About SAFLII
Databases
Search
Terms of Use
RSS Feeds
South Africa: Supreme Court of Appeal
SAFLII
>>
Databases
>>
South Africa: Supreme Court of Appeal
>>
2014
>>
[2014] ZASCA 21
|
|
Esorfranki Pipelines (Pty) Ltd and Another v Mopani District Municipality and Others (40/13) [2014] ZASCA 21; [2014] 2 All SA 493 (SCA) (28 March 2014)
Links to summary
THE
SUPREME COURT OF APPEAL OF SOUTH AFRICA
JUDGMENT
REPORTABLE
Case
No: 40/13
In
the matter between:
ESORFRANKI
PIPELINES (PTY)
LTD
...........................................................
FIRST
APPELLANT
CYCAD
PIPELINES (PTY)
LTD
..................................................................
SECOND
APPELLANT
and
MOPANI
DISTRICT
MUNICIPALITY
..........................................................
FIRST
RESPONDENT
TANGO
CONSULTANTS
CC
.....................................................................
SECOND
RESPONDENT
TLONG
RE TRADING SMN
JV
....................................................................
THIRD
RESPONDENT
TLONG
RE YENG TRADING
CC
............................................................
FOURTH
RESPONDENT
BASE
MAJOR CONSTRUCTION (PTY)
LTD
.............................................
FIFTH
RESPONDENT
MAITE
IRENE
MOAKAMELA
.....................................................................
SIXTH
RESPONDENT
MOTLATSO
CONSTANCE
MALEBATE
..............................................
SEVENTH
RESPONDENT
LU
JINPU
.......................................................................................................
EIGHTH
RESPONDENT
MAILULA
CHRISPOLAND
MAHOWA
......................................................
NINTH
RESPONDENT
Neutral
citation:
Esorfranki Pipelines v
Mopani District Municipality
(40/13)
[2014] ZASCA 21
(28 March 2014)
Coram
:
Mthiyane DP, Lewis and Bosielo JJA, Van Zyl and Legodi AJJA
Heard:
4 March 2014
Delivered:
28 March 2014
Summary:
Judicial review of administrative
action – tender process – contract concluded pursuant to
unlawful tender award declared
void and set aside –
determination of a just and equitable remedy in terms of
s 8
of the
Promotion of Administrative Justice Act 3 of 2000
– relevant
considerations – municipality found to have been biased in its
decision to award the tender – successful
tenderers guilty of
fraud and fronting – orders for costs to reflect the
reprehensible and serious nature of the conduct
of the municipality
and the successful tenderers.
ORDER
On
appeal from:
North Gauteng High Court,
Pretoria (Matojane J sitting as court of first instance):
1
The first and second appellants’ appeal against the orders in
paras 2 and 3 of the order of the high court is upheld with
costs
including the costs of two counsel, such costs to be paid jointly and
severally by the first and the third to fifth respondents
on the
scale as between attorney and client.
2
The aforesaid orders are set aside and are substituted with the
following orders:
‘
(a)
Any contract entered into between the first respondent and the third
to fifth respondents pursuant to the award of the tender
to the
respondents for the construction of a pipeline between the Nandoni
dam and the Nsami water treatment works (Nandoni to Giyani
Pipe
Project; project number LPR018), is declared void
ab
initio
and is set aside.
(b)
The first respondent is ordered to formally approach the Department
of Water Affairs within seven days of the granting of this
order to
request that Department to do the following:
(i)
To take such steps as may be necessary to determine the extent of the
works necessary to perform remedial work and to complete
the
construction of the pipeline and the other works as contemplated in
the aforesaid tender, for purposes of publishing a tender
for the
said remedial work and the completion of the works;
(ii)
To prepare and publish an invitation to tender for the performance of
the remedial work and completion of the works as aforesaid;
(iii)
To evaluate and adjudicate all bids received, and to make an award in
respect of such invitation to bid.
3
The first and the third to fifth respondents jointly and severally
are ordered to pay the costs of the review application by
Esorfranki
Pipelines (Pty) Ltd under case no 13480/2011, and of the third
Rule
49(11)
application dated 27 August 2011 under case no 13480/2011,
such costs to be on an attorney and client scale, and to be inclusive
of all the reserved costs and the costs of two counsel where
applicable.
4
The first and the third to fifth respondents jointly and severally
are ordered to pay the costs of the review application by Cycad
Pipelines (Pty) Ltd under case no 17852/2011, such costs to be on an
attorney and client scale, and to be inclusive of all the
reserved
costs and the costs of two counsel where applicable.
5
The first appellant’s appeal against the order in para 4 of the
order of the high court is dismissed with costs.’
JUDGMENT
Van
Zyl AJA (Mthiyane DP, Lewis and Bosielo JJA and Legodi AJA
concurring)
[1]
In August 2010 the first respondent, the Mopani District Municipality
(the municipality) invited tenders for the construction
of concrete
reservoirs and a welded steel bulk pipeline between the Nandoni dam
in Thohoyandou and the Nsami water treatment works
in Giyani in the
Limpopo Province. The purpose of the pipeline was to provide water to
the greater Giyani area. A drought in 2009
caused the water levels in
the Nsami dam to drop to the extent that there was insufficient water
to ensure a supply of water to
the inhabitants of Giyani. The water
shortage was so severe that a local state of disaster was declared in
terms of the provisions
of the
Disaster Management Act 57 of 2002
and
emergency measures had to be implemented.
[2]
A decision was then made at a national government level to source
water from the Nandoni dam and an amount of more than R284
million
was made available for that purpose. The construction of the pipeline
is a project of the Department of Water Affairs.
The municipality was
appointed by the Department as an ‘implementation agent’.
In terms of their agreement it was made
responsible for the
implementation and management of the project. To that extent it was
tasked with the appointment of contractors
and other service
providers ‘in accordance with procurement procedures approved
by the department and in consultation with
the Department when
inviting bids, considering bids and administering the contracts of
appointed Professional Service Providers
(PSP’s) and
Contractors’.
[3]
The tender was awarded to the third respondent, a joint venture (the
joint venture) consisting of two entities, namely the fourth
respondent, Tlong Re Yeng Trading CC (Tlong Re Yeng) and the fifth
respondent, Base Major Construction (Pty) Ltd (Base Major
Construction).
Two unsuccessful bidders, namely the first appellant,
Esorfranki Pipelines (Pty) Ltd (Esorfranki) and the second appellant,
Cycad
Pipelines (Pty) Ltd (Cycad), then proceeded to bring review
proceedings in the North Gauteng High Court. This culminated in an
agreement in terms of which the award was set aside and the
municipality was ordered to re-adjudicate the tenders received by it.
According to the municipality the reason for this agreement, which
was made an order of court, was the realisation that in the
tender
process it had applied regulations made in terms of the Preferential
Procurement Policy Framework Act,
[1]
which unbeknown to it had been declared
ultra
vires
by the KwaZulu-Natal High Court.
[2]
[4]
The municipality thereafter in February 2011 re-adjudicated the
tenders and once more decided to award the tender to the joint
venture. Esorfranki and Cycad were once again dissatisfied with this
decision and as before individually proceeded to institute
review
proceedings. The main relief sought by each appellant was the setting
aside of the municipality’s decision to award
the tender to the
joint venture and the substitution thereof of a decision to award the
tender to them. Each application was further
accompanied by a claim
for interim relief in the form of an interdict pending the outcome
and final adjudication of the review
application, and in terms of
which the municipality was to be restrained from taking any steps in
implementing the decision to
award the tender to the joint venture.
The joint venture was in turn to be interdicted from taking any steps
towards the execution
of any contract which may have been concluded
pursuant to the decision.
[5]
Cycad chose not to pursue its application for interim relief, because
an interim order (the interim order) was granted by the
high court at
the instance of Esorfranki in March 2011. This order became the
subject matter of a plethora of further proceedings
aimed at either
setting it aside, or its continued operation and implementation. I
intend to refer to some of these proceedings
in such detail as may be
relevant to the issues raised in this appeal. The first step was
taken by the municipality which applied
for leave to appeal the
granting of the interim order. In terms of Rule 49(11) of the Uniform
Rules of Court, the effect of an
application for leave to appeal
against an order of the court is that the order is suspended pending
the decision of such application,
‘unless the court which gave
such order, on the application of a party, otherwise directs’.
When the municipality and
the joint venture failed to give an
undertaking that the award of the tender would not be acted upon,
Esorfranki then proceeded
in terms of sub-rule (11) to apply for an
order that, pending the determination of the application for leave to
appeal, the interim
order should continue to operate. This resulted
in the granting of an interim order suspending any further work on
the project.
[6]
That order was extended from time to time until the dismissal of the
municipality’s application for leave to appeal. In
dismissing
the application the high court held that its order was interim in
nature and effect, that it was not appealable and
that on the merits
there were no reasonable prospects that another court would come to a
different conclusion. The municipality
proceeded to file a petition
to this court for leave to appeal against the grant of the interim
order. This was followed by a second
application brought by
Esorfranki in terms of Rule 49(11). It once again sought to
prevent the implementation and execution
of the tender. Following
upon this application, the municipality and the joint venture gave
certain undertakings with regard to
the continued execution of work
on the tender. Some of these undertakings were incorporated into a
court order, only to be discharged
at a later date. This prompted
Esorfranki to launch a further application for an interim interdict
which was to operate pending
the hearing of the second Rule 49(11)
application. This in turn culminated in an order interdicting the
municipality and the joint
venture from taking any steps to implement
the award of the tender pending the adjudication of the second Rule
49(11) application.
Subsequent to this order this court dismissed the
municipality’s application for leave to appeal. The result was
that there
no longer existed any necessity, as in the case of the
first application, to determine the merits of the second application
in
terms of Rule 49(11).
[7]
Dissatisfied with the decision of this court to dismiss its
application for leave to appeal, the municipality then filed an
application with the Constitutional Court for leave to appeal to that
court. This caused Esorfranki to institute a third application
in
terms of Rule 49(11) (the third Rule 49(11) application). It once
again sought an order that pending the outcome and adjudication
of
the municipality’s application for leave to appeal to the
Constitutional Court, the interim order remain in operation.
In this
application Esorfranki also sought additional relief against certain
of the office bearers of the municipality and the
joint venture (the
sixth to eighth respondents), namely that they be ordered to give
effect to the interim order sought and that
they be held to be in
contempt of the interim order for their earlier failure to do so.
Esorfranki further cited the municipality’s
attorney of record
Mr M C Mahowa (Mahowa) as the ninth respondent, asking the court not
only to order him to give effect to the
interim order, but also to
pay the costs of the third Rule 49(11) application
de
bonis propris
, on an attorney and
client scale.
[8]
In response to the third Rule 49(11) application the municipality
filed a counter application seeking to set aside the interim
order,
and an order declaring Esorfranki’s review application to have
lapsed. On the date of the hearing both these applications
were by
agreement postponed to enable the parties to file further affidavits.
In addition, it was ordered by agreement that the
interim order would
remain in force pending the determination of these applications.
Cycad subsequently entered the fray when it
became aware of the
existence of the municipality’s counter application, and it,
with a view to protect its own interests,
sought leave to intervene
and be afforded an opportunity to file an answering affidavit
therein. At the adjourned hearing of the
third Rule 49(11)
application and the counter application, it was agreed that both the
counter application and Cycad’s application
to intervene would
be postponed
sine die
.
Agreement was further reached with regard to the hearing and further
conduct relating to Esorfranki and Cycad’s applications
for
review. It was inter alia agreed that the two matters would be heard
simultaneously.
[9]
It would appear from the judgment of the high court (per Matojane J)
that at the joint hearing of the two review applications
the issues
for decision were limited to the lawfulness of the municipality’s
decision to award the tender to the joint venture
and the costs of
Esorfranki’s third Rule 49(11) application. Esorfranki
abandoned the remainder of the relief claimed
in the latter
application, whilst the municipality abandoned its counter
application with a tender of costs, such costs to include
the costs
of two counsel. Cycad in turn informed the court that it was no
longer persisting in its claim in its review application
that the
tender be awarded to it.
[10]
The high court upheld the challenge of Esorfranki and Cycad to the
decision of the municipality to award the tender to the
joint
venture. There is no appeal against the order that the award was
unlawful and that it was set aside. Nonetheless it is necessary
briefly to describe the reasons for that order. The high court found
that the tender submitted by the joint venture did not comply
with
the bid specifications, that it was guilty of fronting and that the
municipality’s decision was motivated by bias and
bad faith.
These
findings were based inter alia on the following factors. The joint
venture failed to comply with the required contractor grading.
This
is a standard determined and issued in terms of the
Construction
Industry Development Board Act 30 of 2000
and its regulations.
[3]
To qualify for evaluation a bidder must have the required contractor
grading designation which is based on the estimated tender
value. The
required grading in this matter was 8CE PE or higher. In the case of
a tender by a joint venture the bid documentation
required every
member of the joint venture to be registered with the Construction
Industry Development Board; the lead partner
to have a contractor
grading designation of 8CE PE or higher; and the combined grading to
be higher or equal to 8CE PE. Tlong Re
Yeng was found to have
possessed a grading of 1CE PE, and Base Major Construction a grading
of 8CE. In the circumstances the court
concluded that the joint
venture failed to comply with the tender specifications and ought to
have been disqualified from the tender
process. Cycad and other
similarly placed bidders were eliminated during the re-adjudication
of the tenders on the basis that they
possessed only a grading of
8CE.
[11]
The high court further found that the joint venture failed to submit
some of the information required by the tender specifications
necessary to assess the tender requirements relating to competence
and functionality. Members of the joint venture were also found
to
have made false representations in their tender submission. Tlong Re
Yeng falsely stated that it was conducting its business
at a given
address when it was not, resulting in it being awarded a point in the
adjudication of the tender in respect of locality.
It falsely claimed
to have been in business for three years prior to the submission of
the tender. Base Major Construction in turn
falsely represented that
its sole shareholder, a foreign-born national, obtained South African
citizenship at his/her date of birth,
thereby improving its score for
equity promotion goals. In the joint venture agreement entered into
between Tlong Re Yeng and Base
Major Construction it was recorded
that both entities individually had experience in the construction
industry when it was obvious
that Tlong Re Yeng had no such
experience and was as a consequence unable to manage and execute its
half of the work. Lastly, by
declaring that Tlong Re Yeng and Base
Major Construction were, contrary to the terms of the joint venture
agreement, to manage
and execute the contract for the construction of
the pipeline in equal shares, they managed to acquire additional
points in relation
to equity promotion goals.
[12]
The high court found support for its finding that Tlong Re Yeng was
used as a front in the following facts: it was established
as an
entity only after publication of the invitation to tender and a week
before the tender was submitted; it had no assets, employees
or
income; it did not conduct business at the time the tender was
submitted; it had no business address and did not exist at the
address given in the tender documentation, which was a residential
house with only a few pieces of furniture; and lastly, Tlong
Re
Yeng’s sole member was an employee at an unrelated business.
[13]
Having found that the award of a tender was reviewable on grounds
contained in
s 6
of the
Promotion of Administrative Justice Act
(PAJA
),
[4]
the high court then
proceeded to determine what would constitute a just and equitable
remedy as envisaged in
s 8
of PAJA. The orders made by the court
relevant to this appeal read as follows:
‘
1.
The tender process is declared illegal and invalid and is set aside.
2.
The Municipality is ordered to independently and at the joint
venture’s costs, verify that all the work has been done
according to specifications and that the joint venture does all the
necessary remedial work and work is completed as soon as possible
in
terms of the agreement.
3. Each party is
ordered to pay its own costs.
4.
Esorfranki Pipelines (Pty) Ltd is ordered to pay ninth respondents’
costs on the attorney and own client scale, including
the costs
reserved on 3 and 4 October 2011.’
[14]
The appellants’ appeal is with the leave of the high court.
Esorfranki’s appeal is directed at the orders made
in paras 2,
3 and 4 of the order. It seeks the setting aside of those orders and
the substitution of an order to the effect that
it be declared to
have been the sole successful bidder in respect of the tender; that
the municipality enter into a contract with
it for the completion of
the outstanding work on the pipeline; that the municipality and the
members of the joint venture pay the
costs of the application for
review and of the third
Rule 49(11)
application on a punitive scale;
and that Mahowa pay the costs of the third
Rule 49(11)
application.
Cycad’s appeal is in turn directed only at paras 2 and 3 of the
order of the high court. It seeks an order setting
aside those orders
and substituting them with an order that the contract concluded
between the municipality and the joint venture
be set aside and that
they pay the costs of its application in the review proceedings on an
attorney and client scale. None of
the respondents affected by the
order of the high court chose to challenge either the correctness of
the finding of the court that
the award of the tender to the joint
venture was reviewable and liable to be set aside in terms of PAJA,
or the relief granted.
[15]
Before dealing with the main issue raised by the appeal (that is, the
appropriate relief to be afforded to Esorfranki and Cycad),
there are
two preliminary matters that must first be disposed of. The first
relates to the issue raised by the municipality and
the joint venture
in their heads of argument and in documentation filed subsequently
that any order dealing with the validity of
the contract concluded
between the municipality and the joint venture for the construction
of the pipeline would not have any practical
effect. The submission
was that the work would in all probability have been concluded by the
time of the hearing of this appeal.
This contention, however, stood
in stark contrast to a recent progress report of the Department of
Water Affairs and other evidence
placed before this court by
Esorfranki showing that the work on the project is anything but
complete. Counsel for the relevant
respondents consequently elected
to abandon any argument that the issues raised in the appeal may have
become moot.
[16]
The second aspect is the objection raised by the municipality and the
joint venture to the standing of Cycad. The contention
is based on
the fact that the bid specifications required a tenderer to have a
contractor grading designation of 8CE PE. Because
Cycad had a lower
grading it was argued that it could not submit a tender capable of
acceptance and could not proceed to contest
the award in the
litigation. I am, however, satisfied that Cycad does have standing in
the circumstances of this case. It sought
to vindicate the
constitutional right of just administrative action given expression
in PAJA.
[5]
Its standing is
therefore to be determined in terms of s 38 of the
Constitution
[6]
read into
PAJA:
[7]
In
Giant
Concerts CC v Rinaldo Investments (Pty) Ltd & others
[8]
the principles applicable to standing in this context were summarised
as follows:
‘
(a)
To establish own-interest standing under the Constitution a litigant
need not show the same “sufficient, personal and
direct
interest” that the common law requires, but must still show
that a contested law or decision directly affects his
or her rights
or interests, or potential rights or interests.
(b)
This requirement must be generously and broadly interpreted to accord
with constitutional goals.
(c) The interest
must, however, be real and not hypothetical or academic.
(d)
Even under the requirements for common law standing, the interest
need not be capable of monetary valuation, but in a challenge
to
legislation purely financial self-interest may not be enough –
the interests of justice must also favour affording standing.
(e)
Standing is not a technical or strictly-defined concept. And there is
no magical formula for conferring it. It is a tool a court
employs to
determine whether a litigant is entitled to claim its time, and to
put the opposing litigant to trouble.
(f)
Each case depends on its own facts. There can be no general rule
covering all cases. In each case, an applicant must show that
he or
she has the necessary interest in an infringement or a threatened
infringement. And here a measure of pragmatism is needed.’
[17]
Cycad was a co-tenderer. A tenderer has the right to a fair and
competitive tender process irrespective of whether the tender
is
awarded to him.
[9]
This includes
the right to compete on an equal footing with his competitors who are
similarly placed such as the joint venture
which was also not
registered in the category of contractors required by the bid
specifications. Any decision of the municipality
in the award of the
tender would not only have affected or potentially affected Cycad’s
financial interests in the award
of the tender, but also its interest
in a fair process arising from the submission of its bid. A further
consideration in this
regard is that the issues raised on the facts
of this matter give rise to serious concerns about good governance
and accountability:
‘
To
this observation one must add that the interests of justice under the
Constitution may require courts to be hesitant to dispose
of cases on
standing alone where broader concerns of accountability and
responsiveness may require investigation and determination
of the
merits. By corollary, there may be cases where the interests of
justice or the public interest might compel a court to scrutinise
action even if the applicant’s standing is questionable. When
the public interest cries out for relief, an applicant should
not
fail merely for acting in his or her own interest.’
[10]
[18]
I turn to deal with the appeal against the relief granted by the high
court in para 2 of its order. On the findings made by
the court the
tender process was clearly flawed in material respects rendering it
reviewable and liable to be set aside. Consistent
with s 172(1) of
the Constitution,
[11]
s 8 of
PAJA empowers a court in judicial review to grant ‘any order
that is just and equitable’.
Section
8 confers on a court undertaking judicial review a ‘generous’
discretion.
[12]
The discretion
in s 8 must be exercised judiciously.
[13]
The remedies in s 8 are not intended to be exhaustive: they are
examples of public remedies suited to vindicate breaches of
administrative
justice.
[14]
The ultimate purpose of a public law remedy is said to ‘. . .
afford the prejudiced party administrative justice, to advance
efficient and effective public administration compelled by
constitutional precepts and at a broader level, to entrench the rule
of law’.
[15]
Ultimately
the remedy must be fair and just in the circumstances of the
particular case.
[16]
[19]
In
Bengwenyama
Minerals (Pty) Ltd v Genorah Resources (Pty) Ltd
[17]
Froneman J explained it as follows:
‘
This
“generous jurisdiction” in terms of s 8 of PAJA provides
for a wide range of just and equitable remedies, including
declaratory orders, orders setting aside the administrative action,
orders directing the administrator to act in an appropriate
manner,
and orders prohibiting him or her from acting in a particular
manner.’
And
‘
It
would be conducive to clarity, when making the choice of a just and
equitable remedy in terms of PAJA, to emphasise the fundamental
constitutional importance of the principle of legality, which
requires invalid administrative action to be declared unlawful. This
would make it clear that the discretionary choice of a further just
and equitable remedy follows upon that fundamental finding.
The
discretionary choice may not precede the finding of invalidity. The
discipline of this approach will enable courts to consider
whether
relief which does not give full effect to the finding of invalidity,
is justified in the particular circumstances of the
case before it.’
This
latter passage shows clearly that only once administrative action is
found to be unlawful, may a court then determine what
equitable
relief should be granted.
[18]
[20]
The need for such relief usually arises where adverse consequences
flow from an order declaring administrative action unlawful.
Third
parties may have altered their position on the basis that the
administrative action was valid and may suffer prejudice if
it is
declared invalid. In the context of the procurement of goods and
services an order declaring the tender process unlawful
means that
the decision to award the tender and the contract which was entered
into pursuant thereto are both void
ab
initio
.
[19]
It
has consequently been held that the factual consideration that it may
not be practicable to set the award aside must be given
due weight in
the exercise of the court’s discretion in deciding to declare
the administrative action unlawful and set it
aside.
[20]
That discretion takes into account considerations of ‘pragmatism
and practicality’.
[21]
Its underlying reason is the desirability of certainty.
[22]
[21]
In this case, however, the high court, although correctly finding
that the flaws in the tender process and award tainted it
and the
contract, nonetheless in effect ordered that the joint venture
continue to execute the invalid contract under the municipality’s
supervision. No doubt it was the consideration of pragmatism and
practicality that weighed heavily with the high court in ordering
the
continued execution of an invalid contract. It apparently made that
decision in response to the claim by Esorfranki that an
appropriate
order would be one in terms of which it was to be declared the only
successful bidder, and the municipality be ordered
to award it a
contract to complete the work. The court found that the order
proposed by Esorfranki raised a number of ‘issues
and practical
difficulties’, and that the granting of the order sought by
Esorfranki would not serve to protect the interests
of those who were
to benefit from the construction of the pipeline. These issues, which
it found not to have been properly addressed,
included inter alia
‘the logistical, legal and financial viability of such a
relief’ and ‘the extent to which
the contract has been
completed, the ownership of materials, whether if the balance of the
contract is legally and factually separable,
it should be put out to
tender etc’.
[22]
The decision of the high court to give effect to a contract concluded
pursuant to an unlawful tender award is flawed for several
reasons.
First, the parties to that contract had acted dishonestly and
unscrupulously and the joint venture was not qualified to
execute the
contract. The first order that the high court made – that the
award was unlawful – was undermined by the
order that the joint
venture continue the work. The second reason is that it was premised
on the possible existence of a number
of unknown consequences which
might follow upon an order declaring the award of the tender
unlawful. A decision made in the exercise
of the discretion in s 8 of
PAJA must be based on fact and not on mere speculation. The delay in
the finalisation of the review
proceedings brought about a change in
the factual position and it was the function of the court to ensure
that it be placed in
a position to arrive at an informed decision
with regard to what an appropriate remedy would be. This could and
should have been
addressed by an appropriately worded order.
[23]
[23]
Thirdly, the decision whether to declare conduct in conflict with the
Constitution unlawful but to order equitable relief,
in the
circumstances of any particular case, involves the weighing up of a
number of competing interests. Certainty is but one.
Other factors
include the interests of affected parties and that of the public.
[24]
In
Bengwenyama
Minerals (Pty) Ltd & others v Genorah Resources (Pty) Ltd &
others
[25]
the court also emphasised the importance of the principle of
legality:
‘
The
rule of law must never be relinquished, but the circumstances of each
case must be examined in order to determine whether factual
certainty
requires some amelioration of legality and, if so, to what extent.’
And
‘
[T]hen
the “desirability of certainty” needs to be justified
against the fundamental importance of the principle of
legality.’
[26]
[24]
In the context of an unlawful tender process for the acquisition of
goods and services for the benefit of the public, the finding
as to
an appropriate remedy must strike a balance between the need for
certainty, the public interest, the interests of the successful
and
unsuccessful tenderers, other prospective tenderers, the interests of
innocent parties and the interests of the organ of state
at whose
behest the tender was invited.
On
the facts of the present matter, having declared the tender process
to be unlawful, in deciding to grant equitable relief the
following
considerations were relevant to the exercise of the court’s
discretion. The fact that the joint venture acted upon
the award
immediately was not due to inaction on the part of the appellants. On
two occasions they immediately instituted legal
proceedings to set
aside the municipality’s irregular decision to award the tender
to the joint venture. During the course
of the proceedings Esorfranki
consistently sought to prevent the contract from being
implemented.
[27]
It was rather
the persistence of the municipality and the joint venture, in the
face of a valid challenge to the award, pursuing
a hopeless appeal
against the interim order, and by their opposition to the first
appellant’s Rule 49(11) applications, that
any delay resulted.
That delay and the execution of the contract were therefore of the
municipality and the joint venture’s
own making. The result was
that the joint venture had the benefit of a contract it should never
have had in the first place.
[25]
Further, the invalidity of the tender process was not the result of
negligence or incompetence on the part of anyone. That
the setting
aside of the contract might have been disruptive to the finalisation
of the construction of the pipeline must be assessed
against the fact
that the tender process, and consequently the contract itself, was
tainted by dishonesty and fraud. Accordingly,
problems which might
potentially arise, as foreseen by the high court, in the contractual
relationship between the municipality
and the joint venture by reason
of an order setting the contract aside ‘may not be of any
consequence in the case of corruption
or fraud, or where the
successful tenderer was complicit in the irregularity’.
[28]
The joint venture dishonestly obtained the award and the contract. It
is therefore hardly open to it to complain that it may suffer
prejudice by an order setting the award aside and declaring the
contract void. Fraud is conduct which vitiates every transaction
known to the law.
‘
No
court in this land will allow a person to keep an advantage which he
has obtained by fraud. No judgment of a court, no order
of a
Minister, can be allowed to stand if it has been obtained by fraud.
Fraud unravels everything. The court is careful not to
find fraud
unless it is distinctly pleaded and proved; but once it is proved it
vitiates judgments, contracts and all transactions
whatsoever; . . .
.’
[29]
[26]
The award of public tenders is governed by s 217 of the Constitution.
It requires awards to be made in accordance with a system
that is
‘fair, equitable, transparent, competitive and cost-effective’.
The interests of the members of the community
who are to benefit from
the supply of water via the pipeline must be assessed against their
interest, and that of the public at
large, that this constitutional
imperative be given effect to; that the tender process is free from
corruption and fraud; and that
public moneys do not land up in the
pockets of corrupt officials and business people. It is also in this
context that the high
court’s finding of fronting must be
considered. The difficulty with fronting is that the person or entity
who stands to benefit
financially from the award of the tender is not
the one to whom it was in fact awarded. The person or entity used as
a front, as
in the present matter, more often than not does not have
the capacity or competence to execute the tender. It amounts to the
exploitation
of such persons for financial benefit and constitutes a
fraud on those who are meant to be the beneficiaries of legislative
measures
put in place to enhance the objective of economic
empowerment of historically disadvantaged people.
[27]
I therefore conclude that the high court erred in the exercise of its
discretion and that its decision in effect to allow the
continuation
of the contract should be set aside. I am satisfied that in the
circumstances of this case, and weighing up the relevant
interests,
the only appropriate order would be one expressly declaring the
contract void and granting equitable relief. As the
work on the
project is partially complete it would require the Department of
Water Affairs to assess the extent of the work already
performed, and
to determine not only the value of the completed and uncompleted work
but also what steps, if any, would be necessary
to complete the work
on the project. In the interests of the communities who are to
benefit from the pipeline it is imperative
that this be done as
expeditiously as possible. I accept the submission of Esorfranki and
Cycad that because of the bias displayed
by the municipality in the
adjudication of the tender and its conduct in the review and
interlocutory proceedings, it should play
no part in any further
tender process in relation to this project.
[28]
That leaves the appeal against the costs orders made by the high
court. As stated earlier, it ordered the parties to pay their
own
costs in the review application and in the third Rule 49(11)
application. Esorfranki was, however, ordered to pay the costs
of the
municipality’s attorney Mahowa, whom it cited as the ninth
respondent in the third Rule 49(11) application, on the
attorney and
own client scale. The determination of the issue of liability for
costs is in the discretion of the court that is
called upon to
adjudicate the merits of the issues raised in the litigation between
the parties. It is a discretion which is to
be exercised judicially
upon a consideration of the facts and circumstances of each
individual case and is in essence a matter
of fairness to both sides.
Being a judicial discretion a court of appeal will interfere with the
exercise of such a discretion
only where it is shown that:
‘
[T]he
lower court had not exercised its discretion judicially, or that it
had been influenced by wrong principles or a misdirection
on the
facts, or that it had reached a decision which in the result could
not reasonably have been made by a court properly directing
itself to
all the relevant facts and principles.’
[30]
[29]
The finding of the high court that the parties were to pay their own
costs in respect of the relevant applications was essentially
made on
the basis of what the court described in its judgment as the
‘unreasonable and unconscionable manner in which Esorfranki
and
its attorney including Cycad conducted this litigation’. It
found that the appellants made themselves guilty of collusion.
That
finding is not supported by the facts. Esorfranki and Cycad are
separate legal entities, they separately submitted tenders,
instituted legal proceedings and instructed separate firms of
attorneys to act on their behalf. The mere fact that they were the
joint beneficiaries of a tender awarded to them in another province,
and that there may have been similarities in the papers filed
by them
in the present proceedings, does not support a finding of collusion,
the import of which after all is the presence of dishonesty.
There is
nothing untoward in one litigant aligning itself with another and
co-operating in the quest to achieve a particular result
in legal
proceedings.
[30]
Another factor taken into account in penalising Esorfranki and Cycad
with an unfavourable costs order was that Esorfranki’s
attorney
had suggested in a letter to the municipality that if the matter were
settled, they would not support any future criminal
investigations
against the municipality. The letter was written without prejudice,
and in an attempt to settle the matter. It could
not have been
construed as blackmail, as the municipality attempted to argue.
Whatever its faults, the attorney’s letter
was in itself
insufficient to deprive the appellants of their costs, particularly
in the case of Cycad which the attorney purported
to represent in
sending the letter. Cycad immediately took steps to distance itself
from the letter. To the extent that the attorney
may have wrongly
held himself out to also act on behalf of Cycad, and may have made
himself guilty of unprofessional conduct, that
was effectively
addressed by the high court in directing that his conduct be referred
to the relevant Law Society for investigation.
The court’s
reliance on the fact that Cycad may have abandoned certain of the
relief claimed in its notice of motion was
also misplaced. That did
not mean that the second appellant was not entitled to seek an order
declaring the contract invalid.
[31]
From a reading of the court’s judgment on costs it is evident
that it failed to consider that Esorfranki and Cycad were
substantially successful in their application to review and set aside
the tender process. To that extent they have achieved vindication
of
an important constitutional right. This failure in my view
constitutes a material misdirection. A further aspect of utmost
importance which was overlooked is the reprehensible nature of the
conduct of the municipality and the joint venture in the tender
process.
[31]
As stated
earlier, the court issued an order of invalidity on the basis of
having found the municipality to have been biased in
its adjudication
of the tenders and to have failed to insist on compliance with its
own tender requirements. The joint venture
was in turn found to have
made itself guilty of dishonest conduct by misrepresenting the facts
in their tender bid in an effort
no doubt to achieve an advantage and
to secure the award of the tender. The costs order made by the court
does not reflect the
seriousness of this conduct and the disapproval
which it deserves.
[32]
[32]
The manner in which the municipality conducted itself in the
litigation also calls for censure. Instead of complying with its
duty
to act in the public interest and to allow the serious allegations of
fraud and dishonesty in the tender process to be ventilated
and
decided in legal proceedings, it chose to identify itself with the
interests of the tenderers who stood accused of improper
conduct. To
this extent it failed to provide undertakings not to implement its
decision to award the tender to the joint venture
when reasonably
requested to do so. It instead delayed the finalisation of the review
proceedings by launching hopeless appeals
against the order
interdicting it from implementing its own unlawful decision. This
court in
Municipal
Manager: Qaukeni Local Municipality & another v FV General
Trading CC
said the following on the function of public bodies: ‘. . .
depending on the legislation involved and the nature and the
functions of the body concerned, a public body may not only be
entitled but also duty-bound to approach a court to set aside its
own
irregular administrative act’.
[33]
In
Premier,
Free State & others v Firechem Free State (Pty) Ltd
it was concluded that ‘[t]he province was under a duty not to
submit itself to an unlawful contract and [was] entitled, indeed
obliged, to ignore the delivery contract and to resist . . . attempts
at enforcement’.
[34]
In
all the circumstances I am satisfied that an appropriate court order
would have been one which reflected the disapproval of
the court with
the conduct of the municipality and the joint venture.
[33]
Insofar as the costs of Esorfranki’s third Rule 49(11)
application are concerned, as was the position with the other
two
Rule 49(11) applications, the launching of this application was
clearly motivated by the unreasonable refusal of the municipality
and
the joint venture to undertake to desist from continuing with any
work on the project pending the determination of the municipality’s
application for leave to appeal to the Constitutional Court. The
reasonableness of providing the undertaking requested must be
assessed in the context of it having been found more than once that
Esorfranki had met the requirements for an interim interdict
aimed at
protecting its rights in the review application. In fact, on occasion
the municipality agreed to the granting of such
an order.
[34]
In addition, the attempt to obtain leave to appeal against the
granting of the interim order was ill advised and destined to
fail.
The interim order was clearly not appealable. It was not final in its
effect. That the practical effect of the order may
have been to delay
the execution of the contract for the construction of the pipeline
did not make it a final order. This in any
event does not appear to
have been the complaint of the municipality with regard to the
granting of the order. Its complaint was
rather that it was not given
a proper hearing before the order was granted. The municipality’s
remedy was to apply to the
court which first granted the interim
order for the rescission or amendment thereof. ‘And in the case
of a common-law interim
interdict or attachment
pendente
lite
there is no reason why, for sufficient cause, they would not,
generally, be open to variation, if not rescission’.
[35]
I am accordingly of the view that in the circumstances Esorfranki
acted reasonably and was justified in launching the third Rule
49(11)
application, and that there exists no reason for it to be deprived of
the costs thereof. For the reasons mentioned earlier
an appropriate
order would similarly have been one on an attorney and client scale.
[35]
The next question relates to the order for costs in relation to the
relief claimed against the attorney, Mahowa, in the third
Rule 49(11)
application. Although I do not agree with every finding of the high
court in this regard, I am not convinced that it
misdirected itself
in ordering Esorfranki to pay Mahowa’s costs on a punitive
scale. Mahowa was, as stated earlier, the attorney
acting for the
municipality. He was not a party to any of the proceedings. There
existed no basis in fact or in law to compel him
in either his
personal or professional capacity to comply with any of the orders
sought in the Rule 49(11) application. The relief
claimed in this
regard, on a reading of Esorfranki’s founding affidavit, was
premised on the unsubstantiated allegation that
‘the
representatives of the respondents must be held responsible for their
actions and inaction’ in regard to the failure
of the
respondents to comply with court orders. Its speculative basis is
that Mahowa had ‘significant’ influence over
the
municipality and that its actions must have been on his advice.
[36]
Further, the punitive costs order sought against Mahowa was based on
an allegation in Esorfranki’s founding affidavit
that Mahowa
‘appears not to have advised his client not to act
contemptuously, has repeatedly failed to properly answer letters,
and
has caused substantial sums of taxpayers’ monies to be wasted’.
These allegations, which impugned the professional
integrity of
Mahowa, were similarly made without any factual support and were
dealt with and denied by him in his answering affidavit.
The attempt
by Esorfranki to rectify this by seeking to provide factual support
for its case for costs in its replying affidavit,
cannot on the rules
applicable to motion proceedings, assist it in any way.
[36]
[37]
I may add that complaints were also raised in argument about the
conduct of Mahowa on various occasions during the course of
the
different proceedings in the high court. This was not pertinently
raised in the third Rule 49(11) application and the high
court was
better placed to investigate and determine the merit thereof. In the
circumstances I cannot find that there were no reasonable
grounds for
the costs order made by the high court in para 4 of its order.
[38]
That leaves the costs of the appeal. Esorfranki and Cycad were
substantially successful in their appeal against the orders
in paras
2 and 3 of the high court’s order and they are entitled to
their costs. I agree with counsel for Esorfranki and
Cycad that,
given the serious and reprehensible nature of the conduct of the
municipality and the joint venture in the award of
the tender and in
the subsequent proceedings in the high court, and that the remedy
granted by the said court was clearly inappropriate
and indefensible,
there are on the facts of this matter, circumstances present
[37]
which justify an order that the costs of the appeal should also be
paid on an attorney and client scale.
[39]
In the result:
1The
first and second appellants’ appeal against the orders in paras
2 and 3 of the order of the high court is upheld with
costs including
the costs of two counsel, such costs to be paid jointly and severally
by the first and the third to fifth respondents
on the scale as
between attorney and client.
2
The aforesaid orders are set aside and are substituted with the
following orders:
‘
(a)
Any contract entered into between the first respondent and the third
to fifth respondents pursuant to the award of the tender
to the
respondents for the construction of a pipeline between the Nandoni
dam and the Nsami water treatment works (Nandoni to Giyani
Pipe
Project; project number LPR018), is declared void
ab
initio
and is set aside.
(b)
The first respondent is ordered to formally approach the Department
of Water Affairs within seven days of the granting of this
order to
request that Department to do the following:
(i)
To take such steps as may be necessary to determine the extent of the
works necessary to perform remedial work and to complete
the
construction of the pipeline and the other works as contemplated in
the aforesaid tender, for purposes of publishing a tender
for the
said remedial work and the completion of the works;
(ii)
To prepare and publish an invitation to tender for the performance of
the remedial work and completion of the works as aforesaid;
(iii)
To evaluate and adjudicate all bids received, and to make an award in
respect of such invitation to bid.
3
The first and the third to fifth respondents jointly and severally
are ordered to pay the costs of the review application by
Esorfranki
Pipelines (Pty) Ltd under case no 13480/2011, and of the third Rule
49(11) application dated 27 August 2011 under case
no 13480/2011,
such costs to be on an attorney and client scale, and to be inclusive
of all the reserved costs and the costs of
two counsel where
applicable.
4
The first and the third to fifth respondents jointly and severally
are ordered to pay the costs of the review application by
Cycad
Pipelines (Pty) Ltd under case no 17852/2011, such costs to be on an
attorney and client scale, and to be inclusive of all
the reserved
costs and the costs of two counsel where applicable.
5
The first appellant’s appeal against the order in para 4 of
the order of the high court is dismissed with costs.’
___________________
D
van Zyl
Acting
Judge of Appeal
APPEARANCES
For First Appellant:
K W Lüderitz SC (with him C Woodrow)
Instructed
by:
Thomson
Wilks, Johannesburg
Webbers,
Bloemfontein
For
Second Appellant: J P Daniels SC (with him T D Prinsloo)
Instructed
by:
Du
Toit McDonald Inc, Johannesburg
Webbers,
Bloemfontein
For First, Second
and Sixth
Respondents: K Tsatsawane
Instructed
by:
Mahowa
Inc, Tzaneen
Honey
Attorneys Inc, Bloemfontein
For
Third, Fourth,
Fifth,
Seventh and
Eighth
Respondents: P F Louw SC
Instructed
by:
Routledge
Modise Inc, Johannesburg
Symington
& De Kok, Bloemfontein
For
Ninth Respondent: H van Eeden SC
Instructed
by:
Cliffe
Dekker Hofmeyr Inc, Cape Town
Honey
Attorneys, Bloemfontein
[1]
Act
5 of 2000.
[2]
Regulations
8(2) to 8(7) of the Preferential Procurement Regulations, GN R725,
GG
22549, 10 August 2001 were declared as invalid in the judgment
of
Sizabonke
Civils CC t/a Pilcon Projects v Zululand District Municipality &
others
2011
(4) SA 406 (KZP).
[3]
Regulation
25(3) of the Construction Industry Development Regulations, GN R692,
GG
26427,
9 June 2004, discussed in
Moseme
Road Construction CC & others v King Civil Engineering
Contractors (Pty) Ltd & another
2010 (4) SA 359
(SCA) para 14.
[4]
Act
3 of 2000.
[5]
Bengwenyama
Minerals (Pty) Ltd & others v Genorah Resources (Pty) Ltd &
others
2011
(4) SA 113
(CC) para 82. See also
Bato
Star Fishing (Pty) Ltd v Minister of Environmental Affairs &
others
[2004] ZACC 15
;
2004
(4) SA 490
(CC) para 25;
Zondi
v MEC for Traditional and Local Government Affairs
2005 (3) SA 589
(CC) para 99.
[6]
Relevant
to these proceedings is subpara
(a)
.
It reads as follows:
‘
Anyone
listed in this section has the right to approach a competent court,
alleging that a right in the Bill of Rights has been
infringed or
threatened, and the court may grant appropriate relief, including a
declaration of rights. The persons who may approach
a court are–
(a)
anyone acting in their own interest; . . . .’
[7]
Giant
Concerts CC v Rinaldo Investments (Pty) Ltd & others
2013 (3) BCLR 251
(CC) para 29.
[8]
Above
para 41.
[9]
Allpay
Consolidated Investment Holdings (Pty) Ltd & others v Chief
Executive Officer, South African Social Security Agency
& others
2014 (1) SA 604
(CC) para 60.
[10]
Giant
Concerts
para
34.
[11]
Section
172(1) of the Constitution reads:
‘
(1)
When deciding a constitutional matter within its power, a court–
(a)
must declare that any law or conduct that is
inconsistent with the Constitution is invalid to the extent of its
inconsistency;
and
(b)
may make any order that is just and equitable,
including–
(i)
an order limiting the retrospective effect of the declaration of
invalidity; and
(ii)
an order suspending the declaration of invalidity for any
period and on any conditions, to allow the competent
authority
to correct the defect.’
[12]
Steenkamp
NO v Provincial Tender Board, Eastern Cape
2007 (3) SA 121
(CC) para 30.
[13]
Mvumvu
& others v Minister for Transport
2011 (2) SA 473
(CC) para 46.
[14]
Steenkamp
above
para 30.
[15]
Steenkamp
above para 29.
[16]
Hoffmann
v South African Airways
2001 (1) SA 1
(CC) para 42.
[17]
Bengwenyama
paras 83 and 84.
[18]
See
also
Allpay
above para 28 and 29.
[19]
Seale
v Van Rooyen NO; Provincial Government, North West Province v Van
Rooyen NO
2008 (4) SA 43
(SCA) para 13 and
TEB
Properties CC v MEC, Department of Health and Social Development,
North West
[2012] 1 All SA 479
(SCA) para 26.
[20]
Chairperson,
Standing Tender Committee & others v JFE Sapela Electronics
(Pty) Ltd & others
2008 (2) SA 638
(SCA) para 27;
Millennium
Waste Management (Pty) Ltd v Chairperson, Tender Board: Limpopo
Province & others
2008 (2) SA 481
(SCA) para 23;
Eskom
Holdings Ltd & another v New Reclamation Group (Pty) Ltd
2009 (4) SA 628
(SCA) para 9 and
Moseme
Road Construction CC & others v King Civil Engineering
Contractors (Pty) Ltd & another
2010 (4) SA 359
(SCA) para 20.
[21]
Chairperson,
Standing Tender Committee & others v JFE Sapela Electronics
(Pty) Ltd & others
above para 28.
[22]
Eskom
Holdings
above
para 9.
[23]
See
by way of example the order made in
Allpay
above para 98.
[24]
Millennium
Waste Management
above
para 23.
[25]
Bengwenyama
above
paras 84 and 85.
[26]
Bengwenyama
above paras 84 and 85.
[27]
See
paras 4 to 6 of this judgment.
[28]
Per
Harms DP in
Moseme
Road Construction
above
para 21.
[29]
Per
Lord Denning in
Lazarus
Estates Ltd v Beasley
[1956] 1 QB (CA) at 712. See further
Firstrand
Bank Ltd t/a Rand Merchant Bank & another v Master of the High
Court, Cape Town & others
[2013] ZAWCHC 173
(11 November 2013) paras 20-27.
[30]
National
Coalition for Gay and Lesbian Equality & others v Minister of
Home Affairs & others
2000
(2) SA 1
(CC) para 11;
Naylor
& another v Jansen
2007
(1) SA 16
(SCA) para 24.
[31]
Nel
v Waterberg Landbouwers Ko-Operatieve Vereeniging
1946 AD 597
at 609.
[32]
In
Tshopo
v State
(29/12)
[2012] ZASCA 193
para 37 this court (per Heher JA) said the
following about dishonesty in the procurement of state tenders:
‘
Fraud
in the procurement of state tenders is a particularly pervasive form
of dishonest practice. It undermines public confidence
in the
government that awards tenders, apparently without regard for
nepotism, and it creates perceptions unfavourable to the
services
provided pursuant to such tenders. It is proving notably difficult
for the authorities to identify and root out such
malpractices. The
courts are obliged
to render effective
assistance lest the game be thought to be worth the candle.’
[33]
Municipal
Manager: Qaukeni Local Municipality & another v FV General
Trading CC
2010
(1) SA 356
(SCA) para 23.
[34]
Premier,
Free State & others v Firechem Free State (Pty) Ltd
2000
(4) SA 413
(SCA) para 36.
[35]
Phillips
& others v National Director of Public Prosecutions
2003 (6) SA 447
(SCA) para 21. See also
Atkin
v Botes
2011 (6) SA 231
(SCA) para 12.
[36]
Director
of Hospital Services v Mistry
1979 (1) SA 626
(A) at 635G-636B;
Bowman
NO v De Souza Roldao
1988 (4) SA 326
(T) at 327D-H;
Port
Nolloth Municipality v Xhalisa & others; Luwalala & others v
Port Nolloth Municipality
1991 (3) SA 98
(C) at 111E-F and
Aeroquip
SA v Gross & others
[2009] 3 All SA 264
(GNP) para 6.
[37]
See
Herold
v Sinclair & others
1954 (2) SA 531
(A) at 537D-E and
Ward
v Sulzer
1973 (3) SA 701
(A) at 707B-D with regard to awards of costs of
appeal on an attorney and client scale.