.
I have already
dealt with the special plea in the context of the
summary judgment application, which remains apposite to the present
application.
[37]
Given that the defendant was not able to raise its
delay damages claim as a counterclaim in the present proceedings,
launched after
institution of the arbitration proceedings, the
provisions of r 22(4) are not available to it to seek a court
exercising its discretion
in favour of postponing the plaintiff’s
claim pending determination of its counterclaim, so that both claims
are heard together.
[38]
I agree with the defendant that in this context it
does not matter whether the delay damages claim is liquid or illiquid
and that
the plaintiff now has a tactical advantage. This is a factor
militating in favour of granting a stay.
[39]
It is undisputed that the defendant’s claim
and its entitlement to apply set off are to be determined in the
pending arbitration
proceedings.  It is not for this court to
express a view about the prospects of success of the defendant’s
delay damages
claim. The arbitration tribunal will determine it in
due course. All the arguments raised by the plaintiff will be
available to
it in the arbitration proceedings. It is also for the
arbitration tribunal to decide the interpretational issues under the
contract
and whether set off is available to the defendant to defeat
the plaintiff’s claim.
[40]
I conclude that the special plea must be upheld.
It follows that the defendant is entitled to a stay of
plaintiff’s
claim as sought in the alternative. There is no
reason to deviate from the normal principle that costs follow the
result.
[41]
I grant the following order:
[1] The plaintiff’s
application for summary judgment is refused with costs
[2] The defendant’s
special plea is separated under rule 33 (4);
[3] The plaintiff is
directed to pay the costs of the separation application;
[4] The defendant’s
special plea is upheld with costs;
[5] The plaintiff’s
claim is stayed in terms of
s 6(1)
of the
Arbitration Act 42 of 1965
pending the determination by way of arbitration of the defendant’s
entitlement to delay liquidated damages.
EF DIPPENAAR
JUDGE OF THE HIGH
COURT JOHANNESBURG
APPEARANCES
DATE
OF HEARING
:  09 May 2023
DATE
OF JUDGMENT
:  17 July 2023
PLAINTIFF’S
COUNSEL
Adv.
W G La Grange SC
Adv.
AC Russell
PLAINTIFF’S
ATTORNEYS
:
Tiefenthaler
Attorneys Inc.
Mr
M Van der Schyf
DEFENDANT’S
COUNSEL
:
Adv.
P Carstensen SC
Adv.
KD Iles
DEFENDANT’S
ATTORNEYS
:
Edward
Nathan Sonnenbergs Inc.
Mr
J Haydock
[1]
In Claim 3: Measurement and evaluation of work performed
[2]
PLC Consulting Services para [7]
[3]
42 of 1965
[4]
42 of 1965
[5]
Joob Joob Investments (Pty) Ltd v Stocks Mavundla Zek Joint Venture
2009 (5) SA 1
(SCA) para [32]
[6]
Maharaj v Barclays National Bank Ltd
1976 (1) SA 418
(A) at 423 F-G
[7]
PLC Consulting (Pty) Ltd t/a Phillips Consulting SA v Tresso Trading
119 (Pty) Ltd
2009 (4) SA 68
(SCA) para [7]
[8]
Joob Joob para [17]
[9]
Joob Joob paras [27]-[28] and the authority cited therein
[10]
Capricorn Beach Home Owners Association v Potgieter (752/2012)
[2013] ZASCA 116
(19 September 2013) para [13] with reference to
Schierhout v Union Government (Minister of Justice)
1926 AD 286
at
289
[11]
Lappeman Diamond Cutting Works (Pty) ltd v MIB Group (Pty) Ltd (No1)
1997 (4) SA 908 (W) 927
[12]
PLC Consulting fn 7 above