About SAFLII
Databases
Search
Terms of Use
RSS Feeds
South Africa: South Gauteng High Court, Johannesburg
SAFLII
>>
Databases
>>
South Africa: South Gauteng High Court, Johannesburg
>>
2020
>>
[2020] ZAGPJHC 277
|
|
Kathu Solar Park (RF) (Pty) Ltd v Mahon and Another (2020/4931) [2020] ZAGPJHC 277 (11 March 2020)
REPUBLIC OF SOUTH AFRICA
IN THE HIGH COURT OF SOUTH AFRICA
GAUTENG LOCAL DIVISION,
JOHANNESBURG
CASE NUMBER: 2020/4931
COMMERCIAL COURT
In the matter between:
KATHU SOLAR PARK (RF) (PTY) LTD
APPLICANT
And
TERRY
MAHON FIRST
RESPONDENT
LICIASTAR (PTY)
LTD SECOND
RESPONDENT
J U D G M E N T
UNTERHALTER
J
INTRODUCTION
1.
The
applicant, Kathu Solar Park (Pty) Ltd, (“Kathu”) employed
the second respondent Liciastar (Pty) Ltd (“Liciastar”)
as the construction contractor in terms of an engineering,
procurement and construction contract (“ the EPC contract”).
The EPC contract engaged Liciastar to construct a solar power plant.
The EPC contract, in clause 21, provides for dispute resolution.
One
type of such dispute resolution is fast track dispute resolution by
an independent expert (“ the fast track”).
2.
Liciastar
referred a dispute to the fast track. The first respondent, Mr Mahon,
was appointed as the independent expert to determine
the dispute.
Kathu and Liciastar are at odds as to the scope of Mr Mahon’s
jurisdiction. Mr Mahon abides this court’s
decision.
3.
Kathu
brought an urgent application to interdict Liciastar and Mr Mahon
from proceeding with the fast track process, pending the
determination of Mr Mahon’s jurisdiction. The matter came
before me for certification as a commercial court case. I certified
the case, and rather than burden the urgent court, heard the
application for final relief on an expedited basis.
4.
It
is common ground that on 26 December 2018, Liciastar sent a letter to
the Director of the Law Society of the Northern Provinces.
Liciastar
indicated that a dispute had arisen with Kathu under the EPC
contract.
5.
In
the letter, Liciastar referenced the dispute as follows:
“
The
dispute relates to the intention of the Owner to charge Delay
Liquidated Damages to the Contractor due to potential delays in
achieving the Initial Acceptance Date of the Plant from the 18
th
December 2018 ( the “Dispute”)
The EPC clauses 13.5, 13.6 and 13.7
regulates DLD and payments, the Contractor, taking into account
current Project situation want
to dispute any payment of DLD as the
EPC Contract says in clause 13.7.1 :
“
Any
dispute between the Parties about whether the Contractor is liable to
pay Liquidated Damages pursuant to clauses 13.5 and 13.5
( sic) shall
be determined by an Independent Expert in accordance with clause
21.2”
6.
Kathu
and Liciastar agree that at the time that the letter was written to
the Law Society a particular dispute had crystalized.
The EPC
contract provides for a scheduled initial acceptance date (“SIAD”).
Initial acceptance references when the
facility is considered capable
of commercial operation and ready for initial acceptance by the
owner, as judged against stated
requirements. The SIAD may be
extended or amended. The EPC contract distinguishes the SIAD,
that is the scheduled date
for initial acceptance and the initial
acceptance date (“IAD”), being the date on which the
owner delivers a certificate
to the contractor stating the date upon
which the facility complied with the initial acceptance requirements.
7.
The
EPC contract regulates the consequences of a failure by the
contractor to cause the IAD to occur on or before the SIAD, that
is a
failure to ensure that the facility complies with the initial
acceptance requirements on or before the scheduled date. In
that
event the contractor shall pay to the owner delay liquidated damages
(“DLDs”).
8.
Liciastar
submitted extension of time claims. The effect of these claims, if
recognized, would move the SIAD, thus allowing
Liciastar more
time to meet the initial acceptance requirements. Certain of these
claims were recognized by Eskom. This extended
SIAD to 18 December
2019.
9.
Kathu,
however, was unwilling to suspend the imposition of DLDs beyond that
date and commenced the imposition of DLDs on 19 December
2018.
10.
It
is common ground that this gave rise to a dispute between Kathu and
Liciastar. Kathu’s position was that it was entitled
to invoice
Liciastar from 19 December 2018 for DLDs and to do so until IAD.
Liciastar’s stance was that Kathu had no entitlement
to do so
because the pending extension of time claims would, if recognized,
extend SIAD. The dispute that crystallized in December
2018 was this:
could DLDs be imposed even though the final SIAD might yet be
extended? ( “ the imposition dispute”)
11.
Kathu
contends that the imposition dispute is the only dispute that was
referred to the independent expert, Mr Mahon, and it was
determined
by him. Liciastar contends that the dispute referred to the
independent expert is far wider and encompasses the liability
of
Liciastar for DLDs (“ the liability dispute “) On 16 July
2019, Mr Mahon decided the imposition dispute in favour
of Liciastar.
In his decision, Mr Mahon reflected the difference between the
parties as to the dispute he was required to determine.
Mr Mahon
considered this difference to be “
of
little moment
“ because he considered that the EPC contract in clause 21.2
permitted him to “
take
the initiative in ascertaining the facts and the Law”
and
this included deciding the order in which issues in dispute should be
dealt with. Consequently, Mr Mahon wishes to entertain
the liability
dispute.
12.
I
must decide two issues. First, what disputes have been referred
to the independent expert and what disputes may he determine?
Second,
if the independent expert lacks jurisdiction to determine the
liability dispute, was it permissible for Kathu to approach
this
court for relief as it has done, and is Kathu entitled to the relief
that it claims?
JURISDICTION
13.
Whether
Mr Mahon enjoys the jurisdiction to determine the liability dispute
depends, in the first place, upon an interpretation
of the relevant
provisions of the EPC contract and what it is that was referred for
dispute resolution.
14.
The
EPC contract recognizes two species of dispute resolution. The first
is by way of negotiations to reach a settlement, failing
which the
dispute shall be resolved by arbitration. The second is by way of the
fast track. Dispute resolution by negotiations
and if necessary
arbitration must be used, unless the provisions of the EPC contract
permit a dispute to be referred directly to
the fast track ( clause
21.1). Clause 21.2, which regulates the fast track commences as
follows: “
Disputes
expressly referred for determination pursuant to this clause 21.2
shall be determined by the relevant Independent Expert”
15.
Clauses
13.5, 13.6 and 13.7 regulate DLDs. Clause 13.7.1 read as follows :
“
Any
dispute between the Parties about whether the Contractor is liable to
pay Liquidated Damages pursuant to clauses 13.5 and 13.6
shall be
determined by an Independent Expert in accordance with clause 21.2 “
16.
It
is clear from the wording of clause 13.7.1 , and was common ground
between the parties, that both the imposition dispute and
the
liability dispute are disputes that the EPC contract requires to be
determined by the fast track.
17.
However,
the introductory language of clause 21.2 stipulates that disputes
must be expressly referred for determination. It is disputes
thus
referred that shall be determined by the independent expert by way of
the fast track.
18.
Before
the independent expert can assume jurisdiction over a dispute two
requirements must be satisfied. First, the dispute
must be one
that the EPC contract permits of resolution by recourse to the fast
track. Second, the dispute must be expressly
referred to the
independent expert under the fast track.
19.
Since
it is common ground that the imposition dispute and the liability
dispute may permissibly be resolved by recourse to the fast
track,
the question is whether the liability dispute was expressly referred
to Mr Mahon under the fast track. The parties are at
odds on this
question.
20.
What
is it, then, that Liciastar referred for determination by the
independent expert? I must in the first place consider the text
that
Liciastar used in its letter of 26 December 2018 to the Law Society
in which it defined the dispute and sought to refer the
dispute in
terms of clause 21.2 of the EPC contract.
21.
I
have set out above the relevant passage from the letter.
22.
Liciastar
emphasizes this portion of the letter : “ …
the
Contractor, taking into account current Project situation wants to
dispute any payment of DLD as the EPC contract says in clause
13.71
…”.
Liciastar
submits that it placed in dispute any payment of DLDs and that covers
the liability dispute.
23.
I
do not agree. First, the relevant text defines the dispute. The
dispute, as defined, relates to the intention of Kathu to charge
DLDs
due to potential delays. There can be little doubt that this refers
to the imposition dispute. Having defined the dispute,
Liciastar references the relevant clauses of the EPC contract that
regulate DLDs and payments.
24.
What
then of the portion of the letter emphasized by Liciastar ? This
says, “
taking
into account current (sic) Project situation”.
As at 26 December 2018, the current project situation was that
Liciastar sought extensions of the SIAD, Kathu nevertheless sought
to
impose DLDs, and Liciastar disputed its entitlement to do so.
The only dispute that had crystalized was whether DLDs could
be
imposed, even though extensions of SIAD were sought by Liciastar.
When Liciastar then referenced in the passage quoted that
it “
wants
to dispute any payment of DLD …”,
it
was disputing payment of DLDs on the basis that Kathu could not
impose DLDs while Liciastar sought extensions of SIAD.
That was the
only dispute that then existed concerning payment of DLDs. Hence, the
portion of the letter relied upon by Liciastar,
properly interpreted
as part of the passage as a whole, was simply saying that whether
payment could be claimed when the imposition
of the DLDs was in
dispute was a species of dispute that the EPC contract requires to be
determined under the fast track.
25.
It
is difficult to postulate a different interpretation. To refer
a dispute for determination, there must be a particular
live
controversy between the parties.
Delfante
[1]
,
put it this way: there must be an issue, palpable and genuine. If no
dispute has yet crystalized, there is nothing to refer. Even
if a
party anticipates a dispute, that too does not suffice. The dispute
may not actually come about, or the dispute may yield
to concession
or compromise. In neither case is there anything to refer. If
there is a dispute, there may be further requirements
that must be
met before a referral can take place. But absent a dispute, there can
be no referral – nothing comes from nothing.
26.
It
follows that if, as Liciastar concedes, the only live dispute between
the parties when the referral took place was the imposition
dispute,
then all that could have been referred to the independent expert was
the imposition dispute. That Liciastar may have anticipated
other
disputes, including the liability dispute, is irrelevant. There can
be no anticipatory referral of a dispute that has not
yet
crystalized.
27.
Counsel
for Liciastar,
Mr
Reyneke SC,
pressed
the point that once Liciastar indicated that it wanted to dispute any
payment of DLDs, that permitted of a referral to the
independent
expert of the liability dispute even though this dispute was not yet
an issue between the parties. That submission
falls to be rejected.
An anticipatory referral, for the reasons given, is not competent.
28.
Mr
Mahon considered that the difference between the parties as to the
scope of the referral to be of little moment. He understood
clause
21.2 to allow him to “
take
the initiative”
and on the grounds of convenience entertain the liability dispute.
29.
That
is not a competence that Mr Mahon enjoyed. Clause 21.2 requires the
independent expert to act impartially and “
may
take the initiative in ascertaining the facts and the Law”.
Whatever
freedom this may allow the independent expert to apply his industry
and expertise, and use inquisitorial procedures,
it does not extend
to a competence to fashion the scope of the dispute that has been
referred to him. The manner in which the independent
expert goes
about ascertaining the facts and the law relates only to the dispute
referred to him. This provision in the EPC
contract affords the
independent expert no power to expand the scope of the dispute
requiring his determination.
30.
In
so holding, I should not be misunderstood to say that the independent
expert could not investigate what disputes had been referred
to him.
He could have done so. He might then have declined to
adjudicate further on a reference not properly
made or he may have
decided to proceed and determine the dispute. However, unless the EPC
contract conferred the power upon the
independent expert to decide
the jurisdictional dispute, in addition to the underlying dispute,
the independent expert cannot determine
his own jurisdiction. The
party challenging jurisdiction would then resist enforcement of any
determination, and the courts would
decide the jurisdictional issue.
But here Mr Mahon did not rule on the jurisdictional issue as to what
dispute had been referred
to him. Rather, he decided of his own
initiative to assume jurisdiction to decide the liability dispute.
The EPC contract provides
no competence for the independent expert to
assume jurisdiction by unilateral fiat.
31.
For
these reasons, I find that Mr Mahon enjoys no jurisdiction to
determine the liability dispute.
ARE
THE PROCEEDINGS PERMISSIBLE?
32.
Liciastar
contends that under the terms of the EPC contract, the parties bound
themselves to take their disputes to dispute resolution
and not to
the courts. The parties are before Mr Mahon in the fast track
process. Mr Mahon has adopted a two stage process.
He has
determined the imposition dispute and would now proceed to determine
the liability dispute. The court, it was submitted,
should be slow to
intervene in these circumstances. Rather, Kathu should raise its
jurisdictional objections before Mr Mahon. Should
these be
unavailing, Kathu can always resist enforcement of any adverse
determination that Mr Mahon may make.
33.
Ultimately,
Liciastar does not say that I cannot make an order to vacate the
jurisdiction of Mr Mahon in respect of the liability
dispute, but
that I should not do so.
34.
Fast
track dispute resolution under the EPC contract is not an
arbitration. It is thus not subject to the supervisory jurisdiction
given to this court under the
Arbitration Act 42 of 1965
. Akin to
arbitration ,however, the fast track is based upon agreement by the
parties to have defined disputes referred for private
determination.
This choice, the Constitutional Court in
Lufuno
[2]
has
stressed, should be respected by the courts.
35.
That
respect does not mean that the remedies that a court standardly
applies to agreements are avoided. The lack of a statutory
underpin
for expert determinations means that such determinations are
approached by the courts by reference to the law of contract.
Where
an expert has exceeded his mandate in some material respect, the
resulting determination is a nullity. That is precisely
what
occurs when an expert in the position of Mr Mahon seeks to assume
jurisdiction over a dispute that he does not have. I can
see no
reason of principle why a party to such an agreement where compliance
with the agreement has not taken place may not seek
appropriate
relief. That is the position in English law,
[3]
and our law is no different.
36.
The
burden of Liciastar’s submission is not that I cannot intervene
at this stage of the fast track proceedings, but that
I should not do
so, in deference to the process before Mr Mahon. Kathu submits that
since its case is predicated upon the enforcement
of its contractual
rights, whether I should provide relief is not a question of
discretion, if it has made out its case, an order
must follow.
37.
In
the
Inter-Continental
Finance
case
[4]
,
the court had to decide between two lines of authority as to whether
a court should interdict pending arbitration proceedings
on the
grounds that the reference to arbitration was not binding. On one
view, no harm could come from allowing the arbitration
to proceed.
The party complaining of a want of jurisdiction can participate under
protest. If she succeeds in the arbitration,
the complaint falls
away. If not, she can resist enforcement of the award. The other
view, adopted in
Inter-Continental
Finance,
is
that to await the outcome of the arbitration and then oppose the
enforcement of the award is neither convenient nor just. Rather
a
party should be permitted to seek an order that prevents futile
proceedings that involve wasted and, to some extent, irrecoverable
costs.
38.
I
am seized with an application to declare that Mr Mahon does not have
jurisdiction to determine the liability dispute in the fast
track
process. Although not an arbitration, the issue as to whether a court
should grant a remedy that interferes with a process
of dispute
resolution that is underway is of piece with the question that was
answered in
Inter-Continental
Finance.
39.
Kathu
seeks an order the effect of which is to restrain Mr Mahon from
proceeding with the fast track determination of the liability
dispute. Kathus’s case rests upon Mr Mahon exceeding his
mandate. I have found that Mr Mahon has no jurisdiction and thus
that
he has, in wishing to proceed with the fast track process, exceeded
his mandate. It follows also that Kathu has established
a right to
enforce the EPC contract, and in particular, the limits of what that
contract provides as to dispute resolution.
40.
This
does not mean that the court is bound to prevent the fast track
process that Mr Mahon has commenced. The recognition of Kathu’s
right does not require that the court must grant an interdict or
declaratory relief in all circumstances. This is so because both
of
these remedies require the exercise by the court of a discretion that
is responsive to the circumstances of the case.
41.
Nor,
with respect to the learning reflected in
Inter-Continental
Finance,
is
there a single answer to the question as to whether a court should
intervene when a party complains that an independent expert
lacks
jurisdiction. Where the expert enjoys no competence to determine the
dispute and the proceedings are at their inception,
a court will
incline towards intervention so as to avoid cost and provide
clarity. Where the question of competence is not
self-standing;
or where the complaint concerns how the expert exercised a power and
not whether he enjoyed the power; or if the
proceedings are well
underway; or if there is some benefit to be obtained from securing
the expert’s determination ( the
list is by no means exhaustive
), then the court will incline against intervention.
42.
In
this case, the question of jurisdiction is self-standing and I have
found that Mr Mahon lacks jurisdiction in respect of the
liability
dispute. The proceedings, though underway, have not progressed beyond
the pleadings. Kathu has all along
contended that Mr
Mahon lacks jurisdiction. In these circumstances, I do not consider
that there is benefit in allowing the fast
track proceedings to
continue. It is unwarranted to put the parties to the cost of
proceedings where there is a want of jurisdiction.
True enough, Kathu
may prevail in the fast track determination of the liability dispute.
But it is surely less costly that it achieves
that result by way of
my determination of the question of jurisdiction. And if Kathu were
to fail in the the liability dispute,
the courts would then be
burdened with determining the very question of jurisdiction that I
have decided.
43.
For
these reasons, and upon my assessment of the circumstances, Kathu is
entitled to the declaratory relief that they seek. Liciastar
opposed
this relief and is liable for the costs occasioned by its opposition.
In the result, I make the following
order:
i)
Declaring
that the First Respondent does not have jurisdiction in the fast
track dispute resolution process to determine the issues
or grant the
relief set out in the Second Respondent’s statement of claim
dated 31 January 2020.
ii)
The
Second Respondent shall pay the costs of this application
____________________
David Unterhalter
Judge of the High Court
Gauteng Local Division:
Johannesburg
Date of Hearing: 6 March 2020
Date of Judgement: 11 March 2020
Appearances:
Applicant: Advocate S Symon
instructed by MDA Attorneys
Second Respondent: Advocate CS
Reyneke instructed by Pinsent Masons Attorneys
[1]
Delfante
and another v Delta Electrical Industries Ltd
1992 (2) SA 221
( C ) at 227
[2]
Lufuno
Mphaphuli & Associates (Pty) Ltd v Andrews
2009 (4) SA 526
(CC)
at [219]
[3]
Shell
UK Limited v Enterprise Oil PLC 1999 (2) Lloyd’s Reports 456
at 470
[4]
Inter-Continental
Finance and Leasing Corporation (Pty) Lttd v Stands 56 and 57
Industria Ltd
1979
(3) SA 740
(W)