Orkin v Goldleaf Investment (Pty) Ltd (22321/2018) [2023] ZAGPJHC 356 (21 April 2023)

80 Reportability
Contract Law

Brief Summary

Contract — Breach of contract — Plaintiff claimed damages for breach of sale agreement regarding provision of electricity — Defendant counterclaimed for removal of encroachments — Plaintiff purchased property from defendant, who failed to ensure necessary infrastructure for electricity supply was in place, causing delays in completion of building — Court held that defendant was responsible for providing a fully serviced site, including electricity, and breached the agreement by failing to do so, entitling plaintiff to damages.

Comprehensive Summary

Summary of Judgment


1. Introduction


The proceedings were an action for contractual damages arising from an alleged breach of a written agreement of sale, coupled with a counterclaim in which the defendant sought enforcement-type relief relating to alleged encroachments and unauthorised installations at a residential unit in a complex.


The plaintiff was Nadine Orkin, a retiree and purchaser of a vacant stand in the relevant development. The defendant was Goldleaf Investments (Pty) Ltd, the developer and seller of the stand.


The matter proceeded to trial in the Gauteng Local Division, Johannesburg, before Mia J. The plaintiff claimed damages of R1 012 859.92. The defendant denied liability and pursued a counterclaim based on an alleged ceded right, seeking orders compelling the plaintiff to remove or alter certain walls and items (including an air-conditioning unit, satellite dish, aerial, and electric fence). Evidence was led by three witnesses for the plaintiff and two witnesses for the defendant.


The general subject-matter of the dispute was whether the sale agreement (together with its addendum concerning the building contractor) contained a tacit term obliging the developer to provide, or ensure the provision of, a fully serviced site, including bulk electricity supply, and whether the absence of electricity caused a delay that entitled the plaintiff to recover contractual damages. A further subject-matter was whether the defendant had locus standi to pursue the counterclaim and, if so, whether it had proven entitlement to the relief sought.


2. Material Facts


It was common cause that the plaintiff purchased a vacant stand from the defendant (as developer) in terms of an agreement concluded on 14 November 2014. Clause 4.1 contemplated that the purchaser would conclude a separate building agreement with a specified contractor to erect a dwelling. By addendum dated 12 April 2015, the original contractor was replaced with Claycon (Pty) Ltd, while the remaining contractual terms remained in force.


It was also common cause that the plaintiff paid the purchase price, took transfer on 9 May 2016, and that the building plans were approved on 22 July 2016. On the agreed timeline, completion of the building was to occur within nine months from commencement (the approval date), which meant completion was anticipated by about April 2017. The “major building structure” was completed around April 2017, but the contractor could not hand over the property because the electrical points could not be checked and tested due to the absence of electricity supply to the site.


It was further common cause that bulk electricity was connected by Eskom only in December 2017, with bulk supply becoming available from 18 January 2018 and connected to the plaintiff’s reticulation system on 25 January 2018. Eskom issued a section 82 certificate on 2 February 2018, and the City of Johannesburg issued an occupancy certificate on 22 February 2018.


The material disputed aspect concerned responsibility under the contract: the plaintiff contended that, properly construed (including by implication of a tacit term), the defendant was obliged to provide the necessary electrical (and municipal) infrastructure and ensure a fully serviced site by the time the dwelling was complete. The defendant’s position was that it was not responsible for the lack of electricity supply, attributing the delay to Eskom (and, on its version, to interference by the plaintiff), while accepting responsibility only for internal reticulation within the complex.


On the counterclaim, it was material that the defendant’s claim was advanced on a purported cession from the HOA, and that by the time of argument on the counterclaim it was conveyed to the court that the substantive issues had been resolved, leaving costs as the remaining point in contest. The plaintiff nonetheless persisted that the defendant lacked standing and that the counterclaim relief had not been established on the evidence.


3. Legal Issues


The central legal questions the court was required to determine were whether the sale agreement contained a tacit (implied) term obliging the defendant, as developer, to provide or ensure the provision of a fully serviced site, including bulk electrical supply, and whether the defendant’s failure to do so amounted to a breach that caused compensable loss.


A further set of issues concerned causation and quantification of contractual damages: which heads of damage flowed from the breach (including rental, project management costs, interest-related claims on installed items, and legal costs incurred prior to litigation), and which were too remote or insufficiently proven.


In reconvention, the court had to determine whether the defendant had locus standi to pursue the counterclaim on the basis of a cession from the HOA, and whether (in any event) the defendant had adduced sufficient evidence to justify the demolition/alteration and removal relief sought.


The dispute thus involved questions of law (the standard for implying tacit terms; cedability and standing), questions of fact (what the surrounding circumstances showed; what steps were taken; the timing of submissions and supply), and the application of law to fact (whether the tacit term was established; whether breach and causation were proven; whether damages were established on acceptable proof).


4. Court’s Reasoning


On the plaintiff’s claim, the court approached the matter as one turning on a tacit term. It applied the principle, drawn from Alfred McAlpine & Son (Pty) Ltd v Transvaal Provincial Administration, that a tacit term is an unexpressed provision inferred from the common intention of the parties as revealed by the express terms and surrounding circumstances, and that a court will not import such a term merely because it is reasonable. The judgment emphasised the requirement of necessity for business efficacy and referred to the “bystander test” associated with Reigate v Union Manufacturing Co as adopted in the cited South African authorities.


In applying that framework, the court considered that the contractual scheme contemplated purchasers occupying completed homes and paying for utilities connected to their properties, which, on the plaintiff’s case, presupposed that bulk electricity would be available to the development. In the court’s assessment, the evidence and surrounding circumstances supported the inference that a fully serviced site (including the electrical supply necessary for testing and certification) would be required to give practical effect to the overall transaction.


Significantly, evidence from the defendant’s own witness, Mr Robinson (the builder), supported the proposition that it was the developer’s responsibility to procure bulk electricity or ensure the infrastructure was in place to provide a fully serviced site. The court treated this evidence as confirming what the “bystander” would have understood the arrangement to entail in the context of a residential development, and regarded it as consistent with the practical necessities of completing electrical testing, obtaining compliance documentation, and enabling issuance of an occupancy certificate.


On breach, the court applied the general principle (again with reference to McAlpine) that where a contract does not specify a fixed time for performance, obligations are enforceable forthwith, subject to the qualification that performance cannot be demanded unreasonably in a way that defeats the contract’s object or without allowing sufficient time to comply. On the facts, the court found that although an application for bulk electricity was made in 2014, the defendant did not take adequate steps to satisfy Eskom’s requirements timeously, and only appointed an electrical engineer in 2017 after enquiries were raised.


The judgment reasoned that the defendant mistakenly believed that payment to Eskom in 2014 was sufficient and did not appreciate that additional technical documentation and coordination (including designs and specifications relevant to internal reticulation and Eskom’s connection requirements) had to be submitted to secure the installation within an appropriate timeframe. The court viewed the defendant’s attempt to attribute responsibility to Eskom as not absolving it from its own contractual obligations, particularly in circumstances where the necessary submissions were made only belatedly in 2017 and the developer did not demonstrate earlier follow-up or facilitation consistent with its responsibilities.


The court concluded that the plaintiff could not take occupation from about July 2017 (once construction was effectively complete) until February 2018 when the occupancy certificate was issued, and it attributed that delay to the defendant’s failure to ensure the site was fully serviced with electricity in time. It rejected the contention that the plaintiff caused the delay, characterising that allegation as lacking merit in light of the technical requirements that the defendant had failed to meet timeously.


On damages, the court applied established principles that contractual damages aim to place the innocent party in the position they would have occupied had proper performance occurred, subject to mitigation, causation, and remoteness. It relied on the articulation of these principles in Sandlundlu (Pty) Ltd v Shepstone and Wylie Incorporated and Holmdene Brickworks (Pty) Ltd v Roberts Construction Co Ltd. Having found breach from July 2017, the court allowed damages that it considered to flow from that breach within the proven period.


The court allowed rental damages for the relevant months, project management costs only insofar as they related to the post-breach period, and a gardening-related amount. It further allowed certain legal costs incurred before summons, treating them as flowing from steps taken to protect the plaintiff’s rights in relation to the breach and the delayed installation. However, the court disallowed a substantial claim relating to interest on “PC items” (installed items purchased by the plaintiff), holding that the plaintiff had not proved the amount claimed on the evidence presented and that a table of amounts was insufficient to discharge the burden of proof.


On the counterclaim, the court dealt first with standing. It relied on the SCA decision in Propell Speciallised Finance (Pty) Ltd v Attorneys Insurance Indemnity Fund NPC, including its reference to the earlier authority Densam (as quoted in Propell) on cedability in contexts involving delectus personae considerations. The court held that the HOA’s purported cession to the defendant was not competent insofar as it entailed transferring obligations vis-à-vis the plaintiff, and concluded that the defendant therefore lacked locus standi to pursue the counterclaim on behalf of the HOA.


The judgment further stated that, even if standing were assumed, the defendant had not led sufficient evidence to justify the relief sought concerning the boundary wall and related structures, including the absence of expert evidence to identify the common property or boundary line as necessary for the demolition-type relief claimed. It also reasoned that other aspects raised were not shown to be prejudicial to other owners or to require approvals on the evidence presented. The counterclaim was dismissed.


Finally, on costs, the court exercised its discretion against the defendant. It considered the way the litigation had been conducted, the concessions made during cross-examination, and the view that a more reasonable approach by the defendant would have resolved the reconventional issues without prolonged litigation. The judgment concluded that the defendant’s conduct warranted a punitive costs order, and awarded costs on an attorney-and-client scale.


5. Outcome and Relief


The court upheld the plaintiff’s claim in part and awarded damages in the sum of R486 550.36, together with interest at the prescribed rate from 1 March 2018 to date of final payment.


The court dismissed the defendant’s claim in reconvention in its entirety.


The defendant (as defendant in convention and plaintiff in reconvention) was ordered to pay the costs of suit on the attorney-and-client scale.


Cases Cited


Alfred McAlpine & Son (Pty) Ltd v Transvaal Provincial Administration 1974 (3) SA 506 (A).


Mullin (Pty) Ltd v Benade Ltd 1952 (1) SA 211 (AD).


S. A. Mutual Aid Society v Cape Town Chamber of Commerce 1962 (1) SA 598 (AD).


Reigate v Union Manufacturing Co. 118 L.T. 479.


Sandlundlu (Pty) Ltd v Shepstone and Wylie Incorporated [2011] 3 All SA 183 (SCA).


Holmdene Brickworks (Pty) Ltd v Roberts Construction Co Ltd 1977 (3) SA 670 (A).


Propell Speciallised Finance (Pty) Ltd v Attorneys Insurance Indemnity Fund NPC 2019 (2) SA 221 (SCA).


Densam (full citation not provided in the judgment text; referenced via quotation in Propell Speciallised Finance (Pty) Ltd v Attorneys Insurance Indemnity Fund NPC 2019 (2) SA 221 (SCA)).


Legislation Cited


No legislation was cited in the judgment.


Rules of Court Cited


No rules of court were cited in the judgment.


Held


The court held that the sale agreement, interpreted in context, incorporated a tacit term that the defendant developer would provide or ensure the provision of the necessary infrastructure to deliver a fully serviced site, including bulk electricity, enabling completion-related testing and certification and ultimately occupation.


It held that the defendant breached that obligation by failing to take the steps required to secure electricity supply timeously, and that the plaintiff’s inability to occupy until February 2018 flowed from that breach. The court awarded the plaintiff proven damages that flowed from the breach from July 2017, but rejected a substantial damages component because the plaintiff did not prove the quantum claimed.


In reconvention, the court held that the defendant lacked locus standi to pursue the counterclaim on the basis of the HOA cession, and that the counterclaim also failed on the evidence. The counterclaim was dismissed, and punitive attorney-and-client costs were awarded against the defendant.


LEGAL PRINCIPLES


A tacit (implied) term may be imported into a contract only where, on a reasonable and businesslike construction of the express terms and admissible surrounding circumstances, the implication necessarily arises that the parties intended the contract to operate on that basis. The “bystander test” is applied as a practical tool to assess whether the term is so obvious and necessary for business efficacy that the parties would have assented to it as a matter of course.


Where a contract does not specify a definite time for performance, performance is generally enforceable forthwith, but performance cannot be demanded in a manner that is unreasonable or that defeats the object of the contract, and sufficient time must be allowed for compliance.


Contractual damages are aimed at placing the innocent party in the position they would have occupied had the contract been properly performed, subject to mitigation and the limiting doctrines of causation and remoteness. Only those damages that naturally and generally flow from the breach (or are within the parties’ contemplation in special circumstances) are recoverable, and the plaintiff bears the burden of proving quantum.


In relation to cession and standing, the judgment applied authority to the effect that whether rights are cedable may turn on the nature of the debtor’s obligations and whether the arrangement involves delectus personae features. On the facts as assessed, the HOA cession relied upon was held not competent to confer standing on the defendant vis-à-vis the plaintiff in the manner required for the counterclaim.


Costs are within the court’s discretion, and punitive costs on the attorney-and-client scale may be awarded where the conduct of a party in the litigation, viewed as a whole, is considered to justify such an order.

About SAFLII
Databases
Search
Terms of Use
RSS Feeds
South Africa: South Gauteng High Court, Johannesburg
SAFLII
>>
Databases
>>
South Africa: South Gauteng High Court, Johannesburg
>>
2023
>>
[2023] ZAGPJHC 356
|

|

Orkin v Goldleaf Investment (Pty) Ltd (22321/2018) [2023] ZAGPJHC 356 (21 April 2023)

SAFLII
Note:
Certain
personal/private details of parties or witnesses have been
redacted from this document in compliance with the law
and
SAFLII
Policy
REPUBLIC OF SOUTH
AFRICA
IN THE HIGH COURT OF
SOUTH AFRICA
GAUTENG LOCAL
DIVISION, JOHANNESBURG
Case Number:
22321/2018
NOT
REPORTABLE
NOT
OF INTEREST TO OTHER JUDGES
21.04.23
In
the matter between:
NADINE
ORKIN
Plaintiff
and
GOLDLEAF
INVESTMENTS (PTY) LTD
Defendant
NEUTRAL
CITATION:
Nadine
Orkin v Goldleaf Investment (PTY) LTD
(Case
No: 2018/22321) [2023] ZAGPJHC 356(21 April 2023)
JUDGMENT
MIA, J
Introduction
[1]
The plaintiff instituted an action against
the defendant for breach of a contract. She claimed damages pursuant
to the breach in
the amount of R1 012 859.92. The plaintiff
is a retiree, residing at Erf [...] Sandown Ext 28. The defendant is
Goldleaf
Investments (Pty) Ltd, a company duly registered in terms of
the laws of South Africa. In its plea, the defendant denied liability

and counterclaimed on a ceded right seeking that the plaintiff should
remove a boundary wall and reduce the height of a wall that

encroached over the building line onto the common property; and
directing that the plaintiff removes an air conditioning unit;

satellite dish and aerial on her roof as well as the electric fence
surrounding her unit.
Background Facts
[2]
The
following facts are common cause between the parties. The plaintiff
purchased a vacant stand from the defendant, a developer
in terms of
an agreement concluded on 14 November 2014 (the agreement).
Clause 4.1 of the agreement provided that the purchaser
agreed to
conclude a separate agreement with Galencia Construction Proprietary
Limited, Registration No [...] (Galencia Construction)
to erect a
dwelling on the property. An addendum to the agreement was effected
on 12 April 2015 that provided for Claycon Proprietary
Limited, to
replace Galencia Construction. The addendum replaced the contractor
only and provided that all of the terms not amended
by the addendum
would remain in full force and effect.  The plaintiff paid the
purchase price for the property and took transfer
of the property on
9 May 2016. The building plans for the house were approved on 22 July
2016. According to the agreement the contractor
would complete the
building within nine months from the date of commencement, ie
approval of the building plans, 22 July 2016,
which presupposed the
building would be completed by April 2017
[1]
.
[3]
The major building structure was completed
in April 2017. The contractor could not hand over the property as the
electrical points
could not be checked and tested. At that point,
there was no electricity provided to the site. The bulk supply was
connected by
Eskom in December 2017.At this stage, the builder’s
holiday had commenced. The bulk supply was only available from 18
January
2018 and was connected to the plaintiff’s reticulation
system on 25 January 2018.   Eskom issued a section 82
certificate
on 2 February 2018 and the City of Johannesburg issued an
occupancy certificate on 22 February 2018.
Issues in Dispute
[4]
The issues for determination were:
4.1   whether the
defendant was required to supply the necessary infrastructure so as
to provide a fully serviced site in respect
of municipal services and
electrical services;
4.2   whether the
defendant was required to ensure that all the necessary
infrastructure was in place so as to provide a fully
serviced site
both in respect of municipal and electrical services;
4.3   whether the
defendant breached the sale agreement by failing to provide,
alternatively to ensure the supply of electricity
to the site which
caused a delay in the completion of the building work;
4.4   whether the
plaintiff is liable for the respondent’s costs on the counter
claim?
[5] The plaintiff led the
evidence of three witnesses, Mr. Michael Eric Parsons, Ms. Diane
Forstman and Mr Ivan Orkin. The defendant
led the evidence of Mr
James Robinson and Mr Eran Michaeli.
Plaintiff’s
claim in convention
[6] The plaintiff’s
claim is based on a tacit term. In her particulars of claim she
pleaded that the defendant was to provide
infrastructure which
included a fully serviced site in respect of municipal services and
electrical services; the provision of
bulk supply of electricity
alternatively would ensure all the necessary infrastructure was in
place so as to provide a fully serviced
site both in respect of
municipal and electrical services.
The law
[7]
The Court in
Alfred
McAlpine & Son (Pty) Ltd v Transvaal Provincial Administration
[2]
per
Corbett said:

[An]
implied term is used to denote an unexpressed provision of the
contract which derives from the common intention of the parties,
as
inferred by the Court from the express terms of the contract and the
surrounding circumstances.”

the Court does not
readily import a tacit term. It cannot make contracts for people; nor
can it supplement the agreement of the
parties merely because it
might be reasonable to do so. Before it can imply a tacit term the
Court must be satisfied, upon a consideration
in a reasonable and
businesslike manner of the terms of the contract and the admissible
evidence of the surrounding circumstances,
that an implication
necessarily arises that the parties intended to contract on the basis
of the suggested term, (See Mullin (Pty.) Ltd. v Benade

Ltd., 1952 (1) SA 211 (AD) at pp. 2145, and the authorities there cited;

S. A. Mutual Aid Society v Cape Town Chamber of Commerce, 1962(1) SA
598(AD)). The practical test to be applied and the one which
has
consistently been approved and adopted in this Court- is that
formulated by SCRUTTON, L.J. in the well-known case of Reigate
v
Union Manufacturing Co., 118L.T. 479 at p483:

You must only imply the
term if it is necessary- in the business sense to give efficacy to
the contract; that is if it is such a
term that you can be confident
that if at the time the contract was being negotiated someone had
said to the parties:” What
will happen in such case? They would
have both replied: Of course so and so; we did not trouble to say
that. It is too clear. “
This
is often referred to as the “bystander test”. “
[8]
The plaintiff’s case is the following: In terms of the sale
agreement the purchaser must pay for water and electricity
connected
to a defined property, Erf [...] Sandown Extension.
[3]
Thus,
the agreement presumes that bulk electricity is supplied to the site.
Without the supply of electricity, the plaintiff or
any of the other
purchasers and residents to pay for water and electricity connected
to the defined property.
[4]
Thus,
the agreement presumes that bulk electricity is supplied to the site.
[9]  Counsel for the
defendant submitted that the defendant was not liable to do so and
was not responsible for the lack of
supply of electricity. The
problem was with Eskom and with the plaintiff who harassed Eskom.
Counsel for the defendant conceded,
however, that the defendant was
responsible for the reticulation, internally, in Bellisimo complex.
The delay in April and May,
counsel submitted was as a result of
changes at Eskom which required documents which should have been
demanded in 2014. The incompetence
could not be visited upon the
defendant. Counsel submitted that the defendant appointed an
electrical engineer at its own cost
to facilitate the application for
the installation and it was not due to its inexperience that the
installation did not occur as
the plaintiff suggested.
[10]  In his
evidence, Mr Robinson, who was contracted to build the units,
confirmed that the developer was responsible for
the bulk supply of
electricity or to ensure all the necessary infrastructure was in
place so as to provide a fully serviced site
both in respect of
municipal and electrical services. Mr Michaeli’s evidence was
that Claycon was introduced to him through
the estate agent Ms du
Toit. Mr Robinson who may initially have been “the bystander”
confirmed that in his view that
this was what was implied. He, thus,
confirmed the tacit term. He also confirmed that this was the usual
practice and it was how
the bulk supply infrastructure was delivered
to the site, i.e. by the developer. Later he, assisted the developer,
when the building
operations were nearing its completion, when he
approached Eskom with Mr Michaeli. It was also Mr Robinson who
introduced the electrical
engineers to the developer to submit the
drawings to Eskom to facilitate the installation. The conclusion to
be drawn from this
is that a fully serviced site in respect of
electrical and municipal services would have to be present to enable
the purchasers
to occupy their homes. This could not occur without
the internal reticulation. This required specific submissions which
the developer
had not made.
[11]  He stated
that, Eskom connection was required to enable the builder to test the
electrical points to be in a position
to hand over occupancy
certificates. The purchasers could not apply for their individual
electrical and municipal accounts. Thus
the express terms, the
bystander test and the surrounding circumstances as well as the
evidence all point to the developer being
responsible for having a
fully serviced site in place once the construction was completed to
enable the plaintiff to take occupation
of the home.
The Breach
[12]  In determining
whether there was a breach of the agreement this court must have
regard to the agreement between the parties.
“The general rule
is that contractual obligations for the performance of which no
definite time is specified are enforceable
forthwith; but the rule is
subject to the qualification that performance cannot be demanded
unreasonably so as to defeat the objects
of the contract or to allow
an insufficient time for compliance (See
McAlpine
).
[13]
Reverting to the facts of this matter, in 2014, the developer made an
application for the supply of bulk electricity
to the defined
property. However, when the contractor commenced building and when
the construction was completed it had not been
made. The developer
appears not to have appreciated the requirements and an electrical
engineer was appointed to attend to this
in 2017 after the plaintiff
and the plaintiff’s advisor Mr. Parsons
[5]
enquired
about the electrical connection.
[14]
It is evident that the developer incorrectly believed he did all that
was required by making payment in 2014. He was
not aware that there
were further documents to be furnished and he had no idea about
Eskom’s requirements. These were dealt
with by the electrical
engineer whom the developer eventually appointed in 2017. The
electrical engineer prepared the submission
of the proper design,
construction drawings, the summarised specifications which included
cabling routes up to the end line of
the main distribution board to
meet Council requirements. This referred to the layout of the
internal reticulation to meet the
Eskom connection. The engineer’s
service included site meetings, coordination with the supplier Eskom
and co-ordination with
Eskom.
[6]
These
preparatory documents would have had to be submitted between 2014 and
2016 to ensure the Eskom electricity connection in 2017.
Nothing
happened during this period. The engineers took over and attended to
the submission in March 2017 and after the presentation;
Eskom
indicated in August 2017 that installation would take place in
December 2017.
[15]  The developer
appeared to be under the impression he had paid Eskom to attend to
the project and that it included addressing
the specifications for
the internal reticulation in the development. Moreover, the developer
laboured under the impression that
it was an instant service akin to
a “plug and play” option. It is not surprising that
nothing happened until the electrical
engineers were appointed and
the delay is foreseeable. The defendant did nothing to enquire about
that, to follow up on or to contact
the relevant office in relation
to the complex whilst aware the building was nearing completion.
There is no evidence that the
developer took any steps to ensure the
supply was connected as this was necessary to test plug points and
connections. The developer’s
response that Eskom was to blame
does not absolve the developer of its own obligations in the
contract. It was required to do what
was necessary to ensure the
supply to the complex as required by the agreement.
[16]  The
developer’s indication that it was not responsible for Eskom’s
program between June and December 2017
does not excuse the developer
from performing in terms of its own agreements especially where it
was aware of its obligations and
did nothing from 2014 other than
make payment. The developer was required to perform timeously to
ensure that it could meet its
obligations in terms of the agreement.
That it deflects responsibility to Eskom suggests that the developer
was unaware of Eskom’s
requirements relating to the internal
reticulation and that it expected to jump the queue in terms of
service delivery also assuming
that the service was an instantly
available “a plug and play” over the counter paid
service. When advised of the installation
date to fit in with Eskom’s
own programme the developer attributed the delay to Eskom without
appreciating that the delay
was due to its late own submission
through the electrical engineer which was only handed to Eskom in
March 2017, despite the payment
being made in 2014.
[17]  It is not
clear how this development was to be prioritised in a developing city
such as Johannesburg where other developments
were occurring on a
daily basis and the demand for electrical installation and connection
is in demand. For the installation to
meet the contractor’s
needs the developer was required to submit the documents and
specifications long before it did to ensure
it would be accommodated
in Eskom’s program and that both the Council’s
requirements, the contractor’s requirement
and Eskom’s
programme aligned.
[18]  As
demonstrates above, the defendant’s deflection of
responsibility to Eskom is disingenuous. The developer was

responsible for ensuring a fully serviced site both in respect of
municipal and electrical services by the time the construction
was
complete. This would in turn enable the electrical connections to be
tested and the electrical compliance certificate to be
issued and an
occupancy certificate to be issued. This plaintiff could not take
occupation from July 2017 when the construction
was complete until
February 2018 when the occupancy certificate was issued. The
developer did not manage or facilitate the process
during this period
to ensure the plaintiff could take occupation.
[19]  The
defendant’s claim that the plaintiff delayed the installation
is simply without merit. The electrical engineer’s
application
clearly indicates that there was a submission required by Eskom which
involved technical and or professional input
from an engineer which
the developer did not submit. The plaintiff could not alter the
defendant’s failure to submit the
documents earlier and to
present them to the Eskom forum and facilitate the installation. The
plaintiff’s application for
services had to wait because the
bulk installation was delayed by the defendant’s belated
submission as is evident from Ms
Forstman’s evidence. The
suggestion that the occupancy certificate was based on outstanding
monies fails to appreciate that
the balance of monies was due upon
receipt of the certificate of occupation. After the lengthy delays
and with the builder gone
on holiday in December 2017, it was
unlikely that the plaintiff would pay over any monies until she
received all that was required
to enable he to move into her home
that she paid a substantial amount for.
Causation and Damages
[20]  Counsel for
the defendant submitted that the plaintiff failed to prove causation
or any damages except rental damages.
The general rule is that
contractual damages must flow from the breach. I have already found
for the plaintiff above that
the breach occurred from July 2017. I
proceed to consider which damages flow from the breach.
[21]
In
Sandlundlu
v (Pty) Ltd v Shepstone and Wylie Incorporated
[7]
,
the court said

The
general rule in relation to contractual damages is that the appellant
is entitled to be put in the position it would have been
in if the
respondent executed its mandate properly. The general rule suggests
that some line needs to be drawn to ensure that the
respondent should
not be caused undue hardship. The line is drawn with regard to broad
principles
of
causation
and
remoteness.
In
Holmdene
Brickworks
(Pty)
Ltd
v
Roberts
Construction
Co
Ltd
1977 (3) SA 670
(A) at 687C-F [also reported at
[1977] 4 All SA 94
(A) - Ed], the rationale for the rule in regard to an award of
damages for breach of contract was eloquently stated as follows:
"The
fundamental
rule
in
regard
to
the
award
of
damages
for
breach
of
contract
is
that
the
sufferer
should
be
placed
in
the
position
he
would
have
occupied
had
the
contract
been
properly
performed,
so
far
as
this
can
be
done
by
the
payment of money and without undue hardship to the
defaulting party . . . . To ensure that undue hardship is not imposed
on the
defaulting party the sufferer is obliged to take reasonable
steps to mitigate his loss or damage. . .  and, in addition, the

defaulting party's liability is limited in terms of broad principles
of causation and remoteness, to (
a
)
those damages that flow naturally and generally from the kind of
breach of contract in question and which the law presumes the
parties
contemplated as a probable result of the breach, and (
b
)
those damages that, although caused by the breach of contract, are
ordinarily regarded in law as being too remote to be recoverable

unless, in the special circumstances attending the conclusion of the
contract, the parties”
[22]  The parties
agreed on extensions until July 2017, the breach occurred from July
2017. This meant that the plaintiff’s
rental, if calculated
over a period of seven months at R41 800 amounted to R 292 600.
The cost of the Project Manager at R19 152
is permitted from
July 2017 to February 2018 for the three months. The amounts prior to
this period are not permitted as they do
not flow from the breach.
[23]  The further
damages claimed are for the items installed on the premises and which
the plaintiff did not have the use
of over a period of six months
which the plaintiff paid for and incurred interest on. The plaintiff
was given a credit of one million
for PC items. Had the items been
purchased by the defendant the claim would not arise or would be
subsumed under rental costs.
The plaintiff must thus, be liable for
the interest on these items in any event. She did produce the bank
statements which reflected
the interest claimed. She only discovered
a table of amounts relating to the PC items. This cannot satisfy the
requirement that
a plaintiff must prove her damages claim in this
regard or in the amount claimed. As I result, the conclusion that
must be drawn
is that the plaintiff has not proved the amount of R
355 524. 56.
[24]  The further
damages relate to the legal costs the plaintiff incurred whilst
addressing the issues prior to initiating
summons in the matter in
order to protect her rights. These costs do not arise in connection
with the action however they flow
from the breach. I have perused the
list attached to the heads of argument and am satisfied that the
costs from March 2017 to February
2018 relate to the plaintiff
addressing her rights in relation to the installation and the breach.
The fee is R130 494.36.
The full amount of damages includes
rental for the period R290 021.32, the project manager’s
cost from July 2017 to
February 2018 R57 456, the gardener R6000,
legal costs R130 494 36 yielding a total of R486 550 36;
excluding the R 355 524.56
which the plaintiff has not proven.
Claim in reconvention
[25]  In respect of
the claim in reconvention counsel for the defendant/ plaintiff in
reconvention informed the court that
this issues had become resolved
and the only issue that remained was the costs.  Counsel
submitted that as the plaintiff had
addressed the issues, the
defendants were successful and entitled to costs. In relation to the
issue of
locus standi
counsel submitted that the plaintiff was
misguided in its submissions to submit that the defendant could not
amend its pleading
as it had not objected to the amendment and had
not raised any issue regarding prejudice. The plaintiff raised the
issue of
locus standi
of the developer. It was submitted that
the HOA association board of directors could litigate without the
consent of individual
members of the HOA. Counsel submitted further
that it was a valid and binding cession.  Counsel for the
defendant submitted
furthermore, that the plaintiff had not made out
a case for the breach and if the court found that it had, the
plaintiff had not
proved damages beyond rental and was not entitled
to damages that it did not prove referring to the decision of
Holmdene and Sandlundlu.
[26]
Counsel for the plaintiff submitted that the defendant did not have
locus
standi
to proceed. The cession counsel continued, was in valid. Counsel
referred to the decision of
Propell
Speciallised Finance (Pty) Ltd v Attorneys Insurance Indemnity Fund
NPC
[8]
where
the Court reiterated it this as follows:

This
court in
Densam
[9]
at
112A-D held that:

The
question whether a claim (that is, a right flowing from a contract)
is not cedable because the contract involves a
delectus
personae
falls to be answered with
reference, not to the nature of the cedent’s obligation
vis-à-vis
the
debtor, which remains unaffected by the cession, but to the nature of
the debtor’s obligation
vis-à-vis
the cedent, which is the counterpart of
the cedent’s right, the subject-matter of the transfer
comprising the cession. The
point can be demonstrated by means of the
lecture-room example of a contract between master and servant which
involves the rendering
of personal services by the servant to his
master: the master may not cede his right (or claim) to receive the
services from the
servant to a third party without the servant’s
consent because of the nature of the latter’s obligation to
render the
services; but at common law the servant may freely cede to
a third party his right (or claim) to be remunerated for his
services,
because of the nature of the master’s corresponding
obligation to pay for them, and despite the nature of the servant’s

obligation to render them.’
[27]  In the present
matter the HOA has right which it has ceded to the developer. The
rights which they ceded to the defendant
is a cession, assignment and
delegation. These obligations require that committees be established
in managing the complex Bellisimo
so as to address the various issues
that may arise with the home owners. Counsel for the plaintiff
submitted that the deed of cession
which entailed a cession,
assignment and delegation and ceded both rights and obligations,
could not occur without the agreement
of the plaintiff as a
homeowner. Moreover, the cession, counsel submitted only occurred on
16 July 2019, well after the counterclaim
was filed, it followed that
the defendant did not have standing and did not seek the court’s
leave to proceed with the counterclaim
of the HOA against the
plaintiff. Consequently, the claim should be dismissed.  The
counter claim was brought
in terrorem
against the plaintiff
and used to bully the plaintiff. He also requested that the scale of
costs reflect the time that the plaintiff
was required to invest in
defending a matter which was not capable of succeeding from the
onset.
[28]  In addition,
counsel submitted that the defendant did not tender any expert
evidence to identify the common property
or boundary line in order to
support the relief sought namely tearing down a boundary wall, which
protected an elderly resident.
The building plans despite not being
approved by the municipality were to be submitted for approval as the
builder was working
with the plaintiff throughout. The second change
did not require municipal approval. The plaintiff could regularise
the boundary
wall rather than tear down the wall. Mr Michaeli’s
eventually conceded during cross examination that the walls need not
be
torn down which indicated that the relief sought was unnecessary.
The issues raised by the defendant could be addressed with cladding

and regularised. The counterclaim in prayers two and three were thus
petty. The defendant thus utilised court time to litigate
against the
plaintiff to harass an elderly resident where the plaintiff rights
were infringed.
[29]  The defendant
capitulated and said it had to go to a vote and that could not decide
when the right had been ceded to
it. There was no reason why
demolition of wall was necessary. Counsel for the defendant conceded
that much. On entering the complex,
the units appeared similar with
the L shaped wall which connected the gate house. The forfeiture of a
parking was only to the detriment
of the Orkin family. The
counterclaim was a bullying tactic and should be dismissed with
attorney client costs.
[30]  Having regard
to the decision in
Propell
, the cession by the HOA to the
defendant was not competent as the HOA obligations could not be
transferred to the defendant
vis-a-vis
the plaintiff.
The defendant did not have
locus standi
to pursue the
counterclaim on behalf of the HOA.
[31]  Even if the
defendant had
locus standi
, the defendant did not lead
evidence in relation to the boundary wall to obtain the relief it
sought. The evidence in relation
to the second internal wall which
effectively removed a parking bay affects only the Orkins property
and is not prejudicial to
any other property owner. The conversion of
the home from a four bedroom to a three-bedroom home is an internal
change and no evidence
was led to indicate that it required either
the HOA or the Municipality’s approval. Having regard to the
evidence led by
the in the claim in reconvention, the claim is
dismissed.
Costs
[32] Costs remain in the
discretion of the court. I have considered the manner in which the
litigation has proceeded and the evidence
of the plaintiff and
defendant witnesses. Many concessions were made during
cross-examination. A reasonable approach by the defendant
would have
resolved all of the issues addressed in re -convention as ultimately
occurred and was finally resolved by the end of
the trial had the
defendant adopted a different attitude toward the plaintiff.  Three
days were allocated to the matter and
a further three days were
utilised to accommodate the matter during recess and between other
matters. The development of residential
estates entails a huge
responsibility where other people’s lives are concerned and is
not a fiefdom with no accountability.
The developer resides in the
complex owns units in the estate and still controls hold the
controlling vote on the HOA. It is important
that there be
accountability with regard to what occurred. In this matter an
attorney and client costs order is appropriate having
regard to the
conduct of the defendant.
[33]  For the
reasons above, I make the following order:
Order
1.The
defendant is to pay the plaintiff the sum of R 486 550.36.
2.
Interest on the aforesaid sum at the prescribed rate of interest from
1 March 2018 to date of final payment.
3.
The claim in reconvention is dismissed.
4.
The defendant/ plaintiff in reconvention is ordered to pay the costs
of suit on an attorney and client scale.
SC
Mia
JUDGE OF THE HIGH
COURT
JOHANNESBURG
Appearances
For
the Plaintiff:
Adv.
D Vetten
Instructed
by:
Martini-Patlansky
Attorneys
For
the Defendant:
Adv.
M Nowits
Instructed
by:
Hirschowitz
Flionis Attorneys
Hearing:
16,17,18,19 November 2021 & 11, 12 January 2022
Judgment:
21 April 2023
[1]
This took into account the three weeks’ builders holiday in
December.
[2]
Alfred
McAlpine & Son (Pty) Ltd v Transvaal Provincial Administration
1974(3) SA 506 A at 531
[3]
Clauses 5, 6.5, 15,2
[4]
Clauses 5, 6.5, 15,2
[5]
Mr Parsons raised the issue as a concern in February 2017.
[6]
Caselines Correspondence 012-139
[7]
[2011]
3 All SA 183
SCA
[8]
Propell
Speciallised Finance (Pty) Ltd v Attorneys Insurance Indemnity Fund
NPC
2019(2) SA 221 (SCA)
[9]
Id.