Structured Connectivity Solutions (Pty) Ltd v Absolute Africa Supply Chain Services (Pty) Ltd (32318/08) [2010] ZAGPJHC 140 (5 February 2010)

80 Reportability
Contract Law

Brief Summary

Contract — Breach of contract — Damages for loss of goods in transit — Plaintiff claimed R874 101,98 for damage to goods transported from South Africa to various African countries; defendant counterclaimed R600 162,31 based on alleged agreement of sale, which plaintiff denied. — Legal issue centered on whether the damage occurred during transportation by road or after delivery to assembly sites. — Court held that the evidence supported the plaintiff's claim that the goods were damaged during overland transportation, thus entitling the plaintiff to the full amount claimed, with the defendant's counterclaim dismissed.

Comprehensive Summary

Summary of Judgment


1. Introduction


This matter concerned a trial action in the South Gauteng High Court, Johannesburg, in which the plaintiff sought contractual damages arising from alleged damage to goods while in transit. The plaintiff claimed R874 101,98 as the cost of replacing damaged components of prefabricated banking branch panels supplied for a project in various African countries.


The parties were Structured Connectivity Solutions (Pty) Ltd as plaintiff and Absolute Africa Supply Chain Services (Pty) Ltd as defendant. The plaintiff’s claim was met by a counterclaim in which the defendant sought R600 162,31, alleged to be due under an agreement of sale said to have been concluded between the parties. The plaintiff denied that any such agreement existed.


The dispute arose within the context of a larger commercial project in which a joint venture referred to as “Comdev” had secured a contract to supply prefabricated banking branches to Barclays Bank for installation in Ghana, Uganda, and Tanzania (including Zanzibar). The plaintiff was engaged to procure materials and arrange delivery in prefabricated condition, and the defendant was engaged under a written agreement to provide logistics, warehousing, and transport services in relation to those prefabricated branches.


Procedurally, the matter proceeded to trial, with evidence led by both sides. Although the parties initially spent trial time on whether insurance formed part of the contractual obligations for a portion of the journey, the court considered that issue ultimately irrelevant to the decisive question. The core factual dispute narrowed to whether damage occurred during overland transport by truck after warehousing near the airports, or after delivery on site during unpacking or handling at the assembly sites.


2. Material Facts


It was common cause that Comdev obtained a contract to supply prefabricated Barclays Bank branches in multiple African countries and that the plaintiff was responsible for procurement and arranging delivery, while the defendant was contracted to provide logistics-related services to the plaintiff for this project. The prefabricated components included decals made of hard plastic in “Barclays blue” bearing the Barclays logo, which were attached to certain panels in South Africa before dispatch.


It was also common cause that, due to time pressure, the original plan of seafreight followed by road transport changed: the goods were airfreighted to the destination countries, then warehoused, and thereafter moved overland by truck to the assembly sites. Damage to the decals was discovered in all the relevant countries, and the damage was of such a nature that it was unacceptable to Barclays and required replacement. The damage occurred in July 2007, and the plaintiff’s claim was for the replacement cost of these decals.


On insurance, it was common cause that the defendant insured the goods up to completion of the airfreight portion of the journey, but that the goods were not insured for the subsequent overland road journey from warehousing to the assembly sites. The parties disputed whether the agreement required insurance up to site delivery and whether such insurance could have been obtained. The court considered this dispute to have become immaterial because the defendant ultimately had to concede that the risk of damage in transportation remained with the defendant until delivery to the plaintiff at the site, and because the evidence established, on a balance of probabilities, that the goods were undamaged up to warehousing near the destination airports.


The decisive factual issue was therefore whether the decals were damaged during the overland trucking leg (from warehouses to sites) or on site after delivery. The plaintiff relied on evidence from its personnel that the damage became apparent upon unpacking after delivery and that the nature of the damage indicated friction or rubbing consistent with movement during transport. The court recorded that the plaintiff’s witnesses gave evidence of high quality, including that the panels were protected by 2mm thick synthetic insulation (“aerothene”) between them in the packaging, and that the long-distance road haulage was over roads that were not perfectly smooth.


The defendant led evidence emphasising the high standard of packaging. However, none of the defendant’s witnesses gave direct evidence establishing what caused the damage, and one witness conceded the possibility that the damage could have occurred during truck transport. The court also noted that goods were stacked and strapped for airfreight but were unstacked from pallets for sorting before being transported by truck, implying that the packaging configuration and restraints used for airfreight would not necessarily have remained intact for the overland leg.


As to quantum, it was common cause that the cost of replacing the decals was R874 101,98. It was also common cause that Comdev had paid R672 144,14 to a third party (Sign Out CC) on behalf of the plaintiff to ensure timely replacement, and that an amount of R201 957,84 remained unpaid by Comdev at the time. The defendant argued that the plaintiff suffered no loss, or alternatively that damages should be reduced to reflect the portion paid by Comdev.


The defendant’s counterclaim was founded on an alleged sale agreement, which the plaintiff denied. The court considered the defendant’s evidence on this alleged agreement, particularly the testimony of the defendant’s managing director, and found significant difficulties with that evidence, including ultimate concessions inconsistent with the existence of the pleaded agreement.


3. Legal Issues


The central legal questions before the court were:


The first was a question of causation and factual inference: whether, on a balance of probabilities, the decals were damaged before delivery (during overland transport for which the defendant bore risk) or after delivery on site (in which case the defendant would not be liable on the basis advanced).


The second was the extent to which payments by a third party (Comdev) toward replacement costs affected the plaintiff’s recoverable damages from the defendant, raising the legal characterisation of such payment as collateral and whether it was res inter alios acta in the context of the plaintiff’s contractual claim against the defendant.


The third was whether the defendant could rely on alleged contractual terms and conditions (incorporated by reference) relating to timeous reporting of loss when that defence had not been pleaded.


A further legal issue arose in relation to the counterclaim: whether the defendant had proved, as a matter of fact and contract, the existence and terms of the alleged agreement of sale underpinning the counterclaim, and whether the counterclaim could succeed given the deficiencies the court found in the defendant’s version.


Overall, the dispute primarily concerned questions of fact (what happened to the goods and whether a sale agreement existed), together with the application of legal principles (onus, probability, collateral benefits, and pleading requirements) to those factual findings.


4. Court’s Reasoning


In narrowing the issues, the court held that the insurance debate did not determine liability because the defendant conceded that the risk of damage remained with it until delivery on site, and because the evidence showed the goods were in an undamaged condition up to warehousing near the airports in the destination countries. The case therefore turned on a focused causation inquiry: whether damage occurred during trucking from the warehouses to the sites, or after delivery on site.


On the plaintiff’s claim, the court assessed the probabilities and the quality of the evidence. It accepted the plaintiff’s evidence that the decals were damaged in a manner consistent with friction, and that the damage was apparent when unpacking occurred at the sites. The court also considered that similar damage occurred across multiple sites and countries, which suggested a common cause rather than isolated site-specific mishandling.


A key inference drawn by the court was that the common denominator was the packaging method used during transport, namely the 2mm aerothene placed between panels. The court reasoned that it did not require expert evidence to deduce that such thin insulation would likely be insufficient to prevent friction damage during long road transport over imperfect roads. It further reasoned that the careful packing and strapping used for airfreight would have been undone or altered once the airfreight stage ended (particularly because the goods were unstacked from strapped pallets for sorting), thereby increasing the plausibility that the damage occurred during the subsequent truck leg.


The defendant’s approach on causation was characterised as essentially relying on the plaintiff’s onus while advancing no specific alternative explanation beyond the suggestion that the damage could have been caused by “anything.” The court found, on the probabilities, that the damage occurred during overland transport by truck, before delivery at the assembly sites, and thus within the period when the defendant bore risk.


On quantum and the effect of Comdev’s payment, the court rejected the contention that the plaintiff had suffered no loss or that its claim should be reduced by the amount Comdev had paid. It held that the payment by Comdev was res inter alios acta, describing it as collateral to the contractual relationship between plaintiff and defendant. The court reasoned that the contract in issue was between the litigating parties; the plaintiff’s loss occurred when the breach occurred; and the plaintiff was entitled to compensation from the defendant regardless of the third-party payment.


In dealing with the defendant’s argument raised in heads of argument regarding non-compliance with reporting requirements contained in general terms and conditions, the court accepted the plaintiff’s submission that because this point had not been pleaded, it could not be considered at that stage.


On the counterclaim, the court scrutinised the evidence of the defendant’s managing director and identified multiple credibility and reliability concerns, including failures to put material aspects to the plaintiff’s witnesses, internal contradictions, and concessions undermining the pleaded basis of the counterclaim. The court noted, in particular, that the managing director ultimately conceded that no agreement existed between him and the plaintiff’s director regarding the subject matter of the counterclaim. On that basis, the counterclaim failed.


Regarding interest, the court found that, based on uncontested allegations in the pleadings, the date from which mora interest could “safely” run was 26 July 2007.


5. Outcome and Relief


The court granted judgment in favour of the plaintiff and ordered the defendant to pay R874 101,98. The court further ordered interest on that amount at 15,5% per annum from 26 July 2007 to date of payment. The defendant was also ordered to pay the costs of suit in the main action.


The defendant’s counterclaim was dismissed with costs.


Cases Cited


Santam Versekeringsmaatskappy Bpk v Byleveldt 1973 (2) SA 146 (A).


AA Alloy Foundry (Pty) Ltd v Titaco Projects (Pty) Ltd 2000 (1) SA 639 (SCA).


Legislation Cited


No legislation was expressly cited in the judgment.


Rules of Court Cited


No rules of court were expressly cited in the judgment.


Held


The court held that, on a balance of probabilities, the decals were damaged during overland transportation by truck from warehouses near the destination airports to the assembly sites, and therefore before delivery at the sites while the defendant bore the relevant risk. The plaintiff proved its damages in the claimed amount, and the third-party payment by Comdev did not reduce the plaintiff’s recoverable loss because it was a collateral matter (res inter alios acta). The defendant’s reliance on unpleaded general terms and conditions relating to reporting of loss could not be entertained. The defendant failed to establish the alleged agreement of sale underpinning the counterclaim, which was dismissed.


LEGAL PRINCIPLES


The judgment applied the principle that where causation is disputed in a contractual damages claim, the court determines liability by evaluating the evidence and drawing inferences on a balance of probabilities, including inferences drawn from recurring patterns of damage across multiple sites and the most plausible common mechanism consistent with the proved facts.


It reaffirmed the principle that a payment by a third party towards the plaintiff’s loss does not necessarily reduce the defendant’s liability where that payment is collateral to the contractual relationship and is properly treated as res inter alios acta, with the plaintiff’s loss arising at the time of breach and remaining recoverable from the defendant notwithstanding such third-party intervention, as supported by the cited authorities.


It also applied the procedural principle that a party may not rely on a defence or contractual condition (such as alleged timeous reporting requirements contained in general terms and conditions) if that defence has not been pleaded, and that it cannot be introduced for the first time in argument.


Finally, in relation to the counterclaim, the judgment reflected that a party bearing the onus to prove an alleged agreement must establish its existence and terms through credible and consistent evidence; significant contradictions, failures to put material aspects to opposing witnesses, and concessions inconsistent with the pleaded case may be fatal to such a claim.

About SAFLII
Databases
Search
Terms of Use
RSS Feeds
South Africa: South Gauteng High Court, Johannesburg
SAFLII
>>
Databases
>>
South Africa: South Gauteng High Court, Johannesburg
>>
2010
>>
[2010] ZAGPJHC 140
|

|

Structured Connectivity Solutions (Pty) Ltd v Absolute Africa Supply Chain Services (Pty) Ltd (32318/08) [2010] ZAGPJHC 140 (5 February 2010)

IN THE SOUTH GAUTENG HIGH COURT
JOHANNESBURG
CASE NO:  32318/08
Reportable
in:
SAFLII, JDR (Juta) and JOL
(LexisNexis) only
DATE: 05/02/2010
In the matter between:
STRUCTURED
CONNECTIVITY SOLUTIONS (PTY) LTD
Plaintiff
and
ABSOLUTE
AFRICA SUPPLY CHAIN SERVICES (PTY) LTD
Defendant
JUDGMENT
WILLIS J:
[1] In this trial action, the
Plaintiff claims the sum of R874 101,98 arising from damage to goods
which allegedly occurred in transit
from one destination to another.
The defendant counterclaims R600 162, 31 in terms of an alleged
agreement of sale entered into
between the parties. This agreement is
denied by the plaintiff.
[2] It is common cause that a
so-called “joint venture” which counsel for the parties
and the various witnesses referred
to as “Comdev” secured
a lucrative contract to supply prefabricated banking branches to
Barclays bank in various countries
in Africa: Ghana, Uganda and
Tanzania (which included Zanzibar). These prefabricated branches were
made up in South Africa and
then transported to their countries of
destination for assembly at the sites where they were to function as
branches. Comdev secured
the services of the plaintiff to procure the
materials and to arrange for their delivery in a prefabricated
condition to their
sites of destination.  The plaintiff, in
turn, entered into a written agreement with the defendant for the
defendant to provide
logistical, warehousing and transport services
to the plaintiff in respect of these prefabricated banking branches.
[3]  Although it had originally
been intended that the goods would be sent by seafreight to their
countries of destination
and then transported overland by road in
trucks to the actual sites of assembly, pressure of time resulted in
the goods being airfreighted
to the  countries of destination,
then warehoused and thereafter transported overland in trucks to the
actual sites.
Part of the prefabrication included decals made
of hard plastic in “Barclays blue” which contained the
logo of the
bank. As part of the prefabrication the decals had been
attached to certain of the panels made up in South Africa before
their
despatch to their countries of destination. In all the
countries concerned various of these decals had become damaged or
scratched
to an extent that would be unacceptable to Barclays and had
to be replaced. The damage occurred in July 2007. It is the
replacement
of these damaged decals that has given rise to the
plaintiff’s claim.
[4] It is common cause that the goods
were insured by the defendant for their journey up until their
airfreight journey had been
completed. They were not insured for
their overland journey on road in trucks from the warehousing in
their countries of destination
to the actual sites of assembly. Part
of the dispute between the parties had initially been whether the
agreement between the parties
provided for their insurance for this
part of the journey as well. The defendant contended that there was
no such agreement and
that, in any event, it would not have been
possible to obtain such insurance. The plaintiff, on the other hand,
contended that
insurance right up to delivery on site of assembly
formed part of the agreement between the parties. Although quite a
lot of time
was taken up in the trial on this issue, it ultimately
became irrelevant. The reasons for this are the following:
(i) The defendant had to concede that
the risk in respect of damage in transportation remained with the
defendant until the goods
had been delivered to the plaintiff at
site;
(ii) the evidence established, on a
balance of probabilities, that the goods had indeed been expertly
packaged, loaded, strapped
and transported for the airfreight portion
of their journey and indeed that they had been in an undamaged
condition right up to
the stage of their warehousing near the
airports in their country of destination.
The case therefore turns on a narrow
issue: were the goods damaged while being transported on trucks from
these warehouses to the
sites of assembly or were they damaged on
these sites after delivery had taken place?
[5] Mr Gareth Botha, a director of the
plaintiff, testified that the site managers at the various sites had
reported to him that,
upon unpacking the goods after delivery, the
damage had been uncovered. The damage could not have been detected
before unpacking
out of the packaging and, in any event, almost all
the signatures on the delivery notes were of persons who were not
employees
of the plaintiff or duly authorized to sign on its behalf.
Mr Johan Herbst, the plaintiff’s on-site project manager
in
Tanzania testified that the damage had to have occurred during
transportation as much of the damage (which was similar in every

instance that he saw) was apparent at the time when the goods were
being unpacked. He specifically and firmly denied that the goods

could have been damaged in the way that they were, on site. Mr Herbst
went further: it was clear that damage was caused by friction
or the
rubbing of the various panels against each other. Mr Ernest Seagreen
the Plaintiff’s on-site project manager at three
of the sites
in Tanzania gave evidence which was substantially the same as Mr
Herbst. Mr Seagreen described the damage as “skaafmerke”

which he emphatically disavowed could have been caused on site. He
said that Mr Johan Voges, the project manager at the other four
sites
in Uganda and who was not available to testify had reported to him
the same problem. The plaintiff’s witnesses all
gave evidence
of high quality. It is common cause that the panels in question were
protected in the packaging by a 2mm thick synthetic
insulation known
as “aerothene”.  Although there was a difference of
opinion as to the quality of the roads in
question, it was clear that
long distance haulage was involved in almost every instance and that
the roads could not be described
as being “as smooth as a
baby’s bottom”.
[6] Apart from Mr Derek Westerne, the
managing director of and majority shareholder in the defendant, the
defendant’s witnesses,
Mr Johan Herselmann, Mr Anton Groenewald
and Mr Alain Da Costa all gave evidence as to the high standard of
the packaging of the
goods which were being transported. None of them
gave evidence of a direct nature as to what caused the damage. Mr Da
Costa conceded
that he could not exclude the possibility that the
goods had been damaged when they were transported on the trucks. It
should also
be borne in made that, although the goods were stacked on
to strapped palettes for their air freight, they were unstacked from
these palettes for sorting before they were transported on trucks. Mr
Westerne gave evidence as to what had been agreed between
the
parties.
[7] Various criticisms can be levelled
at the evidence of Mr Westerne:
(i) aspects of his version which
should have been put to the plaintiff’s witnesses were not –
for example (a) that Mr
Botha had specifically been told  by him
that there would be no insurance for the transportation by road in
the countries
of destination and (b) that a “fabricated”
or at very least misleading insurance claim had been submitted with
the
knowing co-operation of Mr Botha;
(ii) His description of the manner in
which the goods had been packed differed from that of his own
witness, Mr Da Costa;
(iii) He was prepared to mislead the
insurers as to the possibility that the goods could have been damaged
during their being airfreighted;
(iv) The documentation upon which he
relied in support of the counterclaim appears to have been contrived,
containing detail that
matches in a fine degree and to an extent that
cannot be mere coincidence with that upon which the plaintiff has
relied  for
its claim;
(v) He not infrequently contradicted
himself and when confronted therewith said that he had “made a
mistake”;
(vi) He eventually conceded that there
had been no agreement between himself and Mr Botha in regard to the
subject matter of the
counterclaim but reasoned that the plaintiff
was liable as the defendant was not responsible for the value of the
goods which the
defendant had replaced.
Accordingly, the defendant’s
counterclaim cannot succeed. It must be dismissed.
[8] Insofar as the plaintiff’s
claim is concerned, the defendant relied, essentially, upon the
plaintiff’s
onus
to prove that, as matter of
probability, the goods had been damaged while they had been
transported on road in their countries
of destination and not after
they had been delivered to their sites of ultimate destination. In
other words, other than to shrug
his shoulders, hold up his hands in
resignation and suggest that the damage could have been caused by
“anything”, Mr
Wannenburg
, who appeared for the
defendant, could not indicate  what could account for the
damage. It seems to me that, as a matter of
probability, the goods in
question were indeed damaged while they were being transported
overland by trucks in their countries
of destination (i.e. before
they had been delivered to the assembly sites). I come to this
conclusion for the following reasons:
(i) exactly the same type of damage
occurred to the same goods at different sites and in different
countries – suggesting
that there must have been a common
denominator;
(ii) the common denominator is the 2mm
thick aerothene between the panels during transportation – one
hardly needs to be an
expert to deduce that this would have been
inadequate to safeguard against the friction that would inevitably
accompany the transportation
of goods in trucks over long distances
on less than perfect roads;
(iii) clear and convincing evidence
was given that the damage to the decals was indeed caused by
friction;
(iv) much of the expert packing,
stacking and strapping for the airfreight would have had to have been
undone when the airfreight
journey had  been completed;
(v) no other explanation for why the
damage should have been of the nature it was suggests itself.
[9] It is common cause that the cost
of replacing the decals was an amount of R874 101.98 and that,
pending the resolution of the
dispute, Comdev had paid an amount of
R672 144.14 to Sign Out CC on behalf of the plaintiff in order to
ensure that the damaged
goods were replaced timeously.  Comdev
has yet to pay an amount of R201 957.84. Mr
Wannenburg
submitted, in one breath, that the plaintiff had, accordingly
suffered no loss, and in the next breath that, alternatively, the

plaintiff’s proven damages stood at R201 957.84 less than that
which had been claimed. In my view, the payment by Comdev
was clearly
res inter alios acta
: the contract in question was between the
plaintiff and the defendant, the plaintiff suffered its loss when the
breach occurred
and is entitled to be recompensed by the defendant -
the payment by Comdev is a collateral matter. (See
Santam
Versekeringsmaatskappy Bpk v Byleveldt
1973 (2) SA 146
(A)
at 150F; 153B-D and 168 and
AA Alloy Foundry (Pty) Ltd v Titaco
Projects (Pty) Ltd
2000 (1) SA 639
(SCA) at paragraph [11].) The
plaintiff’s quantum of damages has been proven in the amount it
has claimed. It seems from
the uncontested allegations in the
pleadings that the date from which
mora
interest can safely be
determined to run is 26th July, 2007.
[10] Finally, there is an issue which
has been raised by Mr
Wannenburg
in his heads: the plaintiff
had failed to comply with certain conditions in the defendant’s
general terms and conditions
to which reference was made in Annexure
“A” of the agreement between the parties in regard to
timeous reporting of
the loss. These terms and conditions were,
according to the defendant, available on request. Quite apart from
any other considerations,
I agree with Mr
Du Plessis
who
appeared for the plaintiff that as this aspect had never even been
pleaded by the defendant, it cannot even be considered now.
[11] Judgment is given for the
plaintiff against the defendant as follows.
A.
The defendant is to pay the plaintiff:
(a)
R874 101,98;
(b)
Interest on the aforesaid sum at the rate
of 15,5%
per annum
from
26th July, 2007 to date of payment;
(c)
Costs of suit.
B.
The
defendant’s counterclaim is dismissed with costs.
DATED AT JOHANNESBURG THIS 5th DAY
of FEBRUARY, 2010.
N.P. WILLIS
JUDGE OF THE HIGH COURT
Counsel
for the Plaintiff:
Advocate
D.T. v R. Du Plessis
Attorneys
for the Plaintiff:
Le Roux Vivier & Associates.
For
the Defendant:
Advocate
W. Wannenburg
Attorneys
for Defendant:
Sim & Botsi Attorneys Inc.
Dates
of hearing:
14th -18th September, 2009 and
26th January, 2010.
Date
of judgment:
5th February,
2010.