Industrial Zone (Pty) Ltd v MEC for Economic Development, Environment, Agriculture and Rural Affairs, Gauteng and Another (7746/18) [2023] ZAGPJHC 376 (25 April 2023)

82 Reportability
Administrative Law

Brief Summary

Administrative Law — Review — Environmental authorisation — Applicant sought authorisation to develop properties and divert a stream — Head of Department granted authorisation subject to the stream remaining undisturbed — Applicant challenged decision, arguing it adversely affected economic viability of development — Court held that refusal to adopt applicant’s preferred alternative was rationally connected to the lawful purpose of protecting the environment — Review application dismissed.

Comprehensive Summary

Summary of Judgment


1. Introduction


The matter concerned a judicial review brought in the High Court under section 6 of the Promotion of Administrative Justice Act 3 of 2000 (PAJA). The applicant, Industrial Zone (Pty) Ltd, sought to review and set aside environmental decision-making that constrained its proposed development of two properties in Denver, Johannesburg. The respondents were the MEC for Economic Development, Environment, Agriculture and Rural Affairs, Gauteng (as the internal appeal authority) and the Head of the Gauteng Department of Agriculture and Rural Affairs (as the original decision-maker).


The dispute arose from an application for an environmental authorisation in terms of section 24 of the National Environmental Management Act 107 of 1998 (NEMA). Industrial Zone sought authorisation to develop the properties as a light industrial township and, crucially, to implement a scheme to divert a stream crossing both properties so as to increase developable land. The Head of Department granted authorisation for development, but subject to an alternative that left the stream undisturbed and imposed development constraints around it. Industrial Zone pursued an internal appeal under section 43 of NEMA to the MEC, who dismissed the appeal.


Industrial Zone then approached the High Court to review both the original authorisation condition (in substance, a refusal to approve stream diversion) and the MEC’s dismissal of the internal appeal. A preliminary procedural complication arose because Industrial Zone initially framed its review as directed only at the MEC’s decision, and later sought to join and directly review the Head of Department’s decision as well, requiring an extension of time under section 9 of PAJA.


The general subject-matter of the dispute was environmental authorisation decision-making under NEMA and the associated administrative-law standards governing the rationality and reasonableness of such decisions, particularly in relation to the selection among alternatives identified in the environmental impact assessment process.


2. Material Facts


Industrial Zone owned or controlled two properties in Denver over which a stream runs from southeast to northwest. In its unmanaged state, the stream significantly limited the developable area of the properties, affecting the feasibility and anticipated economic returns of the proposed light industrial township.


Industrial Zone applied for an environmental authorisation under section 24 of NEMA. In its application, it advanced a preferred proposal to divert the stream so that it would run along the southern and western edges of the properties through a grass-lined channel, with the stream’s flow managed by weirs. Industrial Zone maintained that this would enable substantially greater development of the properties.


In addition to its preferred proposal, Industrial Zone included two alternatives in its Basic Assessment process. The first alternative still diverted the stream but through a cement-lined canal. The second alternative (the “no diversion” option) was to leave the stream on its present course, build a bridge over it, and develop the remaining portions of the properties outside a 30-metre buffer on either side of the stream.


On 13 December 2016, the Head of Department granted the environmental authorisation subject to the second alternative, meaning that the stream would remain in its existing course and development would be constrained by the buffer zone. Industrial Zone appealed to the MEC under section 43 of NEMA, contending in substance that the authorisation should instead have been granted subject to its preferred diversion proposal (and not the approved alternative). It argued, among other things, that development was not economically feasible without diversion, that the stream was already polluted and not on its original course, and that the proposed development and diversion would rehabilitate and enhance the stream environment.


The MEC dismissed the appeal. The MEC’s reasoning included that leaving the stream undisturbed was a legitimate decision available to the Head of Department, and that if the stream was polluted Industrial Zone bore responsibilities as landowner to address that condition irrespective of whether the development proceeded.


Before the High Court, it was common cause that the authorisation ultimately granted did not permit diversion of the stream and thereby restricted Industrial Zone’s ability to pursue its preferred form and extent of development. A further material point for the court was the content and tenor of Industrial Zone’s Basic Assessment Report, which emphasised that the development would not be economically viable and might not proceed at all unless the stream was diverted.


The respondents raised a disputed characterisation issue, contending that because Industrial Zone itself included the “no diversion” alternative in its application, the selection of that alternative did not adversely affect rights and therefore did not constitute administrative action under PAJA. The court treated this as a threshold legal issue requiring determination before the merits of rationality or reasonableness.


3. Legal Issues


The first central question was whether the Head of Department’s decision (granting authorisation but subject to the “no diversion” alternative) and the MEC’s appeal decision constituted “administrative action” as defined in section 1 of PAJA, specifically whether the decisions adversely affected rights and had direct external legal effect, notwithstanding that the “no diversion” option had appeared as an alternative in Industrial Zone’s own application documentation.


If the decisions constituted administrative action, the next central questions were whether the refusal to permit diversion (as embodied in the authorisation and confirmed on internal appeal) was reviewable under section 6 of PAJA on the grounds of irrationality and/or unreasonableness. The court identified that these concepts, while sometimes conflated in argument, are distinct and require separate analytical treatment.


The dispute therefore concerned primarily questions of law (the PAJA characterisation of administrative action and the meaning of rationality and reasonableness review), and the application of legal standards to facts (whether, on the information before the decision-makers and in light of NEMA’s purposes, the refusal to divert was rationally connected to lawful purposes and fell within a range of reasonable outcomes). The court’s assessment necessarily included an evaluative component typical of reasonableness review, but it did not involve the court substituting its own merits view for that of the statutory decision-makers.


A further issue concerned a procedural matter: whether it was in the interests of justice to grant an extension under section 9 of PAJA to permit the amended and “fresh” challenge to the Head of Department’s decision, brought outside the default 180-day period.


4. Court’s Reasoning


On the preliminary point, the court analysed the respondents’ contention that no administrative action existed because Industrial Zone had itself tendered the “no diversion” alternative and thus, in effect, accepted the risk that the decision-maker could choose it. The court approached this by examining the legal framework under NEMA and the Environmental Impact Assessment Regulations, 2014, particularly the role of “alternatives” in a Basic Assessment Report.


The court explained that NEMA provides a structured system for environmental authorisations under section 24, and that applications must comply with the 2014 Regulations. The Regulations define an “alternative” as a different means of meeting the general purpose of the proposed activity, and require that a Basic Assessment Report identify a preferred alternative and record other alternatives considered. The court emphasised that feasible and reasonable alternatives must be placed before decision-makers to enable compliance with NEMA’s evaluative duties, including those in section 24O(1)(b)(iv). The court also highlighted Regulation 24(2), which treats an alternative imposed as a condition of authorisation as having been applied for, consulted upon, and assessed for impacts.


Against that framework, the court reasoned that the inclusion of multiple alternatives in an application does not, without more, mean the applicant waives the right to challenge the selection of an alternative that the applicant regards as unacceptable or commercially destructive. The court considered the substance of Industrial Zone’s Basic Assessment Report, which strongly conveyed that diversion was essential to viability and that authorisation subject to leaving the stream in place would render the development economically infeasible and might mean it would not proceed. On that basis, the refusal to allow diversion materially constrained Industrial Zone’s use and development of its property and therefore adversely affected its rights and had direct external legal effect, as development by diversion was legally prohibited under the authorisation granted.


The court further reasoned that treating the mere inclusion of alternatives as a waiver would undermine NEMA’s purposes, because it would discourage applicants from candidly presenting objectively feasible alternatives. Applicants would be incentivised to include only what they subjectively prefer, reducing the quality of environmental deliberation. Accordingly, the court held that both the Head of Department’s decision and the MEC’s appeal decision constituted administrative action under PAJA.


Turning to the merits under PAJA, the court drew a clear distinction between irrationality and unreasonableness. Irrationality was described as a lack of connection between the decision and a lawful purpose or reason, including decisions based on whim or irrelevant reasons. Unreasonableness was described as a decision that, although connected to the reasons and information before the decision-maker and the power exercised, falls outside the range of outcomes reasonably available on the facts and the law’s purposes.


Applying rationality review, the court found the refusal to divert the stream to be plainly rational, as it was rationally connected to the lawful purpose of environmental protection and to the information and reasons before the decision-makers. The court observed that choosing not to substantially reconfigure a natural feature will ordinarily bear a rational relationship to NEMA’s objectives, absent circumstances such as net environmental harm from inaction or improper motives.


The applicant’s main rationality argument was that refusing diversion would prevent development and therefore prevent rehabilitation of a polluted stream, allowing degradation to continue. The court answered this in two ways, each grounded in the statutory context and the nature of the proposed intervention. First, the court referred to section 28 of NEMA, which imposes a duty of care on landowners to take reasonable measures to remediate environmental harm. It was therefore not irrational for the decision-makers to reject the premise that Industrial Zone would only address remediation if allowed to pursue its preferred development configuration. Second, the court considered that diversion itself constituted a substantial environmental interference. On the information before the decision-makers, diversion was viewed as further “degradation” and raised concerns regarding the stream’s hydrological functioning and impacts on the surrounding environment dependent on the existing flow path. The court held that even if the decision-makers were wrong on the merits, the refusal remained rational because they chose to avoid a further environmental impact in circumstances where the proposed diversion was drastic, including the intended ninety-degree change in direction.


On unreasonableness, the court found no basis to conclude that refusal to divert the stream fell outside the range of reasonable decisions open to the respondents. The respondents were empowered by NEMA to limit the environmental impacts of economic activity and were required to decide whether and how to mitigate impacts while considering the proposed development. They allowed development in principle but restricted it to avoid diversion of the stream. The court reasoned that the fact that this choice imposed economic costs on Industrial Zone did not, in itself, render the decision unreasonable within a legislative scheme designed to constrain environmental impacts even where such constraints reduce economic benefit.


On the procedural issue of time extension, the court considered the section 9 PAJA standard of the interests of justice. It found that the delay problem was technical, arising because Industrial Zone later understood it needed also to review the Head of Department’s decision directly, prompting joinder and amendment. The court held there was no real prejudice, and it was inconceivable that the Head of Department would not have been aware of and involved in the matter. It therefore granted the extension and also granted leave to amend the notice of motion.


5. Outcome and Relief


The court granted Industrial Zone’s application for an extension of time under section 9 of PAJA, extending the period to institute the proceedings to 25 November 2021. The court also granted Industrial Zone leave to amend its notice of motion to accommodate the joinder of the Head of Department and the amended relief.


On the merits, the court dismissed the main review application, holding that the decisions constituted administrative action but were neither irrational nor unreasonable on the information and statutory purposes considered.


The court ordered that the applicant pay the costs of each of the applications, including the costs of two counsel where employed.


Cases Cited


No reported cases were cited in the judgment.


Legislation Cited


National Environmental Management Act 107 of 1998, including section 24, section 24O(1)(b)(iv), section 28, and section 43.


Promotion of Administrative Justice Act 3 of 2000, including section 1, section 6, and section 9.


Rules of Court Cited


No rules of court were cited in the judgment.


Held


The High Court held that the Head of Department’s decision to grant environmental authorisation subject to an alternative that left the stream undisturbed, and the MEC’s decision dismissing the internal appeal, constituted administrative action under PAJA because they adversely affected the applicant’s rights and had direct external legal effect.


The court further held that the refusal to permit diversion of the stream was rationally connected to the lawful purpose of environmental protection and the information before the decision-makers, and that it was also reasonable, falling within the range of outcomes open to the respondents under NEMA.


The review application was dismissed with costs, while the applicant was granted an extension of time and leave to amend.


LEGAL PRINCIPLES


The judgment applied the principle that a decision constitutes administrative action under PAJA where it adversely affects rights and has direct external legal effect, even where the decision-maker selects from among alternatives presented during an environmental assessment process. The inclusion of multiple alternatives in a Basic Assessment Report does not, without more, amount to a waiver by the applicant of the right to challenge the selection of an alternative that materially prejudices the applicant’s ability to use or develop property.


The judgment reaffirmed the distinction between rationality review and reasonableness review in administrative law. Rationality concerns whether a decision is connected to a lawful purpose and the reasons and information before the administrator, while reasonableness concerns whether the decision falls within a range of decisions reasonably available in light of the facts, the empowering provisions, and the purposes of the legislation.


In the environmental context, the judgment applied the principle that refusing to authorise substantial interference with natural features will ordinarily be rationally connected to NEMA’s purposes of environmental protection, and that an administrator may legitimately prioritise avoiding further environmental impacts even where this limits the economic benefits of a proposed development.


The judgment also applied the statutory principle in section 28 of NEMA that landowners bear a duty of care to take reasonable measures to remediate environmental harm, and that decision-makers are not compelled to approve environmentally intrusive development measures on the basis that remediation or rehabilitation will only occur if such measures are allowed.


Finally, the judgment applied the principle that an extension of the PAJA time bar under section 9 depends on the interests of justice, and may be granted where the delay is technical, causes no material prejudice, and enables proper adjudication of the dispute on its merits.

About SAFLII
Databases
Search
Terms of Use
RSS Feeds
South Africa: South Gauteng High Court, Johannesburg
SAFLII
>>
Databases
>>
South Africa: South Gauteng High Court, Johannesburg
>>
2023
>>
[2023] ZAGPJHC 376
|

|

Industrial Zone (Pty) Ltd v MEC for Economic Development, Environment, Agriculture and Rural Affairs, Gauteng and Another (7746/18) [2023] ZAGPJHC 376 (25 April 2023)

FLYNOTES:
PAJA AND A RIVER NOT DIVERTED
AMINISTRATIVE
– Review – Environmental authorisation –
Proposal to develop property – Containing alternative

proposals for river – Decision to leave river undisturbed
affected economic benefit of applicant – Refusal to
divert
stream was rationally connected to lawful purpose of protecting
environment – Review application dismissed –
National
Environmental Management Act 107 of 1998

Promotion of
Administrative Justice Act 3 of 2000
,
s 6.
IN
THE HIGH COURT OF SOUTH AFRICA
(GAUTENG
LOCAL DIVISION, JOHANNESBURG)
Case No. 7746/18
REPORTABLE
OF INTEREST TO OTHER
JUDGES
REVISED
In the matter between:
INDUSTRIAL
ZONE (PTY)
LTD
Applicant
and
MEC FOR ECONOMIC
DEVELOPMENT, ENVIRONMENT,
AGRICULTURE
AND RURAL AFFAIRS, GAUTENG
First
Respondent
HEAD OF THE GAUTENG
DEPARTMENT
OF
AGRICULTURE AND RURAL AFFAIRS
Second Respondent
Summary
Environmental
law –
National Environmental Management Act 107 of 1998

environmental authorisations considered under
section 24

insertion of a number of alternative proposals for undertaking the
activities for which authorisation is sought does not
imply the
waiver of the right to challenge a refusal to adopt the applicant’s
preferred alternative – refusal to adopt
the applicant’s
preferred alternative constitutes “administrative action”
under the
Promotion of Administrative Justice Act 3 of 2000

review application dismissed.
JUDGMENT
WILSON
J
:
1
The applicant, Industrial Zone, wishes to develop two
properties in Denver, to the southeast of the Johannesburg inner
city. A stream
crosses both properties from southeast to northwest.
The stream, in its unmanaged state, renders much of both properties
undevelopable.
2
To address this, Industrial Zone applied to the second
respondent, the Head of Department, for an environmental
authorisation in
terms of section 24 of the National Environmental
Management Act 107 of 1998 (“NEMA”). Industrial Zone
sought permission
to develop the property as a light industrial
township. It also sought leave to divert the stream such that it
would run along
the southern and western edges of both properties.
The stream would be directed through a grass-lined channel. The flow
of the
stream would be managed by a number of weirs, presumably so as
to reduce the risk of erosion posed by sending the stream around
a
ninety-degree angle at the southwestern edge of the property.
3
Implementing this proposal would allow the development of a
much greater portion of Industrial Zone’s two properties. In
the
event that it did not meet with the Head of Department’s
approval, however, Industrial Zone supplemented this proposal with

two alternatives. The first alternative was to divert the stream in
much the same way, but to do so through a cement-lined canal.
The
second alternative was to leave the stream as it is, to build a
bridge over it, and to develop what remains of both of Industrial

Zone’s properties beyond a thirty-metre buffer either side of
the stream’s path.
4
On 13 December 2016, the Head of Department granted Industrial
Zone’s environmental authorisation, subject to the second
alternative:
that the stream remains on its present course, and that
the properties be developed for light industrial purposes around it.
Aggrieved
by this decision, Industrial Zone appealed to the MEC in
terms of section 43 of NEMA. It contended that the Head of Department
ought to have granted the authorisation subject to the stream
diversion scheme that Industrial Zone had preferred in its
application;
that the development of the properties is not feasible
unless that option (or the first alternative, which Industrial Zone
does
not pursue) is adopted; that the stream is in any event in a
highly polluted state and is not on its original course; and that the

development of the properties using Industrial Zone’s preferred
option for dealing with the stream would rehabilitate it
and enhance
the environment.
5
The MEC dismissed the appeal, largely on the basis that
leaving the stream undisturbed was a perfectly legitimate choice open
to
the Head of Department, and that, if the stream is currently
polluted, Industrial Zone is under a duty, as landowner, to clean it

up whether or not the properties are developed.
6
Industrial Zone now asks me to review and set aside the Head
of Department’s and the MEC’s decisions under section 6

of the Promotion of Administrative Justice Act 3 of 2000 (PAJA). It
was not clear to me on reading the papers whether Industrial
Zone
contended that the decision was irrational or unreasonable. Though
separated in form, these two terms were in elided in substance
in
Industrial Zone’s papers and argument.
7
But they are distinct. An irrational decision is one that
lacks any connection to a lawful reason or purpose – one that
is
based on a brute preference; that is taken on a whim; or that is
so tainted by bad reasons as to be unconnected to any good ones.
An
unreasonable decision is one which, while connected to the reasons
given for it, to the information before the decision-maker,
and to
the power being exercised, is not one of the range of options
reasonably available to the decision-maker on the facts before
them,
read in light of the applicable law and the purposes that law serves.
8
The respondents contend that their decisions are both rational
and reasonable. But they raise a prior issue: that the decisions do

not amount to administrative action within the meaning of PAJA at
all, and that Industrial Zone’s application should be dismissed

on that ground alone.
9
Accordingly, I turn first to whether the decisions under
challenge amount to administrative action.
The
nature of the decisions
10
Section 1 of PAJA requires, amongst other things, that, to
constitute administrative action, a decision must adversely affect a
person’s rights, and that it must have “direct external
legal effect”. The respondents say that the condition
placed in
the environmental authorisation which Industrial Zone now challenges
was one tendered by Industrial Zone itself. It sought
environmental
authorisation to develop the properties under any one of three
schemes for diverting the stream set out in its application.
Although
it made clear that its preference was for the first scheme, the legal
effect of proffering all three possible schemes
in the alternative
was that Industrial Zone deferred to the Head of Department’s
selection of which of the schemes is to
apply.
11
It follows, the respondents say, that the decision to adopt
one of the three alternatives Industrial Zone proffered did not
affect
any of Industrial Zone’s rights. In their papers, the
respondents say that this means that Industrial Zone is impermissibly

seeking to “review its own decision” to proffer the
alternative the Head of Department ultimately selected. But I think

the better interpretation of the respondents’ case is that
Industrial Zone waived the right to choose between the alternatives

it set out in its application, and accepted that this choice was
solely for the Head of Department. For that reason, the respondents

contend, the decision to adopt one of the alternatives Industrial
Zone itself proposed did not affect Industrial Zone’s rights
or
have any external legal effect.
12
To determine whether Industrial Zone in fact waived its right
to challenge the refusal to adopt its preferred alternative, it is

necessary to consider the content of its application in light of the
legal framework within which it was submitted and evaluated.
NEMA
and the Environmental Impact Regulations, 2014
13
Section 24 of NEMA sets out the framework within which
activities that may affect the environment are regulated. Section 24
(1)
creates the concept of an environmental authorisation, which must
be granted before any activity that might have environmental impact

may be approved. Section 24 (1A) obliges applicants for environmental
authorisations to comply with an application process, and
the
procedures, reporting requirements and processes associated with it.
Section 24 (2) (a) of NEMA empowers the Minister for Environmental

Affairs, or an MEC with responsibility for environmental affairs with
the Minister’s concurrence, to designate activities
that may
not commence without environmental authorisation.
14
An application for such an environmental authorisation must
comply with the provisions of the
Environmental Impact Assessment
Regulations, 2014
.
Regulation 1
of the Regulations defines “activity”
in the sense conveyed in
section 24
(2) (a) of NEMA as “an
activity identified in any notice published by the Minister or MEC in
terms of section 24D(1)(a) of
the Act as a listed activity or
specified activity”. Regulation 1 goes on to define an
“alternative” “
in relation to a
proposed activity” as a “different means of meeting the
general purpose and requirements of the activity”.
In this
case, there were a number of discrete “activities” for
which Industrial Zone sought authorisation. Taken together,
they
amounted to the development of Industrial Zone’s properties
as a light industrial township and the associated
works to be done on the stream. The “alternatives” were
the three
possible ways of dealing with the stream
.
15
The Regulations require that the
alternatives and their relative merits be set out in a “Basic
Assessment Report”. The
contents of such a report are
prescribed in Appendix 1 to the Regulations. Regulation 3 (1) (h) of
the Appendix requires a Basic
Assessment Report to set out the
preferred alternative, details of all the other alternatives
considered, and, where only one alternative
is considered, why that
was so.
To permit the decision maker to exercise their powers
in compliance with NEMA, the alternatives proposed must be “feasible

and reasonable” in themselves (section 24O (1) (b) (iv) of
NEMA).
Regulation 24 (2) states that, where
environmental authorisation is given subject to any alternative set
out in the application
“such alternative must . . .  be
regarded as having been applied for, consulted on and its impacts
investigated”.
Industrial Zone’s
Basic Assessment Report
16
Industrial Zone’s Basic Assessment
Report makes clear that it wishes to develop the properties as a
light industrial township,
and sets out the three alternatives for
dealing with the stream to which I have already referred. The tenor
of the Basic Assessment
Report is that Industrial Zone’s
preference is for the diversion of the stream. Industrial Zone makes
clear, in emphatic
terms, that it will not be able to develop the
property economically if the stream is not diverted, and that the
development will
not proceed as envisaged, or perhaps at all, unless
the stream is diverted. The implication is that, by Industrial Zone’s

lights, if authorisation is granted subject to the stream remaining
on its current course, the authorisation might as well not
be granted
at all.
17
In these circumstances, I do not think that
Industrial Zone can realistically be said to have waived its right to
review a decision
to authorise the development subject to the stream
remaining on its current course with a thirty-metre buffer zone
either side.
Industrial Zone clearly understood, and indicated in the
Basic Assessment Report, that it would not be able to implement what
it
considers to be an economically viable development on the property
unless the stream is diverted. In this sense the refusal to authorise

the diversion of the stream, which is embodied in the environmental
authorisation, clearly affected Industrial Zone’s rights.

Industrial Zone set out three alternative means of dealing with the
stream, but made clear that only two were really tolerable
to it.
Under the Regulations, Industrial Zone could just as easily have
proposed only its preferred alternative and then explained
why it had
rejected the development of the property without diverting the stream
(see Regulation 3 (1) (h) (x) of Appendix 1 to
the Environmental
Impact Regulations, 2014), but the substance of its position would
have been no different: that it wanted to
develop the property as a
light industrial township, and that it could not realistically do so
without diverting the stream.
18
In these circumstances, the decision to
issue the environmental authorisation, but not to adopt Industrial
Zone’s proposal
that the stream be diverted, clearly affected
Industrial Zone’s property rights. It also had a direct
external legal effect,
in that the properties may not be developed by
diverting the stream.
19
Moreover, it would be contrary to NEMA’s
purposes to hold that the insertion of alternatives into a Basic
Assessment Report
means the waiver of any right to challenge a
decision to adopt an alternative the applicant considers
inappropriate or undesirable.
It would discourage honest and
forthright applications that examine all “feasible and
reasonable” alternatives. It
would accordingly stunt
deliberation over environmental authorisations, because it would
incentivise applicants for authorisations
to include only those
alternatives that they subjectively prefer, rather than all the
alternatives that are objectively “reasonable
and feasible”,
lest they be accused of waiving the right to challenge the adoption
of an alternative they do not like.
20
Industrial Zone says that it included the alternative the Head
of Department ultimately adopted at the Department’s own
insistence.
It was accordingly saddled with an alternative it never
wanted. Industrial Zone argues that it would be artificial to suggest
that
it waived its right to complain about the adoption of that
alternative in these circumstances.
21
Given the conclusion to which I have come, Industrial Zone’s
argument on that score need not be considered. But there are,
in any
event, no primary facts alleged in Industrial Zone’s papers to
support the proposition that the alternative the Head
of Department
ultimately adopted was included in the Basic Assessment Report at the
Department’s insistence. Moreover, such
an insistence would
have been unlawful, and reviewable in itself. As I have already said,
Regulation 3 of Appendix 1 makes clear
that Industrial Zone could
either have proposed alternatives to the stream’s diversion, or
proposed no alternative and explained
why. There was no basis on
which the Department could have forced Industrial Zone to propose the
alternative, and no evidence that
it actually did so.
22
It follows from all this that the Head of Department’s
decision to issue the environmental authorisation and the MEC’s

refusal to set that decision aside on appeal both constitute
“administrative action” under PAJA. They affected
Industrial
Zone’s rights. They had a direct and external legal
effect. To put things in the terms that the respondents used in
opposing
the application, by including the alternative in the Basic
Assessment Report that the Head of Department ultimately approved,
Industrial
Zone did not “decide” to accept that
alternative in the event it was selected. Nor does this application
amount to
a “review” of that “decision”.
The
merits of the decisions
23
None of this means, of course, that either the Head of
Department’s or the MEC’s decision should be reviewed and
set
aside. The question remains whether the decisions were irrational
or unreasonable in the senses conveyed in PAJA.
24
It seems to me that the refusal to divert the stream was
plainly rational, in the sense that it was rationally connected to
the
lawful purpose of protecting the environment, to the information
before the Head of Department and to the reasons both respondents

gave for it.
25
The refusal to interfere with the environment by substantially
reconfiguring a natural feature will rarely lack rational contact

with
NEMA’s objects and purposes
,
unless inaction would cause nett environmental harm, or unless the
decision not to interfere was tainted by motives or reasons
that were
irrelevant to those objects and purposes.
26
Industrial Zone does not suggest any irrationality of that
type. It rather argues that the refusal to adopt its preferred
alternative
was irrational on the facts. The decision has the effect
of preventing the development, which in turn will prevent the
rehabilitation
of the stream. The Basic Assessment Report makes clear
that the approved alternative is undesirable only because it is not,
in
Industrial Zone’s view, economically viable.  Without
the development, the stream – which Industrial Zone says
is in
a wretched state – will not be rehabilitated. Accordingly, so
it is argued, the decision not to permit the diversion
of the stream
is irrational, because it will allow environmental degradation to
continue.
27
There are two answers to this. The first is that section 28 of
NEMA places a duty of care on Industrial Zone as a landowner to take

reasonable measures to remediate any environmental damage that has
been done to the stream in the past. It is hardly irrational
of the
respondents to refuse to accede to Industrial Zone’s position:
that it is only willing to discharge that duty if its
preferred way
of developing the site is facilitated.
28
The second answer is that, even if the stream is currently
polluted and degraded, the diversion of the stream is itself a
substantial
further interference with the stream’s current
state. It is an environmental impact in itself – which both
respondents
described as a further “degradation” of the
stream. Industrial Zone’s preferred scheme for diverting the
stream
is drastic. Instead of following its current course diagonally
across the properties, Industrial Zone proposes that it be directed

around a ninety-degree angle at the south-western corner of the
properties. The MEC’s decision on appeal refers to the
Department’s
obvious concerns about this diversion’s
impact on the stream’s “hydrological functioning”,
and on the surrounding
environment that is currently dependent on the
stream following its present course.
29
On the information presented to them, the respondents chose to
prevent the diversion of the stream and its associated environmental

impact, even if that meant that the development would not yield the
economic benefit Industrial Zone foretold. Whatever criticism
may be
levelled at that choice, it was hardly irrational. The respondents
simply concluded that the diversion of the stream in
the manner
proposed would do more harm than good. Even if it was incorrect, this
conclusion was plainly rational.
30
That leaves the question of whether the decision was
unreasonable. I do not see how. I can find nothing on the facts of
this case,
or in NEMA, that would suggest that the refusal to divert
the stream is not one of the paths open to a reasonable
decision-maker.
The respondents had to decide whether to accommodate
a light industrial development on the properties and, if such a
development
was to be approved, how best to mitigate its
environmental impact. They chose to do so by allowing development on
the property
in principle, but not in a manner that would involve
diverting the stream. That decision obviously imposes costs on
Industrial
Zone, in that it will not be able to develop as much of
the properties as it would like. But the mere imposition of those
costs,
in the context of legislation which empowers the respondents
to place limits on the environmental impact of economic activity,
does not make the respondents’ decisions unreasonable.
31
In these circumstances, the review application must fail.
The
application for an extension of time
32
Industrial Zone originally attacked only the MEC’s
decision on its internal appeal. Industrial Zone was later advised
that
it was necessary also to bring the Head of Department’s
decision under review. This necessitated the joinder of the Head of

Department, and the amendment of Industrial Zone’s notice of
motion. The technically “fresh” challenge to the
Head of
Department’s decision was brought beyond the 180- day limit
stipulated in section 9 of PAJA. For that reason, Industrial
Zone
asked for an extension of time under section 9. Industrial Zone also
sought leave to make a number of technical amendments
to its notice
of motion in order to accommodate the joinder of, and the seeking of
relief against, the Head of Department.
33
An extension of time under section 9 of PAJA is granted where
it is in the interests of justice. In this case, the extension sought

is of an entirely technical nature. No-one could have been under any
misapprehension about what Industrial Zone was seeking to
achieve
when it first brought the application, and it is inconceivable that
the Head of Department would not in any event have
been informed and
consulted on the application in its original form. There could
accordingly have been no real prejudice to the
Head of Department. It
is clearly in the interests of justice that the review, pursued in
its mature form against both respondents,
be heard and decided on its
merits.
34
The extension of time will be granted.
The
application for leave to amend is uncontroversial and will also be
granted.
Order
35
For these reasons, I make the following order –
35.1
The application for an extension of time under
section 9
of the
Promotion of Administrative Justice Act 3 of 2000
is granted. The
period within which the applicant was entitled to institute these
proceedings is extended to 25 November 2021.
35.2
The application for leave to amend in paragraph 2 of the applicant’s

notice of motion dated 25 November 2021 is granted.
35.3
The main review application is dismissed.
35.4
The applicant will pay the costs of each of these applications,

including the costs of two counsel where two counsel were employed.
S
D J WILSON
Judge
of the High Court
HEARD
ON:      11 April 2023
DECIDED
ON:   25 April 2023
For
the Applicant:
JH
Wildenboerer
Instructed
by DDP Attorneys, Rosebank
For
the Respondents:
P
Mokoena SC
LC
Abrahams
Instructed
by the State Attorney