Kathu Solar Park (RF) (Pty) Ltd v Mahon and Another (2020/4931) [2020] ZAGPJHC 277 (11 March 2020)

80 Reportability
Commercial Law

Brief Summary

Dispute Resolution — Independent Expert — Jurisdiction — Applicant sought to interdict the second respondent and the appointed independent expert from proceeding with a fast track dispute resolution process regarding delay liquidated damages (DLDs) under an engineering, procurement and construction contract — Dispute arose over the imposition of DLDs while extension of time claims were pending — Court held that the only dispute referred to the independent expert was the imposition dispute, not the broader liability dispute — Independent expert lacked jurisdiction to determine the liability dispute as it was not expressly referred for determination — Urgent application granted, interdicting the continuation of the fast track process pending resolution of jurisdictional issues.

Comprehensive Summary

Summary of Judgment


1. Introduction


This judgment concerns an urgent application in the Gauteng Local Division, Johannesburg (Commercial Court), arising from a contractual dispute-resolution mechanism in a large construction contract. The proceedings were directed at determining the jurisdictional limits of an appointed independent expert in a contractually agreed “fast track” dispute process.


The applicant was Kathu Solar Park (RF) (Pty) Ltd (“Kathu”), the project owner/employer under an engineering, procurement and construction contract (“the EPC contract”). The second respondent was Liciastar (Pty) Ltd (“Liciastar”), the construction contractor. The first respondent, Mr Terry Mahon, was the independent expert appointed under the EPC contract to determine certain disputes on a fast-track basis; he abided the court’s decision.


Procedurally, Kathu approached the court on an urgent basis seeking to interdict the continuation of the fast-track process pending determination of the expert’s jurisdiction. The matter came before Unterhalter J for certification as a commercial court matter. The judge certified it and, instead of burdening the urgent court, heard the application for final relief on an expedited basis.


The general subject-matter was the scope of a referral to an independent expert concerning delay liquidated damages (“DLDs”) under the EPC contract, and whether the expert could proceed to decide a broader dispute than the one expressly referred.


2. Material Facts


Kathu employed Liciastar to construct a solar power plant under the EPC contract. The contract contained a dispute-resolution clause (clause 21) that provided for negotiation and arbitration as the default pathway, but also provided for a fast track process in which an independent expert could determine disputes that the contract expressly permitted to be referred directly to that process.


It was common ground that on 26 December 2018 Liciastar wrote to the Director of the Law Society of the Northern Provinces indicating that a dispute had arisen and seeking to refer it under the fast-track mechanism. In that letter, Liciastar described the dispute as relating to the owner’s intention to charge DLDs due to potential delays in achieving the Initial Acceptance Date of the plant from 18 December 2018. The letter also relied on clause 13.7.1 of the EPC contract, which provided that disputes about whether the contractor is liable to pay liquidated damages pursuant to clauses 13.5 and 13.6 must be determined by an independent expert in accordance with clause 21.2.


The EPC contract distinguished between the Scheduled Initial Acceptance Date (“SIAD”) and the Initial Acceptance Date (“IAD”). The SIAD was the scheduled date by which initial acceptance was to be achieved, while the IAD was the date on which the owner issued a certificate stating that the facility complied with the initial acceptance requirements. The contract regulated the consequences of a failure to cause the IAD to occur on or before the SIAD, including the obligation to pay DLDs.


Liciastar submitted extension of time claims which, if recognised, would move the SIAD and thereby allow more time to meet the initial acceptance requirements. The judgment records that certain claims were recognised by Eskom, which extended the SIAD to 18 December 2019. The judgment further records that Kathu nevertheless commenced the imposition of DLDs on 19 December 2018.


It was common ground that a dispute crystallised in December 2018 when Kathu began imposing DLDs while Liciastar’s extension of time claims were pending. The court identified that crystallised dispute as whether DLDs could be imposed even though the final SIAD might yet be extended. The judgment referred to this as the “imposition dispute”.


A further, broader dispute existed in concept: whether Liciastar was liable for DLDs at all (the “liability dispute”). The parties were in disagreement about whether the liability dispute had been referred to the independent expert by the December 2018 referral.


The independent expert, Mr Mahon, determined the imposition dispute in favour of Liciastar on 16 July 2019. He considered the parties’ difference about the scope of his mandate to be of “little moment” because he understood clause 21.2 to permit him to “take the initiative in ascertaining the facts and the Law”, and on that basis he proposed to proceed to entertain the liability dispute.


Kathu then sought court relief to prevent the fast-track process continuing in relation to the liability dispute, contending that Mr Mahon lacked jurisdiction to decide it.


3. Legal Issues


The court was required to determine two central questions.


The first was a jurisdictional and interpretive issue grounded in contract: what dispute or disputes had been “expressly referred” to the independent expert under clause 21.2, and therefore what dispute or disputes the independent expert was competent to determine. This was primarily a matter of interpretation of the EPC contract and the application of that interpretation to the text of the referral communication and the existence (or non-existence) of a crystallised dispute at the time of referral.


The second issue was remedial and discretionary: whether it was permissible and appropriate for the court to intervene in an ongoing private dispute-resolution process (the fast-track expert determination), and whether Kathu was entitled to the declaratory and interdictory relief it sought. This entailed a value judgment in the exercise of discretion, informed by legal principles about party autonomy in private dispute resolution, the contractual nature of expert determinations, and the practical consequences of allowing potentially futile proceedings to continue.


4. Court’s Reasoning


Contractual framework and the “express referral” requirement


The court analysed the EPC contract’s dispute-resolution architecture. It recognised that the contract created two dispute-resolution “species”: negotiation followed by arbitration as the default mechanism, and the fast track expert determination mechanism for disputes that the contract permitted to be routed directly to an independent expert.


The court emphasised the introductory wording of clause 21.2: only disputes “expressly referred for determination” pursuant to clause 21.2 were to be determined by the relevant independent expert. On this wording, the court held that two cumulative requirements had to be satisfied before an independent expert could assume jurisdiction: the dispute must be of a kind that the contract permits to go to the fast track, and it must have been expressly referred under the fast-track process.


While it was common cause that both the imposition dispute and the liability dispute were disputes that clause 13.7.1 required to be determined by an independent expert (and were therefore eligible for fast track), eligibility did not resolve the decisive question. The decisive question remained whether the liability dispute had in fact been expressly referred.


Interpretation of the 26 December 2018 referral and crystallisation of disputes


The court considered what Liciastar’s letter of 26 December 2018 actually defined and referred as “the dispute”. It reasoned that the letter’s definition of the dispute was directed at Kathu’s intention to charge DLDs due to potential delays, which the court considered to align with the imposition dispute, namely the permissibility of imposing DLDs while extension-of-time claims were pending and the SIAD might be extended.


Liciastar relied on a portion of the letter in which it stated that it wanted “to dispute any payment of DLD”. The court rejected the submission that this necessarily encompassed the broader liability dispute. It interpreted that language in context, holding that the “current project situation” described in the letter referred to the live controversy that had already arisen: the imposition of DLDs notwithstanding pending extension claims. On that interpretation, the phrase “dispute any payment of DLD” was understood as disputing payment because Kathu was said not to be entitled to impose DLDs at that stage, not as a referral of all possible questions about ultimate liability.


The court then applied a principle concerning what constitutes a dispute capable of referral. Relying on Delfante and another v Delta Electrical Industries Ltd 1992 (2) SA 221 (C), the court held that a dispute must be an issue that is palpable and genuine; absent a dispute that has crystallised, “there is nothing to refer”. The court rejected the possibility of an anticipatory referral of disputes that had not yet crystallised, noting that anticipated disputes may never arise or may be resolved by concession or compromise.


Because Liciastar conceded (as recorded by the court) that the only live dispute at the time of the referral was the imposition dispute, the court concluded that only that dispute could have been referred. Any attempt to treat the letter as referring a broader dispute that was not yet a live controversy was held to be incompetent.


Limits of the independent expert’s power under clause 21.2


The court addressed Mr Mahon’s reliance on clause 21.2’s statement that the independent expert may “take the initiative in ascertaining the facts and the Law”. The court accepted that this language could afford procedural flexibility, including inquisitorial fact-finding or controlling the order in which issues within the referred dispute are addressed. However, it held that such a power does not extend to expanding the scope of the dispute referred for determination.


The court distinguished between an expert’s ability to investigate and understand what has been referred, and any purported power to assume jurisdiction by unilateral fiat. It held that, unless the EPC contract conferred an express competence on the expert to decide his own jurisdiction and to enlarge it, the expert could not determine disputes beyond the express referral. On the facts, the court found that Mr Mahon had not ruled on the scope of referral as a jurisdictional question; instead, he proposed to proceed to decide the liability dispute on grounds of convenience, which the court held the contract did not permit.


On this reasoning, the court concluded that Mr Mahon lacked jurisdiction to determine the liability dispute.


Whether court intervention was permissible and appropriate


Liciastar argued that the parties had agreed to resolve disputes through the contract’s dispute-resolution processes rather than the courts, and that the court should be slow to intervene while the fast-track process was underway. It suggested that Kathu could object before the expert and, if unsuccessful, resist enforcement of any adverse determination later.


The court reasoned that fast-track expert determination under the EPC contract was not arbitration, and therefore not subject to the supervisory jurisdiction conferred by the Arbitration Act 42 of 1965. Nonetheless, it accepted that expert determination is akin to arbitration in that it rests on party agreement to submit defined disputes for private determination. In that respect, the court acknowledged the Constitutional Court’s emphasis in Lufuno Mphaphuli & Associates (Pty) Ltd v Andrews 2009 (4) SA 526 (CC) on respecting parties’ choices to adopt private dispute-resolution mechanisms.


However, the court held that respect for private dispute resolution does not exclude ordinary contractual remedies. Because expert determinations lack a direct statutory underpinning, the court approached them through the law of contract. It held that when an expert exceeds the mandate in a material respect, any resulting determination is a nullity, and the party affected may seek appropriate relief to enforce the agreement’s limits. The court indicated that this approach accords with English law (with reference to Shell UK Limited v Enterprise Oil PLC 1999 (2) Lloyd’s Reports 456) and that South African law is no different.


On whether it should intervene at the present stage, the court treated the issue as analogous to the question addressed in Inter-Continental Finance and Leasing Corporation (Pty) Ltd v Stands 56 and 57 Industria Ltd 1979 (3) SA 740 (W), which concerned whether to interdict arbitration proceedings where jurisdiction was disputed. The court accepted that, in some circumstances, permitting a process to run its course and dealing with jurisdiction only at enforcement may be possible, but it endorsed the Inter-Continental Finance approach that it is often neither convenient nor just to await the outcome where doing so would result in futile proceedings and wasted, at least partly irrecoverable, costs.


The court then exercised its discretion in light of the case’s circumstances. It highlighted that the jurisdictional question was self-standing, that the proceedings had not advanced beyond pleadings, that Kathu had consistently maintained the jurisdiction objection, and that there was no identifiable benefit in allowing the fast-track process to continue on a dispute beyond the expert’s mandate. The court considered that an early judicial determination would avoid unnecessary cost and avoid a later burden on the courts at the enforcement stage.


On that basis, the court held that declaratory relief was warranted, and that Liciastar, having opposed it unsuccessfully, should bear the costs.


5. Outcome and Relief


The court granted declaratory relief determining that the independent expert lacked jurisdiction in the fast-track process to determine the issues and grant the relief set out in Liciastar’s statement of claim dated 31 January 2020 (being the claim advancing the liability dispute in the fast-track process).


The court ordered that Liciastar (Pty) Ltd pay the costs of the application.


Cases Cited


Delfante and another v Delta Electrical Industries Ltd 1992 (2) SA 221 (C).


Lufuno Mphaphuli & Associates (Pty) Ltd v Andrews 2009 (4) SA 526 (CC).


Shell UK Limited v Enterprise Oil PLC 1999 (2) Lloyd’s Reports 456.


Inter-Continental Finance and Leasing Corporation (Pty) Ltd v Stands 56 and 57 Industria Ltd 1979 (3) SA 740 (W).


Legislation Cited


Arbitration Act 42 of 1965.


Rules of Court Cited


No rules of court were cited in the judgment.


Held


The court held that, although both the imposition dispute and the liability dispute were of a type that the EPC contract allowed to be determined by an independent expert, only disputes expressly referred could be determined under clause 21.2. On the facts, the December 2018 referral encompassed only the imposition dispute that had crystallised at the time, and did not validly refer the broader liability dispute. The independent expert’s procedural power to “take the initiative” in ascertaining facts and law did not permit him to enlarge the scope of the referral or assume jurisdiction beyond the contractually referred dispute.


The court further held that it was permissible and appropriate to intervene at this stage, granting declaratory relief to prevent the continuation of a fast-track process in respect of a dispute beyond the expert’s jurisdiction, and awarded costs against Liciastar.


LEGAL PRINCIPLES


A contractual fast-track expert determination clause confers jurisdiction on an independent expert only in respect of disputes that the contract both permits to be resolved by that mechanism and that are expressly referred for determination under the relevant clause.


A dispute capable of referral must have crystallised into a palpable and genuine controversy; an anticipatory referral of a dispute that has not yet arisen is not competent, because absent a live dispute there is nothing to refer for determination.


An independent expert’s power to “take the initiative in ascertaining the facts and the Law” is a procedural power concerning how the expert investigates and determines the dispute referred; it does not confer authority to expand the scope of the dispute or to assume jurisdiction over additional disputes not expressly referred.


Expert determinations are approached through the law of contract rather than the statutory framework applicable to arbitrations. Where an expert exceeds the contractual mandate in a material respect, the purported determination is treated as a nullity, and a party may seek judicial relief to enforce the contractual limits of the process.


Although courts generally respect parties’ choice of private dispute resolution, they retain a discretion to intervene where a self-standing jurisdictional defect would render continuing proceedings futile and costly, and where early determination provides clarity and avoids wasted expenditure.

About SAFLII
Databases
Search
Terms of Use
RSS Feeds
South Africa: South Gauteng High Court, Johannesburg
SAFLII
>>
Databases
>>
South Africa: South Gauteng High Court, Johannesburg
>>
2020
>>
[2020] ZAGPJHC 277
|

|

Kathu Solar Park (RF) (Pty) Ltd v Mahon and Another (2020/4931) [2020] ZAGPJHC 277 (11 March 2020)

REPUBLIC OF SOUTH AFRICA
IN THE HIGH COURT OF SOUTH AFRICA
GAUTENG LOCAL DIVISION,
JOHANNESBURG
CASE NUMBER: 2020/4931
COMMERCIAL COURT
In the matter between:
KATHU SOLAR PARK (RF) (PTY) LTD
APPLICANT
And
TERRY
MAHON                                                                                 FIRST

RESPONDENT
LICIASTAR (PTY)
LTD                                                                 SECOND

RESPONDENT
J U D G M E N T
UNTERHALTER
J
INTRODUCTION
1.
The
applicant, Kathu Solar Park (Pty) Ltd, (“Kathu”) employed
the second respondent Liciastar (Pty) Ltd (“Liciastar”)

as the construction contractor in terms of an engineering,
procurement and construction contract (“ the EPC contract”).

The EPC contract engaged Liciastar to construct a solar power plant.
The EPC contract, in clause 21, provides for dispute resolution.
One
type of such dispute resolution is fast track dispute resolution by
an independent expert (“ the fast track”).
2.
Liciastar
referred a dispute to the fast track. The first respondent, Mr Mahon,
was appointed as the independent expert to determine
the dispute.
Kathu and Liciastar are at odds as to the scope of Mr Mahon’s
jurisdiction. Mr Mahon abides this court’s
decision.
3.
Kathu
brought an urgent application to interdict Liciastar and Mr Mahon
from proceeding with the fast track process, pending the

determination of Mr Mahon’s jurisdiction. The matter came
before me for certification as a commercial court case. I certified

the case, and rather than burden the urgent court, heard the
application for final relief on an expedited basis.
4.
It
is common ground that on 26 December 2018, Liciastar sent a letter to
the Director of the Law Society of the Northern Provinces.
Liciastar
indicated that a dispute had arisen with Kathu under the EPC
contract.
5.
In
the letter, Liciastar referenced the dispute as follows:

The
dispute relates to the intention of the Owner to charge Delay
Liquidated Damages to the Contractor due to potential delays in

achieving the Initial Acceptance Date of the Plant from the 18
th
December 2018 ( the “Dispute”)
The EPC clauses 13.5, 13.6 and 13.7
regulates DLD and payments, the Contractor, taking into account
current Project situation want
to dispute any payment of DLD as the
EPC Contract says in clause 13.7.1 :

Any
dispute between the Parties about whether the Contractor is liable to
pay Liquidated Damages pursuant to clauses 13.5 and 13.5
( sic) shall
be determined by an Independent Expert in accordance with clause
21.2”
6.
Kathu
and Liciastar agree that at the time that the letter was written to
the Law Society a particular dispute had crystalized.
The EPC
contract provides for a scheduled initial acceptance date (“SIAD”).
Initial acceptance references when the
facility is considered capable
of commercial operation and ready for initial acceptance by the
owner, as judged against stated
requirements.  The SIAD may be
extended or amended.  The EPC contract distinguishes the SIAD,
that is the scheduled date
for initial acceptance and the initial
acceptance date (“IAD”), being the date on which the
owner delivers a certificate
to the contractor stating the date upon
which the facility complied with the initial acceptance requirements.
7.
The
EPC contract regulates the consequences of a failure by the
contractor to cause the IAD to occur on or before the SIAD, that
is a
failure to ensure that the facility complies with the initial
acceptance requirements on or before the scheduled date. In
that
event the contractor shall pay to the owner delay liquidated damages
(“DLDs”).
8.
Liciastar
submitted extension of time claims. The effect of these claims, if
recognized,  would move the SIAD, thus allowing
Liciastar more
time to meet the initial acceptance requirements. Certain of these
claims were recognized by Eskom. This extended
SIAD to 18 December
2019.
9.
Kathu,
however, was unwilling to suspend the imposition of DLDs beyond that
date and commenced the imposition of DLDs on 19 December
2018.
10.
It
is common ground that this gave rise to a dispute between Kathu and
Liciastar. Kathu’s position was that it was entitled
to invoice
Liciastar from 19 December 2018 for DLDs and to do so until IAD.
Liciastar’s stance was that Kathu had no entitlement
to do so
because the pending extension of time claims would, if recognized,
extend SIAD. The dispute that crystallized in December
2018 was this:
could DLDs be imposed even though the final SIAD might yet be
extended? ( “ the imposition dispute”)
11.
Kathu
contends that the imposition dispute is the only dispute that was
referred to the independent expert, Mr Mahon, and it was
determined
by him. Liciastar contends that the dispute referred to the
independent expert is far wider and encompasses the liability
of
Liciastar for DLDs (“ the liability dispute “) On 16 July
2019, Mr Mahon decided the imposition dispute in favour
of Liciastar.
In his decision, Mr Mahon reflected the difference between the
parties as to the dispute he was required to determine.
Mr Mahon
considered this difference to be “
of
little moment
“ because he considered that the EPC contract in clause 21.2
permitted him to “
take
the initiative in ascertaining the facts and the Law”
and
this included deciding the order in which issues in dispute should be
dealt with. Consequently, Mr Mahon wishes to entertain
the liability
dispute.
12.
I
must decide two issues.  First, what disputes have been referred
to the independent expert and what disputes may he determine?
Second,
if the independent expert lacks jurisdiction to determine the
liability dispute, was it permissible for Kathu to approach
this
court for relief as it has done, and is Kathu entitled to the relief
that it claims?
JURISDICTION
13.
Whether
Mr Mahon enjoys the jurisdiction to determine the liability dispute
depends, in the first place, upon an interpretation
of the relevant
provisions of the EPC contract and what it is that was referred for
dispute resolution.
14.
The
EPC contract recognizes two species of dispute resolution. The first
is by way of negotiations to reach a settlement, failing
which the
dispute shall be resolved by arbitration. The second is by way of the
fast track. Dispute resolution by negotiations
and if necessary
arbitration must be used, unless the provisions of the EPC contract
permit a dispute to be referred directly to
the fast track ( clause
21.1). Clause 21.2, which regulates the fast track commences as
follows: “
Disputes
expressly referred for determination pursuant to this clause 21.2
shall be determined by the relevant Independent Expert”
15.
Clauses
13.5, 13.6 and 13.7 regulate DLDs. Clause 13.7.1 read as follows :

Any
dispute between the Parties about whether the Contractor is liable to
pay Liquidated Damages pursuant to clauses 13.5 and 13.6
shall be
determined by an Independent Expert in accordance with clause 21.2 “
16.
It
is clear from the wording of clause 13.7.1 , and was common ground
between the parties, that both the imposition dispute and
the
liability dispute are disputes that the EPC contract requires to be
determined by the fast track.
17.
However,
the introductory language of clause 21.2 stipulates that disputes
must be expressly referred for determination. It is disputes
thus
referred that shall be determined by the independent expert by way of
the fast track.
18.
Before
the independent expert can assume jurisdiction over a dispute two
requirements must be satisfied.  First, the dispute
must be one
that the EPC contract permits of resolution by recourse to the fast
track.  Second, the dispute must be expressly
referred to the
independent expert under the fast track.
19.
Since
it is common ground that the imposition dispute and the liability
dispute may permissibly be resolved by recourse to the fast
track,
the question is whether the liability dispute was expressly referred
to Mr Mahon under the fast track. The parties are at
odds on this
question.
20.
What
is it, then, that Liciastar referred for determination by the
independent expert? I must in the first place consider the text
that
Liciastar used in its letter of 26 December 2018 to the Law Society
in which it defined the dispute and sought to refer the
dispute in
terms of clause 21.2 of the EPC contract.
21.
I
have set out above the relevant passage from the letter.
22.
Liciastar
emphasizes this portion of the letter : “ …
the
Contractor, taking into account current Project situation wants to
dispute any payment of DLD as the EPC contract says in clause
13.71
…”.
Liciastar
submits that it placed in dispute any payment of DLDs and that covers
the liability dispute.
23.
I
do not agree. First, the relevant text defines the dispute. The
dispute, as defined, relates to the intention of Kathu to charge
DLDs
due to potential delays. There can be little doubt that this refers
to the imposition dispute.  Having defined the dispute,

Liciastar references the relevant clauses of the EPC contract that
regulate DLDs and payments.
24.
What
then of the portion of the letter emphasized by Liciastar ? This
says, “
taking
into account current (sic) Project situation”.
As at 26 December 2018, the current project situation was that
Liciastar sought extensions of the SIAD, Kathu nevertheless sought
to
impose DLDs, and Liciastar disputed its entitlement to do so.
The only dispute that had crystalized was whether DLDs could
be
imposed, even though extensions of SIAD were sought by Liciastar.
When Liciastar then referenced in the passage quoted that
it “
wants
to dispute any payment of DLD …”,
it
was disputing payment of DLDs on the basis that Kathu could not
impose DLDs while Liciastar sought extensions of SIAD.
That was the
only dispute that then existed concerning payment of DLDs. Hence, the
portion of the letter relied upon by Liciastar,
properly interpreted
as part of the passage as a whole, was simply saying that whether
payment could be claimed when the imposition
of the DLDs was in
dispute was a species of dispute that the EPC contract requires to be
determined under the fast track.
25.
It
is difficult to postulate a different interpretation.  To refer
a dispute for determination, there must be a particular
live
controversy between the parties.
Delfante
[1]
,
put it this way: there must be an issue, palpable and genuine. If no
dispute has yet crystalized, there is nothing to refer. Even
if a
party anticipates a dispute, that too does not suffice. The dispute
may not actually come about, or the dispute may yield
to concession
or compromise. In neither case is there anything to refer.  If
there is a dispute, there may be further requirements
that must be
met before a referral can take place. But absent a dispute, there can
be no referral – nothing comes from nothing.
26.
It
follows that if, as Liciastar concedes, the only live dispute between
the parties when the referral took place was the imposition
dispute,
then all that could have been referred to the independent expert was
the imposition dispute. That Liciastar may have anticipated
other
disputes, including the liability dispute, is irrelevant. There can
be no anticipatory referral of a dispute that has not
yet
crystalized.
27.
Counsel
for Liciastar,
Mr
Reyneke SC,
pressed
the point that once Liciastar indicated that it wanted to dispute any
payment of DLDs, that permitted of a referral to the
independent
expert of the liability dispute even though this dispute was not yet
an issue between the parties. That submission
falls to be rejected.
An anticipatory referral, for the reasons given, is not competent.
28.
Mr
Mahon considered that the difference between the parties as to the
scope of the referral to be of little moment. He understood
clause
21.2 to allow him to “
take
the initiative”
and on the grounds of convenience entertain the liability dispute.
29.
That
is not a competence that Mr Mahon enjoyed. Clause 21.2 requires the
independent expert to act impartially and “
may
take the initiative in ascertaining the facts and the Law”.
Whatever
freedom this may allow the independent expert to apply his industry
and expertise, and use inquisitorial procedures,
it does not extend
to a competence to fashion the scope of the dispute that has been
referred to him. The manner in which the independent
expert goes
about ascertaining the facts and the law relates only to the dispute
referred to him.  This provision in the EPC
contract affords the
independent expert no power to expand the scope of the dispute
requiring his determination.
30.
In
so holding, I should not be misunderstood to say that the independent
expert could not investigate what disputes had been referred
to him.
He could have done so.   He might then have declined to
adjudicate further on a reference not properly
made or he may have
decided to proceed and determine the dispute. However, unless the EPC
contract conferred the power upon the
independent expert to decide
the jurisdictional dispute, in addition to the underlying dispute,
the independent expert cannot determine
his own jurisdiction. The
party challenging jurisdiction would then resist enforcement of any
determination, and the courts would
decide the jurisdictional issue.
But here Mr Mahon did not rule on the jurisdictional issue as to what
dispute had been referred
to him. Rather, he decided of his own
initiative to assume jurisdiction to decide the liability dispute.
The EPC contract provides
no competence for the independent expert to
assume jurisdiction by unilateral fiat.
31.
For
these reasons, I find that Mr Mahon enjoys no jurisdiction to
determine the liability dispute.
ARE
THE PROCEEDINGS PERMISSIBLE?
32.
Liciastar
contends that under the terms of the EPC contract, the parties bound
themselves to take their disputes to dispute resolution
and not to
the courts. The parties are before Mr Mahon in the fast track
process. Mr Mahon has adopted a two stage process.
He has
determined the imposition dispute and would now proceed to determine
the liability dispute. The court, it was submitted,
should be slow to
intervene in these circumstances. Rather, Kathu should raise its
jurisdictional objections before Mr Mahon. Should
these be
unavailing, Kathu can always resist enforcement of any  adverse
determination that Mr Mahon may make.
33.
Ultimately,
Liciastar does not say that I cannot make an order to vacate the
jurisdiction of Mr Mahon in respect of the liability
dispute, but
that I should not do so.
34.
Fast
track dispute resolution under the EPC contract is not an
arbitration. It is thus not subject to the supervisory jurisdiction

given to this court under the
Arbitration Act 42 of 1965
. Akin to
arbitration ,however, the fast track is based upon agreement by the
parties to have defined disputes referred for private
determination.
This choice, the Constitutional Court in
Lufuno
[2]
has
stressed, should be respected by the courts.
35.
That
respect does not mean that the remedies that a court standardly
applies to agreements are avoided. The lack of a statutory
underpin
for expert determinations means that such determinations are
approached by the courts by reference to the law of contract.
Where
an expert has exceeded his mandate in some material respect, the
resulting determination is a nullity.  That is precisely
what
occurs when an expert in the position of Mr Mahon seeks to assume
jurisdiction over a dispute that he does not have. I can
see no
reason of principle why a party to such an agreement where compliance
with the agreement has not taken place may not seek
appropriate
relief. That is the position in English law,
[3]
and our law is no different.
36.
The
burden of Liciastar’s submission is not that I cannot intervene
at this stage of the fast track proceedings, but that
I should not do
so, in deference to the process before Mr Mahon. Kathu submits that
since its case is predicated upon the enforcement
of its contractual
rights, whether I should provide relief is not a question of
discretion, if it has made out its case, an order
must follow.
37.
In
the
Inter-Continental
Finance
case
[4]
,
the court had to decide between two lines of authority as to whether
a court should interdict pending arbitration proceedings
on the
grounds that the reference to arbitration was not binding. On one
view, no harm could come from allowing the arbitration
to proceed.
The party complaining of a want of jurisdiction can participate under
protest. If she succeeds in the arbitration,
the complaint falls
away. If not, she can resist enforcement of the award. The other
view, adopted in
Inter-Continental
Finance,
is
that to await the outcome of the arbitration and then oppose the
enforcement of the award is neither convenient nor just. Rather
a
party should be permitted to seek an order that prevents futile
proceedings that involve wasted and, to some extent, irrecoverable

costs.
38.
I
am seized with an application to declare that Mr Mahon does not have
jurisdiction to determine the liability dispute in the fast
track
process. Although not an arbitration, the issue as to whether a court
should grant a remedy that interferes with a process
of dispute
resolution that is underway is of piece with the question that was
answered in
Inter-Continental
Finance.
39.
Kathu
seeks an order the effect of which is to restrain Mr Mahon from
proceeding with the fast track determination of the liability

dispute. Kathus’s case rests upon Mr Mahon exceeding his
mandate. I have found that Mr Mahon has no jurisdiction and thus
that
he has, in wishing to proceed with the fast track process, exceeded
his mandate. It follows also that Kathu has established
a right to
enforce the EPC contract, and in particular, the limits of what that
contract provides as to dispute resolution.
40.
This
does not mean that the court is bound to prevent the fast track
process that Mr Mahon has commenced. The recognition of Kathu’s

right does not require that the court must grant an interdict or
declaratory relief in all circumstances. This is so because both
of
these remedies require the exercise by the court of a discretion that
is responsive to the circumstances of the case.
41.
Nor,
with respect to the learning reflected in
Inter-Continental
Finance,
is
there a single answer to the question as to whether a court should
intervene when a party complains that an independent expert
lacks
jurisdiction. Where the expert enjoys no competence to determine the
dispute and the proceedings are at their inception,
a court will
incline towards intervention so as to avoid cost and provide
clarity.  Where the question of competence is not
self-standing;
or where the complaint concerns how the expert exercised a power and
not whether he enjoyed the power; or if the
proceedings are well
underway; or if there is some benefit to be obtained from securing
the expert’s determination ( the
list is by no means exhaustive
), then the court will incline against intervention.
42.
In
this case, the question of jurisdiction is self-standing and I have
found that Mr Mahon lacks jurisdiction in respect of the
liability
dispute. The proceedings, though underway, have not progressed beyond
the pleadings.  Kathu has all along
contended that Mr
Mahon lacks jurisdiction. In these circumstances, I do not consider
that there is benefit in allowing the fast
track proceedings to
continue.  It is unwarranted to put the parties to the cost of
proceedings where there is a want of jurisdiction.
True enough, Kathu
may prevail in the fast track determination of the liability dispute.
But it is surely less costly that it achieves
that result by way of
my determination of the question of jurisdiction. And if Kathu were
to fail in the the liability dispute,
the courts would then be
burdened with determining the very question of jurisdiction that I
have decided.
43.
For
these reasons, and upon my assessment of the circumstances, Kathu is
entitled to the declaratory relief that they seek. Liciastar
opposed
this relief and is liable for the costs occasioned by its opposition.
In the result, I make the following
order:
i)
Declaring
that the First Respondent does not have jurisdiction in the fast
track dispute resolution process to determine the issues
or grant the
relief set out in the Second Respondent’s statement of claim
dated 31 January 2020.
ii)
The
Second Respondent shall pay the costs of this application
____________________
David Unterhalter
Judge of the High Court
Gauteng Local Division:
Johannesburg
Date of Hearing: 6 March 2020
Date of Judgement: 11 March 2020
Appearances:
Applicant: Advocate S Symon
instructed by MDA Attorneys
Second Respondent: Advocate CS
Reyneke instructed by Pinsent Masons Attorneys
[1]
Delfante
and another v Delta Electrical Industries Ltd
1992 (2) SA 221
( C ) at 227
[2]
Lufuno
Mphaphuli & Associates (Pty) Ltd v Andrews
2009 (4) SA 526
(CC)
at [219]
[3]
Shell
UK Limited v Enterprise Oil PLC 1999 (2) Lloyd’s Reports 456
at 470
[4]
Inter-Continental
Finance and Leasing Corporation (Pty) Lttd v Stands 56 and 57
Industria Ltd
1979
(3) SA 740
(W)